KIEWIT LEDCOR TMEP PARTNERSHIP 2115 Commissioner Street Site 1 - PER Application, Category C. August 17, Vancouver Fraser Port Authority

Size: px
Start display at page:

Download "KIEWIT LEDCOR TMEP PARTNERSHIP 2115 Commissioner Street Site 1 - PER Application, Category C. August 17, Vancouver Fraser Port Authority"

Transcription

1 August 17, 2017 Vancouver Fraser Port Authority 100 The Pointe, 999 Canada Place Vancouver, BC, Canada V6C 3T4 Attention: Jessica Mehigan Subject: Overview Kiewit Ledcor TMEP Partnership ( KLTP ) has been formed for the construction of the Trans Mountain Expansion Project (the Project ) in the Lower Mainland. KLTP has identified the 2115 Commissioner Street - Site 1 (the Site ) as a potential support site for the construction of the Westridge Marine Terminal expansion. The proposed scope of work for the Site includes; site preparation, construction laydown, security fencing, parking stalls, site offices, and temporary marine structures. This memo is intended to provide an overview of the scope of work associated with the western portion of the Site, designated as Site 1 and Waterlot 1 in Appendix A, in support of our application for a Category C permit, as described in the PER Application Guide. East Vancouver Port Lands The Site is located in the western end of the East Vancouver Port Lands (EVPL) region, within Area 1 as shown in Figure 8 of the EVPL Plan. Commissioner Street and a CP Rail ROW separate the site from the surrounding residential community. The East Vancouver Port Lands Area Plan was approved by the City of Vancouver, the Vancouver Fraser Port Authority (VFPA) and the Burrardview Community Association in 2007 to guide future development and Port operations. As part of the EVPL, the East Vancouver Port Lands Liaison Group was established comprising of representatives from Burrardview Community Association, City of Vancouver, CP Rail and the VFPA to advise on issues of mutual interest. KLTP comprehends the potential community impact of the project operations and will comply with the guidelines to minimize impact on noise, views, air quality of the area. We have reviewed the East Vancouver Port Lands Area Plan and anticipate the planned use for the site to be a mixture of Green - Marine Taxis, and Yellow - Works Yard, uses as defined in Appendix B of the Area Plan.

2 Green Uses Marine Taxis A moderate amount of marine transportation services will be required throughout the operation of the Site. A combination of large and small marine taxi will pick-up and drop-off employees on the Flexi-Float platform at the start and end of shift. A portion of the parking stalls will be allocated to the marine workers and each stall will be painted and numbered. Yellow Uses Works Yards The Site will be used for storage and assembly of construction materials and supplies throughout the duration of the Project. The majority of the lot space will be occupied with equipment and fabricated materials required to support the construction of the Project. An extensive list of equipment and materials can be found in the Operations section of this memo. Key Impacts KLTP recognizes the importance of the preserving the mountain and water views to the surrounding communities. As per the EVPL height guidelines, the proposed site falls under Area 1 with a recommended maximum height of 13.7 m (45 feet). The two mobile cranes on site will exceed the maximum allowable height for structures resulting in the potential obstruction of the views over the Port Lands of the Burrard Inlet and North Shore mountains. The Liebherr LR1300 crawler crane will have a maximum boom height of 240 feet (73.0 m). However, the width of the boom of the crane is approximately 2.5 m, much less than the limit considered in Policy H5 of the EVPL Plan. Likewise, the Tadano Rough Terrain GR-1000XL crane has a maximum boom height of 150 feet (45.7 m) and boom width of approximately 0.6m. The cranes will used in a variety of locations throughout the site and thus will not cause a permanent obstacle to the residents and public s panoramic views. The two proposed cranes will be used to load and offload large and heavy materials from trucks and barges, as this work cannot be safely completed with other material handling equipment such as forklifts. The cranes will also assist in the fabrication and assembly of materials and equipment within the Site. Description of Physical Works and Construction Activities In general, our intended purpose for this site is a marine off-loading facility and laydown yard for the project. In order to prepare the site for the intended use the following activities, as shown in Appendix A, will be undertaken on the property: - Minor clean-up and site grading including: o Removal of any debris left onsite o Filling in of pot holes

3 - Upgrades to existing ground, as required to support the mobile cranes. This may include: o Milling or removal of existing asphalt. o Temporary removal of the top mm of gravel. o Placement of Geotextile grid or fabric o Replacement, compaction and grading of gravel previously removed. o Import and placement of additional gravel required to achieve design capacity and grade. - Installation of 630 m of 1.8m high standard chain link fence, with barb wire above the top bar. - Installation of two 10m wide, double swing gate for vehicle and personnel access. - Placement of 55m of precast concrete barricades to delineate the Old Wharf. - Installation of a 300T crawler crane (Liebherr LR 1300 or equivalent) o Dimensions: 27 x 67 x 16.5 with max boom to tip height of Placement of a mobile rough terrain crane (Tadano GR1000XL or equivalent) o Dimensions: 47 x 11 x 12.5 with max boom tip height of Placement of mobile construction trailers and storage containers that will tie into existing power and communications. The laydown yard will consist of: o One Office Trailer 12 x 60 o One Lunch Room 10 x 40 o One Wash Car 12 x 32 o Two Mechanics Storage containers 10 x 20 o One Mechanics Office 10 x 20 o One Environmental Connex 10 x 20 o Four Storage Connexes 10 x 20 o One Dry Shack Heated Connex 10 x 20 o One 45 x 45 Covered Shop - Layout of approximately 50 parking stalls for onsite and offsite staff. - Construction of a Temporary Trestle consisting of: o A 30 x 115 Access Trestle o A 48 x 180 Main Trestle o 25 ea 600mm diameter pipe piles o 28 ea 900mm diameter pipe piles o 5 ea 900mm diameter dolphin piles o Structural Steel Superstructure o Timber Crane Mat working surface. o Bull rails, hand rails, etc. See Appendix D for the preliminary design of this trestle. Pipe piles will be installed as far as possible via vibratory method. Where necessary the installation will be finished using a diesel impact hammer. Underwater noise and pressure will be monitored and mitigated as detailed in the CEMP, provided in Appendix H-1. - Installation of temporary mobile small boat dock made up of three flexi-float barges.

4 o Dimensions: 10 x 100 flexi-float barge with a 77 x 4 engineered gangway. o Appendix E provides details of this barge and a conceptual design for the gangway. - Installation of ten temporary 1000W flood lights on the existing wooden poles along Commissioner Street. o These lights will be designed and installed based on the PER Guidelines for Lighting. o Specifically, they will be installed to improve safety and security on the site, without creating nuisance lighting for the neighbouring community or marine vessels. o Appendix F shows the detailed site lighting plan prepared by a qualified lighting professional. o We have confirmed the capacity exists within the network and will coordinate the light installation with BC Hydro. Necessary approvals and permits will be obtained prior to any installations. The center portion of the site, designated as the Old Wharf in Appendix A, will be barricaded and fenced off due to various structural deficiencies. Construction for site setup will begin after issuance of the Permit and will take 6-8 weeks to complete. The anticipated construction start day, if the permit review takes the full 120 days, is Monday, January 29 th, Table 1 below provides an approximate schedule for permitting, construction and operations based on accelerated and full-term review periods. Accelerated Review Full-Term Review ITEM PERMIT APPLICATION ASSEMBLY AND SUBMITAL COMPLETENESS REVIEW SITE INVESTIGATIONS TECHNICAL REVIEW CONSTRUCTION OPERATIONS Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 JUL AUG SEP OCT NOV DEC J F M A M J J A S O N D J F M A M J J A S O N D 24-Jul Jul Jul Aug-17 1-Sep-17 1-Sep DAYS 1-Dec DAYS 26-Jan Jan Feb Dec Dec-19 Table 1: Site Schedule Our intention is to complete with work between 7:00 AM and 8:00 PM, Monday to Saturday. If any work is required outside of these hours, we will submit a Request for Amendment to Port of Vancouver. We understand that it may take up to 30 days for this amendment to be approved. During construction KLTP and its subcontractors will access the site to complete the aforementioned site preparations. We anticipate 1-2 contractors will be onsite each day, each having crews of up to 10 people, arriving in personal and/or company vehicles.

5 Marine contractors involved in the dock construction may also access the site via water. We currently anticipate the necessary pile for the trestle to arrive on barges and the structural steel to be delivered by truck. Further details on this will be provided as the design and planning progresses, prior to the issuance of this permit. Studies and Reports Final Structural and Geotechnical Design for the Trestle will be provided to VFPA for review and assessment prior to the issuance of this permit. These will be sealed by a Professional Engineer registered in the Province of BC. KLTP will also provide VFPA intermediary design drawings for review, as the design progresses. The design, construction and inspection of this structure will follow KLTP s policy for the Construction and Design of Temporary Structures and Construction Devices. The design and construction of any crane working surfaces will also follow the aforementioned policy. The final design and construction requirements of the trestle and crane working surfaces will be determined following a geotechnical site investigation. The Category A permit application for the completion of this investigation was recently approved and KLTP plans to complete the work in July and August, Appendix J is provided with this application as a preliminary assessment of the geotechnical site conditions and the work necessary to complete the geotechnical design for the site. The operational activity noise was considered and assessed in accordance to the PER guidelines. Upon completion of the project noise screening, the total weighted project score determined was A copy of the Project Noise Screening Worksheet can be found in Appendix I. A record of any noise complaints received by KLTP during construction or operations will be submitted to Port of Vancouver. Appendix K is provided as a Traffic Impact Study for the construction and operational use of the site. The study was prepared by a qualified Professional Traffic Engineer registered in British Columbia. Appendix H-1 through H-5 provide our Construction Environmental Management Plan (CEMP) and the following supporting documents: - Stormwater Pollution Prevention Plan - Spill Prevention and Emergency Response Plan - Terrestrial and Aquatic Bio-physical Survey Reports - Soil Management Plan (Part of the CEMP) As discussed in the Bio-physical Survey Reports, there is no planned tree or vegetation removal for this site. Prior to the issuance of this permit, KLTP will conduct the following studies in support of the application. - Site Utility Verification - Site topographical and legal surveys. o A preliminary site grading plan shown in Appendix G-1 Site Drainage Plan.

6 o A further detailed site grading plan will be initiated shortly and will be provided as part of Category C permit application in August, Review of any Environment Assessments provided by VFPA, include assessments conducted by the previous tenant. Additional studies and/or testing may be proposed pending KLTP s review of these documents. - The aforementioned geotechnical investigation Operations Once construction is complete, we will commence using the site for construction laydown and loading / offloading barges. Material expected to be handled and stored in the yard includes: steel pipe pile, steel sheet piles, steel beams, rebar, forms, lumber, beams, nuts and bolts, pipe modules, anchors, buoys, wire rope, skip boxes, piping spools, electrical components, and insulation. This storage and handling will continue until the completion of the Project, currently scheduled for December We anticipate approximately 50 vehicles will access the site each day during the operations period. These vehicles will mainly arrive at the site between 0600 hrs and 0700 hrs, and leave the site between 1530 hrs and 1800 hrs, Monday through Friday. The site will also be operational on Saturdays. We anticipate approximately 40 vehicles per day on Saturdays, arriving and leaving at similar times as during the work week. Buses will also be used to transport workers to sites throughout the project. This will require 1-2 buses, each making one trip at the start (~0630 hrs) and end (~1730 hrs) of each shift. Materials will be delivered to and hauled from site on road legal trucks. We anticipate up to 10 trucks per day will access the site. Appendix K is provided as a Traffic Impact Study. A 300T crawler crane and 100T rough terrain mobile crane will be stationed onsite to load / offload material from barges and road legal trucks in the laydown areas. Additional material handling equipment, such as forklifts and wheeled loaders will be onsite during the operational stage of the project. The equipment at Site 1 will consists of: - Liebherr LR T Crawler Crane - GR1000XL Tadano 100T RT Crane - Cat 966 Loader - 10 Ton Forklift - 20 Ton Fortlift - Welders - Air Compressors - Mechanics Truck - Portable Generators - Pile Driving Equipment (storage between season) - Company trucks

7 - Tractor Trucks with Trailer (to move pipe modules) - Man Lifts Marine Traffic We anticipate up to two barges being moored at site at any time and for barges to be brought to site, or hauled away from site approximately once per day. All barge moves will be controlled by tug boats with certified personnel. Appendix C shows our Marine Staging Plan. The anticipated draft of the barges and tug boats will vary between one and three meters. KLTP recently conducted a Bathymetric Survey of the area which confirmed that there is sufficient water depth to operate all our vessels as planned, regardless of the tide. Transit of Marine vessels will be conducted following the practices and procedures outlined in the Port Information Guide, particularly those regarding the MRA-2 area as the Second Narrows Railway Bridge is located between the 2115 Commissioner Street site and the Project site. This bridge provides 10.8m of vertical clearance at higher high water. We anticipate that the majority of our vessels will have an Air Draft of less than 8.8m, allowing for 2m of clearance under the structure. Communication of transits will be made with the Marine Communications and Traffic Services, per the MRA-2 Communications protocol. For vessels with an Air Draft of greater than 8.8m, marine transits may require special planning and consultation with BC Coast Pilots and Pacific Pilotage Authority. The water taxis will transport workers daily to the marine facility located approximately 5 km east of the Second Narrow s Bridge. This will require 2-3 water taxis, each making one trip at the start (~0630 hrs) and end (~1730 hrs) of each shift. One of these vessels will carry ~40 passengers and will measure 10.7m long x 4.8m wide. The other 1-2 vessels will carry 12 passengers and will measure 8.8m long x 3.4m wide. One of these water taxis will be on-call throughout the shift providing site access to supervisors, inspectors and other personnel. Aboriginal Consultation Consultation with Aboriginal groups has not been undertaken with regard to this site-specific project to date. KLTP understands VFPA will undertake an assessment to determine whether any of the proposed work could adversely impact asserted or established Aboriginal or treaty rights and to avoid, mitigate, or otherwise accommodate those impacts. KLTP will provide information requested by VFPA to inform its assessment as part of the application review. It is understood final determination of the legal duty to consult, scope of consultation, potential impacts to archaeological resources, participation funding and general timing will only be made upon review and consideration of a complete Project Application.

8 Public and Stakeholder Consultation The proposed project site is completely located within the jurisdiction of the VFPA. KLTP recognizes the longstanding and respectful relationship the VFPA has established with the communities adjacent to port lands; represented locally by the East Vancouver Port Lands (EVPL) Committee. KLTP has reviewed the EVPL Area Plan and acknowledges the efforts made by the community and the Port to balance the needs of residents and growing port trade. Consultation with the local community will be undertaken subject to guidance from the VFPA on their consultation requirements for this site-specific permit review. KLTP recognizes the proposed Project site was occupied by the original tenant for over 85 years. As such KLTP is respectful of local resident concerns to what changes of activity could be on site, including any changes to viewscape and marine activity to service the site. Consultation will help to refine project plans as the project undergoes project and environmental review; however, should the project be approved, ongoing communication with the community will remain an important element to supporting a collaborative working relationship between the VFPA and the community to address operational issues should they arise. End of Project At the end phase of the project, KLTP will remove all temporary structures, materials, and debris on site and perform a full site clean up to restore the premises back to its original state. Specifically KLTP will remove the trestle dock, flexi-floats, access ramps and any buildings brought onto site during the operations. Removals will follow similar means & methods to the early phase of construction. Closing We believe that we have provided sufficient information for you to review and accept our application as complete. Please do not hesitate to contact us if you have any questions or require any additional information. Sincerely, Kiewit Ledcor TMEP Partnership,

9 APPENDICES APPENDIX A SITE LAYOUT APPENDIX B SENSITIVE RECEPTORS OVERVIEW APPENDIX C MARINE STRUCTURES SITE APPENDIX D PRELIMINARY TRESTLE DESIGN APPENDIX E FLEXI-FLOAT AND ACCESS RAMP APPENDIX F LIGHTING PLAN APPENDIX G-1 SITE DRAINAGE PLAN APPENDIX G-2 EXISTING UTILITIES APPENDIX G-3 PROPOSED UTILITIES APPENDIX G-4 EMERGENCY VEHICLE ACCESS ROUTE APPENDIX H-1 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN APPENDIX H-2 STORMWATER POLLUTION PREVENTION PLAN APPENDIX H-3 SPILL PREVENTION AND EMERGENCY RESPONSE PLAN APPENDIX H-4 TERRESTRIAL BIO-PHYSICAL ASSESSMENT APPENDIX H-5 AQUATIC BIO-PHYSICAL ASSESSMENT APPENDIX I NOISE STUDY APPENDIX J GEOTECHNICAL ASSESSMENT PROPOSAL APPENDIX K TRAFFIC IMPACT STUDY

Kiewit Ledcor TMEP Partnership KLTP Temporary Construction Staging, Parking & Barge Loading COPY

Kiewit Ledcor TMEP Partnership KLTP Temporary Construction Staging, Parking & Barge Loading COPY PER No.: 17-122 Tenant: Project: Project Location: VFPA SID No.: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL REVIEW PROJECT PERMIT Kiewit Ledcor TMEP Partnership KLTP Temporary Construction

More information

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO COMMISSIONER STREET KLTP TEMPORARY CONSTRUCTION STAGING, PARKING & BARGE LOADING

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO COMMISSIONER STREET KLTP TEMPORARY CONSTRUCTION STAGING, PARKING & BARGE LOADING PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO. 17-122 2115 COMMISSIONER STREET KLTP TEMPORARY CONSTRUCTION STAGING, PARKING & BARGE LOADING Prepared for: Director, Planning & Development May 18, 2018

More information

Vancouver Wharves Diesel Handling Facility Expansion Project

Vancouver Wharves Diesel Handling Facility Expansion Project Vancouver Wharves Diesel Handling Facility Expansion Project March 2018 1 Project Information 1. Vancouver Wharves Today 2. Project Rationale 3. Project Overview New Tanks, Railcar and Vessels 4. Project

More information

Trans Mountain Expansion Project Overview

Trans Mountain Expansion Project Overview Trans Mountain Expansion Project Overview 1 Proposed Expansion Project $6.8-billion capital cost Expand capacity to 890,000 bpd Project scope 980 kms new pipe 12 new pump stations 19 new tanks 3 new tanker

More information

Appendix C Canadian Pacific Rail License of Entry Document

Appendix C Canadian Pacific Rail License of Entry Document Appendix C Canadian Pacific Rail License of Entry Document 01-13283-GG-0000-SE-RPT- 0001 Trans Mountain Expansion Project License of Entry CP Rail Contractor Revision Date: Contractor Revision No.: 2017-03-06

More information

Neptune Cargill Overpass Extension

Neptune Cargill Overpass Extension Project Environmental Review UPDATE November 23, 2017 Northshore Waterfront Liaison Committee Teck Agenda Project Objectives Project Description Project Discussion VFPA PER process Project Review Status

More information

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO. 15-322 WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT August 23, 2017 Prepared for: Project and Environmental Review Committee Table of Contents

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

COPY. Land Use Plan to be amended. Port Water proposed.

COPY. Land Use Plan to be amended. Port Water proposed. PER No.: 15-167 Applicant: Project: Project Location: VFPA SID No.: Land Use Designation: Category of Review: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL REVIEW PROJECT PERMIT Vancouver Fraser

More information

APPENDIX 8-A. Valued Component Selection Rationale

APPENDIX 8-A. Valued Component Selection Rationale APPENDIX 8-A Valued Component Selection Rationale This page is intentionally left blank A list of candidate s was compiled based on issues identified through the scoping process described in Section 8.1.2

More information

BC Metis Federation AGM Burnaby. Trans Mountain Expansion Project October 1, 2017 Phil Symington & Troy Schwab

BC Metis Federation AGM Burnaby. Trans Mountain Expansion Project October 1, 2017 Phil Symington & Troy Schwab BC Metis Federation AGM Burnaby Trans Mountain Expansion Project October 1, 2017 Phil Symington & Troy Schwab Current Pipeline Current capacity 47.7 million litres or 300,000 barrels capacity per day 34,000

More information

VFPA Project & Environmental Review Permit Application

VFPA Project & Environmental Review Permit Application Appendix A VFPA Project & Environmental Review Permit Application Western Canada Marine Response Corporation Oil Spill Response Base 2800 Commissioner Street Prepared by WCMRC Revision NR Page 1 of 13

More information

To develop the new facility, the following site preparation and construction activities are planned.

To develop the new facility, the following site preparation and construction activities are planned. Project Description To develop the new facility, the following site preparation and construction activities are planned. Site Preparation: Remove existing structures and asphalt within building footprints.

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013 PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013 NAME LOCATION MAWSS Shelton Beach Road East side of Shelton Beach Road Extension, 2/10± mile North of Moffett Road CITY

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS 1.0 DESCRIPTION The Work shall consist of:.1 Transportation, unloading, erection and grouting of precast prestressed concrete

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Neptune Bulk Terminals Canada Ltd. Neptune Coal Capacity Amendment West Quadrant Shiploader COPY

Neptune Bulk Terminals Canada Ltd. Neptune Coal Capacity Amendment West Quadrant Shiploader COPY PER No.: 12-066-01 Tenant: Project: Project Location: VFPA SID No.: Land Use Designation: Applicant/Permit Holder: Category of Review: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL REVIEW REPORT

More information

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO NEPTUNE BULK TERMINALS (CANADA) LTD. DUST SUPPRESSION UPGRADE

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO NEPTUNE BULK TERMINALS (CANADA) LTD. DUST SUPPRESSION UPGRADE PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO. 16-072 NEPTUNE BULK TERMINALS (CANADA) LTD. DUST SUPPRESSION UPGRADE Prepared for: Director, Planning & Development May 15, 2017 VANCOUVER FRASER PORT AUTHORITY

More information

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development

More information

VANCOUVER FRASER PORT AUTHORITY Project and Environmental Review Project Report COPY

VANCOUVER FRASER PORT AUTHORITY Project and Environmental Review Project Report COPY Project and Environmental Review Report Warehouse Development (Phase 3) Prepared for: Greg Yeomans Director, Planning & Development Date: October 5, 2015 Prepared by: Andrew Taylor, Senior Planner Page

More information

McLoughlin Point Wastewater Treatment Plant. CRD Contract No: CAWTP Submittal No: AGJV-PLAN-022. McLoughlin Point Traffic Management Plan

McLoughlin Point Wastewater Treatment Plant. CRD Contract No: CAWTP Submittal No: AGJV-PLAN-022. McLoughlin Point Traffic Management Plan McLoughlin Point Wastewater Treatment Plant CRD Contract No: CAWTP-17-006 Submittal No: AGJV-PLAN-022 McLoughlin Point Traffic Management Plan Quality Information Prepared by Checked by Approved by J.

More information

TAURANGA CITY COUNCIL

TAURANGA CITY COUNCIL TAURANGA CITY COUNCIL CONDITIONS FOR SOUTHERN PIPELINE APPLICATION (RC13559) 1. The proposal shall proceed in accordance with the application submitted including: - The Assessment of Effects on the Environment

More information

Korea to Vancouver, Wa. by ship discharge directly to river barge transit time about 15 days.

Korea to Vancouver, Wa. by ship discharge directly to river barge transit time about 15 days. Korea to Vancouver, Wa. by ship discharge directly to river barge transit time about 15 days. Traditional routes from the Far East to Ft. McMurray Houston, Tx. Ocean voyage 9,979 nm 32 days at 14 kn. Road

More information

WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY

WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY WESTRIDGE MARINE TERMINAL IN WATER EXCAVATION REPORT WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY Trans Mountain Pipeline ULC Kinder Morgan Canada

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT. General Manager of Engineering Services in consultation with the Director of Current Planning

CITY OF VANCOUVER ADMINISTRATIVE REPORT. General Manager of Engineering Services in consultation with the Director of Current Planning CITY OF VANCOUVER ADMINISTRATIVE REPORT Date: September 1, 2005 Author: Dale Bracewell Phone No.: 604.871.6440 RTS No.: 5291 CC File No.: 8203 Meeting Date: September 20, 2005 TO: FROM: SUBJECT: Standing

More information

A Guide to Project Review

A Guide to Project Review A Guide to Project Review Updated March 2015 Vancouver Fraser Port Authority, doing business as Port Metro Vancouver, has prepared this guide to assist tenants, terminal operators, consulting firms and

More information

New Administration Building

New Administration Building New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180

More information

Cargill. North Vancouver Grain Terminal Power System Upgrade

Cargill. North Vancouver Grain Terminal Power System Upgrade Cargill North Vancouver Grain Terminal Power System Upgrade Project Overview Construction of new 69kV/12.47kV indoor substation c/w environmental safeguards Construction of one new power distribution center

More information

Supports Item No. 3 T&T Committee Agenda February 17, 2009

Supports Item No. 3 T&T Committee Agenda February 17, 2009 Supports Item No. 3 T&T Committee Agenda February 17, 2009 ADMINISTRATIVE REPORT Report Date: February 6, 2009 Contact: Jerry Dobrovolny Contact No.: 604.873.7331 RTS No.: 07712 VanRIMS No.: 08-2000-20

More information

Wharf, Dock and Buoy Policy

Wharf, Dock and Buoy Policy DEV-250 Wharf, Dock and Buoy Policy Effective Date: June 12, 2018 Authorized By: Council Regular Meeting Replaces: August 28, 2012 April 12, 2011 1.1 Policy Statement The District of Peachland has entered

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

PENDER HARBOUR DOCK MANAGEMENT PLAN

PENDER HARBOUR DOCK MANAGEMENT PLAN PENDER HARBOUR DOCK MANAGEMENT PLAN 1.0 INTENT OF DOCK MANAGEMENT PLAN The Pender Harbour Dock Management Plan (the DMP) is an instrument of policy that provides guidance in relation to docks authorized

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Project Area: Outfall IJKL

Project Area: Outfall IJKL Project Area: Outfall IJKL Outfall IJKL is a stormwater drainage pipe at the west end of Crissy Field. Location of Extended Outfall Restricted Beach Access Work Area Manhole Modification CRISSY FIELD DRAINAGE

More information

Welcome. For more information:

Welcome. For more information: Welcome Thank you for attending Port Metro Vancouver s open house about the South Shore Corridor Project. The purpose of this open house is to: Share project information Answer your questions and hear

More information

Maritime Work Plan for the High Rise Bridge Construction

Maritime Work Plan for the High Rise Bridge Construction Maritime Work Plan for the High Rise Bridge Construction Version 6, 10/3/2018 I 64 Southside Widening & High Rise Bridge, Phase 1 Chesapeake, Virginia Design Build Project State Project No.: 0064 131 811,

More information

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE Chapter 17: Construction A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter discusses the various activities that would be involved in constructing Hamilton Green. The potential for significant adverse

More information

Preliminary Project Assessment

Preliminary Project Assessment DISCLAIMERS: Date: March 14, 2014 Case No.: 2014.0097U Project Address: Third Street Crossing of Islais Creek Block/Lot: Public Right-of-Way Zoning: Not Applicable Area Plan: Not Applicable Project Sponsor:

More information

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution. ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special

More information

SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT TENNESSEE VALLEY AUTHORITY

SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT TENNESSEE VALLEY AUTHORITY Document Type: EA-Administrative Record Index Field: Finding of No Significant Impact (FONSI) Project Name: Fukushima Response Strategy Project Number: 2012-12 SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT AND

More information

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO G3 TERMINAL VANCOUVER. Date: May 30, 2016

COPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO G3 TERMINAL VANCOUVER. Date: May 30, 2016 PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO. 15-180 G3 TERMINAL VANCOUVER Date: May 30, 2016 Prepared for: Project and Environmental Review Committee VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL

More information

Project & Environmental Review. Guidelines Demolition. May 2016

Project & Environmental Review. Guidelines Demolition. May 2016 Project & Environmental Review Guidelines Demolition May 2016 TABLE OF CONTENTS 1. Introduction... 3 2. Objectives... 3 3. Applicability and Building Permits... 3 4. Guidelines for Preparing a Project

More information

Environmental Setting

Environmental Setting Trans Mountain is seeking approval for a Certificate of Public Convenience and Necessity (CPCN) from the National Energy Board (NEB) for a $5.4 billion expansion of its oil pipeline system from Strathcona

More information

Dormay Street & King George s Park Community Liaison Working Group 12 October 2017

Dormay Street & King George s Park Community Liaison Working Group 12 October 2017 Dormay Street & King George s Park Community Liaison Working Group 12 October 2017 DORMAY STREET Dormay Street Overview This site will be used to connect the existing local combined sewer overflow to the

More information

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES SAND AND GRAVEL PERMIT APPROVING WORK SYSTEM AND RECLAMATION PROGRAM (Issued pursuant to Section 10 of the Mines Act R.S.B.C. 1996, C.293) Permit:

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology

More information

PUBLIC IMPACT MITIGATION PLAN

PUBLIC IMPACT MITIGATION PLAN PUBLIC IMPACT MITIGATION PLAN CONSULTATION SUMMARY REPORT Phase 1: May 18 to June 8, 2017 Phase 2: June 7 to June 21, 2017 PREFACE This report presents the findings from the Public Impact Mitigation Plan

More information

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC MARINE WORKS shafaconstruction.com SHAFA AL NAHDAH SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC Al Manara Tower, ETA Star 23rd Floor, Office no. 2302-04, Business Bay, P.O. Box 252050

More information

Guideline for Bridge Safety Management February 2012

Guideline for Bridge Safety Management February 2012 Guideline for Bridge Safety Management February 2012 Table of Contents Foreword Part A General 0.1 Definitions 0.2 Scope 0.3 Application 0.4 Responsibility Part B Bridge Safety Assurance 1.1 Scope 1.2

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount CPM Constructors - Freeport, ME $13,984,117.36 Reed & Reed, Inc. - Woolwich, ME $14,883,139.00 Page 1 of 11 CPM Constructors Freeport, ME 201.11 Clearing AC 2.00 10000.00

More information

Project Review Application Form

Project Review Application Form Project Review Application Form Information supplied in this application may be made public during consultation with adjacent municipalities, First Nations groups and other interested parties, as well

More information

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION APPENDIX I BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION South Bay Salt Pond Restoration Project Phase 2 July 2015 Draft Environmental Impact Statement/Report 2185 N. California Blvd., Suite

More information

CH2M Hill Bigge Crane & Rigging SRT Transportation Solutions Union Pacific Distribution Services

CH2M Hill Bigge Crane & Rigging SRT Transportation Solutions Union Pacific Distribution Services CH2M Hill Bigge Crane & Rigging SRT Transportation Solutions Union Pacific Distribution Services ORIGIN TO DESTINATION Port of Wilma, WA to Great Falls, MT October 8, 2015 2015 Breakbulk Americas Houston,

More information

Miami River Freight Improvement Plan Financial Management Number:

Miami River Freight Improvement Plan Financial Management Number: Miami River Commission January 8, 2018 Miami, FL Carlos A. Castro, District Freight Coordinator Miami River Freight Improvement Plan Financial Management Number: 437946-1-22-01 Agenda Study Background

More information

Impacts of Dredging and Reclamation on Noise and Amenity

Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5 Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5.1 Management Goals for Noise and Amenity The management goals for noise and vibration are to: Minimise the noise associated

More information

MIXED ACTIVITY ZONE. Chapter 4. Mixed Activity Zone

MIXED ACTIVITY ZONE. Chapter 4. Mixed Activity Zone Chapter 4 Mixed Activity Zone 4. MIXED ACTIVITY ZONE 4.1 RESOURCE MANAGEMENT ISSUES 1. Activities adjoining main arterial roads can adversely affect the safety, sustainability and efficiency of the network.

More information

B.C. MINIST RY OF TRANSPORTATION. Maintenance Specification Chapter FLOOD CONTROL AND WASHOUT RESPONSE

B.C. MINIST RY OF TRANSPORTATION. Maintenance Specification Chapter FLOOD CONTROL AND WASHOUT RESPONSE B.C. MINIST RY OF TRANSPORTATION Maintenance Specification Chapter 7-760 FLOOD CONTROL AND WASHOUT RESPONSE 1. OBJECTIVE To safeguard Highway Users and adjacent properties; to prevent damage to Highways

More information

Completed Many Studies

Completed Many Studies Overview What is Goods Movement? Strategy Need and Approach Challenges Strategic Directions for Discussion Input from Committee on Issues and Priorities 2 1 What is Goods Movement? 3 Completed Many Studies

More information

2800 Commissioner Street Wharf Stormwater Pollution Prevention Plan

2800 Commissioner Street Wharf Stormwater Pollution Prevention Plan 2800 Commissioner Street Wharf Stormwater Pollution Prevention Plan Prepared for: Western Canada Marine Response Corporation 201 Kensington Avenue Burnaby, BC V5C 5P2 Prepared by: Hemmera Envirochem Inc.

More information

PRECAST CONCRETE GIRDER ERECTION

PRECAST CONCRETE GIRDER ERECTION 7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks

More information

Section Safety Section Cleanup. None Required

Section Safety Section Cleanup. None Required January 2000 Page 1 of 6 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED SECTIONS PART 2 PRODUCTS The General Conditions of the Contract, General Requirements, and Supplemental

More information

South Quay. hayle harbour : : regeneration. Development Proposal for South Quay/Foundry Yard Hayle Harbour. Quay Walls Restoration Method Statement

South Quay. hayle harbour : : regeneration. Development Proposal for South Quay/Foundry Yard Hayle Harbour. Quay Walls Restoration Method Statement hayle harbour : : regeneration South Quay Development Proposal for South Quay/Foundry Yard Hayle Harbour December 2010 Quay Walls Restoration Method Statement 027802 Hayle Harbour, South Quay/Foundry

More information

MARINA PHASING AND COSTS

MARINA PHASING AND COSTS WATERFRONT PLACE IMPLEMENTATION STRATEGY Prepared for Port of Everett TEAM Reid Middleton BST Associates RMC Architects MARINA PHASING AND COSTS This section Prepared by: Reid Middleton September 2014

More information

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10 EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street

More information

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Vancouver Fraser Port Authority Habitat Enhancement Program Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Public consultation September 24 October 12, 2018 Feedback form

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA 106-5(a-f) 09 OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA These Special Provisions amend, revise, and where in conflict, supersede applicable sections of the 2009 Standard

More information

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. December 5, 2017

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. December 5, 2017 SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY December 5, 2017 The Members of the Woods Hole, Martha's Vineyard and Nantucket Steamship Authority ( SSA )

More information

INDEX FM Page

INDEX FM Page INDEX Accessory equipment Adaptation of floating cranes Anchoring of pile driver rafts Anchor piles Cast-in-place piles Precast concrete piles Sheet piles Steel sheet piling Timber piles Batter piles:

More information

B. OVERVIEW OF CONSTRUCTION ACTIVITIES

B. OVERVIEW OF CONSTRUCTION ACTIVITIES Attachment F: Construction A. INTRODUCTION As discussed in Attachment A, Project Description and Screenings, the proposed installation would involve the placement of a skeletal stainless steel sculpture

More information

8367 TRANSPORTATION WORKER 3

8367 TRANSPORTATION WORKER 3 TRANSPTATION WKER 3 Nature of Work Under limited supervision, at the journey level performs skilled work in the construction and maintenance of highways, related buildings and structures, and erecting

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

legend. #1 is a gas relief valve? If so does Enbridge supply with station?

legend. #1 is a gas relief valve? If so does Enbridge supply with station? Michael Pacholok, Director Purchasing and Materials Management Division City Hall, 8 th Floor, West Tower 00 Queen Street West Toronto, Ontario M5H N Joanne Kehoe Manager Construction Services May 4, 06

More information

COPY. Kinder Morgan Canada Westridge Marine Terminal Upgrade and Expansion Project. Suite 2700, Avenue S.W., Calgary, Alberta T2P 5J2

COPY. Kinder Morgan Canada Westridge Marine Terminal Upgrade and Expansion Project. Suite 2700, Avenue S.W., Calgary, Alberta T2P 5J2 PER No.: 15-322 Tenant: Project: Project Location: VFPA SID No.: BBY 092 Land Use Designation: Applicant(s): Applicant Address: Category of Review: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw

More information

Electric Service Handbook

Electric Service Handbook Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated

More information

Nutrient Removing Filtration System

Nutrient Removing Filtration System Nutrient Removing Filtration System Contractor Installation Manual Version 1.0 Suntree Technologies, Inc 798 Clearlake Road, Suite 2 Cocoa, Florida 32922 321.637.7552 www.suntreetech.com info@suntreetech.com

More information

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012 PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375

More information

Trans Canada Hwy. No.1 Donald Bridges and Approaches

Trans Canada Hwy. No.1 Donald Bridges and Approaches Ministry of Transportation and Infrastructure REQUEST FOR EXPRESSION OF INTEREST Project Number 21754 Trans Canada Hwy. No.1 Donald Bridges and Approaches Conceptual and Detailed Bridge Design & Functional

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

Section 6 - Loading/Unloading Rules, Regulations & Charges

Section 6 - Loading/Unloading Rules, Regulations & Charges Section 6 - Loading/Unloading Rules, Regulations & Charges DEFINITION - LOADING AND UNLOADING 600 Loading and unloading means the services of loading or unloading cargo between any place or point of rest

More information

SAND POINT CITY DOCK REPLACEMENT ALTERNATIVES ANALYSIS REPORT

SAND POINT CITY DOCK REPLACEMENT ALTERNATIVES ANALYSIS REPORT SAND POINT CITY DOCK REPLACEMENT ALTERNATIVES ANALYSIS REPORT Prepared for: City of Sand Point 3380 C Street, Suite 205 Anchorage, Alaska 99503 Prepared by: PND Engineers, Inc. 1506 W. 36 th Avenue Anchorage,

More information

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 The General Trade Knowledge examination will be administered in one session

More information

Vancouver Airport Fuel Delivery Project

Vancouver Airport Fuel Delivery Project Vancouver Airport Fuel Delivery Project ABOUT THE PROJECT Vancouver Airport Fuel Facilities Corporation (VAFFC) is constructing a new aviation fuel delivery system to serve the airlines at Vancouver nternational

More information

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area

More information

Division 15 Earthworks Code (including Lot Filling)

Division 15 Earthworks Code (including Lot Filling) Division 15 Earthworks Code (including Lot Filling) 12.15.1 Earthworks Code (1) The provisions in this division comprise the (2) They are compliance with the Earthworks Code (Section 12.15.2); overall

More information

Noise Abatement Guidelines. Regional Official Plan Guidelines

Noise Abatement Guidelines. Regional Official Plan Guidelines Noise Abatement Guidelines Regional Official Plan Guidelines Halton Region Official Plan Guidelines The Regional Official Plan (ROP) is Halton s guiding document for land use planning. It contains policies

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

Construction Noise Management Plan

Construction Noise Management Plan Construction Noise Management Plan Victoria Park Viaduct Side Protection Upgrade Project 27 November 2014 Final Page 2 Record of amendment Revision Description of change Effective date Updated by Incomplete

More information

PORT INFORMATION GUIDE NOTICE OF AMENDMENT

PORT INFORMATION GUIDE NOTICE OF AMENDMENT PORT INFORMATION GUIDE NOTICE OF AMENDMENT Date Issued: June 15 th, 2015 Date effective: July 15 th, 2015 Subject: This notice is being posted publicly to notify industry, stakeholders and the public of

More information

Gunlake Quarry. Traffic Management Plan

Gunlake Quarry. Traffic Management Plan Gunlake Quarry Traffic Management Plan March 2016 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Driver Code of Conduct 3 2.1 Purpose of the Code 3 2.2 General Requirements

More information

6. Project Description

6. Project Description 6. Project Description As previously noted, the Project will supply electricity from the 500 kv system to the 230 kv system in order to replace the loss of the Pickering NGS (see Section 1.1 for the need

More information

DESIGN GRADING AND EROSION CONTROL A. Slope Criteria

DESIGN GRADING AND EROSION CONTROL A. Slope Criteria Section 5. DESIGN GRADING AND EROSION CONTROL A. Slope Criteria Earthen slopes shall conform to the following: Maximum slope should not be steeper than 6:1 (horizontal to vertical) unless protected from

More information

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 ABSTRACT Stephen Schmid Bechtel-SAIC Company, LLC Washington, DC Alexander Thrower U.S. DOE,

More information