UCLH Community Liaison Group

Size: px
Start display at page:

Download "UCLH Community Liaison Group"

Transcription

1 UCLH Community Liaison Group Tuesday 2 nd June, 6.30pm UCLH Phase 4

2 Agenda 1. Introductions Bouygues UK Preferred bidder on Phase 4 2. Advanced Works Agreement Planned activities on site by Bouygues UK 3. Construction update Timescales 4. The main works 5. Minimising the impact on our neighbours 6. Utility Diversions update 7. Next steps Stakeholder Forum - Tuesday 14 July

3 Introducing Bouygues UK Colin Boyd Loic Menard Eric Pincemin Design Director Project Director Production Director 3

4 Bouygues UK Bouygues UK is a major contractor in the construction, housing and development sectors, with a combined turnover of around 860 million, approximately 130 sites and 1,800 people. Bouygues UK deliver innovative and sustainable construction with intelligent management over the life of each project, constantly striving for efficiency and excellence. As a national business, Bouygues UK recognise the importance of a local focus when delivering major projects. Their long-term commitment to clients, partners and the communities in which they operate, shape their decisions and actions. 4

5 Bouygues UK - At a Glance 5

6 Bouygues UK Part of Bouygues Group Bouygues UK is wholly owned by Bouygues Bâtiment International, a subsidiary of Bouygues Construction. A leader in sustainable construction, the Group has a long-term commitment to helping its customers shape a better life. 6

7 Advanced Works Agreement Bouygues UK has been appointed by UCLH to proceed with the relocation of the Oxygen tanks (VIE). Current Oxygen Storage Facility New Oxygen Storage Facility on University Street 7

8 Advanced Works Agreement 1) Extension of the hoarding on University Street to ease works on the new VIE location including the vault. Site Plan - Current Situation 8

9 Advanced Works Agreement 2) Hoarding moved on University Street 9

10 Advanced Works Agreement 3) Propping and cutting of the existing ground floor slab and removal of column in the basement of the future VIE location. 10

11 Advanced Works Agreement 4) Construction of the new VIE structure 11

12 Main construction works - update Bouygues UK is UCLH s preferred contractor for the construction of the new building. Once the advanced works are completed, main construction works will begin. Timescales June 2015 Advanced works begin. July/August 2015 Advanced works completed July 2015 Community Liaison Group July/August 2015 Construction phase starts including preparation for basement excavations. 12

13 The main works July August 2015: Completion of the advanced works August 2015: Extension of the site hoarding on Grafton Way and Huntley Street 13

14 The main works August 2015 August 2016: Demolition of Rosenheim basement and excavation Summer 2016: Cranes installations 14

15 The main works 2017: Main structure works : Façade, trades E&M works including testing and commissioning 15

16 The main works Access to site and hoarding during the main works 16

17 Minimising the impact on our neighbours Working hours as agreed with LB Camden: 8am 6pm, Monday Friday 8am 1pm on Saturdays. No work to be undertaken on Sundays. Traffic management: Most deliveries and vehicles will access the site from Grafton Way. Noise, vibration and dust monitoring: There may be an increase in noise and vibration, but this will be minimal and well within the agreed limits. Non percussive Piling works. Continuous control and monitoring. Communication: During working hours the Site Manager will be contactable by phone. A 24/7 hotline will also be established. Regular information will be provided through newsletters as well as during regular stakeholder forum meetings. 17

18 Utility Diversions Grafton Way Most of the work on Grafton Way is now almost complete. Grafton Way is now partly open to traffic. University Street Work is underway at University Street and nearing completion. University Street will be re-opened to traffic in July Huntley Street Work on Huntley Street (between Grafton Way and University Street) has now started. Traffic and parking restrictions are in place. Work is due to be completed by the end of July

19 Next steps Next Liaison group meeting: Tuesday 14 th July 2015 Contact: James McEwan Local Dialogue

Audley Square House Presentation

Audley Square House Presentation Audley Square House Presentation Progress To Date Key Activities The demolition to ground floor of Audley square house was completed on time in June 2017 Cantillon have since been undertaking investigations

More information

Audley Square House Presentation

Audley Square House Presentation Audley Square House Presentation Company Profile Our history and ethos Second generation family run business Successfully trading for 50 years Annual turnover 25-30m Full client and team focus big enough

More information

Welcome.

Welcome. Welcome Welcome to the consultation event for the proposed Construction and Environmental Management Plan (CEMP) for Taylor Wimpey Central London s development of Mount Pleasant. The CEMP relates to Phoenix

More information

Audley Square House Presentation January 2017

Audley Square House Presentation January 2017 Audley Square House Presentation January 2017 Audley Square Team Operations Director Paul Moody A demolition specialist for over 21 years Extensive industry experience of all forms of demolition and ground

More information

Construction Environment Management Plan. Planning Condition 5.

Construction Environment Management Plan. Planning Condition 5. Construction Environment Management Plan. Planning Condition 5. No development shall take place, including any works of demolition, until a construction method statement in respect of construction environment

More information

Brighton & Sussex University Hospital

Brighton & Sussex University Hospital Brighton & Sussex University Hospital Regional Centre for Teaching, Trauma & Tertiary Care known as the 3Ts Programme Project Address: Eastern Road, Brighton BN2 5BE Principal Contractor: Laing O Rourke

More information

4 Major Challenges 2,000. with Constructing the Hung Hom Section. hours. Aug. of work everyday. On average. Hung Hom Section newsletter.

4 Major Challenges 2,000. with Constructing the Hung Hom Section. hours. Aug. of work everyday. On average. Hung Hom Section newsletter. Aug 2016 4 Major Challenges with Constructing the Hung Hom Section The construction of the SCL s Hung Hom section includes the transformation of Hung Hom Station into a major interchange station. Two new

More information

Demolition & Construction

Demolition & Construction Demolition & Construction Your Concerns: Residents, particularly those who live in close proximity to the site, have raised a number of issues about the demolition and construction process. These include:

More information

ARCHITECTUS FEBRUARY 2010

ARCHITECTUS FEBRUARY 2010 ARCHITECTUS PEDESTRIAN AND TRAFFIC MANAGEMENT PLAN FOR DEMOLITION, EXCAVATION AND CONSTRUCTION OF COLLEGE OF FINE ARTS CAMPUS, PADDINGTON FEBRUARY 2010 COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296

More information

Building a "NEW" NY Bridge

Building a NEW NY Bridge Building a "NEW" NY Bridge From Dysfunction to Construction After more than a decade of delay, a New NY Bridge to replace the Tappan Zee is becoming a reality. Tappan Zee Constructors contract has been

More information

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing OVERVIEW Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing Construction Liaison Group Nov 7th, 2013 1 WORKS IN PROGRESS Construction Liaison Group Nov 7 th, 2013

More information

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017 1107 E. Madison Street Student Housing Project Monthly Update May 12, 2017 Anticipated Completion: Fall 2018 About the Project: This newly constructed building will be ten stories providing eight floors

More information

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017 Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.

More information

Construction Noise Management Plan

Construction Noise Management Plan Construction Noise Management Plan Victoria Park Viaduct Side Protection Upgrade Project 27 November 2014 Final Page 2 Record of amendment Revision Description of change Effective date Updated by Incomplete

More information

8 Noise and Vibration

8 Noise and Vibration 8 Noise and Vibration 8.1 Introduction This chapter of the EIS assesses the potential noise and vibration impact of the Proposed Project on the baseline environment. The potential noise impact due to the

More information

FELNEX TRADING ESTATE, LONDON ROAD, HACKBRIDGE

FELNEX TRADING ESTATE, LONDON ROAD, HACKBRIDGE FELNEX TRADING ESTATE, LONDON ROAD, HACKBRIDGE NEIGHBOURHOOD NEWSLETTER REGARDS THE CONTINUED DEMOLITION AND ENABLING WORKS FELNEX TRADING ESTATE, LONDON ROAD, HACKBRIDGE NEIGHBOURHOOD NEWSLETTER INDEX

More information

LAKE + FOREST CONSTRUCTION TIMELINE

LAKE + FOREST CONSTRUCTION TIMELINE LAKE + FOREST CONSTRUCTION TIMELINE Below is a construction timeline in connection with the project at Lake Street and Forest Avenue. All dates are approximate and subject to change based on weather and

More information

CURRICULUM VITAE. Personal Details. Technical Director Temporary Works. Professional Qualifications. BE (Hons), Eur Ing, CEng, MICE, FIEI

CURRICULUM VITAE. Personal Details. Technical Director Temporary Works. Professional Qualifications. BE (Hons), Eur Ing, CEng, MICE, FIEI CURRICULUM VITAE Personal Details Name: Position: John Sharkey Technical Director Temporary Works Professional Qualifications BE (Hons), Eur Ing, CEng, MICE, FIEI Key Role Responsibilities Responsible

More information

THE EXO BUILDING POINT VILLAGE CONSTRUCTION METHODOLOGY PLAN PROJECT NO. C th SEPTEMBER 2015

THE EXO BUILDING POINT VILLAGE CONSTRUCTION METHODOLOGY PLAN PROJECT NO. C th SEPTEMBER 2015 THE EXO BUILDING POINT VILLAGE CONSTRUCTION METHODOLOGY PLAN PROJECT NO. C705 15 th SEPTEMBER 2015 THE EXO BUILDING POINT VILLAGE NOTICE This document has been produced by O Connor Sutton Cronin & Associates

More information

Code of Construction Practice Part B: Site Specific Requirements

Code of Construction Practice Part B: Site Specific Requirements Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Blackfriars

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE. Construction and Environmental Management Plan

TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE. Construction and Environmental Management Plan TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE Construction and Environmental Management Plan Revisions Date Version Purpose Produced By January 2018 Rev A 1 st Draft JMP February 2018 Rev B 2 nd Draft JMP

More information

6.0 CONSTRUCTION PROGRAMME

6.0 CONSTRUCTION PROGRAMME 6.0 CONSTRUCTION PROGRAMME Introduction 6.1 This chapter of the ES describes the expected construction works programme and the key activities that will be undertaken. Detailed consideration of potential

More information

Code of Construction Practice Part B: Site Specific Requirements

Code of Construction Practice Part B: Site Specific Requirements Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Falconbrook

More information

Lodge Grove Development Sander and Sons 2 St. John s Wood Road NW8. CLP Produced by: Name Signature Date

Lodge Grove Development Sander and Sons 2 St. John s Wood Road NW8. CLP Produced by: Name Signature Date Outline CLP Template Development Name: Landowner: Site address: Site postcode: Lodge Grove Development Sander and Sons 2 St. John s Wood Road NW8 Construction logistics Manager: Phone number: Email: Logistics

More information

The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, :30 p.m. - 8:00 p.m.

The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, :30 p.m. - 8:00 p.m. The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, 2017 6:30 p.m. - 8:00 p.m. Meeting purpose & elected officials represented PURPOSE OF MEETING: Continue

More information

TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE. Construction and Environmental Management Plan

TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE. Construction and Environmental Management Plan TAYLOR WIMPEY MOUNT PLEASANT PHOENIX PLACE Construction and Environmental Management Plan Revisions Date Version Purpose Produced By January 2018 Rev A 1 st Draft JMP February 2018 Rev B 2 nd Draft JMP

More information

Ongoing and Future Project Work. Construction Management

Ongoing and Future Project Work. Construction Management Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era

More information

19. Summary of Impacts and Mitigation

19. Summary of Impacts and Mitigation 19. Summary of Impacts and Mitigation 19.1 The philosophy of the proposed Berth 201/202 works has been to meet the commercial need by avoiding and/or minimising environmental impacts where possible. For

More information

D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS

D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS HIGH SPEED TWO INFORMATION PAPER D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS This paper outlines the range of construction compounds and the criteria used to select them for Phase One of HS2.

More information

El Dorado Avenue

El Dorado Avenue A t t a c h m e n t 1 F i n d i n g s a n d C o n d i t i o n s 1995-1999 El Dorado Avenue Use Permit #08-10000055 JULY 10, 2008 CEQA FINDINGS 1. The project is categorically exempt from the provisions

More information

Environmental Policy

Environmental Policy Environmental Policy July 2014 C.E.P Demolition Ltd Yard E Barclay Curle Complex 739 South Street Whiteinch Glasgow G14 0BX Tel: 0141 569 1577 0141 569 1579 Email: enquiries@cepdemolition.co.uk Section

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE ISSUE 01 SUMMER 2013

We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE ISSUE 01 SUMMER 2013 We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE 020 3697 6220 elephantandcastle.org.uk ISSUE 01 SUMMER 2013 Investing in Elephant & Castle ISSUE

More information

Local Authority Borough: Caerphilly County Borough Council. Contact: Huw Morgan

Local Authority Borough: Caerphilly County Borough Council. Contact: Huw Morgan Case Study Theme: Our Environment Local Authority Borough: Caerphilly County Borough Council Good Practice: Blackwood Transport Interchange Contact: Huw Morgan - 01495 235089 - morganash@caerphilly.gov.uk

More information

I am writing to advise you of the outcome of the COLPAI Progress Event held on the evening of Wednesday 6 February at Tudor Rose Court.

I am writing to advise you of the outcome of the COLPAI Progress Event held on the evening of Wednesday 6 February at Tudor Rose Court. Department of Community and Children's Services Andrew Carter Director of Community and Children's Services The Resident Golden Lane Estate London EC1Y 0SJ Date 22 nd February 2019 Dear Sir/Madam, COLPAI

More information

Chambers Wharf Community Liaison Working Group 12 February 2018

Chambers Wharf Community Liaison Working Group 12 February 2018 Chambers Wharf Community Liaison Working Group 12 February 2018 Legacy 2 Recruitment 42 local people have started working with us 34% of new starters were previously workless 5 ex-offenders 14 apprentices

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

University of Manitoba - Project Site Safety Plan

University of Manitoba - Project Site Safety Plan Project Information Physical Plant 89 Freedman Crescent Winnipeg, MB Canada R3T 2N2 Phone: 204-272-1634 Fax: 204-474-7565 Project Name: Project Location(s): U of M Project Coordinator: Prime Contractor:

More information

Global Waste Technical Services Ltd. Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR. NOISE and VIBRATION MANAGEMENT PLAN

Global Waste Technical Services Ltd. Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR. NOISE and VIBRATION MANAGEMENT PLAN Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR NOISE and VIBRATION MANAGEMENT PLAN Permit No. EPR/XP3598XP Global solutions any waste, anywhere Revision 1.0 May 2013 Global Solutions

More information

General A. General A.1 Activities Not Specifically Provided For A.2 Temporary Activities... 3

General A. General A.1 Activities Not Specifically Provided For A.2 Temporary Activities... 3 Section Contents General... 2 4A. General... 2 4A.1 Activities Not Specifically Provided For... 2 4A.2 Temporary Activities... 3 4A.3 Activities on the Surface of Water... 6 4A.4 Status of Roads... 7 4A.5

More information

Newmarket Level Crossing

Newmarket Level Crossing Newmarket Level Crossing Community Liaison Group 26 th February 2018 Agenda 1. Introductions and housekeeping 2. Programme 3. Construction Staging 5. Communications and Feedback 6. Questions/Discussion

More information

Impacts of Dredging and Reclamation on Noise and Amenity

Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5 Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5.1 Management Goals for Noise and Amenity The management goals for noise and vibration are to: Minimise the noise associated

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

Crudine Ridge Wind Farm

Crudine Ridge Wind Farm Crudine Ridge Wind Farm CCC Presentation December 2017 Page 1 Agenda General Update Pre-construction Update Contracting Road Design Geotechnical study Management Plans Material Sourcing Timeline to construction

More information

Code of Construction Practice Part B: Site Specific Requirements

Code of Construction Practice Part B: Site Specific Requirements Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Cremorne

More information

Trans Mountain Expansion Project Overview

Trans Mountain Expansion Project Overview Trans Mountain Expansion Project Overview 1 Proposed Expansion Project $6.8-billion capital cost Expand capacity to 890,000 bpd Project scope 980 kms new pipe 12 new pump stations 19 new tanks 3 new tanker

More information

West Village, 70 Mississauga Road South, Mississauga. Construction Management Plan Phase I: Demolition & Remediation

West Village, 70 Mississauga Road South, Mississauga. Construction Management Plan Phase I: Demolition & Remediation West Village, 70 Mississauga Road South, Mississauga Construction Management Plan Phase I: Demolition & Remediation FINAL, revision 1 January 26, 2018 Table of Contents 1.0 INTRODUCTION... 2 2.0 HOARDING

More information

Southern Cross Hospitals Ltd Endoscopy Consultants PRESSS Building

Southern Cross Hospitals Ltd Endoscopy Consultants PRESSS Building ENG.HAV.0001.1 Southern Cross Hospitals Ltd Endoscopy Consultants PRESSS Building Gary Haverland BE (Civil)(Hons) Director / Senior Engineer Structex, Christchurch ENG.HAV.0001.2 ENG.HAV.0001.3 ENG.HAV.0001.4

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology

More information

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction www.waterprojectsonline.com Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction by Nathan Crabtree & Daniel

More information

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA) Advantages / Disadvantages of Piling Methods In this Piling Advice Note we will explore the advantages and disadvantages of differing types of piling methods. Continuous Flight Auger (CFA) The pile is

More information

Communication On Progress 2011 of Bouygues Construction

Communication On Progress 2011 of Bouygues Construction Communication On Progress 2011 of Bouygues Construction Sustainable Development Department September 2011 PRINCIPLES OF THE GLOBAL COMPACT Human Rights 1. Businesses should support and respect the protection

More information

Code of Construction Practice Part B: Site Specific Requirements

Code of Construction Practice Part B: Site Specific Requirements Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Deptford

More information

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS APPENDIX A: THE CONSTRUCTION OF A COMPOUND FOR USE BY RAILWAY STAFF AND TRAIN DRIVERS, INCLUDING THE ERECTION OF A TWO STOREY OFFICE AND WELFARE BLOCK WITH ASSOCIATED YARDS, SITE LEVELLING, EXTERNAL LIGHTING,

More information

MANAGEMENT OF DEMOLITION PROJECTS GUIDANCE FOR CLIENTS & ADMINISTRATORS CONSTRUCTION (DESIGN & MANAGEMENT) REGULATIONS 2015

MANAGEMENT OF DEMOLITION PROJECTS GUIDANCE FOR CLIENTS & ADMINISTRATORS CONSTRUCTION (DESIGN & MANAGEMENT) REGULATIONS 2015 The Institute of Demolition Engineers MANAGEMENT OF DEMOLITION PROJECTS GUIDANCE FOR CLIENTS & ADMINISTRATORS CONSTRUCTION (DESIGN & MANAGEMENT) REGULATIONS 2015 This document has been produced to guide

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

UC Press Building 2120 Berkeley Way Berkeley, CA

UC Press Building 2120 Berkeley Way Berkeley, CA CONSTRUCTION NOISE REDUCTION PROGRAM FOR: UC Press Building 2120 Berkeley Way Berkeley, CA RGD Project #: 17-057 PREPARED FOR: Berkeley Way, LLC 1958A University Ave. Berkeley, CA 94704 PREPARED BY: Harold

More information

Complying Development

Complying Development Complying Development Development Control Plan PART 1 - INTRODUCTION PREAMBLE This Development Control Plan (DCP) applies to complying development on lands zoned: For Residential Development: Residential

More information

Second Avenue Subway (SAS) Project. Construction on Second Avenue. Interim Report. Prepared for: MTA Capital Construction.

Second Avenue Subway (SAS) Project. Construction on Second Avenue. Interim Report. Prepared for: MTA Capital Construction. Second Avenue Subway (SAS) Project Air Quality Monitoring Study of the 86 th Street Station Construction on Second Avenue Prepared for: MTA Capital Construction Prepared by: Parsons Brinckerhoff MTA Capital

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

FOURTEENTH SCHEDULE CONDITIONS IMPOSED BY AN BORD PLEANÁLA

FOURTEENTH SCHEDULE CONDITIONS IMPOSED BY AN BORD PLEANÁLA FOURTEENTH SCHEDULE CONDITIONS IMPOSED BY AN BORD PLEANÁLA Modifications to the Railway Order 1. The Railway Order is granted from the Estuary Stop in Swords to St Stephen s Green. The following components

More information

MITIGATION MONITORING PROGRAM

MITIGATION MONITORING PROGRAM MITIGATION MONITORING PROGRAM FOR ASPHALT PLANT NO. 1 REPLACEMENT AND MODERNIZATION W.O. E1907820 Initial Study/ Mitigated Negative Declaration SCH # 2015121036 Prepared By CITY OF LOS ANGELES BUREAU OF

More information

No. 1 SPINNINGFIELDS MANCHESTER

No. 1 SPINNINGFIELDS MANCHESTER No. 1 SPINNINGFIELDS MANCHESTER Client: Project Manager: Description: Allied London Gardiner & Theobald Asbestos Removal Demolition Enabling Works Date: October 2014 to July 2015 Duration: Location: 41

More information

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Out of hours works protocol

Out of hours works protocol Out of hours works protocol March 2017 Document control File name TNR3N_OOH_Work _Protocol_Rev2 Report name Out of hours works protocol Revision number 2 Revision history Revision Date Description Approval

More information

SITA Surrey is building an Eco Park at Charlton Lane, Shepperton on behalf of Surrey County Council

SITA Surrey is building an Eco Park at Charlton Lane, Shepperton on behalf of Surrey County Council Eco Park Surrey Update July 2015 SITA Surrey is building an Eco Park at Charlton Lane, Shepperton on behalf of Surrey County Council Work is getting underway on Surrey County Council s innovative, new

More information

Loading Dock Traffic Management Plan

Loading Dock Traffic Management Plan University of New South Wales Loading Dock Traffic Management Plan Upper Campus Store Shauna Simon 09/11/017 Contents Purpose... 3 General Operations... 3 Upper Campus Store Operating Hours... 3 Access

More information

MITIGATION MONITORING AND REPORTING PROGRAM CHABOT COLLEGE 2012 FACILITIES MASTER PLAN

MITIGATION MONITORING AND REPORTING PROGRAM CHABOT COLLEGE 2012 FACILITIES MASTER PLAN EXHIBIT 2 Prepared for Chabot Las Positas Community College October 29, 2017 Land Use and Environmental Planning 1.0 INTRODUCTION 1.1 Background When adopting a Mitigated Negative Declaration, Public Resources

More information

Introduction. Access arrangements and work schedules

Introduction. Access arrangements and work schedules DublinTown submission in relation to Part VIII planning application 4552/17, the proposed public realm improvement works to Cathedral Street and Sackville Place. Introduction Dublin Town (formerly Dublin

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Planning Application Phase 17 October 2014 for 79-85 Monier Road London E3 2PS Penten Group Ltd 816 Garratt Lane London SW17 0LZ Tel: 020 8772 4040 Description Contents Page

More information

AND STATEMENT OF EVIDENCE OF CHRIS FISHER

AND STATEMENT OF EVIDENCE OF CHRIS FISHER IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER of applications by CYPRESS CAPITAL LIMITED to the TAUPO DISTRICT COUNCIL under section 88 of the Act to authorise construction and use

More information

East Link Extension South Bellevue Completion of Design Open House. November 6, 2014

East Link Extension South Bellevue Completion of Design Open House. November 6, 2014 East Link Extension South Bellevue Completion of Design Open House November 6, 2014 Tonight s agenda 5-7 p.m. Open house Meet the team View design plans 5:30 Presentation Welcome and introductions (Luke

More information

London Good Practice Guide Noise & Vibration Control for Demolition and Construction

London Good Practice Guide Noise & Vibration Control for Demolition and Construction London Good Practice Guide Noise & Vibration Control for Demolition and Construction Table of Content Subject Page Table of Content 1 1 Introduction 2 2 Use of the Good Practice Guide 2 3 Locality / Site

More information

Mogden Sewage Treatment Works: 2011 updates

Mogden Sewage Treatment Works: 2011 updates Mogden Sewage Treatment Works: 2011 updates 20 December 2011 - Mogden Upgrade update Construction work to increase capacity at Mogden Sewage Treatment Works will wind-down for Christmas at 3pm on Friday

More information

2017 INTERNATIONAL WORKBOAT SHOW MOVE-IN/MOVE-OUT SCHEDULE ADDITIONAL MOVE IN PROCEDURES FOR 2017

2017 INTERNATIONAL WORKBOAT SHOW MOVE-IN/MOVE-OUT SCHEDULE ADDITIONAL MOVE IN PROCEDURES FOR 2017 2017 INTERNATIONAL WORKBOAT SHOW MOVE-IN/MOVE-OUT SCHEDULE The 2017 International WorkBoat Show will utilize a target date move-in/move-out schedule to facilitate a smooth, efficient move-in/move-out and

More information

Selecting Activities - Schedule of Daily Activities

Selecting Activities - Schedule of Daily Activities Use the Selecting Activities Worksheet as a means of identifying activities in which to begin using AAC overall, to create or expand daily communication opportunities or to target specific AAC goals. Activities

More information

Eurasia Tunnel Project. Stakeholder Engagement Plan Close-out Report for Detailed Design and Construction Phase

Eurasia Tunnel Project. Stakeholder Engagement Plan Close-out Report for Detailed Design and Construction Phase Avrasya Tüneli İşletme İnşaat ve Yatırım A.Ş. (ATAŞ - the Eurasia Tunnel Operation, Construction and Investment Inc. Co.) Eurasia Tunnel Project Stakeholder Engagement Plan Close-out Report for Detailed

More information

Newsletter July Four Ashes Ltd. Stage 2 Consultation. Introduction

Newsletter July Four Ashes Ltd. Stage 2 Consultation. Introduction Newsletter July 2017 Stage 2 Consultation Introduction The Daventry International Rail Freight Terminal; a modern SRFI Four Ashes Limited (FAL) is proposing to build the West Midlands Interchange, a Strategic

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

Welcome. Welcome to the Wastewater Treatment Project Community Information Meeting.

Welcome. Welcome to the Wastewater Treatment Project Community Information Meeting. Welcome Artist rendering Welcome to the Wastewater Treatment Project Community Information Meeting. Construction is beginning in April 2017 on the McLoughlin Point Wastewater Treatment Plant and undersea

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

<Insert EEB 6 or EEB 7 aerial picture> Community Meeting Meldazy and Hurley Emergency Exit Buildings November 22, 2018

<Insert EEB 6 or EEB 7 aerial picture> Community Meeting Meldazy and Hurley Emergency Exit Buildings November 22, 2018 Community Meeting Meldazy and Hurley Emergency Exit Buildings November 22, 2018 2 Community Meeting Overview Introductions (5 minutes) TTC, City of Toronto and IBI

More information

Centre Buildings Redevelopment Explaining the impact on LSE staff and students

Centre Buildings Redevelopment Explaining the impact on LSE staff and students Explaining the impact on LSE staff and students Creating a new LSE landmark building & public square Improving facilities for staff and students Contents: Background & Programme Construction Traffic and

More information

Draft Code of Construction Practice

Draft Code of Construction Practice Draft Code of Construction Practice This factsheet outlines how it is expected the nominated undertaker will manage the effects of the construction of the Proposed Scheme on communities and the environment

More information

Washington County Landfill Reconstruction Project: Progress Updates

Washington County Landfill Reconstruction Project: Progress Updates Home Site Index Glossary What's New Ask MPCA Visitor Center MPCA Home > Clean Up > Perfluorochemicals > Perfluorochemical (PFC) Waste Sites > Washington County Site Progress Updates Washington County Landfill

More information

City staff responses have been incorporated in the letter in blue bold italic font. February 6, 2017

City staff responses have been incorporated in the letter in blue bold italic font. February 6, 2017 City staff responses have been incorporated in the letter in blue bold italic font. February 6, 2017 February 2, 2017 Dear Mayor Watson, We thank you for agreeing to meet with representatives of the New

More information

Destructive Testing for the following location(s): Daniel Webster Elementary School 465 Missouri Street, San Francisco, CA

Destructive Testing for the following location(s): Daniel Webster Elementary School 465 Missouri Street, San Francisco, CA Facilities Prop A 2011 Bond Program San Francisco Unified School District 135 Van Ness Avenue, Room 207 San Francisco, CA 94102 October 9, 2007 DESCRIPTION OF WORK FOR INFORMAL BID PROPOSAL RE: Destructive

More information

Columbia, Missouri, Manufactured Gas Plant Project Fact Sheet: August 2013

Columbia, Missouri, Manufactured Gas Plant Project Fact Sheet: August 2013 Columbia, Missouri, Manufactured Gas Plant Project Fact Sheet: August 2013 Ameren Missouri is committed to keeping customers informed about planned work at the Ameren Missouri service center property at

More information

New Low-Level Waste Facilities at Dounreay Phase One Vaults Project Summary

New Low-Level Waste Facilities at Dounreay Phase One Vaults Project Summary DSG(2014)C075 New Low-Level Waste Facilities at Dounreay Phase One Vaults Project Summary The Dounreay site requires facilities to dispose of the large volumes of low level waste (LLW) that has been and

More information

Enabling Works Fox Primary School, Kensignton, London. Presentation for Drop-in Session for Fox Primary School Staff & Parents

Enabling Works Fox Primary School, Kensignton, London. Presentation for Drop-in Session for Fox Primary School Staff & Parents Enabling Works Fox Primary School, Kensignton, London Presentation for Drop-in Session for Fox Primary School Staff & Parents Presentation Contents 1. Who s Who 2. Where are the works to be undertaken

More information

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON. REQUEST FOR TENDER - SERVICES 1. PURPOSE AND SCOPE This specification is intended to govern the supply of all labour, materials and equipment for the dismantling, demolition of a single dwelling on the

More information

Outline Construction Management Plan. Redevelopment of Hawkins House Hawkins House, Hawkins St, Dublin 2

Outline Construction Management Plan. Redevelopment of Hawkins House Hawkins House, Hawkins St, Dublin 2 Outline Construction Management Plan Redevelopment of Hawkins House Hawkins House, Hawkins St, Dublin 2 The Commissioners for Public Works in Ireland (OPW), Head Office, Jonathan Swift Street, Trim, Co.

More information

PROPOSED GOOD NEIGHBOUR BYLAW CONSULTATION Spring 2014

PROPOSED GOOD NEIGHBOUR BYLAW CONSULTATION Spring 2014 PROPOSED GOOD NEIGHBOUR BYLAW CONSULTATION Spring 2014 The City of Williams Lake wants to hear what you think about the proposed Good Neighbour Bylaw! E-mail your comments to bylawenforcement@williamslake.ca,

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information