2 CLIENT: MCA NAMIBIA USER CLIENT: NLAS TEAM CONSULTANTS: SE[ARCH] TEAM Nina Maritz Architect: Principal Agent De Leeuw Namibia: QS Buhrmann & Partners: Str-Civil Eng EMCON: Elec-Mech Eng Enviro Dynamics: Environmental Cons.
3 Building Programme - completed 2010 Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Site visits Oshakati Helao Nafidi Oshakati Helao Nafidi Stakeholder meetings Oshakati Helao Nafidi Oshakati Helao Nafidi Oshakati Helao Nafidi Detailed documentation Bill of Quantities Procurement Detailed documentation BoQ Procurement
4 2011 Building Programme - expected Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Procurement Site Handover CONSTRUCTION Procurement Site Handover CONSTRUCTION 2012 Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec CONSTRUCTION CONSTRUCTION
5 Location plan Oshakati
6 Oshakati Site plan Site boundaries Neighbour s access only not for construction Pedestrian access only not for construction Construction access from east side only
7 Oshakati Google
8 CONSTRUCTION SUMMARY Founding conditions: Site previously excavated. Imported fill layer approx 600mm. Raised platform with ground-beams Additional fill to raise floor Site Geology: The buildings are to be founded on the existing soil-raft platform that is ± 800mm thick Foundations: All foundations are generally to be cast on the existing platform, including the blinding. Where and only where specifically approved by the engineer in writing, foundation soffits may protrude up to a maximum of 100mm into the platform. The contractor has to ensure that ponding of water on the Platform will not occur during construction.
9 Oshakati Ground Floor plan
10 Oshakati First Floor plan
11 Section through Archive offices & stores above
12 Bird s eye view of ground floor
13
14 CONSTRUCTION SUMMARY Structure: Ground-beams Load-bearing concrete frame (beams & columns) Partial load-bearing brickwork Infill brickwork Steel roof structure Materials: Steel roof sheeting Steel frame windows Steel frame doors Fired clay bricks Prosopis timber joinery Steel screens & pergola
15 CONSTRUCTION SUMMARY Floor finishes: Tinted steel-float cement floors Paved clay brick floors MARMOLEUM to Kids library floor Timber and tile skirting Wall finishes: Exposed fairface brickwork Plastered & painted int. Timber partitioning limited to a few offices Roof & Ceiling finishes: Painted steel CHROMADECK roof sheeting Off-shutter concrete painted ISOPINE to main areas BROWNBUILT suspended ceilings Only cornices to suspended ceilings
16 CONSTRUCTION SUMMARY Windows & doors: Painted steel Painted steel burglar bars Plastered & painted cills Clay brick cills Timber cills Metalwork: Painted steel Galv. rectagrid Galv. diamond mesh
17 CONSTRUCTION SUMMARY Water & sewerage : Waterborne linked to municipal sewerage Site-works & landscaping: Pedestrian walkway Multi-purpose area Staff parking Public parking Kids courtyard Main courtyard Service yard
18 M&E SUB-CONTRACTS Service Electrical Installation Air-conditioning Installation LAN Installation Audio-visual Installation Electronic Services UPS Installation Solar PV Installation
19 CONSTRUCTION SUMMARY Electrical installation: Connection from existing municipal mini-sub Allows for UPS & Solar PV installations Electronic Services Security System Book detection System CCTV Camera System Access Control System Fire Detection System LAN Installation: Includes PABX System CAT5e system Audio-Visual Installation Integrated Multi-media control systems Lighting control Video Conferencing
20 CONSTRUCTION SUMMARY WET SERVICES Municipal Connection HDPE & upvc for external supply Pex/al/pex pipes for internal supply AIRCON: Evaporative cooling system for the main building Split Aircon s for UPS & Server Rooms FIRE PREVENTION Fire Booster Connection Fire hydrants / Fire hose reels / Fire extinguishers
21 OSHAKATI - 3D RENDERINGS The main entrance court
22 The performance podium and benches in the public avenue
23 looking up from the kids' area into the library main hall
24 View into the kids' area
25 looking back to the Children s and Main Library from the courtyard
26 outside view of the main hall and ramp
27 outside view of the ramp and ablutions
28 Helao Nafidi Google Helao Nafidi
29 Helao Nafidi Site plan site plan
30 CONSTRUCTION SUMMARY Founding conditions: Greenfield site no previous fill Site geology: There are no rock outcrops at the site and in the surrounding area. The site is underlain by red to orange to dark brown sands of the kalahari group. These sands generally extend to below 3,2m below surface level Foundations: The buildings are to be founded on a soil raft of +-Im deep. Foundation excavations to be kept dry at all times. Contractor has to ensure that ponding of water in the trenches will not occur during construction.
31 Helao Nafidi Ground Floor plan Ground floor plan
32 Helao Nafidi First Floor plan First floor plan
33 ground floor With the ablutions at the bottom and kids library to the top
34 first floor With the computer centre at the bottom and the main library to the top
35 CONSTRUCTION SUMMARY Structure: Ground-beams Load-bearing concrete frame (beams & columns) Partial load-bearing brickwork Infill brickwork Steel roof structure Materials: Steel roof sheeting Steel frame windows Steel frame doors Fired clay bricks Prosopis timber joinery Steel screens & pergola
36 CONSTRUCTION SUMMARY Floor finishes: Tinted steel-float cement floors Paved clay brick floors MARMOLEUM to Kids library floor Timber and tile skirting Wall finishes: Exposed fairface brickwork Plastered & painted int. Timber partitioning limited to a few offices Roof & Ceiling finishes: Painted steel CHROMADECK roof sheeting Off-shutter concrete painted ISOPINE to main areas BROWNBUILT suspended ceilings Only cornices to suspended ceilings
37 CONSTRUCTION SUMMARY Windows & doors: Painted steel Painted steel burglar bars Plastered & painted cills Clay brick cills Timber cills Metalwork: Painted steel Galv. rectagrid Galv. diamond mesh
38 CONSTRUCTION SUMMARY Water & sewerage : Waterborne linked to municipal sewerage Site-works & landscaping: Pedestrian walkway Multi-purpose area Amphitheatre Staff parking Public parking Kids courtyard Main courtyard Service yard
39 M&E SUB-CONTRACTS Service Electrical Installation Air-conditioning Installation LAN Installation Audio-visual Installation Electronic Services UPS Installation Solar PV Installation
40 CONSTRUCTION SUMMARY Electrical installation: 11kV connection from Nored Includes MV & LV components Allows for UPS & Solar PV installations Electronic Services Security System Book detection System CCTV Camera System Access Control System Fire Detection System LAN Installation: Includes PABX System CAT5e system Audio-Visual Installation Integrated Multi-media control systems Lighting control Video Conferencing
41 CONSTRUCTION SUMMARY WET SERVICES Municipal Connection HDPE & upvc for external supply Pex/al/pex pipes for internal supply AIRCON: Evaporative cooling system for the main building Split Aircon s for UPS & Server Rooms FIRE PREVENTION Fire Booster Connection Fire hydrants / Fire hose reels / Fire extinguishers
42 HELAO NAFIDI - 3D RENDERINGS main entrance with hall to the left
43 View up to the mezzanine from the main circulation desk
44 main entrance
45 Outside view of the ramp with offices to the right
46 Workroom at the bottom and study halls above
47 Main hall in the centre
48 Hall to the right and main hall and kids 'area to the left
49 ENVIRONMENTAL, HEALTH & SAFETY REQUIREMENTS Local laws & MCA Policies oblige contractors to implement & maintain sound environmental, health & safety standards on site. These requirements are set out in the EMP (Environmental Management Plan), PHSAP (Public Health & Safety Awareness Plan) that includes: the HAAP (HIV/AIDS Awareness Plan).
50 ENVIRONMENTAL, HEALTH & SAFETY REQUIREMENTS 1. These documents & the actions required in them form an integral part of the contract. 2. All tenderers must familiarise themselves with the contents & include the cost for the this in their bids. Lack of budget to adhere to these standards will not be entertained as an excuse & it may be seen as breach of contract. Note the applicable penalties relating to noncompliance.
51 QUESTIONS & ANSWERS
52 THANK YOU & GOOD LUCK
Gobabis Regional Study & Resource Centre Pre-bid meeting
Gobabis Regional Study & Resource Centre Pre-bid meeting RSRC GOBABIS: Location site Sports complex RSRC GOBABIS: Site Plan RSRC GOBABIS: Site Plan FUTURE STREET ALL VEGETATION TO REMAIN AS FAR AS POSSIBLE
More informationSIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT
SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT NEW FACILITY FOR ADULT BASIC EDUCATION AND VOCATIONAL TRAINING By Leigh Hartl Student Number: 207514952 A Report Submitted in Partial Fulfilment of the Requirements
More informationSPECIFICATION OUTLINE. 28 November 2017 REV 2
P a g e 1 ORIGIN PARK, RICHMOND PARK, MILNERTION N7 CAPE TOWN 28 November 2017 REV 2 1. EXTERIOR 1.1 MAIN BUILDING - Main Building design to warehousing building type class J2 as per SANS 10400. Goods
More information9.0 TECHNICAL ANALYSIS
9.0 TECHNICAL ANALYSIS There is a long established tradition of a brick aesthetic in Pretoria, which began with the influence of Dutch architects who arrived in Pretoria in the late 1800 s. Since then
More informationCONSTRUCTION SMARTSCREEN
6704 Level 1 Construction Trade Occupations - 325 + VAT (SS6704-LV1 ) Unit 102 - Construction Trade Occupations - Painting and Decorating Unit 103 - Construction Trade Occupations - Plastering Unit 104
More informationCONSTRUCTION OF STATE VETERINARY OFFICE
CONSTRUCTION OF STATE VETERINARY OFFICE BRIEF PROJECT DESCRIPTION Construction of a new Sate Veterinary Office in the following town: Lot no 4: Epukiro (Including 3 houses) SITE LOCATION FOR EPUKIRO SITE
More informationNOTICE TO BIDDERS. TO: All Bidders FROM: Alvin Kumar DATE: 20 th July 2017 DESIGNATION: Deputy Manager Project
NOTICE TO BIDDERS TO: All Bidders FROM: Alvin Kumar : 20 th July 2017 DESIGNATION: Deputy Manager Project Proposed New Changing Room and Waoom Facility at Nasinu Campus LOCATION: LOCATION: FNU Nasinu Campus
More informationESTIMATE FOR BUILDING WORKS BARONS COURT ROAD
ESTIMATE FOR BUILDING WORKS BARONS COURT ROAD 26TH JANUARY 2017 Project: Barons Court Date: 26/01/2017 QUALIFICATIONS, ASSUMPTIONS & EXCLUSIONS: 1 Qualifications:- 1.1 Prices exclude 20% VAT 1.2 Pre-start
More informationSPECIFICATIONS GENERAL. PAINT EXTERNAL House of Paints White WALL AND WALL FINISHING WINDOW AND DOOR SCHEDULE. INTERNAL White
SPECIFICATIONS GENERAL All building work carried out will comply with the obligations to housing consumers and the NHBRC under the terms of the Housing Consumers protection Measures Act 1998 Cement maxi
More informationPreliminary Inspection Plan Certification On Site Inspection. Ancillary Design... Ancillary Construction Inspecti... Testing Requirement
1 Commencement Setting Out Ground Location of existing below ground service Ground Location of site gas CSD Ground Location of site water mains CSD Ground Location of below ground drainage FFA Ground Location
More informationPreliminary Inspection Plan Certification On Site Inspection. Ancillary Design... Ancillary Construction Inspecti... Testing Requirement
1 Commencement Setting Out Ground Location of existing below ground service Ground Location of site gas CSD Ground Location of site water mains CSD Ground Location of below ground drainage FFA Ground Location
More informationKGN-BDD TENDER FOR SUPPLY OF LABORATORY EQUIPMENT AND PROVISION OF CIVIL WORKS FOR THE OLKARIA CIVIL ENGINEERING LABORATORY.
KENYA ELECTRICITY GENERATING COMPANY LIMITED KGN-BDD-07-2017 TENDER FOR SUPPLY OF LABORATORY EQUIPMENT AND PROVISION OF CIVIL WORKS FOR THE OLKARIA CIVIL ENGINEERING LABORATORY. 11 th May 2017 In accordance
More informationCentral Power Research Institute Prof Sir C V Raman Road, Sadashivnagar Post Office Post Box No: 8066, Bangalore
Name of the SH Construction of boundary wall for CPRI office campus and staff colony at Bangalore Cost Rs.1,55,48,700.00 UP-TO-DATE Stone masonry wall work from T&D Gate to DG s residence has been Stone
More informationCONSTRUCTION OF 5 STATE VETERINARY OFFICES
CONSTRUCTION OF 5 STATE VETERINARY OFFICES BRIEF PROJECT DESCRIPTION Construction of 5 new Sate Veterinary Offices in the following towns: Lot no 1: Outapi Lot no 2: Eenhana & Omuthiya (Including 3 houses)
More informationBuildings Construction Procurement Strategy
Buildings Construction Procurement Strategy Update March 2012 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_24Y2K9 Agenda 1. Overview of the
More informationBILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION.
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT BILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION. Clearing of site, site office/work shed, Toilet, etc. A provisional cost to be allocated in South African Rands.
More informationSAVANNAH HILLS. DOUBLE STOREY SPECIFICATIONS - TYPE D (N) 186m² & D (S) 191m²
SAVANNAH HILLS Updated 14/11/2016 DOUBLE STOREY SPECIFICATIONS - TYPE D (N) 186m² & D (S) 191m² 1. Preliminary and General Engineers certificates for all slabs N H B R C Registration Geological engineer
More informationPROGRESS JAIPUR PH-II AS ON 30 NOV 18
S MILESTONE DESCRIPTION STATUS No 1. MS 01 (D+120 Days) (a) Work commence for all Towers (b) Slab casting for 20 DU (c) Brick work for 25 DU (d) Internal electrical 15 DU (e) Internal Plumbing & Sewage
More informationCOST - EFFECTIVE DESIGN FOR AIR-CONDITIONED OFFICE SPACE : TRANSPORT CORPORATION OF INDIA LTD. ASHOK B. LALL ARCHITECTS, NEW DELHI
COST - EFFECTIVE DESIGN FOR AIR-CONDITIONED OFFICE SPACE : TRANSPORT CORPORATION OF INDIA LTD. ASHOK B. LALL ARCHITECTS, NEW DELHI TCI HOUSE is a modern office building with a high level of environmental
More informationDullstroom Ridge Architectural Guidelines
Dullstroom Ridge Architectural Guidelines Portions 1 to 27 of Erf 599 Dullstroom 1. Description of Theme and Architecture The design of Dullstroom Ridge is based on an Old English theme often seen in the
More informationConstruction Technology Revision Guide
Construction Technology Revision Guide Sub structures and Super structures Super structure (Wall, floors roof) Sub structure (Foundations) 2 Thermal Insulation Thermal insulation helps to prevent heat
More informationTERRACE FACTORY - TYPE A1
TERRACE FACTORY - TYPE A1 Total Built-up Size: 3,401 sq ft No. of Units: 24 TERRACE FACTORY - TYPE A1 Total Built-up Size: 3,401 sq ft No. of Units: 24 SPECIFICATION FACTORY HEIGHT Approximately 6.6 meters
More informationPROPOSED OFFICE BLOCK FOR THE COUNTY ASSEMBLY OF KILIFI - PLOT No MALINDI. Item Description Unit Quantity Rate Amount
EXTERNAL WORKS DEMOLITION AND ALTERATIONS EXTERNALLY Pulling down to ground level; removing debris from Site a 200 mm thick masonry wall finished both sides with plaster and paint; net total area 158 square
More informationPROGRESS JAIPUR PH-II AS ON 20 DEC 18
S No 1. MILESTONE DESCRIPTION STATUS MS 01 (D+120 Days) 2. MS 02 (D+210 Days) (a) Work commence for all Towers (b) Slab casting for 20 DU (c) Brick work for 25 DU (d) Internal electrical 15 DU (e) Internal
More informationSOUTH ELEVATION OF CLASSROOMS. NORTH ELEVATION OF CLASSROOMS (section through hall) HaysomWardMiller Architects CLASS ELEVATIONS
SOUTH ELEVATION OF CLASSROOMS NORTH ELEVATION OF CLASSROOMS (section through hall) CLASS ELEVATIONS 7 Downing Place, Cambridge, CB2 3EL, UK T: 01223 578545 F: 01223 351955 E: info@haysomwardmiller.co.uk
More informationArchitectural Design Guidelines. Zandwyk Industrial Park
Architectural Design Guidelines Zandwyk Industrial Park 1. INTRODUCTION It is the intention of this document to act as an aesthetic guideline to all Property owners in the design and development of their
More informationFOREST PLACE 59 UNITS ERF 5586 PARKLANDS
ANNEXURE "C" MATERIAL AND FINISHES SPECIFICATION FOREST PLACE 59 UNITS ERF 5586 PARKLANDS 1. FOUNDATIONS AND STRUCTURE Foundation walls are to be built in strict accordance with the municipal building
More informationLemm Elementary. Restoring the Heart of the Community. Klein Independent School District
Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main
More informationCOPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31
Contents Preface to the Sixth Edition xi 1 Making Buildings 3 Learning to Build 4 Buildings and the Environment 5 The Work of the Design Professional 11 The Work of the Construction Professional 19 Trends
More information1 BILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION.
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT 1 BILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION. Clearing of site, site office/work shed, Toilet, etc. A provisional cost to be allocated in South African
More informationPremier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017
Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins
More informationINSPECT DIRECT Pty Ltd
Web Page: www.inspectdirect.com.au INSPECT DIRECT Pty Ltd Property Address: Sample.Dilapidation.Report Victoria Building Status / Dilapidation Report This is not a Pest Inspection The Building Status /
More informationManx Accredited Construction Contractors Scheme 2018/19
Manx Accredited Construction Contractors Scheme 2018/19 Appendix 3 - Categories of Contractor The Manx Accredited Contractors Scheme is administered by the IOM Construction Federation and application may
More informationBill of Quantities Project: Tenant Installations Address: Suncadia, First Floor, Pretoria SAHRA/FAC/01/05/2018
T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 Bill of Quantities Project:
More informationTHE TREASURE TOWER PROGRESS REPORT
THE TREASURE TOWER PROGRESS REPORT About the Project: Project Developer Title of Project Project Reference Design & Supervision Consultant Interior Design Consultant Main Contractor Bin Faqeeh Real Estate
More informationPROPOSED ERECTION AND COMPLETION OF CEREAL STORE.
PROPOSED ERECTION AND COMPLETION OF. AB/1 STORE ELEMENT NO. 1 A B SUBSTRUCTURES (ALL PROVISIONAL) Excavations Clear site of small bushes and grub roots of small trees and cart away Excavate average 150mm
More informationArchitectural Design Guidelines
ANNEXURE A Architectural Design Guidelines Zandwyk Industrial Park 1. INTRODUCTION It is the intention of this document to act as an aesthetic guideline to all Property owners in the design and development
More informationGuidelines. Checklist for Building Approval. 1. The Site
Guidelines Checklist for Building Approval Note: This checklist serves as a guide as to the information that the Aesthetics Committee requires and will assist the applicant and the Aesthetics Committee
More informationPROGRESS JAIPUR PH-II AS ON 20 JULY 2018
1. Mobilisation of manpower and material is progressively improving at site. The present labour strength is 345 and will progressively increased to 400 plus by end Jul 18. 2. Progress of Work:- The following
More informationANNEXURE B SECTION 1
ANNEXURE B SECTION 1 HOUSING SPECIFICATIONS 1. Houses 1.1. Roofs Material: Architect approved concrete tiles @ 17,5 degree pitch on SABS approved underlay Colour: As per Architects. 1.2. Rainwater goods
More informationClarification of ITB Amendment No. 1 Pre-Bid meeting Minutes. Excavation and leveling of the Jericho Agro Industrial Park
Clarification of ITB Amendment No. 1 Pre-Bid meeting Minutes Excavation and leveling of the Jericho Agro Industrial Park Date & Time Location Contractors 04 October 2010 @ 11:30hrs Jericho Municipality
More informationKANPUR SMART CITY LIMITED
Nagar Nigam Mukhyalay, 3 rd Floor, Moti Jheel, Kanpur - 208002 Tel.: +91 512 2541258, 2546194 Email:ksclkanpur@gmail.com KANPUR SMART CTY LMTED No.: KSCL/PMC/Open Gym/01/2 Date: 17/02/2018 Reply to queries
More informationICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT
ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : Anbar Ramadi Raja School GO code : IRAKGENASSENG0 TITLE : Raja / School / Rehabilitation SO n : SO 01 WPA n : BAG 17
More informationOwner Builder Inspection Report
www.sherspec.com Owner Builder Inspection Report PREPARED FOR USE IN ASSESSING A PROPOSAL FOR WARRANTY INSURANCE TO BE ISSUED UNDER SECTION 137B (2)(a) OF THE BUILDING ACT 1993 INSPECTION DETAILS Registered
More informationUnit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M.
Bill of Quantities Nature of work : Construction of Health Center with 8 rooms (Clinics, Pharmacy, Labs, Fence & Latrines) Location: Shakreen- El Fasher Town- North Darfur State No. Description Qty Unit
More informationREHABILITATION OF DRIVEWAY AND GROUND FLOOR OF THE SECOND BUILDING AT MIDDLE STREET OFFICE
BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer
More informationCOUNTY GOVERNMENT OF SIAYA: PROPOSED ECD BLOCK
PROPOSED ECD BLOCK ELEMENT NO. 1 SUBSTRUCTURES (ALL PROVISIONAL) A B C D Site clearance Clear the site off grass, shrubs and all vegetation; cart away as directed Excavate vegetable soil average 200mm
More informationINTERNATIONAL BUSINESS CENTRE. General Specifications for Common and Private Offices areas
INTERNATIONAL BUSINS CENTRE General Specifications for Common and Private Offices areas KANIKA INTERNATIONAL BUSINS CENTRE GENERAL SPECIFICATIONS FOR COMMON AREAS 1. BUILDING STRUCTURE Concrete Structure:
More informationSchedule T5. Tender Documents. This tender is for: Tender Documents: The documents issued for this tender include the following: Tender Schedules
Schedule T Tender Documents T This tender is for: Contract: Location: Tender Documents: Norrie Home 56 Hardinge Road The documents issued for this tender include the following: Tender Schedules Schedule
More informationGood Construction Practices Part I
Good Construction Practices Part I This report is solely for the internal use. No part of it may be circulated, quoted, or reproduced for distribution outside the company organization without prior written
More informationDescription Unit Quantity Rate Kshs. Amount Kshs.
BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove
More informationGRAAD 12 NATIONAL SENIOR CERTIFICATE GRADE 12
GRAAD 12 NATIONAL SENIOR CERTIFICATE GRADE 12 CIVIL TECHNOLOGY NOVEMBER 2011 MARKS: 200 TIME: 3 hours This question paper consists of 16 pages, 5 answer sheets and a formula sheet. Civil Technology 2 DBE/November
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT STRUCTURAL FOR CUSTOMS HOUSE JULY 2014 i P a g e Table of Contents 1. INTRODUCTION 3 1.1 Design Criteria and Specifications..
More informationHow to fill in your Timber Frame Order Form
How to fill in your Timber Frame Order Form 1 General Would you like us to check slab or design the building to Architects drawings? Check Slab: Is the Slab in place already, if so has your architect checked
More informationLORD'S VIEW INDUSTRIAL PARK
P a g e 1 LORD'S VIEW INDUSTRIAL PARK APPLICATION: - BUILDING PLANS CHECKLIST APPROVAL PROCESS Contents 1 Property Information...Page 2 2 Owner/Title Holder...Page 2 3 Designer... Page 2 4 Scrutiny Fees...
More informationTechnical Assignment #1 VA State Capitol Thesis
Eric Fritz Construction Management Dr. Messner VA State Capitol Extension and Renovation Richmond, VA October 4, 2004 Technical Assignment #1 Technical Assignment #1 VA State Capitol Thesis By Eric Fritz
More informationDRAWING SCRUTINY. Type I : October of 8
DRAWING SCRUTINY ERF NO.: TYPE.: I DATE OF SCRUTINY: ARCHITECT: CLIENT: NOTE: 1. The notes/corrections or changes made to these drawings together with this Scrutiny List have to be thoroughly discussed
More informationCONSULTATION ON THE SCOPE OF WORKS AND CONTRACTING STRATEGY FOR THE RENOVATION OF THE PALAIS DES NATIONS
CONSULTATION ON THE SCOPE OF WORKS AND CONTRACTING STRATEGY FOR THE RENOVATION OF THE PALAIS DES NATIONS Presented by: UNOG/PTS and UNOG/SHP Date: June 2017 INTRODUCTION David Mc Cuaig Project Director,
More informationICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT
ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : Salah al Din Shirqat Markiz Shirqat GO code : IRAK DPL ASSENG0 TITLE : Mosul Response (2017) Shirqat Unified / WTP /
More informationhandrail and glazing channel. PPC finished. Silver Grey. RAL mm AFFL
Continuous horizontal aluminium handrail and glazing channel. PPC finished. Silver Grey. RAL 1035 1100mm AFFL Glass balustrade clear, with painted metal structure. Silver Grey PPC finished to match handrail
More informationPyrite Testing and Methodology for Remediation Works Key Aspects of I.S. 398 (Parts 1 and 2) Verification and Preparation for Remedial Works
Pyrite Testing and Methodology for Remediation Works Key Aspects of I.S. 398 (Parts 1 and 2) Verification and Preparation for Remedial Works Jim Mansfield November 2013 Verification and Preparation for
More informationPROPOSED OFFICE BLOCK FOR THE COUNTY ASSEMBLY OF KILIFI - PLOT No MALINDI
GROUND FLOOR COMPLETION OF WORKS TO GROUND FLOOR SITE WORKS DEMOLITIONS AND ALTERATIONS Ground floor Removing a polythene damp proof membranes, complete with mesh fabric reference A 252, hacking edges
More informationBRAND NEW DEVELOPMENT
T HE CH E S TE R F I E L D BRAND NEW DEVELOPMENT THE NOVA GROUP P R O P E R T Y D E V E LO P M E N T & CO N S T R U C T I O N SEA POINT 021 434 1223 CONTENTS PAGE 1: PAGE 2: PAGE 2: PAGE 3-5: COMPANY PARTICULARS
More information-SQA-SCOTTISH QUALIFICATIONS AUTHORITY. Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR
-SQA-SCOTTISH QUALIFICATIONS AUTHORITY Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR -Module Number- 0085137 -Session-1988-89 -Superclass- TE -Title- BUILDING TECHNOLOGY
More information*X227/12/01* X227/12/01 BUILDING CONSTRUCTION HIGHER NATIONAL QUALIFICATIONS 2014 FRIDAY, 6 JUNE 9.00 AM AM
X227/12/01 NATIONAL QUALIFICATIONS 201 FRIDAY, 6 JUNE 9.00 AM 11.00 AM BUILDING CONSTRUCTION HIGHER 100 marks are allocated to this paper. Attempt all questions in Section A (0 marks). Attempt any two
More informationLOT QTY DESCRIPTION NOTE FRONT OFFICE. 2 CREDENZA. NATURAL & STORM LAMINATE, 2 x SLIDING DOORS, 1800 x 450 x 700mm
FRONT OFFICE 1 2 x RECEPTION CHAIRS, GREY FABRIC & COFFEE TABLE, LAMINEX TOP, STEEL FRAME, 600 x 600mm 2 CREDENZA. NATURAL & STORM LAMINATE, 2 x SLIDING DOORS, 1800 x 450 x 700mm 3 FILING CABINET, 4 DRAWER,
More informationBuilding Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation
Development Process Learning Objective Understand the development process describe the roles and function of the construction team explain the communication means and essential documents for the development
More informationWASSCE / WAEC BUILDING CONSTRUCTION SYLLABUS
WASSCE / WAEC BUILDING CONSTRUCTION SYLLABUS WWW.LARNEDU.COM Visit www.larnedu.com for WASSCE / WAEC syllabus on different subjects and more great stuff to help you ace the WASSCE in flying colours. STRUCTURE
More informationCompiled by: Civil Works Department, SSA Punjab.
45 Compiled by: Civil Works Department, SSA Punjab. TIPS FOR CIVIL CONSTRUCTION WORKS 1. ISI marked 43 Grade cement of major manufacture must be used. 2. ISI mark Steel must be used. 3. Clean & Fine Sand
More informationAppendix C. Construction Programme
Appendix C Construction Programme Activity ID Activity Name Orig Dur Planned Start Planned Finish Revision 2 827d 14-Oct-13 31-Jul-16 0d Preliminaries 827d 14-Oct-13 31-Jul-16 0d Total Float Contract Key
More informationNATASA COURT, Kyriacou Matsi Av. & Kykkou Str., Ayios Dometios, Nicosia
EKATERINI COURT 48 Kyriacou Matsi Avenue Ριγένης 63Β 2409 Egomi, Nicosia,Cyprus 1010 Λευκωσία NATASA COURT, Kyriacou Matsi Av. & Kykkou Str., Ayios Dometios, Nicosia FOUNDATIONS & CONCRETE STRUCTURE Reinforced
More informationGRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY
Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours *CVLTDM* This question paper consists of 13 pages, including 3 answer
More informationCost Monitoring & EoT
Cost Monitoring & EoT MONITOR YOUR PROGRESS TRACKING CURVES Planned vs Actual How your project performance is monitored by the Engineer Earned Value Analysis (EVA) evaluates project s cost performance
More informationExample Schedule of Condition Report
1 INTERIOR Ground Garage Ceiling Timber members. Members appear to be in a fair and reasonable condition with no signs of any penetration marks noted. Walls Flank wall Brickwork. Part solid construction,
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationDuplicate Instructed Pending Resolved Unknown. Unresolved. Category Date AI REF Job No Project Zone Draft Instruction Explanatory Notes Status
18.01 V18 HG 18.02 V18 HG Room G01 - Joinery: Fabricate and install a painted softwood boxing to house various services panels etc adjacent to the reception desk, as set out in the M&E Engineers information.
More informationStephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018
Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations
More informationPrice List - All Qualifications
Price List - All Qualifications Qualifications Prices in VAT not included 601/1996/2 ProQual Level 1 Award in Health and Safety in a Construction Environment (QCF) 150 601/1858/1 ProQual Level 1 Certificate
More informationRondavels of Botswana
Rondavels of Botswana 1 Rondavels are often made from materials that are locally available. The walls might be made with rocks, cement blocks, or bricks held together with mud or sand mortar. The walls
More informationEKATERINI COURT I 48 Kyriacou Matsi Avenue 2409 Egomi, Nicosia,Cyprus. EKATERINI COURT IV, Kantaras Avenue, Strovolos, Nicosia
EKATERINI COURT I 48 Kyriacou Matsi Avenue 2409 Egomi, Nicosia,Cyprus EKATERINI COURT IV, Kantaras Avenue, Strovolos, Nicosia FOUNDATIONS & CONCRETE STRUCTURE Reinforced concrete based on an anti-seismic
More informationget THE BRIGHTON VIBE. SUMMARY Specification.
get THE BRIGHTON VIBE. SUMMARY Specification. SUMMARY SPECIFICATION THE BRINELL BUILDING Occupancy General Occupancy: 1:8 sq m Means of escape: 1:6 sq m Internal climate: 1:8 sq m Lift provision: 1 person
More informationPRELIMINARY INSPECTION FRAMEWORK
PRELIMINARY INSPECTION FRAMEWORK 1. Oversite Striping of topsoil Forming site entrance Clearing off topsoil for service roadway Roadside drainage continued under entrance bay Any mature trees in vicinity
More informationPROPOSED CONSTRUCTION OF TWIN ECD CLASSROOM AND THREE DOOR PIT LATRINE BILLS OF QUANTITIES PROPOSED TWIN ECD CLASSROOM FINANCIAL YEAR
PROPOSED CONSTRUCTION OF TWIN ECD CLASSROOM AND THREE DOOR PIT LATRINE EMC/EDU/1 ELEMENT 01: SUBSTRUCTURES (All Provisional) A Oversite Excavations Excavate oversite to remove vegetable soil 150mm thick
More informationPRASA HEAD OFFICE NEW GYMNASIUM
Provide skirting as specified. Tel: +27 (0)11 042 7760 Cell: +27 (0)72 616 4315 email: info@archimara.co.za website: www.archimara.co.za PRASA HEAD OFFICE NEW GYMNASIUM PROJECT REF: IMR-52-14 SITE INSPECTION
More information43. CONSERVATORY. Conservatory. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle
Classification: Cluster: Location: Total Area: No. of Stories Acreage Owned: Acquired: 1904 Most Recent Improvements: THE CONSERVATORY Conservatory Close to junction of Inselrhue and Loiter Way, Belle
More informationProviding and laying hammer dressed flat stone paving in cement mortar 1:6 on prepared bedding (excluding the cost of bedding). 40mm 22.
1 CG0001 Clearing grass including removal of rubbish within 50m of site 91.00 m² 2 EW0001 Surface dressing of ground, including removal of vegetation and inequalities < 150mm deep, disposal of rubbish
More informationTITLE: ABLUTION BLOCK WITH BIODIGESTER. ITEM No. D E S C R I P T I O N UNIT QTY
SUBSTRUCTURES 01 SITE CLEARANCE A Clear site of all shrubs, thicket & undergrowth including m² 170 grubbing up of roots and dispose off as directed by the Engineer. (provisional) B Removal of trees and
More informationPROGRESS MEERUT PROJECT AS ON 18 JAN 18
1. The balance work has been awarded to M/s Umaxe Projects Pvt Ltd on 30 Nov 2017. 2. Work has commenced by the contactor on 10 Dec 2017 as per the agreement. 3. The contractor has mobilized the men and
More informationTHE BEST INCLUSIONS ALTI 202
THE BEST INCLUSIONS ALTI 202 WHITE LABEL RANGE WHITE LABEL INCLUSIONS PRELIMINARY WORKS Site Survey, soil test, site inspections as required Building Permit application including applicable fee Full set
More informationPART A: JOB PROCDRE FOR PLASTERING
PART A: JOB PROCDRE FOR PLASTERING 1. SCOPE: The scope of this procedure shall apply to all cement plaster finishes to column, ceilings, walls and similar surfaces on backgrounds met with such as brick,
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationCEDAR PLACE. GrassyPark. Live the dream...
CEDAR PLACE GrassyPark Live the dream... CEDAR PLACE GrassyPark dream... Distinctive location on 5th Ave and conveniently located within close proximity of retail centres, schools, medical centres and
More informationLOT 25 Blueleaf Place. Brookfield $511,879 SUMMARY
RENDERS ARE INDICATION ONLY Home size 27sq Land Size 512m2 LOT 25 Blueleaf Place Brookfield 5 2 2 $511,879 SUMMARY Land Price: $219,000 House Price: $292,879 (Fixed Price) Land Size: 512m2 House Size:
More informationTHE CORPORATION OF THE CITY OF OWEN SOUND
THE CORPORATION OF THE CITY OF OWEN SOUND PROGRAMME AND CONCEPTUAL DESIGNS FOR A RENOVATION TO THE EXISTING OWEN SOUND CITY HALL IN OWEN SOUND, ONTARIO MAY 2, 2016 KONGATS ARCHITECTS CITY HALL DOWNTOWN
More informationBUILDING CONSTRUCTION
EXAMINATION SCHEME BUILDING CONSTRUCTION There will be three papers, Papers 1, 2 and 3 all of which must be taken. Papers 1 and 2 shall be a composite paper to be taken at one sitting. PAPER 1: PAPER 2:
More informationARCHITECTURAL DRAWINGS
PROJECT DETAILS Implementation Partner: Project title: Grant No.: KIS062 Content : ARCHITECTURAL DRAWINGS SHEET NO. REHABILITATION OF GRANT NO.: - KIS062 COVER SHEET INDEX SHEET CONTENTS 01 02 03 04 05
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 21, 2008 SUBJECT: ISLINGTON STATION IMPROVEMENTS PROJECT - FINISHES ACTION ITEM: X INFORMATION ITEM: RECOMMENDATION It
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationSPECIFICATION AND FINISHING SCHEDULE
SPECIFICATION AND FINISHING SCHEDULE 1. PURPOSE OF SPECIFICATION AND FINISHING SCHEDULE... 2 2. SPECIFICATION PRELIMINARIES... 2 3. SPECIFICATIONS... 3 3.1. Siteworks And Excavations... 3 3.2. Availability