Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Size: px
Start display at page:

Download "Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District"

Transcription

1 Lemm Elementary Restoring the Heart of the Community

2 Target Date: August 2018

3 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main entry vestibule natural stone is almost done Multi-purpose room deck and structure will be painted Resinous flooring being installed in all main student restrooms and wash stations Wall finishes being finalized in Area B Area B wainscot has been completed All restroom tile work has been completed A/C has been turned on in Area C Ceiling tiles have been installed in Area C Glass sectional doors have started to be installed in Area A Air is turned on in Area B Operable glass wall has been installed in the covered play collaboration area Carpet has started to be installed in Area C Casework installation has commenced in Area C Door frames are being painted

4 June Work Examples

5

6

7

8

9

10

11

12 May Work Update - Project is on schedule Exterior sheathing has commenced at new addition Concrete saw cutting has commenced for sanitary line replacement New exterior brick installation to start at covered play area Exterior building envelope remediation work is ongoing at designated areas Interior wall framing is ongoing at Area A New windows are being sealed Interior door frames have been installed at Area A Area B wall finishes have commenced Area C tile installation is ongoing Gymnasium floor preparation has started Exterior Wall Mock-up First wall paint coat has started at Area C Window frame installations have started at Area C Solatube roof curbs have been installed

13 May Work Examples

14 Lemm Construction Photographs (May Work)

15 Lemm Construction Photographs (May Work)

16 Lemm Construction Photographs (May Work)

17 Lemm Construction Photographs (May Work)

18 Lemm Construction Photographs (May Work)

19 Lemm Construction Photographs (May Work)

20 Lemm Construction Photographs (May Work)

21 Lemm Construction Photographs (May Work)

22 April Work Update - Project is on schedule Stage Wave work Area A grade beam preparation Area A concrete pad has been poured Steel erection started Exterior punch openings complete and prepped for new windows Area C ready for inspection Area B metal framing and masonry ready for inspection & interior door frames installed Operable partition track installed at cover play area & music room Area B & C ceiling framing commenced Furrdowns at collaboration spaces commenced Area C tile installation begin this week

23 April Work Examples

24 Lemm Construction Photographs (April Work)

25 Lemm Construction Photographs (April Work)

26 Lemm Construction Photographs (April Work)

27 Lemm Construction Photographs (April Work)

28 Lemm Construction Photographs (April Work)

29 Lemm Construction Photographs (April Work)

30 March Work Examples

31 Lemm Construction Photographs (March Work)

32 Lemm Construction Photographs (March Work)

33 Lemm Construction Photographs (March Work)

34 Roofing (March Work)

35 Lemm s Legacy Lemm is committed to high-quality and innovative teaching and learning. We focus on the success of every child! Although Hurricane Harvey affected us in many ways, Lemm will be restored with educational space for our current students and those that will continue the Lemm tradition of greatness for years to come.

36 Lemm Aerial View

37 Covered Entry & Walkways Lemm Front Entry

38 Natural Light via Windows Lemm Next Generation Classroom

39 Natural Light via Solar Tubes Lemm Collaboration Space Shared Flex Space

40 Classroom Doors Garage-Type Doors Glass walls Flexible Spaces Lemm Bird s Eye View of a Classroom Module

41 Acoustical Tiles Stage Lemm Cafeteria & Stage

42 Green Room Makerspaces Learning Commons Library Flexible Seating Lego Wall & Dry Erase Wall

43 Timeline Key Emergency Services Roofing Procurement Klein ISD Lemm Roof Setback Educational Architect Programming Development Construction Punch List FEMA

44 8/29-9/28 8/31 & 9/1 9/1 9/18 9/19 & 21, 28 Emergency Services Roofing Project Emergency Planning Procurement Process Step One Document Collection/Inventory Discussion regarding bond, insurance, FEMA, etc. regarding the Lemm restoration Board approved project initiation for Lemm restoration project with PBK Architects using CSP method 1) As-built documents compiled by KISD for the PBK architect team; 2) Lemm inventory review and planning meeting with KISD purchasing department; 3) Lemm Post-Debris Survey with PBK; 4) KISD met with insurance claims adjuster Debris Removal and Preliminary Demolition 1) Board approves resolution to authorize emergency services to procure roofing project; 2) Roofing consultant begins preparation of construction documents August - September Timeline

45 10/13 & 20 FEMA Requirements Notification 1) Received FEMA letter indicating normal procurement processes must be adhered to after emergency clean-up; 2) FEMA recovery scoping 10/17, & 31-11/17 10/18 Roofing MEP Survey 1) Roofing bids accepted; 2) Roofing contract negotiations and document verification process KISD surveyed Lemm with SOBE (MEP) 10/20 & 27 Educational Programming Lemm restoration programming meeting to start discussion of educational space needs 10/25 & 26 Funding 1) Discussion of estimated expenditures for bond funds; 2) Preliminary discussion of repair estimate; 3) Lemm walkthrough with Vericlaim and Insurance consultant 11/1 & 22 11/3 & 9 11/7 11/3, 17 & 27/17 Architect Development Detention Requirements FEMA Requirements Progress Planning PBK internal meeting with consultants Oct. - Nov. Timeline 1) Inquiry into detention FEMA Program Delivery requirements but HC flood Manager (PDM) meeting control regulations unclear; 2) Lemm restoration progress meeting with discussion about requirements to bring building up to current Fire and Energy Code Lemm restoration progress meeting 10/26 Architect Development PBK internal meeting with consultants

46 12/1, 5, 8,15, 19 & 21 12/6 & 18 12/11 & 12 12/11 12/27 Progress Planning FEMA Roofing Project Procurement Process Steps Two & Three Architect Meeting 1) Board approved the roofing contract; 2) General contractor mobilization Board approved the schematic design and design development for the Lemm restoration process 1) Lemm restoration progress 1) FEMA PDM meeting; 2) Meeting meeting including Klein Cain with HC.; 3) HC notified KISD of interior design students helping requirement to raise Lemm by three with color selections; 2) Bond feet; 4) Clarification of HC expenses discussion; 3) PBK regulations coordination with consultants, 4) PBK 50% document review PBK project milestone meeting with consultants 1/5 1/12, 19 & 23 1/16, 23, 24, 29 & 31 1/ /26 Roofing Project Progress Meeting Architect Meeting FEMA KISD Internal Review Roofing work begins Lemm restoration progress meeting PBK coordination meetings with consultants & 75% set review FEMA Site Inspections with final walk-through on 1/24 Lemm restoration department review with maintenance/it and review of architectural changes Dec. - Jan. Timeline

47 2/5 2/5 2/10 & 17 2/12 Procurement Process Steps Four & Five Progress Meeting Architect Meeting Procurement Ad Lemm restoration progress meeting PBK coordination meeting with consultants Required advertising released in The Chronicle Board approval of construction documents & approval authorizing the superintendent to negotiate and execute the construction contract 2/13 2/20 2/27 Procurement Process Pre-proposal Conference Procurement Process 1) Construction plans released for competitive sealed proposal (CSP); 2) Plans submitted for permitting and accessibility (ADA) Pre-proposal conference for interested general contractors Competitive sealed proposals (CSP) due and evaluation process begins February Timeline

48 3/1 3/2 3/5-19 March 20 March August Procurement Process Procurement Process Contractor Roofing Project Construction 1) CSP evaluation continues; 2) Recommendation of contractor to superintendent Construction contract negotiation and execution Contractor permitting process & mobilization Roofing substantial completion Construction restoration to commence on or about March 19 August Sept. Construction & Move-In Final Construction Construction Restoration; Substantial Completion; Move-In Punch List Items March - Project Completion Timeline

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Dat e: August 2018 March Update Lemm restoration contract awarded to ICI Construction on March 2nd Contractor began mobilization on March 5th

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current

More information

LLANO ISD SCHOOL BOARD MEETING. January 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016 LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in historic Marigny

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

Fleet Elementary School

Fleet Elementary School Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018. Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area

More information

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction October 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY

Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY 2010-2011 October 1, 2010 to September 30, 2011 On August 3, 2011, the US Department of Education

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

Initial Design & Size

Initial Design & Size Want to Save time and money on your next building project? Careful planning will help you to anticipate problems, make the right decisions, and to speed construction. If you don t know the answers to all

More information

A. Remove Table of Contents and insert new attached Table of Contents.

A. Remove Table of Contents and insert new attached Table of Contents. ADDENDUM NO. 01 PROJECT Colby Glass E.S. Window Upgrades and ADA Work PROJECT NO. 16043 DATE February 07, 2018 TO: All Prime Contract Bidders and all others to whom Drawings and Specifications have been

More information

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES I. PURPOSE REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES The Greensboro Housing Authority (GHA) invites qualifications for the Architectural/Engineering Services for RAD Renovations at

More information

SECTION 6. Residential Warranty Corporation 10 Year, Limited Structural Warranty. Year One

SECTION 6. Residential Warranty Corporation 10 Year, Limited Structural Warranty. Year One SECTION 6 Residential Warranty Corporation 10 Year, Limited Structural Warranty Year One Foundations basement, crawl space, slab on grade. Framing ceiling, floor, roof, wall. Exterior structurally attached

More information

REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW:

REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW: Police Headquarters Project REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW: General description The objective is to renovate an approximately 18 x 24 section of the two-bay attached garage at Town

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Introduction & Project Background

Introduction & Project Background Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing

More information

A Program Summary: Complete renovation and addition with code upgrades for a historic academic building

A Program Summary: Complete renovation and addition with code upgrades for a historic academic building Program Summary: Complete renovation and addition with code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in the historic

More information

SECTION ADDENDA

SECTION ADDENDA SECTION 00 91 03 ADDENDA ADDENDUM NO. 2 June 14, 2017 RE: Cana Island Light Station Phase 2 Baileys Harbor, WI RA 1372.A FROM: TO: River Architects, Inc. 740 7 th Street North La Crosse, Wisconsin 54601

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction December 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri

More information

Voorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225 GENERAL NOTES DESIGN NOTES (CONTINUED) FOUNDATION NOTES STRUCTURAL ABBREVIATIONS CONCRETE MASONRY NOTES DESIGN NOTES S-001 CONCRETE NOTES COLD-FORMED STEEL FRAMING NOTES PRE-ENGINEERED METAL BUILDING NOTES

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE

More information

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application) ACCESSORY BUILDING Before your application can be deemed complete and ready for processing you will need the following: (Please hand in entire application package including this cover sheet) Zoning- check

More information

DISTRICT SERVICES BUILDING

DISTRICT SERVICES BUILDING DISTRICT SERVICES BUILDING BUILDING DATA DISTRICT SERVICES BUILDING 1100 Longhorn Dr., Weatherford, TX 76086 Year Built 1993 No. of Buildings 1 No. of Portables 0 Approx. Total Square Footage Grades Served

More information

STANMYRE + NOEL Architects, P.C Preston White Drive, Suite 104 Reston, VA v f

STANMYRE + NOEL Architects, P.C Preston White Drive, Suite 104 Reston, VA v f STANMYRE + NOEL Architects, P.C. 1890 Preston White Drive, Suite 104 Reston, VA 20191 v. 703.471.9350 f. 703.834.1031 info@snarchitects.com S E P T E M B E R 19, 2 0 1 6 ADDENDUM #3 PROJECT: WHITE OAKS

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Drexel Hill Middle School

Drexel Hill Middle School 150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel

More information

BWA ENVIRONMENTAL CONTROL BOARD (ECB) APPLICATION

BWA ENVIRONMENTAL CONTROL BOARD (ECB) APPLICATION BWA ENVIRONMENTAL CONTROL BOARD (ECB) APPLICATION To: The Environmental Control Board I propose to: (please check all that apply) * Repaint my home/garage. Color samples are submitted herewith and are

More information

Cold Spring School District

Cold Spring School District Cold Spring School District Deferred Maintenance & Capital Facilities Program July 9, 2018 Deferred Maintenance District Fund 14 School Facilities Maintenance in General Three types of maintenance projects

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information

Structural Condition Assessment

Structural Condition Assessment 108 6 th Street, Garland, Texas Engineering Report Date: September 29, 2016 RLG No. : 16729 Prepared for: Mr. Jeff D. Bulls III AIA 3030 LBJ Freeway, Suite 1220 Dallas, TX 75234 PM: Harold F. Phillips

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School A D D E N D U M # 1 DATE: TO: FROM: PROJECT: All Bidders Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School CBI JOB NO.: 11063 The following items shall modify

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

PROJECT UPDATE SEPTEMBER 11, 2014

PROJECT UPDATE SEPTEMBER 11, 2014 PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS GENERAL The commercial bidding process is a well-defined path of positioning oneself to be the successful bidder amongst a group purporting to offer the same quality materials and labor. There are certain

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

AN OFFERING OF 1661 EAST OGLETHORPE HIGHWAY FLEMINGTON, LIBERTY COUNTY, GEORGIA PRESENTED BY WHITLEY AND ASSOCIATES, INC.

AN OFFERING OF 1661 EAST OGLETHORPE HIGHWAY FLEMINGTON, LIBERTY COUNTY, GEORGIA PRESENTED BY WHITLEY AND ASSOCIATES, INC. AN OFFERING OF 1661 EAST OGLETHORPE HIGHWAY FLEMINGTON, LIBERTY COUNTY, GEORGIA 31313 PRESENTED BY WHITLEY AND ASSOCIATES, INC. OFFERING DISCLAIMER This offering summary has been prepared solely for informational

More information

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

PROJECTS COMPLETED WITH DIVERSIFIED EMPLOYEES (COMMERCIAL)

PROJECTS COMPLETED WITH DIVERSIFIED EMPLOYEES (COMMERCIAL) PROJECTS COMPLETED WITH DIVERSIFIED EMPLOYEES (COMMERCIAL) 1800 S Washington, Amarillo, TX -------------------------------------------------------------- $126,207.38 Insurance claim was filed due to a

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

BOARD OF EDUCATION OF HARFORD COUNTY INFORMATIONAL REPORT

BOARD OF EDUCATION OF HARFORD COUNTY INFORMATIONAL REPORT BOARD OF EDUCATION OF HARFORD COUNTY INFORMATIONAL REPORT DECISION ON AWARD OF CONTRACT BUILDING BID PACKAGES 2A and 9A YOUTH S BENEFIT ELEMENTARY REPLACEMENT SCHOOL AUGUST 18, 2014 Background Information:

More information

Coos Bay Best Bond Cost Breakdowns

Coos Bay Best Bond Cost Breakdowns Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Estimating & Scope. Additional Lessons Tools / Measuring / Masonry / Framing/

Estimating & Scope. Additional Lessons Tools / Measuring / Masonry / Framing/ Estimating Video Class A 1 of 2 Estimating & Scope Estimating Video Class A 2 of 2 Additional Lessons Tools / Measuring / Masonry / Framing/ Tools / Measuring Lessons Developing An Accurate Property Estimate

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012 Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap

More information