GRAND PRIZE WINNER. ZeroEnergy Design. Phone: Website: Sponsors:

Size: px
Start display at page:

Download "GRAND PRIZE WINNER. ZeroEnergy Design. Phone: Website: Sponsors:"

Transcription

1 GRAND PRIZE WINNER ZeroEnergy Design Phone: Website: Sponsors:

2

3 Entry P122 The Little Green Rhody Narrative We are pleased to submit a net-zero possible design for the competition. Our multidisciplinary team includes both a Rhode Island licensed architect and a residential mechanical designer, who is also a specialist in energy modeling and a certified HERs rater. The requested drawings and visualization capture our proposed design. We ve adapted the same footprint for the both the three and four bedroom plans. Our intent was to create a simple, aesthetically pleasing form that reflects the local vernacular of the neighborhood, and will be economical to construct and operate. Life-Cycle Assessment Global Warming Potential The Little Green Rhody relies on traditional wood frame construction paired with a modified concrete foundation system. For the wood frame, we elected for 2x4 studs at sixteen inches on center. The 2x4s have a minor savings relative to 2x6s at twenty-four inches on center, but the sixteen inch spacing is preferable for the siding attachment the strapping for the rainscreen needs to align with the stud spacing, attaching the siding at twenty-four inches on center over strapping can lead to wavy siding, so sixteen inch spacing is preferred. When comparing 2x4s vs. 2x6 both at sixteen inches on center, we find that the savings of 2-3% (a result of less wood and insulation) is preferable to the minor savings in operational energy, when paired with our exterior insulation detail. There will be a savings in the material cost of the insulation and lumber. Care has been taken to minimize the framing factor (the amount of wood in the stud wall) by setting the overall dimensions of the home on a sixteen inch grid, setting the typical windows within the grid and aligning one side of each door to the grid. The modified concrete foundation system we have used is engineered and manufactured by Superior Walls of America, though there may be comparable systems. When compared to a two foot by one foot spread footing and eight inch cast in place concrete wall, the Superior Walls uses twenty-five less cubic yards of concrete. This is a result of less concrete in the walls system, as well as a rubble footing in place of a poured concrete footing. The system has an ICC Code Approval Report, number ESR The minor modification is that we ve proposed to use expanded polystyrene (EPS) in place of extruded polystyrene (XPS) for reasons indicated above. As the insulation in non-structural, we do not feel the substitution should be problematic. This results in a savings of about three metric tons, or an 18% reduction in the overall foot print of the home. (Note we have accounted for the steel reinforcement that is required by this system see the Calculations page section at the end of this PDF.) The system is structurally sounds and offers a continuous layer of concrete on the exterior of the system that will be beneficial in creating a long-term waterproof foundation, relative to a discontinuous system like concrete blocks. The proposed roof will be constructed of trusses at twenty-four inches on center. The use of a truss constructed of 2x4 and 2x6 material will use less wood than a roof framed with traditional rafters and ENTRY P122

4 ceiling joists. The truss also allows for a raised heel at the top of wall so that the ceiling insulation is not diminished at the pinch point where the roof meets the wall. The insulation materials both above and below grade have been selected for their low global warming potential. We have excluded use of extruded polystyrene (XPS) from the project due to it s high global warming potential. For below slab and the interior of the foundation wall, we ve relied on Expanded polystyrene (EPS.) Below the slab, we ve used Type 9 EPS it has a high compressive strength and is suitable for below grade applications. It s also extruded in Smithfield, RI, a mere 7 miles from the site. Operational Energy Use The Little Green Rhody uses less than half the energy of an equivalent code-built home. The chart below compares operational cost for the four bedroom Little Green Rhody to a code-built baseline, as defined by the User Defined Reference Home (UDRH.) (Note this comparison does not account for PV.) The raw data for this comparison can be found in the REM/Rate export included in this PDF. $4, $3, $3, $2, $2, $1, $1, $ $0.00 Operational Energy Cost Comparison $3, Code-Build Baseline $1, Little Green Rhody (#P122) - 4 BR $4, $3, $3, $2, $2, $1, $1, $ $0.00 Appliances Lighting Hot Water Cooling Heating Total In further support of the operational energy use of the Little Green Rhody, please reference the following included in this PDF: - a Home Energy Rating (HERs) Certificate for the Four Bedroom version of our design with a 7.5kW PV array completed by our certified HERs rater - REM/Rate Performance Factors for the Three Bedroom unit - REM/Rate Performance Factors for the Four Bedroom unit The low operational energy use of the Little Green Rhody is largely attributed to it s air tight and well insulated building envelope. Beyond minimizing heat loss, the heating load is further offset by placing a majority of the well-insulated, high solar heat gain windows on the south side of the home to capture the sun s free heat. Shading from the roof overhang and the wood trellis over the south-facing sliding ENTRY P122

5 door limit overheating during the warmer months. The following sub-sections further describes the attributes of the building envelope and mechanical systems. Building Envelope Foundation: The basement is continuously insulated both on the foundation walls and below slab. This insulation keeps the basement within the conditioned space making it a similar temperature as the rest of the house, with controlled humidity. These attributes, paired with the access from both the first floor and the back yard, will make it a great place for storage, mechanical equipment, and even play space for the children. Above Grade Walls: We ve employed an external insulation strategy to allow for continuous insulation of the walls system. This wall system with perform significantly better than a wall that relies on cavity insulation as the wood studs have great structural capacity but are a poor insulator when compared to insulation. There are a couple of different types of rigid insulation that are suitable for an exterior insulation detail. We ve proposed to use 3 of mineral wool insulation it has a low global warming potential, is not a petroleum based product, and does not expand and contract like foam-based insulation products. This last point is particularly important because we ve proposed just one layer of three inch thick mineral wool. If polyisocyanurate were to be substituted, for example, it would be important to install two layers with staggered seams as each panel is prone to expand and contract with temperature creating small gaps between the panels, reducing overall performance and creating a potential for condensation on the sheathing. The images below, created in Therm, show a typical wall with a post compared to the same wall with exterior insulation. Not only is the interior surface temperature of the exterior insulated wall warmer, but it s condensing surface, the sheathing, is warmed such that it will not reach the dew point and cause condensation. This will increase the durability and longevity of the wall. ENTRY P122

6 Roof: We ve proposed a vented roof assembly with a truss structure and fourteen inches of loose filled cellulose at the attic ceiling. The vented assembly allows for the use of economical yet effective insulation at the attic ceiling. The raised heal at the edge of the truss avoids the typical thermal bridge that occurs at the roof wall intersection. Though the attic space will not be suitable for storage or mechanical equipment, we feel this is not an issue as the basement if fully insulated and conditioned. Window & Doors: Our design calls for triple glazed windows and doors. The triple glazing not only reduces heat loss in a cold climate, but also significantly improves thermal comfort for the occupants as the interior surface temperature of the windows will be a few degrees warmer than a double paned window. Though there are many manufacturers in the US who are making triple and even simulated triple pane (through using a film in place of the center pane of glass) windows, our experience is that the triple pane windows being manufactured in Europe are actually more economical and higher performing. The imported windows have lower U-frame values, better performing glass spacers, and higher solar heat gain glass an important quality for a cold climate as the glass will admit more of the sun s free heat. Luckily, many of the manufacturing facilities are near ports as is the site. Shipping the windows across the sea can actually have a smaller carbon footprint than trucking them across the country or for Canada, where some of the best performing windows in North America are currently made. Shipping from manufacturing facilities in to ports in Europe is often a short distance by truck or rail. Shipments can be received in Port of Providence. Using the transportation carbon calculator found at log-net.com, we compared the carbon foot print of windows fabricated by a supplier we ve used in Germany vs. another in Ontario, Canada. The result was over 5% more metric tons of carbon for the windows fabricated in Canada. With both a better price point and performance, the imported windows are a great option. Air Barrier: A continuous air barrier is detailed from the foundation up to the roof and back down again. An effective air barrier will significantly decrease operational energy, make the envelope more durable as the majority of moisture is carried through air movement, and improve the thermal comfort for the occupants. The air barrier is called out in one of our building sections. Of note is the use of both the ZIP wall sheathing and building paper. The ZIP system is a great air barrier it s more economical than plywood and it s continuity can be visually verified. Though the coating on the ZIP system does double as a code approved weather barrier, we ve included a layer of building paper in order to allow traditional flashing details throughout the wall assembly. Heating, Cooling, Ventilation & Hot Water We ve designed the house to be all electric so that the electricity can be offset in part or in full by PV or solar panels atop the roof. The heating and cooling is provided via an air-source heat pump. It s simple and economical to install. The small size of the system is well suited to a low energy home such as this one where the heating and cooling loads have been significantly decreased. National Grid, the local electricity provider, offers a rebate up to $500 of this piece of equipment. There is also a Heat Recovery Ventilator (HRV) that will provide dedicated ventilation with heat recover, an important addition to an air tight home. ENTRY P122

7 For domestic hot water, we ve proposed a heat pump hot water heater. Though a solar thermal system can be an efficient means of creating hot water, it still requires a backup system. It also adds an additional system to the house and competes for roof space with the PV panels. The energy consumed by the heat pump hot water heater can be offset by the production from the PV panels. National Grid also offers a $750 rebate of heat pump hot water heaters. Renewable Energy We ve sized a 7.5 kw PV or solar electric system for the four bedroom home and a 7.3 kw for the three bedroom home. Both array sizes will easily fit on the south-facing roof surface and will result in net-zero energy meaning the home will produce as much energy as it uses over the course of a year. There are currently two sources to offset the cost of the proposed PV array. The current installed cost of PV is about $4.00 / watt. At this rate, the 7.5 kw array will have an installed cost of about $30,000. It may be possible to further decrease this up front cost with in-kind donations. Though neighboring states, like Massachusetts, offer PV leasing programs, they are not currently available in Rhode Island. If the project does move forward to construction, this option should be reinvestigated. There is currently a grant available from the Rhode Island Renewable Energy Fund (RIREF) that will offset 25% of the system cost. There is also a federal 30% tax credit available for the installed cost. If the homeowner does not use the entire tax credit in the year the house is purchased, the credit can be rolled over until Affordability and Constructability The proposed construction system by Superior Walls should be cost competitive with a poured foundation with comparable insulation. Because it is a manufactured and marketing system, there may also be a greater potential for sponsorship relative to a traditional poured foundation. The framed above grade walls should be easy and economical to construct with volunteer labor. If the project is constructed, our team would be happy to provide framing plans that will minimize the use of wasted wood, showing how the window and door placement, as well as the overall dimensions, conform to a sixteen inch on center grid. The ZIP wall sheathing is less expensive than plywood. It is installed like conventional sheathing. Volunteers can tape the seams to create the air barrier, and a supervisor can easily verify with a visual inspection that the system is continuous prior to the application of the building paper. The wood roof trusses can be pre-manufactured or assembled by volunteers. The rigid insulation can also be installed by volunteers. Though the product is available in 3 x 48 x 96 boards, it will be easier to install in the 3 x 36 x 48 size as it can be carried and handled by one person. The proposed use of furring strips to strap the siding back to the structure is a code approved and tested installation detail. It should be noted, however, that we feel the installation of the strapping should be executed by trained professionals and not volunteer labor. In addition to connecting the siding back to the structure, the furring strips also create a drainage space behind the siding, which will improve the life of the finish. This detail, typically called a rainscreen, is a best practice for siding installation. After the furring strips are installed, volunteer labor can install the siding if this is common practice for Habitat projects. ENTRY P122

8 This home, even without PV, will significantly exceed the basic requirements of the Energy Star program. Our experience working in Rhode Island is that homes of similar performance have received a $4,000 rebate which helps to offset the upfront premium for additional insulation. Aesthetics and Livability Site & Exterior look The exterior of the Little Green Rhody fits well with neighborhood vernacular of gabled homes with either clapboard, brick veneer, or shingle siding. The majority of homes in the area do not conform with the current zoning code they are located too close to the street. The proposed design respects the building setbacks and includes a front porch that will help to activate the street space. Parking, on a two- or double-track driveway will limit paved area and increase the permeability of the site. The parking is located along the north side of the site where there are few windows on the lower level. This leaves the south side of the house open to the side yard. For the time being, the view out the south side also enjoys the view to the undeveloped neighboring lot. Rain barrels located on the bottom of the down spouts collect rainwater for use in landscaping. Storage for garbage bins, typically an eye sore, is conveniently located close to the street, between the front and side doors. Shading from summer heat gain for the south facing second floor windows is provided by the two foot long overhangs. A wood shade trellis over the south facing sliding door will shade the door and the small patio. Additional covered outdoor space is provided at the front porch. The front door serves as both the everyday and guest entrance for the home. The covered porch shield the entrant from the elements. To the right of the entry is a bench with storage below for taking off shoes and a coat closet sized to accommodate a large family. The open kitchen, living and dining space is flexible to allow the family to furnish it to their liking. There is even space for a work space (not shown on plans) if the family would like to include one. The nine foot ceilings on the first floor will work well with the scale of the space. A full bathroom on the first floor will be important for a large family. The three bedroom plan creates acoustical privacy between each bedroom by using the closets as a buffer space. All of the bedrooms are generously sized with ample closet space. Bedroom 2 has two closets and a larger size than Bedroom 3, allowing to be shared by two children. The four bedroom plan fits three modest sized children s bedrooms in addition to a more generously sized master bedroom. The large linen closet provides ample storage space for the family. Each bedroom contains one south facing window. ENTRY P122

9

10

11 PROPOSED WOOD FENCE HATCH TO BASEMENT RAIN BARREL BUILDING SETBACK CAR 2 PV ARRAY CAR 1 STORAGE FOR GARBAGE BINS RAIN BARREL 2 TRACK DRIVEWAY N PROPOSED 10' CURB CUT SCALE: 1"= 20' ENTRY P122 - SITE PLAN

12 P REF 7.5' x 5' BDRM 3 9' x 9' 7.5' x 5' DN BDRM 2 9' x 11' TRELLIS ABOVE UP LINEN BDRM ' x 12.5' BENCH COVERED FRONT PORCH N SCALE: 1/8" 1"= = 81' ' - 0" ENTRY P122-3 BEDROOM PLANS

13 P REF 7.5' x 5' BDRM 4 9' x 9' 7.5' x 5' DN BDRM 3 9' x 9' TRELLIS ABOVE UP BDRM 2 9' x 9' LINEN BENCH BDRM ' x 10' COVERED FRONT PORCH N SCALE: 1/8" 1"= = 81' ' - 0" ENTRY P122-4 BEDROOM PLANS

14 SCALE: 1/4" 1"= = 41' ' - 0" ENTRY P122 - EAST ELEVATION

15 SCALE: 1/4" 1"= = 41' ' - 0" ENTRY P122 - WEST ELEVATION

16 NORTH SOUTH SCALE: 1"= 1/8" = 81' ' - 0" ENTRY P122 - ELEVATIONS

17 LAP NON PERFORATED HOUSEWRAP OVER TOP OF WALL PRIOR TO INSTALLING ROOF TRUSS TO CONNECT WALL AND CEILING AIR BARRIERS BEDROOM HALLWAY LINEN GYPSUM WALL BOARD CEILING TAPED AS AIR BARRIER ZIP WALL SHEATHING TAPED AS AIR BARRIER LIVING SPACE WINDOW HEADER AND SILL PROFILE TAPED TO AIR BARRIER TAPE SHEATHING TO FOUNDATION W/ ZIP TAPE INSULATED BASEMENT TAPE AND SEAL INTERSECTION OF SLAB, POLYETHELENE AND FOUNDATION TO CREATE AIR SEAL ENTRY P122 - BUILDING SECTION

18 PV ARRAY ROOF ASSEMBLY (OUTSIDE IN): - ASPHALT SHINGLES - ROOFING PAPER - SHEATHING 2' OVERHANG SHADES SOUTH-FACING SECOND STORY WINDOWS RAISED HEEL TRUSS 14" LOOSE FILL CELLULOSE TRIPLE GLAZED HIGH SOLAR GAIN WINDOWS WOOD TRELLIS TO SHADE SOUTH FACING SLIDING DOOR TRIPLE GLAZED HIGH SOLAR GAIN SLIDING DOOR 9' - 0" 8' - 0" BEDROOM LIVING SPACE HALLWAY GUTTERS TO DOWNSPOUTS TO RAIN WATER BARRELS WALL ASSEMBLY (OUTSIDE IN): - FIBER CEMENT CLAPBOARD SIDING - 1x4 16" O.C. - 3" MINERAL WOOL INSULATION - BUILDING PAPER - ZIP WALL SHEATHING - 16" O.C., CAVITY FILLED W. MINERAL WOOL OR COTTON BATT - 1/2" GYPSUM WALLBOARD - NO VOC PAINT & PRIMER INSULATED BASEMENT FOUNDATION WALL BY SUPERIOR WALL OR EQUIVALENT (OUTSIDE IN): - 1 3/4" CONCRETE - 4 1/2" EPS INSULATION - 1/2" POLYISOCYANURATE INSULATION - 2 1/4" x 7 1/2" REINFORCED CONCRETE 24" O.C. - 1" EPS INSULATION WRAPPING STUDS 4" CRUSHED STONE CONCRETE BASE TO FOUNDATION SYSTEM DRAINAGE PIPE TO SUMP PUMP OR DAYLIGHT SLAB ASSEMBLY (TOP DOWN): - 4" CONCRETE SLAB - 6 MIL. POLYETHELENE VAPOR BARRIER - 3" TYP IX EPS INSULATION ENTRY P122 - BUILDING SECTION & AIR BARRIER DIAGRAM

19 APA 4BR Net Zero, Registry ID: Rating Number: Certified Energy Rater: Rating Date: Rating Ordered For: 4 Bedroom Entry P122 Estimated Annual Energy Cost 5 Stars Plus Uniform Energy Rating System Energy Efficient 1 Star 1 Star Plus 2 Stars 2 Stars Plus 3 Stars 3 Stars Plus 4 Stars 4 Stars Plus 5 Stars 5 Stars Plus or Less HERS Index: -0 Efficient Home Comparison: 100% Better General Information Conditioned Area: 2039 sq. ft. HouseType: Single-family detached Conditioned Volume: cubic ft. Foundation: Conditioned basement Bedrooms: 4 Mechanical Systems Features Air-source heat pump: Electric, Htg: 10.5 HSPF. Clg: 17.5 SEER. Water Heating: Heat pump, Electric, 2.40 EF, 66.0 Gal. Use MMBtu Cost Percent Heating 6.3 $ % Cooling 2.0 $83-535% Hot Water 6.2 $ % Lights/Appliances 18.1 $ % Photovoltaics $ % Service Charges $0-0% Total $ % This home meets or exceeds the minimum criteria for all of the following: 2009 International Energy Conservation Code Duct Leakage to Outside: 1.00 CFM. Ventilation System: Balanced: HRV, 60 cfm, 30.0 watts. Programmable Thermostat: Heating: Yes Cooling: Yes Building Shell Features Ceiling Flat: R-52 Exposed Floor: NA Vaulted Ceiling: NA Window Type: Schuco Si82 Above Grade Walls: R-27 Infiltration: Foundation Walls: R-10.7 Rate: Htg: 1.00 Clg: 1.00 ACH50 Slab: R-13.2 Edge, R-13.5 Under Method: Blower door test Lights and Appliance Features Percent Interior Lighting: Range/Oven Fuel: Electric Percent Garage Lighting: Clothes Dryer Fuel: Electric Refrigerator (kwh/yr): Clothes Dryer EF: 3.01 Dishwasher Energy Factor: 0.75 Ceiling Fan (cfm/watt): 0.00 The Home Energy Rating Standard Disclosure for this home is available from the rating provider. REM/Rate - Residential Energy Analysis and Rating Software v13.0 This information does not constitute any warranty of energy cost or savings Architectural Energy Corporation, Boulder, Colorado. ZeroEnergy Design 156 Milk Street, Suite 3 Boston, MA Certified Energy Rater

20 PERFORMANCE FACTORS - C:\...\JMC 2011 UDRH v2 for REM 12.9.udr Date: March 01, 2013 Rating No.: Building Name: APA 3BR No PV Rating Org.: Owner's Name: Phone No.: Property: Rater's Name: Address:, Rater's No.: Builder's Name: Weather Site: Providence, RI Rating Type: File Name: APA_REM_3BR NoPV.blg Rating Date: 3 Bedroom #P122 UDRH APA 3BR No PV DIFF % DIFF Normalized Loads (Btu/sf shell area/dd) Heating: % Cooling: % Normalized Consumption (kbtu/sf floor area/yr) Heating: 22.6 a % Cooling: % Water Heating: % Lighting: Appliances: Photovoltaics: Total w/o PV: % Total: % Normalized Consumption (Btu/sf floor area/dd) Heating: % Cooling: % Normalized Costs ($/sf floor area/yr) Heating: $ $ $ % Cooling: $ $ $ % Water Heating: $ $ $ % Lighting: $ $ $ % Appliances $ $ $ % Photovoltaics $ $ $ Total: $ $ $ % Normalized Design Loads (Btuh/sf shell area/dd) Heating: % Cooling: % Normalization Factors Floor Area: Shell Area: Heating Degree Days (B65): Cooling Degree Days (B74): a Duct loss exceeds 50% of equipment capacity. Verify duct and equipment sizing inputs. REM/Rate - Residential Energy Analysis and Rating Software v13.0 This information does not constitute any warranty of energy cost or savings Architectural Energy Corporation, Boulder, Colorado.

21 PERFORMANCE FACTORS - C:\...\JMC 2011 UDRH v2 for REM 12.9.udr Date: March 01, 2013 Rating No.: Building Name: APA 4BR Net Zero Rating Org.: Owner's Name: Phone No.: Property: Rater's Name: Address:, Rater's No.: Builder's Name: Weather Site: Providence, RI Rating Type: File Name: APA_REM_4BR wpv.blg Rating Date: 4 Bedroom #P122 UDRH APA 4BR Net Zero DIFF % DIFF Normalized Loads (Btu/sf shell area/dd) Heating: % Cooling: % Normalized Consumption (kbtu/sf floor area/yr) Heating: 22.0 a % Cooling: % Water Heating: % Lighting: Appliances: Photovoltaics: Total w/o PV: % Total: % Normalized Consumption (Btu/sf floor area/dd) Heating: % Cooling: % Normalized Costs ($/sf floor area/yr) Heating: $ $ $ % Cooling: $ $ $ % Water Heating: $ $ $ % Lighting: $ $ $ Appliances $ $ $ Photovoltaics $ $ $ Total: $ $ $ % Normalized Design Loads (Btuh/sf shell area/dd) Heating: % Cooling: % Normalization Factors Floor Area: Shell Area: Heating Degree Days (B65): Cooling Degree Days (B74): a Duct loss exceeds 50% of equipment capacity. Verify duct and equipment sizing inputs. REM/Rate - Residential Energy Analysis and Rating Software v13.0 This information does not constitute any warranty of energy cost or savings Architectural Energy Corporation, Boulder, Colorado.

22 Calculations Concrete Volume at Superior Wall Foundation System: Walls & Cast Concrete Columns Walls= 163 cf Column= 34 cf Total= 197 cf (1cf = yd3) = 197cf x yd3 = 7.29 yd^3 of Concrete, 4 Slab= 7.22 yd3 Slab + Superior Wall System: = 14.5 yd^3 of Concrete Comparison: Typical Concrete Foundation (Basement) Based on Same design. Walls= cf Footing= cf Slab= cf Total = cf (1cf = yd3) = cf x yd3 = 40yd^3 of Concrete Potential CO2: Calculations Include Whole Assemblies, with matching insulation specifications. Superior Wall System: Walls= 9.87 Tonnes, Slab 2.93 Tonnes; Total= 12.8 Tonnes Typical Foundation: Walls= 10.1 Tonnes, Footing 2.98 Tonnes, Slab 3.33 Tonnes; Total= Tonnes Overall Project Totals: Superior Wall System Model= Tonnes ; Typical Foundation Tonnes Extra Base Materials: Rebar at Superior Wall=.6 cf (Density of Steel=0.283 lb/in^3) (1lb=.0005 t (short tons) ( 1cf = 1728 in^3) 1728 in^3 x lb/in^3 = lb lb x 0.6= lb 294 lb x t (tons) = (.147t ) x 1.10 =.1617t Metal Studs at Superior Wall= 4cf (Density of Steel=0.283 lb/in^3) (1lb=.0005 t (short tons) ( 1cf = 1728 in^3) Attic Insulation= 638 sf x 14 = 8932 sf (1 ) Insulation Measured From Inside face of framing lb x 4 = lb lb x t (tons)= t (short tons) Trellis & Deck/ Porch lumber= Trellis= 20cf, Columns= 15.68cf; Total= 35.68cf Strapping, Interior & Exterior= 279 bf (1 Mbfm= 1000 bf) 35.68cf x 12bf= bf bf / 1000 bf=.428 Mbfm Deck/ Porch Concrete footings= 4cf 279bf / 1000 bf=.279 Mbfm 4cf x yd^3= 0.15 yd^3 ENTRY P122

PV Generation Potential 17.1 kbtu/ft2/yr 15.4

PV Generation Potential 17.1 kbtu/ft2/yr 15.4 TOWNHOME PROTOTYPE BASELINE 60 kbtu/sf/yr 50 kbtu/sf/yr 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 54.4 Baseline 54.4 kbtu/ 2/yr 21.8 High Performance 18.2 PHIUS - IES 60 MMBtu

More information

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 50 kbtu/sf/yr 45.1 PROJECT INFORMATION 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 13.0 kbtu/ft2/yr Baseline 10.8 kbtu/ft2/yr

More information

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 40 kbtu/sf/yr 35 kbtu/sf/yr 30 kbtu/sf/yr 25 kbtu/sf/yr 20 kbtu/sf/yr 15 kbtu/sf/yr 10 kbtu/sf/yr 5 kbtu/sf/yr 0 kbtu/sf/yr 11.9 kbtu/ft2/yr 36.0

More information

MID-RISE APARTMENT BUILDING PROTOTYPE PHIUS - WUFI PASSIVE

MID-RISE APARTMENT BUILDING PROTOTYPE PHIUS - WUFI PASSIVE MID-RISE APARTMENT BUILDING PROTOTYPE PHIUS - WUFI PASSIVE 50 kbtu/sf/yr 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 45.1 Baseline 13.0 High Performance 15.5 PHIUS - IES 25.2 PHIUS

More information

PV Generation Potential 17.1 kbtu/ft2/yr 15.4

PV Generation Potential 17.1 kbtu/ft2/yr 15.4 TOWNHOME PROTOTYPE HIGH PERFORMANCE 60 kbtu/sf/yr 50 kbtu/sf/yr 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 54.4 Baseline 21.8 kbtu/ 2/yr 15 MMBtu 12 MMBtu 9 MMBtu 6 MMBtu 3 MMBtu

More information

- Inbound/Outbound window placement - Window buck & air sealing - Weep holes IN THE WOODS DETAILS - WINDOW SILL

- Inbound/Outbound window placement - Window buck & air sealing - Weep holes IN THE WOODS DETAILS - WINDOW SILL - Inbound/Outbound window placement - Window buck & air sealing - Weep holes IN THE WOODS DETAILS - WINDOW SILL PRE-EXISTING SITE Program: Traditional farmhouse Single level living potential Garage connection

More information

14.8 kwh/(m²a) Project Documentation. 1 Abstract. R-951 Residence: Three Family Passive House Building. 1.1 Data of building. Year of construction

14.8 kwh/(m²a) Project Documentation. 1 Abstract. R-951 Residence: Three Family Passive House Building. 1.1 Data of building. Year of construction Project Documentation 1 Abstract R-951 Residence: Three Family Passive House Building 1.1 Data of building Year of construction U-value external wall/ U-Wert Außenwand 2013 0.112 W/(m²K) Space heating

More information

Water control Vapor control and drying Room for growth

Water control Vapor control and drying Room for growth How do we decide whether to insulate to inside or the outside? How to install windows in a DER wall (let me count the ways ) What s the best approach for historic buildings? How to deal with basement walls

More information

Three-Story Victorian Partial Retrofit. Overview. Case Study

Three-Story Victorian Partial Retrofit. Overview. Case Study Case Study National Grid Deep Energy Retrofit Pilot Program Three-Story Victorian Partial Retrofit Brookline, Massachusetts Overview The owners of this single family Victorian had previously gone through

More information

2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012

2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012 2012 Ontario Building Code Requirements for New Construction Bradford West Gwillimbury Building Division March 5, 2012 1 Ontario Building Code changes Applicable to permits applied for after December 31,

More information

EPA ENERGY STAR Homes Certification Report

EPA ENERGY STAR Homes Certification Report EPA ENERGY STAR Homes Certification Report Sponsored by For the property located at: 703 Suncook Valley Highway, Epsom, NH 1181 Elm Street, Suite 205, Manchester, New Hampshire 03101 Telephone: 603.656.0336

More information

National Grid Deep Energy Retrofit Pilot Program Second Floor Reframing Comprehensive Retrofit of 19 th Century Small Colonial

National Grid Deep Energy Retrofit Pilot Program Second Floor Reframing Comprehensive Retrofit of 19 th Century Small Colonial Case Study National Grid Deep Energy Retrofit Pilot Program Second Floor Reframing Comprehensive Retrofit of 9 th Century Lancaster, Massachusetts Photo: Transformations, Inc. Overview Habitat for Humanity

More information

Single Family Homes less than 3,000 sq.ft.

Single Family Homes less than 3,000 sq.ft. SIP walls: 4 and 6-1/2 with EPS insulating core 2019 Winner SIP roof: 6" roof with EPS insulating core Ferrier Builders Heather Laminack 3 Sisters Project Ft. Worth, TX Ferrier Builders Heather Laminack

More information

TELLUs FLORIDA USA. Tellus Integrated Panel System

TELLUs FLORIDA USA. Tellus Integrated Panel System Miami Dade College Kendall Campus - Miami, Florida USA Product: Tellus Integrated Panel System - Plant-Cast Architect: Perkins & Will Miami Precast Producer: Metromont Corporation General Contractor: Kaufman

More information

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING WWW.STOPWASTE.ORG New Addition Consider the following green remodeling options in a new addition.

More information

Residential Energy Code Update

Residential Energy Code Update Residential Energy Code Update www.phrc.psu.edu August 28 th, 2018 Brian Wolfgang Provider # 60114115 PPP ID: 1562 Description On May 1, 2018, the PA Uniform Construction Code (PA UCC) Review and Advisory

More information

2 stories + basement 1,200 finished SF 2 bedrooms 1 bath 5 people

2 stories + basement 1,200 finished SF 2 bedrooms 1 bath 5 people 2 stories + basement 1,200 finished SF 2 bedrooms 1 bath 5 people Prior Airport Noise Retrofit Windows with Storms Mechanicals Airtightness Initial Test 8.5 ACH50 [2,100 CFM50] Pre-Existing Conditions

More information

National Grid Deep Energy Retrofit Pilot Program Cape Basement Renovation Turned Comprehensive DER

National Grid Deep Energy Retrofit Pilot Program Cape Basement Renovation Turned Comprehensive DER Case Study National Grid Deep Energy Retrofit Pilot Program Cape Basement Renovation Turned Comprehensive DER Newton, Massachusetts Overview The owners of this single family home initially set out to remodel

More information

Energy Efficiency Requirements 9.36

Energy Efficiency Requirements 9.36 The following information has been obtained from the HPO Illustrated Guide, Energy Efficiency Requirements for Houses in British Columbia, BCBC 9.36 & 9.32, Building Officials Association of British Columbia

More information

FirstEnergy Program Overview

FirstEnergy Program Overview FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio

More information

CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION

CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION Chapter 1: Overview of Energy Efficient Construction 1 CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION Chapter 1 is a quick reference guide that discusses the key components and features of energy

More information

Hamilton Way - Case Study of a High Performance Community in a Cold Climate

Hamilton Way - Case Study of a High Performance Community in a Cold Climate March 11, 2010 Northeast Sustainable Energy Association Conference Peter Baker, P.Eng. Building Science Corporation Chris Nelson Nelson Construction Hamilton Way - Case Study of a High Performance Community

More information

Single Family Homes - over 3,000 sqft. Parfitt Residence

Single Family Homes - over 3,000 sqft. Parfitt Residence Participant information Zero-Energy Plan LLC/Clifton View Homes Ted L. Clifton 107 S. Main St. Ste. G201 Coupeville, WA 98239 Phone: 360-969-2363 Email Address: ted@zero-energyplans.com Website: www.zero-energyplans.com

More information

Airport Vicinity Acoustic Insulation

Airport Vicinity Acoustic Insulation PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Airport Vicinity Acoustic Insulation By-law No. 6419/94 of the City of Winnipeg to establish minimum acoustic insulation requirements for buildings within

More information

Oregon High Performance Home Requirements

Oregon High Performance Home Requirements Oregon High Performance Home Requirements A Business Energy Tax Credit for Homebuilders Homebuilders who construct homes to the Oregon High Performance Home (HPH) standard are now eligible for the Business

More information

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over

More information

Construction Report NYSERDA Residential Performance Challenge

Construction Report NYSERDA Residential Performance Challenge Construction Report NYSERDA Residential Performance Challenge WELYTOK TOWNHOMES October 2014 Submitted to: NYSERDA 17 Columbia Circle Albany, NY 12203 Submitted by: HOMEPIC Team CDH Energy Corp. PO Box

More information

Low-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity

Low-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity Low-cost Construction for High-energy Savings Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity construction@rahh.org Objectives: 1. Control air & moisture in high-performance, low-cost

More information

ENERGY STAR Qualified Homes National Program Requirements, Version 3.0

ENERGY STAR Qualified Homes National Program Requirements, Version 3.0 Qualifying Homes The following homes are eligible to earn the ENERGY STAR: Single-family homes; Units in multi-family buildings that are three stories or less; Units in multi-family buildings that are

More information

ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes. Thursday, February 24, 2011

ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes. Thursday, February 24, 2011 ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes Thursday, February 24, 2011 1 Efficiency Vermont is a Registered Provider with The American Institute of Architects Continuing

More information

THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012

THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012 THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012 Compliance with the code for new residential construction, additions, and substantial remodels will

More information

ADDENDUM A CONSTRUCTION SPECIFICATIONS

ADDENDUM A CONSTRUCTION SPECIFICATIONS ADDENDUM A Description of Improvements: CONSTRUCTION SPECIFICATIONS The Improvements shall consist of constructing an approximate square foot single-family residence including car garage on the real property

More information

Final 2016 UDRH Inputs: Addendum to Massachusetts Single- Family Code Compliance/Baseline Study DOCUMENT TITLE.

Final 2016 UDRH Inputs: Addendum to Massachusetts Single- Family Code Compliance/Baseline Study DOCUMENT TITLE. DOCUMENT TITLE Final 2016 UDRH Inputs: Addendum to 2015-16 Massachusetts Single- Family Code Compliance/Baseline Study March 6, 2017 SUBMITTED TO: The Electric and Gas Program Administrators of Massachusetts

More information

Urban Revitalization Plan For Responsible and Sustainable Growth and Development City of Adel, Iowa

Urban Revitalization Plan For Responsible and Sustainable Growth and Development City of Adel, Iowa Urban Revitalization Plan For Responsible and Sustainable Growth and Development City of Adel, Iowa Residential Tax Abatement Program Application Applicant Name (Print) Address / City / State Phone Email

More information

HCM UNIVERSITY OF ALASKA FAIRBANKS Building Challenges in Alaska UNIVERSITY OF ALASKA FAIRBANKS

HCM UNIVERSITY OF ALASKA FAIRBANKS Building Challenges in Alaska UNIVERSITY OF ALASKA FAIRBANKS HCM-00952 UNIVERSITY OF ALASKA FAIRBANKS UNIVERSITY OF ALASKA FAIRBANKS Building Challenges in Alaska INTRODUCTION Special considerations for building in Alaska are recommended that are normally not included

More information

The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits

The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits 3. Development and Septic Fees 4. Tarion New Home Warranty

More information

CRM Homes BUILDER Mangan Drafting Jim Mangan

CRM Homes BUILDER Mangan Drafting Jim Mangan BACK ELEVATION 1/8" = 1' LEFT SIDE 1/8" = 1' RIGHT SIDE 1/8" = 1' ROOF LINE NTS FRONT VIEW 1/4" = 1' A-1 Springfield MO 65610 Fremont Hills Lot 57 12/12 12/12 14/12 14/12 12/12 12/12 12/12 MAIN ROOF PITCH

More information

Project Name: Enforcement Agency: Permit Number:

Project Name: Enforcement Agency: Permit Number: Installation (Page 1 of 4) If more than one person has responsibility for installation of the items on this certificate, each person shall prepare and sign a certificate applicable to the portion of construction

More information

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com Edouard Modern Living Made Easy uichomes.com - new construction - 3 stories + full basement - 4 bedrooms - 2.5 baths - 2,380 s.f. call 314.881.2333 or e-mail sales@uicstl.com PLAN NTS DECK 13' 0" X 12'-0"

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes 2014 British Columbia Building Code Changes A City of Prince George interpretation of the 2014 Building Code Changes for 9.32 & 9.36 The following changes reflect the most notable revisions and staff interpretations.

More information

Supplementary Standard SB-12. Energy Efficiency For Housing

Supplementary Standard SB-12. Energy Efficiency For Housing OBC Excerpt: SB 12 Ministry of Municipal Affairs and Housing Building and Development Branch 2006 Building Code - Supplementary Standards Supplementary Standard SB-12 Energy Efficiency For Housing November

More information

Not useable for compliance

Not useable for compliance Project Name: 1 Story Example Calculation Date/Time: 14:29, Wed, Sep 21, 2016 Page 1 of 8 GENERAL INFORMATION 01 Project Name 1 Story Example 02 Calculation Description 2100 ft2 CEC Prototype with tile

More information

Plan /Submission Requirements

Plan /Submission Requirements Plan /Submission Requirements As a result of the Code changes additional information will be required at the building permit application stage to ensure compliance with new 2012 BCBC requirements. This

More information

This Certificate of Compliance is not registered

This Certificate of Compliance is not registered Project Name: 2016 - Base w/ HPA Opt. A (R-8) Calculation Date/Time: 11:24, Tue, Jul 18, 2017 Page 1 of 8 GENERAL INFORMATION 01 Project Name 2016 - Base w/ HPA Opt. A (R-8) 02 Calculation Description

More information

2010 Residential Energy Checklist: Additions/Alterations (Prescriptive Approach)

2010 Residential Energy Checklist: Additions/Alterations (Prescriptive Approach) 2010 Residential Energy Checklist: Additions/Alterations (Prescriptive Approach) Component Less than equal to 100 sq. ft. Addition Less than equal to 1000 sq. ft. Addition Greater than 1000 sq. ft. Addition

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches and shall be sized to carry the applicable roof and

More information

This Certificate of Compliance is not registered

This Certificate of Compliance is not registered Project Name: 2016 - Base w/ HPA Opt. A (R-8) Calculation Date/Time: 12:04, Tue, Jul 18, 2017 Page 1 of 8 GENERAL INFORMATION 01 Project Name 2016 - Base w/ HPA Opt. A (R-8) 02 Calculation Description

More information

A. GENERAL INFORMATION

A. GENERAL INFORMATION STATE OF CALIFORNIA Prescriptive Residential Additions 300 Ft 2 or Less, or Additions That Do Not Require HERS Field Verification CEC-CF1R-ADD-05-E (Revised 06/14) CALIFORNIA ENERGY COMMISSION CERTIFICATE

More information

Boyle. contemporary new homes with great curb appeal. boyle call or 3br/2.5bth, 1905sf

Boyle. contemporary new homes with great curb appeal. boyle call or  3br/2.5bth, 1905sf Boyle Modern Living Made Easy uichomes.com contemporary new homes with great curb appeal 3br/2.5bth, 1905sf boyle call 314.881.2333 or email sales@uicstl.com DECK BEDROOM 3 SUMP BEDROOM 3 WIC FIN BDRM

More information

Building Envelope

Building Envelope 9.36.2. Building Envelope Module 2 BCBC 9.36. 2014 1 Richard Kadulski Architect 9.36.2. Building Envelope Focus is on total building performance, not just thermal insulation Heat transfer and air leakage

More information

Main Floor Plan Scale: 1/8"=1'-0"

Main Floor Plan Scale: 1/8=1'-0 16'-0" 1 6'-6" 1 36'-0" Future Deck 10'-6" 4'-11" 4'-11" 10'-6" 36'-0" Future Deck 1 6'-6" 1 16'-0" 6068 3030 3030 6068 1 20'-9 1/2" 20'-9 1/2" 1 D/W D/W 26'-4" 24'-8" 2'-0" '-4" '-4" '- 1/2" 20'-10 1/2"

More information

FLOOR PLAN SCALE: 1/8 = 1 0

FLOOR PLAN SCALE: 1/8 = 1 0 B 4 3 2 1 A MASTER SUITE 218 sq ft. BEDROOM 01 144 sq ft. BEDROOM 02 144 sq ft. 1400 gross square feet 1336 net square feet 3 bedrooms, 2 baths 30 x 110 lot dimensions 24 x 72 footprint KITCHEN / DINING

More information

Program: Home and professional studio Option for air b-n-b rental Living space on upper level to improve lake views Desire for cathedral ceiling space

Program: Home and professional studio Option for air b-n-b rental Living space on upper level to improve lake views Desire for cathedral ceiling space Program: Home and professional studio Option for air b-n-b rental Living space on upper level to improve lake views Desire for cathedral ceiling space LAKE DUNMORE GOALS, INSPIRATION & CONSTRAINTS 0'-"

More information

HOUSE ADDITIONS A guide to the plans required when applying for a Building Permit

HOUSE ADDITIONS A guide to the plans required when applying for a Building Permit PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT HOUSE ADDITIONS A guide to the plans required when applying for a Building Permit November 2017 contents Introduction... 3 Site Plan... 4 Floor Plan... 6 Foundation

More information

ADDITIONS BUILDING AND ZONING REQUIREMENTS (REVISED 4/22/2008)

ADDITIONS BUILDING AND ZONING REQUIREMENTS (REVISED 4/22/2008) ADDITIONS BUILDING AND ZONING REQUIREMENTS (REVISED 4/22/2008) PERMIT SUBMITTAL CHECKLIST: Signed completed Building Permit application form. Two (2) Copies of a Certificate of Survey. Draw to scale the

More information

DESIGN SUMMARY: Shadow Trail. Passive Solar, Forest Meadow Home. Conceptual Drawings

DESIGN SUMMARY: Shadow Trail. Passive Solar, Forest Meadow Home. Conceptual Drawings DESIGN SUARY: 1) The owners will live in this home located in the forest east of ount Elden full time. 2) The home's primary heating and cooling will be accomplished using passive solar principles; sunshine

More information

National Grid Deep Energy Retrofit Pilot Program Comprehensive DER of Three-Family Triple Decker

National Grid Deep Energy Retrofit Pilot Program Comprehensive DER of Three-Family Triple Decker Case Study National Grid Deep Energy Retrofit Pilot Program Comprehensive DER of Three-Family Triple Decker Jamaica Plain, Massachusetts Project Profile Overview This triple decker, built in 907, was purchased

More information

WeatherSmart Air Barrier Installation Guide

WeatherSmart Air Barrier Installation Guide WeatherSmart Air Barrier Installation Guide 1 The intent of this document is to provide a guide for the installation of WeatherSmart as both a Weather Resistive Barrier (W.R.B.) and an Air Barrier Material

More information

Values That Matter PLAN CERTIFICATION WORKSHEET

Values That Matter PLAN CERTIFICATION WORKSHEET Values That Matter PLAN CERTIFICATION WORKSHEET Builder Name: Main Floor: sq. ft. Plan Name/Number: Upper Floor: sq. ft. Contact Person: Total: sq. ft. Phone: Email: For any item labeled as (option), you

More information

ENCLOSURE: SIMPLE LAYERS

ENCLOSURE: SIMPLE LAYERS ENCLOSURE: SIMPLE LAYERS THE BEST RESIDENTIAL WALL ASSEMBLY Brick Face/ cavity/ impermeable membrane as drainage plane Impermeable foam as insulation 1 Moisture Movement through Air Leakage vs. Diffusion

More information

Inspection of New One- and Two- Family Dwellings

Inspection of New One- and Two- Family Dwellings Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Inspection of New One- and Two- Family Dwellings Planning and Development

More information

Chapter Four: Green Remodeling Illustrations

Chapter Four: Green Remodeling Illustrations Chapter Four: Green Remodeling Illustrations We believe that homeowners deserve a home that is not only beautiful, but one that is more energy-efficient, comfortable and healthier for the family. Fred

More information

Z & C Construction, Inc. Subdivision:

Z & C Construction, Inc. Subdivision: : Buyer(s): Address: Lot: Block: Model: Subdivision: A. Foundations Unfinished basement or crawlspace included per buyer selection (extra fees may apply) Engineered concrete foundation Perimeter drainage

More information

One and Two Family Additions

One and Two Family Additions One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri

More information

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw RESIDENTIAL CONSTRUCTION DETAILS U.S. EDITION A visual guide to construction detailing Emma Walshaw Contents INTRODUCTION 4 PRINCIPLES OF CONSTRUCTION DETAILING 6 FOUNDATIONS 9 PRINCIPLES OF FOUNDATION

More information

Work Order (Bid Form) Upper East Tennessee Human Development Agency

Work Order (Bid Form) Upper East Tennessee Human Development Agency Upper East Tennessee Human Development Agency WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10620 CLIENT INFORMATION Address: FALL BRANCH, TN 37656 AGENCY INFORMATION Agency:

More information

Up Hill House. Cambridge, New York. Title: Cover. Scale: NA. Date: 19-Apr-2010 A-0

Up Hill House. Cambridge, New York. Title: Cover. Scale: NA. Date: 19-Apr-2010 A-0 ambridge, New York Up Hill House over cale: NA A-0 1"=500' 43 Latitude Elevation: Approx. 820' 202' Approx. 100' radius Proposed House ite ambridge, New York Perc test hole Proposed Garage Proposed Barn

More information

Willowbend. Model Coming Soon Price range: $268k-$354k. For More Information. Will Conrad Sales Consultant

Willowbend. Model Coming Soon Price range: $268k-$354k. For More Information. Will Conrad Sales Consultant Willowbend Model Coming Soon Price range: $268k-$354k Centrally located with easy access to the Downton and Highway 90 Community will feature a brick wall around the community with gorgeous landscaping

More information

Town of Pawling Residential Building Permit Application

Town of Pawling Residential Building Permit Application Town of Pawling Residential Building Permit Application Property Address: Street: City: Zip: Grid Number: Zoning District: Project Description: Owners Name: Phone: H W/C Address: Street: City: State: Zip:

More information

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016 CHEBOYGAN COUNTY DEPARTMENT OF BUILDING SAFETY 870 South Main Street P.O. Box 70 Cheboygan, Michigan 49721 Phone: (231) 627-8813 Fax: (231) 627-8454 www.cheboygancounty.net 2015 MICHIGAN UNIFORM ENERGY

More information

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process NC Energy Code Requirements ENERGY STAR and NC Energy Code in Alignment RESNET Standards HERS Index A scoring

More information

Town of Pawling Residential Building Permit Application

Town of Pawling Residential Building Permit Application Town of Pawling Residential Building Permit Application Property Address: Street: City: Zip: Grid Number: Zoning District: Project Description: Owners Name: Phone: (H) (W) Address: Street: City: State:

More information

A Closer Look Inspection Service 2015 IECC Residential DFW area handout

A Closer Look Inspection Service 2015 IECC Residential DFW area handout 103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted

More information

Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4)

Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4) Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4) A. QUALITY (QII) PREPARATION FOR INSULATION 01 Air barrier installation and preparation for insulation was done and verified

More information

SpacePak Manual J Load Analysis Project Sheet

SpacePak Manual J Load Analysis Project Sheet SpacePak www.spacepak.com Telephone: (413) 564-5530 Fax: (413) 564-5815 e-mail: presalesupport@spacepak.com This PDF has pull-down menus and text boxes that can be completed on your computer and either:

More information

AIR LEAKAGE REPORT. Blower door test Whole House Infiltration

AIR LEAKAGE REPORT. Blower door test Whole House Infiltration AIR LEAKAGE REPORT Date: March 12, 2009 Rating No.: CET7380 Building Name: unit 10 left Rating Org.: CET Owner's Name: RDI, Inc. Phone No.: 413 586 7350 Property: 35 Solar Way Rater's Name: Jonathan Bates

More information

2013 COMMERCIAL PRODUCTS

2013 COMMERCIAL PRODUCTS 2013 COMMERCIAL PRODUCTS EXPLORE GEOMETRY AND SPACE WITHOUT COMPROMISING BUILDING ENVELOPE PERFORMANCE Commercial design considerations come with very specific challenges that can t be addressed with just

More information

EXW3 EXISTING DOWEL NEW FOOTING TO EXISTING WALL WITH 3-15M DOWELS, DOWEL THE NEW

EXW3 EXISTING DOWEL NEW FOOTING TO EXISTING WALL WITH 3-15M DOWELS, DOWEL THE NEW -4 /4" 8" 4'-9 /" 6'-4" '-8" DEPRESS TO ACCOMODATE DOOR ABOVE DOWEL NEW FOOTING TO WITH 3-5M DOWELS, DOWEL THE NEW S TO THE S WITH 5M @ 4" O.C. VERTICALLY, PROVIDE -5M BARS 6" LONG IN THE FOOTING 4'-9"

More information

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209) City of Hughson Building Safety Division 7018 Pine Street Hughson, CA 95326 (209) 883-4054 RESIDENTIAL ATTACHED PATIO COVERS Patio covers are one story roofed structures not more than 12 feet above grade,

More information

Customer A101. Front Elevation. Roof Peak 24' /32" Roof 17' - 6" Main Floor 9' - 6" Floor Joist 8' - 6" Basement 0' - 6" Grade 0' - 0"

Customer A101. Front Elevation. Roof Peak 24' /32 Roof 17' - 6 Main Floor 9' - 6 Floor Joist 8' - 6 Basement 0' - 6 Grade 0' - 0 /300 ROOF VENTILATION REQUIRED TYPICAL ROOF OVERHANG '-6" 2 7 Peak 24' - 9/32" 7' - 6" 9' - 6" Floor Joist Grade 0' - 0" Front Elevation 24"x8" STRIP. FOOTING (TYP.) MIN. 42" HIGH GUARD AROUND DECK (TYP.)

More information

Green Points Rating System for Remodeling Projects Due to the diversity of remodeling project types, assigning a "total points" value to a project to be considered environmentally friendly is not feasible.

More information

Thermal Bridging in Residential Construction

Thermal Bridging in Residential Construction PHRC Webinar Series Tuesday, May 12, 2015 @ 1pm Thermal Bridging in Residential Construction Brian Wolfgang Housing Systems Specialist Pennsylvania Housing Research Center 219 Sackett Building University

More information

About Insulation & R Value - cmhc.ca

About Insulation & R Value - cmhc.ca About Insulation & R Value - cmhc.ca Insulating Your House While previous generations may have been content to live in drafty houses, most people now want comfortable warm houses. A healthy house today

More information

Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort

Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Please add relevant logo here Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Presented by: Peter J. Arsenault, FAIA, NCARB, LEED-AP Disclaimer: This presentation was developed by

More information

5. SANDSTONE, ELLENDALE, DE

5. SANDSTONE, ELLENDALE, DE 5. SANDSTONE, ELLENDALE, DE 5.1 Executive Summary Gate 3 Community: Sandstone, Colter Construction, Ellendale, DE Overview Key Results Gate Status Table 5.1.1: Stage Gate Status Summary Must Meet Gate

More information

Ducts in Conditioned Space High Performance Attics

Ducts in Conditioned Space High Performance Attics 2016 Title 24 Codes & Standards Enhancement (CASE) Proposal Ducts in Conditioned Space High Performance Attics May 8, 2014 Matt Christie (TRC) Abhijeet Pande (TRC) Stakeholder Meeting: Agenda Code change

More information

Not useable for compliance

Not useable for compliance Project Name: ACM Tests Calculation Date/Time: 15:40, Thu, Jul 07, 2016 Page 1 of 9 GENERAL INFORMATION 01 Project Name ACM Tests 02 Calculation Description CEC Prototype 03 Project Location 1516 Ninth

More information

1 BASE HOME CONSTRUCTION SPECIFICATIONS: TOWNHOMES 5-13-2015 Note: Specifications noted below may change based on selected options. Verify upgrades from the base specifications with the option sheets and

More information

1.1 BUILDING DESCRIPTION:

1.1 BUILDING DESCRIPTION: 1.1 BUILDING DESCRIPTION: Location: 2958 Princess Ave, North Vancouver, BC Building Type: Single Family Residential - Retrofit Certification Type: EnerPHit Year of Construction: 2017 Gross Floor Area:

More information

General Contractor: Company Name: Location of Proposed Structure: Tax Map #: Lot #:

General Contractor: Company Name: Location of Proposed Structure: Tax Map #: Lot #: New Hampshire Residential Energy Code Application Town of Sutton for Certification of Compliance for New Construction, Additions and/or Renovations to be submitted with completed building permit (EC-1

More information

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance www.epa.gov/iaq/moisture Foundations Issue Building foundations are vulnerable to moisture problems for a number of reasons, including: Water from rain and from plumbing leaks is drawn by gravity to foundations,

More information

Overview. Historic Preservation Meets Building Science: The Mallett Deep Energy Retrofit. R-Value Targets. The Mallett Deep Energy Retrofit

Overview. Historic Preservation Meets Building Science: The Mallett Deep Energy Retrofit. R-Value Targets. The Mallett Deep Energy Retrofit Kohta Ueno Historic Preservation Meets Building Science: Overview 2 The design decision process for how the team chose assemblies and details Energy efficiency, durability, constructability R-Value Targets

More information

Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011

Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011 Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011 S D E S G r o u p 2 W a s h i n g t o n S t r e e t S u i t e 2 0 6 D o v e r, N H 0 3 8

More information

Appendix B. Certification of Intent to Comply

Appendix B. Certification of Intent to Comply Appendix B Certification of Intent to Comply Required: Submit this certification at time of application. The project applicant and project architect/project designer are required to sign the certification

More information

CERTIFICATE OF COMPLIANCE - RESIDENTIAL PERFORMANCE COMPLIANCE METHOD CF1R-PRF-01

CERTIFICATE OF COMPLIANCE - RESIDENTIAL PERFORMANCE COMPLIANCE METHOD CF1R-PRF-01 Project Name: Status Addition Calculation Date/Time: 15:10, Wed, Jul 06, 2016 Page 1 of 7 GENERAL INFORMATION 01 Project Name Status Addition 02 Calculation Description Addition 225 ft2 03 Project Location

More information

Inspection Report. Property Address:

Inspection Report. Property Address: Inspection Report provided by: Safe Side Home Inspection Inspector: Corey Stuart TN License # 778 434 Margaret Circle McMinnville, TN 37110 safesideinspection@blomand.net Property Address: 1234 Anywhere

More information

EXPLORE GEOMETRY AND SPACE

EXPLORE GEOMETRY AND SPACE COMMERCIAL PRODUCTS EXPLORE GEOMETRY AND SPACE WITHOUT COMPROMISING BUILDING ENVELOPE PERFORMANCE Commercial design considerations come with very specific challenges that can t be addressed with just any

More information

National Grid Deep Energy Retrofit Pilot Program Millbury Cape

National Grid Deep Energy Retrofit Pilot Program Millbury Cape Case Study National Grid Deep Energy Retrofit Pilot Program Millbury Cape Millbury, Massachusetts Overview This Cape Cod style house was built in 95. While the owners had made interior improvements and

More information