Second Avenue Subway. Quarterly Public Workshop. February 25, 2015

Size: px
Start display at page:

Download "Second Avenue Subway. Quarterly Public Workshop. February 25, 2015"

Transcription

1 Second Avenue Subway Quarterly Public Workshop February 25,

2 Current Project Status Overall Construction Progress is 78.7% complete as of 2/1/2015. All 10 SAS Contracts have been awarded for Phase 1 5 Construction Contracts Completed: Tunnel Boring Machine Tunneling 86 th St Excavation, Utility Relocation, and Road Decking 96 th St Site Work and Heavy Civil 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14) 86 th St Cavern Mining & Heavy Civil (12/16/14) MTA Capital Construction 2

3 Station Renderings 72 nd Street Platform Level 86 th Street Mezzanine - South 96 th Street Proposed Art Installation Artist Sarah Sze, MTA Arts & Design commissioned work Goto and click on Vision Gallery 63 rd Street Mezzanine Fare Array 3

4 Community Information Center & Community Tours 9,300 visitors to date 48 presentations to school groups with over 1,375 students attending New exhibit coming in March 2015 Community Tours- we have hosted 47 tours with 1,493 participants Hours Monday: 10AM - 6PM Tuesday: 11AM - 7PM Wednesday: 10 AM - 6PM Thursday: 11AM - 7PM Friday: 10AM - 6PM Saturday: 11AM - 3PM* Sunday: Closed Closed most public holidays *Open the second Saturday of every month. Opened July

5 96 th Street Station Area MTA Capital Construction 5

6 Above ground Ancillary 1 work at 93 rd Street January

7 96 th Street Ancillary 1 Rendering NE corner 93 rd Street and Second Avenue 7

8 60 Water Main Twin 42 Water Main Con Ed Electric 30 Gas Main 96 th Street Station Area - Utility Installation 93 rd 94 th Street & Second Avenue Looking South January

9 Backfill over Utilities 95 th 96 th Street and Second Avenue 9

10 86 th Street Station Area MTA Capital Construction 10

11 86 th Street Milestones Highlight Completed 96% of lower mezzanine slabs in cavern Dec. 16, 2014 Cavern Mining and Heavy Civil contract substantially completed Oct. 3, 2014 Completed dismantling of 86 th - 87 th Street Muck House Aug. 8, 2014 Completed casting of concrete arch ceiling April 10, 2014 Completed dismantling of 83 rd - 84 th Street Muck House Nov. 19, th Street Station Mezzanine and Platform Dec Looking North All blasting completed on contract and entire Phase 1 project 11 11

12 May 2014 Muck House removal at 86 th Street and Second Avenue October 3,

13 13 MTA Capital Construction 13 Yorkshire Building at 86 th Street and Second Avenue January 28, looking East

14 86 th Street Station Area New 20 foot sidewalks poured on 86 th Street between 1 st and 2 nd Avenues, East of Yorkshire building Looking east 14

15 72 nd Street Station Area MTA Capital Construction 15

16 72 nd Street Station Area New fence wrap installed in January between 69 th and 70 th Streets, looking south. MTA Capital Construction 16

17 72 nd Street Station Area Ancillary 2/Entrance 2 at northwest corner of 72 nd Street and Second Ave 17 17

18 72 nd Street Entrance 2 / Ancillary 2 Rendering NW corner 72 nd Street and Second Avenue 18

19 Ductwork Arch Ceiling Ventilation Ducts Electrical Conduits 72 nd Street Station - Mezzanine Public Area Looking North at 69 th Street 19

20 Lexington Ave / 63 rd Street Station Area MTA Capital Construction 20

21 Lexington Ave/63 rd Street Station Area Pre repair Post repair Looking east towards Third Ave Sidewalk repair 163 E. 63 rd Street MTA Capital Construction 21 Looking west towards Lexington Ave 21

22 Lexington Ave/63 rd Street Station Area Water treatment tanks removed from the eastside of Third Avenue between E. 62 nd and E. 63 rd Streets. 22

23 Lexington Ave/63 rd Street Station Station rehabilitation includes new track wall tiles, ceilings and lighting Lower Level Platform - February

24 Streetscape Visioning Process MTA Capital Construction 24

25 Streetscape Visioning Process MTACC wanted to give the community something better Numerous meetings, s and calls with city agencies, including DOT and Parks Community input solicited at a November 3 rd workshop Meeting with CB8 Second Avenue Subway Taskforce and CB11 Transportation Committee members to select streetscape components Full CB8 board meeting on February 18th MTA Capital Construction 25

26 Typical Pre-Construction Block MTA Capital Construction 26

27 Concept Rendering Post-Construction Block For conceptual purposes only. Placement and selection of specific street elements to be decided. MTA Capital Construction 27

28 City Light 28

29 Zelkova Street Trees: Large Canopy Linden Bald Cypress Sweetgum Red/bronze fall color One of the most common street trees Yellow fall color Strong pyramidal shape Orange/brown fall color Strong, yellow fall color 5-inch diameter trees will be used whenever possible 29

30 Street Trees: Columnar Form Fastigiata Oak Zelkova Musachino 30

31 Street Trees: Small Understory Serviceberry Japanese Tree Lilac Eastern Redbud Community Board committees decided to let Parks Department make decisions as appropriate 31

32 Rail Guards for Tree Pits MTA Capital Construction 32

33 City Benches MTA Capital Construction 33

34 Bicycle Rack MTA Capital Construction 34

35 Way-Finding Signage To be installed by DOT at SBS Bus Stops MTA Capital Construction 35

36 Second Avenue Subway distribution list: 36

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction Phase 1 Overview The Re-routed Q train will

More information

Second Avenue Subway (SAS) Project. Construction on Second Avenue. Interim Report. Prepared for: MTA Capital Construction.

Second Avenue Subway (SAS) Project. Construction on Second Avenue. Interim Report. Prepared for: MTA Capital Construction. Second Avenue Subway (SAS) Project Air Quality Monitoring Study of the 86 th Street Station Construction on Second Avenue Prepared for: MTA Capital Construction Prepared by: Parsons Brinckerhoff MTA Capital

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE February 15, 2011 SECOND AVENUE SUBWAY - PHASE 1 Scope: Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation. FACT SHEET GENERAL INFORMATION The project extends the existing No.7 Line subway service via a 1.5 mile extension from Times Square to the new 34 Street Hudson Yards station located at West 34th Street

More information

Second Avenue Subway Phase 2. NEPA Supplemental Environmental Assessment. Public Meeting. July 31, 2018

Second Avenue Subway Phase 2. NEPA Supplemental Environmental Assessment. Public Meeting. July 31, 2018 Second Avenue Subway Phase 2 NEPA Supplemental Environmental Assessment Public Meeting July 31, 2018 Purpose of Meeting Supplemental Environmental Assessment (EA) for Phase 2 Opportunity for public comments

More information

Progress update (November to March) 03/23/2009 2

Progress update (November to March) 03/23/2009 2 Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)

More information

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing OVERVIEW Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing Construction Liaison Group Nov 7th, 2013 1 WORKS IN PROGRESS Construction Liaison Group Nov 7 th, 2013

More information

SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY

SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY WEEK ENDING SEPTEMBER 14, 2018 SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY Contractor: Independence Excavating, Inc 1. Work Shift Day shift (M-F) with Saturday as a makeup day. 2. Traffic Candor

More information

MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0

MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0 MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, 2013 MTA Capital Construction 0 UPCOMING MTA CAPITAL CONSTRUCTION SOLICITATIONS Presented by David K. Cannon Sr. Director and Chief Procurement

More information

AGENDA ITEM J-3 Public Works

AGENDA ITEM J-3 Public Works AGENDA ITEM J-3 Public Works STAFF REPORT City Council Meeting Date: Staff Report Number: Informational Item: 8/22/2017 17-180-CC Update on the formation of the Transportation Master Plan Oversight and

More information

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School

More information

2. PROJECT DESCRIPTION

2. PROJECT DESCRIPTION 2. PROJECT DESCRIPTION This chapter presents the Proposed Project location and surrounding uses, project history, project description, and the estimated construction schedule and phasing. Briefly, the

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

nue Sub Secon nd Aven bway Phase

nue Sub Secon nd Aven bway Phase Q U A R T E R LY R E P OR T Secon nd Aven nue Sub bway Phase e1 2 Waterprooofing Ahead d of CIP Lineer West Tunnel Contrract C-26002 TABLE OF CONTENT Executive Summary ------------------------------------------------------------------------------------------------

More information

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Roosevelt Station Construction Kristin Hoffman, Station Project Manager Next Steps

More information

Description of Phase 2 Modified Design

Description of Phase 2 Modified Design Description of Phase Modified Design. INTRODUCTION This chapter provides an overview of the preliminary engineering design for Phase of the Second Avenue Subway that was evaluated in the Final Environmental

More information

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

GROUP DUTY ROSTER WITH MULTIPLE SHIFTS IN A DAY

GROUP DUTY ROSTER WITH MULTIPLE SHIFTS IN A DAY 1 1 GROUP DUTY ROSTER WITH MULTIPLE SHIFTS IN A DAY SUGGESTIONS & SOLUTIONS FOR TCMS V2 2 Conditions that requiring this feature: 1. More than 1 working shift. 2. Each working shift is clearly defined.

More information

\ Second Sem. B.Arch. (C.B.S) Winter 2018 (309) * * * * SECOND SEM. B. ARCH. EXAMINATION OF (CREDIT BASED SYSTEM) WINTER 2018 ---------------------------------------------------------------------------------------------------------------------------------------

More information

Construction Project Briefing. November 16, 2016

Construction Project Briefing. November 16, 2016 Construction Project Briefing November 16, 2016 Today s Presentation 95 th Street Terminal Improvement Program Wilson Transfer Station, Track, and Structure Reconstruction O Hare Line Addison, Irving Park,

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017 AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.:

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing April 2018 Study Purpose and Goals Initiated to address concerns about impacts resulting from cut-and-cover construction

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 21, 2008 SUBJECT: ISLINGTON STATION IMPROVEMENTS PROJECT - FINISHES ACTION ITEM: X INFORMATION ITEM: RECOMMENDATION It

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Trans Mountain Expansion Project Overview

Trans Mountain Expansion Project Overview Trans Mountain Expansion Project Overview 1 Proposed Expansion Project $6.8-billion capital cost Expand capacity to 890,000 bpd Project scope 980 kms new pipe 12 new pump stations 19 new tanks 3 new tanker

More information

Woodbine Station Upgrades

Woodbine Station Upgrades Community Update Danforth Mennonite Church 1 Easier Access Program Wide Committed to making all stations accessible by 2025 Almost half way there with 34 stations completed Working with the Advisory Committee

More information

Crenshaw/LAX Transit Project

Crenshaw/LAX Transit Project Crenshaw/LAX Transit Project Construction Update Community Meeting January 25 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

Appendix C. Gallery Place Chinatown Station Structural Assessment

Appendix C. Gallery Place Chinatown Station Structural Assessment Appendix C Gallery Place Chinatown Station Structural Assessment Washington Metropolitan Area Transit Authority February 2018 Gallery Place Chinatown Station Passageway RFI Contents APPENDIX C 1.0 Introduction:

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

2

2 CROSSTOWN LRT 2 3 4 5 6 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate and

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Construction Project Briefing. June 14, 2017

Construction Project Briefing. June 14, 2017 Construction Project Briefing June 14, 2017 Today s Presentation 95 th Street Terminal Improvement Program Wilson Transfer Station, Track, and Structure Reconstruction Ravenswood Loop Signals Upgrade Project

More information

\ Second Sem. B.Arch. (C.B.S) SUMMER 2018 (823) * * * * SECOND SEM. B. ARCH. EXAMINATION OF (CREDIT BASED SYSTEM) SUMMER 2018 -------- Time: - 9.30. A.M. To 12.30.P.M. Wednesday 02-05-2018 Construction

More information

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Second Avenue Subway - A Status Report

Second Avenue Subway - A Status Report CHRISTOPHER K. BENNETT Second Avenue Subway - A Status Report Christopher K. Bennett, P.E. DMJM Harris AECOM 20 Exchange Place New York, NY 10005 212 607 4167 917 670 5711 (cell) chris.bennett@dmjmharris.com

More information

Last Mile Freight Delivery: Cities and Logistics

Last Mile Freight Delivery: Cities and Logistics Last Mile Freight Delivery: Cities and Logistics Presented October 4, 2013 to University Transportation Research Center Region II Presented by Stacey D. Hodge, NYCDOT Office of Freight Mobility Outline

More information

1 April 8, 2015 Public Hearing

1 April 8, 2015 Public Hearing 1 April 8, 2015 Public Hearing APPLICANT: PROPERTY OWNER: CONTE ACQUISITIONS, LLC STAFF PLANNER: Kevin Kemp REQUEST: Conditional Use Permit (Craft Brewery) ADDRESS / DESCRIPTION: 1805 Laskin Road, Suite

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 08/12/2018 to 08/18/2018

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 08/12/2018 to 08/18/2018 AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN, WASHINGTON, DC. DC Contract No.:

More information

901 NEW YORK Avenue. Thesis Proposal. 901 New York Avenue. Washington, D.C. Advisor: Ali Memari Written by: Timothy H Park.

901 NEW YORK Avenue. Thesis Proposal. 901 New York Avenue. Washington, D.C. Advisor: Ali Memari Written by: Timothy H Park. Proposal 901 NEW YORK Avenue Washington, D.C. Advisor: Ali Written by: Timothy H Park Page 1 of 7 Executive Summary This report is a summary of design options for. is an 11-story building rising 130-0

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Indirect and Cumulative Effects

Indirect and Cumulative Effects Indirect and Cumulative Effects 19.1 INTRODUCTION This chapter discusses potential indirect and cumulative effects of the Modified Design, in comparison to the 2004 FEIS Design. The White House Council

More information

Metro Gold Line Eastside Extension Construction Update April 20, Gold Line

Metro Gold Line Eastside Extension Construction Update April 20, Gold Line Metro Eastside Extension Construction Update April 20, 2006 Metro Eastside Extension Project Overview 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At- Grade and 2 Underground) Park & Ride Facility

More information

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT PROJECT OFFICE PARK 7, SUITE 112, 4020 MINNESOTA AVENUE NE, WASHINGTON, DC 20019 MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S 12/11/2017 12/16/2017 12/14/2017 Minnesota Ave. NE Sta.

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority CALL FOR ARTISTS - PUBLIC ART CLIFTON ENHANCEMENT PROJECT CFA NO. 1-2014 Due Date: Friday, March 14, 2014 4:00 P.M. Official Time February 14, 2014 Prospective

More information

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006 Review Advisory Committee May 11, 2006 1 Ramona Opportunity High School/ Indiana Station Status 2 Ramona Opportunity High School/ Indiana Station Status 1. On April 19, 2006, Metro held an Indiana Station

More information

ACHD Bridge and Culvert Policy DRAFT

ACHD Bridge and Culvert Policy DRAFT ACHD Bridge and Culvert Policy DRAFT Standard Drawings and additional construction details are contained in the separate ACHD Bridge Design Guide and are hereto made part of this policy by reference. DEFINITIONS

More information

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014 Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Brooklyn Station Construction Open House

Brooklyn Station Construction Open House Brooklyn Station Construction Open House November 16, 2011 Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Louise Little, Greater University

More information

SAE Engineering Events Tabletop Rules & Display Reference Guidelines

SAE Engineering Events Tabletop Rules & Display Reference Guidelines SAE Engineering Events Tabletop Rules & Display Reference Guidelines The following Exhibitor Rules & Display Reference Guidelines have been established by SAE On-Board Diagnostics Symposium Show Management.

More information

Construction Update. November 2015

Construction Update. November 2015 Construction Update November 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 1 2

More information

Construction Project Briefing. March 9, 2016

Construction Project Briefing. March 9, 2016 Construction Project Briefing March 9, 2016 Today s Presentation 95 th Street Terminal Improvement Program Wilson Transfer Station, Track, and Structure Reconstruction O Hare Line Addison, Irving Park,

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

York City Special Events Sponsorship & Marketing Opportunities

York City Special Events Sponsorship & Marketing Opportunities York City Special Events 2019 Sponsorship & Marketing Opportunities Box Lunch Revue Olde York Street Fair Yorkfest Fine Arts Festival Labor Day York Bike Night Light Up York New Year s Eve Celebrate York

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Capital Program Oversight Committee Meeting

Capital Program Oversight Committee Meeting Capital Program Oversight Committee Meeting December 2015 Committee Members T. Prendergast, Chair F. Ferrer R. Bickford A. Cappelli S. Metzger J. Molloy M. Pally J. Sedore V. Tessitore C. Wortendyke N.

More information

Purple Line Extension. Construction Community Meeting March 16, 2017

Purple Line Extension. Construction Community Meeting March 16, 2017 Purple Line Extension Construction Community Meeting March 16, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking:

More information

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 INFORMATION IS CURRENT AS OF APRIL 19, 2018 AND SUBJECT TO CHANGE 2 Agenda Caledonia Station Update Fairbank Station Update Oakwood Station Update

More information

229 Rehoboth Avenue Telephone P.O. Box 1163 Fax

229 Rehoboth Avenue Telephone P.O. Box 1163 Fax Building & Licensing City of Rehoboth Beach 229 Rehoboth Avenue Telephone 302-227-6181 P.O. Box 1163 Fax 302-227-4504 Rehoboth Beach, Delaware 19971 www.cityofrehoboth.com NOTICE TO CONTRACTORS BUSINESS

More information

WHO IS METROLINX? PLAN BUILD OPERATE

WHO IS METROLINX? PLAN BUILD OPERATE CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 PROJECT: 300 Seneca New Academic Campus DATE: September 23, 2013 300 Seneca Ave., S.F.,

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

ROOSEVELT ISLAND OPERATING CORPORATION OF THE STATE OF NEW YORK DESIGN OF TWO NEW ELEVATORS FOR MANHATTAN TRAM STATION

ROOSEVELT ISLAND OPERATING CORPORATION OF THE STATE OF NEW YORK DESIGN OF TWO NEW ELEVATORS FOR MANHATTAN TRAM STATION ROOSEVELT ISLAND OPERATING CORPORATION OF THE STATE OF NEW YORK DESIGN OF TWO NEW S FOR MANHATTAN TRAM STATION 254 EAST 60th STREET, NEW YORK, NY 10022 PROJECT PROPOSAL Modernization of the Manhattan Aerial

More information

County of Santa Cruz

County of Santa Cruz County of Santa Cruz County Administrative Office 701 Ocean Street, Suite 520, Santa Cruz, CA 95060-4073 Phone:(831) 454-2100 Fax:(831) 454-3420 TDD/TTY: call 711 Carlos J. Palacios, County Administrative

More information

Transformer Vault Placement and Space Requirements

Transformer Vault Placement and Space Requirements Transformer Vault Placement and Space Requirements Consolidated Edison Company of New York, Inc. 4 Irving Place New York NY 10003 www.coned.com Transformer Vault Placement and Space Requirements Whether

More information

Soft Ground Tunneling through Contaminated Groundwater

Soft Ground Tunneling through Contaminated Groundwater 5 th Annual Technical Forum GEOHAZARDS IN TRANSPORTATION IN THE APPALACHIAN REGION Soft Ground Tunneling through Contaminated Groundwater Nasri Munfah P.E. and Subal Sarkar P.E. Parsons Brinckerhoff, New

More information

Construction Project Briefing. November 14, 2012

Construction Project Briefing. November 14, 2012 Construction Project Briefing November 14, 2012 Today s Presentation Loop Track Purple Line Viaducts North Red Line Stations 2 Project Title: Loop Track Renewal Project Managing Department: Power & Way

More information

Sponsorship Program Catalog

Sponsorship Program Catalog 2009 Sponsorship Program Catalog The Flatiron/23rd Street Partnership is soliciting sponsorship funds from corporations, universal brands, local property owners, restaurants, and retailers that will help

More information

YORK CITY SPECIAL EVENTS

YORK CITY SPECIAL EVENTS YORK CITY SPECIAL EVENTS MARKETING & SPONSORSHIP OPPORTUNITIES Box Lunch Revue Olde York Street Fair Yorkfest Fine Arts Festival Labor Day Bike Night Light Up York New Year s Eve Celebrate York City with

More information

District of Ucluelet Building Permit Guide

District of Ucluelet Building Permit Guide District of Ucluelet Building Permit Guide The purpose of this guide is to advise on the applicable regulations within the District of Ucluelet regarding construction, repairs, alterations or additions

More information

Single Family Residential Building Permit Questions & Answers

Single Family Residential Building Permit Questions & Answers City Of Edwardsville Public Works Department 200 East Park Street Edwardsville, IL 62025 (618)692-7535 (618)692-7505 Fax Hours: Monday thru Friday 8:00 AM to 5:00 PM Single Family Residential Building

More information

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

CROSSTOWN LRT Construction Liaison Committee November 1, 2017 CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole

More information

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT PROJECT OFFICE PARK 7, SUITE 112, 4020 MINNESOTA AVENUE NE, WASHINGTON, DC 20019 MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT 12/04/2017 12/09/2017 12/07/2017

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/23/2016 to 10/29/2016

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/23/2016 to 10/29/2016 AECOM Field Office Water Street, NW Under Key Bridge along Water Street, NW REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.: DCKA-2014-C-0074

More information

LITHIA ARTISANS MARKET HANDBOOK. P.O Box 3585 Ashland, OR

LITHIA ARTISANS MARKET HANDBOOK.   P.O Box 3585 Ashland, OR LITHIA ARTISANS MARKET HANDBOOK www.lithiaartisansmarket.com P.O Box 3585 Ashland, OR 97520 1-888 303 2826 " Welcome to the Lithia Artisans Market This handbook is designed to assist you in getting to

More information

Construction Update. July 2015

Construction Update. July 2015 Construction Update July 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 2014 2015

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #15

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #15 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #15 Date: January 29, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org On January

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Construction Project Briefing. July 11, 2018

Construction Project Briefing. July 11, 2018 Construction Project Briefing July 11, 2018 Today s Presentation ELMI East Lake, Milwaukee, Illinois Substation Upgrade Ravenswood Loop Signals Upgrade Project 95 th Street Terminal Improvement Program

More information

WHO IS METROLINX? PLAN BUILD OPERATE

WHO IS METROLINX? PLAN BUILD OPERATE CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)

More information

L Project Update. New Design Recommendations Overall Project Update. January 15, 2019

L Project Update. New Design Recommendations Overall Project Update. January 15, 2019 L Project Update New Design Recommendations Overall Project Update January 15, 2019 Project Overview Sandy Rehabilitation, Core Capacity Improvement, Additional Projects Brooklyn Union Sq Station 1 Av

More information

The Times Leader 2018 MEDIA KIT. 200 South Fourth Street, Martins Ferry, OH

The Times Leader 2018 MEDIA KIT. 200 South Fourth Street, Martins Ferry, OH The Times Leader 2018 MEDIA KIT 200 South Fourth Street, Martins Ferry, OH 43935 740-633-1131 www.timesleaderonline.com Our Mission The Times Leader has built a large, local audience serving Belmont county

More information

Informational Outreach Meeting

Informational Outreach Meeting NOTICE The information presented at the MTA System Expansion Industry Outreach on September 12, 2006 and provided herein is intended to provide general information about upcoming MTACC projects. It is

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

Transportation Asset Management Webinar Series

Transportation Asset Management Webinar Series Transportation Asset Management Webinar Series Webinar 34 Integrating PM2 Targets with the TAMP Sponsored by FHWA and AASHTO Webinar 34 October 10, 2018 FHWA-AASHTO Asset Management Webinar Series This

More information