Eglinton Crosstown LRT Construction Liaison Committee
|
|
- Kathleen Tucker
- 5 years ago
- Views:
Transcription
1 Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017
2 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated Guideway Tunnel Fit Out Keelesdale Station Caledonia Station 2
3 Eglinton Crosstown LRT A 19-kilometre route separated from regular traffic 10-kilometres underground in west and central areas; 9-kilometres at surface in east 15 underground stations and 10 surface stops A maintenance and storage facility Transit communications system Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station 3
4 Eglinton Crosstown LRT: Key Milestones 74 Months Substantial Completion Ready for Testing and Commissioning March LRV Delivery Dates November EMSF Ready 1 st LRV Delivery October Contract signed and Mobilization July
5 Maintenance & Storage Facility Concept: Aerial View Vehicle Cleaning Staff Building 2. Vehicle Cleaning & Inspection Facility (VCIF) *60% rendering 3. Maintenance Building 4. Operations Control Center 5. Operations Company (OPSCO) 5
6 Eglinton Progress Maintenance to Date EMSF and Storage Facility Maintenance Building foot print Train Wash Staff Building 6
7 Progress to to date: Date EMSF EMSF Environmental & geotechnical testing Foundations for Maintenance, OPSCO, Vechile Cleaning and Staff Buildings Site services dry/wet utilities (ongoing) Steel erection for Maintenance Building (started) 7
8 Mount Dennis Concept: Aerial View Bus Loop 2. Main Entrance 3. Second Entrance 4. Building 9 Third Entrance 5. Maintenance Building 6. Operations Company 7. New Photography Drive Bridge 8. Rail Corridor *60% rendering 8
9 Mount Dennis Station No. 9 Building CP Rail Station Box Secondary Entrance 9
10 Progress to date: Mount Dennis Station Foundations Mount Dennis station box concrete structure main entrance (ongoing) Site services water main, sanitary and storm sewer placement Building 9 foundation 10
11 West Portal & Elevated Guideway 11
12 Progress to date: West Portal & Elevated Guideway 2000 m3 reinforced concrete poured to date Ongoing Walls and roof formwork and rebar box tunnel construction Utility relocation works for Elevated Guideway To follow: Retaining wall and backfilling for Eglinton Avenue West realignment 12
13 Tunnel Fit Out Invert Pour With the completion of the tunnel boring, we now start the next step for work in the tunnels with pouring of concrete slabs to invert or flatten the tunnel floor. This must occur prior to the installation of track and transit systems. Concrete slab to be poured 13
14 Tunnel Fit Out Concrete Pour Overview Concrete trucks deliver concrete every minutes, depending on how far down the tunnel the work is occurring Trucks park beside the shaft at Cedarvale (Allen Rd. and Eglinton), and unload 9 m 3 of concrete into a large pipe, into one of two mini concrete trucks (4.5 m 3 each) at the shaft floor. The mini truck in the shaft then drives down the tunnel to the next section of tunnel to be inverted. The first stage of concrete pour began in tunnel section 1 on April 4, 2017, and tunnel section 2 on April 17, On average, crews complete a section approximately 80 metres in length of the concrete slab per day in each tunnel. 14
15 Tunnel Invert Pour Stage 1 Concrete trucks deliver loose concrete to the work area Loose concrete mix is used to fill the bottom of the tunnel Tunnel Fit Out Crew flatten and smooth it 15
16 Tunnel Invert Pour Stage 2 Workers install welded mesh which functions like rebar to help reinforce the next layer of concrete Higher strength concrete is poured to provide the flat track slab for the rail tracks Workers spread the concrete, and a truss screed machine vibrates it into a perfectly level surface 16
17 Keelesdale Concept: Aerial View Main Entrance 2. Third Entrance 3. Second Entrance 4. Traction Power Substation (TPSS) 5. Bus Loop 17
18 Keelesdale Station Main Entrance Third Entrance Secondary Entrance TPSS Building 18
19 Progress to date: Keelesdale Station First station to start construction in March 2016 Utility relocations Shallow Excavation complete on the North Side of intersection Excavation at the Traction Power Substation (TPSS), third & main entrance North side major utility support beams installed North east side deck beams and timber mat installation All lanes to re-open to east and westbound traffic end May
20 Caledonia Station Construction Update Complete Installation of geotechnical monitoring equipment Hydro utility relocation work Bell utility relocation Traffic signal relocation at Blackthorn Ave and Eglinton Ave W Piling of the station box Installation of dewatering system Shallow excavation to first round of tie-backs Installation of first round lagging, tie-backs, braces and walers Tower crane erection Spring/Summer 2017 Site service connection to wet utilities (one month) Dewatering (ongoing) Deep excavation (8 months) Monitoring of geotechnical instruments (ongoing)
21 Current Construction Staging Began May 29 for 1.5 weeks 21
22 Current Construction Staging Beginning June 8 for two (2) weeks 22
23 Caledonia Station Aerial Concept 23
24 Caledonia Station Construction Progress Drilling Tie-backs Pile Installation 24
25 Caledonia Station Construction Progress Hauling Spoils Trenching for Dewatering Tower Erection 25
26 Thank you! For more information about the Eglinton Crosstown LRT please visit:
2
CROSSTOWN LRT 2 3 4 5 6 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate and
More informationWHO IS METROLINX? PLAN BUILD OPERATE
CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)
More informationCROSSTOWN LRT Construction Liaison Committee November 1, 2017
CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole
More informationCROSSTOWN LRT Science Centre June 15, 2017
CROSSTOWN LRT Science Centre June 15, 2017 WHO IS METROLINX? 2 3 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year,
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationEGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018
EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 INFORMATION IS CURRENT AS OF APRIL 19, 2018 AND SUBJECT TO CHANGE 2 Agenda Caledonia Station Update Fairbank Station Update Oakwood Station Update
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,
More informationWHO IS METROLINX? PLAN BUILD OPERATE
CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationWelcome to the Online Consultation
Welcome to the Online Consultation Western Alignment & Vehicle Maintenance & Storage Facility Update Please review the presentation and complete the survey by July 10, 2012. 1 Format for Feedback Please
More informationWELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION
WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION Relief Line Study Area and Process Relief Line Project Assessment Primary Study Area Background 2009 City Council
More informationCOMMUNITY BOARD EIGHT
SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationFleet Elementary School
Fleet Elementary School Community Newsletter () This is the February update on the status and progress of construction for the project. All monthly updates will also be posted to the project website and
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationThe Construction of the Langham Place in Mong Kok An Introduction
The Construction of the Langham Place in Mong Kok An Introduction Artist Impression of Langham Place r o j e c t c o m p r i s i n g a i l / h o t e l c o m p a n o f f i c e / r e t Fast Fact The site
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr
More informationCommunity Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018
1 Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018 Community Meeting Overview Introductions (5 minutes) TTC, City of
More informationConstructability Guidelines
Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million
More informationProgress update (November to March) 03/23/2009 2
Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million
More informationPurple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction
More informationRegional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting
Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationPROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012
PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375
More informationSeven Wonders of the Ancient World
Seven Wonders of the Ancient World Pyramid of Meidum shed 250,000 tons of limestone outer casings Typical Pyramid Pyramid at Meidum Mexico Alameda buildings Palace of Fine Arts National Theater
More information4.0 CONSTRUCTION METHODS AND ACTIVITIES
4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationDESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION
DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION INTRODUCTION By Dawn Tattle, P. Eng. Anchor Shoring & Caissons Ltd. TTC Yonge Station is the largest and most complicated of the
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion
More informationGautrain construction update
Month end 30 April 2008 Gautrain construction update SOUTHERN SECTION Underground section Park Station Excavation of the single-track rail tunnel towards Emergency Shaft 2 in Houghton has reached approximately
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationDESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.
DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change
More informationJobsite Layout Considerations
1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration
More informationEastside Transit Corridor Phase 2
Eastside Transit Corridor Phase 2 Community Meeting, June 22, 2016 Page 1 Purpose of Tonight s Meeting Page 2 Update on Metro Board directed Technical Study (Nov. 2014) SR-60 Alternative Washington Blvd
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More informationTrenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions
Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions Case Study Trevor Kealey, P.Eng. R.V. Anderson Associates Limited TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention
More informationDETROIT RIVER INTERNATIONAL CROSSING STUDY MAG
DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG Meeting September 5 th, 2006 1 Agenda 1. Study Update 2. Construction Staging for Tunneling 3. Other Business 2 Deep Borehole Program 3 Status Update - Engineering
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationPurple Line Extension. Beverly Hills Community Meeting August 22, 2016
Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section
More informationThe Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok
The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District
More informationStructural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options
Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More informationIndex to Technical Specifications
Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation
More informationDulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868
More informationAn Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System
An Introduction to Metal Foundation System By Michael L. Schumaker, P.E. Introduction Various types of deep foundations are routinely used to support structures. Selection of the appropriate type of deep
More informationConstruction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk
Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk Presented by Raymond Wong Wai Man, Division of Building Science & Technology, City University of Hong Kong Raymond
More informationCWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending March 2, 2013
CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending March 2, 2013 RIVER DIVERSION SEGMENT At the first of the week, Spindler stripped the wall forms off of the 100 cy pour that was placed toward at the
More informationNew Main Hospital, Site Park, and Underground Garage Construction Progress Update #15
New Main Hospital, Site Park, and Underground Garage Construction Progress Update #15 Date: January 29, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org On January
More informationAndy Kirby. Prepared for: Senior Project Manager for The Church of Jesus Christ of Latter-day Saints. April Graduate Mentor: Andrew Luna
Prepared for: Andy Kirby Senior Project Manager for The Church of Jesus Christ of Latter-day Saints April 2015 Graduate Mentor: Andrew Luna PROVO, UT Department of Civil & Environmental Engineering Ira
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationIntroduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring
Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot
More informationHUDSON TUNNEL PROJECT
HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen
More informationJohn Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53
John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationCTA Capital Construction Update August 8, 2007
Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block
More informationPresented by: Frank Guyamier
FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal
More informationHamilton Rapid Transit Preliminary Design and Feasibility Study
Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT
More informationChuck Brooks, P.E., P.Eng. C&S Engineers
Chuck Brooks, P.E., P.Eng C&S Engineers 315-455-2000 cbrooks@cscos.com AGENDA INTRO BASICS KEY CONSIDERATIONS DESIGN CONSTRUCTION Questions to be Explored 1. Concrete Tiltup Panels are designed for the
More informationTechnical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction
Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ 739.6 Million Total
More informationWoodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017
Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.
More informationStructural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/
120 Montgomery Street, Suite 1410 San Francisco, California 94104 415/781-1505 Fax 415/781-2718 sde@sdesf.com Rajendra Sahai, SE Principal John W. Laws, SE Principal Steven Lepisto, SE Principal STRUCTURAL
More informationWestside Purple Line Extension Section 1 Project Overview
Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension (WPLE) Section 1 Project Purple Line Project Alignment The WPLE corridor traverses portions of three jurisdictions,
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total
More informationProject Status Report
Project Status Report Date: Friday 3 June 2016 The Project Construction of a two level 116 bed hospital. Current Status Works carried out this week: Tie reo bar to stair and lift shaft walls Close off
More informationProject: King Abdulaziz International Airport KAIA 2
Project: King Abdulaziz International Airport KAIA 2 Jeddah, KSA King Abdulaziz International Airport Phase 1 Development Project Project Newsletter Client / Owner: Saudi Binladin Group 22 June 2013. Newsletter
More informationCOMMUNITY BOARD EIGHT
SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE February 15, 2011 SECOND AVENUE SUBWAY - PHASE 1 Scope: Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and
More informationFormwork being erected
CONCRETE FORMWORK Formwork being erected Most of the pads and concrete footing poured Formwork for the parkade walls is built for each pour Most of the parkade walls been completed 2 TYPES OF FORMWORK
More informationTCC Systems. Timber-Concrete Composite TIMBER IMAGINEERING INNOVATIVE TIMBER SOLUTIONS
TCC Systems Timber-Concrete Composite TIMBER IMAGINEERING INNOVATIVE TIMBER SOLUTIONS INTRODUCTION Timber-Concrete Composite (TCC) is an innovative structural system that maximizes the structural advantage
More informationCAC Meeting Construction Update April 8, 2014
CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,
More informationVTA s BART Silicon Valley Phase II Extension
VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods
More informationSection 4 - Design and Construction Overview
Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First
More informationCapital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager
Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.
More informationTRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT
P a g e 0 Prepared for: Trinity Development Group, Inc. TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT OTTAWA, ON November 2016 P a g e 1 TABLE OF CONTENTS
More informationGround Freezing for Tunnel, Shafts, and Adits
Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction
More informationReview of Plans and Specs from a Constructability Perspective
Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability
More informationKiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project
South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationWestside Subway Extension
Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives
More informationUNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer
More informationESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA
ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek
More informationJohn Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47
John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationTechnical Report #2. Matthew R Peyton
Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study
More informationTilikum Crossing Transit Bridge. Portland, OR
Tilikum Crossing Transit Bridge Portland, OR Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The
More informationElevated Slab Sequence
Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)
More informationConstruction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay
Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay External view of Manulife Tower from various location Block plan showing the building layout of the new
More informationJohn Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48
John Hart Generating Station Replacement Project June 2017 Community Construction Update Report #48 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationPrevious Tunnel News
Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above
More informationNew Reclaim Tunnel at Coal Fired Plant
Omaha SAME Post Monthly Meeting 10 July 2014 New Reclaim Tunnel at Coal Fired Plant By: Steve Morrissette Zapata Incorporated Omaha, NE Coal Fired Power Plant Generating capacity: 2,090 megawatts base
More information