Purple Line Extension. Construction Community Meeting March 16, 2017

Size: px
Start display at page:

Download "Purple Line Extension. Construction Community Meeting March 16, 2017"

Transcription

1 Purple Line Extension Construction Community Meeting March 16,

2 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking: Phase I,II, III, Detours, Outreach and Communication La Cienega K-Rail and Pile Installation Safety Eat Shop Play Wilshire Business Interruption Fund Question & Answers 2

3 Purple Line Extension Project Alignment 3

4 Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Under Construction Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles 2.59 Miles 2.48 Miles New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital Pre-Construction Activities Current * Construction * * Operations * 2035* 4

5 Purple Line Extension Section 1 Alignment 5

6 Purple Line Maintenance Facility 590 S Santa Fe Avenue Located in the Arts District, near 6 th St Bridge Initial excavation and grading ongoing Sanitary sewer and storm drain relocation continues March Design of Building 61S continues Artists selected Design Advisory Group Advisory group composed of Arts District leaders and artists to review and provide input on building s exterior design Next Meeting: March 22, 2017 Sewer pipe line installed at Santa Fe Av / Palmetto St - complete 6

7 Wilshire/Western Station Tie-in Western Staging Yard Northeast corner of Wilshire Bl and Manhattan Pl one block west of Western Av Soundwall construction substantially completed Remaining work includes adding new banners and widening of driveways Western Yard used intermittently for storage Current Work Jet grouting began February 2017 along: Wilshire Bl between Bronson Av and Wilton Pl Wilshire Bl between Gramercy Pl and Western Av K-rail (concrete barriers) installed; intermittent (off peak) lane reductions and eastbound Wilshire Bl closures on weekends Jet grouting anticipated will require 8 to 12 weeks to complete Median removal and repaving completed 7

8 Jet grouting set-up at Wilshire Bl/Wilton Pl 8

9 Crenshaw Yard Staging Site Wilshire/Crenshaw Mitigation efforts and maintenance: Banners replaced with durable vinyl Lorraine Gate temporarily closed until further notice Recent maintenance included graffiti removal, debris removal and trimming of vines Yard used for storage of materials New banners on east side of Crenshaw Yard 9

10 Wilshire/La Brea Station 10

11 Wilshire/La Brea Station Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St 11

12 Wilshire/La Brea Station Schedule *As of March 2017, subject to change 12

13 Wilshire/La Brea Station Staging Yards Staging Yard Activities and Equipment Sound wall is ft high Yard usage hours is 24/7 Yard will be used for: Maintenance of equipment Deliveries of materials Removal of excavated soil Mitigations Must comply with City of Los Angeles noise requirements Noise Control Signage Low Impact Back up alarms Acoustical Insulation Metro 5 Step Noise Plan 13

14 Wilshire/La Brea Station: installing ventilation ducts in south shaft, looking west 14

15 Pulling ventilation pipes to west end of Wilshire/La Brea Station, looking east 15

16 Wilshire/La Brea Station Center Opening What A material handling shaft in the Wilshire Bl center median between Sycamore Av and Orange Dr, in lieu of multiple intermittent closures and panel openings Wilshire Bl remains two lanes in each direction between La Brea Av and Mansfield Av Left turns open on Wilshire Bl at La Brea Av and Detroit St in both directions Some parking restored on north side of Wilshire Bl and south side of Wilshire Bl More robust noise mitigation rather than series of lane closures When Proposed dates March 2017 through December 2017 How The work zone would be established using k-rail, fencing and sound blankets Center opening will feature new banners highlighting adjacent businesses 16

17 Wilshire/La Brea Station Center Opening Concept 17

18 Center opening will resemble Jet grouting enclosure 18

19 Wilshire/La Brea Station Center Opening Concept Area Center opening work zone on Wilshire Bl between Sycamore Av and Mansfield Av, Wilshire Bl two lanes in each direction 19

20 Wilshire/La Brea Station Deck Openings What: Deck openings are openings of the street-deck for the purpose of delivering materials for underground construction Deck openings will be done at deck locations designed to open and close Deck openings will occur periodically, as needed Deck panels are 8 ft by 14 ft Decking opening will occur at all 3 station areas Deck opening at Wilshire/La Brea 20

21 Wilshire/La Brea Station Excavation When Now through the Fall of 2017 Work hours are 7am to 11pm, and 11pm to 7am as needed What Excavation will occur under the concrete deck, with intrinsically safe equipment certified by the State of California Work includes hanging utilities underneath Wilshire Bl, dewatering system installation, and maintenance of geotechnical instruments and dewatering wells 21

22 Northwest corner of Wilshire/La Brea Station looking east 22

23 Pulling ventilation pipes close to west end of Wilshire/La Brea Station, looking southeast 23

24 Jet Grouting Overview Jet grouting is a construction process that uses high-pressure air and grout to create a deep soil-concrete block Jet grouting reinforces and strengthens the soil with concrete to support tunneling and cross-passage construction Locations Jet grouting will occur at 16 cross passage locations along Wilshire Bl between La Cienega Bl and Western Av There will be no more than three jet-grouting operations performed at one time (this can make traffic control simpler and safer), in consultation with LADOT Jet grouting requires approximately 8 to 12 weeks at each location, due to traffic control and installation of geotechnical instrumentation for future tunneling Work Hours Mon. thru Fri. 7am to 9pm, Sat. and Sun. 8am to 6pm *Work hours subject to change 24

25 Six Businesses Open signs placed along jet grouting locations 25

26 Location Jet Grouting Updates Wilshire Bl between Plymouth Bl and Windsor Bl *Dates and work activities subject to change Status Complete Wilshire Bl between Norton Av and Wilton Pl In process Wilshire Bl between Gramercy Pl and St. Andrews Pl Crenshaw Bl In process Upcoming *Construction notices will be sent and outreach will be conducted for each location 26

27 Jet Grouting Activities & Layout Work Activities Potholing, street level excavation, vertical drilling, trucking, cement silos, pumps, generators Layout Concrete barriers placed on the middle lanes of Wilshire Bl Lanes reduced to two lanes each direction at jet grouting locations Bus stops will be temporarily relocated as required Wilshire BRT lane not enforced in these areas during jet grouting Intermittent material deliveries during off peak hours 27

28 Wilshire/Fairfax Station 28

29 Wilshire/Fairfax Station Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr 29

30 Wilshire/Fairfax Station Schedule *As of March 2017, subject to change 30

31 Wilshire/Fairfax Station Pile Installation Overview - COMPLETED Pile Installation includes: Rig to construct 95-ft (L) deep Crane lifting 95-ft (L), 24-inch H-piles into holes 460 piles Drilling, pile installation and backfilled concrete completed same day Piling Start Dates: Piling started in August 2016 on the north side of Wilshire Bl and switched to the south side in November 2016 Lane Reductions & Turn Restrictions: Wilshire Bl is reduced to two lanes in each direction with left turn restrictions in the area 31

32 Wilshire/Fairfax Station Decking Overview Decking Location: on Wilshire Bl, between Ogden Dr and the 99 Cents Store Construction of a concrete deck goes from curb to curb Sidewalks are maintained or pedestrian detours created Decking will serve as the temporary street surface Traffic will travel on the installed deck panels while the station is constructed underground Fairfax Decking began as of February 2017 Additional activities under decking closures include piling and temporary civil improvements Fairfax Station Stats 800-ft long 70-ft wide 60-ft deep 32

33 Aerial view of decking progress from roof of the Petersen Automotive Museum 33

34 Wilshire/Fairfax Station Decking Overview Example of decking operations 34

35 Wilshire/Fairfax Station Decking Schedule *Dates and work activities subject to change February 2017 through Summer 2017 Approximately 18 weekend closures, scheduled in three phases beginning east and moving west on Wilshire Bl Phase 1: Ogden-Fairfax 10 weekends Began Friday, February 10 th Phase 2: Fairfax intersection 4 weekends Phase 3: West of Fairfax 4 weekends Friday 8pm: Full closure of Wilshire Bl or Wilshire Bl/Fairfax Av intersection Monday 6am: Streets open LADOT approved early lane reductions to start Fridays at 10am Wilshire Bl will be reduced to one lane in each direction from Crescent Heights Bl to Spaulding Av to allow for the loudest work (breaking of concrete) to be completed during day time hours Work occurs continuously throughout weekend 35

36 Wilshire/Fairfax Station Traffic Action Plan Traffic Action Plan: Detour routes Proposed mitigations Signage Signal timing adjustment Traffic Control Officer locations Maintains local access Bus detours Approved by Board of Public Works and LADOT Traffic signage examples 36

37 Phase 1 Traffic Detour 10 Weekends Wilshire Bl, Ogden Dr Fairfax Av Closure Westbound: Northbound La Brea Av to westbound 6th St to southbound Fairfax Av to westbound Wilshire Bl Eastbound: Northbound Fairfax Av to Eastbound 6th St to southbound La Brea Av to Eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Crescent Heights Bl Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr Essentials Wilshire Bl reduced to one lane in each direction from Spaulding Av to Fairfax Av on Fridays from 10am to 8pm Full closure of Wilshire Bl, from Spaulding Av to Fairfax Av starting at 8pm on Fridays until Mondays at 6am Lane reductions on Fairfax Av for west end work Anticipated duration: 10 weekends 37

38 Phase 1 Traffic Detour 10 Weekends Wilshire Bl, Ogden Dr Fairfax Av Closure 38

39 Phase 2 Traffic Detour 4 Weekends Wilshire Bl/Fairfax Av Intersection Westbound: Westbound Wilshire Bl to southbound La Brea Av to westbound Olympic Bl to northbound San Vicente Bl to westbound Wilshire Bl Eastbound: Eastbound Wilshire Bl to southbound La Cienega Bl to eastbound Olympic Bl to northbound La Brea Av to eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr Hard closure at San Vicente Bl Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr Essentials Early start lane reductions on Wilshire Bl and Fairfax Av starting on Fridays from 10am until 8pm Full closure of Fairfax Av starting at 8pm on Fridays until Monday at 6am Full closure of Wilshire Bl starting at 8pm on Fridays until Monday at 6am Anticipated duration: 4 weekends 39

40 Phase 2 Traffic Detour 4 Weekends Wilshire Bl/Fairfax Av Intersection 40

41 Phase 2 Fairfax Av Traffic Detour Fairfax Av/Wilshire Bl Intersection Closure Southbound: Southbound Fairfax Av to eastbound 6 th St to southbound La Brea Av to westbound Olympic Bl to southbound Fairfax Av Northbound: Northbound Fairfax Av to eastbound Olympic Bl to northbound La Brea Av to westbound 6 th St to northbound Fairfax Av Lane reductions on Fairfax Av going northbound will start: Wilshire Bl/Whitworth Dr Lane reductions on Wilshire Bl going southbound will start: Wilshire Bl/Maryland Dr Local access on Fairfax Av for business and residents will be maintained Essentials Early start lane reductions on Wilshire Bl and Fairfax Av starting on Fridays from 10am until 8pm Full closure of Fairfax Av starting at 8pm on Fridays until Monday at 6am Full closure of Wilshire Bl starting at 8pm on Fridays until Monday at 6am Anticipated duration: 4 weekends 41

42 Phase 2 Fairfax Av Traffic Detour Fairfax Av/Wilshire Bl Intersection Closure 42

43 Phase 3 Traffic Detour 4 Weekends Wilshire Bl, West of Fairfax Av Westbound: Southbound Fairfax Av to westbound San Vicente Bl to westbound Wilshire Bl Eastbound: Eastbound Wilshire Bl to southbound La Cienega Bl to eastbound Olympic Bl to northbound La Brea Av to eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr Hard closure at San Vicente Bl Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr Essentials Wilshire Bl from Fairfax Av to Crescent Heights Bl reduced to one lane in each direction on Fridays from 10am until 8pm Full closure of Wilshire Bl from 8pm on Fridays until 6am on Mondays Working with City of Los Angeles to address access to buildings between Crescent Heights Bl and Fairfax Av (zone shown in yellow), work zone shown in purple Lane reductions on Fairfax Av to support work on the east end of the closure Anticipated Duration: 4 weekends 43

44 Phase 3 Traffic Detour 4 Weekends Wilshire Bl, West of Fairfax Av 44

45 Wilshire Bus Detours Phase 1: Fairfax Decking 720/20 Wilshire bus stops have been relocated In effect: 8pm Friday, February 10, 2017, until 6am Monday February 13, 2017 and continuing every weekend until further notice Eastbound Detour Regular route to Wilshire Bl and McCarthy Vista then continue via Wilshire Bl to Fairfax Av to 3 rd St to La Brea Av to Wilshire Bl and regular route Westbound Detour Regular route to Wilshire Bl and La Brea Av then La Brea Av to 3 rd St and Fairfax Av to Wilshire Bl and regular route *Passenger stops available at all intersection where it is safe, while on detour route. 45

46 Wilshire/Fairfax Station Decking Community Outreach Robust Marketing Campaign Social media: Facebook, Twitter, and Nextdoor Advertising: print, radio, and online Media coverage: press releases Business and residential outreach Meetings with local groups, leaders Elected Official Briefings Safety Presentations School Presentations Community Partnerships 46

47 Wilshire/Fairfax Station Decking Community Outreach Chrysalis, non-profit, helps with door to door outreach 47

48 Wilshire/Fairfax Station Deck Openings What: Deck openings are openings of the street-deck for the purpose of delivering materials for underground construction Deck openings will be done at deck locations designed to open and close Deck openings will occur periodically, as needed Deck panels are 8 ft by 14 ft Decking opening will occur at all 3 station areas Typical deck opening 48

49 Wilshire/La Cienega Station 49

50 Wilshire/La Cienega Station Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr 50

51 Wilshire/La Cienega Station *As of March 2017, subject to change 51

52 Wilshire/La Cienega Station La Cienega Staging Yards Photos of preparation work for soundwalls at the La Cienega staging 52

53 Wilshire/La Cienega Station Gale Staging Yard Completed soundwall at Gale Staging Yard 53

54 Wilshire/La Cienega Station Upcoming Work March thru May, 2017 Instrumentation installation on Wilshire Bl, La Cienega Bl and adjacent streets to began in January and continues thru May. Pre-pile activities and instrumentation will be ongoing behind k-rail and throughout the station area Piling on the south side of Wilshire Bl to start mid-march Jet grouting at east and west ends of the station Details for all work will be communicated in construction notices and through outreach to affected businesses, residents and stakeholders 54

55 Wilshire/La Cienega Station Work zone, south side of Wilshire Approximate location of south side pile work zones at Wilshire Bl/La Cienega Bl 55

56 Wilshire/La Cienega Station Pile installation, south side of Wilshire between La Cienega Av and Tower Dr Approximately 470 piles total to be installed approximately 166 piles on the south side Work zone delineated by k-rail and fencing Piling is projected to start mid-march 2017 Work hours: 7am-8pm; drilling and setting of piles; 8pm-10pm; breakdown, cleanup, non-drill activities. Wilshire/La Cienega Stats: 990 ft long 70 ft wide 60 ft deep 56

57 Wilshire/La Cienega Station Piling Mailer 57

58 Wilshire/La Cienega Station Upcoming Work Pending Approval Cross-section showing work zone and drill rig for pile installation 58

59 Wilshire/La Cienega Station Upcoming Work Jet Grouting at Wilshire/La Cienega Jet grouting is soil reinforcement using a drill rig to support station excavation and tunneling. Additional equipment include generators, pumps and a grout silo Jet grouting will occur within the south side k-rail work zone Additional jet grouting will happen under lane reductions outside of work zone Anticipated to start in March of 2017 Work hours: 7am-8pm; drilling 8pm-10pm; breakdown, cleanup, non-drill activities (Lane closures will follow permitted hours) Pending City of Beverly Hills approval 59

60 Staying Safe Near Construction Sites Stop, Look, & Listen Be alert and aware of your surrounding Avoid distractions See and be seen Obey construction signage Use designated sidewalk or walkways 60

61 Help Us Keep You Safe Purple Line Extension 24/7 Project Hotline On Metro Transit See Something, Say Something SAFE (7233) Construction Safety Awareness Program Glyssa Alcazar, Community Relations Officer alcazarg@metro.net Phone:

62 Win 7-Day Metro TAP Card 62

63 Recap: Lunch Meet-Up with Book My-Lot Food Trucks 63

64 Next Lunch Meet-Up at Bru's Wiffle Beverly Hills Tuesday, April 4, :30am to 1:30pm 8635 Wilshire Blvd., Beverly Hills, CA

65

66 BIF Grant Award Update > Purple Line Extension, Phase 1 (as of 3/10/17) > BIF Applications Submitted: 99 > BIF Applications Awarded: 77 > BIF Grant Amount Awarded: $1,627, *13 applications pending completion *9 applicants have been deemed ineligible > Noteworthy Updates: > 41 businesses have received one or more BIF grants > Average amount per grant: $21,130.65

67 Metro Business Interruption Fund Financial assistance to small mom & pop businesses impacted by Metro transit rail construction along three project areas: Purple Line Extension, Phase 1 Crenshaw/LAX Transit Project Regional Connector, Little Tokyo area & 2nd/Broadway segment Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements Grant amount determined by demonstrated loss of business revenue directly related to the period of construction disruption Maximum annual grant amount per business is $50,000 BIF Business Advisor for PLE Brian Lazo, PCR at , ext

68 Next Meeting Section 1: Construction Community Meeting Thursday, May 18, pm 7:30pm SAG/AFTRA 5757 Wilshire Bl Los Angeles, CA

69 Stay in Touch 69

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

Purple Line Extension. Construction Community Meeting January 19, 2017

Purple Line Extension. Construction Community Meeting January 19, 2017 Purple Line Extension Construction Community Meeting January 19, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Seismic Boring Study Advance Utility Relocation

More information

Purple Line Extension. Construction Community Meeting May 19, 2016

Purple Line Extension. Construction Community Meeting May 19, 2016 Purple Line Extension Construction Community Meeting May 19, 2016 Agenda Western look ahead: Sound wall construction La Brea Piling Update La Brea Decking: Phase l, ll,lll detours, outreach and communication

More information

Westside Purple Line Extension Section 1 Project Overview

Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension (WPLE) Section 1 Project Purple Line Project Alignment The WPLE corridor traverses portions of three jurisdictions,

More information

Purple Line Extension. Section 1 Construction Community Meeting March 17, 2016

Purple Line Extension. Section 1 Construction Community Meeting March 17, 2016 Purple Line Extension Section 1 Construction Community Meeting March 17, 2016 Agenda Western look ahead: Demo and sound wall construction La Brea Piling Update La Brea Decking phases l, ll,lll Fairfax

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Purple Line Extension. Westside/Central Service Council August 13, 2014

Purple Line Extension. Westside/Central Service Council August 13, 2014 Purple Line Extension Westside/Central Service Council August 13, 2014 1 Project Overview & Schedule 2 Approved Project 3 Approved Project - Schedule Planned Schedule Forecasted Schedule Section 1 Section

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

STAFF REPORT. Attachments: 1. Location Map 2. Project Schedule 3. Sound Wall Graphics Design Concept

STAFF REPORT. Attachments: 1. Location Map 2. Project Schedule 3. Sound Wall Graphics Design Concept STAFF REPORT Meeting Date: June 5, 218 To: Honorable Mayor & ity ouncil From: Darren Grilley, ity Engineer Robert Welch, Project Manager Subject: Metro Purple Line Extension Section 1, La ienega Station

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015 Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-16. Santa Monica/San Vicente 1/4-Mile Station Area August 16, 2010 Page 5-35 Figure 5-17. Beverly Center 1/4-Mile Station Area August 16, 2010 Page 5-36 5.8 Alternative 5 Santa Monica Extension

More information

Crenshaw/LAX Transit Project

Crenshaw/LAX Transit Project Crenshaw/LAX Transit Project Construction Update Community Meeting January 25 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-6. Century City 1/4-Mile Station Area August 16, 2010 Page 5-14 Figure 5-7. Wilshire/Westwood 1/4-Mile Station Area August 16, 2010 Page 5-15 Alternative 1 would be constructed underneath existing

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

Eastside Transit Corridor Phase 2

Eastside Transit Corridor Phase 2 Eastside Transit Corridor Phase 2 Community Meeting, June 22, 2016 Page 1 Purpose of Tonight s Meeting Page 2 Update on Metro Board directed Technical Study (Nov. 2014) SR-60 Alternative Washington Blvd

More information

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 INFORMATION IS CURRENT AS OF APRIL 19, 2018 AND SUBJECT TO CHANGE 2 Agenda Caledonia Station Update Fairbank Station Update Oakwood Station Update

More information

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address. Application 06-12-005 et al. Exhibit Date: August, 2008 PREPARED TESTIMONY OF LEE LISECKI Q. Please state your name, professional position, and business address. A. My name is Lee Lisecki. I am a principal

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer April 18, 2018 MEMORANDUM PUBLIC WORKS DEPARTMENT HILLS BEVERLY CITY OF BEVERLY HILLS Public Works Commission Rob Welch, Acting City Engineer Capital Projects Update Capital Improvement Projects Update

More information

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House May 22, 2018 1 Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House Rendering of Trail and Community Improvements at Project Completion 2

More information

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222 Water Projects Maple Wells Project (CIP No. 0916) Scope of Work: Construction of two municipal supply wells at the Maple Yard (342 Foothill Road) and a pipeline to convey well water to the water treatment

More information

OPTIONAL STATIONAVIATION/MANCHESTER

OPTIONAL STATIONAVIATION/MANCHESTER CRENSHAW/LAX TRANSIT CORRIDOR PROJECT FEIS/FEIR OPTIONAL STATIONAVIATION/MANCHESTER Aviation and Manchester, Looking East Aviation/Manchester Station (Optional) The Optional Aviation/Manchester Station

More information

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Presented in Beverly Hills: June 7, 2010 Where We are in the

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

4.15 Construction Impacts and Mitigation

4.15 Construction Impacts and Mitigation 4.15 Construction Impacts and Mitigation This section provides an overview of the construction methods, the potential construction impacts, and the proposed mitigation measures the Build Alternatives.

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system.

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system. Water Projects Pump Station No. 8 Rehabilitation (CIP No. 0796) Scope of Work: Rehabilitation of aging mechanical equipment and the associated piping at the existing pump station adjacent to Reservoir

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Roosevelt Station Construction Kristin Hoffman, Station Project Manager Next Steps

More information

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line Board Update Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line 10.5 mile light rail line Starts at Nine Mile Station Eight stations Serves Aurora City Center Serves

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction

More information

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017 West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Meeting June 2017 Agenda > Welcome and Introductions > Purpose of Scoping > Timeline and Process > Environmental Approach and Methodology >

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

Public Works Department

Public Works Department Public Works Department Monthly Report Public Works Department Monthly February Report 2017 George Chavez Assistant City Manager/Director of Public Works Key Message The Public Works Department reached

More information

2. PROJECT DESCRIPTION

2. PROJECT DESCRIPTION 2. PROJECT DESCRIPTION This chapter presents the Proposed Project location and surrounding uses, project history, project description, and the estimated construction schedule and phasing. Briefly, the

More information

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE Project Background As part of the Seaterra Program, Clover A new conveyance pipe (forcemain) Pump Station will be upgraded and will run

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update May 1, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 86% complete Construction Construction

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

CROSSTOWN LRT Construction Liaison Committee November 1, 2017 CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole

More information

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

Westside Subway Extension

Westside Subway Extension March 2012 Westside Subway Extension Final Environmental Impact Statement/Environmental Impact Report Volume 1 State Clearinghouse No. 2009031083 10-1407cmc 2010 lacmta Final Environmental Impact Statement/

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report

More information

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017 VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident

More information

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018 City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House March 27, 2018 Agenda 1. Construction Team 2. Anticipated Construction Staging 3. Anticipated Construction Schedule

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013

State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013 State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013 Frank Quon, P.E. Executive Officer, Metro Highway Program Michelle Smith, P.E. Project Manager, Metro Highway Program

More information

Executive Summary Introduction and Background

Executive Summary Introduction and Background ES.1 Introduction and Background The Los Angeles County Metropolitan Transportation Authority (LACMTA) completed the Final Environmental Impact Report/Environmental Assessment (Final EIR/EA) for the Wilshire

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 4.18 Construction Impacts This section summarizes the potential construction impacts of the proposed alternatives, including the Locally Preferred Alternative (LPA). These

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG

More information

ALAMEDA CORRIDOR EAST San Gabriel Valley

ALAMEDA CORRIDOR EAST San Gabriel Valley ALAMEDA CORRIDOR EAST San Gabriel Valley San Pedro Bay ports: 40% of nation s imports; 30% of exports. ACE Trade Corridor: 21% of waterborne containers entering/exiting the U.S. 81 trains/day (2009) 141

More information

FACT SHEETS LOS ANGELES COUNTY

FACT SHEETS LOS ANGELES COUNTY FACT SHEETS LOS ANGELES COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares a

More information

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018 Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day

More information

NEPA and Design Public Hearings

NEPA and Design Public Hearings NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

Construction Notice: Infrastructure Renewal on York and Talbot Streets

Construction Notice: Infrastructure Renewal on York and Talbot Streets Construction Notice: Infrastructure Renewal on York and Talbot Streets Date: March 22, 2019 To: Business owner, resident and/or property owner Project Details: The City of London in partnership with J-AAR

More information

Welcome. Welcome to the Wastewater Treatment Project s community meeting about Niagara Street.

Welcome. Welcome to the Wastewater Treatment Project s community meeting about Niagara Street. Welcome NIAGARA STREET COMMUNIT Y MEETING Welcome to the Wastewater Treatment Project s community meeting about Niagara Street. Thank you for coming to the community meeting. We are here to provide information

More information

I-4 Ultimate Social Media

I-4 Ultimate Social Media January 7, 2015 I-4 Ultimate Social Media Learning about #I4Ultimate construction and how the project will keep traffic on the go on @idriveorlando @MyFDOT_CFL #I4Ultimate Interstate Today Designed and

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

Overview of Construction Activities

Overview of Construction Activities Chapter 5.0 Overview of Construction Activities This chapter describes, to the extent feasible, how construction of the Preferred Alternative might be undertaken and summarizes the measures that have been

More information

Executive Summary/Summary of Findings Introduction and Background

Executive Summary/Summary of Findings Introduction and Background ES.1 Introduction and Background In March 2004, the Los Angeles Department of Transportation (LADOT) and the Los Angeles County Metropolitan Transportation Authority (LACMTA) implemented peak period bus

More information

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006 Review Advisory Committee May 11, 2006 1 Ramona Opportunity High School/ Indiana Station Status 2 Ramona Opportunity High School/ Indiana Station Status 1. On April 19, 2006, Metro held an Indiana Station

More information

Brooklyn Station Construction Open House

Brooklyn Station Construction Open House Brooklyn Station Construction Open House November 16, 2011 Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Louise Little, Greater University

More information

Strategies to keep people and goods moving in and through Seattle

Strategies to keep people and goods moving in and through Seattle Strategies to keep people and goods moving in and through Seattle Period of Maximum Constraint and the Permanent Viaduct Closure 2018-2024 West Seattle Transportation Coalition September 27, 2018 Department

More information

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing OVERVIEW Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing Construction Liaison Group Nov 7th, 2013 1 WORKS IN PROGRESS Construction Liaison Group Nov 7 th, 2013

More information

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ) FREQUENTLY ASKED S (FAQ) The purpose of this document is to provide detailed information about the Harvard Road Reconstruction & Water Main Replacement Project. This project will directly affect residents

More information

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La

More information

RPM Phase One: Lawrence to Bryn Mawr Modernization

RPM Phase One: Lawrence to Bryn Mawr Modernization RPM Phase One: Lawrence to Bryn Mawr Modernization Public Update April 2018 Chicago Transit Authority RPM program history 2009-2010 2011 2012-2013 2014-2015 2016-2017 2018 2019-2025 Vision Study Environmental

More information

4.0 CONSTRUCTION METHODS AND ACTIVITIES

4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential

More information

Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018

Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018 1 Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018 Community Meeting Overview Introductions (5 minutes) TTC, City of

More information

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017 Palo Alto Rail Committee Meeting November 29, 2017 Slide 1 Project Area Millbrae Station City Limits Existing Railroad Crossing at Broadway Caltrain Operational Constraint Major Constraints Millbrae Station

More information

4.12 Public and Emergency Services

4.12 Public and Emergency Services 4.12 Public and Emergency Services Public services include schools, community centers, cemeteries, and social service providers. Emergency services include fire and police stations and services, hospitals,

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Frequently Asked Questions The Basics Who, What, When, Where, Why, How Why is the project being performed? The project is being constructed to reduce flooding in

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Why is the project being performed? Frequently Asked Questions The Basics Who, What, When, Where, Why, How The project is being constructed to reduce flooding in

More information

Environmental Setting

Environmental Setting Section 5.2 Environmental Justice This section describes the potential of the proposed changes to the approved project to result in disproportionately high and adverse health or environmental effects on

More information