4 Construction of the Project
|
|
- Oswald Nichols
- 6 years ago
- Views:
Transcription
1 71 4 Construction of the Project Overview The following is a summary of the current Project construction methodology and assumptions. It should be read in conjunction with Technical Report 1: Design Philosophy Statement in Volume 3 of these documents and the Construction Environmental Management Plan (CEMP) in Volume 4 of these documents. Those documents provide furtherr detail on construction activities that are referenced below. The final construction process will not be confirmed until after detailed design as there may be further modifications occurring during the construction period. Where a specific form of construction is proposed it may be replaced by alternative methods providing the effects are no greater than anticipated by the methodology proposed and in accordance with conditions. This flexibility is desirable as alternative methods will be geared towards reducing the overall construction period and so that monitoring of effects through the construction period can be undertaken. The scope of the Project extends from the existing Mount Victoria Tunnel in the east and joins into the existing SH1 at Buckle Street, just west of the intersection with Sussex Street, as well as the proposed intersection improvements at Pirie/Vivian Street and Taranaki Street/ /Karo Drive. 4.1 Construction Programme and Sequence The forecast duration of the construction period is 28 to 34 months. Assuming a start in mid 2014, the forecast completion date is the first quarter of The upper bound duration of 34 months allows for six months of contingency. The exact construction phasing sequence will be developed and refined as the design nears finalisation but there has been the benefit of the contactor that will be undertaking the works being involved to date in terms of a construction methodology. While there is the desirability of maintaining contractor flexibility there is also the need to provide sufficient certainty to ensure that environmental management and monitoring will be undertaken during the construction period. As such the conditions of consent proposed and the Construction Environmental Management Plan (CEMP) will provide a certification process to appropriately manage the precise methods of construction. However the general approach to constructing the Project is likely to entail: work at Pirie/Vivian/Kent/Cambridge and Buckle/Taranaki intersections to accommodate construction activities and to manage the impact of the construction activities on the overall transport network;
2 72 realignment of the eastbound state highway occurring early in the programme to facilitate pier and bridge superstructure construction; concurrent work on abutments with pier construction. This approach is likely to maximise resource availability and usage while acknowledging technical complexity at either end. In addition it is important to have as many concurrent activities occurring as reasonably and safely practical at any time; bridge deck construction will progress as bridge piers are constructed; the building under the bridge are likely to be constructed after piers and the bridge superstructure have been completed; the Northern Gateway Building would be constructed concurrently with the bridge; and improvements in the Sussex and Rugby Streets and to Rugby Street area will occur after the bridge has been opened to westbound state highway traffic. An overview of the construction programme for the bridge and at grade road sections is shown in Figure 4-1. More detailed staging plans for the construction process covering the entire Project works are included as Appendix A to the Construction Environmental Management Plan in Volume 4 of these documents. The key activities that willl influence the likely construction methods are listed below. Potential construction sequencing and programming are indicative only and might be amended as a result of detailed design provided that this will not have any material bearing on the management of effects. The CEMP sets out alternative methods of carrying out certain actitivites where possible. For example, methods to test, treat and discharge groundwater. The CEMP will be finalised during the detailed design phase and will subject to certification by GWRC and WCC as proposed by the designation and resource consent conditions submitted with this application. The programme is based on the following construction elements: Relocation of Services; Site clearance; Existing intersection capacity improvements Pirie/Kent/Cambridge/Vivian and Taranaki/Buckle intersections; at the SH1 Eastbound realignment (Kent Terrace Paterson Street) and part of the eastern abutment; Western Abutment; Pier construction; Deck construction; ; Completion of the eastern abutment; Dufferin and Rugby Street works; Kent/ Ellice Cornerr Building and Green Screen;
3 73 Basin Reserve Screen and Building; and Landscaping. An overview of these elements is provided below and more detailed descriptions are included in Appendix A of the Construction Environmental Management Plan in Volume 4 of these documents.
4 74 Figure 4-1: Potential construction sequence and programme
5 Relocation of Services Service authorities with infrastructure in the Project Area with potential conflicts with the proposed design are: Wellington Electricity (Northpower as contractor); Powerco (Electrix as contractor); WCC Water, stormwater, sewers (Capacity as contractor); Wellington Cable Car Limited; Chorus as contractor (on behalf of Telecom); Telstra Clear; and City Link. Service relocation work is normally undertaken directly by the service authorities, with the work being coordinated to suit the construction programme, access and preferred outage timing where possible. It is expected that most services will be able to be relocated before construction commences, but it may only be possible for others to be relocated once construction work is underway in the case event of discovering utilities. Trial hole operations will be required during the design phase of the Project to confirm servicee locations and allow best fit of the design around the existing infrastructure. Thesee trial holes will be carried out by jet vacuuming techniques which significantly reduce the risk of damage to services and therefore reduce any impact on utility users Site Clearance Site clearance will occur just before construction work commences in specific areas. This activity will be coordinated with archaeological work and provision of temporary erosion and sediment control measures. During the site clearance phase, works will be undertaken in accordance with a Construction Traffic Management Plan (CTMP). Sites will be appropriately fenced. Stabilised exits will be provided in order to manage the potential for mud to be dragged onto roads. Sites will, as necessary, be dampened to manage dust while shade cloth will be attached to the fencing to further reduce potential dust issues Existing Intersection Capacity improvements Prior to commencing the main works the proposed improvements to the Taranaki Street/Karo Drive and Pirie Street / Kent Terrace / Cambridge Terracee / Vivian Street intersection will be undertaken. This work is required to accommodate construction traffic, to mitigate Project accessibility impacts and to offset any potential delays experienced through construction of the bridge. Further detail on these improvements is providedd in Technical Report 4.
6 SH1 Eastbound Re-alignment (Kent Terrace Paterson Street) A significant part of the new east-west realigned link will be constructed offline i.e. outside of existing live traffic lanes and footpaths. The eastbound re-alignment (involving the constructionn of the traffic lanes, shared cycle and pedestrian paths and linkages into Ellice and Hania Streets) largely utilises land to the east of the existing alignment. This component of work needs to be undertaken in advance of construction of the two eastern most bridge piers and the eastern abutment, and will be undertaken in the first stages of the Project construction SH1 Bridge (westbound) The construction methodology that has been developed is based on the use of a cast in situ concrete box girder structures, but other methods may be utilised, providing they result better outcomes including managing of adverse effects. The order in which the sections of the bridge are constructed may also vary. The key construction phasing consideration, given its effects, is the construction of the eastern abutment and tie-in of the existing carriageway upon exiting the Mount Victoria Tunnel. To minimise traffic disruption, the eastern abutment work will need to be undertaken in the later stages of the bridge work. This is to ensure other improvements to State highway and local accesss are implemented and operational before the impact of reduced capacity at Paterson Street occurs. With this staging the related effects of construction can be managed effectively by the contractor, WCC, NZTA and other transport providers (taxis, bus companies etc.). In planning the timing of these works consideration needs to be given to minimising traffic impacts. Other operations during construction that will influence movement around Wellington City include: during construction of the bridge over Kent and Cambridge Terrace it may be necessary to close the road link in front of the northern entrance (the CS Dempster Gate entrance) to the Basin Reserve. This will require vehicles who would otherwise use this link to travel further north up Cambridge Terrace before undertaking a u-turn within the median and heading along Kent Terrace; during construction of the bridge across Cambridge Terrace it will be necessary to restrict vehicle movements to one lane northbound between Sussex Street and Cambridge Terrace; and during construction in the area at the base of Ellice Street it is likely that Hania and Ellice Street will need to be either partially (one way access) or fully closed to motor vehicles for periods of time. Pedestrian access will be maintained at all times.
7 77 The different effects of this traffic management have been assessed as part of Technical Report 4: Assessment of Traffic and Transportation Effects in Volume 3 of these documents Western Abutment Ground improvement works will be required due to consolidation and/or seismic induced liquefaction and a potential settlement period will be required. Ground improvement works will entail deep soil mixing, stone column or cellular piling techniques. Deep soil mixing involves mechanical augering of the ground to a depth of approximately 18m to loosen the material with large plant. The disturbed ground is then mixed with cement or lime with paddles pushed down to the same depth. The cement then cures to produce a column that is seismically stronger than the original ground. These columns are grouped in cells or rows to provide a hard point below a structure. Stone columns involve displacing weaker ground with higher strength columns of clean quarry sourced stone. Columns are drilled out and replaced with the stone by compaction techniques. This method forms a dense column of stone within the weaker existing strata. Stone columns are ordinarily laid out in grids. Cellular piles or secant piles are piling techniques whereby concrete piles (often with reinforcing bars) are formed by augering out the weaker strata with heavy plant and replacing it with concrete. This method is traditionally set out in cells or underground walls as the piles touch each other. The decision on the piling method will be made by the contractor taking into account ground conditions but within the framework of the conditions attached and the CEMP. The western abutment is built off line from the existing road network with access from Cambridge Terrace. It is anticipated that the existing road network will be unaffected. The footpath may require minor adjustment in order to provide a suitable level of public safety. Given the limited working space, the preferred methodology for the is likely to utilise pre-cast wall panels with a cast in situ concrete possibly infill. This will provide an efficient method in confined areas space is available, a mechanically stabilised earth wall solution can be abutment walls base slab and s. Where more used. The abutment beam will be cast monolithically with its supporting piles. During construction of the abutment beam concrete will be pumped into forms supported on a falsework system. Together these will provide the design outcomes shown on the drawings and referredd to within Technical Report 3: Urban and Landscape Design Framework in Volume 3 of these documents.
8 Pier Construction Pier construction will generally be undertaken from both ends of the bridge towards the centre. Each pier may have its own geotechnical solution. Some may be formed on a spread footing on pre-stabilised ground, but it is likely that a piled solution will be required at most piers. It is estimated that each pier will have a construction time of 3 months. Each pier comprises a foundation (piles and related) a piling cap and a column. Each pile will consist of a steel cylinder of 1.2m diameter. The tubes will be rotated or oscillated into the ground until they reach solid founding material. The earth inside each cylinder will be removed by the drill rigs and replaced with reinforced concrete. Groundwater pressure which may affect the construction of the piles will be controlled with a small diameter borehole and valve at each pile group location. Figure 4-2: Typical bored pile rig Each pier comprises a foundation (piles and related) a piling cap and a column. The pile cap is likely to be a reinforced concrete base sized to suit the piling arrangement and available land. It will be excavated and formed taking cognisance of retaining any excavation with a road or building above. During excavation of the piling cap, any services not previously diverted will be protected or moved. The final component is the column of the bridge. The shape of each column will be different and likely cast in situ concrete in a mould. The concrete will be placed in the mould by concrete pump.
9 79 On completion of the column, the work zone will be backfilled and the ground reinstated or prepared for the falsework. The piers for the shared path connection from Paterson Street onto the bridge are substantially smaller in scale than those required to support the main bridge itself and can therefore be undertaken in much shorter time frames, 3-4 weeks as compared to the 3 months estimated for each bridge pier Bridge Deck Construction The bridge superstructuree will commence upon completion of Pier S2 (western most pier adjacent to the west abutment). The superstructure will be constructed on a temporary scaffold and structural steel falsework system. Where the new bridge crosses over existing roads a bridging system for the falsework will be installed. Diagrams of these temporary supporting structures are included in the CEMP included in Volume 4 of the application documentation. Appendix A to The bridging system will maintain vehicular access under the bridge and minimise disruption to the trolley buses by maintaining power through the site. Each bridging system will require a one or two night time road closures for erection and the same for dismantling of the falsework. The construction work will be carried out above live traffic within a system of handrails, solid flooring, screens and safety nets that will manage the risk of items falling on to the vehicles below. Typically the concrete willl be delivered to the bridge deck using concrete pumps. The cross section can be poured at one time or alternatively the webs and base slab could be cast first with the deck pour undertaken when the webs and base slabs have attained sufficient strength. When cured, the concrete willl then be post tensioned. After appropriate curing, the falsework will be removed from the completed span and moved to the next piers in sequence. Final works will include street light installation, anti-graffiti coating and laying road pavement and all related works. These final stages of work can be undertaken with minimal interference on existing roads (underneath and at connections) Eastern Abutment As with the west abutment, potential settlement due to consolidation and/or seismic induced liquefaction needs to be addressed. Ground improvement works will be required and may entail deep soil mixing, stone column or cellular piling techniques. Although these methods are all plant intensive, the treatment area of this abutment is also likely to be limited to a plan area comprising 4 metres beyond the abutment and approach fill footprint. The potential ground improvement techniques used are described in section above and are as per the western abutment.
10 80 The eastern end of the bridge will be supported on bearings on a reinforced concrete abutment beam in the same manner as the western abutment. The abutment beam will be cast monolithically with its supporting piles. Pile construction will be undertaken using the method described above for the piers and the construction effects will be similar. Construction of the abutment beam will use the methodology described above for the western abutment. Together these works are consistent with the design outcomes shown on the drawings and referred to within Technical Report 3: Urban and Landscape Design Framework in Volume 3 of these documents. Works at the eastern abutment will be constructed in a staged manner to minimise potential disruption to the public and maximise the available working space (see above). Work on the northern wall could commence at the same time as construction of the new eastbound at-grade carriageway. Once east-bound traffic has been switched onto the new at-grade carriageway, works to the abutment and northern wall could be completed and works to the southern retaining wall commenced. West-bound traffic could then be split between a single lane on the bridge and a single Paterson Street/Dufferin Street lane link to enable the southern retaining wall and tie in to be completed. Closing the single Paterson Street/Dufferin Street lane link for short periods during school holidays would be an advantage and will be considered if timing allows. Likewise the ability to close the Mount Victoria Tunnel completely for a two week period over the Christmass holiday could also significantly accelerate construction in this location, and will also be considered if timing allows. Where these measures are not possible, alternative traffic management solutions could be to divert traffic onto the Paterson Street footpath for a short period (probably up to 2 weeks) if necessary. Completion of this construction work adjacent to live traffic lanes will need to be carefully managed and considered against the desirability of a longer construction period. Nearby stakeholders have indicated both a need for existing access to be maintained and for work to be undertaken in as short a period as possible (whereas the schools consider thatt work should be undertaken during the school holidays). The wall construction methodology will be developed specifically to enable construction in the limited space available. The ability to deliver pre-cast wall sections at night would be an advantage as that will reduce affects on traffic and avoid potential effects on schools. Given the limited working space, the preferred methodology for the abutment walls is likely to utilise pre-cast wall panels with a cast in situ concrete base slab and possibly infill. This will provide an efficient method in confined areas. Where more space is available, a mechanically stabilised earth wall solution may be used South- East Quadrant (Dufferin Street/Rugby Street/Adelaide Road) This work is likely to occur after the SH1 westbound traffic is moved onto the new bridge when there will be less traffic on this part of the network.
11 81 These works involve the modification to the traffic flow, bus movements and parking arrangements in front of St Marks School and the entry to Government House and Wellington College. On Rugby Street the work involves widenedd footways to accommodate the relocated bus stop from Adelaide Road in a southbound direction and significant changes to the intersection to increase the size of the central island and ensure safe flow of traffic, buses and cycles through the intersection. These works will need to be coordinated with school drop-off and pick-up activities of the schools (St Marks School and Wellington College) as well as any functions at Government House. 4.2 Landscaping It is expected that soft and hard landscaping work will be undertaken on a sectionby-section basis as soon as construction work is completed. The proposed landscape measures for paving, pathways, and plantings will stabilise areas that have been exposed to earthworks and achieve the overall design that will assist with the intergration of the Project into its surrounds. It is intended that landscape work will commence as soon as possible to enable any new plantings to establish ahead of opening the Project to traffic where possible. 4.3 Northern Gateway Building The construction of the Northern Gateway Building within the Basin Reserve is expected to be undertakenn in the following sequence. Careful removal of the CS Dempster Gates will be the first phase, followed by marking of in-ground services and demolition of any residual structures, e.g fences. The new building will most likely need to be piled. These are, at this point, assumed to be steel reinforced concrete piles with casings in the order of 15 piles, 22 metres deep to match the column structure in the lower floor. These piles will be cased, and these casings will be either vibratory hammered or oscillated into the ground. The type of machinery involved is 60 tonne cranes with 30m booms or 37 tonne Soilmec piling rigs which have an 18 metre high telescoping drill rig on the front. Once each pile is bored out, steel reinforcing cages are lowered in and concrete follows shortly after. Floors will predominantly be concrete, poured in sections, requiring access with concrete pumps to enable the reach across the floor area. concrete truck There are several options to construct the building structure. The first is to use a tower crane or self erecting crane located on the north west or south east side of the building. The second is to use a mobile crane to construct the building to full height starting from the west end against the existing grandstand and building towards the east end. The selected option will be determined in conjunction with the structural designer to provide the most appropriate solution.
12 Building under the Bridge and the Green Screen The construction of the building on the corner of Kent Terrace and Ellice Street and the green screen adjoining Grandstand Apartments is expected to be undertaken as per the following sequence. Once the temporary support structure for the bridge deck and superstructure are removed foundation preparation can occur. The building may need to be piled, these could be either steel screw piles or reinforced concrete. If significant piling is required these may need to be installed at the same time as the piles for the bridge piers. The green screen truss structure will require a piled foundation. Floors will predominantly be concrete, poured in sections, requiring access with concrete pumps to enable the reach across the floor area. concrete truck There are two components to the super structure, being the building structure and the green screen. The building is currently expected to be a relatively simple structure will a fully glazed façade and at this stage will follow a typical sequence of slab; structure erection; roofing; exterior cladding; and internal fitout. The green screen is slightly different requiring larger craneage of the articulated steel truss into its vertical position. This will be erected in sections with soil containers added afterwards. 4.5 Extent of Works Construction activities will, at times, occupy most of the extent of the Project Area. Due to the confined nature of the site and the need to maintain traffic movements, it is likely that all or most of the site will be a live construction site. Some specific construction activities will be concentrated in certain locations, e.g. piling to be focused at bridge pier locations. It is expected that the site compounds will include temporary site buildings, material lay down areas, plant and equipment storage areas, fuel storage and refuelling facilities, car parking, wheel washing and cleaning facilities. It is not anticipated that a concrete batching plant or pre-cast yard will be required on site as beams will be manufactured off-site and transported in. 4.6 Earthworks It is assumed there will be undercut to waste below the abutments and approaches to the bridge, with imported structural fill for abutment reinforced earth walls. It is
13 83 assumed the retaining wall from Ellice Street to Paterson Street will also require structural fill. Similarly, construction of the foundations/pile caps at each pier willl require cut to waste below the foundation footprint followed by landscaping with imported material to cover the foundation after the concrete has cured. It has been assumed thatt all cut to waste will be disposed of off-site, at approved landfills. The contaminated land management plan (Volume 4) includes details on likely contaminated material and methods for treating or removing where necessary. All erosion and sediment control measures shall be in accordance with the erosion and sediment control plan (see draft in the CEMP, Volume 4 to these documents) and with GWRC s Erosion and Sediment Control Guidelines for the Wellington Region published in The constructor shall maintain all these works to achieve the required outcomes for the duration of the contract period and until approval for the removal is attained from GWRC. 4.7 Environmental Compliance Prior to any site works commencing, the constructor will be required to prepare, implement and manage a CEMP. The detailed CEMP shall address measures to minimise and manage any adverse construction effects. A draft CEMP is included in Volume 4 of these documents. As this plan has been developed prior to development of the final construction methodology, the information included is generic in some cases. The final CEMP is proposed to be submitted for certification prior to commencement of the works. There are some properties or activities which are located closer to the construction activities than others for example Grandstand Apartments (and related commercial operators), Mitsubishi Motors (car sales yard), St Josephs Church, St Mark s Church School and Regional Wine and Spirits. Special consideration needs to be given when working in close proximity to these properties or activities. The special considerationn may include programming works to minimise impacts, selection of machinery or construction techniques which have a lesser impact in respect of noise generation, vibration and speed of construction. An important part of minimising the impacts will be liaising closely with the relevant parties. The methods for liaison have been identified in the draft CEMP in the Community and Consultation section.
ARCHITECTUS FEBRUARY 2010
ARCHITECTUS PEDESTRIAN AND TRAFFIC MANAGEMENT PLAN FOR DEMOLITION, EXCAVATION AND CONSTRUCTION OF COLLEGE OF FINE ARTS CAMPUS, PADDINGTON FEBRUARY 2010 COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296
More informationManagement Plan: Hazardous Materials Removal & Demolition
Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council
More informationThe HKIE Structural Examination Written Examination
The HKIE Structural Examination Written Examination Section 2: Design Questions (80% of the Written Examination) Date: 28 November 2014 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationBasin Bridge Project Draft Construction Transport Management Plan
This report has been prepared by Opus International Consultants for the benefit of the (NZTA). No liability is accepted by this company or any employee or sub-consultant of this company with respect to
More informationREPORT Condition D19 Permanent Noise Barriers
REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended
More informationAdvantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)
Advantages / Disadvantages of Piling Methods In this Piling Advice Note we will explore the advantages and disadvantages of differing types of piling methods. Continuous Flight Auger (CFA) The pile is
More informationA. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE
Chapter 17: Construction A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter discusses the various activities that would be involved in constructing Hamilton Green. The potential for significant adverse
More informationConstruction Method Statement
Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN for LEICHHARDT PARK CHILDCARE CENTRE
CONSTRUCTION TRAFFIC MANAGEMENT PLAN for LEICHHARDT PARK CHILDCARE CENTRE 1. LOCATION The project address is located in Leichhardt Park, Mary Street Lilyfield. The site is bounded by Mary Street to the
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More informationReview of Plans and Specs from a Constructability Perspective
Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability
More informationPurple Line Extension. Beverly Hills Community Meeting August 22, 2016
Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section
More informationPRECAST CONCRETE GIRDER ERECTION
7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks
More informationBUILDING THE MERSEY GATEWAY a step by step guide
BUILDING THE MERSEY GATEWAY a step by step guide BUILDING THE MERSEY GATEWAY a step by step guide Bridge pylons Elevated approach viaduct Supporting piers Main bridge deck Stay cables INTRODUCTION Construction
More informationSR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA
ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN
More informationRailway Bridge: Design and Detailing for Construction
Railway Bridge: Design and Detailing for Construction R. A. Presland 1, D. A. Fleming 1, M. A. Callaghan 1, R. J. T. Park 1 and W.R. Rushbrook 2 Abstract Holmes Consulting Group have been involved in a
More informationFURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP
A. TECHNICAL INFORMATION OF OUR FOUNDATION WORKS The major types of our foundation works (with illustrative diagram, where applicable) are set out below: 1. Bored piles 0.80m 3.5m pile shaft By Grabbing
More informationAdvantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)
Advantages / Disadvantages of Piling Methods In this Piling Advice Note we will explore the advantages and disadvantages of differing types of piling methods. Continuous Flight Auger (CFA) The pile is
More informationSPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.
2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction
More informationThe Construction of the Langham Place in Mong Kok An Introduction
The Construction of the Langham Place in Mong Kok An Introduction Artist Impression of Langham Place r o j e c t c o m p r i s i n g a i l / h o t e l c o m p a n o f f i c e / r e t Fast Fact The site
More informationWalls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.
TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported
More informationLesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD
Lesson 2 Substructure Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD Outline Syllabus 1. Demolition 2. Site problems 3. Substructure 4. Basements 5. Structural Frames 6. Floors 7. External walls
More informationConceptual Design Report
Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More information4.0 CONSTRUCTION METHODS AND ACTIVITIES
4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential
More informationGEOTECHNICAL SERVICES
GEOTECHNICAL SERVICES Aarsleff Ground Engineering EXPERIENCE: Aarsleff s expertise as Ground Engineers is evidenced not only by its 25 years in UK construction and its dedicated staff, but in the decades
More informationEXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10
EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street
More informationMIXED ACTIVITY ZONE. Chapter 4. Mixed Activity Zone
Chapter 4 Mixed Activity Zone 4. MIXED ACTIVITY ZONE 4.1 RESOURCE MANAGEMENT ISSUES 1. Activities adjoining main arterial roads can adversely affect the safety, sustainability and efficiency of the network.
More informationTraffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))
11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of
More informationSEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE
SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE Paul Gauvreau University of Toronto, Canada (formerly J. Muller International) Thomas E. Kelly, Jr. Earth Tech/J.
More informationCarpinteria Avenue Bridge Replacement Project Description Introduction
Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with
More informationJSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with
More informationThe HKIE Structural Examination Written Examination 2017
The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question
More informationE13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION
HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed
More information7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by
Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than
More information1 Introduction. 2 Site Description. Auckland Transport Private Bag Auckland 1142 New Zealand. 2 March Attention: Sunil Kariyawasam
21 Pitt Street PO Box 6345, Auckland 1141, New Zealand T: +64 9 300 9000 // F: +64 9 300 9300 E: info@beca.com // www.beca.com Auckland Transport Private Bag 92250 Auckland 1142 New Zealand Attention:
More informationTENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2
TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions
More informationHastings District Council. Whakatu Arterial Link Traffic Management Plan
Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...
More informationSIEA LUNGGA POWER STATION RETAINING WALL
SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor
More informationAn Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System
An Introduction to Metal Foundation System By Michael L. Schumaker, P.E. Introduction Various types of deep foundations are routinely used to support structures. Selection of the appropriate type of deep
More informationConstruction Noise Management Plan
Construction Noise Management Plan Victoria Park Viaduct Side Protection Upgrade Project 27 November 2014 Final Page 2 Record of amendment Revision Description of change Effective date Updated by Incomplete
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationTagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment
Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment
More informationDesign and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway.
Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway. ABSTRACT James Nasr, Senior Bridge Engineer, Cardno The Nan-Tien Pedestrian Bridge project
More informationAn indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20.
The land required for the Sydney Park construction compound would be used temporarily throughout construction only. The construction compound site would be rehabilitated at the completion of construction,
More information13. NETWORK UTILITIES
13. NETWORK UTILITIES Overview The Project directly affects a number of existing network utilities, including electricity transmission and distribution lines, telecommunications, water supply, wastewater
More informationPlessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions
Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared
More informationACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE
ACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE JOHN MITCHELL, MEHEDI CHOWDHURY, MICHAEL CHAN, PETER WILES Opus International Consultants Ltd SUMMARY Adopting an Accelerated Bridge
More informationENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM
ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project
More informationULDA Decision Notice
ULDA Decision Notice Site Address Bowen St, Roma Real property description Lot 142 SP250497 Type of approval UDA development approval subject to conditions Aspects of development Reconfiguring a Lot with
More informationConstructability Guidelines
Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final
More informationCode of Construction Practice Part B: Site Specific Requirements
Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Blackfriars
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More informationNorthern Busway - Bridge Structures Linking Communities, New Zealand
SYNOPSIS Northern Busway - Bridge Structures Linking Communities, New Zealand Ted Polley, Kevin Crawford, Beca Infrastructure Ltd This project provides a new two lane busway located adjacent to Auckland
More information15. Network utilities
15. Network utilities Overview The Project will affect a number of existing network utilities within the Project area. This will require the protection and / or relocation of these utilities. The NZTA,
More informationConstruction Innovations / Sustainability
Category: 2 Meeting the Challenge of a Difficult Job Specialty Contractor Contractor: Baker Concrete Construction, Inc. Project Name: Confluence Park Tower Project Overview Construction projects are never
More informationAppendix P. Design Philosophy Bridges
Appendix P REPORT S T R U C T U R A L A N D C I V I L E N G I N E E R S PEKA PEKA TO NORTH OTAKI EXPRESSWAY CONTRACT NO. 440PN: DESIGN PHILOSOPHY BRIDGES PREPARED FOR NZ TRANSPORT AGENCY 12 SEPTEMBER 2011
More informationAPPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014
GEOTECHNICAL INVESTIGATION UPDATE. CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 October 5, 2013 Project No. SCR-0720 SANTA CRUZ SEASIDE COMPANY Craig French 911 Center Street, Suite B Santa
More informationDISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS
DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver
More informationKicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd.
Kicking Horse Cantilever Structure Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Brian Borton, P. Eng., Klohn Crippen Berger Ltd. Paper prepared for
More informationAPPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer
APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationWelcome.
Welcome Welcome to the consultation event for the proposed Construction and Environmental Management Plan (CEMP) for Taylor Wimpey Central London s development of Mount Pleasant. The CEMP relates to Phoenix
More informationTRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT
P a g e 0 Prepared for: Trinity Development Group, Inc. TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT OTTAWA, ON November 2016 P a g e 1 TABLE OF CONTENTS
More informationConstruction Management Plan (CMP) 227 Princess Highway, Dandenong
Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale
More informationPossible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan
Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible
More informationThe Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok
The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District
More informationHamilton Rapid Transit Preliminary Design and Feasibility Study
Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT
More information1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3
Contents 1. Introduction 3 2. Selection of Pile Type 3 3. Soil Report / Boreholes 3 4. Obstructions 3 5. Design and Installation of Piling Mat 3 6. Permit to Dig 4 7. Setting out 4 8. Water 5 9. Attendant
More informationDESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.
DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change
More informationAuckland Transport Code of Practice 2013
26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways
More informationDESIGN OF ROAD OVERBRIDGES
Civil Engineering Technical Requirement CIVIL-SR-001 DESIGN OF ROAD OVERBRIDGES Revision: G Updated: 30 May 2011 Queensland Rail 2011 Reproduction by any means (including electronic, mechanical, photocopying,
More informationIntroduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring
Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot
More informationModular System Advantages
Modular System Advantages The Modular System advantages can be summarised as follows: Truly Modular Off-site build Competitive cost Multi-storey capability Fits any shape, any size Fast programme completions
More informationSOUTH MEDFORD INTERCHANGE BRIDGES
Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationURBAN SETTLEMENT ZONE - RULES
URBAN SETTLEMENT ZONE - RULES.1 Rule Statement The following rules, shall apply to all land shown as being within the Urban Settlement Zone in the District Plan Maps. These rules shall be read in conjunction
More informationConstruction Method Statement
Construction Method Statement Planning Application Phase 17 October 2014 for 79-85 Monier Road London E3 2PS Penten Group Ltd 816 Garratt Lane London SW17 0LZ Tel: 020 8772 4040 Description Contents Page
More informationShelly Beach Overbridge Modification, Auckland
Shelly Beach Overbridge Modification, Auckland Geoff Brown, BEng, CEng, MICE, MIStructE, MIPENZ, SYNOPSIS Opus International Consultants, Wellington Shelly Beach Overbridge is located on one of the busiest
More informationPermeability across the entire site within the General Residential Zone is a minimum of 30%.
Partly Operative District Plan Rule Assessment The following assessment is to demonstrate compliance or non-compliance with the rules of the Partly Operative District Plan. The proposed duplex dwellings,
More informationNo. 1 SPINNINGFIELDS MANCHESTER
No. 1 SPINNINGFIELDS MANCHESTER Client: Project Manager: Description: Allied London Gardiner & Theobald Asbestos Removal Demolition Enabling Works Date: October 2014 to July 2015 Duration: Location: 41
More informationSINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.
SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical
More informationStage 4 Geotechnical Investigations Information Sheet
Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical
More informationProgressive Erection Applied to Box Girder with Strutted Wing Slab
Progressive Erection Applied to Box Girder with Strutted Wing Slab Koji Osada 1, Taketo Kanamoto 1, Kimito Saito 2, Takahiro Arai 2 1 Introduction The Uchimaki Viaduct is a multi-span continuous box girder
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationLinfairn Wind Farm Addendum Chapter A3: Project Description
A3. PROJECT DESCRIPTION 3.1 Introduction This chapter provides a description of the changes to the Project since the ES was published. An outline Construction Environmental Management Plan (CEMP) is included
More informationDistrict of North Vancouver Construction Traffic Management Plan Guidelines
District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction
More informationUNDERPINNING A CRANE FOUNDATION
UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New
More informationDiaphragm wall Construction
Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support
More informationHale Allen Jones The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence Submission
The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence - 2003 Submission Details of Project Location Jarrold Whitefriars Office Development Whitefriars, Norwich. Project
More informationNeptune Cargill Overpass Extension
Project Environmental Review UPDATE November 23, 2017 Northshore Waterfront Liaison Committee Teck Agenda Project Objectives Project Description Project Discussion VFPA PER process Project Review Status
More informationSECTION A1 EXCAVATION AND BACKFILL GENERAL
SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such
More informationLandscaping and Fencing
Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing
More informationCode of Construction Practice Part B: Site Specific Requirements
Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Deptford
More informationRapid Axial Load Testing of Drilled Shafts
Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More information