ANALYSIS AND REMEDIATION OF THE PINOPOLIS DAM ABSTRACT. During the course of routine review and analysis Santee Cooper, their consultants, and

Size: px
Start display at page:

Download "ANALYSIS AND REMEDIATION OF THE PINOPOLIS DAM ABSTRACT. During the course of routine review and analysis Santee Cooper, their consultants, and"

Transcription

1 ANALYSIS AND REMEDIATION OF THE PINOPOLIS DAM Mark Carter P.E. 1 3 Steve Collins P.E., Ph.D. Ray Pinson E.I.T. 2 Paul Rizzo P.E., Ph.D. 4 ABSTRACT During the course of routine review and analysis Santee Cooper, their consultants, and the FERC determined that the Pinopolis Dams did not have an adequate margin of safety against failure during and immediately subsequent to a postulated recurrence of the famous 1886 Charleston Earthquake. Subsequent soil testing, computer stability analyses, research of remedial alternatives, and implementation of a pilot testing program led to a seismic mitigation plan that was engineered to include state of the art ground modification in conjunction with downstream berms. In all, the work consisted of constructing nearly 3,500 column elements requiring over 30,000 tons of rock, installing over 10 miles of perforated drainage pipe, and placing nearly 310,000 cubic yards of berm material over the top of the stone column areas at various locations along the 6-miles of dam. This paper summarizes the evaluation of project parameters such as seismic loading and soil properties, the various remedial alternatives considered, the engineering calculations associated with the selected remediation scheme, and the construction methods used during implementation of the Pinopolis East Dam Seismic Mitigation Project. INTRODUCTION The Federal Energy Regulatory Commission (FERC) mandates periodic inspections and review of design basis for all licensed hydroelectric projects in the United States. During the course of routine review and analysis Santee Cooper, their consultants, and the FERC determined that the Pinopolis Dams did not have an adequate margin of safety against failure during and immediately subsequent to a postulated recurrence of the famous 1886 Charleston Earthquake. The Pinopolis Dams essentially consist of three earthen embankments, named the West Dam, East Dam, and the East Dam Extension as shown in plan view on Figure 1. The West Dam and East Dam are separated by a concrete gravity section that includes a lock 1 Manager, General Construction, Santee Cooper, Moncks Corner, SC Principal Engineer, General Construction, Santee Cooper, Moncks Corner, SC Lead Engineer, Division of Dam Safety and Inspections, FERC Atlanta Regional Office, 3125 Presidential Parkway, Atlanta, GA Principal, Paul C. Rizzo & Assoc., Expo Mart Suite 270-E, Monroeville, PA 15146

2 to allow navigation between the Cooper River and the impounded Lake Moultrie. The SANTEE RIVER East Dam Extension East Dam West Dam COOPER RIVER Figure 1. Location of the Pinopolis Dams in Eastern South Carolina West Dam was remediated during the late 1980 s by constructing downstream bolster sections in those areas where the foundation sand was particularly loose. At these bolster sections, the loose sand was over-excavated and replaced as structural fill. The remediation of the East Dam and the East Dam Extension, which are founded on loose sands similar to the West Dam, are the subject of this paper. Initial stability analyses resulted in acceptable factors of safety for the structures under static conditions. However, factors of safety representing post-seismic stability were found to be less than 1.0 following dynamic loading with a 0.42g peak horizontal acceleration. Following several years of soil borings, laboratory tests, computer stability analyses, and research of remedial alternatives, a remediation program was developed which consisted of two main elements - (1) stone columns designed to relieve excess dynamic pore pressure and (2) a downstream berm of varying height over the stone columns. The following sections discuss the design and construction aspects for seismic mitigation of the Pinopolis East Dam and East Dam Extension.

3 GENERAL INFORMATION The Santee Cooper Hydroelectric Project was constructed from 1939 to 1942 in an attempt to alleviate the effects of the Great Depression on the poverty-stricken Southeast. Over 156,000 acres of bottomland were impounded to form Lakes Marion and Moultrie which are connected by a 6.5-mile canal. At the time of construction, Santee Cooper was boasted as being the largest land-clearing project on the North American subcontinent while nearly 40 miles of dams and dikes were constructed in order to generate hydroelectric power for the region. The Pinopolis Dams were constructed to impound the 60,000-acre water body, Lake Moultrie. The dams are compacted-fill earthen structures having a combined total length of 7.5 miles. They are located in the vicinity of Moncks Corner, South Carolina as indicated in Figure 1. The dams and powerhouse are approximately 35 miles upstream of Charleston, SC and the Atlantic Ocean. The Santee Cooper Project, which combined the Santee and Cooper Rivers to form the two connected lakes, is situated on the Atlantic Coastal Plain. The foundation soils in this part of the Coastal Plain consist generally of about 70 feet of sand, silty sand, and clay overlying the dense, somewhat cemented Cooper Formation. The Cooper Formation is the preferred founding medium for most foundations in the Charleston area. The dams were constructed 60 years ago over a layer of relatively low-blow-count natural material that is subject to liquefaction during a substantial seismic event. This layer is generally 15 to 20 feet below the ground surface at the toe of the dam and varies from 5 to 10 feet in thickness. The weak layer overlies the Cooper Formation as shown in Figure 2. The residual strength of this loose sand is very low, in the range of 100 psf, as determined from back-calculation of known liquefaction failures, both static and dynamic, as shown later in Figure 3c.

4 Figure 2. Typical Cross Section of the Pinopolis East Dam The stiff clay and clayey sands above the liquefied layers of loose sand are relatively dense and the dam embankment is a well-compacted, low-plasticity clay (CL). The maximum embankment height found near the powerhouse is approximately 60 feet above the downstream toe; however, the average embankment height over the entire 6-mile length is around 28 feet. The crest is approximately 20 feet wide with a typical top elevation of 88.0 MSL. The upstream face is covered with 10 inches of porous concrete for slope protection and is inclined at an average 2.8 horizontal (H):1 vertical (V). The downstream slope of the dams are grassed and inclined at an average 2.25H:1V. The normal pool lake elevation is 75.0 MSL, which equates to 13 foot of freeboard for the impoundment structures. The controlling earthquake in the area, and for a major portion of the East Coast of the United States, is a postulated recurrence of the 1886 Charleston Earthquake. The epicenter of this event is estimated to have been near Summerville, SC northwest of Charleston and the scene of numerous low magnitude events as many as two or three per year. The 1886 event was felt as far away as New York and Pittsburgh and caused extensive damage in the Charleston Area, including liquefaction. Paleoseismic investigations conducted over the past 20 years have yielded evidence of prior events large enough to cause liquefaction, with a recurrence interval estimated at approximately 450 years. The Modified Mercalli Intensity of the 1886 Event is estimated to be in the range of X near its epicenter. Moment magnitude estimates (there were no records) range from 6.9 to 7.6, but most professionals accept M 7.3 as being a reasonable estimate. A recurrence of this event near its epicenter is estimated to cause a peak ground acceleration at the East Dam of 0.42g. This estimate is the basis of the seismic design criteria adopted for this remediation project. Initial post-seismic stability analyses used the conventional and generally accepted effective stress approach with estimated excess pore pressures in the non-liquefied stiff clays of the foundation and embankment. This approach lead to factors of safety of approximately 0.6 to 0.7 at various cross sections. At this time (1994), Dr. Collins joined the regulatory oversight team and recommended modification of two important factors in the stability analyses, namely: Use of undrained shear strengths for the stiff, low permeablity clayey soils, For wedge or sliding block failure mechanisms, change from the Spencer solution method to the Lowe & Karafiath procedure, also commonly called the Corps of Engineers' method. This change was in solution techniques only, and did not incorporate the strength interpolation procedures ascribed to these methods.

5 The reasons for and implication to stability of these modifications are as follows: The first recommendation acknowledges that the two-step stability analysis developed by John Lowe et al, using undrained strengths for the embankment and stiff foundation strata, would better represent a potential dam slope failure in the moments and first several days following an earthquake at this particular site. In this short time frame, the low permeability soils must fail undrained, neither expelling nor taking up water. Migration of pore pressures from the deep liquefied stratum and from the reservoir would eventually eliminate the negative pore pressure effects that provide relatively high, undrained strengths in stiff soils. To prevent the migration tendency, a row of closely spaced drains at the downstream toe, that would bleed off the elevated pore pressures in the liquefied zone, was mandated as a minimal requirement whenever undrained strengths of non-liquefiable soils was used. Finite difference analyses concluded that the these liquefied strata pore pressures would be significantly reduced after two days by effective drainage into stone/sand columns at the toe. The second recommendation arose when noting that the inter-slice force for wedge failure surfaces was nearly horizontal when using the Spencer solution routine, implying no shear interaction between blocks. While the Spencer routine produced a lower FS for the critical failure surface compared to circular failure surfaces, the implication for stresses and forces is not kinematically possible. The critical failure surface is deep, passing through a long, relatively horizontal zone of liquefied sand, and then rising as a passive wedge to the ground surface, daylighting downstream of the toe of the dam. The upward movement of this wedge creates a shear displacement with the central block, and a downward shear force on the passive wedge at this interface, increasing stability in either drained or undrained soils. The fact that "complete equilibrium" programs satisfy equilibrium does not guarantee that the stresses are kinematically possible, or that the resulting FS is reasonable. The solution routine was switched to the methods developed by John Lowe, wherein the inter-slice angle could be pre-chosen. This value was conservatively set at 10 degrees, improving the stability results in both the passive and active wedge areas. The net effect of making these two modifications to evaluating the post-seismic stability resulted in a typical FS for the East Dam of around 1.10, below the required value of 1.3, but indicating much improved conditions when compared to the values obtained in the conventional analyses. A typical post-seismic FS for the East Dam Extension was 1.0, also indicating remediation was necessary. ADOPTION OF UNDRAINED STRENGTH PARAMETERS In order to perform the stability and deformation analyses, the shear strength for the soil predicted to undergo shear failure was assessed under three classifications: Non-Liquefied Soils;

6 Liquefied Soils; and Treated Soils. The shear strengths for Non-Liquefied Soils used in the stability analysis are summarized in Table 1 and typical summary plots of triaxial test data are shown in Figures 3a and 3b. SHEAR STRENGTH ON FAILURE PLANE (PSI) (PSF) STRENGTH ENVELOPE SATURATED EMBANKMENT 1,440 2,880 4,320 5,760 7,200 8,640 C = 864 PSF CS Strength Envelope based on regression analysis NORMAL STRESS (PSI) calculated used E4 E10 5,760 φ=25.8 4,320 2,880 63C CS Strength Envelope 67D used for Stability Analysis 1,440 69D φ=25.8 (PSF) Figure 3a. Soil Strength Plot for Saturated Embankment Material SHEAR STRENGTH ON FAILURE PLANE (PSI) (PSF) STRENGTH ENVELOPE STIFF CLAY (ALL DATA) 1,440 2,880 4,320 5,760 7,200 C = 1,034 PSF CS Strength Envelope based on regression analysis and used for Stability Analysis φ= NORMAL STRESS (PSI) 68C 67G E11 E25 64A 70C 8,640 4,320 2,880 1,440 (PSF)

7 Figure 3b. Soil Strength Plot for Stiff Clay Material Table 1. Strength Parameters (Non-Liquefied Soils) Drained Strength Undrained S trength* Material φ ( o ) C (PSF) φ ( o ) C (PSF) Unsaturated Embankment Saturated Embankment Stiff Clay Clayey Sand Ditch Fill Materials Rip-Rap Dense Sand Borrow Pit Mud SP material * C and φ refer to the intercept and slope in the τ ff versus σ fc format. A few supplementary comments pertaining to Table 1 are appropriate: 1. Undrained strengths were used in all instances where at least one row of stone columns, spaced 15-foot on centers, were to be installed at the toe of the dam, parallel to the axis. Utilization of undrained strengths for the stiff clay in the dam and foundation was a critical consideration in the stability analysis of the remediated structure. 2. Conservatively, the Upper Sands were assumed to liquefy unless the SPT blow counts were relatively high (N>30), ignoring any potential base isolation effects provided by the lower sands. In areas where these soils are near the surface at the toe of the dam, the lower of the drained strength or the post-liquefaction residual shear strength was used in the analysis. 3. Drained Strength Parameters were used for all SP soils with proper allowance for dynamic pore pressure. Figure 3c was used to assess the Residual Undrained Shear Strength of liquefied soils. This figure is taken from the work of Seed and Booker, 1976 and modified by expanding the abscissa to accommodate a broader (N1) 60-CS range. The undrained residual strength for the Lower Sand layer ranged between 75 psf and 435 psf depending on the (N1) 60-CS. The undrained residual strength for the Upper Sand Layers was interpreted to be in the range of 240 psf and 940 psf, which again depended on the (N1) 60-CS.

8 Figure 3c. Undrained Residual Shear Strength With the foundation and embankment soil strengths identified, Santee Cooper conducted a full-scale stone column test program to assess the technical and economic issues associated with the use of vibro-replacement as a remediation technique. Vibroreplacement, commonly referred to as stone columns, is generally accomplished by forcing rock into the ground by a combination of compressed air and vibration to form a dense column element. The goal of which creates a composite material of lower overall compressibility and higher shear strength than that of the native soil alone. Three separate test areas were selected along the toe of the East Dam and East Dam Extension. At each Test Area, nominal 42 diameter stone columns were installed in a triangular pattern with various spacings ranging from 6 to 10 feet. The evaluation was conducted by comparing Before and After Standard Penetration Test Results and Cone Penetrometer Test Results. In addition to verifying the applicability and cost issues associated with stone columns at this specific site, several important conclusions were developed for use in the final design. 1. Regardless of the soil classification, it was not practical to obtain adequate density to preclude liquefaction as measured with the SPT in the loose sand stratum at the

9 bottom of a stone column. Some other means of supplemental strengthening for this marginally improved material had to be considered. 2. The fines content of the soil being improved can have a significant negative effect, to the degree that, for some of the lower sands containing a relatively high percentage of fines, the desired benefits associated with stone columns are not realizable. 3. Using two sets of SPT Borings, we assessed the potential for beneficial aging in the treated soils. We found no real increase in N values due to aging within a time frame of about 4 to 6 weeks and again after four years with tests in Because of the inability to achieve substantial improved density at the bottom of the loose sand overlying the dense Cooper Formation, all parties concluded that the use of stone columns to preclude liquefaction could not be accomplished at this particular site. 5. Enlarged diameter bases could be achieved in the lower sands without excessive heave or other negative consequences to the existing dam. However, conducting the pilot test program was extremely beneficial, since it allowed Santee Cooper to eliminate a remedial alternative that was not viable for the project. It also allowed the designers to focus on the use of stone columns for drainage purposes and as structural elements, rather than densification, as a more efficient means of achieving increased shear resistance in the foundation. Therefore, the method of treatment for potentially liquefiable soils chosen for remediation of the East Dam and East Dam Extension consists of the installation of one to several rows of stone columns at the downstream toe in combination with an overlying berm where necessary. The installed columns supply the necessary drainage of earthquake-induced excess pore pressures and justify the use of undrained strength parameters in the stability analyses. Hence, the strength of the treated soils is based on the composite strength of the stone columns and the soil between the columns where multiple rows are used. SELECTING THE REMEDIAL APPROACH Throughout the data collection and analysis process, numerous options for seismic remediation were considered including the following: Over-excavation and replacement of the loose soil foundation layers at the toe of the dam, Various forms and types of grouting, Dynamic compaction with a falling weight, and

10 Downstream bolsters similar to the West Dam remediation, with stone columns in the foundation. With due consideration given to lessons learned from the West Dam project and from the pilot testing program, engineers selected stone columns used strictly as a structural and drainage element. Construction of an overlying berm would also be necessary at various sections along the dam to enhance the vertical stress in the columns, thereby increasing the post-seismic stability of the structures. Much effort was expended towards optimizing the remedial design by varying the column diameters, spacing, and berm height to target the most economical alternative. Each time a specific diameter, spacing, and berm height was selected, an individual stability run was necessary to ensure that the factor of safety and deformation criteria had been achieved. Designers and engineers had to find the break-even point of adding berm, increasing column diameter or rows, or varying the column spacing. These four (4) variables were rarely consistent for each cross-section analyzed due to the variability of foundation soils and the initial factor of safety at each specific location along the dam. For the East Dam, this typically required raising the FS from approximately 1.10 to The design process is generally termed the "Japanese" method, and details can be found in literature by Goughnour, et al. Once a stone column and berm configuration is chosen, the shearing strength through the column must be calculated, which depends on the shear surface inclination. For this project, the critical failure surface was known to be through the weak liquefied sand stratum. Due to its thin nature, only horizontal failure surfaces needed to be considered. The general scheme for the East Dam is shown in Figure 4. The equilateral triangular arrangement for stone columns was chosen, with two rows of enlarged base stone columns constructed on 12-foot centers, with bases 6 feet in diameter in the loose sand and nominal 30-inch columns rising to the surface. This configuration equates to one stone column per six linear feet of dam. The capacity of the stone column is thus divided by 6 feet to yield the applicable force in the slope stability program. This force per foot is further divided by a length representative of the stone column remediation area, in this case 20.8 feet, to yield a stress, or cohesion, for input into the stability program. The shear capacity of the column depends on how much load from the berm is attracted into the stiffer column versus the area subject to liquefaction between columns, and is expressed as a ratio S rv. Taking a simplified approach, which does not fully account for strain compatibility, Goughnour et al, recommend a range of 3 to 5 for S rv. A value of 3 is used in the example below. In this case, it is the higher modulus of the enlarged stone pedestal compared to the loose sand surrounding the pedestal that allows the column to attract more than the average vertical stress from the overlying berm. Thus, the column is effectively 6 feet in diameter rather than 30 inches.

11 Given: γ T Berm = 125 lb/ft 3 γ T Column = 110 lb/ft 3 Berm Height = 9.5 feet 30-inch columns w/ 72-inch enlarged base = 28.3 ft 2 2 rows of columns, spacing = 12 feet o.c. Calculation: Berm stress = 9.5 feet x k/ft 3 = 1.19 ksf average Foundation stress = 15 x ( ) = ksf Unit cell = 6 ft x 20.8 ft = ft 2 In a 6 ft x 20.8 ft cell (124.8 ft 2 ) there is one column: A.8 ft 2 r = area ratio = 28.3 ft 2 /124 = S rv = 3 = σ s /σ c σ c =.33 σ s σ s (0.227) +.33 σ s ( ) = 1.19 ksf σ s = 2.46 ksf Vertical stress on top of base (berm + foundation overburden): 2.46 ksf ksf = 3.17 ksf Shear from column: 3.17 ksf x 28.3 ft 2 x tan φ; where φ = 36Ε for # 789 granite stone = 65.2 kips Shear from liquefied soil around column, with residual strength of 100 psf: ( ) x (124.8 ft 2 ) x 0.1 ksf = 9.6 kips Total shear : 65.2 kips kips = 74.8 kips Stress: 74.8 kips/124.8 ft 2 = 0.60 ksf, treated as cohesion This 0.60 ksf is then treated as cohesion in a zone 20.8 feet wide in the loose sand stratum, representative of the conditions at the top of the loose sand. Minor increases in strength with depth in the stratum are neglected. Corresponding calculations up the 30- inch column could be made, but at this site the additional strength provided in the stiff portion of the foundation was not needed to produce acceptable FS values.

12 Computer runs of slope stability were then examined to confirm that the critical failure surface was horizontal through the remediation area. The S rv of 3 and φ = 36Ε for the stone column base are lower limit values that provide the additional force to raise the stability of the critical failure surface to FS = Values in the range of S rv = 4 and φ = 42Ε would have been acceptable, yielding a cohesion of 0.80 ksf and somewhat higher calculated FS. Recognition of a modest N value increase of 3-5 in this remediation zone, as determined in the 1995 test sections, would also increase the strength by an additional 50 psf, and has been neglected in the above calculations. The adopted shear strength took no credit for dissipation of pore pressures during or after the earthquake. Post-seismic stability must be maintained immediately after the earthquake when the dynamic excess pore pressures are still in effect and not yet dissipated. As discussed previously, the dam stability will increase with time as the pore pressures dissipate in the liquefied zone. Within several days, the liquefied zone will reconsolidate to the point where the pre-earthquake static stability has been reestablished. CONDUCTING THE REMEDIAL WORK In January of 2002, Santee Cooper initiated the stone column portion of the Pinopolis East Dam and East Dam Extension Seismic Mitigation project. The specialty contractor performing the work was Hayward Baker, Inc. (HBI), of Tampa, Florida - specializing in ground modification, site improvement, and soil stabilization. Installation of the columns was accomplished by using the Dry Bottom-Feed Vibro-Replacement method in accordance with the FERC-approved remediation plan. The rock backfill used for the stone column work was SCDOT #789 granite stone. Extensive filter criteria analyses were conducted to verify the adequacy of the 789 stone for column production in the Pinopolis Dam foundation soils. Several grain size distributions representative of the liquefiable layers along the dams were compared to the gradation of the 789 stone. Typical filter criteria comparing the D 15 of the filter material to the minimum D 85 of the contact soil were utilized. The 789 stone met this criterion and was selected for use on the project. A supplier for the aggregate was found to be only two hours from the project site. In order to allow for penetration of the vibrator, the Contractor pre-augured each stone column using a 30-inch diameter auger as shown in the Figure 5. The 30-inch diameter hole was predrilled one foot into the dense Cooper Formation, which was generally 30 feet below the ground surface. After reaching full depth, the auger was reversed to reduce the amount of excess material removed from the hole. The 72-inch diameter column portion was installed starting approximately one foot into the dense sand and the column was then constructed in approximate 2-foot lifts. Pursuant to the project specifications, when the recorded vibrator amperage exceeded 70 amps of the free hanging amperage, the minimum 72-inch diameter requirement was waived and the crane operator pulled up to the next lift. As expected, this scenario rarely occurred. Next, the

13 30-inch diameter column portion was installed from the bottom of the stiff clay layer to the ground surface. Figure 5. Drill Rig and Stone Column Crane at the toe of the Pinopolis East Dam Stone Column Construction Procedures: The Contractor installed the stone columns utilizing a nominal 30-inch diameter bottom feed S-23 vibrator. The vibrator was driven by an electric motor powered by a 250 kw Caterpillar diesel generator. The motor type was a 3-phase squirrel cage, delivering 161 hp at 1,800 rpm, producing 23 tons of centrifugal force. The length of the base vibrator was approximately ten feet and the weight was three tons. Extension tubes were added to reach the treatment depths. The stone backfill was delivered to the tip of the vibrator using an eightinch diameter feed tube attached to the vibrator. The top of the feed tube was connected to a pressure chamber with a 1.25 cubic yard capacity to hold the stone for delivery to the vibrator tip. With the chamber pressurized, an air-controlled valve operated the door to allow the rock to fall into the chamber from the hopper. The stone was delivered to the hopper via a two cubic yard skip that was raised to the hopper once it was filled with stone from a front-end loader. The entire vibrator assembly was suspended from a 150-ton

14 crawler-type crane as indicated in Figure 6. Figure 6. Stone Column Crane and Vibrator The stone column production was monitored by the Contractor using a real-time automated recorder. The data recorded included the column identification number, installation time, depth of probe, height of each lift, weight of material added to each lift, column diameter for each lift, and air pressure of the gravel feed system. This data was provided to the project engineer in the form of daily reports that included a log of pertinent information and a graph for each column. Each graph showed the column diameter, column depth, construction amps, penetration amps, and air pressure. The daily logs were used to tabulate the cumulative column depths and rock quantities that were contract pay items. Also, each graph was used for quality control purposes since the minimum column diameter and vibrator amperage had to be achieved with very little tolerance pursuant to the project specifications. The following work was accomplished over a 10-month period ending October 4, 2002: Two (2) rows of 30-inch top diameter with 72-inch base diameter stone columns were installed on 4,125 linear feet of the East Dam proper. HBI constructed 553 stone columns with a cumulative footage of 16,251 feet requiring over 8,800 tons of rock backfill. On the East Dam Extension, three (3) rows of 30-inch diameter stone columns were installed on 9,300 linear feet and a single row of 30-inch diameter columns was installed in a 9,000 linear foot section of dam that required pore pressure relief only. HBI constructed 2, inch diameter stone columns on the East Dam Extension with a cumulative footage of 98,103 feet requiring over 21,000 tons of rock backfill. Installation of the Drainage Netwo rk: Following installation of the columns, consideration had to be given to conveying water from the columns that would be generated from relief of excess pore pressures during and after a seismic event. As opposed to a conventional sand/gravel drainage blanket, a piping network was designed as a more economical alternative. As indicated in Figure 7, the piping system is composed of 18 wide

15 Figure 7. Placement of Drainage Pipe at Toe of Dam corrugated and perforated high density polyethylene pipe to route upward flow from the columns and discharge the accumulated water out the toe of the new berm. The pipe is offset from the high vertical stress zone over the columns, and connected by a shallow trench backfilled with 789 stone. A six foot wide strip of filter fabric over the columns and trench prevent infiltration of soil fines from the overlying berm. The flow capacity of this pipe used in a horizontal manner with 1 of head is 28.0 gpm. Flow rates from the columns using relief well calculations and surrounding soil permeability were conservatively estimated to be 1.5 gpm. The piping network shown in the photograph parallels the dam and continues through the areas where multiple rows of columns were installed with an overlying berm. This drainage design met the projected flow requirement and represents distinct advantages from an installation aspect in terms of uniformity, handling, and cost. Berm Construction: As mentioned in the remedial approach section, the columns needed to be loaded with mass in order to effectively increase the composite soil strength at depth. Therefore, a berm ranging in height from 9.5 to 13.5 feet was constructed over the stone columns. Various berm crest widths, ranging from 56 to 40 feet, were required to cover the different spacings and rows of stone columns. On the East Dam there was sufficient area available to flatten the berm slope to 2.5H:1V; however, the East Dam Extension had very little room to work as a result of the original borrow pit location. Since original construction in 1940, the borrow pit area has evolved into a pristine wetland area providing habitat to many species of plants and animals. Therefore, the engineering design in this area had to take into account the potential environmental impacts associated with the work. Tighter column spacings and a 1H:1V berm slope prevented encroachment into the downstream wetland boundary. The materials for berm construction were obtained from borrow areas in the vicinity of the project and meet the USCS classification of SW, SM, SP, SC or CL. The berm material was specified to have no more than 50% fines (material passing the #200 sieve) by weight. Over 300,000 yards of berm material were placed in compacted lifts of 6 inches or less and compacted to 95% of the maximum dry density obtained from the Standard Proctor test (ASTM D-698). The moisture content was required to be + 4% of the optimum. A combination of smooth drum and padfoot vibratory rollers were used to accomplish compaction which was verified by field testing in accordance with ASTM D and ASTM D SUMMARY The Pinopolis East Dam Seismic Mitigation Project was a cost effective solution to a seismic deficiency problem. With a combination of strategically placed stone columns

16 and downstream berm material, Santee Cooper was able to meet the current earthquake standards for dam structures in addition to safeguarding the downstream floodplain, which includes portions of metropolitan Charleston, SC. The final plan also considered space constraints due to the presence of jurisdictional wetlands downstream of the dam and the economies of scale associated with berm height versus diameter and spacing of stone columns. Several valuable lessons were learned during the analysis, design, and construction phases of the project as follows: In certain circumstances, the use of undrained soil strengths for non-liquefied, stiff clayey soils can be appropriate in evaluating remedial alternatives for embankment stability. Engineering a viable solution also requires a substantial amount of economic analysis. Engineers and designers expended much effort on optimizing the remedial design by varying the column diameters, spacing, and berm height to target the most economical alternative. When applicable, implementation of a pilot testing program can confirm whether or not a selected remedial method will achieve the desired results. The stone column full-scale testing program allowed engineers and designers to evaluate a remedial alternative that is typically used for in-situ soil densification. Test results showed that the stress transfer method was a better technique for the specific site conditions and presented a viable option for increasing the factor of safety against dam failure. During the past 20 years, Santee Cooper has completed an extensive program of seismic analysis, design, and construction for its project embankments. At the conclusion of the Pinopolis East Dam work, Santee C ooper achieved the dam safety goal of meeting the current seismic evaluation standards for its project structures. REFERENCES Barksdale, R. D. and Bachus, R. C., Design and Construction of Stone Columns, Report FHWA/RD-83/026, FHWA, Goughnour, R. R., Sung, J. T., and Ramsey, J. S., Slide Correction by Stone Columns, Deep Foundation Improvements: Design, Construction, and Testing, ASTM STP 1089, Melvin I. Esrig and Robert C. Bachus, Eds., American Society for Testing and Materials, Philadelphia, Seed, H. B. and John R. Booker, Stabilization of Potentially Liquefiable Sand Deposits Using Gravel Drain Systems, Report No. EERC 76-10, Earthquake Engineering Research Center, University of California, Berkeley, California, 1976.

17

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams by James K. Mitchell, Sc.D., P.E., Dist. M.ASCE University of Alberta, Edmonton, Alberta October 6, 2010 1 SCOPE OF THE LECTURE

More information

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT

A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT Karen Dawson, P.E. and Seungcheol Shin, Ph.D., P.E., CH2M HILL, Bellevue, WA, USA Suthan

More information

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003 ODOT Geotechnical Information Exchange Seminar Ground Improvement Martin G. Taube, P.E., P.G. February 4, 2003 Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 ph. (412) 221-4500 fax (412)

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Converting slurry tailings facilities to filtered dry stacks a case history. John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant

Converting slurry tailings facilities to filtered dry stacks a case history. John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant Converting slurry tailings facilities to filtered dry stacks a case history John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant Objectives General discussion on the geotechnical issues. Case

More information

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE 4 3 2 1 D D C C B B A A 4 3 2 1 Thrust Restraint Design Equations and Soil Parameters These equations and soil

More information

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities 1 Introduction This document, developed by the San Francisco Public Utilities Commission

More information

Design Illustrations on the Use of Soil Nails to Upgrade Loose Fill Slopes

Design Illustrations on the Use of Soil Nails to Upgrade Loose Fill Slopes Design Illustrations on the Use of Soil Nails to Upgrade Loose Fill Slopes Geotechnical Engineering Office and The Hong Kong Institution of Engineers (Geotechnical Division) November 2013 2 Disclaimer

More information

ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION

ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION Rolando P. Orense 1, Yukio Morita 2 and Masanori Ide 3 ABSTRACT This paper outlines the mitigation measures performed to

More information

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Specification Guidelines: Allan Block Modular Retaining Wall Systems Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's

More information

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA 73171 JANUARY 06 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION GEOTECHNICAL REPORT I-15

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No Environmental Resources Management January 13, 2017 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0352436 CityCentre Four 840 West Sam Houston Parkway North, Suite 600 Houston,

More information

Taxiway embankment over soft ground using staged construction

Taxiway embankment over soft ground using staged construction Taxiway embankment over soft ground using staged construction R. Wells, X. Barrett & T. Wells Trigon Kleinfelder, Inc., Greensboro, North Carolina, United States ABSTRACT: The Piedmont Triad International

More information

Preview of LEAME Computer Software

Preview of LEAME Computer Software Appendix Preview of LEAME Computer Software Thus far, this book has focused on the fundamental principles and methods for analyzing slope stability using the limit equilibrium method. The computer software

More information

Nonlinear Modeling of Dynamic Soil-Structure Interaction: A Practitioner s Viewpoint

Nonlinear Modeling of Dynamic Soil-Structure Interaction: A Practitioner s Viewpoint Nonlinear Modeling of Dynamic Soil-Structure Interaction: A Practitioner s Viewpoint By (Arul) K. Arulmoli Earth Mechanics, Inc. Fountain Valley, California Workshop on Nonlinear Modeling of Geotechnical

More information

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. H A Y W A R D B A K E R I N C. RIGID INCLUSIONS Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. Above: HBI installed Rigid Inclusions on a congested downtown

More information

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011 APPENDIX A EARTHEN EMBANKMENT VERSION 1.0 March 1, 2011 SECTION A-1: DESCRIPTION OF PRACTICE An earthen embankment is a raised impounding structure made from compacted soil. The embankment is the feature

More information

techie-touch.blogspot.com www.vidyarthiplus.com CE2305 FOUNDATION ENGINEERING 2 MARKS QUESTIONS & ANSWERS 16 MARKS QUESTIONS UNIT -1 1. What are components of total foundation settlement? elastic settlement,

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

t ghi yr Cop

t ghi yr Cop In many situations, soil itself is used as a construction material Highway embankments Railway embankments Earth dams Highway / Airfield pavements Backfilled trenches Landfills When soil is used as foundation

More information

Temporary Structures. Excavations and Excavation Supports

Temporary Structures. Excavations and Excavation Supports UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Excavations and Excavation Supports CM 420

More information

Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California

Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California The First Pan American Geosynthetics Conference & Exhibition 2-5 March 2008, Cancun, Mexico Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California

More information

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM T. C. NEEL and K.BOZKURT ABSTRACT This work shall consist of the design, manufacture

More information

Evaluation of ALDOT Ditch Check Practices using Large Scale Testing Techniques

Evaluation of ALDOT Ditch Check Practices using Large Scale Testing Techniques Research Report No. 2 Project Number: 930 826R Evaluation of ALDOT Ditch Check Practices using Large Scale Testing Techniques Large scale Channel Testing (ASTM D 7208 modified) of Evaluation of ALDOT Class

More information

Vibroflot Modular Product Range

Vibroflot Modular Product Range NTERNTONL CONSTRUCTON EQUPMENT Vibroflot Modular Product Range Deep Vibro Techniques NTERNTONL CONSTRUCTON EQUPMENT Deep Vibro techniques by CE nternational Construction Equipment CE nternational Construction

More information

Challenges in Seismic Stability Analysis of Tailings Dams

Challenges in Seismic Stability Analysis of Tailings Dams Challenges in Seismic Stability Analysis of Tailings Dams David Zeng Dept. of Civil Engineering Case Western Reserve University International Workshop on Seismic Stability of Tailings Dams November 10,

More information

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement Name of Project: Maintenance Dredging AIWW Vicinity Jupiter

More information

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD FOR NCIG CET3 COAL STOCKYARD Charles CH Chua 1, Ming Lai 2, Graeme Hoffmann 2 and Brett Hawkins 1 1 Connell Hatch, Australia, 2 Keller Ground Engineering Pty Ltd ABSTRACT This paper presents an overview

More information

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates LA Transportation Conference: 10 Jan 2011 Drilled Shaft Foundations For Two Mississippi River Bridges in Louisiana Dan Brown and Associates Projects John James Audubon Bridge, St. Francisville New Construction

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

Redi Rock Specification and Installation Manual

Redi Rock Specification and Installation Manual Redi Rock Specification and Installation Manual 1.0 General Scope This Specification covers the Design, Materials and Installation of Redi Rock modular block Retaining and Freestanding Wall systems as

More information

Please include this addendum in your Bid proposal for the above referenced project. Questions are in black ink, and the answers are in red ink.

Please include this addendum in your Bid proposal for the above referenced project. Questions are in black ink, and the answers are in red ink. JAHarchitects, LLC PROJECT NO. 393 RIVERCREST CDD 11560 RAMBLE CREEK DRIVE, RIVERVIEW FL ADDENDUM TO BID PROJECT: RIVERCREST CDD MULTI PURPOSE FIELD MAINTENANCE BUILDING & DOG PARK POOL & CABANNA JAH PROJECT

More information

GEOTECHNICAL REPORT B-1942

GEOTECHNICAL REPORT B-1942 GEOTECHNICAL REPORT TUSCARORA BRIDGE REPLACEMENT B-1942 E.A. 73561 March 2011 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION GEOTECHNICAL REPORT

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp Geneva Dam Design of a Steep, Temporary, Riprap Ramp A Run-of of-river Dam Analysis for Geneva Dam Credit to: Yu-Chun Su, Ph.D., P.E., CFM David T. Williams. Ph.D., P.E, CFM Presentation Purpose History

More information

R-TANK SPECIFICATIONS

R-TANK SPECIFICATIONS TECHNICAL STORMWATER MANAGEMENT R-TANK SPECIFICATIONS PART 1 GENERAL 1.01 Related Documents A. Drawings, technical specification and general provisions of the Contract as modified herein apply to this

More information

Consultant Specifications for Subsurface Investigation & Geotechnical Analysis and Design Recommendations

Consultant Specifications for Subsurface Investigation & Geotechnical Analysis and Design Recommendations Consultant Specifications for Subsurface Investigation & Geotechnical Analysis and Design Recommendations Mn/DOT Geotechnical Section - Office of Materials & Road Research http://www.mrr.dot.state.mn.us/geotechnical/foundations/tcontract.asp

More information

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois AGI Project No. 13-276 Subsurface Investigation Report For the Proposed New Retail Center 9601 South Pulaski Road Evergreen Park, Illinois Prepared for Mr. Feras Sweis FHS Design + Build LLC 2010 West

More information

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide Stormwater Standards Clackamas County Service District No. 1 APPENDIX E Infiltration Testing Guide Table of Contents Appendix E - Infiltration Testing Guide... Page E.1 General... 1 E.2 Basic Method -

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015 Subsurface Investigations PDCA Professor s Driven Pile Institute Loren R. Anderson Utah State University June 25, 2015 Ralph B. Peck (1962) Subsurface engineering is an art; soil mechanics is an engineering

More information

PE Exam Review - Geotechnical

PE Exam Review - Geotechnical PE Exam Review - Geotechnical Resources and Visual Aids Item Page I. Glossary... 11 II. Parameters... 9 III. Equations....11 IV. Tables, Charts & Diagrams... 14 1. Module 1 - Soil Classification... 14

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

UPDATED 04 OCT GEOTECHNICAL INVESTIGATIONS

UPDATED 04 OCT GEOTECHNICAL INVESTIGATIONS 8.0 GEOTECHNICAL INVESTIGATIONS Throughout this section, reference to the Contractor simply means the entity responsible for the subject work. The same procedures and requirements generally apply to anyone

More information

2010 Hayward Baker Inc. (www.haywardbaker.com) 1 of 16. Vibro Systems

2010 Hayward Baker Inc. (www.haywardbaker.com) 1 of 16. Vibro Systems 1 of 16 Vibro Systems 2 of 16 Site Improvement Begins With Hayward Baker Vibro Technologies Contents 4 Vibro Compaction 6 Vibro Replacement 8 Design Considerations Increased Bearing Capacity Reduced Settlement

More information

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM 6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, 23 25 October 2012 THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM Peter BUCHANAN Principal Dams Engineer, Bulk Water

More information

VERTI-BLOCK - DESIGN MANUAL

VERTI-BLOCK - DESIGN MANUAL Company Information General Information Verti-Block is the latest innovative forming system from Verti-Crete, LLC. Recognized worldwide for outstanding aesthetics and performance, Verti-Crete s proprietary

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Shaw AFB East Gate Entrance Control Facility Amendment Sumter, South Carolina September 13, 2010 Terracon Project No. 73105020A Prepared for: TranSystems North Charleston,

More information

MKT VIBRATORY HAMMER SELECTION AND SOILS TRAINING

MKT VIBRATORY HAMMER SELECTION AND SOILS TRAINING MKT VIBRATORY HAMMER SELECTION AND SOILS TRAINING While reviewing this guide if you see this symbol please click to the next slide. Press the F5 key when you are ready to start the slide show. MKT MANUFACTURING,

More information

PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE. Abstract

PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE. Abstract PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE By: D.N. Clute, P.E.; M.S. Garsjo, P.E.; K.R. Worster, P.E. National Design, Construction, and Soil Mechanics Center, USDA-NRCS, Fort Worth, Texas

More information

Over the last decade, drilled and postgrouted micropile foundations have

Over the last decade, drilled and postgrouted micropile foundations have Seismic Design of Micropile Foundation Systems Leo Panian, S.E., and Mike Korolyk, S.E. Over the last decade, drilled and postgrouted micropile foundations have come to be increasingly relied on for resisting

More information

Preliminary Geotechnical Exploration Armstrong Tract Rivers Avenue and Hanahan Road North Charleston, South Carolina S&ME Project No.

Preliminary Geotechnical Exploration Armstrong Tract Rivers Avenue and Hanahan Road North Charleston, South Carolina S&ME Project No. Preliminary Geotechnical Exploration Rivers Avenue and Hanahan Road S&ME Project No. 4213-16-016 Prepared for: Charleston Water System 103 Saint Phillip Street Charleston, South Carolina 29403 Prepared

More information

aggregate piers / vscs

aggregate piers / vscs aggregate piers / vscs 1 2 HT1.0 1-1 1-2 1' - 1" 34' - 0" 16' - 11" 1' - 1" 13' - 10" BOF 817' - 6" (TYPICAL WITHIN HATCHED REGION) 1-17 1-32 1-47 1-62 1-3 1-18 1-33 1-48 1-63 1-4 1-19 1-34 1-49 1-64 1-5

More information

Rapid Drawdown with Effective Stress

Rapid Drawdown with Effective Stress 1 Introduction Rapid Drawdown with Effective Stress Stability analysis during rapid drawdown is an important consideration in the design of embankment dams. During rapid drawdown, the stabilizing effect

More information

The following sections provide the approved standard infiltration testing specifications.

The following sections provide the approved standard infiltration testing specifications. APPENDIX F.2 INFILTRATION TESTING To properly size and locate stormwater management facilities, it is necessary to characterize the soil infiltration conditions at the location of the proposed facility.

More information

(1) All sanitary landfill facilities, at a minimum, shall include the following:

(1) All sanitary landfill facilities, at a minimum, shall include the following: 3745-27-08 Sanitary landfill facility construction. (A) Applicability. The construction requirements for a sanitary landfill facility specified in this rule are applicable to a particular facility or permit

More information

GENERAL SOILS EVALUATION REPORT. For

GENERAL SOILS EVALUATION REPORT. For GENERAL SOILS EVALUATION REPORT For EL PASO WATER UTILITIES (EPWU) PROPOSED AUSTIN STORMWATER POND IMPROVEMENTS NE OF ALTURA AVE. & LACKLAND ST. EL PASO, EL PASO COUNTY, TEXAS Prepared For MORENO CARDENAS

More information

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year.

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year. ICC-ES Evaluation Report ESR-1959 Issued July 1, 2011 This report is subject to renewal in one year. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council DIVISION:

More information

Design Data 4. Jacking Concrete Pipe

Design Data 4. Jacking Concrete Pipe Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information

Design Manual: Gravity Wall. Section 1

Design Manual: Gravity Wall. Section 1 Design Manual: Gravity Wall Section 1 A Design Manual: Gravity Wall General Information Company Information Verti-Block is the latest innovative forming system from Verti-Crete, LLC. Recognized worldwide

More information

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures Preferred QC/QA Procedures The Federal Highway Administration (FHWA) has provided QC/QA guidance for this technology as noted below. The reference document also contains information about construction

More information

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements: TNC Fisher Slough Final Design and Permitting Subject: Inverted Siphon Construction Feasibility To: From: Jenny Baker (TNC) Dave Olson (DD3) Brian Olson (DD17) Bob Boudinot Skagit County David Cline (Tetra

More information

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch MSE WALLS CASE STUDIES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch COMMON RETAINING WALL TYPES CONCRETE BLOCK MSE TEMPORARY EARTH SPREAD FOOTING Gabions Drilled Shaft Soil Nail Tiedback

More information

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NPTEL Course GROUND IMPROVEMENT USING MICROPILES Lecture 22 NPTEL Course GROUND IMPROVEMENT USING MICROPILES Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Contents

More information

Soil Mechanics IX. SOIL IMPROVEMENT

Soil Mechanics IX. SOIL IMPROVEMENT Soil Mechanics IX. SOIL IMPROVEMENT Methods for Soil Improvement Ground Reinforcement Stone Columns Soil Nails Deep Soil Nailing Micropiles (Mini-piles) Jet Grouting Ground Anchors Geosynthetics Fiber

More information

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment MATEC Web of Conferences 11, 03006 ( 2014) DOI: 10.1051/ matecconf/ 20141103006 C Owned by the authors, published by EDP Sciences, 2014 Study of Various Techniques for Improving Weak and Compressible Clay

More information

Seismic Retrofit of Crane Valley Dam

Seismic Retrofit of Crane Valley Dam Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2013) - Seventh International Conference on Case Histories in Geotechnical

More information

Design Data 9. Standard Installations and Bedding Factors for the Indirect Design Method

Design Data 9. Standard Installations and Bedding Factors for the Indirect Design Method Design Data 9 Standard Installations and Bedding Factors for the Indirect Design Method Background The classic theory of earth loads on buried concrete pipe published, in 1930 by A. Marston, was developed

More information

Retaining Wall Design

Retaining Wall Design SIL 211 MEKANIKA TANAH Retaining Wall Design DR. IR. ERIZAL, MAGR DEPARTEMEN TEKNIK SIPIL DAN LINGKUNGAN FAKULTAS TEKNOLOGI PERTANIAN IPB 1 Conventional Retaining Walls Gravity Retaining Structures Stability

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

NPTEL Course GROUND IMPROVEMENT

NPTEL Course GROUND IMPROVEMENT Lecture 8 NPTEL Course GROUND IMPROVEMENT Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Vibro-compaction methods Compaction

More information

RETAINING WALL LEVEL BACKFILL

RETAINING WALL LEVEL BACKFILL City of Poway Development Services Department Building Division (858) 668-4645 (858) 668-4646 (Inspection Line) building@poway.org RETAINING WALL LEVEL BACKFILL Construction of retaining walls, except

More information

REROUTING DRAINAGE SYSTEMS

REROUTING DRAINAGE SYSTEMS MINNESOTA WETLAND RESTORATION GUIDE REROUTING DRAINAGE SYSTEMS TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-4 Publication Date: 10/14/2015 Table of Contents Introduction Application Design Considerations

More information

Introduction to Foundations on Fill and Backfilling

Introduction to Foundations on Fill and Backfilling Introduction to Foundations on Fill and Backfilling Course No: G01-003 Credit: 1 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Effective Stress Design For Floodwalls on Deep Foundations

Effective Stress Design For Floodwalls on Deep Foundations Effective Stress Design For Floodwalls on Deep Foundations Glen Bellew, PE Geotechnical Engineer USACE-Kansas City 23 April 2015 Contributors James Mehnert, PE USACE-Kansas City Paul Axtell, PE, D.GE Dan

More information

SITE INVESTIGATION. Foundation Engineering

SITE INVESTIGATION. Foundation Engineering SITE INVESTIGATION Assist. Prof. Berrak TEYMUR Foundation Engineering Analysis Design Construction As a foundation engineer, you need to consider geotechnical/structural issues (involves geology, subsurface

More information

Case Studies on Soil Nailed Retaining Systems for Deep Excavations

Case Studies on Soil Nailed Retaining Systems for Deep Excavations Indian Geotechnical Conference 2010, GEOtrendz December 16 18, 2010 IGS Mumbai Chapter & IIT Bombay Case Studies on Soil Nailed Retaining Systems for Deep Excavations Murthy, B.R. Srinivasa Professor e-mail:

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

INSPECTION GUIDE FOR SEGMENTAL RETAINING WALLS TEK 18-11B

INSPECTION GUIDE FOR SEGMENTAL RETAINING WALLS TEK 18-11B An information series from the national authority on concrete masonry technology INSPECTION GUIDE FOR SEGMENTAL RETAINING WALLS TEK 18-11B Quality Assurance and Testing (2012) INTRODUCTION Segmental retaining

More information

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1 PUBLIC WORKS DEPARTMENT David A. Jones, P.E., Director April 7, 2017 Webster Street Sub-Surface Stormwater Storage System Bid No. 2017-022 Bid Date: 4/13/17 ADDENDUM NO 1 Please make the following changes

More information

Ground Improvement Specialists

Ground Improvement Specialists is a design-build specialty geotechnical contractor offering expertise on ground improvement for sites with poor soil. We combine value engineering and innovative techniques to deliver practical, sustainable

More information

SECTION AGGREGATES

SECTION AGGREGATES SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational

More information

Smarter, Cheaper, Ash Pond Dewatering

Smarter, Cheaper, Ash Pond Dewatering 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Smarter, Cheaper, Ash Pond Dewatering David M. Seeger, PhD, Steven Kosler AECOM, 9400 Amberglen Blvd.,

More information

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES Elizabeth City, North Carolina G E T Project No: EC14-188G May 30, 2014 PREPARED FOR: 106 Capital Trace, Unit E Elizabeth City,

More information

A.2.a Random Riprap... Table

A.2.a Random Riprap... Table 3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide

More information

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan INSERT DATE HERE Ground Improvement - What is it? Ground Improvement = Black Box? Ground Improvement - Introduction Ground

More information

DREDGING TECHNIQUES USED TO DEVELOP A MAN-MADE IJXE ON A DEEP ORGANIC PROFILE ABSTRACT

DREDGING TECHNIQUES USED TO DEVELOP A MAN-MADE IJXE ON A DEEP ORGANIC PROFILE ABSTRACT DREDGING TECHNIQUES USED TO DEVELOP A MAN-MADE IJXE ON A DEEP ORGANIC PROFILE by Thomas D. Swantko, Geotechnical Consultant, Los Angeles, California, and Stephen W. Berry, Vice President, Michael D. Sims

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geotechnical Engineering Office Civil Engineering Department The Government of the Hong Kong Special Administrative Region

More information

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois AGI Project No. -11 Subsurface Investigation Report For the Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois Prepared for Mr. Steve Panko Key Development Partners, LLC North State Street,

More information