Exposition Light Rail Transit Project

Size: px
Start display at page:

Download "Exposition Light Rail Transit Project"

Transcription

1 Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update May 1, 2008

2 PHASE 1

3 Phase 1 Project Status Design Design approximately 86% complete Construction Construction approximately 8% complete Construction Packages Negotiated 10 of the 19 construction packages Third Party Agreements Executed 5 of the 8 third party agreements

4 Phase 1 Project Status CPUC Grade Crossing Applications Supplemental information on alternative configurations at each crossing was provided by Expo to ALJ on March 28, 2008 Comments filed by other parties on April 18, 2008 Meet and Confer was held April 24, 2008 Workshop scheduled for May 8, 2008 at the PUC Offices on 4 th Street in Los Angeles Pre-Hearing Conference (Telephonic) scheduled for May 9, 2008

5 Phase 1 Project Status CPUC Grade Crossing Applications (cont.) Environmental work on the Farmdale Alternatives is proceeding Farmdale crossing approval by the PUC is required by September, 2008 in order not to delay the project. Grade-separated direction by the PUC will result in significant delays to the project.

6 Phase 1 Project Status Current Construction Activities Completed relocation of 61 water line Began replacement of damaged sewer line in front of USC Conducted full weekend closures of Figueroa to install girders at intersection of Exposition Blvd and Figueroa St Continued soil stabilization, installation of CIDH piles and construction of pile caps for trench structure Continued curb, gutter, sidewalk and street removal along Flower St from Adams Blvd to Jefferson Blvd Began installation of K-Rail along Exposition Blvd from Vermont Ave to 7 th Ave

7 Construction Progress Prep for installation of Box Girders at Exposition and Figueroa

8 Construction Progress Installation of Box Girders along Flower

9 Construction Progress Installation of Box Girders at Exposition and Figueroa

10 Construction Progress Concrete Deck over Girders at Exposition and Figueroa

11 Construction Progress K-Rail Installation from Vermont to 7 th

12 Construction Progress Street Demolition Along Flower

13 Phase 1 Project Status Project Budget Summary Construction Budget 10 of 19 construction packages have been negotiated in an amount totaling $206 million Currently under running the revised construction budget Project Budget All tasks are within the revised budget Remaining significant risks to the budget include: - Contracts yet to be negotiated - Contractor claims - Changes to Farmdale crossing - Changes to Harvard Pedestrian Tunnel - Change Orders

14 Phase 1 Project Status Project Schedule Summary Areas of Potential Delay Aerial structures at La Cienega, La Brea and Ballona Creek Delay in approval of the Farmdale and Harvard Pedestrian Tunnel PUC Applications Any changes to the Farmdale Ave and/or Harvard Blvd crossings LADWP power line relocations Culver City Aerial Station

15 Phase 1 Project Status Project Issue Summary Service and Inspection Facility Metro has identified a preferred site on Metro owned right-of-way at Washington/Long Beach Boulevards Metro will procure a separate DB contract for this facility Additional Environmental Studies Draft Environmental Assessment for Traction Power Substations 3 and 4 was circulated for Public Review and Comment on March 20, 2008 and a Community Meeting took place on April 8, The Public Comment period closed on April 18, Metro will now perform environmental studies for the S&I facility Environmental study for Farmdale Crossing Alternatives is on-going

16 Government/Community Relations Phase 1 Project Status Held a Project Status Update Meeting at Holman United Methodist Church (Seg B) Held a Project Status Update Meeting at the Culver City Senior Center (Seg C) Provided project update presentations to: United Homeowners Association (Seg B) Cameo Woods Homeowners Association (Seg C) Culver City Chamber Membership Luncheon (Seg C) Hosted informational tables at: Rancho Cienega Park Health Fair (Seg B) Culver City Farmers Market Earth Day Event (Seg C) Continued coordination of construction fence Art Mural with Dorsey High School Continued Segment C Business Assessments Continued School Safety outreach to schools along the project alignment Attended regularly scheduled meetings with USC and Expo Park to discuss coordination of events and construction activities

17 Summary of Jobs Program Activities APRIL 2008 There are 65 active construction workers currently working on the Expo Project (Laborers, Carpenters or Operators). 17 (all minority) are from the Expo Corridor. All Expo Construction Jobs are Union Jobs. 86 people are currently working for FFP in non-union jobs (clerical or professional level positions). 20 workers are from the Expo Corridor (12 are minorities). To date, FFP has sponsored 24 individuals into local unions (Laborers, Carpenters or Operators). 616 individuals have attended orientation sessions hosted by PVJOBS and have been placed on a priority list for employment and apprenticeship training. Of these individuals, 26 have been placed on the Expo Project, 42 have been placed in non- Expo related jobs by PVJOBS and 9 have been placed in construction jobs by the LA Urban League. DBE goal was set for Pomeroy Corporation in the amount of 23% to furnish all labor, materials, and incidentals necessary to erect specialty girders for the National Boulevard Bridge across Ballona Creek FFP awarded a subcontract to Quality Engineering, Inc., a DBE firm, for construction engineering services

18 Summary of DBE Program Activities DBE Goals and Signed Contracts through April % DBE Goal 20% 20% To Date 21.45% DBE Goal 20% 20% To To date date 15.6% DBE Goal 20% 20% To date 15.35% DBE DBE Design Design Service Service Firms Firms $6.2 $6.2 Million Million DBE DBE Professional Professional Service Service Firms Firms $6.95 $6.95 Million Million DBE DBE Construction Construction Service Service Firms Firms $33.2 $33.2 Million Million

19 PHASE 2

20 Phase 2 Project Status AA/EIS/Conceptual Engineering Continued preparation of draft technical background reports for EIS Advanced draft Milestone 2 grade crossing reports in coordination with Culver City, LADOT and Santa Monica Conducted review meeting with CPUC on status of all project related grade crossings Worked with Metro on ridership model corrections and recalibration Conducted project briefing with City of LA Planning Continued work on station/parking layouts and locations

21 Phase 2 Project Status Government/Community Relations Conducted briefings with: Office of LA City Councilmember Rosendahl (CD 11) Colorado Avenue and Olympic Boulevard Stakeholders SM-UCLA Medical Center BOMA (Building Owners and Managers Association) LAUSD Office of Environmental Health and Safety Businesses along alternative alignments, east of the 405 Project Issue Summary Metro Ridership Model expected on May 5 Remaining Grade Crossing determinations expected in May Coordinating with LADOT and Metro to develop a continuous bikeway where feasible within our project scope

22 Phase 2 Project Status Phase 2 Milestones Activity Scheduled Completion Date Forecast Completion Date Status Comments Scoping Meetings & Report Mar-07 May-07 Complete Screening of Alternatives May-07 Oct-07 Complete Delay in receiving ridership model from Metro Administrative Draft to FTA Oct-07 June/July-08 Delay due to need to recalibrate model received from Metro Start Public Hearings on Draft DEIS/DEIR Feb-08 Fall-08 FTA must sign off on Draft DEIS before document can be circulated Board Adoption of LPA May-08 Oct/Nov-08 May be reforecast based on Model delivery date Request to enter Preliminary Engineering (PE) May-08 Oct/Nov-08 May be reforecast based on Model delivery date Risks to Current Schedule: Ridership Model Maintenance Facility for Phase 2

AGENDA REGULAR BOARD MEETING

AGENDA REGULAR BOARD MEETING Exposition Metro Line Construction Authority 707 Wilshire Blvd #34 Los Angeles, CA 90017 213-243-5500 BuildExpo.org AGENDA REGULAR BOARD MEETING Kenneth Hahn Hall of Administration 500 West Temple Street

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update January 14, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 78% complete Construction Packages

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015 Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three

More information

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address. Application 06-12-005 et al. Exhibit Date: August, 2008 PREPARED TESTIMONY OF LEE LISECKI Q. Please state your name, professional position, and business address. A. My name is Lee Lisecki. I am a principal

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

Eastside Transit Corridor Phase 2

Eastside Transit Corridor Phase 2 Eastside Transit Corridor Phase 2 Community Meeting, June 22, 2016 Page 1 Purpose of Tonight s Meeting Page 2 Update on Metro Board directed Technical Study (Nov. 2014) SR-60 Alternative Washington Blvd

More information

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April / May 2016 (Final) TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015 Expo Board Presentation Monthly Project Status Update December 3, 215 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Working with Metro and City of

More information

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community

More information

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006 Review Advisory Committee May 11, 2006 1 Ramona Opportunity High School/ Indiana Station Status 2 Ramona Opportunity High School/ Indiana Station Status 1. On April 19, 2006, Metro held an Indiana Station

More information

Project Budget And Schedule Status Report

Project Budget And Schedule Status Report Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project

More information

OPTIONAL STATIONAVIATION/MANCHESTER

OPTIONAL STATIONAVIATION/MANCHESTER CRENSHAW/LAX TRANSIT CORRIDOR PROJECT FEIS/FEIR OPTIONAL STATIONAVIATION/MANCHESTER Aviation and Manchester, Looking East Aviation/Manchester Station (Optional) The Optional Aviation/Manchester Station

More information

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer April 18, 2018 MEMORANDUM PUBLIC WORKS DEPARTMENT HILLS BEVERLY CITY OF BEVERLY HILLS Public Works Commission Rob Welch, Acting City Engineer Capital Projects Update Capital Improvement Projects Update

More information

Public Works Department

Public Works Department Public Works Department Monthly Report Public Works Department Monthly February Report 2017 George Chavez Assistant City Manager/Director of Public Works Key Message The Public Works Department reached

More information

CM/GC Contracting Lessons Learned from Portland and San Francisco

CM/GC Contracting Lessons Learned from Portland and San Francisco CM/GC Contracting Lessons Learned from Portland and San Francisco Lance Erz, TriMet Robin M Reitzes, SF City Attorney s Office American Public Transportation Association Legal Affairs Seminar February

More information

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222 Water Projects Maple Wells Project (CIP No. 0916) Scope of Work: Construction of two municipal supply wells at the Maple Yard (342 Foothill Road) and a pipeline to convey well water to the water treatment

More information

Caltrain Downtown Extension Project

Caltrain Downtown Extension Project Presentation to TJPA Board Caltrain Downtown Extension Overview and Update March 12, 2009 Agenda: Caltrain Downtown Extension Project Preliminary Engineering (PE) Term 2 Update Design Contract Task Progress

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

LAWA Update Ground Transportation Planning and Metro Coordination

LAWA Update Ground Transportation Planning and Metro Coordination LAWA Update Ground Transportation Planning and Metro Coordination SPAS Approved LAX Ground Transportation Projects The Specific Plan Amendment Study (SPAS) includes LAX Ground Transportation Projects:

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Presented in Beverly Hills: June 7, 2010 Where We are in the

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT

PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT 34 One Gateway Plaza Los Angeles, CA 90012-2952 CONSTRUCTION COMMITTEE SEPTEMBER 20, 2012 PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT ACTION: APPROVE USE OF DESIGN-BUILD CONTRACTING DELIVERY

More information

-1- Intermodal Parking Facilities And Enhancements Design-Build Project

-1- Intermodal Parking Facilities And Enhancements Design-Build Project -1- Intermodal Parking Facilities And Enhancements Design-Build Project Presentation Foothill Extension Phase 2A Pasadena to Azusa Three Design-Build Projects Intermodal Parking Facilities and Enhancements

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Central Corridor. Light Rail Transit. Navigating NEPA Between St. Paul and Minneapolis

Central Corridor. Light Rail Transit. Navigating NEPA Between St. Paul and Minneapolis Navigating NEPA Between St. Paul and Minneapolis Improving mobility Easing congestion Strengthening our communities 19 th Century Navigation 2 Early 20 th Century Navigation 3 Later 20 th Century Navigation

More information

Restoration of Historic Streetcar Service in Downtown Los Angeles. Executive Summary -- Alternatives Analysis (AA) FINAL

Restoration of Historic Streetcar Service in Downtown Los Angeles. Executive Summary -- Alternatives Analysis (AA) FINAL Restoration of Historic Streetcar Service in Downtown Los Angeles Executive Summary -- Alternatives Analysis (AA) FINAL January 13, 2012 This page intentionally left blank Table of Contents S1.0 PURPOSE

More information

Mid-Coast Corridor Transit Project Project Working Group June 16, 2014

Mid-Coast Corridor Transit Project Project Working Group June 16, 2014 Mid-Coast Corridor Transit Project Project Working Group June 16, 2014 Project Overview $1.7 billion TransNet and federal funding 11 mile extension of San Diego Trolley Blue Line Old Town Transit Center

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods

More information

. '- oate : _-=o_s-4-.b...;.t_t>-~f-..2..:: /} () 0 ' CAJA Environmental Services. ~: LllM M -tt~ ~ tt loa.( C./ May 10, 2016

. '- oate : _-=o_s-4-.b...;.t_t>-~f-..2..:: /} () 0 ' CAJA Environmental Services. ~: LllM M -tt~ ~ tt loa.( C./ May 10, 2016 CAJA Environmental Services 11990 San Vicente Boulevard, Suite 250 Phone 310-469-6700 Fax 310-806-9801 May 10, 2016 Ms. Luci Ibarra, Sr. City Planner Major Projects 200 North Spring Street City Hall Room

More information

Si nificant Issues. Transit Pro'ect Deliver Status Re orgy. J Y p. Item xx. Presented By K.N. Murthy

Si nificant Issues. Transit Pro'ect Deliver Status Re orgy. J Y p. Item xx. Presented By K.N. Murthy t Item xx Transit Pro'ect Deliver Status Re orgy J Y p Si nificant Issues Presented By K.N. Murthy I~t~'~ Construction Committee ~ -405 Sepulveda Pass Improvements Project ~rm ~r _. / _ y.. ' ;sir.,~.

More information

THIS PAGE INTENTIONALLY LEFT BLANK.

THIS PAGE INTENTIONALLY LEFT BLANK. THIS PAGE INTENTIONALLY LEFT BLANK. DRAFT ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT LEAD AGENCIES: Federal Transit Administration, U.S. Department of Transportation and Los Angeles County

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT

KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT February 2012 Submitted March 15, 2012 PROJECT TYPE: Multimodal (bicycle, pedestrian, roadway, transit) LOCATION: Kansas City metropolitan area

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager

More information

Metro Board Action: Motion 22.1

Metro Board Action: Motion 22.1 Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016 Background Motion 22.1 October

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1. Introduction 1.1 Purpose of the Supplemental Environmental Impact Report (EIR) The California Environmental Quality Act (CEQA) requires preparation of an Environmental Impact Report (EIR) when

More information

Purple Line Extension. Construction Community Meeting March 16, 2017

Purple Line Extension. Construction Community Meeting March 16, 2017 Purple Line Extension Construction Community Meeting March 16, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking:

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

Gloucester Parkway Extension RFQ Information Meeting

Gloucester Parkway Extension RFQ Information Meeting Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction

More information

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system.

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system. Water Projects Pump Station No. 8 Rehabilitation (CIP No. 0796) Scope of Work: Rehabilitation of aging mechanical equipment and the associated piping at the existing pump station adjacent to Reservoir

More information

REGIONAL LIGHT RAIL CONNECTOR DOWNTOWN

REGIONAL LIGHT RAIL CONNECTOR DOWNTOWN @ Metro 12. Los Angeles County One Gateway Plaza ~13.gzz.zooo Tei Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net * PLANNING AND PROGRAMMING COMMITTEE June 20,2007 SUBJECT: ACTION:

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

Civil Construction Pre-Bid and DBE Meet and Greet. November 13, 2017

Civil Construction Pre-Bid and DBE Meet and Greet. November 13, 2017 Civil Construction Pre-Bid and DBE Meet and Greet November 13, 2017 1 Today s Topics Welcome/Introductions Bid Requirements Review of DBE Participation Overview of Project Specifications DBE Meet and Greet

More information

City of Los Angeles Department of Public Works Bureau of Engineering (BOE) Task Order Solicitation (TOS) No. 2

City of Los Angeles Department of Public Works Bureau of Engineering (BOE) Task Order Solicitation (TOS) No. 2 City of Los Angeles Department of Public Works Bureau of Engineering (BOE) Task Order Solicitation (TOS) No. 2 Century Boulevard Extension Grape Street to Alameda Street Design Support Services During

More information

INTERGOVERNMENTAL AGREEMENT TRANSPORTATION PROJECT FUNDING AGREEMENT

INTERGOVERNMENTAL AGREEMENT TRANSPORTATION PROJECT FUNDING AGREEMENT INTERGOVERNMENTAL AGREEMENT TRANSPORTATION PROJECT FUNDING AGREEMENT This Intergovernmental Agreement ( Agreement ) is made and entered into by and between the City of Tualatin ( Tualatin ) and Metro,

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

DART Capital Program Symposium WELCOME

DART Capital Program Symposium WELCOME DART Capital Program Symposium WELCOME DART Capital Program Symposium Project Narrative Dallas CBD Second Light Rail Alignment (D2): Will be the 2nd light rail line through Downtown Dallas Will connect

More information

FACT SHEETS LOS ANGELES COUNTY

FACT SHEETS LOS ANGELES COUNTY FACT SHEETS LOS ANGELES COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares a

More information

Final Quiet Zone Work Plan

Final Quiet Zone Work Plan Executive Summary Recognizing the impacts of commuter train horns on the communities they serve, RTD will assist and facilitate the local jurisdictions Quiet Zone applications along the Gold Line, Northwest

More information

Railyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis

Railyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis Railyard Alternatives & I-280 Boulevard Feasibility Study 1 Railyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis San Francisco Planning Department TJPA

More information

C-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options

C-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options Project Number C-01c Subarea North King Primary Mode Light Rail Facility Type Corridor Length 7.5 miles Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report March 2015 TABLE OF CONTENTS Project Manager

More information

4.0 AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES

4.0 AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES 4.0 Affected Environment & Environmental Consequences 4.0 AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES INTRODUCTION This section examines the environmental consequences associated with the proposed

More information

MOTION NO. M Contract Amendment for Downtown Bellevue to Spring District Construction within the East Link Extension

MOTION NO. M Contract Amendment for Downtown Bellevue to Spring District Construction within the East Link Extension MOTION NO. M2018-09 Contract Amendment for Downtown Bellevue to Spring District Construction within the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board 1/11/2018

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

STAFF REPORT I. BACKGR~ Community Development Department

STAFF REPORT I. BACKGR~ Community Development Department STAFF REPORT Date: March 04, 2014 To: Steven A. Preston, FAICP, City Manager From: Daren Grilley, PE, City Engin~ Community Development Department By: Algis J. Marciuska, PE, Senior Civil Engineer ~ Subject:

More information

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line Board Update Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line 10.5 mile light rail line Starts at Nine Mile Station Eight stations Serves Aurora City Center Serves

More information

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Village of Forest Park Council Meeting Presented by Carole Morey, CTA Chief Planning Officer October 13, 2015 Slide 2: Purpose and Study

More information

AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE

AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE This Amendment D to the Contract for Independent Contractor between the City of Fernley and NCE is entered

More information

Progress update (November to March) 03/23/2009 2

Progress update (November to March) 03/23/2009 2 Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)

More information

Tier 1 EIS Round 2 Local Officials Briefing Fall 2011

Tier 1 EIS Round 2 Local Officials Briefing Fall 2011 1 Tier 1 EIS Round 2 Local Officials Briefing Fall 2011 Agenda AGENDA 2» Corridor Level Environmental Review (TIER 1 Environmental Impact Statement)» Next Steps» Public Involvement» Questions 3 Corridor

More information

Cotton Belt Corridor. Open House Meetings September 2017

Cotton Belt Corridor. Open House Meetings September 2017 Cotton Belt Corridor Open House Meetings September 2017 0 Welcome Open House format with break for brief presentation and Question/Answer Allows for one-on-one discussions with staff Brief presentation

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

Crenshaw/LAX Transit Project

Crenshaw/LAX Transit Project Crenshaw/LAX Transit Project QUARTERLY PROJECT STATUS REPORT SEPTEMBER 2015 CRENSHAW/LAX TRANSIT PROJECT QUARTERLY PROJECT STATUS REPORT THE PREPARATION OF THIS DOCUMENT HAS BEEN FINANCED IN PART THROUGH

More information

Gateway Corridor Transitway

Gateway Corridor Transitway Locally Preferred Alternative Summary Gateway Corridor Transitway 1 Metropolitan Council, Nov. 12, 2014 Gateway Corridor Transitway Proposed highcapacity transit improvement connecting east metro suburbs

More information

FACT SHEETS SAN BERNARDINO COUNTY

FACT SHEETS SAN BERNARDINO COUNTY FACT SHEETS SAN BERNARDINO COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares

More information

PENINSULA CORRIDOR ELECTRIFICATION PROJECT (PCEP)

PENINSULA CORRIDOR ELECTRIFICATION PROJECT (PCEP) PENINSULA CORRIDOR ELECTRIFICATION PROJECT (PCEP) Q2 Quarterly Update #17 October 1 December 31, 2018 JPB Board Meeting February 7, 2019 Agenda Item # 8a PCEP Work Segment Map 2 1 Design Progress ELECTRIFICATION

More information

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-16. Santa Monica/San Vicente 1/4-Mile Station Area August 16, 2010 Page 5-35 Figure 5-17. Beverly Center 1/4-Mile Station Area August 16, 2010 Page 5-36 5.8 Alternative 5 Santa Monica Extension

More information

CMAA - BREAKFAST OF CHAMPIONS May 2, 2012

CMAA - BREAKFAST OF CHAMPIONS May 2, 2012 CMAA - BREAKFAST OF CHAMPIONS May 2, 2012 SIXTH STREET VIADUCT REPLACEMENT Gary Lee Moore, P.E. City Engineer Deborah Weintraub, AIA, LEED AP Chief Deputy City Engineer Alfred L. Mata, P.E. Project Manager

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

Construction Manager / General Contractor CM/GC Procurement Case Study February 2016

Construction Manager / General Contractor CM/GC Procurement Case Study February 2016 Construction Manager / General Contractor CM/GC Procurement Case Study February 2016 WORLD TRADE CENTER PATH TERMINAL PROJECT MBTA GREEN LINE EXTENSION PROJECT Federal Transit Administration Wendy A. Lee,

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

Crenshaw/LAX Transit Project

Crenshaw/LAX Transit Project Crenshaw/LAX Transit Project Construction Update Community Meeting January 25 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Atlanta BeltLine Corridor Environmental Study. Technical Advisory Committee/Agency Coordination. Kick-Off Meeting

Atlanta BeltLine Corridor Environmental Study. Technical Advisory Committee/Agency Coordination. Kick-Off Meeting Atlanta BeltLine Corridor Environmental Study Technical Advisory Committee/Agency Coordination Kick-Off Meeting July 17, 2008 Overview Project Overview Objectives Milestones Why GEPA and NEPA? Environmental

More information

MAJOR TRANSIT AND TRANSPORTATION CONSTRUCTION TRAFFIC MANAGEMENT COMMITTEE

MAJOR TRANSIT AND TRANSPORTATION CONSTRUCTION TRAFFIC MANAGEMENT COMMITTEE JOURNAL MAJOR TRANSIT AND TRANSPORTATION CONSTRUCTION TRAFFIC MANAGEMENT COMMITTEE Thursday, October 30, 2014, 9:00 A.M., 1149 S. Broadway, first floor conference room 150, Los Angeles Committee Members:

More information

PUBLIC HEARING April 24, 2017

PUBLIC HEARING April 24, 2017 PUBLIC HEARING April 24, 2017 1 Agenda SDEIS Public Review Environmental Process Overview Project Highlights Comments to Stenographer 2 3 SDEIS Public Review Public Hearing Schedule Monday, April 24, 2017

More information

University Corridor Draft Environmental Impact Statement (DEIS)

University Corridor Draft Environmental Impact Statement (DEIS) University Corridor Draft Environmental Impact Statement (DEIS) Public Meetings/Open Houses August 13, 27 August 14, 27 5: pm to 7: pm 5: pm to 7: pm Holiday Inn Select- Greenway* Wheeler Avenue Baptist

More information

Staffing Request for Expo Line Phase 2 and Gold Line Foothill Phase 2A - Systems Integration

Staffing Request for Expo Line Phase 2 and Gold Line Foothill Phase 2A - Systems Integration Los Angeles County Metropolitan Transportation Authority Staffing Request for Expo Line Phase 2 and Gold Line Foothill Phase 2A - Systems Integration System Safety and Operations Committee July 17, 2014

More information