October 9, U. S. Army Corps of Engineers Omaha District Attn: CENWO-ED-ED (Jeffery Skog) 215 North 17 th Street Omaha, NE

Size: px
Start display at page:

Download "October 9, U. S. Army Corps of Engineers Omaha District Attn: CENWO-ED-ED (Jeffery Skog) 215 North 17 th Street Omaha, NE"

Transcription

1 Baker Environmental, Inc. A Unit of Michael Baker Corporation Airside Business Park 100 Airside Drive Moon Township, PA October 9, 2007 (412) FAX (412) U. S. Army Corps of Engineers Omaha District Attn: CENWO-ED-ED (Jeffery Skog) 215 North 17 th Street Omaha, NE Re: LNAPL Investigation Pilot Study Report Former Atlas E Missile Site Windsor, Colorado Mr. Skog: Provided herein are results of the Light Non-Aqueous Phase Liquid (LNAPL) Investigation Pilot Study performed by Baker Environmental, Inc. (Baker) for the U.S. Army Corps of Engineers - Omaha District (USACE). The pilot study field program was conducted August 6 through 10, This pilot study is the initial phase of the investigation to delineate the LNAPL contamination identified at the site. The pilot study was designed to evaluate investigative methods, including passive soil gas and directpush technology (DPT) drilling, due to the site stratigraphy and unknown source of the LNAPL. Once the most appropriate investigative methods are determined, a more in depth investigation likely will be conducted to delineate the extent of the LNAPL. Delineation will be defined as the lateral boundaries of the plume, the thickness of the LNAPL throughout the plume and the source of the LNAPL. The pilot study was completed according to procedures described in the USACE approved Final LNAPL Investigation Pilot Study Work Plan (Baker, August 2007) prepared for the Site. Copies of the Daily Quality Control Reports, summarizing the daily activities, are provided as Attachment A. A discussion of the field activities, including exceptions to the proposed procedures made necessary by field conditions, is provided in the five subsequent sections including: Section Direct Push Technology Evaluation Section Field Screening Section Soil Gas Survey Section LNAPL Sampling and Sulfur Evaluation Section Conclusions 1.0 Direct Push Technology Evaluation The DPT drilling program pilot study was performed by Vironex, Inc. (Vironex) (13551 West 43rd Drive, Suite L, Golden, Colorado 80403, ) on August 6, The drilling pilot test was conducted using a Geoprobe 6600 equipped a GH62 soil probing hammer mounted on a one ton flatbed truck. Mike Martin, Vironex Rocky Mountain Regional Manager, along with a two man crew, was onsite and directed the drilling pilot test approach, oversaw the activities and provided DPT conclusions. The DPT testing was conducted approximately 20 feet northeast and upgradient of monitoring well MW-7 (Figure 1). Monitoring

2 Mr. Jeffery Skog October 9, 2007 Page 2 well MW-7 contains measurable LNAPL (this issue is discussed further in Section 4.0). The initial DPT evaluation activity involved advancing a 1.5-inch drive point that simulated a Membrane Interface Probe (MIP). Refusal was encountered at 19 feet below ground surface (bgs). Consequently, MIP technology cannot be used since the groundwater at the Site is at an approximate minimum depth of 35 feet bgs and the required depths cannot be obtained using the MIP/DPT configuration. For the DPT continuous soil sampling evaluation, a precleaned steel Macro-Core (MC) sampler was hydraulically pushed over a four-foot sampling interval through the vadose zone. Advancement was slow as two-foot sampling interval runs were employed at 20 feet bgs due to the increasing hardness of the stratigraphy. Refusal was encountered at 34 feet bgs. Note: A gravel-sized piece of competent siltstone was in the nose of the MC sampling upon retrieval. Consequently, DPT cannot be used since the groundwater at the Site is at an approximate minimum depth of 35 feet bgs and the required depths cannot be obtained using the continuous soil sampling/dpt configuration. Also, a fuel sample for total sulfur analysis was not collected from the DPT test borehole. Logging of the DPT soil cores correlated well with logs of boreholes advanced in the vicinity of the test borehole including SB-2 and SB-16/MW-7. Copies of the HTW Drilling Logs for soil boring SB-2 and monitoring well MW-7 are provided as Attachment B. Note: The following stratigraphic details from the SB-2 and SB-16/MW-7 drilling logs correlate with the DPT drilling logs: SB-2: several moderately cemented pieces around 19 ft bgs. SB-2: fine grained, hard, sandstone at the 30 to 31 foot interval, plus the rotosonic core barrel was stuck in the borehole after Run #8 (i.e., 29.5 to 32.5 foot interval). SB-16/MW-7: increase in sandstone pieces and minor increase in cementation around 20 feet bgs. SB-16/MW-7: 0.3 foot lense of moderately cemented sandstone around 33.5 feet bgs and medium hard siltstone around 34.5 feet bgs. Both DPT boreholes (i.e., MIP and continuous soil sampling boreholes) were backfilled with bentonite chips and hydrated with potable water. 2.0 Field Screening Field screening for total volatile organic compounds (VOCs) was conducted using a photoionization detector (PID) equipped with a 10.6 ev probe and calibrated to isobutylene. The PID was calibrated prior to use in accordance with the manufacturer's instructions. General PID air monitoring for the purpose of health and safety was conducted during the DPT pilot study and included periodic screening of the driller's breathing zone and the top of the borehole. VOC soil screening was conducted by taking a portion of the sample and placing it in a new plastic baggie (filled approximately one-third to one-half full). The sample was allowed to equilibrate and was vigorously agitated prior to screening. The PID probe was quickly inserted into the baggie. Prior to measuring the

3 Mr. Jeffery Skog October 9, 2007 Page 3 sample headspace, the ambient air background concentration was measured and recorded as 0.0 ppm. The headspace screening results are provided in Table 1 along with screening results recorded during advancement of boreholes SB-2 and SB-16/MW-7 (Attachment B). TABLE 1 DPT Test Boring (1) SB-2 (2) SB16/MW-7 (2) Depth 8/6/ /22/ /15/1996 (ft. bgs) (ppm) (ppm) (ppm) BKG (2) NA (3) (1) Background (BKG) PID measurement of 0.0 ppm. (2) Background (BKG) PID measurment of 0.4 ppm. (3) No PID screening since the drill cuttings from this interval were lost due to the rotosocic drill cuttings collection bag breaking. (4) Parts per million (ppm) Considering the different screening methodologies and drilling equipment used during the two investigations, the pilot study headspace screening results generally correlate to screening levels documented during advancement of boreholes SB-2 and SB-16/MW Soil Gas Survey The soil gas survey pilot test was performed in the vicinity of monitoring well MW-7 and southwest of the Launch and Service Building during the period of August 6 through 10, Twenty GORE Modules were installed along an approximate 25-foot grid at the locations identified on Figure 1. The modules were installed to a depth of 3 feet. The narrow diameter holes were advanced using a 1 1/4 -inch DPT drive point. The modules were installed and retrieved according to procedures described in GORE Soil Gas Sampling Storage, Installation and Retrieval Guidelines provided as Attachment C. The GORE TM Surveys Final Report, including data summary tables, total ion chromatograms, five color contour maps, and project specific comments is provided as Attachment D. The five color contour maps represent mass values of the following compounds desorbed from the GORE Modules: benzene, toluene, ethyl benzene and total xylenes (BETX) undecane, tridecane and pentadecane (C11, C13 and C15) gasoline-range petroleum hydrocarbons (GRPH) diesel-range petroleum hydrocarbons (DRPH) trichloroethene (TCE)

4 Mr. Jeffery Skog October 9, 2007 Page 4 The GORE Modules results and associated contour maps show that moderate to high mass levels were observed for fuel-related compounds and TCE. The spatial patterns indicate fairly well-defined petroleum soil gas plumes with the suspected source being the former RP-1 fuel tank and a TCE plume west/southwest of the wastewater drainage sump and wastewater drainage sump discharge headwall. Soil gas and product fingerprint analysis suggest that diesel fuel was stored in the former RP-1 tank after facility operations. Additional soil gas sampling is recommended to assist the delineation of the nature and extent of the fuel and TCE contamination. Note: additional soil gas data can be combined and mapped with these data. 4.0 LNAPL Sampling and Sulfur Analytical Results The LNAPL thickness in monitoring wells MW-7 and MW-9 were measured using an interface probe on August 10, An LNAPL thickness of approximately 0.3 feet was measured in MW-7 and a petroleum odor was prevalent. In an effort to confirm that LNAPL was not present in monitoring well MW-9, a new, disposable bailer was lowered into the well and groundwater was retrieved for visible inspection. The groundwater was clear with no visible or olfactory LNAPL evident. LNAPL was not measured in MW-9 and petroleum odor was not evident. An evaluation of sulfur in the fuel was recommended to provide insight to the age of the fuel present at the site. Since a fuel sample for total sulfur analysis was not collected from the DPT test borehole, a sample was collected from MW-7 on August 10, The fuel was collected using a disposable bailer. Since only approximately 0.3 feet of fuel was measured, only approximately 20 ml of LNAPL sample could be retrieved from the well. The product and water sample was placed in a 100 ml plastic bottle. A photograph of the LNAPL/water sample is provided as Attachment E. The sample was described as the following: the top of the sample is product, then degraded product with bacterial/fungal flocs, then water, then minerals (residuals from degradation process). Per an odor test, the degradation appears to be aerobic due to the absence of hydrogen sulfide odor. The observance of degraded product conflicts with the analytical interpretation of the fuel fingerprint analysis of product sampled in 2006 indicating there was no evidence of weathering on the chromatogram of the fuel product, as evidenced by the lower molecular weight hydrocarbons being present in the same ratios as the standard. After confirming the sulfur analysis could be run with the lesser quantity, the sample was placed in a 40 ml glass vial and shipped overnight on August 14, 2007 to Core Laboratories in Houston, Texas. No preservation was required. The sample was analyzed for sulfur by ASTM Method D-4294 Standard Test Method for Sulfur in Petroleum and Petroleum Products by Energy-Dispersive X-Ray Fluorescence Spectrometry. The analytical report stated WT% (1,590 ppm) total sulfur was detected in the sample. The sulfur analytical report is provided as Attachment F. From a historic perspective, a sulfur concentration of 1,590 ppm is within the historic range (210 to 6,500 ppm) and below the average (2,680 ppm) of sulfur in No.2 diesel fuel in the Rock Mountain Region for 1965 (Mineral Industry Surveys, 1965 [reference in Attachment F]). In addition, prior to 1993, on-road diesel fuels No. 2 contained an average of 2,500 ppm sulfur (U.S. EPA, 2000). In 1993, due to concerns surrounding air emissions, the EPA required that on-road varieties of low sulfur diesel fuel contain less than 500 ppm sulfur. Subsequently, the Highway Diesel rule, published on January 18, 2001 is a comprehensive national program would require refiners to further reduce the sulfur maximum to 15 ppm (ultra low sulfur diesel fuel for 80% of the on-road diesel fuels by June 2006 and the remaining 20% by 2010).

5 Mr. Jeffery Skog October 9, 2007 Page 5 Based on the historic sulfur information and the site s sulfur concentration, the site s fuel is most likely refined prior to Conclusions Advancement of DPT tools, including continuous soil sampling and MIP, were unsuccessful at attaining the required depths. Typical drilling technologies (e.g., air rotary, coring, rotosonic) are required for subsurface investigations at the Site. The field screening results generally correlated to screening levels documented during advancement of boreholes SB-2 and SB-16/MW-7 in The GORE Modules results and associated contour maps show that moderate to high mass levels were observed for fuel-related compounds and TCE. The spatial patterns indicate fairly well-defined petroleum soil gas plumes with the suspected source being in the former RP-1 fuel tank and a TCE plume southwest of the wastewater drainage sump and wastewater drainage sump discharge headwall. Additional soil gas sampling is recommended to assist the delineation of the nature and extent of the fuel and TCE contamination. Note: additional soil gas data can be combined and mapped with these data. Based on the historic sulfur information and the Site s sulfur concentration, the Site s fuel was likely refined prior to Baker is pleased to be involved with completion of this pilot study project for USACE. Should you have any questions or require clarification of this report, or any other issues related to this project, please do not hesitate to contact me by phone at or by at sfrund@mbakercorp.com. In my absence, please contact Mr. Robert Roselius at or at rroselius@mbakercorp.com. Sincerely, BAKER ENVIRONMENTAL, INC. Susan R. Frund, P.G. Project Manager

6 Baker Environmental, Inc. FIGURES

7

8 Baker Environmental, Inc. ATTACHMENT A Field Daily Quality Control Reports

9

10

11

12

13

14

15 Baker Environmental, Inc. ATTACHMENT B SB-2 and SB-16/MW-7 Drilling Logs

16

17

18

19

20

21

22

23

24

25

26

27

28

29 Baker Environmental, Inc. ATTACHMENT C GORE TM Soil Gas Sampling Storage, Installation and Retrieval Guidelines

30

31

32

33 Baker Environmental, Inc. ATTACHMENT D GORE TM Surveys Final Report

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57 Baker Environmental, Inc. ATTACHMENT E MW-7 LNAPL Photograph

58 SITE NAME: BAKER ENVIRONMENTAL, INC. PHOTOGRAPHIC RECORD Atlas E Missile Site, Windsor, Colorado PHOTOGRAPH 1 VIEW Petroleum Sample MW-7 PHOTOGRAPHS BY Baker Comments: Petroleum sample collected from MW-7 on August 10, PHOTOGRAPH 2 VIEW Petroleum Sample MW-7 After Shaking PHOTOGRAPHS BY Baker Comments: Petroleum sample collected from MW-7 on August 10, 2007 (after shaking).

59 Baker Environmental, Inc. ATTACHMENT F Sulfur Analytical Report

60 8210 Mosley Rd. Houston, TX Telephone Facsimile CORE LABORATORIES BARBARA JO HALL TEST AMERICA LABS 450 WILLIAM PITT WAY PITTSBURGH, PA Sample Number: Sample Date: Date Reported: 8/17/07 Date Received: 8/16/07 Sample ID: MW-7, Windsor,Co,8/10/07 Description: Analytical Report Test Result Units Method Date Analyst Sulfur, Total by X-Ray Fluoresc WT % ASTM D /16/07 ANM Approved By: Pat Gideons Laboratory Supervisor The analytical results, opinions or interpretations contained in this report are based upon information and material supplied by the client for whose exclusive and confidential use this report has been made. The analytical results, opinions or interpretations expressed represent the best judgment of Core Laboratories. Core Laboratories, however, makes no warranty or representation, express or implied, of any type, and expressly disclaims same as to the productivity, proper operations or profitableness of any oil, gas, coal, or other mineral, property, well or sand in connection with which such report is used or relied upon for any reason whatsoever. This report shall not be reproduced, in whole or in part, without the written approval of Core Laboratories. Page 1

61

62 References AEHS. Soil Sediment & Water. The Influences of Refining on Petroleum Fingerprinting, Part 3. Distillate Fuel Production Practices. January/February Scout, S.A., et al. Marten Law Group. Environmental News. Chemical Fingerprinting of Gasoline and Diesel Fuel What is it? Where did it come from? Who is Responsible? August 23, U.S. Department of the Interior Bureau of Mines. Mineral Industry Surveys. Diesel Fuel Oils, Petroleum Products Survey No. 42, January Table 6.

Comments provided by Dave Kacheck, CENWO-ED-GG Dated: November 2, 2007

Comments provided by Dave Kacheck, CENWO-ED-GG Dated: November 2, 2007 Baker Environmental, Inc. A Unit of Michael Baker Corporation Airside Business Park 100 Airside Drive Moon Township, PA 15108 (412)-269-6300 FAX (412) 375-3986 U. S. Army Corps of Engineers Omaha District

More information

Figure 1 illustrates the location of the Site and Figure 2 illustrates the Site layout, including borehole locations.

Figure 1 illustrates the location of the Site and Figure 2 illustrates the Site layout, including borehole locations. 1.0 Introduction Stantec Consulting Ltd. (Stantec) was retained by Mr. John Doe, on behalf of The Client to conduct a Phase II Environmental Site Assessment (ESA) at a property located at 151 Main Street,

More information

VOCs, including fuel oxygenates, via EPA Analytical Method The second soil sample from MW-24 (MW ) was analyzed for Total Organic Carbon.

VOCs, including fuel oxygenates, via EPA Analytical Method The second soil sample from MW-24 (MW ) was analyzed for Total Organic Carbon. December 5, 2012 Mrs. Jenny Herman Maryland Department of the Environment Oil Control Program 1800 Washington Boulevard Baltimore, Maryland 212301719 Re: Additional Monitoring Well Installation Report

More information

Converting Membrane Interface Probe Sensor Results Into Volatile Organic Chemical Non Aqueous Phase Liquid Distribution Information

Converting Membrane Interface Probe Sensor Results Into Volatile Organic Chemical Non Aqueous Phase Liquid Distribution Information Converting Membrane Interface Probe Sensor Results Into Volatile Organic Chemical Non Aqueous Phase Liquid Distribution Information Presented by: Roger Lamb, R.G Roger Lamb Consulting Gasoline NAPL in

More information

April 10, Ms. Lynn Dittmer Metropolitan Area Planning Agency 2222 Cuming Street Omaha, NE 68102

April 10, Ms. Lynn Dittmer Metropolitan Area Planning Agency 2222 Cuming Street Omaha, NE 68102 April 10, 2014 Ms. Lynn Dittmer Metropolitan Area Planning Agency 2222 Cuming Street Omaha, NE 68102 Re: South Omaha Brownfields Coalition Assessment Grant Phase II ESA Report Vacant Warehouse 2630 'N'

More information

COMPARISON OF DIRECT-PUSH ANALYTICAL INSTRUMENTATION

COMPARISON OF DIRECT-PUSH ANALYTICAL INSTRUMENTATION ORGANIC SYSTEMS Laser Induced Fluorescence (LIF) TWO MAJOR SYSTEMS Site Characterization and Analysis Penetrometer System (SCAPS) Rapid Optical Screening Tool (ROST TM ) Real-time, in-situ, field screening

More information

LIMITED PHASE II ENVIRONMENTAL SITE ASSESSMENT

LIMITED PHASE II ENVIRONMENTAL SITE ASSESSMENT REPORT ON LIMITED PHASE II ENVIRONMENTAL SITE ASSESSMENT 2005 Greenwood Road Shreveport, Louisiana October 2012 Prepared for: Biomedical Research Foundation of Northwest Louisiana 1505 Kings Highway Shreveport,

More information

Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 5 - Fire Training Area. NAS JRB Willow Grove Horsham, Pennsylvania

Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 5 - Fire Training Area. NAS JRB Willow Grove Horsham, Pennsylvania Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 5 - Fire Training Area NAS JRB Willow Grove Horsham, Pennsylvania Engineering Field Activity Northeast Naval Facilities

More information

Area B Groundwater Investigation Fort Detrick

Area B Groundwater Investigation Fort Detrick Area B Groundwater Investigation Fort Detrick Progress Report to the RAB November 6, 2013 John Cherry ARCADIS Imagine 1 the result Overview of Topics Groundwater Tracer Study Overview Shallow Off-Post

More information

3. FIELD INVESTIGATION PROGRAM

3. FIELD INVESTIGATION PROGRAM Department of Public Works U.S. Army Corps of Engineers Phase 1B Geotechnical Investigation Geotechnical Data Report 3.3 FIELD METHODS AND PROCEDURES 3. FIELD INVESTIGATION PROGRAM The borings were advanced

More information

Triad Case Studies from the Navy. Tim Shields and Adrianne Saboya U.S.Navy PWC Environmental Department San Diego, CA

Triad Case Studies from the Navy. Tim Shields and Adrianne Saboya U.S.Navy PWC Environmental Department San Diego, CA Triad Case Studies from the Navy Tim Shields and Adrianne Saboya U.S.Navy PWC Environmental Department San Diego, CA The Navy PWC Road to Triad Site ite Characterization and Analysis nalysis Penetrometer

More information

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1 PUBLIC WORKS DEPARTMENT David A. Jones, P.E., Director April 7, 2017 Webster Street Sub-Surface Stormwater Storage System Bid No. 2017-022 Bid Date: 4/13/17 ADDENDUM NO 1 Please make the following changes

More information

Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 1 - Privet Road Compound. NAS JRB Willow Grove Horsham, Pennsylvania

Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 1 - Privet Road Compound. NAS JRB Willow Grove Horsham, Pennsylvania Soil Investigation for Volatile Organic Compound Soil To Groundwater Impact Site 1 - Privet Road Compound NAS JRB Willow Grove Horsham, Pennsylvania Engineering Field Activity Northeast Naval Facilities

More information

IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B

IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B SITE: CHAMPAIGN FORMER MGP SITE CHAMPAIGN, ILLINOIS JULY 24, 2013 PREPARED FOR: PSC INDUSTRIAL OUTSOURCING, LP 210 WEST SAND BANK

More information

Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial Heating Oil Systems. National Oilheat Research Alliance (NORA)

Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial Heating Oil Systems. National Oilheat Research Alliance (NORA) Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial National Oilheat Research Alliance (NORA) Forward Heating oil is used to heat many private homes as well as small commercial

More information

E N V I R O N M E N T A L I N C O R P O R A T E D

E N V I R O N M E N T A L I N C O R P O R A T E D H P E N V I R O N M E N T A L I N C O R P O R A T E D April 10, 2015 Ms. Lisa Wiersma Development Manager Vornado/Charles E. Smith 2345 Crystal Drive Suite 1100 Arlington Virginia 22202 Re: Limited Phase

More information

GAMSBY AND MANNEROW Limited CONSULTING PROFESSIONAL ENGINEERS GUELPH- OWEN SOUND- LISTOWEL

GAMSBY AND MANNEROW Limited CONSULTING PROFESSIONAL ENGINEERS GUELPH- OWEN SOUND- LISTOWEL GAMSBY AND MANNEROW Limited GUELPH- OWEN SOUND- LISTOWEL 255 WOODLAWN ROAD WEST, SUITE 210 GUELPH, ONTARIO, N1H 8)1 PHONE (519) 824-8150 FAX (519) 824-8089 email: info@gamsby.com February 22, 2005 Our

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

BOS 200 Remediation at a Iowa City Terminal Coralville, Iowa USA

BOS 200 Remediation at a Iowa City Terminal Coralville, Iowa USA BOS 200 Remediation at a Iowa City Terminal Coralville, Iowa USA Background Information The Iowa City Terminal is an approximately 66-acre refined products terminal that stores and distributes various

More information

Technical Memorandum

Technical Memorandum To: J. Hamrick, J. Cain, Cotter Corporation Technical Memorandum From: E. Lawrence, HydroSolutions, W. Huskie, Nankoweep Environmental Consulting Date: July 27, 2011 Subject : TCE Soil Gas Survey, Source

More information

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL Bay County Solid Waste 11411 Landfill Rd. Panama City Beach, Florida 32413 Telephone: (850) 236-2212 Fax: (850) 233-5053 Board of County Commissioners www.baycountyfl.gov Sepetember 27, 2018 Florida Department

More information

BROWARD COUNTY ENVIRONMENTAL PROTECTION DEPARTMENT (EPD) MINIMUM CRITERIA FOR MONITORING WELL INSTALLATION AND SAMPLING

BROWARD COUNTY ENVIRONMENTAL PROTECTION DEPARTMENT (EPD) MINIMUM CRITERIA FOR MONITORING WELL INSTALLATION AND SAMPLING Failure to follow these criteria, or to obtain approval for variation to these criteria, is a citationable offense and bears an associated civil penalty, as provided in Section 27-38(h) (9), of the Broward

More information

This work will be completed in support of the corrective measures evaluation. The objectives of this study are as follows:

This work will be completed in support of the corrective measures evaluation. The objectives of this study are as follows: Peter Quackenbush Hazardous Waste Section Michigan Department of Environmental Quality 525 West Allegan Constitution Hall, 1S PO Box 30242 Lansing, Michigan, 48909 ARCADIS of Michigan, LLC 10559 Citation

More information

September 14,

September 14, September 14, 2006 001-09359-20 Ms. Barbara Cook, P.E. Chief, Northern California Coastal Cleanup epartment of Toxic Substances Control 700 Heinz venue, Suite 200 Berkeley, California 94710 Subject: Field

More information

Vapor Intrusion Assessment A Comparative Analysis of Subsurface Vapor Sampling Methods

Vapor Intrusion Assessment A Comparative Analysis of Subsurface Vapor Sampling Methods Proceedings of the Annual International Conference on Soils, Sediments, Water and Energy Volume 16 Article 10 2011 Vapor Intrusion Assessment A Comparative Analysis of Subsurface Vapor Sampling Methods

More information

May 5, Mr. Mostafa Mehran Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118

May 5, Mr. Mostafa Mehran Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118 May 5, 2015 Mr. Mostafa Mehran Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118 Re: Response to ADEQ Correspondence Dated March 30, 2015 Whirlpool Corporation

More information

April 16, Dear Mr. Beedie:

April 16, Dear Mr. Beedie: April 16, 2012 Mr. Michael Beedie, P.E. City of Ft. Walton Beach Engineering Services Department 105 Miracle Strip Parkway SW Ft. Walton Beach, FL 32548 Re: Proposal for a Supplemental Site Assessment

More information

MIP System Field Test for Mid-Low Level TCE

MIP System Field Test for Mid-Low Level TCE MIP System Field Test for Mid-Low Level TCE Dan Pip and Blake Slater of Geoprobe Systems running an MIP log at the Wall St. location in Salina, KS. Schematic of MIP Probe with VOCs penetrating the membrane.

More information

Johanna Heywood, PE, PG

Johanna Heywood, PE, PG Johanna Heywood, PE, PG MEMPHIS BROWNFIELD WORKSHOP, SEPTEMBER 10, 2014 Past use of the site Chemicals used on-site Surrounding property usage Does not generally confirm or delineate contaminated areas

More information

Case Studies: Overcoming Annoying Contaminant Rebound Using Adsorptive Technologies. RemTech Banff, AB October 11, 2018 Kevin French

Case Studies: Overcoming Annoying Contaminant Rebound Using Adsorptive Technologies. RemTech Banff, AB October 11, 2018 Kevin French Case Studies: Overcoming Annoying Contaminant Rebound Using Adsorptive Technologies RemTech Banff, AB October 11, 2018 Kevin French Presenter Kevin French, P.Eng Vice President, Vertex Environmental Inc.

More information

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133 GEOTECHNICAL EXPLORATION AND ENGINEERING SERVICES REPORT CONDUCTED FOR: Immokalee Stormwater Master Plan Implementation Immokalee, Collier County, Florida PREPARED FOR: Mr. Marc Stonehouse, P. E. Project

More information

Interim Source Removal Summary Groundwater Extraction System Former American Beryllium Company Site Tallevast, Florida

Interim Source Removal Summary Groundwater Extraction System Former American Beryllium Company Site Tallevast, Florida Interim Source Removal Summary Groundwater Extraction System Former American Beryllium Company Site Tallevast, Florida Soil and Groundwater Sampling Program On August 3, 2008, approximately 5,000 gallons

More information

Vertex Environmental Inc.

Vertex Environmental Inc. Vertex Environmental Inc. Optimizing Oxidant Delivery for In-Situ Remediation Remediation Technologies Symposium 2012 Banff, Alberta October 19, 2012 Bruce Tunnicliffe Overview Background Purpose of Talk

More information

SUBSURFACE ROTARY DRILLING INVESTIGATION SPECIFICATIONS

SUBSURFACE ROTARY DRILLING INVESTIGATION SPECIFICATIONS I. SCOPE OF WORK SUBSURFACE ROTARY DRILLING INVESTIGATION SPECIFICATIONS The Department of Environmental Protection, Bureau of Abandoned Mine Reclamation requires a contractor to conduct subsurface rotary

More information

MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No ) Van Nuys Fire Station 39

MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No ) Van Nuys Fire Station 39 MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No. 2015031067) Van Nuys Fire Station 39 W.O. E170094B ENGINEERING mtm CITY OF LOS ANGELES Transmittal

More information

APPENDIX A GENERAL FIELD PROCEDURES

APPENDIX A GENERAL FIELD PROCEDURES APPEIX A GENERAL FIELD PROCEDURES The following sections outline the general field procedures and protocols followed by Pinnacle Environmental Technologies (Pinnacle) in the completion of field tasks.

More information

RIMINI ROAD IMPROVEMENT PROJECT RESTORATION OF ABANDONED MINE SITES PROJECT DRAFT REPORT

RIMINI ROAD IMPROVEMENT PROJECT RESTORATION OF ABANDONED MINE SITES PROJECT DRAFT REPORT RIMINI ROAD IMPROVEMENT PROJECT RESTORATION OF ABANDONED MINE SITES PROJECT DRAFT REPORT Prepared by U.S. Army Corps of Engineers Omaha District Omaha, Nebraska August 2004 Table of Contents 1 Introduction...

More information

COKE OVEN AREA SPECIAL STUDY AREA INTERIM MEASURES WORK PLAN PHASE 1

COKE OVEN AREA SPECIAL STUDY AREA INTERIM MEASURES WORK PLAN PHASE 1 COKE OVEN AREA SPECIAL STUDY AREA INTERIM MEASURES WORK PLAN PHASE 1 SEVERSTAL SPARROWS POINT, LLC SPARROWS POINT, MARYLAND Prepared for: Severstal Sparrows Point, LLC Sparrows Point, Maryland In accordance

More information

ATHENS COUNTRY STORE REVISED MODIFIED CORRECTIVE ACTION PLAN REPORT ATTF CP-21

ATHENS COUNTRY STORE REVISED MODIFIED CORRECTIVE ACTION PLAN REPORT ATTF CP-21 ATHENS COUNTRY STORE REVISED MODIFIED CORRECTIVE ACTION PLAN REPORT ATTF CP-21 Athens Country Store 1303 East Elm Street Athens, Limestone Co., AL Fac ID 15310-083-009322 UST 91-07-20 PREPARED FOR Watkins

More information

SR (Sustained Release) ISCO Reagent CASE STUDY

SR (Sustained Release) ISCO Reagent CASE STUDY T r e a t m e n t T r a i n A p p r o a c h U s i n g R e m O x S R + I S C O R e a g e n t C y l i n d e r s a t F o r m e r D r y C l e a n e r SR (Sustained Release) ISCO Reagent INTRODUCTION Achieving

More information

ENVIRONMENTAL GEOLOGY - GEOL 406/506

ENVIRONMENTAL GEOLOGY - GEOL 406/506 ENVIRONMENTAL GEOLOGY - GEOL 406/506 Glossary of useful Terms: 1. Abiotic: not living. 2. A b s o r p t i o n: the penetration of atoms, ions, or molecules into the bulk mass of substrate. 3. Acclimation:

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM DATE: June 3, 2009 EMI PROJECT NO: 01-143 TO: COPY: FROM: SUBJECT: John Chun, P.E. / Port of Long Beach (POLB) Jorge Castillo

More information

PILOT PROJECT «ILE DE FRANCE»

PILOT PROJECT «ILE DE FRANCE» FINAL CONFERENCE, May 16th 2013, Ghent, Belgium PILOT PROJECT «ILE DE Direct Push Technologies (DPT) Passive Samplers for groundwater sampling Soil-gas well designs and soil-gas sampling techniques Natural

More information

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland 21230-1719 1-800-633-6101 http:/www.mde.state.md.us Darlington Citgo 3940 Conowingo Road, Darlington Harford County,

More information

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description September 22, 2016 American Infrastructure Development, Inc. 3810 Northdale Boulevard, Suite 170 Tampa, Florida 33624 Attn: Mr. Mohsen Mohammadi, Ph.D., P.E. Senior Consultant Mob: (813) 244-6609 E-mail:

More information

Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area

Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area Review of Site 16 Information Phase III Quality Assurance Project Plan Scope of Work Implementation and Schedule Site 16 Map

More information

REPORT OF LIMITED SUBSURFACE AND EXISTING PAVEMENT EVALUATION Melrose Street Reconstruction Winston-Salem, North Carolina S&ME Project No.

REPORT OF LIMITED SUBSURFACE AND EXISTING PAVEMENT EVALUATION Melrose Street Reconstruction Winston-Salem, North Carolina S&ME Project No. REPORT OF LIMITED SUBSURFACE AND EXISTING PAVEMENT EVALUATION Melrose Street Reconstruction Winston-Salem, North Carolina S&ME Project No. 1583-12-129 Prepared for: City of Winston-Salem Engineering 100

More information

HAZARDOUS MATERIAL SPILLS INFORMATION REQUEST

HAZARDOUS MATERIAL SPILLS INFORMATION REQUEST Page 1 HAZARDOUS MATERIAL SPILLS INFORMATION REQUEST QAZI TOWING 41-01 23RD STREET LONG ISLAND CITY, NY 11101 Spill Number: 0412186 Close Date: ADDRESS CHANGE INFORMATION Revised street: 4101 23RD STREET

More information

Magnesium Sulfate A METHOD TO ENHANCE THE BIODEGRADATION OF DISSOLVED PHASE-MTBE AND TBA IN ANAEROBIC ENVIRONMENTS

Magnesium Sulfate A METHOD TO ENHANCE THE BIODEGRADATION OF DISSOLVED PHASE-MTBE AND TBA IN ANAEROBIC ENVIRONMENTS Magnesium Sulfate A METHOD TO ENHANCE THE BIODEGRADATION OF DISSOLVED PHASE-MTBE AND TBA IN ANAEROBIC ENVIRONMENTS Samantha Sheer Clark and Richard A. Jasaitis C.P.G Magnesium Sulfate What is it: A salt

More information

SUPPLEMENTAL PHASE II INVESTIGATION REPORT

SUPPLEMENTAL PHASE II INVESTIGATION REPORT SUPPLEMENTAL PHASE II INVESTIGATION REPORT 8888 WEST WASHINGTON BOULEVARD CULVER CITY, CALIFORNIA Prepared For: Watt Investment Partners, LLC 2716 Ocean Park Boulevard, Suite 2025 Santa Monica, CA 90405

More information

MPCA Site Assessment: Vapor Intrusion Investigation. Remediation Division Superfund Unit 1

MPCA Site Assessment: Vapor Intrusion Investigation. Remediation Division Superfund Unit 1 MPCA Site Assessment: Vapor Intrusion Investigation Remediation Division Superfund Unit 1 MPCA Project Team Doug Wetzstein, Supervisor Dave Moore, Project Leader Dave Scheer, Hydrogeologist Hydrogeologist

More information

J ~~the following information: media type (soil cuttings and so forth), sampling location (well ID, Earth & Environmental

J ~~the following information: media type (soil cuttings and so forth), sampling location (well ID, Earth & Environmental File: 18G LIAIG CA AGRA Earth-&-- ~~~~fl~~~~~~~u~~~~~fl ~~~~~~Environmental, Inc. Earth & Environmental 600 University Avenue Suite 5E Fairbanks, Alaska U.S.A. 99709-3695 Tel (907) 479-7586 354 CES/CEVR

More information

Soil Vapor Surveys for Cost Cutting Site Characterization

Soil Vapor Surveys for Cost Cutting Site Characterization Soil Vapor Surveys for Cost Cutting Site Characterization Item Type text; Proceedings Authors Camp, Stephen E. Publisher Arizona-Nevada Academy of Science Journal Hydrology and Water Resources in Arizona

More information

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146 GEOTECHNICAL EXPLORATION SERVICES REPORT CONDUCTED FOR: Collier Boulevard PREPARED FOR: Mr. Christopher L. Johnson Director of Land Development Stock Development, LLC Professional Circle, Suite 01 Naples,

More information

In-Situ Remediation of Chlorinated Solvent Source Zone using ZVI-Clay Treatment Technology

In-Situ Remediation of Chlorinated Solvent Source Zone using ZVI-Clay Treatment Technology In-Situ Remediation of Chlorinated Solvent Source Zone using ZVI-Clay Treatment Technology Detailed site assessment work at a manufacturing facility in South Carolina indicated that a former French drain

More information

2012 Additional Block E Soil Investigation Report Lockheed Martin Middle River Complex 2323 Eastern Boulevard Middle River, Maryland

2012 Additional Block E Soil Investigation Report Lockheed Martin Middle River Complex 2323 Eastern Boulevard Middle River, Maryland 2012 Additional Block E Soil Investigation Report Lockheed Martin Middle River Complex 2323 Eastern Boulevard Middle River, Maryland Prepared for: Lockheed Martin Corporation Prepared by: Tetra Tech, Inc.

More information

Surface Soil Sampling

Surface Soil Sampling Surface Soil Sampling SSFL SOP 2 Date: December 2012 Prepared: J. Sobol Technical Review: C. Werden QA Review: J. Oxford Approved and Issued: 12/13 /2012 Signature/Date 1.0 Objective The purpose of this

More information

January 13, Mr. Mike Zamiarski New York State Department of Environmental Conservation, Region East Avon Lima Road Avon, New York 14454

January 13, Mr. Mike Zamiarski New York State Department of Environmental Conservation, Region East Avon Lima Road Avon, New York 14454 January 13, 2017 Mr. Mike Zamiarski New York State Department of Environmental Conservation, Region 8 6724 East Avon Lima Road Avon, New York 14454 Re: Quarterly Monitoring Report Third Quarter 2016 Buckeye

More information

LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING

LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING TRS Group, Inc. ABSTRACT An Electrical Resistance Heating (ERH) pilot test was conducted in the fall of 1998 to determine the effectiveness of using

More information

Advancing Mobility Testing and Aqueous-Phase Sampling in NAPL Zones

Advancing Mobility Testing and Aqueous-Phase Sampling in NAPL Zones Advancing Mobility Testing and Aqueous-Phase Sampling in NAPL Zones Michael J. Gefell, P.G., C.P.G. (mgefell@anchorqea.com) (Anchor QEA, Lakewood, CO, USA) Dimitri Vlassopoulos, Ph.D., and Masa Kanematsu,

More information

Vertex Environmental Inc.

Vertex Environmental Inc. Vertex Environmental Inc. Case Study: Innovative Use of the MIP and LIF to Direct In-Situ Remediation RPIC Conference Toronto, ON May 1, 2012 Bruce Tunnicliffe Agenda Vertex Background Subsurface Impacts

More information

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program www.pca.state.mn.us Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program This document describes the requirements for excavating petroleum-contaminated soil

More information

FIGURES Printed By: aday Print Date: 3/23/2011 12:48:08 PM File Name: \\geodesign.local\files\jobs\m-r\penskeauto\penskeauto-1\penskeauto-1-01\figures\cad\penskeauto-1-01-vm01.dwg Layout: FIGURE 1 VICINITY

More information

Industrial Activity and Site Contamination

Industrial Activity and Site Contamination Name: Date: Figure1,Mapofcontaminatedwaterfrontsites;somedegreeofcleanuphasoccurredatallofthese sites.(figure:timesstandard,april29,1996).theballoontracksiteisatlocationnumber6 (SouthernPacificyard). IndustrialActivityandSiteContamination

More information

REAL-TIME IN SITU DETECTION OF ORGANIC CONTAMINANTS BY LASER-INDUCED FLUORESCENCE SYSTEM

REAL-TIME IN SITU DETECTION OF ORGANIC CONTAMINANTS BY LASER-INDUCED FLUORESCENCE SYSTEM REAL-TIME IN SITU DETECTION OF ORGANIC CONTAMINANTS BY LASER-INDUCED FLUORESCENCE SYSTEM Final Topical Report Prepared for: Federal Energy Technology Center AAD Document Control U.S. Department of Energy

More information

EKOS Oct 2010 COMBINING SOIL GAS SAMPLING AND MIP INVESTIGATION TO OPTIMIZE A DNAPL SOURCE ZONE CHARACTERIZATION

EKOS Oct 2010 COMBINING SOIL GAS SAMPLING AND MIP INVESTIGATION TO OPTIMIZE A DNAPL SOURCE ZONE CHARACTERIZATION COMBINING SOIL GAS SAMPLING AND MIP INVESTIGATION TO OPTIMIZE A DNAPL SOURCE ZONE CHARACTERIZATION Paulo Valle Principal Consultant ERM Benelux EKOS Oct 2010 Area Layout & Project Goals Groundwater Flow

More information

Residual LNAPL Remediation Using BOS 200 at Budget Rental Car Site in Louisville, Kentucky USA

Residual LNAPL Remediation Using BOS 200 at Budget Rental Car Site in Louisville, Kentucky USA Residual Remediation Using BOS 200 at Budget Rental Car Site in Louisville, Kentucky USA Background Information Linebach Funkhouser, Inc. (LFI) personnel performed permanent closure, assessment and corrective

More information

RE: Public Comment Period regarding proposed closure of the following four Leaking Underground Fuel Tank (LUFT) Cases:

RE: Public Comment Period regarding proposed closure of the following four Leaking Underground Fuel Tank (LUFT) Cases: 2646 Palma Drive, #450 Ventura, CA 93003 P 805-654-9611 F 805-654-9613 October 17, 2014 UCSB Environmental Health & Safety Attn: Ms. Jodi Woods 565 Mesa Road Santa Barbara, California 93106-5132 RE: Public

More information

Three Case Studies: Using High Resolution Site Characterization. Patrick O Neill Vertex Environmental

Three Case Studies: Using High Resolution Site Characterization. Patrick O Neill Vertex Environmental Three Case Studies: Using High Resolution Site Characterization Patrick O Neill Vertex Environmental SMART Remediation Toronto, ON January 25, 2018 O awa, ON February 15, 2018 SMART is Powered by: www.vertexenvironmental.ca

More information

Full-Scale Permanganate Remediation of a Solvent DNAPL Source Zone in a Sand Aquifer

Full-Scale Permanganate Remediation of a Solvent DNAPL Source Zone in a Sand Aquifer Full-Scale Permanganate Remediation of a Solvent DNAPL Source Zone in a Sand Aquifer Beth L. Parker, Ph.D. University of Waterloo 1 Presented at the EPA Seminar: In Situ Treatment of Groundwater Contaminated

More information

Chlorinated DNAPL Identification using the Membrane Interface Probe (MIP)

Chlorinated DNAPL Identification using the Membrane Interface Probe (MIP) Chlorinated DNAPL Identification using the Membrane Interface Probe (MIP) Daniel Pipp, Chemist, Geoprobe Systems September 2017 Presented as a poster at the RemTEC Summit March 2017 1 Chlorinated DNAPL

More information

AR No. IR No. EIELSON AFB ALASKA. Administrative Record Cover Sheet NOTES:

AR No. IR No. EIELSON AFB ALASKA. Administrative Record Cover Sheet NOTES: AR No. IR No. EIELSON AFB ALASKA NOTES: Administrative Record Cover Sheet Aaron Lambert 2013.03.06 14:20:30-08'00' DEC/EPA Comments Dated 14 December 2012 on Draft QAPP, Phase 2 Source Evaluation at SS085

More information

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan Site Location 0606 1771 North Dixie Highway Monroe, Michigan 48162 Tel: 734-289-2200 Fax: 734-289-2345 www.manniksmithgroup.com Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe

More information

DES Waste Management Division 29 Hazen Drive; P.O. Box 95 Concord, NH

DES Waste Management Division 29 Hazen Drive; P.O. Box 95 Concord, NH DES Waste Management Division 29 Hazen Drive; P.O. Box 95 Concord, NH 03302 0095 Underground Storage Tank Closure Report Concord Steam 123 Pleasant Street Concord, NH NHDES Site Number: 198608003 Project

More information

One Oxford Valley, Suite 200 Langhorne, PA Phone: (215)

One Oxford Valley, Suite 200 Langhorne, PA Phone: (215) Enhanced Hydrostratigraphic Modeling Approach Using Direct Push Electrical Conductivity Logging (DP e-logging) By: Vincent J. Grassi,, P.G., Foster Wheeler Environmental Corporation One Oxford Valley,

More information

MARYLAND DEPARTMENT OF THE ENVIRONMENT

MARYLAND DEPARTMENT OF THE ENVIRONMENT MARYLA DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Suite 620 Baltimore, Maryland 21230-1719 410-537-3442 800-633-6101 x 3442 www.mde.state.md.us Land Management Administration Oil Control Program

More information

1.0 PROJECT INFORMATION. 1.1 Site Location and Description. October 31, 2017

1.0 PROJECT INFORMATION. 1.1 Site Location and Description. October 31, 2017 October 31, 2017 City of Oelwein c/o Fox Engineering 414 South 17 th Street, Suite 107 Ames, IA 50010 Attn: Re: Ms. Jessica M.B. Fisher, P.E. Project Manager P: (515) 233-0000 E: jmf@foxeng.com Proposal

More information

New Developments in Thermal Desorption (TD) Tube & Canister Technologies for Collection & Analysis of Soil Gas

New Developments in Thermal Desorption (TD) Tube & Canister Technologies for Collection & Analysis of Soil Gas New Developments in Thermal Desorption (TD) Tube & Canister Technologies for Collection & Analysis of Soil Gas Presented by Roy Smith, M.Sc., MBA, C.Chem. Why Use TD Tube or Canister Sampling For Collection

More information

Best Practices for Collecting Soil Samples for VOC Analysis. David Kaminski - QED Environmental Systems Inc. Dave Turriff - En Novative Technologies

Best Practices for Collecting Soil Samples for VOC Analysis. David Kaminski - QED Environmental Systems Inc. Dave Turriff - En Novative Technologies Best Practices for Collecting Soil Samples for VOC Analysis David Kaminski - QED Environmental Systems Inc. Dave Turriff - En Novative Technologies Today s Webinar Topics The science behind collecting

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

Best Practices for Collecting Soil Samples for VOC Analysis

Best Practices for Collecting Soil Samples for VOC Analysis Best Practices for Collecting Soil Samples for VOC Analysis David Kaminski - QED Environmental Systems Inc. Sarah Conard - En Novative Technologies Today s Webinar Topics The science behind collecting

More information

Christopher Gaule 1, Kenneth J. Goldstein 2,and Curtis A. Heckelman 3. Abstract

Christopher Gaule 1, Kenneth J. Goldstein 2,and Curtis A. Heckelman 3. Abstract Dual Reactive Barrier Walls for the Remediation of CHC Contamination, Watervliet Arsenal, New York: Design and Installation of an Innovative Technology Abstract Christopher Gaule 1, Kenneth J. Goldstein

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

Vapor Extraction / Groundwater Extraction (VE/GE) System Initial Report

Vapor Extraction / Groundwater Extraction (VE/GE) System Initial Report Vapor Extraction / Groundwater Extraction (VE/GE) System Initial Report Gasoline Fueling Station Royal Farms #96 500 Mechanics Valley Road North East, MD 21901 MDE OCP Case No. 2011-0729-CE Facility ID

More information

BACKGROUND OFFSITE FACILITIES/RELEASE CASES

BACKGROUND OFFSITE FACILITIES/RELEASE CASES Project No. S9955-05-02 September 18, 2017 Kemble Pope Trackside Center LLC 2940 Spafford Street, Suite 202 Davis, California 95618 Subject: ENVIRONMENTAL DATA SUMMARY TRACKSIDE CENTER 901 919 THIRD STREET

More information

Removal of Perchloroethylene within a Silt Confining Layer Using Hydrogen Release Compound

Removal of Perchloroethylene within a Silt Confining Layer Using Hydrogen Release Compound Proceedings of the Annual International Conference on Soils, Sediments, Water and Energy Volume 15 Article 20 June 2010 Removal of Perchloroethylene within a Silt Confining Layer Using Hydrogen Release

More information

DPT/MIP Investigation Scope of Services

DPT/MIP Investigation Scope of Services DPT/MIP Investigation Scope of Services An investigation will be performed using direct push technology (DPT) and membrane interface probe (MIP) analysis to close data gaps within the site conceptual model

More information

Site Characterization Technologies for DNAPL Investigations

Site Characterization Technologies for DNAPL Investigations Site Characterization Technologies for DNAPL Investigations ACEC Meeting December 8, 2004 Linda Fiedler Environmental Engineer Technology Information and Field Services Division Office of Superfund Remediation

More information

February 16, Mr. Ender Sezgin Lakeside Motorsports Altamont LLC 3500 West Olive Avenue, Suite 650 Burbank, California 91505

February 16, Mr. Ender Sezgin Lakeside Motorsports Altamont LLC 3500 West Olive Avenue, Suite 650 Burbank, California 91505 February 16, 2006 Mr. Ender Sezgin Lakeside Motorsports Altamont LLC 3500 West Olive Avenue, Suite 650 Burbank, California 91505 Re: Environmental Investigation Summary, Alameda County, California Dear

More information

P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer

P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer 2. Field Program 2.1 Health and Safety Plan Prior to beginning the field program, CH2M HILL developed a health and safety plan (H&SP). The H&SP provided a summary of potential physical hazards that could

More information

Site Profiles - View. General Information. Contaminants: Site Name and Location: Description: Historical activity that resulted in contamination.

Site Profiles - View. General Information. Contaminants: Site Name and Location: Description: Historical activity that resulted in contamination. Site Profiles - View General Information Site Name and Location: Description: Historical activity that resulted in contamination. Contaminants: Contaminants: Contaminants present and the highest amount

More information

Best Practices for Collecting Soil Samples for VOC Analysis

Best Practices for Collecting Soil Samples for VOC Analysis Best Practices for Collecting Soil Samples for VOC Analysis David Kaminski - QED Environmental Systems Inc. Sarah Conard - En Novative Technologies Today s Webinar Topics The science behind collecting

More information

If you have any questions regarding the report, please contact me at (510) , ext. 109.

If you have any questions regarding the report, please contact me at (510) , ext. 109. March 16, 2006 Mr. Nick Thom City Of San Leandro Engineering and Transportation Department 835 East 14th Street, Suite 101 San Leandro, California 94577 RE: Soil Characterization Report 2660 Eden Road,

More information

APPENDIX E SOIL VAPOR PROBE AND PIEZOMETER INSTALLATION AND MONITORING PROCEDURES Central Los Angeles High School#11 and Vista Hermosa Park

APPENDIX E SOIL VAPOR PROBE AND PIEZOMETER INSTALLATION AND MONITORING PROCEDURES Central Los Angeles High School#11 and Vista Hermosa Park Prepared for: Los Angeles Unified School District 1055 West 7 th Street, 9 th Floor Los Angeles, California 90017 APPENDIX E SOIL VAPOR PROBE AND PIEZOMETER INSTALLATION AND MONITORING PROCEDURES Central

More information

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) #47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) by Michael J. Carey Michael J. Fisher Steven R. Day Presented at: International Containment Technology

More information

ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360

ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360 ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360 Prepared for: THE MICHIGAN CITY REDEVELOPMENT COMMISSION 100 EAST MICHIGAN BOULEVARD

More information

Improved Management/Remediation of Legacy Contaminated Sites Through High-Resolution Characterization

Improved Management/Remediation of Legacy Contaminated Sites Through High-Resolution Characterization Improved Management/Remediation of Legacy Contaminated Sites Through High-Resolution Characterization Jim Langenbach, P.E., BCEE Principal Engineer Geosyntec Consultants, Cape Canaveral, FL April 2013

More information

Best Practices for Collecting Soil Samples for VOC Analysis

Best Practices for Collecting Soil Samples for VOC Analysis Best Practices for Collecting Soil Samples for VOC Analysis David Kaminski - QED Environmental Systems Inc. Sarah Conard - En Novative Technologies Today s Webinar Topics The science behind collecting

More information

Cost-Effective, Accurate Environmental Investigations Using Passive Soil Gas Sampling

Cost-Effective, Accurate Environmental Investigations Using Passive Soil Gas Sampling Cost-Effective, Accurate Environmental Investigations Using Passive Soil Gas Sampling Jay W. Hodny, Ph.D. and George E. Shaw W. L. Gore & Associates, Inc. Intersol 2009 8 th International Conference-Exhibition

More information

Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights

Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights Brian D. Symons, P.E. FOTH Infrastruture & Environment, LLC Overland Park, Kansas What We Want to Learn? Complexities of Nature Treatment

More information