1 MARCH 16, 2011 DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS FOR REROOF DFW BUSINESS CENTER SOUTH CONTRACT NO The specifications are revised as follows. Bid proposals shall include the following revisions. ALL OTHER SECTIONS OF THE SPECIFICATIONS AND DRAWINGS SHALL REMAIN THE SAME. THIS ADDENDUM CONSISTS OF NINE (9) PAGES. Item 1 Item 2 Issue specification section (2 pages), Attachment A (4 pages) and Attachment B (1 page) to provide copies of documents in the event they were omitted from the Bidder s copy of the issued Contract Documents. Issue the following responses to submitted questions. Question 1: On Business Center South: Will debris removal by use of hoist mounted over the open center section of the spiral access ramp? Response: Contractor s use of hoist down the center of the spiral access ramp will not be permitted due to safety considerations and public use of the spiral access ramp. Question 2: Can you provide information regarding who installed the original lightning protection system on South Business Center? Response: DFW Airport does not have information regarding the original lightning protection system on Business Center South. Question 3: Will existing davit arms be available for use during load testing of he davits? Response: Bidders shall assume that the davit arms will not be available for load testing. Question 4: Clarify if Contractor or DFW Airport personnel will move, disconnect/reconnect security camera mounted on the east parapet wall. Page 1 of 2

2 DFW INTERNATIONAL AIRPORT REROOF DFW BUSINESS CENTER SOUTH ADDENDUM 1 Response: Contractor shall coordinate with DFW Construction Manager to schedule time period camera to be moved (as required) and reset by contractor. After being reset by contractor, the unit will be recalibrated by DFW personnel. Note: The existing camera installation includes flexible electrical connection and bolted unistrut mounting detail which should permit camera unit to be moved for roofing, coping and davit load testing work without complete disconnection of the unit electrical service and cables. END OF ADDENDUM NO. 1 03/16/2011 Page 2 of 2

3 SECTION WAGE RATES AND FORMS PART 1 GENERAL 1.1 SUMMARY A. This section includes the required Forms and Schedules. 1.2 FORMS (Attached herein after this section.) A. Request for Authorization of Additional Classification and Rate (Standard Form 1444) B. General Wage Decision Rates for Tarrant County, TX (General Decision Number: TX (dated 01/07/2011) 1.3 WAGE RATES A. U.S. Department of Labor (DOL) provides the required minimum wages and fringe benefits to be paid to all laborers and mechanics employed to work on this contract, either under this contract or under a related subcontract. The Contractor and all subcontractors are required to report the actual wages paid to laborers and mechanics doing work under this contract. The reported wages will be verified by review of the weekly payroll reports and by periodic on-site interviews conducted by the Owner s Authorized Representative. B. The Wage Determination establishes the minimum wages and fringe benefits to be paid to laborers and mechanics throughout the duration of this contract. In no event shall these minimum wages be modified. C. In the event that the work specified in this contract requires work to be done by laborers or mechanics whose job classification is not listed in the Wage Determination, the Contractor is responsible for preparing the attached Request for Authorization of Additional Classification and Rate Standard Form 1444 (additional copies are available from the Owner s Authorized Representative). The Contractor must complete Items 3 through 15 and submit the request to the Owner s Authorized Representative prior to issuance of the Contractor's Notice to Proceed or as soon as the need for the additional classification or rate is identified (if the work has been authorized to begin). DFW International Airport WAGE RATES & FORMS Contract No ADDENDUM 1 Reroof DFW Business Center South MARCH 16, 2011

4 PART 2 PRODUCTS Not used. PART 3 EXECUTION Not used. -END OF SECTION- DFW International Airport WAGE RATES & FORMS Contract No ADDENDUM 1 Reroof DFW Business Center South MARCH 16, 2011

5

6

7

8

9 DFW International Airport Wage Rates and Forms Contract NO: B ADDENDUM 1 Reroof DFW Business Center South March16, 2011

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR TAXIWAY Y BRIDGE REINFORCEMENT FOR GROUP VI AIRCRAFT CONTRACT NO. 9500498 November 30, 2017 The Request

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

CHAPTER 12: LABOR STANDARDS

CHAPTER 12: LABOR STANDARDS CHAPTER 12: LABOR STANDARDS CHAPTER PURPOSE & CONTENTS This chapter provides states with general information on labor standards as these requirements apply to CDBG-funded construction work. The following

More information

GOVERNMENT-CONTRACTOR WAGE AND BENEFIT COMPARISONS

GOVERNMENT-CONTRACTOR WAGE AND BENEFIT COMPARISONS Appendix C GOVERNMENT-CONTRACTOR WAGE AND BENEFIT COMPARISONS PAYING LOWER WAGES AND BENEFITS In the course of this and a previous competition, we have often heard the argument that contractors provide

More information

March 6, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Addendum No. 1/RFP Y15-1023-CH DISASTER DEBRIS MONITORING SERVICES Proposal Opening Date: March 17, 2015 This addendum is hereby incorporated

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

U.S. DEPARTMENT OF LABOR SCA RESOURCE BOOK 11/2002 SCA WAGE DETERMINATIONS SERVICE CONTRACT ACT WAGE DETERMINATIONS

U.S. DEPARTMENT OF LABOR SCA RESOURCE BOOK 11/2002 SCA WAGE DETERMINATIONS SERVICE CONTRACT ACT WAGE DETERMINATIONS SERVICE CONTRACT ACT WAGE DETERMINATIONS SERVICE CONTRACT ACT, as amended (excerpt) SERVICE CONTRACT ACT WAGE DETERMINATIONS REQUESTING SCA WAGE DETERMINATIONS GUIDE TO COMPLETING AN INDIVIDUAL SF-98 REQUEST

More information

For Receipt Prior To 3:00 PM Local Time Wednesday, March 29, 2017 And Will Be Publicly Opened And Read At 3:30 PM.

For Receipt Prior To 3:00 PM Local Time Wednesday, March 29, 2017 And Will Be Publicly Opened And Read At 3:30 PM. Section BF Bid Form For Receipt Prior To 3:00 PM Local Time Wednesday, March 29, 2017 And Will Be Publicly Opened And Read At 3:30 PM. Bid Proposals will be received at the office of the Owner. Identified

More information

EDS Upgrades and CBRA Improvements. Addendum No. 2 DATE OF ADDENDUM: 08/17/2016

EDS Upgrades and CBRA Improvements. Addendum No. 2 DATE OF ADDENDUM: 08/17/2016 EDS Upgrades and CBRA Improvements Addendum No. 2 DATE OF ADDENDUM: 08/17/2016 The following changes, additions, and/or deletions are considered as Addendum No. 1, and are hereby made a part of the contract

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 3: Roofs 1 & 3 DATE: December 29, 2017 1235 Mission

More information

Scope of Work Bid Package C-4 - West Polished Concrete

Scope of Work Bid Package C-4 - West Polished Concrete Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

JOINT GUIDELINE #5. Temporary Job Utilities and Services. Construction Industry Survival Kit. The Second in a Series

JOINT GUIDELINE #5. Temporary Job Utilities and Services. Construction Industry Survival Kit. The Second in a Series The Second in a Series JOINT GUIDELINE #5 Temporary Job Utilities and Services tion between parties to the construc- tion contract. When adequate iden- tification of temporary services is pro- vided and

More information

TELEPHONE: (215) Addendum No. 1

TELEPHONE: (215) Addendum No. 1 THE SCHOOL DISTRICT OF PHILADLPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor - Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 1 Subject:

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

VANDERBILT UNIVERSITY

VANDERBILT UNIVERSITY VANDERBILT UNIVERSITY CAMPUS PLANNING & CONSTRUCTION PROJECT MANUAL GUIDELINES INTRODUCTION These instructions are intended to guide the Architect in preparing the Project Manual for Vanderbilt University

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Document Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction

Document Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction Document 00 41 13 - Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction Sealed bids will be received by Miami University at 181 Cole Service Building, Oxford,

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

42E? flwt?bl5 TEXAS TRANSPORTATION COMMISSION. ALL Counties MINUTE ORDER Page 1 of 1. ALL Districts. Submitted and reviewed by: R Co t

42E? flwt?bl5 TEXAS TRANSPORTATION COMMISSION. ALL Counties MINUTE ORDER Page 1 of 1. ALL Districts. Submitted and reviewed by: R Co t TEXAS TRANSPORTATION COMMISSION ALL Counties MINUTE ORDER Page 1 of 1 ALL Districts The Texas Department of Transportation (department) issued Purchase Order 601000000000000000000000000421 on September

More information

OSHA REQUIREMENTS FOR FAÇADE ACCESS SYSTEMS. Michael Murphy Project Engineer BOMA Brown Bag Lunch

OSHA REQUIREMENTS FOR FAÇADE ACCESS SYSTEMS. Michael Murphy Project Engineer BOMA Brown Bag Lunch OSHA REQUIREMENTS FOR FAÇADE ACCESS SYSTEMS Michael Murphy Project Engineer BOMA Brown Bag Lunch Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction,

More information

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the CONTRACT AGREEMENT This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the "City") and Contractor as of the date the last party to this Contract Agreement signed below. W I T N E

More information

Elmhurst Community Unit School District 205 Invitation to Bid

Elmhurst Community Unit School District 205 Invitation to Bid Elmhurst Community Unit School District 205 Invitation to Bid Bidders are invited to submit bids in conformance with the requirements established by the specifications herewith: Bid Number: 15-02 Item

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL DATE: February 24, 2015 Shimizu North America LLC 909 3rd Avenue, 28th Floor New York, NY 10022 RFP Queries (646) 205-4722 Fax (212) 223-1930 PROJECT: The Japan Foundation New York

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO SECTION 01010 - SCOPE OF WORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General provisions of Contract, General Conditions and Technical Specification Sections, apply to this Section. 1.02 PROJECT DESCRIPTION

More information

PURCHASING DEPARTMENT

PURCHASING DEPARTMENT PURCHASING DEPARTMENT The bid listed below has had addenda issued. Documents are available over the Internet at http://www.norwalkct.org Adobe Acrobat reader is required to view this document. If you do

More information

- Employment Law Guide A Companion to the FirstStep Employment Law Advisor

- Employment Law Guide A Companion to the FirstStep Employment Law Advisor Page 1 of 5 - Employment Law Guide A Companion to the FirstStep Employment Law Advisor Federal Contracts-Working Conditions: Prevailing Wages in Service Contracts Who Is Covered Basic Provisions/Requirements

More information

Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms

Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms To be completed and signed by the Prime Vendor/Contractor Bid/RFP : Title: Company Name: Company Address: City: State: Zip: Contact

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

FTW 175 Wireless Monitoring System Reference Manual Part Number

FTW 175 Wireless Monitoring System Reference Manual Part Number FTW 175 Wireless Monitoring System Reference Manual Part Number 7911751 SERIAL NUMBER Flash Technology, 332 Nichol Mill Lane, Franklin, TN 37067 www.spx.com/en/flash-technology (615) 261-2000 Front Matter

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION LOBBY AND CAFETERIA FLOORING INSTALLATION EVERETT MIDDLE SCHOOL ADDENDUM NO.

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION LOBBY AND CAFETERIA FLOORING INSTALLATION EVERETT MIDDLE SCHOOL ADDENDUM NO. SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION LOBBY AND CAFETERIA FLOORING INSTALLATION ADDENDUM NO. 1 PROJECT: 450 CHURCH STREET DATE: 13 FEBRUARY 2015 San Francisco, 94114 OWNER:

More information

ADDENDUM NO. 1. FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA

ADDENDUM NO. 1. FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA ADDENDUM NO. 1 FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA Bids to be received until 2:00 p.m., local time, July 9, 2012 SPECIFICATIONS Delete Section 00 41 53 Bid Unit Price in

More information

ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH

ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH ADDENDUM NO. 1 TO CONTRACT DOCUMENTS DATED FEBRUARY 12, 2015 FOR ADDITION TO ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH Located at 8910 Gap Newport Pike Avondale, PA 19311 ARCHITECT 270 South Main Street,

More information

AASHTOWARE PROJECT. Civil Rights and Labor Training Guide

AASHTOWARE PROJECT. Civil Rights and Labor Training Guide AASHTOWARE PROJECT Civil Rights and Labor Training Guide CONTACT INFORMATION AASHTOWare Project CRL Administrators KDOT#AWP.ADMIN@KS.GOV KDOT Computer Training Component KDOT.KCTC@KS.GOV SYSTEM BENEFITS

More information

INVITATION TO BID. WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226

INVITATION TO BID. WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226 INVITATION TO BID WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226 February 23, 2016 DESCRIPTION OF SERVICES The intent of this invitation

More information

INVITATION TO BID. Roof Repair Multiple Elastomeric Coating Roofs. Invitation to Bid No. 2013/14-09

INVITATION TO BID. Roof Repair Multiple Elastomeric Coating Roofs. Invitation to Bid No. 2013/14-09 INVITATION TO BID Invitation to Submittal Deadline: Wednesday, April 30, 2014 at 2:00 p.m. Mail bids to the following address: Curry County Administration 700 N. Main Street, Suite 10 Clovis, NM 88101

More information

Scope of Work Bid Package C-3 - West Precast Concrete

Scope of Work Bid Package C-3 - West Precast Concrete Scope of Work Bid Package C-3 - West Precast Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

Solicitation No Passenger Wait Time System, please be advised of the following clarifications to the above referenced Solicitation.

Solicitation No Passenger Wait Time System, please be advised of the following clarifications to the above referenced Solicitation. February 2, 2018 CLARIFICATION LETTER No. 1 Re: Solicitation No. 7006612 Passenger Wait Time System, please be advised of the following clarifications to the above referenced Solicitation. (Note: Other

More information

DATE: August 22, All Proposers

DATE: August 22, All Proposers DATE: August 22, 2017 TO: All Proposers RE: Addendum No. 2 RFP for the Design of Lighting Upgrades for David L. Lawrence Convention Center Roadways and Sidewalks and North Shore Garage Interior and Exterior

More information

ADDENDUM No 1 - date 9 April 2016 The Specifications and Bid Documents are modified as follows:-

ADDENDUM No 1 - date 9 April 2016 The Specifications and Bid Documents are modified as follows:- Page 1 of 3 SECTION 00 91 13 - ADDENDUM th ADDENDUM No 1 - date 9 April 2016 The Specifications and Bid Documents are modified as follows:- 1. DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS Section

More information

Penn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications

Penn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications Penn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications 1. FENCE REQUIREMENTS Hazard Trees All hazard trees, which are within tree length of the fence, must be felled

More information

ADDENDUM NUMBER 01 TO THE BID DOCUMENTS. BID NUMBER: SJCC Parking Garage LED Lighting Retrofit EVERGREEN VALLEY COLLEGE

ADDENDUM NUMBER 01 TO THE BID DOCUMENTS. BID NUMBER: SJCC Parking Garage LED Lighting Retrofit EVERGREEN VALLEY COLLEGE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT ADDENDUM NUMBER 01 TO THE BID DOCUMENTS To all general contract bidders of record on the Bid Proposal: BID NUMBER:0215-17 SJCC Parking Garage LED Lighting

More information

The Columbus Regional Airport Authority (CRAA) hereby issues addenda to the subject solicitation:

The Columbus Regional Airport Authority (CRAA) hereby issues addenda to the subject solicitation: February 13, 2015 NOTICE OF ADDENDUM ADDENDUM #4 Subject: Date Due: Wireless System Design and Replacement; Request For Proposals (RFP) # FIT-2015-001 February 23, 2015 at 2:00 PM EDT Dear Sir or Madam:

More information

Queen Anne s County. ADDENDUM NO. 1 July 31, 2015

Queen Anne s County. ADDENDUM NO. 1 July 31, 2015 Queen Anne s County County Commissioners: James J. Moran, At Large Jack N. Wilson, Jr., District 1 Stephen Wilson, District 2 Robert Charles Buckey, District 3 Mark A. Anderson, District 4 OFFICE OF BUDGET,

More information

Online Certified Payroll Systems (OCPS)

Online Certified Payroll Systems (OCPS) Online Certified Payroll Systems (OCPS) User Manual 1 Table of Contents Table of Contents.... 2 Welcome. 3 Registration. 4 Request for Access Form... 5 E-Signature Authorization.. 6 Getting Started 7 Login

More information

AIPHONE Installation Specifications. Addendum I. December 12, 2014

AIPHONE Installation Specifications. Addendum I. December 12, 2014 TECHNOLOGY SERVICES AIPHONE Installation Specifications Addendum I December 12, 2014 425 Prescott Street Greensboro, NC 27401 P 336.335.3000 Addendum I Sections with modifications, additions, or deletions

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

Davis-Bacon Overview and Step-By-Step Guide

Davis-Bacon Overview and Step-By-Step Guide September 2004 Davis-Bacon Overview and Step-By-Step Guide Table of Contents Section 1- The Letter of the Law...... 2 Section 2- A Step-by Step guide...... 3 Section 3- What happens when things go Wrong....

More information

To: All Interested Bidders Re: RFP # 09-X CONTRACTED SYSTEM ADMINISTRATOR FOR THE CHILDREN S SYSTEM OF CARE ADDENDUM #2

To: All Interested Bidders Re: RFP # 09-X CONTRACTED SYSTEM ADMINISTRATOR FOR THE CHILDREN S SYSTEM OF CARE ADDENDUM #2 State of New Jersey DEPARTMENT OF THE TREASURY JON S. CORZINE DIVISION OF PURCHASE AND PROPERTY R. DAVID ROUSSEAU Governor PURCHASE BUREAU State Treasurer P.O. BOX 230 TRENTON, NEW JERSEY 08625-0230 November

More information

Request For Proposal. Interactive Projectors

Request For Proposal. Interactive Projectors Jackson County Intermediate School District On Behalf of Columbia School District Request For Proposal Interactive Projectors 1/22/2015 Issued by: Jackson County Intermediate School District Attention:

More information

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011 TO: All Bidders From: Gila River Indian Community, Property and Supply Department The following addendum to the George Webb Village Subdivision Infrastructure construction project is made. Acknowledgment

More information

BID PROPOSAL. For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES. Page Article 1 Bid Recipient...

BID PROPOSAL. For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES. Page Article 1 Bid Recipient... BID PROPOSAL For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES Page Article 1 Bid Recipient... 1 Article 2 Bidder s Acknowledgements... 1 Article 3 Bidder s Representations...

More information

PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA. Terrazzo Floors at Concourse B, C and E ADDENDUM NO. 4

PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA. Terrazzo Floors at Concourse B, C and E ADDENDUM NO. 4 Addendum No. 4 Page 1 of 5 ATTENTION ALL POTENTIAL BIDDERS: PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA Terrazzo Floors at Concourse B, C and E ADDENDUM NO. 4 DATE OF ADDENDUM:

More information

ADDENDUM NO. A. April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR

ADDENDUM NO. A. April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR ADDENDUM NO. A April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR LOTHIAN RESIDENCE HALL SEISMIC UPGRADES BID PACKAGE 4 PROJECT NO. 956366 CONTRACT NO. 956366-LF-2017-163 UC Rev. 0, August 1, 2007 UCR Rev

More information

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY 67-A1. Definitions. 67-A2. City of Toronto Council references. 67-A3. Purpose and history of Fair Wage Policy. 67-A4. Intent of Fair Wage Policy. 67-A5. Application. 67-A6.

More information

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

Management. Construction. Development. WE PROVIDE A complete roster of building services to streamline the construction process

Management. Construction. Development. WE PROVIDE A complete roster of building services to streamline the construction process WE ARE: We are a family-owned construction company providing construction services to general contractors and real estate owners throughout the San Francisco Bay Area. Founded in 2001, Argo Construction

More information

What is the Department of Public Works Project Labor Agreement (DPW-PLA)?

What is the Department of Public Works Project Labor Agreement (DPW-PLA)? City of Los Angeles Department of Public Works PLA / Public Works Infrastructure Stabilization Policy Frequently Asked Questions for Project Labor Agreement 2015-2020 Please note: This document is meant

More information

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS

More information

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project RES. NO. PROPOSAL FOR THE COMPLETION OF 2015-28 TO THE SATISFACTION OF THE BUTLER COUNTY COMMISSIONERS AND THE COUNTY ENGINEER: SAID WORK CONSISTING OF TYLERSVILLE ROAD IMPROVEMENTS, PHASE I TO THE COUNTY

More information

ADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1

ADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1 ADDENDUM No. 6 ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1 Due: June 9, 2016 at 2:00 p.m. (local time) The following changes, additions, and/or deletions

More information

Amalie Arena Sixth Floor East Roof Replacement

Amalie Arena Sixth Floor East Roof Replacement Amalie Arena Sixth Floor East Roof Replacement 401 Channelside Drive Tampa, Florida 33602 February 18, 2016 ROOF ENGINEERING ASSOCIATES, INC. 500 County Road One, P.O. Box 549 Palm Harbor, FL 34682-0549

More information

Midwester State University Health Science Center

Midwester State University Health Science Center Bid Proposal For: Bid Due: Bids Received At: Email Bid to: Midwester State University Health Science Center 8-Aug-17 Midwestern State University Attn: Steven Shelley - Director of Purchasing/Contract Management

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION PROJECT: West Portal Elementary School DATE: January 18, 2017 5 Lenox Way, CA 94123 Yard #4 Improvements SFUSD Project No. 11869

More information

Department of Labor and Workforce Development

Department of Labor and Workforce Development Department of Labor and Workforce Development Labor Standards and Safety Wage and Hour Administration 1251 Muldoon Road, Suite 113 Anchorage, Alaska 99504 Main: 907.269-4909 Fax: 907.269-4915 1) What is

More information

PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15

PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15 TENDER NO MR 151/2016 PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15 Notes : 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan to be incuded in tender

More information

Janet L. Ravey. Town of Truckee

Janet L. Ravey. Town of Truckee Janet L. Ravey Town of Truckee A Transit Shelter Engineering support background Transit support background 10 years Town of Truckee Up for challenges! Project Background Workforce Housing Grant had been

More information

REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements

REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements Page 1 of 16 University of Washington REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements Project No. 205729 Submittal Deadline Date: No later than

More information

Supply to Rancho De Viti Investments Corporation at Maranitawa - Ba (Scheme No. G52/07)

Supply to Rancho De Viti Investments Corporation at Maranitawa - Ba (Scheme No. G52/07) MR 96/2015 Supply to Rancho De Viti Investments Corporation at Maranitawa - (Scheme No. G52/07) Notes: 1. Safety Plan to be included in tender bid. 2. Lineman and Trainee Lineman/Line worker Certificate

More information

1. Revision: The bid date has been postponed to July 18, 2012 at 1:30 PM.

1. Revision: The bid date has been postponed to July 18, 2012 at 1:30 PM. East Energy Chiller 1 Cooling Tower Addition State Project Number H27-1969 Addendum Three July 12, 2012 NOTE: The following amendments, additions, and deletions shall be made to the Construction Documents

More information

Furnish, Deliver and Install New Generator USC Aiken

Furnish, Deliver and Install New Generator USC Aiken AMENDMENT NO. 1 TO: FROM: SUBJECT: ALL VENDORS Lana Widener USC-IFB-2710-LW Furnish, Deliver and Install New Generator USC Aiken DATE: October 24, 2014 This Amendment No. 1 modifies the Invitation for

More information

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES 1 of 15 CS & ASSOCIATES EXPERIENCE & BACKGROUND Established in 2003 by Charla Curtis, Former LCP Director for LAUSD Certified MBE/

More information

UMBC PAHB II AV Classroom Systems BID # BC R ADDENDUM #4

UMBC PAHB II AV Classroom Systems BID # BC R ADDENDUM #4 Department of Procurement University of Maryland, Baltimore County 1000 Hilltop Circle Baltimore, MD 21250 DATE: August 7, 2013 TO: All Prospective Bidders Cc: Procurement File PHONE: 410-455-2273 FAX:

More information

UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL

UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL DATE: January 5, 2018 UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL 32170-010 ITB# 04-18 REPLACE 12 WATER MAIN AT TURNBULL BAY (DAMAGED DURING

More information

Local Area Apprenticeship and Employment Opportunities Program

Local Area Apprenticeship and Employment Opportunities Program Local Area Apprenticeship and Employment Opportunities Program Definitions For the purposes of the Procedures described herein, the following terms are defined as follows: WSIP: Water System Improvement

More information

REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM PROJECT DESCRIPTION

REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM PROJECT DESCRIPTION REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM The Carroll County Public Service Authority requests bids from properly licensed well drilling firms, hereafter referred to as

More information

City of Augusta SIDEWALK REPLACEMENT PROGRAM

City of Augusta SIDEWALK REPLACEMENT PROGRAM CONDITIONS 1. This program is designed to replace older public sidewalks in the City. 2. This program will not cover new sidewalks, driveways or sidewalks from the public sidewalk to the dwelling or business.

More information

ALL BIDDERS shall acknowledge receipt of this Addendum No. 1 on the BID FORM or the BID will be deemed to be invalid for the purposes of this project.

ALL BIDDERS shall acknowledge receipt of this Addendum No. 1 on the BID FORM or the BID will be deemed to be invalid for the purposes of this project. LOS ANGELES COMMUNITY COLLEGES 770 Wilshire Boulevard, Los Angeles, CA 90017 Telephone: 213/891-2000 CITY EAST HARBOR MISSION PIERCE SOUTHWEST TRADE TECHNICAL VALLEY WEST ADMINISTRATIVE OFFICES Date: October

More information

Maintenance, Repair, and Operations JOC Program

Maintenance, Repair, and Operations JOC Program Maintenance, Repair, and Operations JOC Program Pre-Proposal Meeting CSP #16-11-07 Building Automation Systems CSP #16-11-08 Glass and Glazing Service CSP #16-11-09 HVAC / Mechanical CSP #16-11-10 Plumbing

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

DESIGN ARCHITECTS, INC.

DESIGN ARCHITECTS, INC. DESIGN ARCHITECTS, INC. ROOF REPLACEMENT WOOD RIVER PUBLIC LIBRARY DAi # 270-0325 Wood River Public Library 326 E. Ferguson Ave. Wood River, Madison County, Illinois Kate Kite, Director April 21, 2015

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

City of New Haven. 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone * * Fax

City of New Haven. 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone *  * Fax City of New Haven 101 FRONT STREET PO BOX 236 NEW HAVEN, MO 63068 Phone 573-237-2349 * www.newhavenmo.org * Fax 573-237-4696 February 19, 2013 Request for Bids New Haven City Park Bock Field fencing The

More information

IMPACTING DAVIS-BACON WAGE DETERMINATIONS

IMPACTING DAVIS-BACON WAGE DETERMINATIONS IMPACTING DAVIS-BACON WAGE DETERMINATIONS A Guide for Contributing to the Accuracy of Published Prevailing Wage Rates in Construction By: Tamika C. Carter, Director of Construction HR Contractors and other

More information

1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately $1.2 million a year.

1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately $1.2 million a year. RFP for Information Technology Services- Questions Due: 8/11, 3pm, Answers due 8/16 Questions/Answers 1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately

More information

Request for Qualifications Professional Services For. Wood Recycling Center Facility. Contract Number: C City of Chattanooga, Tennessee

Request for Qualifications Professional Services For. Wood Recycling Center Facility. Contract Number: C City of Chattanooga, Tennessee Request for Qualifications Professional Services For Wood Recycling Center Facility Contract Number: C-17-017-101 City of Chattanooga, Tennessee December 2017 Section 1 Introduction REQUEST FOR QUALIFICATIONS

More information

JEFFERSON PARISH SHERIF S OFFICE

JEFFERSON PARISH SHERIF S OFFICE ADDENDUM NO. 1 TO THE BID DOCUMENTS FOR: NEW JEFFERSON PARISH SHERIFF S OFFICE 1 ST DISTRICT STATION 3620 HESSMERAVENUE METAIRIE, LOUISIANA 70002 JEFFERSON PARISH SHERIF S OFFICE Jefferson Parish Bid No.:

More information

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE AZUSA UNIFIED SCHOOL DISTRICT 1 TABLE OF CONTENTS Filing of PreQualifications Submittals 3 PREQUALIFICATION QUESTIONNAIRE 6 Page Part I:

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

I. General Information. A. Project Team & Contacts: Role Company Name Phone City of Johnson City Jeff Owner Water & Sewer Harmon, PE Department

I. General Information. A. Project Team & Contacts: Role Company Name Phone  City of Johnson City Jeff Owner Water & Sewer Harmon, PE Department I. General Information Civil Engineering Surveying Environmental Consulting Tysinger, Hampton & Partners, Inc. OPTIONAL PRE-BID MEETING MINUTES Austin Springs Road Water Line Replacement Project ITB #6190

More information

PLANNING DESIGN & CONSTRUCTION PROCESS. Campus Department Owner Guide

PLANNING DESIGN & CONSTRUCTION PROCESS. Campus Department Owner Guide PLANNING DESIGN & CONSTRUCTION PROCESS Campus Department Owner Guide PLANNING DESIGN & CONSTRUCTION PROCESS 1. Identify Need 2. Work Order Process 3. Project Management 4. Identify Funding 5. Design Process

More information

FLOORS 3, 14 & 21 D322, D1422, D2122 Qty. 3 Size 2-6 x 6-0

FLOORS 3, 14 & 21 D322, D1422, D2122 Qty. 3 Size 2-6 x 6-0 entirely and masonry as required for installation of new door & frame (Kitchen Floors 5, 12, & 19). 4. At the DEMOLITION NOTES, DELETE Note D-4 in its entirety and REPLACE with the following: Saw cut and

More information

FEDERAL CONTRACTOR VETERANS EMPLOYMENT REPORT VETS-4212

FEDERAL CONTRACTOR VETERANS EMPLOYMENT REPORT VETS-4212 FEDERAL CONTRACTOR VETERANS EMPLOYMENT REPORT VETS-4212 OMB NO: 1293-0005 Expires: 11/30/2017 Persons are not required to respond to this collection of information unless it displays a valid OMB number.

More information

Depot Park Gazebo Project

Depot Park Gazebo Project BID SET Contract Documents & Specifications Depot Park Gazebo Project Whitefish, Montana Prepared for City of Whitefish, Montana Prepared by: Robert Peccia & Associates Kalispell, Montana April, 2016 Set

More information

REVISED NEW HANOVER COUNTY OGDEN SKATEPARK SPECIALTY PRE-QUALIFICATION PACKET

REVISED NEW HANOVER COUNTY OGDEN SKATEPARK SPECIALTY PRE-QUALIFICATION PACKET REVISED NEW HANOVER COUNTY OGDEN SKATEPARK SPECIALTY PRE-QUALIFICATION PACKET This project is being readvertised due to the small number of prequalification packages received in response to the county's

More information

Asbestos Removal at Forest Blvd., Hugo, MN

Asbestos Removal at Forest Blvd., Hugo, MN Request for Bids for Asbestos Removal at 14383 Forest Blvd., Hugo, MN This Request for Bids ( RFB ) is for the services of a qualified and licensed contractor to provide removal of Asbestos contaminated

More information

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated. SECTION 024119 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information