Building for the Future - Greensboro to Charlotte Double Track Projects on the North Carolina Railroad

Size: px
Start display at page:

Download "Building for the Future - Greensboro to Charlotte Double Track Projects on the North Carolina Railroad"

Transcription

1 Building for the Future - Greensboro to Charlotte Double Track Projects on the North Carolina Railroad By Jason Orthner, P.E. Engineering Manager, Design and Construction North Carolina Department of Transportation Rail Division Brad Kerchof, P.E. Director of Engineering Norfolk Southern Corporation Jim Kessler, P.E. Senior Rail Project Manager Gibson Engineers, PC American Railway Engineering and Maintenance of Way Association Annual Technical Conference Orlando, FL August 2010

2 ABSTRACT The NCDOT, NCRR and Norfolk Southern have been upgrading the NCRR corridor between Raleigh and Charlotte to improve safety, speeds, capacity and operations. The NCRR corridor segment between Charlotte and Greensboro is the most heavily used rail corridor in NC with over 40 freight trains daily and is a key link in NSR s freight rail Crescent Corridor. This rail line also hosts eight daily Amtrak trains and is a part of the Southeast High Speed Rail corridor. The NCRR was upgraded after its original construction in the 1850s to improve geometry and add a second track. In the 1960s, however, the line generally became single track again as railroad traffic decreased. Today s SEHSR corridor designation and increasing freight traffic require additional capacity. Four significant projects between Charlotte and Greensboro were necessary to fully double track this segment. Construction of the 9-mile Greensboro to High Point section was completed in December Three projects totaling 27 miles are in preliminary design and environmental phases. The entire double track program is expected to be completed in When these projects are complete, the railroad between Charlotte and Greensboro will be more efficient and safer, and will enhance both the freight and passenger transportation systems in North Carolina. The paper describes the importance of the rail corridor, methods employed in completing design and construction, and the key challenges of upgrading the corridor to meet both freight and HSR requirements.

3 Building for the Future - Greensboro to Charlotte Double Track Projects on the North Carolina Railroad TABLE OF CONTENTS Title ABSTRACT INTRODUCTION THE NCRR AND THE GREENSBORO TO CHARLOTTE CORRIDOR FREIGHT OPERATIONS PASSENGER OPERATIONS NORTH CAROLINA RAILROAD IMPROVEMENT PROGRAM (NCRRIP) THE SOUTHEAST HIGH SPEED RAIL CORRIDOR AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) CP COX TO CP HOSKINS - LESSONS LEARNED THE NEW PROJECT APPROACH ENVIRONMENTAL AND PUBLIC INVOLVEMENT PROCESS PROJECT DETAILS ESTIMATED COSTS CURRENT STATUS AND SCHEDULE FOR COMPLETION SUCCESS IN THE FREIGHT-PASSENGER RELATIONSHIP CONCLUSION LIST OF FIGURES

4 INTRODUCTION The NCDOT, NCRR and Norfolk Southern have been upgrading the NCRR corridor between Raleigh and Charlotte to improve safety, speeds, capacity and operations under a program entitled the North Carolina Railroad Improvement Program (NCRRIP). With over forty freight trains a day, the NCRR segment between Charlotte and Greensboro is the most heavily used rail corridor in North Carolina and is a key link in NS s freight rail Crescent Corridor. This rail line also hosts eight daily Amtrak trains and is a part of the Southeast High Speed Rail (SEHSR) corridor. The NCRR was originally constructed in the 1850s and was later upgraded to improve geometry and add a second track. In the 1960s, however, the line generally became single track again as railroad traffic decreased. Today s SEHSR corridor designation and increasing freight traffic require additional capacity and modernization. Construction of four segments of second main track between Charlotte and Greensboro are required to fully double track the route. The first nine miles between Greensboro and High Point (CP Cox to CP Hoskins) was completed in December Three additional projects totaling approximately 27 miles are currently in the preliminary design and environmental document phase: CP Bowers to CP Lake, CP Reid to CP North Kannapolis, and CP Haydock to CP Junker. The entire double track program is expected to be completed in When these projects are complete, the railroad between Charlotte and Greensboro will be more efficient and safer, and will enhance both the freight and passenger transportation systems in North Carolina.

5 THE NCRR AND THE GREENSBORO TO CHARLOTTE CORRIDOR The North Carolina Railroad Company is the owner of the right-of-way and tracks on the Charlotte to Greensboro corridor. The NCRR, a private railroad company owned by the State of North Carolina, is a 317-mile rail corridor that connects Morehead City, the location of one of North Carolina State Port Authority's major facilities, to Charlotte, North Carolina s largest city. The NCRR was authorized by the NC State Legislature in 1848 to construct a railroad linking the eastern part of the state to the Piedmont. Construction began in 1851 and in 1859 the first train ran between Goldsboro and Charlotte. In 1989, the Atlantic and North Carolina Railroad, which ran from Goldsboro to Morehead City, was merged into the NCRR. Figure 1: North Carolina Railroad Company Corridor The NCRR owns and manages the rail corridor and Norfolk Southern Railway (NS), through an operating agreement with NCRR, operates and maintains the railroad for NCRR.

6 The Charlotte to Greensboro portion of the NCRR is known as the Main Line. This heavily used line extends 92 miles between the Charlotte yard and Elm Interlocking in Greensboro. NS's mainline continues south from Charlotte to Greenville, SC and Atlanta, GA, while northward from Greensboro, the NS continues to Danville and Lynchburg, VA and eventually the northeast United States. THE NCRR Main Line is a part of NS's Crescent Corridor connecting the northeast US with the South. FREIGHT OPERATIONS Norfolk Southern provides both through and local freight service over the NCRR corridor. The main line between Greensboro and Charlotte carries more than 40 MGT in traffic per year and the volume is growing. As part of its Crescent Corridor, this portion of the NCRR provides a critical link for NS growing interstate traffic. The Crescent Corridor is both a collection of rail lines and a transportation infrastructure concept. It is a 2500-mile network of existing track, stretching from New Jersey, Philadelphia and Harrisburg in the Northeast, to Memphis and New Orleans in the Southeast. Two predominately north-south routes, one running parallel to I-85 between Raleigh and Atlanta, and a second running alongside I-81 through the Shenandoah Valley between Manassas and Knoxville, make up the mid-section of the Corridor. Crescent is being developed as a solution to the growing traffic congestion on these interstate corridors, congestion that is caused in large part by expanding inter-city truck volume. NS is partnering with federal, state and local governments to create a rail transportation alternative to new highway construction: by building rail infrastructure and moving trucks off the highway and onto trains, Crescent offers a fuel efficient alternative to building new highways.

7 Figure 2: Norfolk Southern Crescent Corridor In this public-private partnership model, NS pays for the benefits it receives - the additional rail business while government is asked to pay for the benefits it receives avoiding very expensive new highway construction and highway maintenance. Further public benefits include lower fuel consumption, lower emissions, more efficient land use and enhanced highway safety. At full build-out, Crescent anticipates moving one million truck hauls from highway to rail. Crescent allows truckers to do what they do well moving freight short distances, while allowing the railroad to do what it does well moving freight longer distances. NS is already making improvements to the corridor that will increase its capacity and make it more efficient, such as building second main tracks and passing sidings, straightening curves and improving signal systems. New (and expanded) intermodal terminals are a critical component of the Crescent Corridor, and work is already underway at two Southern cites

8 Birmingham and Memphis, where $100 million facilities will be built in the next two years, funded half by NS and half by Federal Stimulus money through the TIGER program. The Crescent Corridor freight initiative is important to the Greensboro to Charlotte corridor for a couple of reasons: North Carolina will benefit from the expanded rail service and the economic advantages that rail provides; but the additional eight intermodal trains forecast when Crescent reaches it full potential means that capacity improvements are critical if North Carolina is going to operate a fast, reliable and frequent intercity passenger service. PASSENGER OPERATIONS North Carolina has one of the most comprehensive programs in the country for investing and operating intercity passenger rail services. In addition to national system Amtrak services, the state subsidizes two Amtrak services, the Carolinian (Charlotte Washington, D.C. New York) and the Piedmont service (Charlotte Raleigh). The state has also been heavily involved in the development of station facilities, improving dozens of stations across the state including the signature Greensboro station. Greensboro Passenger Station

9 Amtrak operates several services in the Greensboro to Charlotte corridor. The Crescent provides daily intercity service between New Orleans and New York, making stops in Charlotte, Salisbury, High Point and Greensboro. The Carolinian operates one round trip between New York and Charlotte on a daily basis. The Piedmont complements the Carolinian service between Raleigh and Charlotte with two round trip pairs. Both the Carolinian and Piedmont make stops at Kannapolis in addition to the Crescent stops. The Piedmont service was expanded in June 2010 to include a mid-day round-trip, resulting in eight daily passenger trains between Greensboro and Charlotte. Future expansion of the Piedmont service will be coordinated with the development of the double track projects. Figure 3: Passenger Rail Service in North Carolina NORTH CAROLINA RAILROAD IMPROVEMENT PROGRAM (NCRRIP) In 2001, the NCDOT, NCRR, and NS signed a master agreement providing a platform for significant improvements along the NCRR route between Raleigh and Charlotte. Funding primarily flowed through the NCDOT from state sources, with some federal surface

10 transportation funds, to improve existing tracks, install new signals and build stretches of new track. The projects were designed to enhance the existing NCDOT sponsored passenger services between Raleigh and Charlotte. In addition, related work has been completed on the Raleigh to Selma portion of the NCRR. Figure 5 illustrates the scope of NCRRIP improvements. Projects included new traffic control signal systems, new and extended passing sidings, major interlocking improvements, and the further advancement of the nationally recognized Sealed Corridor grade crossing safety initiative. The NCRRIP program has also coordinated with the states station development program in the improvement of station tracks and platforms. NCRRIP has constructed approximately $65 Million in improvements and reduced the travel time between Raleigh and Charlotte by more than 35 minutes since the work began in In addition to reducing the travel time, the work greatly increased efficiency and reliability for both freight and passenger trains in the corridor. Figure 4: Track Improvements on the North Carolina Railroad

11 Planning and design of the double track projects began under the umbrella of NCRRIP. The projects were originally envisioned largely as double track replacements without significant track alignment, bridge, and grade crossing improvements. Funding under the American Recovery and Reinvestment Act (ARRA) has provided an opportunity to develop a more robust set of improvements than originally envisioned under NCRRIP, particularly with regard to alignment improvements and grade crossing elimination. THE SOUTHEAST HIGH SPEED RAIL CORRIDOR (SEHSR) The SEHSR corridor between Washington, D.C. and Richmond, Raleigh and Charlotte was among five high speed rail corridors originally designated by the US Department of Transportation in The final Tier I draft environmental impact statement (EIS) was completed in June 2002 and selected the corridor through Petersburg VA, and Henderson, Raleigh, Greensboro, and Charlotte, NC. In October of that year, the FRA and FHWA issued a Record of Decision approving the project and allowing a second round of environmental studies to begin. The Draft Tier II EIS for the route between Richmond and Raleigh was completed in 2010 and FRA signed the document in May The final Tier II EIS is expected to be completed in mid 2011 with a Record of Decision expected in late This portion of the corridor will initially operate at speeds up to 110 mph. The SEHSR passenger service will operate via the NCRR between Raleigh, Greensboro and Charlotte with a proposed maximum passenger speed of 90 mph. Four additional round trips between Charlotte and Washington are envisioned with the new route. One of the key components of the double track projects, in addition to increasing capacity, is improving the NCRR corridor to enable passenger trains to operate at higher speeds with enhanced safety.

12 Figure 5: Southeast High Speed Rail Corridor AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) The American Recovery and Reinvestment Act (ARRA) was authorized by the federal government in February The purpose of ARRA is to stimulate the economy and generate employment. North Carolina applied for over $5 billion under the high speed rail funding in October In January 2010 the state was awarded $545 million in grants for high speed rail, the sixth highest total of all states. The majority of the grant is for projects on the NCRR. Among the projects that received funding are the three remaining Greensboro to Charlotte double track projects. These projects comprise approximately half of the funding received, which is testament to their importance in the scope of the overall program to develop SEHSR. With significant funding, the state is

13 proceeding to implement these projects through the ARRA program in a new and sustainable manner. Figure 6: Greensboro to Charlotte Double Track Projects COX TO HOSKINS - LESSONS LEARNED CP Cox to CP Hoskins was the first double track restoration project to be constructed in North Carolina in over 30 years, the previous being an approximate 10-mile segment of the NCRR Main Line constructed with the new Southern Railway hump yard at Linwood. The Cox to Hoskins project was developed under the NCRRIP program with limited funding. State funding sources and FHWA congestion mitigation air quality funds were used. This section of previous single track was identified early in capacity modeling as being critical for network fluidity and ensuring on-time meets of passenger trains. The majority of scheduled passenger train meets

14 for Carolinian and Piedmont services have historically, and are proposed, to occur within this segment between Thomasville and Greensboro. The Cox to Hoskins project has been a success for bettering network fluidity and improving ontime meets of passenger trains. However, the project team learned of many ways to enhance this type of project for the future. One key decision early in the project development phase was to construct the project within the existing 200 wide NCRR right-of-way. Environmental documents were prepared accordingly, and public involvement was more limited than current projects. The decision to contain the Retaining walls at Jamestown, NC work within the right-of-way was an effort to reduce cost and the schedule time for planning and right-of-way acquisition. This decision limited the opportunity to make robust changes to the railroad geometry in support of SEHSR. It also increased cost in one area of the project that required a multi-million dollar retaining wall to contain the construction within the right-of-way. The remaining double track projects include the required environmental documents and public involvement to progress acquisition of both railroad and highway right-of-way.

15 Another limiting decision was to not include at-grade crossing evaluation, consolidation and elimination as part of the project planning. It was determined that these efforts should progress separately in the future. Again, limited funding drove the decision, but an opportunity was missed to perform comprehensive planning and a master plan of improvements. One crossing within the project limits, Stallings Rd., was closed prior to the project as a separate effort tied to a larger highway project, but no other crossings were evaluated for elimination. It was determined that the planning for the remaining double track projects would include comprehensive evaluation of at-grade crossings for closure, grade separation, and safety improvements. Interlocking Construction at Cox One other important take-away from Cox to Hoskins related to interlocking construction. For train operations, Cox and Hoskins control points were proposed in good locations for temporarily holding trains away from at-grade crossings and yard operations. However, these locations required construction of the new universal crossover control points atop the existing equilateral turnouts. This complexity added to the project cost and required several long work windows with train annulments. It was determined that for the remaining sections of double

16 track, the new crossover control points would be built in new locations. This is facilitated by a robust crossing closure program. THE NEW PROJECT APPROACH NCDOT is managing the planning, design, and environmental analysis of the remaining double track projects in a more comprehensive manner. Project design and environmental analysis evaluates the benefits and impacts of railroad and highway elements together for the full length of each double track corridor. In real time as project development progresses, the environmental, planning, and design members of the project team work together to adjust designs to meet objectives, reduce impacts, and produce a quality project. As the NCRR corridor is the only viable route for handling traffic in this largely urbanized area of North Carolina, making lasting, sustainable improvements is the primary objective in the development of the remaining double track projects. The project objectives must be met while not precluding future capacity improvements within the corridor. The objectives of the Greensboro to Charlotte double track projects can be summarized as: Increase railroad capacity Improve railroad operations Modernize the railroad Improve safety Capacity and operation efficiency will be enhanced not only through the construction of double track, but through the coordinated locations of universal crossovers, auxiliary tracks, signal layout, and elimination of highway crossings. Railroad modernization will be created through the complete renewal of the traffic control signal system, replacement of obsolete bridges, and realigning curves to achieve consistent near term and future operating speeds and to reduce fuel use and rail, wheel, and brake wear. Most notably, safety and train operations will be

17 significantly improved through these projects with the proposed elimination of 22 public and 11 private at-grade crossings and the construction of up to 10 new grade separated structures. Once completed, the corridor will be mostly grade separated through the limits of the new double track. Changes to design and operating practices are being explored and developed as part of the projects. This includes the use of Number 24 turnouts in place of the current standard Number 20 to create faster (60 mph vs. 45 mph) diverging moves for both intermodal freight and passenger trains. Future higher speed, higher cant deficiency operation for passenger trains is facilitated through improved track geometry, flatter curvature and longer spirals to allow greater passenger comfort in curves. Spirals are designed for a future 5 cant deficiency operation for conventional passenger equipment using AREMA formulas where greater than NS standards. A desirable maximum degree of curvature of one and a half degrees has been employed to provide for a consistent design speed of 90 mph throughout the projects. This has been successful for all but three curves on the Reid to N. Kannapolis segment where heavily urban conditions forced curvature to one degree forty two minutes. Vertical and horizontal clearances at proposed overhead structures are also being evaluated to allow for possible future electrification and future additional tracks. New ways are being explored to construct the remaining double track projects as well. Previously, NS managed all elements of construction and projects were constructed in a primarily sequential manner. With the volume of work proposed, NCDOT field divisions, with their long history of corridor construction experience, are proposed to manage the vast majority of civil work on the new projects including roadbed, drainage, and structures. Track and signal construction will be managed by the experts at Norfolk Southern Railway to ensure a high quality final project.

18 ENVIRONMENTAL AND PUBLIC INVOLVEMENT PROCESS Development of the double track projects requires documentation of the project impacts through the National Environmental Policy Act (NEPA) process. It was determined, through coordination with the FRA, that Environmental Assessment documents would be prepared for each project, encompassing the total scope of work for each project. Railroad and highway improvements were evaluated together for the benefit of both systems. This comprehensive transportation approach has proved more successful and less time consuming, than previous efforts to evaluate railroad improvements separately from highway crossing consolidations and closures which when handled separately can encumber resources and generate more scrutiny without the context and momentum of the overall systems improvement. The environmental and public involvement process is managed by the NCDOT Rail Division Environmental and Planning Branch. Consultant teams are utilized to prepare the documents, including necessary project mapping, and evaluate impacts to the natural and human environment. Natural environment evaluations included defining the boundaries of wetlands, streams, and endangered species habitats and avoiding these areas to the extent possible. Human environment evaluations included identifying historic architecture and archeology, presence of public parks and recreation facilities, emergency services access, and noise analysis. In many places along these projects, it was necessary to thread the needle for both roadway and railroad improvements through many environmental constraints. Well planned public involvement has been critical to the successful development of these projects. As these projects not only include critical improvements to the railroad infrastructure but also include major highway system changes for safety, the clear communication of the benefits of the projects to the public was critical. Public involvement began with informal workshops for each project in August and September At these meetings, team members from NCDOT and NCRR were present to answer questions in a one-on-one format. Much of

19 the public interest related to concerns of impacts on homes and businesses and inconvenience and diversion of traffic related to certain crossing closures. For context, the team defined the projects like an interstate highway rather than a utility improvement. Just like interstate highways, these projects need to be largely grade separated and aligned for consistent speeds to operate efficiently and safely. Public involvement continued with follow-up workshops on the Haydock to Junker and Reid to N. Kannapolis projects in early These were necessary in order to present updated crossing closure and grade separation plans and address public and community leader suggestions. Public comment is expected to formally conclude with public hearings in the fall of In real time, the environmental, planning, and design members of the project team have worked together to adjust designs to meet objectives, reduce impacts, and produce a quality project. The draft documents are in process of being sent to the FRA for review. Once the EA documents are signed by the FRA, it is the hope of the project team that this carefully coordinated and comprehensive process will result in the necessary follow-up documents called Finding of No Significant Impact (FONSI), culminating the end of the planning process. PROJECT DETAILS The three remaining double track projects located on the NCRR Main Line are, from north to south, CP Bowers to CP Lake, CP Reid to CP North Kannapolis and CP Haydock to CP Junker. CP Bowers to CP Lake CP Bowers to CP Lake is the northernmost of the three projects located in Davidson County between Thomasville and Lexington, NC. This project is 4.2 miles long (Milepost to 314.0). Major aspects of this project include: Retire and remove existing CP Bowers interlocking (Milepost 309.8)

20 Construct new CP Lake interlocking with No. 24 crossovers (MP 311.2) Retire and remove existing CP Lake interlocking (MP 314.0) Construct new grade separations at Upper Lake and Turner Roads Rehabilitate concrete arch bridge over Jimmy's Creek Rehabilitate concrete arch bridge over Richford Creek and lower track profile 2' to reduce load on bridge structure Replace existing twin thru girder superstructures on bridge over Abbotts Creek with ballasted deck double track superstructure Realign four curves and introduce longer spirals to permit future 90 MPH passenger train operations Close three public and one private at-grade crossing Twin Thru Girder Bridges over Abbotts Creek While this project is not particularly long and difficult from a road construction view point, the key challenge is to deal with environmental concerns due to the numerous wetlands bordering, and

21 encroaching into, the railroad right-of way. Particular attention is paid to reducing the environmental impacts through track relocations and construction of short gabion basket retaining walls as required. CP Reid to CP North Kannapolis CP Reid to CP North Kannapolis is located in Rowan County between Salisbury and Kannapolis. Project length is 11.3 miles (MP to 348.3). Major aspects of this project include: Retire and remove existing CP Reid interlocking (MP 337.0) Construct new CP Sumner Interlocking with No. 24 crossovers (MP 340.0) Retire and remove existing North Kannapolis interlocking (MP 347.5) Construct new CP North Kannapolis Interlocking with No. 24 crossovers (MP 347.0) Construct new overhead grade separations at Peeler Road in Salisbury and 22nd Street in Kannapolis Construct new undergrade grade separation at Kimball Road Realign six curves with longer spirals for future 90 MPH passenger train operations Close 10 public at-grade crossings and 5 private crossings Construct safety improvements at 4 remaining public at-grade crossings The challenge with this urban project is minimizing impacts to adjacent structures, streets and other infrastructure, particularly in the town of China Grove. Although the NCRR Corridor is generally 200 feet wide, over the years many encroachments have been constructed within railroad right-of-way such as streets, businesses, or residences with or without agreements in place.

22 Right-of-Way Encroachments in China Grove CP Haydock to CP Junker This, the southernmost of the three projects, in located in Cabarrus and Mecklenburg counties between Concord, Harrisburg and Charlotte, a length of 12.2 miles. Significant features of this project include: Retire and remove existing CP Haydock interlocking (MP 360.0) and replace with a new interlocking at CP Shamrock (MP 363.0). The relocation of the interlocking will improve railroad operations. The new interlocking will include No. 24 crossovers to permit improved freight and passenger train speeds. Replace existing CP Junker interlocking with new No. 24 crossovers. New Junker interlocking is designed to accommodate a future third track into Charlotte. Realign five curves and introduce longer spirals to permit future 90 MPH passenger train operations,

23 Construct a new rail bridge over Coddle Creek for the main tracks. The condition of the existing bridge structure and curve realignments at this location required a new structure. CP Junker and Industrial Tracks Construct new ballast deck spans over Rocky River Construct four new overhead grade separations at Pharr Mill Road, Roberta Road (Harrisburg), Caldwell Road and Grier Road which will permit the closing of nine atgrade public highway crossings and five private crossings. Coordinate with the City of Charlotte the possible construction of a new undergrade grade separation with their proposed Mallard Creek Parkway which will permit the closing of Back Creek Church Rd. Construct safety improvements at one remaining at-grade highway crossing

24 The unique aspect of this project is the staging of construction to minimize impacts to railroad operations and to maintain service to local industries. Especially challenging are the curve realignments, bridge construction and track reconfigurations at the north end of the project. ESTIMATED COSTS The estimated costs for the double track projects are: CP Bowers to CP Lake: $47.5 million ($37.4 million for railroad roadbed, railroad structures, track and signals, $10.1 million for grade separations) CP Reid to CP North Kannapolis: $92.6 million ($63.8 million for railroad roadbed, railroad structures, track and signals, $28.8 million for grade separations) CP Haydock to CP Junker: $95.1 million ($79.2 million for railroad roadbed, railroad structures, track and signals, $15.9 million for grade separations) CURRENT STATUS AND SCHEDULE FOR COMPLETION The preliminary design for all three projects is scheduled for completion in mid-summer The Finding of No Significant Impact (FONSI) is anticipated by 1 st Quarter Final design Requests for Proposal will be issued in late 2010 and early 2011 with all final designs completed by mid Construction will begin in late 2012 on the grade separations and in early 2013 on the railroad related work. All construction is scheduled for completion in SUCCESS IN THE FREIGHT- PASSENGER RELATIONSHIP Unless a new passenger operator has the funding and political muscle to build (or buy) its own right-of-way, its success will depend upon the relationship that it can develop with an existing freight railroad. After all, the railroad has what the passenger operator needs a well-

25 positioned right-of-way. The success of this relationship very much a public-private partnership - is determined by how prepared each side is to provide what the other side needs. It is most helpful to this partnership for the passenger operator to adopt the position, at the outset, that the proposed passenger operations will not adversely impact current freight operations or constrain future freight capacity. (While a passenger operation can never truly be transparent due to the inflexibility of passenger train schedules the passenger operator can do much to minimize its impact.) And the passenger operator must be prepared to spend money lots of it. A rail line that is already of high quality (and thus fairly high speed) is probably flush with freight trains, and capacity improvements will be essential. Passing sidings, additional main track and high-speed crossovers are some of the anticipated improvements. Railroads that adopt a supportive attitude towards passenger rail do so because they realize that passenger rail is a growth industry, one that increasingly is earning political and popular support. A railroad that says no stands in the way of transportation progress and may suffer long-term consequences in other venues, particularly those that require government and public support. By saying yes, a railroad, in addition to gaining popular support, may obtain some infrastructure improvements that help its freight operations. In the case of Greensboro to Charlotte, the most obvious benefit to NS is the continuous double track corridor (and an improvement that is clearly needed to support multiple daylight passenger trains). But NS will also enjoy the benefits of high-speed crossovers, curve improvements that will expedite intermodal trains, and perhaps most importantly, a dramatic reduction in the number of highway grade crossings, which will have a significant positive impact on the freight railroad s safety, service reliability and maintenance. These are improvements that NS would not have funded on its own.

26 CONCLUSION ARRA funding requires that these projects be in service by September of This funding has brought the opportunity to construct the projects in a viable and sustainable manner. It also brings new challenges in the form of project reporting and approval processes to the previously established NCRRIP processes. However, the project team comprised of NCDOT, NCRR, and NS is confident that with the previous experience and trust developed through working closely together, these projects will progress to success and provide lasting improvements for future passenger and freight traffic. LIST OF FIGURES Figure Title 1 North Carolina Railroad Corridor 2 Norfolk Southern Crescent Corridor 3 Passenger Rail Service in North Carolina 4 Track Improvements on the North Carolina Railroad 5 Southeast High Speed Rail Corridor 6 Greensboro to Charlotte Double Track Projects

Project Overview. A Collaborative Effort

Project Overview. A Collaborative Effort Project Overview A Collaborative Effort DRPT and FRA are working closely with CSX, which owns and operates the corridor, as well as with passenger operators Amtrak and Virginia Railway Express (VRE), the

More information

Major Capital Improvements

Major Capital Improvements Major Capital ments Completed Description Wayne, Lenoir, Craven, and Carteret Counties: Upgrade track condition between Goldsboro and Morehead City Upgraded the track condition between Goldsboro and Morehead

More information

North Carolina Railroad Company Engineering Department. Design and Construction Guidelines

North Carolina Railroad Company Engineering Department. Design and Construction Guidelines North Carolina Railroad Company Engineering Department Design and Construction Guidelines January 2019 Version 2.0 PREFACE These Design and Construcion Guidelines are provided as information only to assist

More information

Joint Legislative Transportation Oversight Committee January 8, NCDOT Rail Division. Paul Worley, NCDOT Rail Division Director

Joint Legislative Transportation Oversight Committee January 8, NCDOT Rail Division. Paul Worley, NCDOT Rail Division Director Joint Legislative Oversight Committee January 8, 2015 NCDOT Rail Division Paul Worley, NCDOT Rail Division Director Rail Division Rail Division Director Administrative Business Office Planning & Development

More information

North Carolina Railroad Company

North Carolina Railroad Company North Carolina Railroad Company Shared Corridor Commuter Rail Capacity Study Greensboro to Goldsboro, NC American Railway Engineering and Maintenance of Way Association 2008 Annual Conference September

More information

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project 1.0 INTRODUCTION 1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project Connecticut is centrally located in a part of

More information

Section IMPLEMENTATION PLAN. 7. Implementation Plan

Section IMPLEMENTATION PLAN. 7. Implementation Plan Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 Final EIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need

More information

Major Capital Investments

Major Capital Investments Completed Description Wayne, Lenoir, Craven, and Carteret Counties: Upgrade track condition between Goldsboro and Morehead City Upgraded the track condition between Goldsboro and Morehead City, included

More information

Major Capital Investments

Major Capital Investments Completed Description Wayne, Lenoir, Craven, and Carteret Counties: Upgrade track condition between Goldsboro and Morehead City Upgraded the track condition between Goldsboro and Morehead City, included

More information

I-95 Corridor Coalition

I-95 Corridor Coalition I-9 Corridor Coalition Southeast Rail Operations Study, Phase II Tasks 1 and 2: Strategic Corridor Identification and Mapping FINAL REPORT June 2011 Southeast Rail Operations Study, Phase II Tasks 1 and

More information

Tier 2 Environmental Impact Statement for the High-Speed Rail Project from Granite

Tier 2 Environmental Impact Statement for the High-Speed Rail Project from Granite This document is scheduled to be published in the Federal Register on 02/18/2014 and available online at http://federalregister.gov/a/2014-03324, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

Upgrading Rail Lines for Higher Speeds

Upgrading Rail Lines for Higher Speeds Upgrading Rail Lines for Higher Speeds Railroad Infrastructure Diagnosis and Prognosis David E. Staplin, PE University of Nevada Las Vegas, October 16, 2018 Upgrading Rail Lines for Higher Speeds A Perspective

More information

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan.

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan. Rail Rail plays a significant role in transportation planning, especially when considering economic development, safety, freight, and intermodal connectivity. Jackson has two rail lines serving the area,

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016 House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions March 28, 2016 US Highway 70 Main highway route from I-40 & I-95 to the Global TransPark and the Port of Morehead

More information

LONG BRIDGE CAPACITY NEEDS. Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA

LONG BRIDGE CAPACITY NEEDS. Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA LONG BRIDGE CAPACITY NEEDS Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA 1 TODAY S PRESENTATION VRE Overview Project Location and Partners Challenges and Opportunities Funding

More information

JOINT APPROPRIATIONS COMMITTEE ON TRANSPORTATION NORTH CAROLINA RAILROAD COMPANY MARCH 22, 2017

JOINT APPROPRIATIONS COMMITTEE ON TRANSPORTATION NORTH CAROLINA RAILROAD COMPANY MARCH 22, 2017 JOINT APPROPRIATIONS COMMITTEE ON TRANSPORTATION NORTH CAROLINA RAILROAD COMPANY MARCH 22, 2017 WHO WE ARE Our Mission Putting the North Carolina Railroad Company to work for the good of the people of

More information

HAMPTON ROADS HIGH-SPEED AND INTERCITY PASSENGER RAIL PRELIMINARY VISION PLAN

HAMPTON ROADS HIGH-SPEED AND INTERCITY PASSENGER RAIL PRELIMINARY VISION PLAN PREPARED FOR HAMPTON ROADS TRANSPORTATION PLANNING ORGANIZATION July 2010 HAMPTON ROADS HIGH-SPEED AND INTERCITY PASSENGER RAIL PRELIMINARY VISION PLAN PROGRESS REPORT C: PRELIMINARY INFRASTRUCTURE ANALYSIS

More information

The Crescent Corridor Improving Lives and Livelihoods

The Crescent Corridor Improving Lives and Livelihoods The Crescent Corridor Improving Lives and Livelihoods Philadelphia, Pennsylvania October 2009 1 Vision and Leadership Rail freight is an important component of any transportation infrastructure discussion.

More information

American Association of Port Authorities Spring Meeting March 24, 2009

American Association of Port Authorities Spring Meeting March 24, 2009 American Association of Port Authorities Spring Meeting March 24, 2009 Prepared Remarks Allen Biehler, Secretary of Transportation, State of Pennsylvania President, American Association of State Highway

More information

Project Purpose and Need Statements

Project Purpose and Need Statements Norfolk Southern Railway Company Pittsburgh Vertical Clearance Projects Purpose and Need Summary: Project Purpose and Need Statements August 2018 The principal purpose of the Pittsburgh Vertical Clearance

More information

HAMPTON ROADS PASSENGER RAIL STUDY DATA COLLECTION PHASE 2A NORFOLK-RICHMOND CORRIDOR

HAMPTON ROADS PASSENGER RAIL STUDY DATA COLLECTION PHASE 2A NORFOLK-RICHMOND CORRIDOR Presentation To: Agenda Item #11 Hampton Roads Transportation Planning Organization Board HAMPTON ROADS PASSENGER RAIL STUDY DATA COLLECTION PHASE 2A NORFOLK-RICHMOND CORRIDOR Presentation By: March 21,

More information

Section IMPLEMENTATION PLAN. 7. Implementation Plan

Section IMPLEMENTATION PLAN. 7. Implementation Plan Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 DEIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need of the

More information

University of Illinois at Urbana-Champaign April 2, 2010

University of Illinois at Urbana-Champaign April 2, 2010 1 1 CSXT Network Planning: The View in 2010 University of Illinois at Urbana-Champaign April 2, 2010 1 CSX connects the nation and the globe CSX facts: 30,000000 employees 21,000 route miles Chicago Buffalo

More information

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD September 18, 2013 District Department of Transportation Federal Railroad Administration AGENDA Vision History & Background Study Area Purpose & Need

More information

Environmental Impact Statement for the Southeast High Speed Rail Project from

Environmental Impact Statement for the Southeast High Speed Rail Project from This document is scheduled to be published in the Federal Register on 10/23/2014 and available online at http://federalregister.gov/a/2014-25219, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Railroad

More information

Long Bridge - Present & Future: A Multimodal Analysis

Long Bridge - Present & Future: A Multimodal Analysis Long Bridge - Present & Future: A Multimodal Analysis Edward La Guardia P.E. American Public Transportation Association (APTA); American Railway Engineering and Maintenance-of- Way Association (AREMA);

More information

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis,

More information

Modeling Applications for Freight Tennessee DOT Freight Planning

Modeling Applications for Freight Tennessee DOT Freight Planning Modeling Applications for Freight Tennessee DOT Freight Planning presented to Tennessee Model Users Group presented by Dike Ahanotu Cambridge Systematics, Inc. July 17, 2008 Transportation leadership you

More information

Rail Division. Riding the Rails

Rail Division. Riding the Rails Rail Division Riding the Rails Amtrak Ridership within Texas Remains Strong The annual ridership within Texas on all three services (Heartland Flyer, Texas Eagle and Sunset Limited) continues to soar.

More information

Appendix C Presentation Slides with Script

Appendix C Presentation Slides with Script Appendix C Presentation Slides with Script 32 Grand Crossing Rail Project 10 S. Riverside Plaza, Suite 400 Chicago, IL 60606 www.grandcrossingrail.com info@grandcrossingrail.com [title slide no narration]

More information

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative Appendix C: Port Jervis Line Capacity Improvements Analysis Technical Memorandum 2: Passing Siding Alternative January 2018 TABLE OF CONTENTS 1. Introduction... 1 2. Passing Sidings: Locations and Components...

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

ARROWS RANSPORTATION LAN

ARROWS RANSPORTATION LAN ARROWS RANSPORTATION LAN Developed by the Transportation Planning Division Of the Virginia Department of Transportation In Cooperation With The U.S. Department Of Transportation, Federal Highway Administration

More information

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need Environmental Impact Statement (EIS) Revised Purpose and Need November 9, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure

More information

2-2 ALTERNATIVES CONSIDERED AND ELIMINATED

2-2 ALTERNATIVES CONSIDERED AND ELIMINATED Section 2: Alternatives Development and Evaluation 2-1 INTRODUCTION This section of the Scoping Information Packet describes the alternatives to be evaluated in the Environmental Impact Statement (EIS)

More information

Becoming part historian to identify unknown and abandoned utility infrastructure from the bygone eras of railroading within the same footprint.

Becoming part historian to identify unknown and abandoned utility infrastructure from the bygone eras of railroading within the same footprint. RANDOLPH STREET IMPROVEMENT PROJECT AT ROANOKE, VIRGINIA Brian L. Putman, P.E. Principal Design Engineer Design & Construction Norfolk Southern Railway Company 1200 Peachtree Street, NE Atlanta, GA 30309-3579

More information

Corridors of Statewide Significance: Introduction

Corridors of Statewide Significance: Introduction Virginia s Long-Range Multimodal Transportation Plan Corridors of Statewide Significance: Introduction Prepared for: Commonwealth Transportation Board Prepared by: Office of Intermodal Planning and Investment

More information

Transportation Committee DRPT Presentation

Transportation Committee DRPT Presentation Transportation Committee DRPT Presentation Thelma Drake, Director January 14, 2013 www.drpt.virginia.gov Rail and Public Transportation Systems in Virginia 62 Transit Systems 55 Human Service Operators

More information

2.0 ALTERNATIVES. 2.1 Introduction. 2.2 No Build Alternative

2.0 ALTERNATIVES. 2.1 Introduction. 2.2 No Build Alternative 2.0 ALTERNATIVES 2.1 Introduction The alternatives selected for evaluation in this Environmental Assessment (EA) include the No Build Alternative and a Build Alternative that provides for increased HSR

More information

MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia May 8,

MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia May 8, MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia 24148 May 8, 2018 MEETING OVERVIEW AND OBJECTIVES Introduce study

More information

Environmental Impact Statement for the Baltimore-Washington Superconducting Maglev (SCMAGLEV) Project, between Baltimore, Maryland and Washington, DC

Environmental Impact Statement for the Baltimore-Washington Superconducting Maglev (SCMAGLEV) Project, between Baltimore, Maryland and Washington, DC This document is scheduled to be published in the Federal Register on 11/25/2016 and available online at https://federalregister.gov/d/2016-28285, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

Design Constraints Railroad

Design Constraints Railroad Design Constraints Railroad 46 Design Constraints Railroad 47 Design Constraints 75 Interchange 48 Design Constraints MSD Lick Run Project 49 Alternatives - Rehabilitation 50 51 Alternatives - Rehabilitation

More information

LONG BRIDGE - PRESENT & FUTURE: A MULTIMODAL ANALYSIS

LONG BRIDGE - PRESENT & FUTURE: A MULTIMODAL ANALYSIS LONG BRIDGE - PRESENT & FUTURE: A MULTIMODAL ANALYSIS Review of the Potomac River Crossing a Rail Resource for the Washington, DC Region and Beyond Presenter: Edward La Guardia P.E. Michael Baker International

More information

Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study

Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study Rail Modeling Update May 4, 2017 www.dot.state.mn.us/passengerrail/tc-mil-chi/

More information

Peninsula Widening. Project Description. Overview of Project Status. Estimated Total Project Cost $4.7 - $7.3 Billion

Peninsula Widening. Project Description. Overview of Project Status. Estimated Total Project Cost $4.7 - $7.3 Billion Peninsula Widening SYSTEM: Interstate FROM: I-664 (Hampton Roads) TO: I-95 (Richmond) DESCRIPTION OF WORK: Provide for increased capacity, improve safety standards and minimize roadway geometric and structural

More information

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN COORDINATING COMMITTEE MEETING #3 NOVEMBER 17, 2015 1 Progress to Date Base data collection Freight network inventory Truck parking inventory and utilization

More information

Texas Transportation Forum The Fast Track: Passenger Rail In Texas. Federal Railroad Administration Karen Rae, Deputy Administrator

Texas Transportation Forum The Fast Track: Passenger Rail In Texas. Federal Railroad Administration Karen Rae, Deputy Administrator US Department of Transportation Federal Railroad Administration Texas Transportation Forum The Fast Track: Passenger Rail In Texas Federal Railroad Administration Karen Rae, Deputy Administrator January

More information

Sorrento to Miramar 4(f) De Minimis Determination

Sorrento to Miramar 4(f) De Minimis Determination Sorrento to Miramar 4(f) De Minimis Determination LOSSAN Overview Bruce Smith PE SM2 Project Manager with SANDAG What is LOSSAN? A 351-mile coastal rail corridor Los Angeles San Diego San Luis Obispo Built

More information

A Concept for Measuring the Effects of Severe Weather and Weather Trends on Freight Movement In and Between Major Urban Areas

A Concept for Measuring the Effects of Severe Weather and Weather Trends on Freight Movement In and Between Major Urban Areas A Concept for Measuring the Effects of Severe Weather and Weather Trends on Freight Movement In and Between Major Urban Areas Jeffrey Short, Senior Research Associate, ATRI American Transportation Research

More information

Michigan DOT: Design Challenges of Dearborn to Ypsilanti Double Track Project

Michigan DOT: Design Challenges of Dearborn to Ypsilanti Double Track Project Michigan DOT: Design Challenges of Dearborn to Ypsilanti Double Track Project Daniel Schulte, P.E. Quandel Consultants, LLC 161 N. Clark St., Suite 2060 Chicago, IL 60601 312-634-6219 dschulte@quandelconsultants.com

More information

MPO/RPO Briefings. MPO/RPO Briefing. Briefing Topics Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans

MPO/RPO Briefings. MPO/RPO Briefing. Briefing Topics Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans 7/7/2011 MPO/RPO Briefings July 2011 MPO/RPO Briefing Briefing Topics 1. 2040 Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans 2. Study process o Schedule o Public

More information

Tier 1 Environmental Impact Statement for the Chicago, Illinois, to Detroit-Pontiac,

Tier 1 Environmental Impact Statement for the Chicago, Illinois, to Detroit-Pontiac, This document is scheduled to be published in the Federal Register on 08/31/2012 and available online at http://federalregister.gov/a/2012-21587, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

COAST LINE CONNECTOR. Facilities Redevelopment Port Commerce Department

COAST LINE CONNECTOR. Facilities Redevelopment Port Commerce Department Title of Project: Name of Applicant: Contact & Job Title: STATEN ISLAND RAILROAD: CHEMICAL COAST LINE CONNECTOR Port Authority of New York and New Jersey Rudy Israel, General Manager Waterways & Facilities

More information

I-95 Corridor Coalition

I-95 Corridor Coalition I-95 Corridor Coalition Southeast Rail Operations Study, Phase II Tasks 1 and 2: Strategic Corridor Identification and Mapping FINAL REPORT June 2011 Southeast Rail Operations Study, Phase II Tasks 1 and

More information

All Aboard Florida. DRAFT Environmental Impact Statement. Martin Metropolitan Planning Organization (MPO) Staff Review. Photo courtesy Carla McMahon

All Aboard Florida. DRAFT Environmental Impact Statement. Martin Metropolitan Planning Organization (MPO) Staff Review. Photo courtesy Carla McMahon All Aboard Florida DRAFT Environmental Impact Statement Martin Metropolitan Planning Organization (MPO) Staff Review Photo courtesy Carla McMahon Environmental Process An environmental assessment (EA)

More information

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN W. W. HAY SEMINAR SERIES NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN Tower 55 Multimodal Improvements 2015 HDR, Inc., all rights reserved. W. W. HAY SEMINAR SERIES TOWER

More information

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis Port Jervis Line Service Strategy Report Appendix C: Port Jervis Line Capacity Improvements Analysis January 2018 TABLE OF CONTENTS Introduction... 1 1. Future PJL Service... 1 2. Project Alternatives...

More information

FOR IMMEDIATE RELEASE June 7, ATK Contact: Media Relations

FOR IMMEDIATE RELEASE June 7, ATK Contact: Media Relations FOR IMMEDIATE RELEASE June 7, 2010 ATK-10-080 Contact: Media Relations 202 906.3860 NATIONAL RAIL PLAN NEEDS TO RECOGNIZE THE VALUE OF AMTRAK S INTERCITY PASSENGER RAIL NETWORK Serves as foundation to

More information

ACKNOWLEDGEMENT/DISCLAIMER

ACKNOWLEDGEMENT/DISCLAIMER ACKNOWLEDGEMENT/DISCLAIMER Prepared in cooperation with the U.S. Department of Transportation (USDOT), the Federal Highway Administration (FHWA), the Virginia Department of Rail and Public Transportation

More information

NS and Public Private Partnerships: The Heartland Corridor & The Crescent Corridor. Robert E. Martinez Norfolk Southern Corporation October 2007

NS and Public Private Partnerships: The Heartland Corridor & The Crescent Corridor. Robert E. Martinez Norfolk Southern Corporation October 2007 NS and Public Private Partnerships: The Heartland Corridor & The Crescent Corridor Robert E. Martinez Norfolk Southern Corporation October 2007 Heartland Corridor Route Next Day Service to Columbus Norfolk

More information

Transportation Update

Transportation Update Transportation Update Projects Underway Norview Avenue About the Project: The Norview Avenue Interchange Improvement Project will eliminate the existing weave movement associated with the on- and off-ramps

More information

INCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP

INCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP INCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP Presented By Ken Galt, Caltrans Division of Rail John Fleming, Burlington Northern Santa Fe Railway William Brewster, Hanson-Wilson

More information

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN ADVISORY COMMITTEE MEETING

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN ADVISORY COMMITTEE MEETING GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN ADVISORY COMMITTEE MEETING April 12, 2016 Welcome Safe, reliable, & efficient movement of goods is essential for continued economic success Every day, products

More information

Statewide Multimodal Networks

Statewide Multimodal Networks Statewide Multimodal Networks Introduction In Virginia, long-range transportation planning is carried out by the state, metropolitan planning organizations (MPOs), planning district commissions (PDCs),

More information

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017 Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives December 14, 2017 Today s Agenda Project Overview Project Schedule Purpose and Need Concept Screening Process Level

More information

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure

More information

Preapplication for HSIPR Program OMB No

Preapplication for HSIPR Program OMB No U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in

More information

Carolina Connector Intermodal Terminal (CCX)

Carolina Connector Intermodal Terminal (CCX) Joint Legislative Oversight Committee January 6, 2017 Carolina Connector Intermodal Terminal (CCX) Paul C. Worley, CPM, Rail Division Director CCX is a three legged stool: State, Community and Railroad

More information

Preapplication for HSIPR Program OMB No

Preapplication for HSIPR Program OMB No U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in

More information

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

2.0 Purpose. 3.0 Work Plan. Page 1 of 7 2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide

More information

The Challenges of Improving High Speed Rail in Pennsylvania:

The Challenges of Improving High Speed Rail in Pennsylvania: The Challenges of Improving High Speed Rail in Pennsylvania: The Keystone Corridor June 4, 2013 2013 Rail Conference Marilyn Jamison Senior Director Major Projects & Environmental Support Amtrak NEC Infrastructure

More information

Rail Division 2012 Annual Summary

Rail Division 2012 Annual Summary Rail Division 2012 Annual Summary Overview The Rail Division oversees rail planning and inspection, highway rail crossings, management of stateowned lines (such as the South Orient Rail line (SORR) and

More information

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation 2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan Minnesota Department of Transportation ! First Statewide Comprehensive Rail Plan for MN! Commissioned by 2008 Legislature! Compliant

More information

ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK

ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK During FY 2011, in the interest of improving the region s potential for passenger rail service, the HRTPO retained the services

More information

Appendix D Presentation Slides with Script

Appendix D Presentation Slides with Script Appendix D Presentation Slides with Script 18 Grand Crossing Rail Project 10 S. Riverside Plaza, Suite 400 Chicago, IL 60606 www.grandcrossingrail.com info@grandcrossingrail.com [title slide no narration]

More information

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN

GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN GREATER CHARLOTTE REGIONAL FREIGHT MOBILITY PLAN PLANES, TRAINS, & SEMIS: KEEPING A DYNAMIC ECONOMY ON THE MOVE NOVEMBER 13, 2015 1 1. Understanding the Current Freight Climate 2. Looking Toward the Future

More information

I-81 Update July 2007

I-81 Update July 2007 I-81 Update July 2007 Status of I-81 The Federal Highway Administration issued a preliminary record of decision on the I-81 Tier I Environmental Impact Statement in June, now under a 120-day comment period.

More information

Strategic Long-Term High-Speed and Intercity Passenger Rail Plan: Phase 2 Study Approach

Strategic Long-Term High-Speed and Intercity Passenger Rail Plan: Phase 2 Study Approach Presentation To HRTPO Transportation Advisory Committee Meeting Agenda Item #7 Strategic Long-Term High-Speed and Intercity Passenger Rail Plan: Phase 2 Study Approach Presentation By September 1, 2010

More information

NEW JERSEY DEPARTMENT OF TRANSPORTATION. New Jersey Statewide Strategic Freight Rail Plan

NEW JERSEY DEPARTMENT OF TRANSPORTATION. New Jersey Statewide Strategic Freight Rail Plan NEW JERSEY DEPARTMENT OF TRANSPORTATION New Jersey Statewide Strategic Freight Rail Plan OVER-ARCHING PROJECT PURPOSE In short, the plan is intended to: Identify Issues That Constrain Freight Rail Operations

More information

2010 Indiana Logistics Summit

2010 Indiana Logistics Summit 2010 Indiana Logistics Summit Michael B. Cline Commissioner, INDOT October 26, 2010 INDOT 3,912 INDOT employees 1,702 Highway Technicians 594 Managers/Supervisors 325 Engineers 805 District CO 3,106 State

More information

How HRTPO Helps Freight Move. Presented by Robert B. Case, PE, PhD Transportation Technical Advisory Committee Agenda Item #13 April 1, 2015

How HRTPO Helps Freight Move. Presented by Robert B. Case, PE, PhD Transportation Technical Advisory Committee Agenda Item #13 April 1, 2015 How HRTPO Helps Freight Move Presented by Robert B. Case, PE, PhD Transportation Technical Advisory Committee Agenda Item #13 April 1, 2015 Overview This summary was originally prepared for FHWA s Talking

More information

Connectivity North and Beyond Nevada s I 80 Corridor

Connectivity North and Beyond Nevada s I 80 Corridor I 11 NORTHERN NEVADA ALTERNATIVES ANALYSIS Connectivity North and Beyond Nevada s I 80 Corridor May 2018 Prepared for Nevada Department of Transportation Contents 1. Introduction... 1 1.1. I 11 Corridor

More information

Norfolk Southern Comments on the GoTriangle Durham Orange LRT DEIS

Norfolk Southern Comments on the GoTriangle Durham Orange LRT DEIS Norfolk Southern Comments on the GoTriangle Durham Orange LRT DEIS Cochran, J. Lee [Lee.Cochran@nscorp.com] Sent: To: Cc: 10/7/2015 4:02 PM "'info@ourtransitfuture.com'" "David

More information

WELCOME TO THE LONG BRIDGE PROJECT

WELCOME TO THE LONG BRIDGE PROJECT WELCOME TO THE LONG BRIDGE PROJECT Public Meeting Thursday, December 14, 2017 Open House Format: 4:00 p.m. to 7:00 p.m. Formal Presentations: 4:30 p.m. and 6:00 p.m. (same presentation at both times) Project

More information

NEPA and Design Public Hearings

NEPA and Design Public Hearings NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg

More information

REPORT. Freight Physical Infrastructure Profile May 11, Submitted to: Rappahannock-Rapidan Regional Commission (RRRC)

REPORT. Freight Physical Infrastructure Profile May 11, Submitted to: Rappahannock-Rapidan Regional Commission (RRRC) Submitted to: Rappahannock-Rapidan Regional Commission (RRRC) REPORT Freight Physical Infrastructure Profile May 11, 2009 Initial Draft- April 29, 2009 Revised May 11, 2009 Submitted by: Whitehouse Group

More information

VRE AT WORK PREPARING VIRGINIA RAILROADING FOR ITS NEXT QUARTER CENTURY

VRE AT WORK PREPARING VIRGINIA RAILROADING FOR ITS NEXT QUARTER CENTURY VRE AT WORK PREPARING VIRGINIA RAILROADING FOR ITS NEXT QUARTER CENTURY T. R. ( Tom ) Hickey Chief Development Officer April 4, 2017 1 1 TONIGHT S PRESENTATION Introduction Safety Briefing VRE Overview

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information

Design Challenges and Construction Benefits of Precast Segmental Rail Bridges

Design Challenges and Construction Benefits of Precast Segmental Rail Bridges Design Challenges and Construction Benefits of Precast Segmental Rail Bridges by Amy R. Kohls, P.E., S.E. Director Texas Office Figg Bridge Engineers, Inc. 10000 North Central Expressway Suite 1300 Dallas,

More information

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally

More information

Moving Washington Forward: State and Ports working together for freight mobility in reauthorization

Moving Washington Forward: State and Ports working together for freight mobility in reauthorization Moving Washington Forward: State and Ports working together for freight mobility in reauthorization Andrew Wood Deputy Director - State Rail and Marine Association of Port Authorities Tacoma, Washington

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

Great Lakes Basin Transportation, Inc. Railroad Proposal

Great Lakes Basin Transportation, Inc. Railroad Proposal Great Lakes Basin Transportation, Inc. Railroad Proposal A Kankakee County Perspective June 15, 2016 Kankakee County Planning Department 189 E. Court St, Room 201 Kankakee, IL 60901 815-937-2940 Delbert

More information

King of Prussia Rail Project Frequently Asked Questions - Archive Version: Summer 2018

King of Prussia Rail Project Frequently Asked Questions - Archive Version: Summer 2018 - Archive Version: Summer 2018 These frequently asked questions (FAQ) have been developed to help residents, businesses and area stakeholders develop a better understanding of the proposed King of Prussia

More information

Northeast Rail Operations Study (NEROps)

Northeast Rail Operations Study (NEROps) I-95 Corridor Coalition Northeast Rail Operations Study (NEROps) Phase I Final Report Executive Summary June 2007 Northeast Rail Operations Study (NEROps) Phase I Final Report Executive Summary Prepared

More information

U.S. 70 Corridor Economic Assessment

U.S. 70 Corridor Economic Assessment U.S. 70 Corridor Economic Assessment prepared for U.S. 70 Corridor Commission and NCDOT prepared by Cambridge Systematics, Inc. with Sanford Holshouser Economic Development Consulting March 07, 2014 www.camsys.com

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018 Item 9, Report No. 14, of the Committee of the Whole, which was adopted, as amended, by the Council of the City of Vaughan on April

More information

February 24, Basis of Design. Technical Criteria for Concept & Preliminary Engineering. Final Report

February 24, Basis of Design. Technical Criteria for Concept & Preliminary Engineering. Final Report February 24, 2015 Basis of Design Technical Criteria for Concept & Preliminary Engineering Final Report APPROVALS This document was developed by the Virginia Department of Rail and Public Transportation

More information