1 CMAA - BREAKFAST OF CHAMPIONS May 2, 2012 SIXTH STREET VIADUCT REPLACEMENT Gary Lee Moore, P.E. City Engineer Deborah Weintraub, AIA, LEED AP Chief Deputy City Engineer Alfred L. Mata, P.E. Project Manager City of Los Angeles Department of Public Works Engineering
2 VISION STATEMENT TO LEAD THE TRANSFORMATION OF LOS ANGELES INTO THE WORLD S MOST LIVABLE CITY.
3 BUREAU OF ENGINEERING PROJECTS CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF ENGINEERING
4 BUREAU OF ENGINEERING PROJECTS PROJECTS COMPLETED SINCE JULY 1, 2005 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS ACTIVE PROJECTS BUREAU OF ENGINEERING
5 Sixth Street Viaduct Replacement Project In Conjunction with FHWA & Caltrans Fourth Street Sixth Street
6 Existing Conditions Alkali Silica Reactivity (ASR) deterioration exists throughout Past repairs have been ineffective and ASR will continue Seismic reliability is poor, with high collapse probability Viaduct geometrics are functionally deficient Light Damage Moderate Damage Moderate to Severe Damage Severe Damage
7 Selected Project Replacement Alignment 3B Bridge Concept - Type 4 $401M ANDERSON ST. Alignment 3B Benefits Creates Roadway Shoulders Provides Wider Sidewalks Removes Kink in Bridge Provides Safety Median Buffer Multimodal: Peds & Bikes River Access & Enhancements N MISSION CLARENCE ST. RD. UPRR SCRRA (METROLINK) L.A. R I V E R SANTA FE Existing Viaduct NO SCALE JESSE ST. SCRRA (METROLINK) BNSF RAILWAY INC. LACMTA (METRO_) MESQUIT ST. AVE. 6TH ST. IMPERIAL ST. 6TH ST. MATEO ST.
8 Railroad Corridors Project Constraints Los Angeles River High Voltage Transmission Lines
9 Preferred Project Elements Alignment 3B Bridge Concept 4 Iconic Bridge: Viaduct: Roadway: Utility Relocations: Railroad Corridors: LA River: Street Improvements: Demolition: Four Span Extradosed Concrete Box Girder Cast in Place Box Girders, including Hwy 101 Crossing Four Lanes with Median, Shoulders and Sidewalks Avoid Transmission Lines, Relocate Others Safety Shields, River Access Tunnel In-Water Work, Pedestrian Access, Revitalization Plans Temporary and Permanent, 20 Intersections Safety is Paramount: Railroads, Businesses, Public
10 Architectural Enhancement and Design As part of the RFQ/P released on 4/25/12, the City will conduct a design competition to refine the bridge concept to ensure an architecturally distinctive and cost-effective design expression.
11 Renderings Looking south Looking west to downtown
12 Architectural Expressions Rio-Antirio Bridge (Greece)
13 Architectural Expressions Gerald Desmond Bridge Port of Long Beach, California Proposed Final Design Existing
14 Architectural Expressions Willamette River Bridge Collection Portland, Oregon Under Construction Existing
15 Architectural Expressions Modern Bridges Millau Viaduct (France) Dusseldorf, Germany
16 Architectural Expressions Slanted Tower Illuminated Towers Sun Dial Bridge Redding, California Missouri River Bridge Omaha, Nebraska
17 Project Budget Project Phase Preliminary Engineering and Environmental Clearance $ Amount (in millions) 17 Program Management and Final Design Right-of-Way Construction and Construction Management 259 Total (incl. Bond Financing Cost) 401
18 Construction Budget by Element Design Consultant Scope $ Amount (in millions) New Viaduct 140 Demolition 12 Roadway and Intersection Improvements 10 Other Street Improvements 13 Tunnel and Railroad Improvements 10 River, Landscaping, Bicycle, Pedestrian 5 Subtotal 190
19 Project Schedule Milestone Date City Approval of Project and Financial Plan Nov 18, 2011 Record of Decision Issued Dec 21, 2011 Issue Design Consultant RFP Apr 25, 2012 Begin Right-of-Way Acquisition Process May 2012 Begin Final Design Dec 2012 Complete Final Design Aug 2014 Advertise for Construction Bids Sep 2014 Begin Advance Construction Early 2015 Begin Bridge Construction Mid 2015 Complete Construction 2018
20 Project Delivery Program Management: City and Consultant Design: International Design Competition, For RFQ/P, register at Design Aesthetic Advisory Committee Construction Management: City and Consultant Utility Relocations: Utility Agencies and Contractor Potential Construction Packages: Utility Relocations, Intersections, Demolition Construction: Conventional Design-Bid-Build or Construction Manager / General Contractor
21 For Contracting Opportunities - City of LA Business Assistance Virtual Network Contracting Opportunities are Posted on Construction Bid Documents RFQ s RFP s To download documents, your company must be registered (free) on BAVN. Use BAVN for outreach to subcontractors/subconsultants
22 Sixth Street Viaduct Replacement Project For more information: Project Manager: Alfred L. Mata, P.E.
SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013
SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager
More informationextent feasible. Per the and low constructability,
RELEVANT PUBLIC PROJECTS AND REFERENCES TranTech is proud of its accomplishments in structural engineering. Our staff members have provided design servicess to numerous public agencies on very successful
More informationMichael Gillam Deputy Program Director - Southern California
International Right of Way Association Los Angeles Chapter: C A L I F O R N I A H I G H - S P E E D R A I L Michael Gillam Deputy Program Director - Southern California January 25, 2011 A Statewide System
More informationMetro Board Action: Motion 22.1
Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016 Background Motion 22.1 October
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationA~~~ Gary Lee Moore, P.E. City Engineer
BOARD OF PUBLIC WORKS MEMBERS ANDREA A. ALARC6N PRESIDENT JERILYN L6PEZ MENDOZA VICE PRESIDENT JOHN J. CHOI PRESIDENT PRO TEMPORE STEVEN T. NUTTER COMMISSIONER VALER IE LYNNE SHAW COMMISS IONER ARLEEN
More information3.6 GROUND TRANSPORTATION
3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to
More informationADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012
ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationUS-101 CORRIDOR ADVISOR S UPDATE
US-101 CORRIDOR ADVISOR S UPDATE MONTECITO ASSOCIATION BOARD OF DIRECTORS 12 MAY 2015 1 SCOPE OF SERVICES Identify & evaluate innovative project delivery strategies: Avoid & minimize delays / expedite
More informationCHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION
CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...
More informationNotice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report
Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,
More informationRegional Transportation Studies Regional Council
Pima Association of Governments 1 E. Broadway, Tucson, Arizona Santa Rita Conference Room Regional Transportation Studies Regional Council September 28, 2017 I-11 Tier 1 Environmental Impact Statement
More informationPROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT
PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform
More informationA long-term, comprehensive solution
A long-term, comprehensive solution Nancy Boyd CRC Project Director for Washington Portland State University Transportation Seminar April 15 2011 Frank Green April 15, 2011 CRC Structural Engineering Manager
More informationNATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD
NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD September 18, 2013 District Department of Transportation Federal Railroad Administration AGENDA Vision History & Background Study Area Purpose & Need
More informationREHABILITATION PACKAGE 4-a
4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.
More informationLONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17
LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La
More informationMetro Blue Line Improvements & Project Update
Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing
More informationTHE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY
THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel
More informationFACT SHEETS SAN BERNARDINO COUNTY
FACT SHEETS SAN BERNARDINO COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares
More informationThe Gateway Expressway FTBA Conference. February 2-3, 2017
The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north
More informationSunrise Project South I-205 Corridor Improvement Project
Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More informationSCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS
SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS Each Technical Proposal (Volume A of Package 2 of the Proposal) should address each of the items and requests for information described in this
More informationFunding Intelligent Transportation Systems in the Los Angeles Region
Funding Intelligent Transportation Systems in the Los Angeles Region 2017 ITS California Annual Meeting Ed Alegre, PTP Los Angeles County Metropolitan Transportation Authority (Metro) Los Angeles Region
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationCarpinteria Avenue Bridge Replacement Project Description Introduction
Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with
More informationBarrington Road. at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study. Community Advisory Group Meeting #1
Barrington Road at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study Community Advisory Group Meeting #1 Hoffman Estates Village Hall July 25, 2012 Meeting Agenda 1. Welcome and
More informationAREAWIDE BRIDGE REPLACEMENT AND REHABILITATION
CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally
More informationTECHNICAL MEMORANDUM
California High-Speed Train Project TECHNICAL MEMORANDUM 15% Design Scope Guidelines TM 0.1 Signed document on file Prepared by: 12 May 08_ Ken Jong, PE Checked by: Signed document on file 12 May 08_ John
More informationDENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING
DENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING 2001 2002 4 2005 6 2007 2008 RTD ACQUIRES DUS MASTER PLANNING DEVELOPER SELECTION DESIGN REFINEMENT PRELIMINARY ENG. August 2001 RTD acquires
More informationSCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS
SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS MARCH 2017 SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS 1.0 General A. All work activities within the SCRRA operating corridor and right-of-way, or work activities that
More informationGEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects
GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationMega Projects at WSDOT
Mega Projects at WSDOT Managing multiple projects in major urban corridors LINEA LAIRD, WSDOT ASSISTANT SECRETARY ENGINEERING & OPERATIONS Presentation to Oregon State Legislature Congestion Work Group
More informationGeometric Design: Past, Present, and Future
A2A02: Committee on Geometric Design Chairman: Daniel B. Fambro Geometric Design: Past, Present, and Future DANIEL B. FAMBRO, Texas A&M University JOHN C. COLLINGS, Delcan Corporation ROBERT DELLA VEDOVA,
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction
More informationSOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY
SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY Ryers Station Improvement Project Robert L. Lund, Jr., PE Assistant General Manager Engineering, Maintenance and Construction Division David J. Sands,
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More information$500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources
$500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources Regional Transportation District (RTD) City and County of Denver (CCD) Denver Regional Council
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationALTERNATIVE PROJECT DELIVERY DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION ALTERNATIVE PROJECT DELIVERY DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design-Build Requirements for Advertisement SPECIFIC SUBJECT: APPROVED:
More informationBonnie Doon Grade Separation
6. 2 Bonnie Doon Grade Separation Recommendation: That the April 18, 2017, Integrated Infrastructure Services report CR_4461, be received for information. Report Summary This report provides information
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationHighway Construction Program
Highway Construction Program Monthly Delivery Progress Report Watch List February 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,
More informationConstruction of the Superstructure of Major Sea Crossings
Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge 2 Second Penang Bridge Donghai Bridge
More informationProject Initiation Form
Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination
More informationFolsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL
Design and Construction Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL View of the Folsom Dam and the canyon just upstream of construction. The area
More informationI-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation
I-11 Project 2017 Nevada Transportation Conference Ryan Wheeler, P.E. NDOT, Senior Project Manager Nevada Department of Transportation nevadadot.com About NDOT NDOT Core Values: Respect treating others
More informationClick to edit Master title style I N D U S T R Y D AY O C T O B E R 1,
Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, 2 0 1 4 Welcome Nevada Governor Brian Sandoval Nevada DOT Director Rudy Malfabon, PE Goals Goals Obtain the best value for the costs
More informationNortheast States Materials Engineers Meeting (NESMEA) October 9, 2006 Newark, DE
Northeast States Materials Engineers Meeting (NESMEA) October 9, 2006 Newark, DE Delaware DOT s Use of Slag Cement Jim Pappas, P.E. Chief Materials & Research Engineer Materials & Research Section Outline
More informationEngineers Perspective on the State of Transportation Infrastructure in NC
Engineers Perspective on the State of Transportation Infrastructure in NC Pamela B. Townsend, PE MS Civil Engineering, BSCE, NC State University Vice President, Earth Tech, Inc. David Peterson, PE Past
More informationLUNDY S LANE COMMUNITY IMPROVEMENT PLAN STUDY
PUBLIC INFORMATION MEETING # October, 0 LUNDY S LANE COMMUNITY IMPROVEMENT PLAN STUDY AGENDA :00 to :0pm: Open House :0 to :pm: Presentation : to :00pm: Individual paced workshop with the Study Team PUBLIC
More informationLos Angeles Westside Purple Line Extension Project Challenges and Lessons Learned
Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,
More informationDESIGN AND CONSTRUCTION SCHEDULE
DESIGN AND CONSTRUCTION SCHEDULE DESIGN BID & CONTRACTING CONSTRUCTION 2017 2018 2019 2020 2021 2022 2023 Pier 62 Rebuild & Habitat Improvements Status: Construction Main Corridor Alaskan Way, Elliott
More informationMiami-Dade Transit. Alice N. Bravo, P.E. Director. Miami-Dade Transit 1
Miami-Dade Transit Alice N. Bravo, P.E. Director Miami-Dade Transit 1 Miami-Dade Transit MDT is the largest transit agency in the State of Florida, and one of the largest departments within Miami-Dade
More informationSCRRA GRADE SEPARATION GUIDELINES
SCRRA GRADE SEPARATION GUIDELINES APRIL 2016 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Purpose... 1 1.2 Limitations and Disclaimers... 1 1.3 Changes, Updates, and Effective Date... 1 1.4 References...
More informationGrade-Separated Trail Crossings How Do We Get Over There?
Grade-Separated Trail Crossings How Do We Get Over There? 2008 National Trails Symposium Rory Renfro, Alta Planning + Design Scott Belonger, Loris and Associates Peter Loris, Loris and Associates PRESENTATION
More informationSELLWOOD BRIDGE REPLACEMENT PROJECT
SELLWOOD BRIDGE REPLACEMENT PROJECT Eric Rau, PE David Goodyear, PE, SE, PEng, NAE BIOGRAPHY Eric Rau is a Senior Bridge Engineer for T.Y. Lin International with over fifteen years of experience. He has
More informationCONTRACTOR S PROPOSAL FISCAL YEAR STREET IMPROVEMENT PROJECT AND MAIN STREET BRIDGE REHABILITATION
CONTRACTOR S PROPOSAL COMPANY ADDRESS CITY, STATE, ZIP ( ) TELEPHONE NUMBER City of Hesperia 9700 Seventh Avenue Hesperia, CA 92345 Ladies and Gentlemen: STATE LICENSE NUMBER Pursuant to the Public Notice
More informationCIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM
CIVIL ENGINEERING BENEFITS OF BIM Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM WHAT S INSIDE: 1 BENEFITS Keep constructability top-of-mind Improve project margins Make better
More informationDBE AND SBE OPEN HOUSE. North Metro Rail Line BUILT FOR REGIONAL TRANSPORTATION DISTRICT (RTD) December 18, 2014
DBE AND SBE OPEN HOUSE December 18, 2014 North Metro Rail Line BUILT FOR REGIONAL TRANSPORTATION DISTRICT (RTD) KEY TEAM MEMBERS Dave Trent, Project Director Mike Salmon, Deputy Project Director Mike Chilcott,
More informationLA 1 Bridge Project Status Update Feb. 12, 2007 WSA/DOTD A Partnership
New Bridge Old Bridge LA 1 Bridge Project Status Update Feb. 12, 2007 Satellite Image of Southern Louisiana Project Location Project Overview 2 1C 1B 1A Major Project work modules 1. Mapping, Location,
More informationConclusions & Lessons Learned
What is a DDI Recommended Practices Traffic Operations Analysis Geometric Design FHWA Review Conclusions & Lessons Learned It s not about you, it s about the public Developed by Access Utah County
More informationNorthwest State Route 138 Corridor Improvement Project
Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816
More informationDistrict Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016
District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About
More informationProject Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce
Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,
More informationAccelerated and Innovative Bridge Construction In Washington State
Accelerated and Innovative Bridge Construction In Washington State Bijan Khaleghi Bijan.Khaleghi@WSDOT.WA.Gov Washington State Department of Transportation Bridge and Structures Office Olympia Washington
More informationTransbay Transit Center Program
Transbay Transit Center Program Quality Management System Manual Revision 1 September 2013 Quality Management System Manual Revision 1 September 2013 Prepared for the Transbay Joint Powers Authority
More informationTRANSPORTATION PLAN Donald Vary
LOUISIANA STATEWIDE TRANSPORTATION PLAN Donald Vary March 2, 2016 AGENDA Plan Development Decision-Making Process Outreach Activities Vision and Goals Transportation Needs Financial Analysis (revenue scenarios
More informationRosslyn Circle Improvements, WB Lee Hwy. - US 29. April 6, :30 a.m North Fort Myer Drive, LL-10, Arlington, VA
REQUIRED PROJECT SHOWING MINUTES Project No. 0029-000-859, C501, B605 UPC No. 109813 PROJECT SHOWING MINUTES, WB Lee Hwy. - US 29 Project No. 0029-000-859, C501, B605 UPC No. 109813 April 6, 2017 10:30
More informationProgress Report Sounder Program
Progress Report Sounder Program Continued construction work for the Tacoma Trestle at East 26th and East G Streets. March 2017 Prepared by Project Control l Design, Engineering & Construction Management
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationLarge Diameter Highway Tunnels
Large Diameter Highway Tunnels Richard Prust Towards a solution Need Feasibility Whole-life cost Corridors for through trips SR-99 carries a significant proportion of total through trips SR-99 corridor
More information2016 TEAM Conference. Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS. March 10, HDR, all rights reserved.
2016 TEAM Conference Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS March 10, 2016 2015 HDR, all rights reserved. Project Location Project Location BNSF Transcon Tracks Gardner,
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationConstruction Administration Updates
Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Construction Administration Updates Clint Bishop Construction Administration Updates Construction Administration Updates
More informationRequest for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2
Addendum Number 1 Request for Proposals No. 17-001 Various On-call Professional Design and Engineering Services To all prospective firms under specifications for Request for Proposals (RFP) No. 17-001,
More informationComparison of Bridge Rehabilitation versus Bridge Replacement Concepts
Comparison of Bridge Rehabilitation versus Bridge Replacement Concepts Technical Memorandum Introduction The comparison of rehabilitation versus replacement of the Sellwood Bridge is being conducted in
More informationURBAN RENEWAL DISTRICT II TAX INCREMENT FINANCING CRITERIA FOR REVIEW
URBAN RENEWAL DISTRICT II TAX INCREMENT FINANCING CRITERIA FOR REVIEW BACKGROUND INFORMATION In 1991, the Missoula City Council adopted an Urban Renewal Plan creating Urban Renewal District II. The intent
More informationUS-101 CORRIDOR ADVISOR S UPDATE 19 MARCH 2015
US-101 CORRIDOR ADVISOR S UPDATE 19 MARCH 2015 1 DELIVERY RECOMMENDATION GOALS Project Readiness: Enhance Funding pursuits Corridor Related Projects Coordination Develop Information to: Resolve Questions
More informationNCDOT s Performance Based Contracting Experience in Charlotte. Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009
NCDOT s Performance Based Contracting Experience in Charlotte Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009 Overview Performance Base Contracting in NC Project Scope Contract Development
More informationRoute 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing
Project Reston Avenue to Jarrett Valley Drive Public Hearing Nicholas J. Roper, P.E. District Project Development Engineer Email: nicholas.roper@vdot.virginia.gov Phone: (703)259-1953 Agenda 7:00-7:15
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,
More informationLos Angeles Area Chamber of Commerce, 08/05/14
Los Angeles Area Chamber of Commerce, 08/05/14 Overview California s global trade position Trade Corridors Improvement Fund (TCIF) Federal and State Encouragement & Requirements California Freight Advisory
More informationState Route 8 Bridge Replacement Project
OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel
More informationApplication of Accelerated Bridge Construction for Local Agencies
Application of Accelerated Bridge Construction for Local Agencies APWA Public Works Conference November 9, 2017 Dorie Mellon Senior Bridge Engineer, Caltrans Matt Randall Senior Engineer, County of Placer
More informationFinal Recommendations Identification of Improvements, Strategies, and Solutions
Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...
More informationTRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM
VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:
More informationNorthern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?
WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities
More informationScope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration
Scope of Work Route 116/Hinesburg Growth Center Corridor Study Town of Hinesburg and CCRPC Project Approach and Understanding Route 116 through Hinesburg had seen substantial changes in the past 15 years,
More informationElizabeth River Tunnels Project. ASHE October Technical Meeting ERT Project Overview October 8, 2015
Elizabeth River Tunnels Project ASHE October Technical Meeting ERT Project Overview October 8, 2015 Project Location: Hampton Roads, VA ERT Project Scope New, two-lane, WB tunnel Rehab and lifesafety improvements
More informationApplications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction
Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction 2018 Virginia Concrete Conference March 2, 2018 Bardia Emami, PE Outline Projects
More informationFor Public Input Period
20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,
More information- FACT SHEET - THE GUIDING PRINCIPLES
THE GUIDING PRINCIPLES The General Plan begins with seven ideas that together create a vision for the City s future. When the City approved the General Plan in 1994, these idea were dubbed the Seven Guiding
More informationLOCATION AND DESIGN DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More information