Route 18 Widening and Reconstruction Project Abington Weymouth Project File No

Size: px
Start display at page:

Download "Route 18 Widening and Reconstruction Project Abington Weymouth Project File No"

Transcription

1 Route 18 Widening and Reconstruction Project Abington Weymouth Project File No Responses to Inquiries from 25% Design Public Hearing April 24, I currently own the property 88 Barbara Lane which happens to be the last house on the left. I was unable to make the meeting a week or so ago. So I am concerned and would like to know what impact this will have on my property etc the drainage lines in front of my house, will any of my property by affected in this replacement and will any of my property be affected where the temporary bridge is placed? My name is Steven Solletti and I am anxious to hear back from you. Thank u for your time No permanent loss of acreage on this property is required by the project. However, a temporary construction easement is needed and it will extend approximately 16 feet into the property, measuredfrom the back property line that is adjacent to the bridge site. This temporary easement will be in effect for the duration of the construction project, a period estimated to be 2 1/2 3 years. Within the temporary easement all existing trees will need to be removed. The existing fence will be removed. The existing shed will remain. A temporary overhead utility line will extend over the temporary easement area, with one temporary utility pole placed within the easement. A temporary 6 high chain link fence will be installed within the temporary easement, near the easement line, to secure the work site. The temporary bridge will not be located within the temporary easement, but it is likely that construction equipment will move in and out of the area while the temporary bridge is constructed and while the temporary bridge is removed. Following completion of construction, the temporary overhead utility line, the temporary utility pole, and the temporary fence will be removed. The area that was cleared of vegetation will be replanted with trees and shrubs. The existing drainage structures and pipes in Barbara Lane will remain. A downstream drain pipe that connects the most southerly catch basin at the end of Barbara Lane to the drainage system in Route 18 will be replaced with a larger pipe. 2. I attended the public hearing on April 24th and had a couple additional questions. My father s property is at 1445/1449 Main St. There were some items on the right of way drawings that I would like clarified. A. There is an existing sign that is called to be R&R by others. Will this need to be done by the owner? Will the owner be compensated? The sign will need to be removed by the owner prior to MassDOT s project. The owner will be compensated to do this, with the amount of compensation to be discussed between MassDOT and the owner during the ROW process, prior to construction. B. There is an existing leaching basin in the north east corner of the lot that will be in the future widened section of the roadway. This basin is the low point for the parking lot. The note on the drawing said R&D. If this structure is removed there will be no drainage for the parking lot. Will a new structure be installed? Will the owner be responsible for new structure? If so will the owner be reimbursed? 1

2 MassDOT will not install a new structure. The owner will be responsible for installation of a new structure if the owner chooses to do so. MassDOT s ROW section will be in contact with the property owner. C.. The existing driveway width needs to be wider. When the roadway was widened as part of the MBTA commuter rail parking lot project the driveway width was narrowed. In looking at the plans there are plans for a traffic signal in the future at this location. Can the driveway width be widened to accommodate traffic entering and exiting at the same time? There is a day care business on the property that has a lot of in and out traffic. Thank you for your time Kevin Cleary (C) (H) The existing width is approximately 27 wide. The MassDOT standard commercial driveway width is set at 30 wide and the driveway will be reconstructed to that width. 3. Mr. Timothy M. Mitchelson on behalf of South Shore Bank: What is the timeline for this project? The project is scheduled to be advertised for construction in September Is there any proposed taking of the property from 1530 Main Street? Yes. Please see detail below. What, if any, portion of the Bank s property at 1530 Main Street will be subject to incursion inward on both 18 and/or 58 as a result of this expansion? Impacts to the South Shore Bank parcel are as follows: State - Permanent taking along Route 18 due to widening: 3,337 sf Town - Permanent taking along Route 58 due to widening: 485 sf State - Permanent easement for a utility pole and overhead utility wires: 85 sf State Permanent drainage easement for drain pipe: 99 sf State Permanent easement for detention basin (including access): 11,372 sf (pending determination) The Massachusetts Department of Environmental Protection requires comprehensive investigation of all potential stormwater management sites in proximity to the project. We have conducted soil investigation at South Shore Bank to determine if a portion of the parcel, within the lawn and landscape area near the Route 58 intersection, is suitable for this purpose. The results are pending. If the site is determined to be suitable, the permanent easement listed above will be required. MassDOT will work with a representative of the bank to design screening and landscaping to mitigate this impact as much as possible. 4. Susan M Kay, Mayor, on behalf of two residents, pertaining to the intersection of Main Street (Route 18)/Shea Drive: 2

3 Pedestrian Accommodations At this signalized intersection, there are two crosswalks but the traffic lights are not equipped with pedestrian signals or push buttons. The town requests that the improved Route 18/Shea Drive signal include an exclusive pedestrian phase. The proposed intersection improvements include new pedestrian signals and push buttons servicing three crosswalks. Analysis was conducted using HCM 2000 software to evaluate the effect on Level of Service (LOS) at the intersection with the addition of an exclusive pedestrian phase for all legs of the intersection under 2030 Build Conditions. Overall intersection LOS deteriorates from B to C during the worse peak hour (PM peak hour) travel period with the inclusion of an exclusive pedestrian phase. Driveway Signalization A 4-unit residential complex at Main Street is located right across from Shea Drive. This development is served by a 10-car lot. In the past, residents have had difficulty in exiting the parking lot, and this task will become more difficult after the intersection is reconstructed. The town requests that the driveway be signalized. The driveway signal phase will be called infrequently and should not degrade the operation of the intersection in the future. MassDOT concurs with the suggestion to signalize the westerly approach. Vehicular detection will be required to activate the signal on the westerly approach, but the particular method of detection (loops, video, microwave) remains under evaluation. 5. Briefly explain how your process works on the state level for notification of this meeting. MassDOT is required by law to post two notices, fourteen and seven days prior to the hearing in local newspapers. A notice was printed in the Patriot Ledger and in the Weymouth News on April 10 th and April 17 th and in the Abington Mariner on April 12 th and April 19 th of When the temporary bridge goes up, what measures will be taken to alleviate some of the traffic that may want to cut through Pond Street [to avoid Route 18]? The temporary bridge alignment will introduce temporary curvature to Route 18 and this will likely slow traffic, but should not introduce delay to the extent that Pond Street becomes a more attractive route. However, some travelers will prefer to avoid traveling through a construction zone and will seek alternatives in any case. Truck prohibition signing on the approaches to Pond Street will be reviewed and supplemented in coordination with the Weymouth traffic engineer. 7. In the vicinity of the bowling alley and by the car wash there is currently inadequate drainage. The design may not be enough to alleviate the amount of water coming from both directions. The project provides surface roadway drainage in conformance with state and federal standards for stormwater interception of rainfall intensity that has a 10% probability of occurring in any given year. The project will review this proposed design with Chip Fontaine, the town of Weymouth engineer, and adjust the design if needed to address local concerns. 8. Concern exists about the water that comes off of Route 18 and heads down Derby

4 Street. There is no granite curb there. There is not even Cape Cod berm. A new catch basin is located in the proposed Route 18 gutter line on the upstream side of the Derby Street intersection to intercept stormwater on Route 18 before it flows down Derby Street. The intersection includes new granite curb. The project does not include street improvements on Derby Street. 9.What would the speed limit be on the finished roadway? After the project is completed MassDOT will conduct a speed study that will involve data collection, safety evaluation and assessment of traffic operation to establish the posted speed limits along the various sections of the project. 10.There is nothing in the drawings about the temporary bridge. The bridge drawings are preliminary and temporary bridge details will be developed in the final design. The temporary bridge will be a prefabricated steel structure. 11.I did not understand which scenario you were moving towards, if you have chosen one. The grade-separated railroad crossing was determined to provide better public safety than the at-grade crossing, based on the evaluation that MassDOT conducted. The west temporary bridge alignment was determined to have less permanent environmental and right of way impact than the east temporary bridge alignment. Based on these evaluations Route 18 traffic will be maintained on a temporary bridge located on the west side of Route What measures will be taken to prevent children from getting in the work area? A 6 high temporary chain link fence will be erected along the temporary construction easement line. A temporary locked gate will be installed at the end of Thomas Street for emergency access. 13.Where are the wetland mitigation sites and how big are they? Both sites are on the former South Weymouth Naval Air Station. The site in Weymouth is south and adjacent to Calnan Road. The site in Abington is to the west of the existing runway in a wooded area adjacent, but uphill, to a stream. The Weymouth site is approximately 24,700 square feet in area and the Abington site is approximately 22,000 square feet in area. 14.Will this project have a website? MassDOT has set up a webpage specific to the project within the MassDOT- Highway website. 15.Do you anticipate additional work being done at the Pleasant Street intersection that was recently completed? Yes, although no curb or pavement work is proposed at this intersection. Tunnel visors will be installed on the overhead northbound signals and some signals will be slightly adjusted in location and orientation for better visibility. On the northbound approach to the intersection, some curb work and pavement markings are proposed to avoid blocking the driveway to the mall. 16.Did the project engineers receive the latest Town of Weymouth zoning guidelines? Tetra Tech received the guidelines from Jim Clark by November 9, 2012.

5 17.The Town of Weymouth requests that the project contact the Town of Weymouth Health Department to determine if the base noise level is in line with the Town and how much over or under it is. MassDOT will coordinate with the Town of Weymouth. 18.Town of Weymouth requests that the project manages dust during construction. MassDOT requires dust suppression in its construction contracts. The contractor is responsible for having dust suppression equipment on site at all times and to apply water spray to control the level of dust. MassDOT s resident engineer and his staff will be available on site to direct the contractor to apply water at specific locations as needed or in response to local requests. 19.Town of Weymouth requests that MassDOT establish a complaint log for the project. A resident construction engineer will be available to field complaints during construction. 20.Why did MassDOT dig up Route 18, then stop work, then begin this process again? MassDOT previously reconstructed five intersections on Route 18 that are within the limits of the currently proposed widening project. These intersections were in immediate need of reconstruction because they were high accident locations. The proposed project will match into these previously completed intersections. The number of lanes will remain consistent at two lanes in each direction, with turn lanes added at some intersections. 21.Where are you getting these traffic volume figures? My experience does not fit your statistics. The traffic volumes used for the design of the Route 18 improvements are based on traffic counts performed along Route 18 in 2006 and These volumes were then projected to a future design year, which for Route 18 is The 2030 volume forecasts for the Route 18 corridor were developed by the Central Transportation Planning Staff (CTPS), which is part of the Boston Metropolitan Planning Organization (MPO), and provides traffic forecasts for MassDOT for many projects such as Route 18. The 2030 forecasts for Route 18 include traffic from the redevelopment of the South Weymouth Naval Air Station as well as other expected growth within the region. 22.How are the ambulances going to get through? A minimum of one travel lane per direction will be provided during all phases of construction for traffic traveling along Route 18, including emergency vehicles such as ambulances. 23.There should be a tremendous amount of traffic lights. An intersection must meet a rigorous set of engineering criteria (warrants) in order to justify the installation of a traffic control signal. All intersections on Route 18 that meet these criteria are signalized. 24.You should take that bicycle accommodation off the project. MassDOT is required to provide bicycle accommodation in accordance with state law and to the standards that are applicable to the classification of the street/highway. Bicycle accommodation cannot be removed from the project.

6 25.If the bridge is so dangerous how can you wait two years to take it down? The bridge is primarily being removed so that a new bridge, capable of carrying two lanes in each direction, can be built. No components of the existing bridge can be reused. 26.What is the reason for doing this road? Sections of Route 18 experience severe congestion during peak travel periods under current conditions. Traffic volumes are projected to increase over time due to expected growth along Route 18 and nearby areas from which traffic feeds into Route 18, including the former South Weymouth Naval Air Station development. The future volumes (2030) indicate that a 4-lane roadway will be required in order to provide acceptable peak hour levels of operation with the expected traffic demands. 27.Can we do a sound check? You are doing a sound check now with a two-lane road and with the trees still in place. What about when the trees are down, four lanes are open for travel, plus the trains? See answer to Question 29 below. 28.What about the noise when a train is going by? When the train goes by, that bridge just really shakes. The noise analysis did not evaluate train noise because there was assumed to be no changes in their operations. 29.You need to reassess noise after the trees are removed. FHWA does not consider vegetation to be a noise reduction measure. Vegetative strips have no significant effect on sound levels. The impacted area will be densely replanted with trees and shrubs after the temporary bridge is removed. 30.How are the construction vehicles going to get in there? Construction vehicles are prohibited already from using Pond Street, so access by way of Clarendon Street, Barbara Lane and Thomas Street is also prohibited. Access to the construction site will be made from Route 18. Access using the existing MBTA maintenance road that is located adjacent to the tracks is also being investigated. 31.On Barbara Lane and other roads coming down in that area, the drainage is terrible. The Route 18 construction project is a federally funded transportation project and it can only address drainage infrastructure that it directly impacts. The deteriorated drainage system in the Clarendon Street neighborhood and on adjacent streets is not impacted by the project and must therefore be repaired or replaced under a separately funded project through local government. The water level at the existing wetland is being monitored twice a month and will continue to be monitored through construction so that water levels can be maintained at their current levels through construction by pumping, with Massachusetts Department of Environmental Protection authorization. 32.Consider an at-grade Route 18 temporary road for maintenance of traffic originating at Trotter Road and continuing adjacent to and north of the MBTA tracks heading west and then turn north and reconnect to Route 18. This temporary Route 18 roadway would need to be located outside of the MBTA

7 right of way, to the north of their right of way fence. This temporary roadway will impact Natural Heritage Endangered Species Habitat (NHESP), as well as wetlands adjacent to Route 18. Other alternative temporary roadways for Route 18 traffic have been studied and evaluated for impacts. An alternative roadway location that avoids NHESP habitat has been identified - the westerly alignment with the temporary bridge. As a result, the reviewing regulatory agency will not permit any other roadway locations that impact NHESP habitat to be constructed, even for temporary use. 33.What are the endangered species? MA NHESP has confirmed that the PH/EH (Priority and/or Estimated Habitat) mapped on the project includes habitat of the Eastern Box Turtle and the Mocha Emerald dragonfly, both species of special concern. In addition, MA NHESP also indicated that the grassland areas to the east of the Abington wetland mitigation site are within habitat for the Upland Sandpiper, a state listed endangered species, and the Grasshopper Sparrow, a state listed threatened species. 34.I own the preschool at 1449 Main Street. I need to know when [MassDOT] will enter my property for safety reasons and emergency reasons. During the design phase, MassDOT will contact you when they will need access to your property to conduct soil borings or survey and coordinate around your critical drop off and pickup hours. During construction, the resident engineer will be available for daily coordination. 35.Why are the round white circles with X s in them marked on my property? These are the locations for future traffic signal mast arms that will be installed when the East-West Parkway intersection is constructed. Soil borings will be drilled at these locations in the near future, if not already completed. 36.How much square footage are you going to take on my frontage at 1449 Main Street? How many parking spaces will be lost? The area of permanent taking by the Commonwealth is 2,536 square feet. In addition, permanent easements are required for traffic signal equipment (216 square feet) and for overhead utility wires (987 square feet). Based on aerial photography of the existing parking lot, the number of spaces permanently lost due to the project is Will there be a barrier on Route 18 dividing the northbound and southbound traffic along my property frontage at 1449 Main Street? There will be no raised island along the #1449 Main Street property frontage because the property frontage will be within the limits of the future intersection. Because this property is within the limits of the future intersection, it is likely that the driveway will be signalized in the future. Under interim conditions, after Route 18 is widened but before the East - West Parkway is built, Route 18 will have a center lane that services left turning vehicles in both the southbound and northbound directions, with no raised island, between Trotter Road and the bridge over the MBTA.. 38.Will the Trotter Road intersection be moved to Southfield? Under the interim condition described in answer to the comment above the Trotter Road intersection will remain operative in much the same way that it operates now

8 under existing conditions. Under final conditions after the East-West Parkway is built the Trotter Road intersection will become a right-turn-in, right-turn-out only driveway without signals and with a raised island on Route 18 through the former intersection. 39. I have a gigantic sign that says Early Childhood Preschool on it. I need to know if that is going to have to be replaced and moved. You will need to move your sign. MassDOT Right of Way Bureau will contact you regarding that relocation. 40.When are the new Route 3 ramp connections to be constructed? As noted by Diane Madden of MassDOT at the April 24, 2013 Public Hearing, a new interchange on Route 3 (between Exits 14 and 15) with a direct roadway connection to the South Weymouth Naval Air Station (SWNAS) was a component of an earlier redevelopment proposal. Because of the significant environmental impacts associated with the new interchange/connector road, the current redevelopment proposal does not include these elements. Instead, the current plan specifies that the eastern terminus of the cross-base Parkway will be at Weymouth Street. Improvements are proposed along Hingham Street and Reservoir Park Drive that will provide an enhanced connection between the Parkway and Route 3. The western terminus of the Parkway will be at Route 18, north of Trotter Road. 41.Have you worked with Southfield as far as that new bridge so that we are not spending taxpayer s money, after you widen the road, to build this new bridge over the base? MassDOT has coordinated with MBTA and Southfield for the design of the East- West Parkway, the East-West Parkway bridge over the railroad, and the future intersection at Route 18. The MBTA commuter rail station and parking lot are planned to be relocated to the northerly side of the tracks as part of that project. 42.Concerned about water shedding off the road, flooding upstream as well as downstream, existing developer detention basins operating poorly, and poor condition of drain pipes. To the extent that will be allowed by the scope of this transportation project existing drainage infrastructure directly and indirectly affected by the project will be cleaned, repaired or replaced. Existing cross culverts under Route 18 will be cleaned. New public detention basins will be constructed in several locations. The existing culverts crossing under the railroad track to the west of the Route 18 bridge over the railroad will be cleaned as will the existing drainage ditch that continues from the end of that culvert to Route 18. These are located downstream of the Clarendon Street neighborhood. Repair or replacement of the Clarendon Street neighborhood drainage system itself and its outlet cannot be funded or conducted under this project. Existing detention basins on private property are the responsibility of the owners and will not be cleaned under this project. 43.Is there anything the Clarendon Street neighborhood can do to have a noise wall constructed? Because funding for the project is 80% federal, federal (FHWA) design criteria and noise thresholds must be met to justify the expense to construct the wall and those thresholds are not met at this location. FHWA does not have a waiver policy or process through which local petitions for noise walls can be recognized. The

9 impacted area will be replanted with trees and shrubs after the work site is vacated by the contractor. 44.What are the impacts to gas pumps, diesel, at 1465 Main Street? The proposed roadway widening affects access to the pumps closest to the road and those will need to be removed by the owner prior to construction. Prior to construction MassDOT Right of Way Bureau will meet with the owner to discuss these impacts and to coordinate relocation of these pumps elsewhere on the property. 45.What will be done to alleviate construction noise? Hours of contractor operation of heavy equipment, such as pile drivers, will be subject to MassDOT approval during construction. The resident engineer will have an office on the project and residents and businesses should alert the engineer if construction noise becomes a problem. Construction equipment is required to have noise suppression, but certain work activities will be noisy. 46.How will construction traffic access the bridge site? Construction vehicles are prohibited already from using Pond Street, so access by way of Clarendon Street, Barbara Lane and Thomas Street is also prohibited. Access to the construction site will be made from Route 18. Access using the existing MBTA maintenance road that is located adjacent to the tracks is also being investigated. 47. Are the people who will be impacted with temporary easements adjacent to the bridge site going to be compensated? The MassDOT Right of Way Bureau will contact abutters prior to construction. 48.Was there any thought to using the existing paved road within Southfield for use as the Route 18 detour at the bridge site to avoid all the impacts? There is a paved road named Calnan Road in Southfield that is located to the west of the runways. Between connection points that would need to be made back to Route 18 to the north and south, the route length measures approximately 1 ¼ miles, or approximately ½ mile longer than the Route 18 temporary bridge detour route between the same two connection points. The width of Calnan Road measures only feet on average, resulting in travel lane widths of only 9 9 ½ feet. These widths are inadequate for two-way highway travel and widening would be needed. Widening Calnan Road would require an environmental evaluation of impacts. Traffic would be required to pass through 90 degree turns at both ends of the road to connect to Trotter Road and Route 18. Existing traffic signals at the Route 18 connection points would require the detoured Route 18 traffic that uses Calnan Road to turn left, significantly increasing the amount of time required for traffic to pass through both the signals, resulting in long queues. Illegal access to private lands adjacent to Calnan Road would be impossible to control. For this length of road, police patrols would likely be needed. Fairly long temporary dead end sections of Route 18 approaching the bridge work site would be created, leading to fire safety and emergency response problems, as well as potential negative affects to the businesses along those sections of Route 18. For these reasons, the proposed temporary bridge route adjacent to Route 18 is preferred. 49. Could the East-West Parkway be opened early to alleviate traffic on Route 18

10 during construction? The East-West Parkway construction cannot be completed early because funding is not available to complete it in this time frame. 50.Is the East-West Parkway shown on the plans? Yes, the outline of the future East-West Parkway approach to Route 18 is shown on the plans. 51.Is Trotter Road going to carry through traffic? In the future, when the East-West Parkway is completed, the Trotter Road intersection will be right-turn-in, right-turn-out only, without a traffic signal. 52. Do you know what is across the street from the East-West Parkway? The property on the westerly side of the East-West Parkway intersection is #1449 Main Street. It is likely that the driveway to that property will be signalized because it will be within the intersection. 53.Have you decided where you are going to stage for construction? The contractor will establish his material and equipment areas. MassDOT requirements are only that the contractor must adhere to local, state and environmental regulations. 54. What are the work hours on the project? The MassDOT contract will establish work hours for the contractor that are typically 7:00 am to 3:30 pm, but these may be adjusted in consideration of traffic congestion or in response to specific contractor requests. Night work is typically not allowed except for specific requests, such as temporary water service shut off to make water main and service connections. On this project some work must be conducted over live railroad tracks. For those specific tasks only, weekend or night work will be conducted. 55. Will MBTA need to bus people if the commuter rail is shut down for this project? MassDOT is coordinating the project with the MBTA. If a commuter rail shutdown is scheduled during periods of normal commuter rail service, then temporary bus service will be operated during those periods. The MBTA does not currently provide weekend service or continuous overnight service. The MassDOT construction contract will contain provisions for the contractor to conduct work at the railroad during periods that do not impact commuter rail service, such as overnight and on weekends. 56. Is it a federal requirement to put the center island between the northbound and southbound lanes? No. The center median island is proposed to enhance safety, separating opposing traffic, providing improved visibility to better define turn lanes, and providing a target and a refuge to place signing for turning traffic to go around. 57.Are these islands standard curbed islands or do these have 3 high barrier? The islands are all curbed with granite. There are no high barriers. 58. When it snows, the turn lanes do not get plowed at the intersections. MassDOT District 6 is responsible for maintenance and operations. They will review

11 the plans so that they are aware of the changes and account for this in plowing. 59.When will construction start? Construction is projected to start in 2015 and continue for approximately 2 ½ to 3 years. 60. Provisions to limit contractor noise and dust need to be in the contract. MassDOT includes provisions for controlling dust in all their contracts, specifically with the application of water. In addition, the Massachusetts Department of Environmental Protection (MADEP) includes requirements for the limitation of dust as conditions in their permits, and the contractor must be in compliance with those requirements. MassDOT imposes work hour limitations on the contractor to minimize disturbance caused by construction noise. At times, however, work will be allowed at night. In addition, MassDOT construction contracts include an antiidling provision to reduce noise. 61. In the area of the temporary bridge, has an investigation been conducted to determine if hazardous materials are present? The Massachusetts Department of Environmental Protection hazardous materials database has been reviewed for spill incidents throughout the project. There is no record of hazardous material releases in the area of the bridge. To verify that hazardous materials have not been released in the area, sampling needs to be conducted. Two monitoring wells have been previously installed along the temporary bridge alignment. The project will collect ground water samples from each of these two wells and submit them to a laboratory for analyses. The results of the lab testing will be posted for public viewing on MassDOT s website. 62. What are the blue flags, and other colored flags at the back of our houses? The blue flags mark the edges of wetlands and have nothing to do with the limits of work on the project. The other flagging marked objects for the convenience of the surveyor and also have nothing to do with the limits of the work on the project. 63. Concern that traffic will divert to Pond Street during the Route 18 construction period and side street traffic on Pond Street will be unable to enter Pond Street due to the increased traffic volume. MassDOT cannot prohibit traffic from accessing Pond Street. However, work on Route 18 will be conducted and managed to minimize travel delays so that use of Pond Street to bypass the construction zone will not appear as an attractive option for drivers. 64.Request to stake off the limits of the project work in the backyards of the people impacted by the temporary bridge. A temporary fence will be erected to delineate the work area.

Route 18 Widening and Reconstruction Project Abington Weymouth Project File No Responses to Inquiries

Route 18 Widening and Reconstruction Project Abington Weymouth Project File No Responses to Inquiries Route 18 Widening and Reconstruction Project Abington Weymouth Project File No. 601630 Responses to Inquiries 1. What is the amount of footage being taken from our property [505 Pond Street]? 2080 SF +/-,

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares

More information

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel

More information

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies APPENDIX B Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies Revised December 7, 2010 via Resolution # 100991 Reformatted March 18, 2011 TABLE OF CONTENTS

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Categorical Exclusion (CE)

Categorical Exclusion (CE) Categorical Exclusion (CE) Project Information Project Name: Federal Project#: Project Number: 0029-002-135, D624, P101 Project Type: Construction UPC: 77383 Charge Number: Route Number: 29 Route Type:

More information

Welcome to the Public Information Centre. Red Hill Business Park South Transportation Master Plan Addendum. June 25, :00 p.m. to 8:00 p.m.

Welcome to the Public Information Centre. Red Hill Business Park South Transportation Master Plan Addendum. June 25, :00 p.m. to 8:00 p.m. Welcome Welcome to the Transportation Master Plan Addendum June 25, 2012 6:00 p.m. to 8:00 p.m. Please sign-in Background In 2006 the City of Hamilton completed the North Glanbrook Industrial Business

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

S.O.P. No. HMD

S.O.P. No. HMD Page: 1 of 9 PURPOSE: To establish (SOP) for submission requirements, review process and approval of applications for Non-vehicular Access Permits for the purpose of connection or discharge to any MassDOT

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

Standard Performance Attributes for Transportation Projects

Standard Performance Attributes for Transportation Projects Standard s for Transportation Projects Mainline Operations Local Operations Maintainability Construction Impacts Environmental Impacts Project Schedule An assessment of traffic operations and safety on

More information

I-10 CONNECT. Public Meeting #1

I-10 CONNECT. Public Meeting #1 I-10 CONNECT Public Meeting #1 The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

Staff Priority and UPWP Committee Priority List 3/25/2016. ID Proposed Study Name Project Category Tentative Project Cost

Staff Priority and UPWP Committee Priority List 3/25/2016. ID Proposed Study Name Project Category Tentative Project Cost Staff and UPWP Committee List 3/25/2016 Projects with Only (No Bottom Non- ) C-2 Safety and Operations at Selected Intersections: FFY 2017 Roadway Network Performance $65,000 Purpose: The purpose of this

More information

TRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT

TRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT TRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT AGENDA ITEM #4 T/T MTG: 092616 DATE: SEPTEMBER 26, 2016 TO: TRAFFIC & TRANSPORTATION COMMISSION FROM: BENJAMIN CHAN, P.E, T.E., DEPUTY PUBLIC WORKS DIRECTOR

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition

More information

Airport Road from 1 km North of Mayfield Road to 0.6 km North of King Street Public Information Centre #1

Airport Road from 1 km North of Mayfield Road to 0.6 km North of King Street Public Information Centre #1 Municipal Class Environmental Assessment Airport Road from 1 km North of Mayfield Road to 0.6 km North of King Street Public Information Centre #1 Date: Thursday, June 20, 2013 Time: 6:30 p.m. 8:30 p.m.

More information

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail

More information

Categorical Exclusion Programmatic Agreement Between the Federal Highway Administration And the Indiana Department of Transportation

Categorical Exclusion Programmatic Agreement Between the Federal Highway Administration And the Indiana Department of Transportation Categorical Exclusion Programmatic Agreement Between the Federal Highway Administration And the Indiana Department of Transportation Introduction The Indiana Department of Transportation (INDOT) and the

More information

6.2.2 Environmental Consequences and Mitigation Measures

6.2.2 Environmental Consequences and Mitigation Measures 6.2 6.2.1 Introduction The existing conditions, regulatory setting, and methods of analysis for transportation under CEQA are described in Chapter 3, NEPA and CEQA Analysis. Impacts that would result from

More information

TRANSPORTATION IMPACT STUDIES

TRANSPORTATION IMPACT STUDIES January 28, 2009 POLICIES AND PROCEDURES FOR TRANSPORTATION IMPACT STUDIES Related to Highway Occupancy Permits Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

TRANSPORTATION FACTS. OUR CUSTOMERS: Travel Patterns

TRANSPORTATION FACTS. OUR CUSTOMERS: Travel Patterns OUR CUSTOMERS: Travel Patterns TRANSPORTATION FACTS The more than 6.5 million people in the Commonwealth have many reasons to travel and several ways to get to their destinations. A recent statewide survey

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

Interchange Workshop Report (August 2004)

Interchange Workshop Report (August 2004) U.S. Highway 14 Corridor Study New Ulm to North Mankato Table of Contents Section Interchange Workshop Report (August 2004) Page 1. Introduction and Next Steps 1 2. Interchange Workshop Participants &

More information

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM I-15 South, MP 0 to MP 16 Environmental Assessment Public Hearing August 7, 2012 5:00 PM to 7:00 PM 1 PROJECT OVERVIEW The Federal Highway Administration (FHWA) and the Utah Department of Transportation

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority CALL FOR ARTISTS - PUBLIC ART CLIFTON ENHANCEMENT PROJECT CFA NO. 1-2014 Due Date: Friday, March 14, 2014 4:00 P.M. Official Time February 14, 2014 Prospective

More information

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS COMPLETE THROUGH REVISION #18 April 2009 CITY STANDARD DETAILS REVISIONS Revision No. Revision Date Effective Date 2 August

More information

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # )

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # ) H.O. 03/24/14 SP-14-01 Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS #201400001) Request: Approval of a Special Permit for major earthmoving in the A (General Agriculture)

More information

Woodburn Interchange Project Transportation Technical Report

Woodburn Interchange Project Transportation Technical Report Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...

More information

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS Prepared for: City and County of Denver 201 West Colfax Avenue, Department 509 Denver,

More information

Downtown Estes Loop Project Frequently Asked Questions

Downtown Estes Loop Project Frequently Asked Questions May 15 th, 2015 Project Status 1) Has Alternative 1 already been selected? Is it a done deal? Response: The NEPA process will proceed with environmental analysis of both the No Action and Alternative 1.

More information

STATE AID GUIDE FOR: Updated: December 16, 2005

STATE AID GUIDE FOR: Updated: December 16, 2005 STATE AID GUIDE FOR: Updated: December 16, 2005 1. AFTER THE FACT RIGHT OF WAY DEPARTMENT OF MINNESOTA TRANSPORTATION 2. MISCELLANEOUS AFTER THE FACT Traffic Signals, Lighting, Retaining Walls, Sidewalk,

More information

Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance

Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance APPENDICES Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance D.1 Functional classification identifies the role a highway or street plays in the transportation

More information

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1 TRANSPORTATION IMPACT STUDY (TIS) GUIDELINES FOR DEVELOPMENT APPLICATIONS Transportation and Works Department The Regional Municipality of York 17250 Yonge Street Newmarket, Ontario L3Y 6Z1 August, 2007

More information

CITY OF CLOVIS Traffic Impact Study Guidelines

CITY OF CLOVIS Traffic Impact Study Guidelines CITY OF CLOVIS Traffic Impact Study Guidelines CLOVIS, A WAY OF LIFE Approved August 25, 2014 City Council Resolution 2014-79 Prepared by City of Clovis Engineering Division Steve White, City Engineer

More information

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway

More information

Electrically Charged Fencing Standards

Electrically Charged Fencing Standards Rev. 07/2017 Electrically Charged Fencing Stards Before you dig, call 1-800-332-2344 for utility locates! COMMUNITY DEVELOPMENT Planning 541-917-7550 Building 541-917-7598 9.360 Purpose. Fences can create

More information

Funding for this guidebook was provided through the Genesee Transportation Council s Unified Planning Work Program

Funding for this guidebook was provided through the Genesee Transportation Council s Unified Planning Work Program Acknowledgments Funding for this guidebook was provided through the Genesee Transportation Council s 1999-2000 Unified Planning Work Program Steve Gleason Director, Genesee Transportation Council Paul

More information

Fence and Wall Requirements

Fence and Wall Requirements Fence and Wall Requirements Definitions Decorative wall - A wall constructed of stone or other material erected for the sole purpose of providing a decorative and/or landscaped feature, and not to include

More information

TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK

TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK I, swear (affirm) that I have read the Town of Ocean Ridge s Construction Site Management Handbook in its entirety and do hereby agree to comply

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

Suncoast Parkway 2/SR Toll 589 FPID: & 3, -4

Suncoast Parkway 2/SR Toll 589 FPID: & 3, -4 When will the Turnpike have right-of-way and parcel maps available? We anticipate receipt of 100% plans, parcel sketches and legal descriptions in late June or early July of 2015. When will the Turnpike

More information

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis,

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

Section Safety Section Cleanup. None Required

Section Safety Section Cleanup. None Required January 2000 Page 1 of 6 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED SECTIONS PART 2 PRODUCTS The General Conditions of the Contract, General Requirements, and Supplemental

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

Field Guide on. Safe Maintenance and. Work Zone Operations

Field Guide on. Safe Maintenance and. Work Zone Operations Field Guide on Installation and Removal of Temporary Traffic Control for Safe Maintenance and Work Zone Operations August 2008 Introduction This field guide provides field personnel with introductory guidance

More information

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 Section 7-10.1 Off Street Parking. Off-street parking spaces, with proper access from a street, alley or driveway shall be provided in all districts

More information

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections. Village of Vernon Hills Community Development Department 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http:// www.vernonhills.org FENCES This hand out is for REFERENCE

More information

PROGRAMMATIC AGREEMENT FOR APPROVAL OF CERTAIN CATEGORICAL EXCLUSIONS

PROGRAMMATIC AGREEMENT FOR APPROVAL OF CERTAIN CATEGORICAL EXCLUSIONS NEW 3AN 1 3 KI% JERSEY PROGRAMMATIC AGREEMENT FOR APPROVAL OF CERTAIN CATEGORICAL EXCLUSIONS BETWEEN THE FEDERAL HIGHWAY ADMINISTRATION AND THE NEW JERSEY DEPARTMENT OF TRANSPORTATION The Federal Highway

More information

Curb Ramps [ 4.7.3] [ 4.7.2; 4.8.2; 4.1.6(3)(a)] [ 4.3.7] ADA Accessibility Survey Instructions Curb Ramps Page 1 of 6

Curb Ramps [ 4.7.3] [ 4.7.2; 4.8.2; 4.1.6(3)(a)] [ 4.3.7] ADA Accessibility Survey Instructions Curb Ramps Page 1 of 6 : Curb Ramps 1 [ 4.7.3] Only measure the width of the ramp section of the curb ramp (labeled ramp to the right). The ramp section of a curb ramp is also known as the ramp run. If the curb ramp has flared

More information

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Access Management and Public Involvement: Lessons Learned the Hard Way in Utah

Access Management and Public Involvement: Lessons Learned the Hard Way in Utah TRB Committee AD107 Access Management and Public Involvement: Lessons Learned the Hard Way in Utah Matt Riffkin Tim Boschert President Access Management Program Coordinator InterPlan Co. Utah Department

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Active Risk Management - Charles River Basin

Active Risk Management - Charles River Basin Protecting, Promoting and Enhancing our Commonwealth: Assisting MassDOT to deliver projects on Time and on Budget Active Risk Management - Charles River Basin September 18, 2013 & Massachusetts Accelerated

More information

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance 2010-70s Revisions to Title 2 Administration 2.45 Land Use Advisory Commissions. Twelve individual LUAC chapters were

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

Carpinteria Avenue Bridge Replacement Project Description Introduction

Carpinteria Avenue Bridge Replacement Project Description Introduction Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with

More information

This comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that:

This comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that: 6.0 Comparison of Proposed Project and Alternatives This chapter summarizes the environmental advantages and disadvantages associated with the Proposed Project and the alternatives. Based upon this discussion,

More information

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer

More information

November 8, RE: Harrah s Station Square Casino Transportation Analysis Detailed Traffic Impact Study Review. Dear Mr. Rowe:

November 8, RE: Harrah s Station Square Casino Transportation Analysis Detailed Traffic Impact Study Review. Dear Mr. Rowe: November 8, 2006 Mr. Glenn Rowe, P.E. Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering Commonwealth Keystone Building 400 North Street, 6 th Floor Harrisburg,

More information

SECTION CONSTRUCTION SERVICES

SECTION CONSTRUCTION SERVICES SECTION 01100 CONSTRUCTION SERVICES PART 1 GENERAL 1.01 - Section Includes A. Mobilization. B. Construction Surveys. C. Record Documents. 1.02 Description Of Work A. Mobilization: includes the preparatory

More information

SECTION 5 EXCEPTIONS AND MODIFICATIONS

SECTION 5 EXCEPTIONS AND MODIFICATIONS Sec. 5-1 Walls and Fences. SECTION 5 EXCEPTIONS AND MODIFICATIONS All walls and fences shall be erected or constructed in compliance with the provisions of this section. These regulations shall not prohibit

More information

Georgia Department of Transportation Railroad Coordination Submission Checklist

Georgia Department of Transportation Railroad Coordination Submission Checklist Georgia Department of Transportation Railroad Coordination Submission Checklist Project Number: PI Number: Project Manager: County(s): Railroad Owner(s): Project Manager Contact Number: GDOT Project Designer

More information

Transit Service Guidelines

Transit Service Guidelines G R E AT E R VA N CO U V E R T R A N S P O RTAT I O N A U T H O R I T Y Transit Service Guidelines PUBLIC SUMMARY REPORT JUNE 2004 Greater Vancouver Transportation Authority TRANSIT SERVICE GUIDELINES

More information

ADMINISTRATIVE HEARING STAFF REPORT

ADMINISTRATIVE HEARING STAFF REPORT ADMINISTRATIVE HEARING STAFF REPORT Salt Lake City Water Treatment Facility 1365 West 2300 North CONDITIONAL USE Case #PLNPCM2013-00762 December 12, 2013 Planning and Zoning Division Department of Community

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Chapter URBAN & RURAL FREEWAY DESIGN

Chapter URBAN & RURAL FREEWAY DESIGN Chapter 5 URBAN & RURAL FREEWAY DESIGN 5.1 INTRODUCTION This chapter provides standards and guidance for urban and rural freeways on new construction/reconstruction projects. The chapter also provides

More information

The rezoning application and proposed transportation facility warrants consideration.

The rezoning application and proposed transportation facility warrants consideration. Date: November 11, 2014 To: Re: Chair and Members Planning & Development Committee PDE File Number: REZ1400020 275 Conception Bay South Bypass Road, Ward 5 Application to Rezone Land to Industrial General

More information

Staff Report. Application: A Application #: A Parcel number:

Staff Report. Application: A Application #: A Parcel number: Staff Report Application: 2016 20A Application #: 2016 20A Parcel number: 87-029-1110 Applicants: Bob and Carol Faye Muller on property described as: All that part of Government Lot 1, Section 29 Township

More information

Qualitative Hot Spot Analysis for PM2.5 February 4, 2008

Qualitative Hot Spot Analysis for PM2.5 February 4, 2008 Technical Guidance for TG-POL-01-08 Qualitative Hot Spot Analysis for PM2.5 February 4, 2008 This technical guidance provides general guidelines for performance of a qualitative hot spot analysis for particulate

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016

Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016 Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016 Presentation Outline Project Background Demographic and Economic Data Review Competitive Market Analysis Feasibility Assessment

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

# 17 ) UN DESERT GREEN FARMS SPECIAL USE PERMIT EXTENSION OF TIME PUBLIC HEARING

# 17 ) UN DESERT GREEN FARMS SPECIAL USE PERMIT EXTENSION OF TIME PUBLIC HEARING # 17 ) UN-101-14 DESERT GREEN FARMS SPECIAL USE PERMIT EXTENSION OF TIME PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: December 9, 2015 Item: UN-101-14 Prepared by: Robert Eastman GENERAL

More information

U.S. Army Corps of Engineers Permit Application Tips

U.S. Army Corps of Engineers Permit Application Tips U.S. Army Corps of Engineers Permit Application Tips MnDOT Environmental Conference Ben Orne and Sarah Wingert, USACE 4-29-2015 US Army Corps of Engineers BUILDING STRONG Outline Introduction to Corps

More information

Natural Gas Transmission Line SAFETY BULLETIN

Natural Gas Transmission Line SAFETY BULLETIN Natural Gas Transmission Line SAFETY BULLETIN At New Jersey Natural Gas (NJNG), safety is our top priority. Make it yours too. Join us as a Partner in Safety by following the important information in this

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

Sandstone Curb Replacement Standards

Sandstone Curb Replacement Standards Sandstone Curb Replacement Standards Division of Infrastructure Management SCOPE OF CURB REPLACEMENT (Funding Dependent) Sandstone Curb Section I - Purpose: Sandstone curb may be replaced only if existing

More information

Sidewalk Repair Program. Charter Township of Canton Engineering Services

Sidewalk Repair Program. Charter Township of Canton Engineering Services Sidewalk Repair Program Charter Township of Canton Engineering Services Sidewalk Repair Program History Canton lost a landmark case at the Michigan Supreme Court level in 1997. The Supreme Court has determined

More information

FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT

FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT District 2 1109 South Marion Avenue Lake City, FL 32025-5874 INTERSTATE 10 (SR 8) / SR

More information

2016 MUTCD CONCEPT TTC COMMENTS. Michael A. Chacon Traffic Operations Division

2016 MUTCD CONCEPT TTC COMMENTS. Michael A. Chacon Traffic Operations Division 2016 MUTCD CONCEPT TTC COMMENTS Michael A. Chacon Traffic Operations Division MUTCD 4 Ballot items were discussed at the June 2014 meeting in TTC, as well as additional topics. TTC No. 1 Pedestrian and

More information

Section 13. Guidelines for the Design of Ground Mounted Sign Supports

Section 13. Guidelines for the Design of Ground Mounted Sign Supports Section 13 BDC11MR-04 13.1 Introduction Highway signs fall into two main categories, which are subdivided as follows: 1. Overhead Signs a. Sign Bridge Structures (GO) b. Sign Cantilever Structures (GO)

More information

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI)

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI) 2013 ITE Western District Annual Meeting COCEPT DEVELOPMET, AALYSIS, AD DESIG OF A EW PARKWAY AT GRADE ITERSECTIO (PAGI) Lead Author: James M. Witkowski, PhD Supporting Author: Darrell Truitt, PE The Pima

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects 2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

RE: Jackson Row - truck route

RE: Jackson Row - truck route Will Rasbach From: Sent: To: Cc: Subject: Mayor Pat Patterson Tuesday, January 13, 2015 3:46 PM Will Rasbach; Bart Robinson; Randy Barber (rbarber@oxfordms.net); jowens@oxfordpolice.net

More information