1 BAC ADVANCED COMPOSITE TECHNOLOGIES Bridge Installation Guide Revision 1: 11 March 2016 Prepared By: Lachlan Nicol 11/03/16 Page 1 of 10

2 Contents 1. Introduction BAC Bridges Purpose of this guide Bridge Components Handling & Installation Safety Recommendation Delivery Lifting Bridge Installation Preferred Installation Procedure Optional/Additional Installation Procedures Page 2 of 10

3 1. Introduction 1.1 BAC Bridges BAC s fibre composite modular bridge systems utilise state of the art fibre composite technology and procedures to create a single, integral structure. BAC has designed and certified both pedestrian and cyclist bridges as well as fully functional road bridges. Being a lightweight, integral structure; installation costs and site works are significantly reduced, allowing the bridge system to be installed in less than one day onto pre-established abutments or headstocks. The bridge and handrail system is manufactured in BAC s Toowoomba factory and trucked as a single unit to the desired location ready for installation. All bridges are designed in accordance with the Australian Standard for bridge design: AS 5100 and in conjunction with other relevant standards including but not limited to: AS 1170, AS 2156, AS 1657, and AS All bridges are design certified by a structural Registered Professional Engineer of Queensland (RPEQ) as well as having construction certification for the manufacture of the bridge superstructure. A standard BAC bridge has a design life in excess of 100 years with no structural maintenance required over its lifespan. Bridge units can be designed to meet site-specific parameters and tolerances and can also incorporate specific customer requirements such as colour, handrailing, and sizing. All BAC bridges are provided with appropriate slip resistance coating to the top of the decks depending on the specific use. BAC prides themselves on delivering customised solutions to help maximize installation, performance, and budgetary outcomes for their customers. Figure 1 - Hardgrave Rd. Bridge Page 3 of 10

4 1.2 Purpose of this guide This guide outlines the construction procedures and requirements for the installation of BAC s modular, fibre composite bridge system. This document should be reviewed by supervisory personnel prior to commencing any bridge installation. This guide is of general nature only and should be read in conjunction with any project-specific documents including contract, project specifications, and project drawings. This guide is not a substitute for the official project management plans and documentation. Site specific requirements may take precedence over any aspects outlined within this guide. All photos and drawings in this guide are purely for explanation purposes and are not site specific. Where the contents of this guide differs from project specification and drawings, supervisory personnel should consult with BAC s project engineer for clarification. In the event of any conflict between the information in this guide and local legislative requirements, the legislative requirements will take precedence. It is the responsibility of the site supervisor and all associated contractors and consulting engineers to determine the site s suitability for construction, including access for plant and other issues. No statement in this guide is to be interpreted as a guarantee or warranty. Figure 2 - Noble St. Pedestrian Bridge Page 4 of 10

5 2. Bridge Components BAC s fibre composite bridges are manufactured as a single integrated part by our state of the art resin infusion process. Although BAC s composite bridges are supplied as a single part, there are several components which should be identified for identified for purpose of explanation. The various bridge components are shown in Figure 3 and are as listed below: Composite Bridge Components - - Girders - Deck - Concrete Abutments/Headstocks - Approach Works - Handrailing - Hold Down Brackets and Bolts Approach Works Bridge Deck Handrailing Concrete Abutments Bridge Girders Figure 3 - Bridge Component Layout Hold Down Brackets & Bolts Page 5 of 10

6 3. Handling & Installation 3.1 Safety Recommendation Safety requirements and regulations must be observed during the transportation, handling, storage, and installation of BAC s modular bridges. It is the responsibility of the contractor installing the bridges to produce a Safe Work Method Statement that complies with relevant law, codes of practice, standards, and safety regulations. All lifting equipment must be certified to lift the specific mass and approved for lifting heavy componentry. The mass of BAC s bridges varies depending on their geometry; delivered weights will be clearly marked on all relevant project drawings and given to site supervisor. Figure 4 - John W. Mott Pedestrian Bridge 3.2 Delivery The rate of delivery should be decided by the main contractor or installation contractor in consultation with BAC; this will be dependent on factors including: - On-site access - Crane size & reach - Transport availability - Site traffic control - Nominated project timing BAC recommends the development of a shipping plan to document the sequence, date, and delivery time of each bridge should the project require several deliveries. This will provide better management of transport access, carriage, and on-site materials. Figure 5 - Bridge Delivery Page 6 of 10

7 3.3 Lifting This set of lifting instructions is to be taken purely as a guide with final lifting plans to be developed by the onsite installers based on but not limited to the following variables: - Weather at time of install - Ground conditions onsite - Available crew onsite - Crane type and size used for bridge lift - Relevant health and safety procedures for onsite work Prior to delivery to site, BAC will supply the onsite installation contractors with all critical lifting data including: length, width, height, weight, and centre of gravity. The manufactured deck will be transported in a Figure 6 - Bridge Delivery & Crane Setup horizontal position as per Figure 6. Predominantly, BAC will have handrails fitted to the bridge therefore careful attention needs to be made to ensure handrails are not damaged during the lifting process. Where possible, all modular bridge components should be lifted from the delivery truck and installed directly to the prepared substructure. However, if temporary site storage is necessary, the bridges can be stored on firm, levelled ground onto hardwood timber bearers. If the ground is suitable, a maximum of three decks may be stacked with hardwood timber bearers in between (one side of handrail may need to be removed for stacking). Figure 7 - Stacked Bridges During Packing & Shipping Page 7 of 10

8 3.4 Bridge Installation The preferred bridge installation procedure is as follows: 1. Lift bridge off truck using suitable crane. 2. Place bridge superstructure on prepared abutments/headstocks and mark hold down bolt locations. 3. Lift bridge back off abutments/headstocks. 4. Drill holes in abutments at all hold down locations (including through bearing pads). 5. Place bridge back on abutments/headstocks and fill drilled holes with Ramset - Chemset 801 or approved equivalent. 6. Insert threaded rod and secure bridge 7. Pour ballast walls and approach works up to installed bridge. BAC s preferred installation procedure provides the most accurate positioning of the bridge for final securing and reduce onsite installation time. Variations of procedure may be undertaken and are detailed in section Optional/Additional Installation Procedures Preferred Installation Procedure Installation Setup Upon delivery of the BAC bridge, it is assumed that abutment/headstock work has been cured and finished appropriately according to project specifications. For ease of installation, it is suggested that the ballast wall of the abutment is not poured until the bridge has been fully positioned and secured. Bridge Mark Out Once lifted off the delivery truck, the bridge superstructure needs to be aligned and placed on the prepared abutments/headstocks for marking. Figure 8 - Prepared Abutments & Bearing Pads BAC will provide all relevant drawings detailing the position of the bridge onto the abutments/headstocks and hold down bracket locations. The beam extents and hold down bolt locations should be marked. Rubber bearing pad locations must be also be marked at this stage. Drill Holes Once the bridge superstructure has been removed off the abutments/headstocks and safely stored, holes can be drilled at all hold down bracket locations using a carbide or core drill bit. BAC requires a minimum depth of 200mm to be drilled through concrete abutments/headstocks to ensure full restraint is achieved mm hole diameters are necessary for effective bonding of Chemset 801. Holes must also be drilled in 6mm rubber bearing pads at all appropriate locations. All holes must be flushed, cleaned, dry, and free of any remaining dust or debris generated by drilling of holes into concrete. Page 8 of 10

9 Bridge Placement & Securing The bridge superstructure can now be reinstated onto the abutments/headstocks on top of the 6mm rubber bearing pads. Fill predrilled holed approximately 2/3 to 3/4 full with Chemset 801. Insert M24 threaded rod into all holes through hold down brackets and bearing pads and lightly secure appropriate nuts & washers. Ensure the final position of threaded rod is perpendicular to the abutments/headstocks. Allow to cure for a minimum of 60 minutes (depending on weather conditions & temperature) before fully tightening. Figure 9 - Bridge Placement For further Chemset 801 installation details and safety data please refer to appropriate technical and safety data sheets provided on the Ramset website: Finishing Once all brackets have been secured tightly and the bridge is positioned in final location according to relevant drawings, the ballast wall and approach works can be poured up to the bridge superstructure. 10mm expansion adhesive is to be placed at ends of bridge superstructure before pouring of ballast wall. Figure 10 - Josling St. Completed Bridge Page 9 of 10

10 3.4.2 Optional/Additional Installation Procedures - Handrailing will typically be supplied pre-fitted to BAC s bridges however under certain circumstances, such as stacking for delivery, handrails may be supplied separate. BAC will have already pre-fitted and then removed the handrails before transport to reduce onsite installation time. Onsite installation subcontractors will need to reinstate the handrail into specified, pre-drilled bolt locations and securely tighten. Figure 11 - Handrail & Hold Down Bracket Diagram - Where multiple spans are to be installed, BAC will supply relevant information regarding expansion joint installation. - Ballast walls may be pre-poured before delivery of bridge to reduce installation time, careful attention needs to be taken to ensure ballast walls are poured accurately to ensure the BAC bridge will fit within the nominated tolerance. - Ferrules may be pre cast into abutments/headstocks to allow for hold down brackets, this will remove the need for drilling onsite and can save time during installation. Before casting ferrules into concrete abutment/headstock, seek accurate measurements from BAC of all hold down bracket locations to ensure onsite alignment. - Should the contractor propose an alternative bridge installation procedure, prior approval by BAC is required before commencement. Page 10 of 10

SPECIFICATIONS FOR ERECTION OF PRECAST PRESTRESSED CONCRETE GIRDERS

SPECIFICATIONS FOR ERECTION OF PRECAST PRESTRESSED CONCRETE GIRDERS SPECIFICATIONS FOR ERECTION OF PRECAST PRESTRESSED CONCRETE GIRDERS 1.0 DESCRIPTION The Work shall consist of:.1 Transportation, unloading, and erection of precast prestressed concrete girders;.2 Supply

More information

CONCRETE FORMWORK CHECKLIST AT SITE

CONCRETE FORMWORK CHECKLIST AT SITE CONCRETE FORMWORK CHECKLIST AT SITE Concrete formwork is a temporary supporting structure for concrete when it is placed at the construction site to keep the concrete in position and shape till it gets

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans Layher Allround Bridging System Instructions for Assembly and Use Modular truss system for wide spans Certification according to DIN ISO 9001/EN 29 001 by TÜV-CERT Allround Scaffolding } CONTENT 1. Introduction...3

More information

MODULAR ACOUSTIC FENCING INSTALLATION GUIDE

MODULAR ACOUSTIC FENCING  INSTALLATION GUIDE MODULAR ACOUSTIC FENCING WWW.QUICKBUILTSYSTEMS.COM.AU INSTALLATION GUIDE INTRODUCTION THE QUICKBUILT FENCE SYSTEM IS A SMARTLY DESIGNED MODULAR SYSTEM EASY AND FAST TO INSTALL AND COST EFFECTIVE. // THE

More information

CHAPTER 3: Modern Methods of Construction (MMC)

CHAPTER 3: Modern Methods of Construction (MMC) CONTENTS 3.1.1 INTRODUCTION 3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS 3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC) 3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS 3.1.5 INSULATED CONCRETE

More information

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2) Installation Manual Orion TL-3 Steel Barrier VHD (v2) 300914 Table of Contents Orion Introduction.......... 3 Limitations & Warnings. 4 Before Installation..... 3 System Design & Design Considerations

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

Access Chambers Systems

Access Chambers Systems 2011 Access Chambers Systems S y s t e m s Pioneers in PE Pipe Technologies Index QuadBox Access Chamber p.4 QuadBox Fittings p.6 RadBox Access Chamber p.8 RadBox Fittings p.10 Specialist Chambers p.11

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements

More information

Lattice Plate Flooring

Lattice Plate Flooring Lattice Plate Flooring Introduction Pekso Precast manufacturers and supplies a range of precast concrete structural building products ranging from foundations and flooring systems that includes Lattice

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

Griffith University Cable Stayed Pedestrian Bridge

Griffith University Cable Stayed Pedestrian Bridge Griffith University Cable Stayed Pedestrian Bridge John Steele BE (Hons 1) M Eng SC, Associate SKM Sydney Laura Chong BE (Hons) Project Engineer SKM Sydney Eugene Newman BE (Civil) Project Manager Abigroup

More information

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

SECTION CLIMBING WALLS

SECTION CLIMBING WALLS SECTION 13120-1 PART 1 - GENERAL 1.1 SUMMARY A. This section includes the following: 1. Custom Climbing Wall. B. Related Sections 1. Section Structural Steel 2. Section Rough Carpentry 3. Finishes 1.2

More information

PREFABRICATED STEEL TRUSS SPECIFICATIONS

PREFABRICATED STEEL TRUSS SPECIFICATIONS PREFABRICATED STEEL TRUSS SPECIFICATIONS 1. GENERAL 1.1 Scope All engineering design and related detailing of the bridge(s) shall be provided by the supplier. The design and detailing shall conform to

More information

MassBloc Permeable Instant Wall System

MassBloc Permeable Instant Wall System PIPELINE SYSTEMS 131 004 www.rocla.com.au MassBloc Permeable Instant Wall System PIPELINE SYSTEMS MassBloc Retaining Wall Permanent Retaining Structures The Rocla MassBloc retaining wall system comprises

More information

Fig Beam Clamp Retaining Strap (B-Line B3367)

Fig Beam Clamp Retaining Strap (B-Line B3367) Fig. 69 - Beam Clamp Retaining Strap (B-Line B3367) Size Range: 3 /8"-16 thru 3 /4"-10 rod 4 (101.6mm) thru 16 (406.4mm) lengths Note: longer lengths are available consult factory Material: Pre-Galvanized

More information

HANDSET WALL FORM. Handset Wall Form. Quick Assembly - can be built using only a hammer. Reduced weight increases productivity

HANDSET WALL FORM. Handset Wall Form. Quick Assembly - can be built using only a hammer. Reduced weight increases productivity HANDSET WALL FORM Quick Assembly - can be built using only a hammer Reduced weight increases productivity Unsurpassed flexibility in design and availability of panels for a wide variety of applications

More information

Single Post Anchor Part Number Spectrum Lane ~ Missoula MT ~

Single Post Anchor Part Number Spectrum Lane ~ Missoula MT ~ Single Post Anchor Part Number 21700 7100 Spectrum Lane ~ Missoula MT 59808 800.791.8056 ~ www.spectrumproducts.com 21700 Man Rev B You have purchased a Spectrum Aquatics Single Post Anchor. Providing

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

BioPrism Solid Surface

BioPrism Solid Surface Please read all instructions before installing products. STORAGE & HANDLING: Check for damage that may have occurred during transit. Keep receptor flat on pallet, as it was shipped, until ready to install.

More information

Protective Capony RTC-16

Protective Capony RTC-16 Protective Capony RTC-16 ASSEMBLY AND OPERATION MANUAL Protective Canopy RTC-16 Assembly and Operation Manual CONTENT: 1 APPLICATION...3 2 OPERATION CONDITIONS...3 3 TECHNICAL SPECIFICATIONS...3 4 DELIVERY

More information

REPLACEMENT BRIDGES FOR LOW TRAFFIC PART ONE: CONCRETE HOLLOWCORE

REPLACEMENT BRIDGES FOR LOW TRAFFIC PART ONE: CONCRETE HOLLOWCORE REPLACEMENT BRIDGES FOR LOW TRAFFIC VOLUME ROADS PART ONE: CONCRETE HOLLOWCORE BRIDGE Chris Dowding Director Structures Group TOD Consulting - engineers and project managers BACKGROUND What is the true

More information

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck)

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck) SECTION 13125 ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck) PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Installation Instructions

Installation Instructions Installation Instructions Dynarail Safety Ladder System Corrosion Resistant Nonconductive Fire Retardant High Strength-To-Weight Ratio Long, Low Maintenance Life Meets OSHA, BOCA & Other Building Code

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

Proudly Made in the U.S.A.

Proudly Made in the U.S.A. 5-Year Warranty Proudly Made in the U.S.A. Cast-In-Place (wet-set) 2 Cast-In-Place (wet-set) Tactile Proudly Made in the U.S.A. In stock colors White 37875 Brick Red 20109 Yellow 33538 Blue 15187 Safety

More information

At last! Construction bracing made easy...

At last! Construction bracing made easy... At last! Construction bracing made easy...... a fast, smart and simple system with a range of applications THE SMART BRACING SYSTEM There are many situations in building with a need for the bracing of

More information

RapiDeck TM Composite Equipment Platform

RapiDeck TM Composite Equipment Platform RapiDeck TM Composite Equipment Platform Installs in Hours Light Weight Low Installation Cost Highly Slip Resistant Corrosion Resistant Non-Conductive High Performance Composite Solutions RapiDeck TM -

More information

Noetop is a versatile, robust integrated formwork panel system. The basic panels incorporate the strongbacks and

Noetop is a versatile, robust integrated formwork panel system. The basic panels incorporate the strongbacks and NOEtop Noetop is a versatile, robust integrated formwork panel system. The basic panels incorporate the strongbacks and walers into one timber faced panel. The panel range provides economic forming with

More information

Product Data Sheet. QuadCore Karrier. Applications

Product Data Sheet. QuadCore Karrier. Applications Applications The Quad Karrier system is face fixed, provides the support, thermal and weathering functions to the Benchmark facades. The panel can be laid horizontally or vertically. Suitable for all building

More information

T R I C O N P R E C A S T L T D. TRICON RETAINED SOIL WALL SYSTEM CrimpLock Connection System CONSTRUCTION MANUAL

T R I C O N P R E C A S T L T D. TRICON RETAINED SOIL WALL SYSTEM CrimpLock Connection System CONSTRUCTION MANUAL T R I C O N P R E C A S T L T D. TRICON RETAINED SOIL WALL SYSTEM CrimpLock Connection System CONSTRUCTION MANUAL TRICON TM RETAINED SOIL WALL SYSTEM The Tricon TM Retained Soil Wall System is a mechanically

More information

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE.

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE. The Steel Strong-Wall is a corrugated steel panel which is designed to be fixed directly to the concrete foundations of a building, within the external or internal wall, via a bolted connection. FEATURES

More information

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and

More information

Hoesch isorock vario Installation recommendations

Hoesch isorock vario Installation recommendations A company of ThyssenKrupp Steel 1/12 D tk Info 2.4.2 5.2005 1 Table of contents Page 1. Regulations / Directives 2 2. Delivery / Unloading 3 3. Storage on the site 4 4. Preparation for installation 4 5.

More information

SEM EXPANSION JOINTS.

SEM EXPANSION JOINTS. SE EXPANSION JOINTS www.arsankaucuk.com.tr 1 PROPERTIES ridge expansion joints are designed to permit the longitudinal, vertical movements and small rotation presented on bridge decks due to changes in

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Planning, Ordering, and Installing FRP Trail Bridges In the Forest Service, the recreation program has the

Planning, Ordering, and Installing FRP Trail Bridges In the Forest Service, the recreation program has the In the Forest Service, the recreation program has the responsibility for planning and conducting environmental analyses for trail bridges. The forest engineer is responsible for ensuring that a site survey

More information

Raised Basement. Mechanical Installation Guide

Raised Basement. Mechanical Installation Guide R Raised Basement Mechanical Installation Guide Ensure masonry work is correct. If recessed, the depth must be 14 inches deep unless otherwise specified for a custom application. Width and length may vary

More information

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority SYNOPSIS In recent years, there has been heightened concern over the performance of half joints

More information

SYSTEM S7-RHOMBOS INSTALLATION MANUAL

SYSTEM S7-RHOMBOS INSTALLATION MANUAL SYSTEM S7-RHOMBOS INSTALLATION MANUAL GENERAL INFORMATION GENERAL INFORMATION This assembly manual addresses all metal ceilings manufactured by durlum. The different sections describe the related/relevant

More information

SENTRY PERMANENT GUARDRAIL SYSTEM

SENTRY PERMANENT GUARDRAIL SYSTEM SENTRY PERMANENT GUARDRAIL SYSTEM The Sentry Permanent Guardrail System provides the highest level of safety for maintenance personnel when working at heights and other fall risk areas. Sentry ensures

More information

Cantilevered Rail System

Cantilevered Rail System Knight Global's Cantilevered Rail Systems are designed to eliminate the need for a four post floor structure system. It provides an alternative to workstations with minimal floor space. A wide range of

More information

PRODUCT SPECIFICATIONS

PRODUCT SPECIFICATIONS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: High density cast resin architectural products, including columns, panels, caps, bases, trim elements and balustrade systems. Specifier Note: Article below

More information

SECTION ROOF PEDESTAL PAVER SYSTEM

SECTION ROOF PEDESTAL PAVER SYSTEM SECTION 07 76 00 ROOF PEDESTAL PAVER SYSTEM ************************************************************************************************************************ Edit entire master to suit project requirements.

More information

Instructions for 12 and 15 IGT systems (12 pictured)

Instructions for 12 and 15 IGT systems (12 pictured) Instructions for 12 and 15 IGT systems (12 pictured) Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system.

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

Easy to Use A7 Saves You Time and Money

Easy to Use A7 Saves You Time and Money ADHESIVE ANCHORING SPECIALISTS Easy to Use Saves You Time and Money DESCRIPTION/SUGGESTED SPECIFICATIONS* Fast Dispensing, Fast Curing The acrylic resin and hardening agent are completely mixed as they

More information

SECTION ORNAMENTAL ALUMINUM RAILING. ** NOTE TO SPECIFIER ** Superior Aluminum Products, Inc.; Ornamental aluminum railing products.

SECTION ORNAMENTAL ALUMINUM RAILING. ** NOTE TO SPECIFIER ** Superior Aluminum Products, Inc.; Ornamental aluminum railing products. SECTION 05720 ORNAMENTAL ALUMINUM RAILING ** NOTE TO SPECIFIER ** Superior Aluminum Products, Inc.; Ornamental aluminum railing products. This section is based on the products of Superior Aluminum Products,

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Bridge Beams. Product brochure

Bridge Beams. Product brochure Bridge Beams Product brochure Bridge Beams Stahlton offers economic bridge systems to suit a variety of spans, loadings and site conditions. Our Super Tee and Single or Double Hollowcore elements are manufactured

More information

Safety Barrier Solutions

Safety Barrier Solutions S E P A R A T I N G P E O P L E F R O M H A Z A R D S Safety Barrier Solutions SOLUTIONS TO YOUR BARRIER NEEDS SIMPLE TO DESIGN AND SPECIFY UNRIVALLED TECHNICAL SUPPORT WORLDWIDE AVAILABILITY The Kee Safety

More information

Titan HV panel decking system from

Titan HV panel decking system from Titan HV panel decking system from Virtually no plywood required Drop-head allows early striking Main components erected from below All components man handleable Titan HV panel decking system The Titan

More information

Steel Floor Framing Solutions

Steel Floor Framing Solutions Steel Floor Framing Solutions Complete packages for domestic floors, decks and additions Product Manual & General Information Individually designed solutions Full design and quote service Drawings and

More information

DECKING INSTALLATION, CARE & MAINTENANCE INSTRUCTIONS

DECKING INSTALLATION, CARE & MAINTENANCE INSTRUCTIONS DECKING INSTALLATION, CARE & MAINTENANCE INSTRUCTIONS 866.729.2378 MOISTURESHIELD.COM limited lifetime warranty 866.729.2378 W W W.MOISTURESHIELD.COM Welcome To The Even Greater Outdoors. Congratulations

More information

Northpointe Renovation EPN #1701 F/A Project #17027 September 8, 2017

Northpointe Renovation EPN #1701 F/A Project #17027 September 8, 2017 SECTION 055213 - PIPE AND TUBE RAILINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

TRICON TM RETAINED SOIL WALL SYSTEM

TRICON TM RETAINED SOIL WALL SYSTEM T R I C O N P R E C A S T L T D. TRICON TM RETAINED SOIL WALL SYSTEM CONSTRUCTION MANUAL TRICON TM RETAINED SOIL WALL SYSTEM The Tricon TM Retained Soil Wall System is a mechanically stabilized earth retaining

More information

FORMWORK PROCEDURES MANUAL CONTENTS Isometric Profile of MFE System Formwork 3 SECTION (1) - PRE-CONCRETE ACTIVITIES 1. Receipt Of Equipment On Site 2

FORMWORK PROCEDURES MANUAL CONTENTS Isometric Profile of MFE System Formwork 3 SECTION (1) - PRE-CONCRETE ACTIVITIES 1. Receipt Of Equipment On Site 2 FORMWORK PROCEDURES MANUAL ALL RIGHTS RESERVED. NO PART OF THIS PUBLICATION MAY BE REPRODUCED OR TRANSMITTED IN ANY FORM OR BY ANY MEANS, INCLUDING PHOTOCOPYING AND RECORDING, WITHOUT THE WRITTEN PERMISSION

More information

Legacy report on the 1997 Uniform Building Code, the 2000 International Building Code and the 2000 International Residential Code.

Legacy report on the 1997 Uniform Building Code, the 2000 International Building Code and the 2000 International Residential Code. LEGACY REPORT ER-2895 Reissued March 1, 2004 www.icc-es.org Business/Regional Office 5360 Workman Mill Road, Whittier, California 90601 (562) 699-0543 Regional Office 900 Montclair Road, Suite A, Birmingham,

More information

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Wall - Option 4 Steps and Stairs Q & A E CONSTRUCTION

More information

Seismic Installation Manual

Seismic Installation Manual Seismic Installation Manual This manual provides the design strength capacities and installation guidelines for the Restraint systems brace components for use in the design of an overall bracing/restraint

More information

SECTION TOILET COMPARTMENTS. A. Section Metal Fabrications: Concealed steel support members.

SECTION TOILET COMPARTMENTS. A. Section Metal Fabrications: Concealed steel support members. SECTION 10155 TOILET COMPARTMENTS PART 1 GENERAL 1.1 SECTION INCLUDES A. Plastic laminate partitions. 1.2 RELATED SECTIONS A. Section 05500 - Metal Fabrications: Concealed steel support members. B. Section

More information

ArmorZone TL-2 Barrier and End Treatment

ArmorZone TL-2 Barrier and End Treatment ArmorZone TL-2 Barrier and End Treatment Product and Installation Manual ANOTHER AMORFLEX DEVELOPMENT Table of contents Introduction 3 System Overview 3 Before Installation 3 Limitations and Warnings 4

More information

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE Introduction to Echo Floors The oldest company in the group, established in Gauteng in 1982. The core business is the manufacture

More information

A. Section Metal Decking. (05300 in MF95) B. Section Cold Formed Metal Framing. (05400 in MF95)

A. Section Metal Decking. (05300 in MF95) B. Section Cold Formed Metal Framing. (05400 in MF95) SECTION 05 44 00 - PRE-ENGINEERED PRE-FABRICATED COLD-FORMED STEEL TRUSSES (Section 05425 in MasterFormat 1995) PART 1 GENERAL 1.1 SECTION INCLUDES A. Pre-engineered cold-formed steel trusses. B. Cold-formed

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

REHABILITATION AND UPGRADING OF A HERITAGE LISTED TIMBER TRUSS BRIDGE

REHABILITATION AND UPGRADING OF A HERITAGE LISTED TIMBER TRUSS BRIDGE REHABILITATION AND UPGRADING OF A HERITAGE LISTED TIMBER TRUSS BRIDGE Keith Crews Professor of Structural Engineering & Assoc Dean University of Technology Sydney, Australia keith.crews@uts.edu.au Keith

More information

TERWA REBAR CONNECTION COUPLERS

TERWA REBAR CONNECTION COUPLERS TERWA REBAR CONNECTION COUPLERS CARES Technical Approval 5058 TA1B Introduction The Terwa Parallel Threaded Coupler is a full bar strength system (the coupling is stronger than the associated rebar, sometimes

More information

The Aizhai Suspension Bridge is

The Aizhai Suspension Bridge is INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing

More information

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM T. C. NEEL and K.BOZKURT ABSTRACT This work shall consist of the design, manufacture

More information

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,

More information

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: DEWALT 701 EAST JOPPA ROAD TOWSON, MARYLAND EVALUATION SUBJECT:

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: DEWALT 701 EAST JOPPA ROAD TOWSON, MARYLAND EVALUATION SUBJECT: 0 Most Widely Accepted and Trusted ICC ES Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2966 Reissued 12/2016 This report is subject to renewal 12/2017. DIVISION: 04 00 00 MASONRY

More information

General Construction Supervisory Authority Approval

General Construction Supervisory Authority Approval General Construction Supervisory Authority Approval (Translation of the German original text which has not been checked by the DIBt.) Approval no.: Z-21.8-2018 Period of validity: April 1, 2014 until:

More information

Wabo Modular STM and D Series Large movement expansion joint system

Wabo Modular STM and D Series Large movement expansion joint system Wabo Modular STM and D Series Large movement expansion joint system Features Benefits Watertight Durable Versatile DESCRIPTION: The continuous elastomeric gland prevents runoff water from passing through

More information

D D TYPE A1, A2 & B MICHIGAN DEPARTMENT OF TRANSPORTATION 5-40 CONNECTION. L4" x 4" x 3/8" Brace. C8 x 4.25 Strut. WT9 x 17.5.

D D TYPE A1, A2 & B MICHIGAN DEPARTMENT OF TRANSPORTATION 5-40 CONNECTION. L4 x 4 x 3/8 Brace. C8 x 4.25 Strut. WT9 x 17.5. Sign length minus Adjust to avoid interference with sign legend A Deck fascia A 6" Equal Equal 6" Sign length (L) varies 6 to 12 PLAN 0 CONNECTION (DECK FASCIA) Angle connection assembly F Face of concrete

More information

Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders

Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders Catbas, Darwash, Fadul / 0 0 0 Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders F.N. Catbas, H. Darwash and M. Fadul Dr. F. Necati Catbas, P.E. Associate

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2016 to December 31, 2016 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT SECTION 230548 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Elastomeric Isolation pads. 2. Elastomeric Isolation mounts. 3. [Freestanding] [Restrained] [Freestanding and restrained]

More information

Concert Halls, Lyric Theatres and Performing Arts Venues

Concert Halls, Lyric Theatres and Performing Arts Venues APPLICATIONS AP-SVI-Concert Halls-13a Acoustic isolation of: CONCERT HALLS Concert Halls, Lyric Theatres and Performing Arts Venues Concert halls are an important and popular part of arts and leisure culture

More information

WALL MOUNTED ARTICULATING JIB CRANE

WALL MOUNTED ARTICULATING JIB CRANE SECTION 14656 WALL MOUNTED ARTICULATING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and

More information

Construction and Civil Contracting SLIPFORM CONSTRUCTION

Construction and Civil Contracting SLIPFORM CONSTRUCTION Construction and Civil Contracting SLIPFORM CONSTRUCTION Slipform construction of the building core on the Bishops See project in Perth, WA SLIPFORM CONSTRUCTION 2 The advantages of the slipform system

More information

BoSS Climalite Camera and lighting tower

BoSS Climalite Camera and lighting tower Contents Safety First Safety First Quantity Schedules Toeboard 2 9 13 33 INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. User guides are also

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

ROOF PAVER SYSTEM National Distribution SPEC - SECTION 07760

ROOF PAVER SYSTEM National Distribution SPEC - SECTION 07760 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

More information

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: HILTI, INC DALLAS PARKWAY, SUITE 1000 PLANO, TEXAS 75024

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: HILTI, INC DALLAS PARKWAY, SUITE 1000 PLANO, TEXAS 75024 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 687 (6) 699 0 www.icc es.org ESR 8 Reissued 0/08 This report is subject to renewal 0/09. DIVISION: 0 00 00 MASONRY SECTION:

More information

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: HILTI, INC DALLAS PARKWAY, SUITE 1000 PLANO, TEXAS 75024

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: HILTI, INC DALLAS PARKWAY, SUITE 1000 PLANO, TEXAS 75024 0 Most Widely Accepted and Trusted ICC ES Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3056 Reissued 10/2015 This report is subject to renewal 10/2017. DIVISION: 04 00 00 MASONRY

More information

HAWORTH PORCELAIN FLOORING SYSTEM CSI Specifications 03/29/2017. A. Concrete work and concrete floor sealer is specified in Section

HAWORTH PORCELAIN FLOORING SYSTEM CSI Specifications 03/29/2017. A. Concrete work and concrete floor sealer is specified in Section SECTION 09 36 00 Dry-Lay Tile PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Concrete work and concrete floor sealer is specified in Section 03 30 00. B. Tiling as specified in Section 09 30 00. 1.2 SUMMARY

More information

CTP STITCH-TIE AGAIN! Quick and easy way to re-anchor existing veneers to back-up structures.

CTP STITCH-TIE AGAIN! Quick and easy way to re-anchor existing veneers to back-up structures. Helical Wall Tie System for Stabilizing Veneers and Structural Repair AGAIN! ANOTHER CTP SOLUTION! CTP STITCH-TIE Quick and easy way to re-anchor existing veneers to back-up structures. Brick to Concrete

More information

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35 Packaged-Products for Less-Than-Truckload (LTL) Shipment ISTA 3 Series General Simulation Performance Test PROCEDURE VERSION DATE Last TECHNICAL Change: MARCH 2017 Last EDITORIAL Change: MARCH 2017 For

More information

fischer Test Report Fixing Tests for Bison Hollow Core Slabs

fischer Test Report Fixing Tests for Bison Hollow Core Slabs fischer Test Report Fixing Tests for Bison Hollow Core Slabs Testing on Bison Hollow Core Slabs 1. Introduction Contents Test Parameters Bison Hollow Core Slab Information 2. Fixings Products Tested FISV

More information

HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT

HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT SAMPLE GUIDE FOR RESIDENTIAL DECKS revised 7 16 Call before you dig! 1 800 272 1000 New Jersey One Call. Utility Mark Out. THIS GENERIC GUIDE IS NOT ALL INCLUSIVE

More information

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 )

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 ) SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 ) WARNING - When unpacking SpaVault, DO NOT discard styrofoam pieces, these are not packaging materials. Step 1 Excavation Important:

More information

YOUR LITE-DECK SECTIONS

YOUR LITE-DECK SECTIONS General Information Warning - Serious injury or death may result from safety hazards caused by improper use or installation. When in doubt about proper use or installation of Lite-Deck, immediately contact

More information