BRIDGES OVERVIEW 100% INDOORS WITH CONTROLLED CONDITIONS MANUFACTURED MODULAR BRIDGES & FOOTINGS PRESTRESSED GIRDERS PROJECT SPECIFIC COMPONENTS
|
|
- Bridget Barnett
- 5 years ago
- Views:
Transcription
1 BRIDGES OVERVIEW MANUFACTURED 100% INDOORS WITH CONTROLLED CONDITIONS MODULAR BRIDGES & FOOTINGS PRESTRESSED GIRDERS PROJECT SPECIFIC COMPONENTS
2 GIRDERS Bridge assets reach new levels of sustainability when prestressed concrete and precast concrete components are manufactured inside under 100% controlled conditions SUPERSTRUCTURE NU Girders (NU900 to NU2400) I-Girders (CPCI900 to CPCI2300) Box Girders (B700 to B1000) Solid Slabs (SS300 to SS400) Hollow Slabs (HS400 to HS600) Integral Deck Bridges Deck Panels and Slabs Barriers
3 SUBSTRUCTURE Wingwalls Abutments Approach Slabs Culvert Slabs Partial and full depth deck slabs Piers Pier Caps Footings NU-Girders GIRDER SPACING (mm) GIRDER SPACING (mm) I-Girders CPCI 900 NU 900 CPCI 1200 NU 1100 CPCI 1400 NU 1350 CPCI 1600 NU CPCI 1900 CPCI NU 1800 NU Lengths up to 50 m Lengths up to 45 m Box Girders APPLICATIONS Large or small bridge construction and replacements Vehicular Bridges Pedestrian Bridges Rail Bridges SERVICES Final structural drawings for are sealed (stamped) by a Professional Engineer DECAST quality verification engineers (QVE) on staff to provide services when required Installation assistance and consultation can be provided DEPTH (mm) Solid Slabs Girders DEPTH (mm) Hollow Slabs Girders DEPTH (mm) / / 1220 Depth Lengths up to 35 m Depth Lengths up to 14 m 915 / 1220 Depth Depending on depth, lengths up to 17m
4 DE-SPAN MODULAR PRECAST BRIDGE SYSTEM DIMENSIONS Span 4m to 16m Rise 0.9m to 3.6m Laying Length 1.2m to 2.5m Leg Thickness 250mm minimum Deck Thickness 300mm minimum Haunch Length 1371mm, 2032mm, 4270mm ADDITIONAL FEATURES & INFORMATION Skewed sections Cast inserts for guardrails, approach slabs and railings Wingwalls, headwalls and footings Section dimensions dependent on design, shipping and context of installation APPLICATIONS Small bridge construction and replacement Underpasses / overpasses for roads, stream crossings (to preserve natural streambed), pedestrian walkways SERVICES Final structural drawings for DE-SPAN are sealed (stamped) by a Professional Engineer. DECAST holds a Certificate of Authorization licence # , issued by Professional Engineers Ontario Installation assistance and consultation can be provided decastltd.com
5 DE-SPAN AT A GLANCE DE-SPAN is designed by DECAST structural engineers High quality, test-fitted modules Can be inspected by a contract administrator at our manufacturing facility prior to shipment Bridge legs sit in precast keyway footings Can be manufactured well in advance and installed within environmental windows for preservation of fish and wildlife habitat Varying skews available Fast installation to minimize traffic interruptions LAYING LENGTH DECK THICKNESS HAUNCH THICKNESS HAUNCH THICKNESS RISE LEG THICKNESS SPAN SPAN Width of the frame from inside the leg on one side to inside the leg on the other side, 4m to 16m RISE Distance from the bottom of midpoint, 0.9m to 3.6m LAYING LENGTH Individual length of modular section, 1.2m to 2.5m LEG THICKNESS 250mm minimum DECK THICKNESS 250mm minimum the vertical leg to the underside of the deck at
6 BOX CULVERTS AS BRIDGES APPLICATIONS ADDITIONAL INFORMATION Conveyance of storm water from urban developments Designed for gravity flow of fluids Can be used as small bridges and for stream crossing where natural stream bed does not have to be maintained Contact us at for: Box culvert sizes, not listed on next page 3-sided box culverts Special loading conditions (increased depth of cover, railway loading, other special loading conditions) Post tensioned box culverts STANDARD(S) REFERENCES Plant Prequalification Program OPSS 1821 CSA S6 CHDBC OPSS 422 ASTM C1433 CSA A23.4 DIMENSIONS OPSS Design: standard length of sections is 2.44m DECAST Design: standard length of sections is 2.5m decastltd.com
7 SPAN X RISE (mm) OPSS DESIGN WALL THICKNESS (mm) APPROX. MASS (kg/m) 1800 x , x , x , x , x , x , x , x , x ,020 SPAN X RISE (mm) DECAST DESIGN WALL THICKNESS (mm) APPROX. MASS (kg/m) 3600 x , x , x , x , x , x , x , x , x , x , x , x , x , x , x , x ,250 FEATURES AVAILABLE ON REQUEST Bends Reducers & Increasers Radius Sections Beveled Ends Scribed Holes Flush Ends Maintenance Hole Tees Plugs and Caps Dowels and Inserts - 15 M
8 CONTACT! % Rob Micieli Vice President, Sales SALES sales@decastltd.com Mauro DeFranco, P.Eng Technical Sales Engineer Frank Mazza, C.E.T Sales John Pozzobon, C.E.T Sales Martin Fischer Sales B.J. Cochrane Manager, Fleet & Yard ext 2284 ENGINEERING engineering@decastltd.com INFO & INQUIRIES info@decastltd.com 0 DECAST Ltd County Road 56 Utopia, ON L0M 1T WEB 4 decastltd.com
DE-SPAN Design Guideline. Manufactured 100% indoors. Under 100% controlled conditions.
DE-SPAN Design Guideline Manufactured 100% indoors. Under 100% controlled conditions. DE-SPAN DE-SPAN is a rigid-portal framed bridge system. Modules are designed with a horizontal deck to support soil
More informationCONCRETE PRESSURE PIPE
CONCRETE PRESSURE PIPE ENGINEERED VERSATILE LONG LASTING HIGH PRESSURE CAPACITIES EASY ECONOMICAL INSTALLATIONS BUILT-IN CORROSION PROTECTION CONCRETE PRESSURE PIPE Concrete Pressure Pipe (CPP) is an engineered
More informationSTRUCTURES INSPECTION CERTIFICATION TRAINING COURSE
STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE Code Pre/Route AFE Function Part 0 1000 7116 1174 N Hadley Eisenbeisz Bridge Construction Engineer Rick Brandner Mitchell Area Darrell utter Assistant
More informationAlberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.
STANDARD BRIDGE & CULVERT COMPONENTS Alberta Bridge Inventory In Alberta there are about 13,300 bridges. Types of bridges in Alberta: Standard bridges 3521 (26%) Bridge size culverts 8348 (63%) Major bridges
More informationAccelerated Bridge Construction in USA
Accelerated Bridge Construction in USA Abstract Rush hour traffic is a common daily occurrence in the USA. Highway and bridge construction further aggravates the situation. The Federal Highway Administration
More informationRt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening
Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationSCHEDULE A. Page 1 of 5. THIS SCHEDULE lists the precast concrete products of
SCHEDULE A Page 1 of 5 THIS SCHEDULE lists the precast concrete products of Forterra Building Products R.R. #2 2099 Roseville Road Cambridge, Ontario N1R 5S3 That have been found to comply with the Prequalification
More informationThe Pennsylvania Rapid Bridge Replacement Project
1 The rebuilding of 558 structurally deficient bridges in the Commonwealth of Pennsylvania over a 3+ year span April 2017 Charles Zugell The Plenary Walsh Keystone Partners believe engaging local community
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS
MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS SECTION 1 - MISCELLANEOUS STANDARDS 1.00.01 -.05 Table of Contents 1.11.01 Decimal Parts of a Foot and Inch 1.21.01 Factors
More informationStructural - Engineering Review Checklist
Structural - Engineering Review Checklist Project: List Corridor Criteria ID Review Priority (H,M,L) TOPICS S-_-## Structural Design Codes, Manuals and Specifications 6.1.0 REFERENCES DESIRED Criteria
More informationACHD Bridge and Culvert Policy DRAFT
ACHD Bridge and Culvert Policy DRAFT Standard Drawings and additional construction details are contained in the separate ACHD Bridge Design Guide and are hereto made part of this policy by reference. DEFINITIONS
More informationApplication of Ultra High Performance Concrete in Expediting the Replacement and Rehabilitation of Highway Bridges
Application of Ultra High Performance Concrete in Expediting the Replacement and Rehabilitation of Highway Bridges Abstract M. Ataur Rahman, P.Eng., Ph.D. and Tyler McQuaker, P.Eng. Ministry of Transportation
More informationTHE BEBO SYSTEM. World s Best for Overfilled Arches. For Precasters, Bridge Suppliers, General Contractors, Road/Rail Authorities and Consultants
THE BEBO SYSTEM World s Best for Overfilled Arches For Precasters, Bridge Suppliers, General Contractors, Road/Rail Authorities and Consultants AREAS OF APPLICATION Overpasses Bridges Spans of 3.6 m to
More informationMARTA Rapid Transit Bridges
MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically
More informationGrade Separation Inspection and Rating
Grade Separation Form Grade Separation Inspection and Rating Applies to structures which have traffic going over and under Applies to Wildlife/Cattlepass or Pedestrian Underpass structures Replaces channel
More informationHighway Bridge Structure Components
Highway Bridge Structure Components Basic Bridge Components 1 Deck and 2 Stringer 3 Bearing 4 Pedestal 5 Footing 6 Piles 7 Underpass 8 Embakment 9 Live Loading Basic Bridge Components 1-Deck & wearing
More informationSpecial Provision No. 904S11 July Section of OPSS 904, January 1995 is amended by the addition of the following:
CONCRETE IN STRUCTURE - Item No. CONCRETE IN SUBSTRUCTURE - Item No. CONCRETE IN APPROACH SLAB - Item No. CONCRETE IN DECK - Item No. CONCRETE IN BARRIER WALLS - Item No. CONCRETE IN PARAPET WALLS - Item
More informationThe Right Solution for Any Job.
bigrbridge.com The Right Solution for Any Job. When it comes to infrastructure projects, Big R Bridge is the design specialist with a proven reputation for consistently delivering the right solutions,
More informationOHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO
OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 20, 2018 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure
More informationCONCRETE PRESSURE PIPE INSTALLATION GUIDE. Leading Infrastructure Solutions
CONCRETE PRESSURE PIPE INSTALLATION GUIDE Leading Infrastructure Solutions ! CONTACT Rob Micieli 416.605.7374 Vice President, Sales Mauro DeFranco, P.Eng. 647.500.3789 Technical Sales Engineer Jenny Ogden
More informationBRIDGE INSPECTION REPORT
NC DEPARTMENT OF TRANSPORTATION ATTENTION DIVISION OF HIGHWAYS BRIDGE MANAGEMENT UNIT BRIDGE INSPECTION REPORT INSPECTION TYPE: Routine Inspection COUNTY IREDELL BRIDGE NUMBER 480596 INSPECTION CYCLE 2
More informationI2-0 LIST OF ACTIVE SSDs
I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006
More informationChapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction
Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the
More informationGrade Separation Inspection and Rating
Grade Separation Form Grade Separation Inspection and Rating Applies to structures which have traffic going over and under Applies to Wildlife/Cattlepass or Pedestrian Underpass structures Replaces channel
More informationBridge and Culvert Design Standards
3004 ROADWAY DESIGN STANDARDS 3004.1 Roadway Design Roadway planning and design for the public road system shall conform to the following guidelines and referenced specifications. Use the most current
More informationMINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION
MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION Common Name: Camp Ripley Bridge Bridge Number: 4969 Identification Number: Location: Feature Carried: TH 115 Feature
More informationLYNNVILLE ROAD BRIDGE. Site Number D00027 LYNNVILLE ROAD, CONCESSION 11, WINDHAM. 2.3km W of Highway 24
LYNNVILLE ROAD BRIDGE Site Number LYNNVILLE ROAD, CONCESSION 11, WINDHAM 2.3km W of Highway 24 Ontario Structure Inspection Manual - Inspection Form Site Number: Inventory Structure Name Lynnville Road
More informationInnovative, Cost-Effective Options for Short Span Steel Bridge Design
Innovative, Cost-Effective Options for Short Span Steel Bridge Design Infrastructure Week 2015 May 12, 2015 Gregory K. Michaelson, Ph.D. Marshall University, Weisberg Div. of Engr. Short-Span Steel Bridge
More informationDESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.
DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change
More informationPrestressed Concrete Structure Tutorial
AASHTOWare BrD/BrR 6.8 Prestressed Concrete Structure Tutorial PS5 Void Prestressed Box Beam Example BrR and BrD Training PS5 Void Prestressed Box Beam Example From the Bridge Explorer create a new bridge
More informationAGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.
Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE
More informationHorizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing
Horizontal Ellipse By eliminating the need for concrete footings this shape can often provide the lowest overall installed cost of any long span structure. If a natural stream bottom is desired the invert
More informationCONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG
CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What
More informationLecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...
Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... LECTURE 13 May 17, 2005 May 17, 2005 1 Where we have been Basics Allowable Stress Ultimate Strength Shear Camber
More informationEAST ¼ LINE BRIDGE, CONCESSION 2
NORFOLK COUNTY EAST ¼ LINE BRIDGE, CONCESSION 2 Site Number 010055 VILLA NOVA ROAD, TOWNSEND 1.13 km S of County Road 20 Ontario Structure Inspection Manual - Inspection Form Site Number: 010055 Inventory
More informationMASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK
MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,
More informationSOIL-STRUCTURE INTERACTION ANALYSIS OF A RAILWAY BRIDGE IN ROTTERDAM
SOIL-STRUCTURE INTERACTION ANALYSIS OF A RAILWAY BRIDGE IN ROTTERDAM Cenan OZKAYA Technical Consultant, Yüksel Proje International, Ankara, Türkiye Tel : +90 (312) 4957000 E-mail : kucukdahi@hotmail.com
More informationMIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating
2016 v2.1 Release Webinar PSC Composite Design Check / Load rating What is Composite Girder Module? Wizard-modeling - Steel Composite Bridge - PSC Composite Bridge Report Generation for Design & Load Rating
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada
More informationSuperstructure Guidelines
Superstructure Guidelines The following are additional guidelines on using the following types of superstructure. Pre-stressed Concrete Beams To check beam size use the beam size chart. The chart was created
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationAppendix A. Sample Inspection Report
Appendix A Sample Inspection Report This page intentionally left blank. PORT AUTHORITY OF ALLEGHENY COUNTY PITTSBURGH, PENNSYLVANIA REPORT ON THE INITIAL NBIS INSPECTION OF CHARTIERS CREEK BRIDGE BMS No.
More information2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN
2016 STRUCTURE INSPECTION APPRAISAL REPORT Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN by K. SMART ASSOCIATES LIMITED 8 McIntyre Drive Kitchener ON N2R 1H6 August 2016
More informationBRANT - NORFOLK TOWNLINE ROAD
Municipal Structure Inspection Form NORFOLK COUNTY TOWNLINE BRIDGE Site Number 010057 BRANT - NORFOLK TOWNLINE ROAD 0.3 km W of County Road 5 Inventory Structure Name Townline Bridge On Crossing Rail Road
More informationDesign & Detail Installation Manual. LongSpan Bridge and Culvert Construction System
Design & Detail Installation Manual LongSpan Bridge and Culvert Construction System Table of Contents 1.0 Long Span Installation... 2 2.0 Long Span Conceptual Details... 3 3.0 Footing Options... 6 4.0
More informationThis precast prestressed concrete pedestrian
The Rockach Boulevard Pedestrian Bridge by ELIEZER SHAMIR Partner, E. Shamir - H. Posner Consulting Engineers Tel-Aviv, Israel This precast prestressed concrete pedestrian bridge crosses the Rockach Boulevard,
More informationEGCE 406: Bridge Design
EGCE 406: Bridge Design Design of Slab for Praveen Chompreda Mahidol University First Semester, 2006 Bridge Superstructure Outline Components of bridge Superstructure Types Materials Design of RC Deck
More informationGet In, Get Out, Stay Out!
Get In, Get Out, Stay Out! FHWA Accelerated Bridge Construction Program By Gary Jakovich, P.E. Senior Bridge Engineer, FHWA Virginia Concrete Conference Richmond, VA March 6-7, 2007 Federal Highway Administration
More informationLRFD Bridge Design Manual Changes
LRFD Bridge Design Manual Changes Dave Dahlberg Bridge Design Manual & Policy Engineer May 17, 2017 Bridge Office mndot.gov/bridge Overview 1) Concrete mix designations 2) Reinforcing bar development and
More informationCONSTRUCTION SPECIFICATION FOR FORMWORK AND FALSEWORK
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 919 NOVEMBER 2011 CONSTRUCTION SPECIFICATION FOR FORMWORK AND FALSEWORK TABLE OF CONTENTS 919.01 SCOPE 919.02 REFERENCES 919.03 DEFINITIONS 919.04
More informationTS 4"x3" 4 7 6 ( 9 5 3 ( C L GUIDE POST & OFFSET BRACKET G (100x75) 1 6 ( HEXHEAD BOLT WITH HEX NUTS () 350 (14") 75 (3") TOP OF CURB 50 (2") CLR. 25 ODx52 LONG ( 1 " O D x SLEEVE h 175+ h ( 6! (3") 75
More informationVOLUME 2 TECHNICAL SPECIFICATIONS BID NO PROJECT MANUAL FOR BONDS RANCH ROAD WIDENING PROJECT BIDS DUE JULY 9, :00 P.M.
Vendor Name: JACK BEACHAM, C.P.M., A.P.P. PURCHASING AGENT TARRANT COUNTY PURCHASING DEPARTMENT ROB COX, C.P.M., A.P.P. ASSISTANT PURCHASING AGENT VOLUME 2 TECHNICAL SPECIFICATIONS BID NO. 2015-161 PROJECT
More informationB R I D G E O F F I C E
LRFD Bridge Design Manual BRIDGE OFFICE MANUAL 5-392 MINNESOTA DEPARTMENT OF TRANSPORTATION Bridge Office LRFD Bridge Design Manual MnDOT BRIDGE OFFICE LRFD Bridge Design Manual Minnesota Department of
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationMULTI-PLATE VERSATILE BRIDGE AND CULVERT PRODUCT MADE OF CURVED CORRUGATED STEEL PLATES ECONOMICAL DURABLE EASY TO INSTALL ARMTEC.
DRAINAGE SOLUTIONS SINCE 1908 MULTI-PLATE VERSATILE BRIDGE AND CULVERT PRODUCT MADE OF CURVED CORRUGATED STEEL PLATES ECONOMICAL DURABLE EASY TO INSTALL ARMTEC.COM MULTI-PLATE MULTI-PLATE HAS A PROVEN
More informationAASHTOWare BrD 6.8. BrR and BrD Tutorial. PS7-3 Stem PS Bridge Example
AASHTOWare BrD 6.8 BrR and BrD Tutorial PS7-3 Stem PS Bridge Example BrR and BrD Training PS7 3 Stem PS Bridge Example From the Bridge Explorer create a new bridge and enter the following description data.
More informationB R I D G E O F F I C E
LRFD Bridge Design Manual BRIDGE OFFICE MANUAL 5-392 MINNESOTA DEPARTMENT OF TRANSPORTATION Bridge Office LRFD Bridge Design Manual MnDOT BRIDGE OFFICE LRFD Bridge Design Manual Minnesota Department of
More informationChapter 13 Bridge Load Rating
Chapter 13 Bridge Load Rating Contents 13.1 General 13.1-1 13.1.1 WSDOT Rating (LRFR) 13.1-2 13.1.2 NBI Rating (LFR) 13.1-8 13.2 Special Rating Criteria 13.2-1 13.2.1 Dead Loads 13.2-1 13.2.2 Live Load
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationLIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)
LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul
More informationInventory Inspection and Load Rating of a Complex Segmental Concrete Bridge. Presented by Matthew J. Lengyel, PE, SE
Inventory Inspection and Load Rating of a Complex Segmental Concrete Bridge Presented by Matthew J. Lengyel, PE, SE Introduction Project Overview Parallel Segmental Bridges (1F 763 and 3F 763) Number of
More informationNew Development in Accelerated Bridge Design and Construction in WA
Delivery of Accelerated Bridge Construction WSDOT Workshop Wednesday April 1st, 2015 New Development in Accelerated Bridge Design and Construction in WA Washington State Department of Transportation Bridge
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More informationFairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program. January 29, 2014
Fairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program - Creek Road Bridge Presented by the Team of January 29, 2014 Bridge Design Process Project team explores both repair and replace
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationBasarab Cable Stayed Bridge in Bucharest
Basarab Cable Stayed Bridge in Bucharest Javier MANTEROLA Pr. Dr. Civil Engineer Carlos Fernández Casado,S.L. Madrid, SPAIN jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. Civil Engineer Carlos Fernández Casado,S.L.
More informationAppendix III. A. Classification of Concrete Bridge Components
Appendix III A. Classification of Concrete Bridge Components 1. Concrete beam/girder Concrete beam-type bridges normally can be classified into two types. One is the T beam bridge which is generally a
More informationMATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 APRIL 2004 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES
More informationCE 435/535, Fall 2003 Preliminary Design Example 1 / 6
CE 435/535, Fall 2003 Preliminary Design Example 1 / 6 Perform a preliminary design for a bridge on a state highway over a large creek in rural Alabama. Produce a construction layout drawing showing profile
More informationConstruction and design features of the Bridge over the Danube River. Bulgaria
Construction and design features of the Bridge over the Danube River. Bulgaria Javier MANTEROLA Pr. Dr. jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. amartinez@cfcsl.com Juan Antonio NAVARRO janavarro@cfcsl.com
More informationOntario Structure Inspection Manual Inspection Form Structure Number: 12
Inventory Data: Structure Name Gailbraith Road Bridge 1 Main Hwy/Road # On Under Crossing Navig. Water Non-Navig. Water Rail Type: Road Ped. Other Hwy/Road Name Structure Location Latitude Owner(s) Galbraith
More informationPLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES. Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project
PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project KEY ELEMENTS IN RURAL INFRA Planning & Design Bridges Potable Communal Small Water Roads
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationHigh Bridge Re-Deck Project
High Bridge Re-Deck Project MnDOT Contract No. 1000532 Presented to: Minnesota Department of Transportation Bridge Repair Recommendations - September 22, 2016 Bridge Overview 11 Total Spans, 2755-0 Long
More information7 Bridges in 74 Days. NC 12 Detour
7 Bridges in 74 Days (Or Less) NC 12 Detour Ocracoke NC 12 Bridges Ocracoke NC 12 Bridges Existing 7 bridges built in 1950's Timber structures w/ ACP Clear width 22.5 ft. 36 to 152 ft. long Limited redirective
More informationJULY 2014 LRFD BRIDGE DESIGN 5-1
JULY 014 LRFD BRIDGE DESIGN 5-1 5. CONCRETE STRUCTURES Reinforced and prestressed concrete are used extensively in bridge projects. In addition to general design guidance and information on detailing practices,
More informationVDOT s Experience with Reinforced Concrete and Metal Culverts
2015 Virginia Concrete Conference VDOT s Experience with Reinforced Concrete and Metal Culverts Adam Matteo, P.E. - Assistant State Structure and Bridge Engineer - Maintenance Jeff Milton - Bridge Preservation
More informationSpecial Provision No. 599S22 March 2001
RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM RETAINED SOIL SYSTEM, WALL/SLOPE,
More informationDESIGN OF SLAB PANEL BY PIGEAUD S CURVES USING IRC: AND IRC:
DESIGN OF SLAB PANEL BY PIGEAUD S CURVES USING IRC: 21-2000 AND IRC: 112-2011 Shivanand Tenagi Department of Civil Engineering, D.Y.Patil College of Engineering, Savitribai Phule Pune University, Pune,
More informationChapter 1. General Design Information. Section 1.03 Loads and Load Factors. Introduction. Load Modifying Factors
Chapter 1 Bridge Design Manual General Design Information Section 1.03 Loads and Load Factors Introduction This section defines the loads and load factors to be used in structural analysis and design.
More informationUSE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES
David P. Hohmann, P.E., and John M. Holt, P.E. 1 USE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES Submission Date: July 31, 2002 Word Count: 2529 David P. Hohmann, P.E. Director, Bridge Design Branch Bridge
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationFor Two Steel Bridges
Load Rating For Two Steel Bridges Jing juan Li PHD, PE, SE Senior Project Manager RHC ENGINEERING September 2013 Project Introduction Outline Load rating procedure: Determine load rating method Determine
More informationNew Jersey Turnpike Authority
New Jersey Turnpike Authority DOCUMENT UPDATE REQUEST Forward to Assistant Chief Engineer, Design Initiator Russell Saputo, PE Submittal Date 6/21/16 Firm Stantec Consulting Services Inc. Telephone 201-587-9040
More informationMEMORANDUM Oregon Department of Fish and Wildlife Fish Division
MEMORADUM Oregon Department of Fish and Wildlife Fish Division Date: March 28, 2008 To: From: Art Martin, Statewide Transportation Coordinator Tom Stahl, Fish Passage Coordinator Subject: Clarification
More informationSOUTH MEDFORD INTERCHANGE BRIDGES
Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is
More informationSCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report
SCCRTC- MP 19.43 San Lorenzo River Bridge Walkway Widening Feasibility Report May 19, 2016 INTRODUCTION Jacobs Engineering Group was selected to provide a feasibility report for the Santa Cruz County Regional
More informationGuidelines for Checking Final Design Bridge Plans
MNDOT BRIDGE OFFICE Guidelines for Checking Final Design Bridge Plans Edited by the MnDOT Bridge Office ES ESS Committee February 2018 Disclaimer: This document is meant to be used as a checklist for the
More information12 MILE OVER THE CHARLOTTE RIVER CHIPPEWA COUNTY ROAD COMMISSION STEVEN A. DELAIRE UPPER PENINSULA CONCRETE PIPE CO ESCANABA, MI
LowSpan and MegaBox 12 MILE OVER THE CHARLOTTE RIVER CHIPPEWA COUNTY ROAD COMMISSION STEVEN A. DELAIRE UPPER PENINSULA CONCRETE PIPE CO ESCANABA, MI Who Are We? Innovative Concrete Pre-casting Company
More informationTable of Contents. July
Table of Contents 36.1 General... 3 36.1.1 Bridge or Culvert... 3 36.1.2 Box Culvert Size Restrictions... 4 36.1.3 Stage Construction for Box Culverts... 4 36.2 Dead Loads and Earth Pressure... 5 36.3
More informationCONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF
More informationCONSTRUCTION SPECIFICATION FOR MODULAR BRIDGE STRUCTURES FOR TEMPORARY INSTALLATIONS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 918 APRIL 2017 (formerly OPSS 918 Common, March 1998) Note: The MUNI implemented in April 2017 replaces OPSS 918 COMMON, March 1998 with no technical
More informationARMTEC.COM. Proven quality and dependability in drainage solutions and water treatment
ARMTEC.COM Drainage Solutions and WATER Treatment Proven quality and dependability in drainage solutions and water treatment DRAINAGE SOLUTIONS AND WATER TREATMENT Armtec is known for quality and dependability
More informationPlease direct any questions to:
================================ PennDOT BQAD Publications e-notification Bureau of Design ================================ Publication No. 219M Standard: BC-762M RE: Sheet 1 No. 1 Date: 6-18-03 ================================
More informationClass Topics & Objectives
EGCE 406: Bridge Design Design of Slab for Bridge Deck Praveen Chompreda, Ph.D. Mahidol University First Semester, 2010 Class Topics & Objectives Topics Objective Bridge Superstructures Students can identify
More information