1 REDEVELOPMENT AGENCY BOARD SUSAN F. SHICK EXECUTIVE DIRECTOR SEE BELOW APRIL 3, 2001 SUBJECT: FOX CALIFORNIA THEATRE CONSTRUCTION CONTRACT RECOMMENDATION It is recommended that the Agency Board approve an agreement with Swinerton & Walberg Company, Inc., for construction of the Fox California Theatre Phase 2, in an amount not to exceed $11,000,000, and establishing a construction contingency of $1,000,000. BACKGROUND The Agency publicly bid Phase 1 of the Fox California Theatre Project, which included the demolition of a parking structure and the theatre stagehouse. As authorized by the Agency Board, the Executive Director awarded the demolition contract to Iconco, Inc., in the amount of $964,800, and established a 10% contingency. The demolition work was completed mid-january 2001, within the approved budget, for a final demolition cost of $1,027,664. On December 12, 2000, the Agency Board authorized the Executive Director to issue a Request for Qualifications to secure a general contractor and negotiate a contract with the most qualified contractor for Phases 2 and 3 of the Fox California Theatre Project. Phase 2 includes construction of the soil cement columns and drilled foundation piers, construction of the new stage tower and the new service drive from First Street that will serve the adjacent buildings: the Hyatt Sainte Claire Hotel, Original Joe s and the Dohrmann Building. Phase 3 is the balance of the construction for renovation and expansion of the historic theatre, including construction of a new three-story building on Market Street, with an expanded lobby and back-of-the-house facilities, and construction of a new support building and courtyard on the First Street frontage.
2 Redevelopment Agency Board Page 2 The Engineer s Estimate, prepared by Rudolph & Sletten for Phase 2 direct construction costs, is $6,377,850. In addition, Rudolph & Sletten estimated costs for general conditions and construction services for Phases 2 & 3 to be $3,450,000, with a fee for overhead, profit, bonds and insurance, to be applied to all direct costs including the general conditions cost and subcontract costs, estimated to be within the 5.25% to 5.50% range. The approved contractor selection process involved the following steps: 1. Issue a Request for Qualifications (RFQ). 2. Receive and review Statement of Qualifications responses and develop a shortlist of prequalified contractors. 3. Obtain cost proposals from short-listed general contractors for Phase 2 and Phase 3 construction services. 4. Review proposals and negotiate an Owner-Contractor Agreement with the recommended general contractor and return to the Agency Board for approval. The Request for Qualifications was advertised in the San Jose Mercury News on December 13, In addition, Rudolph & Sletten, the Agency s construction manager, made outreach telephone calls to a number of Bay Area contractors to generate interest in the project. Eight general contractors initially requested and received RFQ packages. A pre-rfq meeting was held on December 19 th, with three general contractors attending: Hathaway-Dinwiddie, Hensel Phelps, and Swinerton & Walberg. RFQ packages were also distributed to Webcor, Devcon, Gilbane, Toenisketter & Breeding; and Huber, Hunt & Nichols. ANALYSIS Swinerton & Walberg Company submitted a Statement of Qualifications on January 11, 2001, the established deadline for receipt. This was the only qualification submittal received. Prior to the submittal deadline, Rudolph & Sletten contacted all contractors who had received the RFQ package. Many contractors decided not to pursue the project and did not submit their qualifications, stating as their reasons a lack of management staff, field labor and manpower resulting from the extraordinarily hot construction market. Agency staff, along with the construction manager, reviewed the Statement of Qualifications from Swinerton & Walberg. The general contractor meets all of the qualification standards established in the RFQ. Based on this analysis and the recommendation of the project team (Rudolph & Sletten, Agency staff, General
3 Redevelopment Agency Board Page 3 Counsel and Agency outside Counsel, Tom Maser, a specialist in constructionrelated issues and an attorney with Tomlinson Zisko Morosoli & Maser, LLP), the Executive Director authorized staff to request a cost proposal from Swinerton & Walberg, the next step in the approved contractor selection process. Agency staff met with Swinerton & Walberg on January 25, 2001, to tour the theatre and initiate the cost proposal process. Fox California Theatre construction documents were distributed to Swinerton & Walberg at that time. The documents consist of the general conditions prepared by the Redevelopment Agency, supplemental conditions developed together with Rudolph & Sletten, and plans and specifications for Phase 2 developed by ELS/Elbasani & Logan Architects and approved by the Department of Public Works. On February 8, 2001, Swinerton & Walberg submitted a cost proposal for the direct cost of general conditions, including project staff and temporary facilities for Phases 2 and 3; and a percentage fee, to include required insurance and bond costs applied as percentage of the direct cost of the work for Phases 2 and 3. On February 12, 2001, Agency staff interviewed three members of the project team proposed by Swinerton & Walberg. The contractor proposed three project staff members, all of whom have experience with projects of similar size and complexity to the Fox California Theatre Project. The overall project staff will consist of a project manager, two construction superintendents, two project engineers and supporting administrative and accounting personnel. The Agency s project team reviewed the contractor s cost proposal, with Rudolph & Sletten providing cost analysis. Swinerton & Walberg submitted a cost for general conditions and construction services in the amount of $3,524,846 and a fee of 5%, for overhead, profit, bonds and insurance, which will apply to all direct costs. The contractor s proposal for the direct cost of general conditions was 1% higher than the Engineer s Estimate, while the proposed percentage fee was a quarter percent lower than estimated by Rudolph & Sletten. Tom Maser participated in the negotiations with Swinerton and Walberg. The cost proposal has been refined and a contract has been developed based on Swinerton & Walberg s proposal and subsequent negotiations. The not-to-exceed value of $11,000,000 includes the contractor s lump sum proposal for general conditions and construction services for Phases 2 and 3 ($3.6 million) with allowances for temporary power installation and power consumption, funds set aside for remaining direct costs of the Phase 2 construction work (up to $6.9 million) and the 5% contractor s fee applied to all direct costs (estimated $500,000).
4 Redevelopment Agency Board Page 4 The remaining direct costs of the construction work will include the cost of subcontracts and self-performed work. The Agreement will require Swinerton & Walberg to solicit bids from subcontractors for Phase 2 construction. Once the subcontract direct costs are known, the Agency s Executive Director will have authority to issue work authorizations to Swinerton & Walberg to begin construction. A work authorization is a signed, written order to the contractor to proceed with a specific scope of work, for a specified sum, and within a specified time. The sum of the subcontract direct costs, self-performed work and general conditions costs becomes the cost of the work upon which the contractor s fee is based. Each work authorization will include a fee (5%) for bonds, insurance, overhead and profit. Additionally, the agreement will require Swinerton & Walberg to solicit bids for Phase 3 subcontractor packages in June 2001, after construction documentation for Phase 3 has been completed, plan checked and approved. The Redevelopment Agency and Packard Humanities Institute will designate artisans and specialized contractors to perform some of the historically sensitive work. Agency staff intends to seek Board approval of an amendment to the agreement with Swinerton & Walberg, for Phase 3 construction, after the subcontract direct costs are known. Total costs for the project, including all soft costs, hard costs and contingencies, are estimated to be $64.99 million, per the attached project budget estimate. Construction of Phase 2 is expected to start in mid-may with mobilization of temporary utilities and site offices. An Order of Possession for the adjacent parcels known as the Lin property was granted by Santa Clara Superior Court and will be effective June 14, Approval of the contract with Swinerton & Walberg allows the contractor to proceed with preconstruction services and bidding of subcontracts. Because the June 14 th possession date would delay the start of construction, staff will seek permission from Caltrans to access the theatre construction site from the parking lane of Market Street. This will cause some congestion on Market Street and will require the removal of three existing trees along the site. The Agency will attempt to move and relocate the trees. Arrangements for temporary access now will allow the Agency to proceed with the Swinerton & Walberg proposal rather than lose an additional four to six months of time on the project. The contractor may not be available for the project if it is delayed, and such a delay would mean reissuing the Request for Qualifications in order to solicit new cost proposals.
5 Redevelopment Agency Board Page 5 PUBLIC OUTREACH A Construction Impact Mitigation Plan was developed for this project to identify hours of operation, dust and noise control, truck haul routing and deliveries, and maintenance of access/egress to the adjacent properties. It was reviewed with the Downtown Association and the SOFA Committee and in meetings with adjacent property owners. The Agency will continue to perform public outreach in the neighborhood and will address any issues and conditions that arise as construction continues over the next several years. COORDINATION The Fox California Theatre Project is being coordinated with the Departments of Public Works; Convention, Arts and Entertainment; Streets and Traffic; and Planning, Building and Code Enforcement. This report was coordinated with the Agency s General Counsel. FISCAL IMPACT Funding for the project is available in the Redevelopment Agency s Adopted FY Capital Budget and Five Year CIP, Market Gateway: Fox California Theatre Opera San Jose line item. Approximately one-third of the cost of the Project will be financed with grant funds from Packard Humanities Institute. CEQA Resolution No Attachment SUSAN F. SHICK Executive Director
LEVEL I PREQUALIFICATION DOCUMENTS COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION
Project No. 4863/A4L-396 LEVEL I PREQUALIFICATION DOCUMENTS for COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North
More informationLEVEL I PREQUALIFICATION DOCUMENTS GEISEL RESTROOM RENOVATIONS
Project No. 5005/A4L-424/ 962520 LEVEL I PREQUALIFICATION DOCUMENTS for GEISEL RESTROOM RENOVATIONS University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La
More informationADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION)
ADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION) Subject to conditions prescribed by the University of California, San Francisco (the University or UCSF ), bids for a Construction Manager at Risk Agreement
More informationConstruction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119
Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts
More informationLEVEL I PREQUALIFICATION DOCUMENTS
Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,
More informationContract No Amendment: Conversion Management Associates, Inc. for the Center Street Garage Replacement Project
Office of the City Manager CONSENT CALENDAR April 28, 2015 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works Subject:
More informationUCSF Precision Cancer Medicine Building January 31, th Street R&S Job No San Francisco, CA Page 1 of 1
UCSF Precision Cancer Medicine Building January 31, 2017 San Francisco, CA Page 1 of 1 AMENDMENT F INSTRUCTIONS BIDDERS 1. Bid Security: REVISED Each Bid shall be accompanied by Bid security in the amount
More informationRFQ WEB Advertisement
165 Capitol Avenue, Hartford, CT 06106 Selection Type: Request for Qualifications (RFQ) Web Advertisement Construction Manager at Risk Adv. No.: Web Advertisement Date: July 18, 2008 General Statement:
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationSTAFF REPORT. Highway 166 Cuyama School Bus Stop Improvements. MEETING DATE: January 15, 2015 AGENDA ITEM: 5A
STAFF REPORT SUBJECT: Highway 166 Cuyama School Bus Stop Improvements MEETING DATE: January 15, 2015 AGENDA ITEM: 5A STAFF CONTACT: Sarkes Khachek and Fred Luna RECOMMENDATION: 1. Approve plans and specifications
More informationLEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA
Project No. 4484/A4L-379/964840 LEVEL I PREQUALIFICATION DOCUMENTS for OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North
More informationSan Francisco State University San Francisco, California Seismic Rehabilitation - Administration Building SF-454
San Francisco State University San Francisco, California Seismic Rehabilitation - Administration Building SF-454 GOAL The goal of KPMG, Peat Marwick, LLP s review of the San Francisco State University
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationTOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR
February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for
More informationREQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services
REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request
More informationScience Technology Engineering and Mathematics (STEM) Initiative
DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 14 DIVISION: Capital Programs and Construction BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Awarding San Francisco Municipal Transportation Agency
More informationREQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for
More informationADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No.
ADDENDUM NO. 1 Date: January 11, 2017 for RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College BID No. 332 South Orange County Community College District General-All
More informationREQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN Introduction Becker County is issuing a RFQ for Construction Management at Risk Services
More informationEXHIBIT A. 1) General:
1) General: EXHIBIT A FINDINGS OF FACT FOR EXEMPTION FROM COMPETITIVE BIDDING AND USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) METHOD OF CONTRACTING FOR TILLAMOOK PUD OPERATIONS CENTER AND
More informationMARYLAND STADIUM AUTHORITY
MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS Warehouse at Camden Yards General Contractor for Warehouse Elevator Modernization Project MSA Project No. 18-061 ISSUE DATE: March 7, 2018 Contents
More informationRFQ for General Contractor-Construction Manager Page 1 of 11
REQUEST FOR GENERAL CONTRACTOR QUALIFICIATIONS PROJECT #2017-23 Baker Heights 3.6 Acre Re-development August 30, 2017 The Everett Housing Legacy, LLLP ( Owner ) and the Everett Housing Authority as the
More informationTown of York, Maine Request for Qualifications
Town of York, Maine Request for Qualifications Historic Restoration Contractor The Town of York is accepting Statement of Qualifications from General contractors experienced in historic restoration, for
More informationLease-Leaseback Project Delivery Method
Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,
More informationMARYLAND STADIUM AUTHORITY
MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS Warehouse at Camden Yards Construction Manager for Warehouse Improvements Project MSA Project No. 18-070 ISSUE DATE: April 13, 2018 Contents A. Instructions...
More informationREQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA
REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA GENERAL INFORMATION Greenwood School District 50 is
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time
More informationREQUEST FOR QUALIFICATIONS AND PROPOSALS
REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER
More informationForsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101
Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS
More informationADVERTISEMENT FOR QUALIFICATION AND PROPOSALS OF DESIGN/BUILD TRADE PARTNERS
ADVERTISEMENT FOR QUALIFICATION AND PROPOSALS OF DESIGN/BUILD TRADE PARTNERS PROJECT NOTICE Skanska USA Inc. hereinafter called SKANSKA, intends to award design-build subcontracts to HVAC, Electrical,
More informationREQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS
REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS 1. REQUEST FOR PROPOSALS. Clearwater Public Schools, Ewing Public Schools,
More informationFACILITY PROJECT BIDDING OPTIONS OVERVIEW
FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview
More informationCity and County of San Francisco
City and County of San Francisco Office of the Controller CITY SERVICES AUDITOR REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION CONTRACT AUDIT AND PROJECT CONSULTING SERVICES RFQ#CON2013-11 CONTACT: Mary Hom,
More informationSUBJECT: SEE BELOW DATE: June 1,2016
SAN IPSE COUNCIL AGENDA: 06/14/16 ITEM: Memorandum CITY OF, CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Kerrie Romanow SUBJECT: SEE BELOW DATE: June 1,2016 Approved ( 2 \ SUBJECT:
More informationOhio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011)
Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Sec. 153.65. As used in sections 153.65 to 153.73 of the Revised Code: (A)(1)
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Wide HVAC Upgrades - Steam Lines Response
More informationTHE NUCLEUS INNOVATION AND RESEARCH PARK PARKING GARAGE
REQUEST FOR DESIGN-BUILD PROPOSALS THE NUCLEUS INNOVATION AND RESEARCH PARK PARKING GARAGE Lump Sum Proposal ISSUED TUESDAY, JUNE 10, 2014 RESPONSES DUE WEDNESDAY, JULY 2, 2014 BY 4:00 PM EDT TABLE OF
More informationADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION
ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build
More informationHouse Doctor Consulting Services Application Package
Public Facilities Department House Doctor Consulting Services Application Package For FY2013 FY2015 House Doctor Consulting Services Project #7005 City of Boston Thomas M. Menino, Mayor Michael Galvin
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE Memphis Cook Convention Center Renovation City of Memphis, Department of Housing and Community Development
More information2060 FOLSOM APARTMENTS
REQUEST FOR QUALIFICATIONS FOR GENERAL CONTRACTOR SERVICES 2060 FOLSOM APARTMENTS Chinatown Community Development Center and Mission Economic Development Agency ( Chinatown CDC and MEDA ; together, Sponsors
More informationADVERTISEMENT FOR QUALIFICATION AND PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS) (BUILDING 590 Deep Foundations)
ADVERTISEMENT FOR QUALIFICATION AND PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS) (BUILDING 590 Deep Foundations) PROJECT NOTICE Skanska USA Inc. hereinafter called SKANSKA, intends to award
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More informationWEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES
1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified
More informationAlternative Delivery Methods in the Post-Davis World
CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationVANDERBILT UNIVERSITY
VANDERBILT UNIVERSITY CAMPUS PLANNING & CONSTRUCTION PROJECT MANUAL GUIDELINES INTRODUCTION These instructions are intended to guide the Architect in preparing the Project Manual for Vanderbilt University
More informationDesign Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2)
DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) CHANGES TO STAGE 2b, STAGE 3 & STAGE 4 ARISING FROM AMENDMENTS TO THE PUBLIC WORKS CONTRACTS 1. Introduction 1.1 Changes to Public Works Contracts (a)
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS DESIGN / ENGINEERING TEAM RIVERFRONT TOWN CENTER Town of Shallotte 106 Cheers Street, PO Box 2287 Shallotte, North Carolina 28459 Deadline for Submittal: February 9, 2018 at
More informationSAN ANTONIO WATER SYSTEM University Pump Station Improvements Project SAWS Job No Solicitation No. B DD
TO BIDDER OF RECORD: SAN ANTONIO WATER SYSTEM University Pump Station Improvements Project SAWS Job No. 12-6002 Solicitation No. B-14-002-DD ADDENDUM NO. 1 February 17, 2014 The following changes, additions,
More informationDecember 7, :30pm
Pre-Qualification Conference for Construction Manager at Risk Services for the New County Office Building and Parking Structure at San Mateo County Government Center, Redwood City December 7, 2017 1:30pm
More informationADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center.
ADDENDUM #2 Design/Build Contractor RFP Bid #0606-14 for the Joint-Use 21 st Century Post-Century Education Center SJECCD California July 7, 2014 SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT 4750 San
More informationJanuary 22, Table of Contents
January 22, 2014 PROCEDURES SINGLE SELECTION PROCUREMENT OF DESIGN AND CONSTRUCTION MANAGEMENT SERVICES (Section 30 of Chapter 193 of the Acts of 2004) Table of Contents 1.0 Introduction...3 1.1 Purpose
More informationRequest for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018
Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,
More informationPage 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ)
Page 1 of 2 Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ) Amendment No. 2 RFQ No. 4018000166 COMPANY NAME AND ADDRESS (To be completed by Bidder) Project Name Construction Management Services
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE
CAYUCOS SANITARY DISTRICT 200 Ash Avenue P.O. Box 333, Cayucos, California 93430-0333 www.cayucossd.org 805-995-3290 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED
More informationREQUEST FOR OFFER RFO: For: Business Continuity Program Development Consultant Services. For: Covered California
REQUEST FOR OFFER RFO: 2017-04 For: Business Continuity Program Development Consultant Services For: Covered California Date: Tuesday, September 19, 2017 You are invited to review and respond to this Request
More informationAGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018
AGENDA REPORT Meeting Date: November 20, 2018 Item Number: E 15 To: From: Honorable Mayor & City Council Vincent Chee, Project Manager Subject: A CONTINUATION OF DECLARATION THAT THE PUBLIC INTEREST AND
More informationADVERTISEMENT FOR SUBCONTRACTOR QUALIFICATION AND ADVERTISEMENT FOR PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS)
ADVERTISEMENT FOR SUBCONTRACTOR QUALIFICATION AND ADVERTISEMENT FOR PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS) PROJECT NOTICE DPR Construction, hereinafter called DPR, intends to award
More informationPUBLIC ANNOUNCEMENT REQUEST FOR DESIGN-BUILD SERVICES STATEMENTS OF QUALIFICATIONS (GREENVILLE CITY SCHOOL DISTRICT)
PUBLIC ANNOUNCEMENT REQUEST FOR DESIGN-BUILD SERVICES STATEMENTS OF QUALIFICATIONS (GREENVILLE CITY SCHOOL DISTRICT) The Greenville City School District (the "District") invites interested parties to submit
More informationREQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT
REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT The Reno-Tahoe Airport Authority (RTAA) Reno, Nevada, is seeking
More informationConstruction Manager as Constructor (CMc) Manual
Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements
More informationSAN IPSE CAPITAL OF SILICON VALLEY
COUNCIL AGENDA: 11/8/16 ITEM: CITY OF SAN IPSE CAPITAL OF SILICON VALLEY Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Jim Ortbal Barry Ng SUBJECT: AWARD OF 2016 DOT GENERAL DATE: October 17, 2016
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS TOWN OF VAIL Professional Design Services For the Redevelopment of Booth Creek Park 2900 Manns Ranch Road Vail, CO REQUESTED BY TOWN OF VAIL Department of Public Works and Transportation
More informationRFQC Bidders Conference (RFQC( No ) Tolling Systems Integrator/ I-85 Express Lanes and Back Office Conversion Project Terri Slack &
RFQC Bidders Conference (RFQC( No. 927-10-00002) Tolling Systems Integrator/ I-85 Express Lanes and Back Office Conversion Project Terri Slack & Chris Tomlinson September 3, 2009 Agenda Project History
More informationREPORT TO MAYOR AND COUNCIL
AGENDA ITEM NO. 3.f REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: April 5, 2011 SUBJECT: AWARD OF CONSTRUCTION CONTRACT IN THE AMOUNT OF $219,556 TO DON GARCIA EXCAVATING AND PAVING,
More informationADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION
ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build
More informationEXHIBIT 6 Preconstruction Work
EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements
More informationENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM
ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project
More informationPROCUREMENT DEFINITION
PROCUREMENT DEFINITION PROCUREMENT DEFINITION as well as the end receipt and approval of payment. It often involves (1) purchase planning, (2) standards determination, (3) specifications development, (4)
More informationChapter 4 State Requirements for Educational Facilities Section 4.1
providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Harshman Demolition Response Deadline 3/28/18
More informationMemorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kerrie Romanow. SUBJECT: SEE BELOW DATE: May 30, 2017
CITY OF ^2 SAN TOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 6/20/17 ITEM: Q, \0 - Memorandum FROM: Kerrie Romanow SUBJECT: SEE BELOW DATE: Approved Date SUBJECT:
More informationDefinition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan.
Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Addenda - Documents used by the Owner to incorporate interpretations or clarifications, modifications,
More informationCoastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina
Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464
More information6.a DATE: FEBRUARY 7, 2013 BOARD OF DIRECTORS RICHARD D. THORPE CHIEF EXECUTIVE OFFICER
6.a DATE: FEBRUARY 7, 2013 TO: FROM: ACTION: BOARD OF DIRECTORS RICHARD D. THORPE CHIEF EXECUTIVE OFFICER AUTHORIZE THE CHIEF EXECUTIVE OFFICER TO ISSUE AN INVITATION TO BID FOR THE CONSTRUCTION OF THE
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response
More information2. Clarification: The building address is 801 Henderson Street.
East Energy Structural Steel Painting University of South Carolina Project Number H27-Z037 Addendum One October 19, 2015 NOTE: The following amendments, additions, and deletions shall be made to the Construction
More informationMONTGOMERY STREET. Construction Manager at Risk (CMAR) Services
2 nd PRE-PROPOSAL CONFERENCE March 6, 2015 MONTGOMERY STREET (City Project #02432) Construction Manager at Risk (CMAR) Services PROCUREMENT MARCH 19, 2015 1 Michael Weiss, P.E. City of Fort Worth Project
More informationCattaraugus County Little Valley County Center Court Renovations Second Floor Little Valley, NY
140 John James Audubon Parkway, Suite 201, Amherst, New York 14228 P 716.688.0766 F 716.625.6825 ADDENDUM NO. 1 Cattaraugus County Little Valley County Center Court Renovations Second Floor Little Valley,
More informationMetro. Board Report SUBJECT: METRO EXPRESSLANES OPERATIONS AND MAINTENANCE TECHNICAL OVERSIGHT SUPPORT
29 Metro Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File#: 2015-0511, Version: 1 AD HOC CONGESTION REDUCTION COMMITTEE
More informationCOUNCIL AGENDA: 9/20/2016 jjtojt ITEM: 7.. I. SUBJECT: SEE BELOW DATE: August 29, 2016
COUNCIL AGENDA: 9/20/2016 jjtojt ITEM: 7.. I CITY OF C: SAN JOSE CAPITAL OF SILICON VALLEY Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Kerrie Romanow Jon Cicirelli SUBJECT: SEE BELOW DATE: Approve^,
More information08/09 RIGHT OF WAY AND UTILITIES DIVISION PROCEDURES FOR THE PROCUREMENT OF RIGHT OF WAY ACQUISITION CONSULTANTS
08/09 RIGHT OF WAY AND UTILITIES DIVISION PROCEDURES FOR THE PROCUREMENT OF RIGHT OF WAY ACQUISITION CONSULTANTS RIGHT OF WAY AND UTILITIES DIVISION PROCEDURES FOR THE PROCUREMENT OF RIGHT OF WAY ACQUISITION
More informationREQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES Memorial Ballpark Renovation
REQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES Memorial Ballpark Renovation The Mandan Park District, Mandan, ND (Owner) is seeking proposals from qualified Civil Engineering firms to provide professional
More informationPUBLIC CONTRACT CODE SECTION
PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized
More informationNotice to Bidders (REV 1)
Page 1 of 6 MATADERO CREEK SEDIMENT REMOVAL & EROSION REPAIR AND SAN TOMAS AQUINO CREEK EROSION REPAIR PROJECT Project No. 62084001, Task No. 5188 Contract No. C0642 1. Notice. Notice is hereby given that
More informationNOTICE INVITING GENERAL CONTRACTOR PREQUALIFICATION
University of California, Irvine 2016-17 State Funded Reroof Multiple Buildings Project No. 5110248 NOTICE INVITING GENERAL CONTRACTOR PREQUALIFICATION The University of California, Irvine (UCI) requests
More informationPROJECT SPECIFIC QUALIFICATION STATEMENT REQUIREMENTS for CONSTRUCTION MANAGEMENT SERVICES
PROJECT SPECIFIC QUALIFICATION STATEMENT REQUIREMENTS for CONSTRUCTION MANAGEMENT SERVICES Kraus Edward Henry Building Renovation and Addition U-M Project Number P00011092 Submittal Deadline: April 12,
More informationAmity School District 4J
Amity School District 4J Code: DJCA-AR Adopted: 10/11/00 Revised/Readopted: 06/22/05 Personal Services Contracts I. Personal Services Contracts Defined A. Personal services contracts include, but are not
More informationUNC Charlotte Residence Hall Phase XVI Early Site Utilities Package SCO ID: B JPA Project #: 18NCC016
Jenkins Peer Architects 112 South Tryon Street Charlotte, N.C. 28284 704/372-6665 ADDENDUM No. 1 Date: March 12, 2018 To: From: Re: All Bidders Jenkins Peer Architects Charlotte, N.C. UNC Charlotte Residence
More informationBidding Conditions Attachment C
Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS
More informationBidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue
Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued
More informationRequest for Proposals Triennial Performance Audit of Public Transit Systems and The Council of Governments in San Joaquin County
Request for Proposals Triennial Performance Audit of Public Transit Systems and The Council of Governments in San Joaquin County April 09, 2018 Responses Due Date/Time April 30, 2018 before 4:00 PM Pacific
More informationAgenda. Hugh Tucker, Deputy Chief Procurement Officer Legislation Request for Qualifications/Proposals
August 15, 2016 1 Agenda Welcome & Introduction Design-Build Vision Comprehensive Modernization Projects 2016 Legislation Request for Qualifications/Proposals Proposal Scoring Information Provided By LAUSD
More information1. PROJECT INFORMATION
Request for Proposal (RFP) Tribune Building Project Incourage Community Foundation, Inc. ( Incourage ) located in rural central Wisconsin, invites proposals from interested firms for Construction Management
More informationPre Proposal Proposal Meeting
SOUTHERLY WWTC SECOND STAGE RETURN SLUDGE PUMP IMPROVEMENTS Design Build Project Pre Proposal Proposal Meeting August 15, 2012 Introduction Progressive Design-Build Procurement Approach Request For Proposals