ADDENDUM NUMBER ONE Clarifications

Size: px
Start display at page:

Download "ADDENDUM NUMBER ONE Clarifications"

Transcription

1 August 25, 2017 ADDENDUM NUMBER ONE Clarifications RE: Interdisciplinary Science and Technology Building VII (ISTB 7) Request for Qualifications No. CMAR Total pages in this addendum: Five (5) The Pre-Submittal Conference Presentation power point is incorporated into the RFQ Scope (separate attachment on bid board). Please note the following questions were submitted prior to the deadline for inquiries date of 08/21/17 at 5:00 P.M., MST. 1. Q. This project requires some additional forms (supplemental forms) that I have not completed before. Can you verify that this is correct? A. Supplemental Requirements will be required from the awarded firm. The supplemental forms do not need to be included in your RFQ submittal package. 2. Q. Following a submission of the RFQ, what will be the next stage of the procurement process (e.g., financial tender, design competition, etc)? A. Selection Process is outlined in General Information & Instructions on the forms board following DP(CM@RISK) Single Agreement, Forms and RFQ Information 3. Q. Should we include a local executive architect on our team, or can this be added at a later date? A. Your RFQ submittal must include this information. Reference General Information & Instructions located at this link following DP(CM@RISK) Single Agreement, Forms and RFQ Information Part V: General Instructions, License in Arizona. 4. Q. I note the requirement in Section 4 for a number of attached forms. I have checked the specified website and I can only find some of the forms. A. All forms are under the heading: DP(CM@RISK) Single Agreement, Forms and RFQ Information at this link 1

2 5. Q. Could the University provide a list of the pre-submittal conference attendees? A. The pre-submittal conference attendee list and all information for this RFQ are posted on the ASU bid board: 6. Q. Is it acceptable for a firm to submit a proposal with the intention of choosing a local architectural firm to partner with, in collaboration with the University, should we be successful? A. Your RFQ submittal must include this information, per General Information & Instructions located at this link following DP(CM@RISK) Single Agreement, Forms and RFQ Information 7. Q. Does the cover letter count towards the 20 page limit? 8. Q. Would imagery and a small amount of text on tabs be considered a page? 9. Q. Will commissioning services be procured as a separate RFQ or will that be included as part of the design team? A. ASU s preference is to have a third party commissioning agent. 10. Q. (Pre-Submittal Conference): During the pre-proposal conference, it was stated that the presentation slides would be posted online for further viewing. Can you please confirm when this information will be made available? A. The pre-submittal presentation and all information for this RFQ will be posted on the ASU bid board: Q. (Part II section 2): Does ASU currently have a more detailed program or project brief other than that stated on the RFQ (page 6 of 13)? If so, will this information be shared with the DP bidders prior to award? A. All information available is in the RFQ and addenda. There is no additional programmatic information available at this point. 12. Q. (Part II section6): On the Project Schedule (page 8 of 13), it appears the date stated for 100% Design Development and GMP is out of sequence or a typo. Can you please confirm the correct date? A. 100% Design Development and GMP 02/16/18 is revised to: Q. (Part III section 4): In section 4 (page13 of 13), it states that by submitting a response to the RFQ, DP acknowledge and agree to all terms and conditions of the Standard Form Agreement, however in Part IV Selection Process it states that negotiation of the contract will take place. Can you confirm that the selected Design Professional will have an opportunity to negotiate specific terms, such as cap on liability, copyright, etc? A. Negotiation of the contract would occur with selected design professional and address defining the scope of work, timeframe of the work, and pricing. 2

3 14. Q. During the Pre-Submittal Conference on August 15th, Ed Soltero mentioned that the presentation given during the conference would be posted on the Construction / Facilities Bid Board. Can you please confirm when this will be posted? A. The pre-submittal presentation and all information for this RFQ will be posted on the ASU bid board: Q. Can you please clarify the Estimated Project Schedule dates provided in the RFQ? For example, the 100% Design Development and GMP completion date is in February 2018, while the Schematic Design completion date is in April 2018)? A. See answer to question no. 12. Please refer to revised scheduled posted as part of the presubmittal presentation on the ASU bid board: Q. Part 3, Section 1, Point 3: Client References Client references are noted as a submission requirement within Section 1, which would be within the 20-page limit. Client references are then listed again in Section 4, Attachment 3. Is it acceptable to only include the full client references within Section 4, Attachment 3 and not within Section 1? A. Yes. 17. Q. Part 3, Section 2, Point 5: Sub-consultants In assembling our team, we have assumed ASU will retain a surveyor, geotechnical engineer and commissioning agent directly. Are there other consultants that ASU will retain directly? 18. Q. Per the DP (CM@RISK) RFQ General Information & Instructions under page 6 of 13, Arizona Office, please elaborate on any specific requirements about the nature of a relationship between Architects, including: may either party act as Architect of Record? Must certain scopes of service be performed by one or the other party? Must professional design fees be split in any prescribed manner? A. There are no specific requirements for the nature of the relationship other than what is outlined in the General Information & Instructions located at this link following DP(CM@RISK) Single Agreement, Forms and RFQ Information 19. Q. Please confirm that a letter-sized, double-sided portrait format submission is the preferred format and orientation. A. Reference Part III: Proposal Format and Contents, Page 9 of the RFQ. 20. Q. Per RFQ page 7, Items 3, 4: Item 3 states that the Historical Preservation review will be over the counter. However, Item 4 states no Historic Preservation issues are anticipated. Please clarify, particularly given that in the Pre-Proposal meeting, mention was made of the waterway on site having potential historic value to indigenous populations. A. ASU Historic Preservation/Archaeological staff will address any issues pertaining to the historic waterway on the site. 3

4 21. Q. Per RFQ Page 7, Item 5, please clarify what specific project costs are included and/or excluded in the Estimated Project Budget target of $175M. This items include design team fees; permitting and approval costs; all regulatory and outreach costs associated with the light rail and pedestrian bridge, other site improvements and/or enabling projects; FF&E, etc. What is the anticipated Construction Cost (aka hard cost ) for the 258K GSF? A. ASU typically commences project design with a 70% hard cost to 30% cost ratio. At this point, the construction cost is slated at approximately $122.5M. 22. Q. Please elaborate on the work completed by ASU liaising with regulatory authorities with regards to, individually, the pedestrian bridge spanning University Avenue and ISTB-7 spanning the light rail right-of-way. Please elaborate on what role(s) is/are anticipated for the Design Professional vis-à-vis public outreach and regulatory approval? Please elaborate on to what extent these efforts are already accommodated in the Estimated Project Schedule. A. ASU has begun discussions with all regulatory authorities on issues pertaining to air rights, right-of-way intergovernmental agreements with Valley Metro and others. The selected design team will support ASU internal staff with design and construction documentation necessary to secure the appropriate agreements. The aforementioned support documentation will begin during the Project Definition phase and be completed by the end of the Schematic Design phase. 23. Q. Please elaborate on the qualitative allocations anticipated to be for assigned to this project and/or additional information on the program elements described in item 2 Project Description. A. A complete program addresses both the quantitative and qualitative aspects in support of a project design. We are expecting the proposing teams to determine and respond as to how they expect to address these. The Selection Committee will scrutinize this closely and determine which team best addressed such. 24. Q. Please elaborate on the anticipated funding source(s) for ISTB-7. A. ASU will provide funding for the project from different funding sources that will be finalized by the time it is presented to ABOR. 25. Q. Will ASU make publicly available, prior to the RFQ submission date, the excerpts of the planning study shown as part of the 8/15 Pre-Proposal meeting? A. There is no planning documentation other than that which was presented during the presubmittal session. 26. Q. Shall submissions list only the firm names of proposed subconsultants, or shall key personnel be listed individually? If the latter, shall the submission include brief biographies/resumes of those individuals? A. Both; key personnel with relevant experience will be scrutinized closely. While CVs are important, the Selection Committee is looking for relevant experience on project type. 27. Q. If a general contractor is submitted as a consultant to the design team, would that exclude the general contractor from being considered for the ISTB-7 CMAR contract? A. Yes. There is a vehicle for General Contractor selection as part of the CMAR selection 4

5 protocol. This RFQ is limited to design professionals. 28. Q. It is our understanding that the 20-page (single-sided) limitation applies to Sections 1 3, and that the cover letter falls outside of these sections and is therefore excluded from this limit. Please confirm. A. Yes. 29. Q. Was it intentional to ask us to include lab consultants (plural)? Would you like us to propose multiple lab consultants so that we can discuss preference at a later stage, and ultimately choose one together? A. Please include a lab consultant as deemed necessary for the project type. The Selection Committee will base its selection decision partly on the lab consultant included within the RFQ. 30. Q. Can you clarify that the workload chart should depict the percentage of time each individual will be devoted to this project compared to time the individual will devote when considering other projects/tasks in their workload? A. The Selection Committee wants to determine the amount devoted by each individual on the project milestones as illustrated on the table. The Planning Committee will require direct interface with the nominated individual throughout the specific milestone. 31. Q. It is our understanding that we should address the experience of each subconsultant, but do not need to list individual members of each of these firms. Please confirm. A. Please see response to Question Q. Do we need to show an experience matrix for our subconsultant team? A. This is up to the responding team. Please be advised that the Selection Committee will look closely at relevant experience. 33. Q. Is it ASU s intent to sign a contract for Phase 1 work only, and then, if the university is satisfied with the results of the DP s Phase 1 work, re-enter into negotiations for the Phase 2 design through construction work? ASU will sign a contract for the entire scope of the project, albeit with the right to terminate the consulting agreement upon review of the completeness and quality of the Project Definition phase. All other specifications, terms and conditions of the solicitation shall remain unchanged. NOTE: Please acknowledge your firms' receipt of this addendum in your bid on the Addendum Acknowledgement form. Gail Horney Gail Horney, Sr. Buyer Purchasing and Business Services Construction Group gail.horney@asu.edu 5

Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ)

Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ) Page 1 of 2 Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ) Amendment No. 2 RFQ No. 4018000166 COMPANY NAME AND ADDRESS (To be completed by Bidder) Project Name Construction Management Services

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS PROJECT: ISSUE DATE: October 22, 2018 ISSUED BY: INQUIRIES: SUBMISSION DEADLINE: SUBMIT TO: City of Delaware, Ohio Public Works Department, Traffic & Engineering Services 440

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK FOR THE NEW

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK FOR THE NEW REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK FOR THE NEW Fire Station No. 1, Fire Administration, Training/Emergency Operations, and Public Works Service Center DUE April 17, 2017 BY 4:00

More information

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS

More information

ADDENDUM NO. 1 Questions and Answers

ADDENDUM NO. 1 Questions and Answers ADDENDUM NO. 1 Questions and Answers Addendum to the Indianapolis Bond Bank RFQ-LJF-2017-004 Request for Qualifications Design and Design Criteria Consulting Services for the Indianapolis-Marion County

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN Introduction Becker County is issuing a RFQ for Construction Management at Risk Services

More information

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No.

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No. ADDENDUM NO. 1 Date: January 11, 2017 for RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College BID No. 332 South Orange County Community College District General-All

More information

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013) SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS 1.0. Invitation Capital Region Water (CRW) owns and operates the drinking water, wastewater and stormwater facilities and infrastructure for the city of Harrisburg, PA and portions of surrounding communities

More information

REQUEST FOR QUALIFICATIONS (RFQ-18084) CONSTRUCTION MANAGEMENT AT RISK (CMAR) SERVICES STATEMENT OF QUALIFICATIONS (SOQ)

REQUEST FOR QUALIFICATIONS (RFQ-18084) CONSTRUCTION MANAGEMENT AT RISK (CMAR) SERVICES STATEMENT OF QUALIFICATIONS (SOQ) REQUEST FOR QUALIFICATIONS (RFQ-18084) CONSTRUCTION MANAGEMENT AT RISK (CMAR) SERVICES STATEMENT OF QUALIFICATIONS (SOQ) Project: Ludden Library Renovation & Expansion By Laramie County Community College

More information

This Addendum consists of:

This Addendum consists of: ADDENDUM No. 1 Sealed Bid # 18-6298 Request for Proposal Design and Building Services for the New Animal Control Annex Building # 2 Cobb County Property Management Department Page 1 of 6 Date: September

More information

Amendment 01. Issued: August 18, For. RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School

Amendment 01. Issued: August 18, For. RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School Amendment 01 Issued: August 18, 2017 For RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School Academy District 20 Proposals Due: August 25, 2017 by 2:00pm MST Issued by:

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Professional Engineering Services for 2016 Public Works Transportation and Mobility On-Call Project Control No. PWTES2016-006 EBid Document No. 4409833

More information

MARYLAND STADIUM AUTHORITY

MARYLAND STADIUM AUTHORITY MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) DESIGN CONSULTANT FOR EXPANSION JOINT REPLACEMENT Small Business Reserve Procurement M&T BANK STADIUM MSA Project No. 19-021 ISSUE DATE: October

More information

REQUEST FOR QUALIFICATIONS AND PROPOSALS

REQUEST FOR QUALIFICATIONS AND PROPOSALS REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan

More information

If you are downloading the RFQ from the website, continue to monitor the website for addenda. Failure to incorporate any addenda into your submittal

If you are downloading the RFQ from the website, continue to monitor the website for addenda. Failure to incorporate any addenda into your submittal If you are downloading the RFQ from the website, continue to monitor the website for addenda. Failure to incorporate any addenda into your submittal may cause your submittal to be considered non-responsive.

More information

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA REQUEST FOR PROPOSALS FOR Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA City of Coralville Iowa Coralville, IA Page 1 of 6 Please review and provide response to this letter

More information

REQUEST FOR STATEMENTS OF QUALIFICATIONS FOR REAL ESTATE BROKERAGE SERVICES FOR THE CITY OF TOLLESON

REQUEST FOR STATEMENTS OF QUALIFICATIONS FOR REAL ESTATE BROKERAGE SERVICES FOR THE CITY OF TOLLESON REQUEST FOR STATEMENTS OF QUALIFICATIONS FOR FOR THE CITY OF TOLLESON City of Tolleson 9555 West Van Buren Street Tolleson, Arizona 85353 SOLICITATION INFORMATION AND SELECTION SCHEDULE Solicitation Number:

More information

RFP 3512R09 Strategic Consultant Services for the Office of Policy and Public Private Partnerships Addendum 3 Appendix H Questions & Answers

RFP 3512R09 Strategic Consultant Services for the Office of Policy and Public Private Partnerships Addendum 3 Appendix H Questions & Answers 1. Question Is pre-registration required for the pre-proposal conference on May 3? Answer Pre-registration is not required. Please refer to Section I-8 of the RFP for further information. 2. Question Please

More information

City of Frederick PURCHASING DEPT.

City of Frederick PURCHASING DEPT. ADDENDUM #4 RFP #12-D CITY OF FREDERICK WWTP ENR UPGRADE March 12, 2012 TO: SUBJECT: REF: All Potential Proposers RFP #12-D, CITY OF FREDERICK WWTP ENR UPGRADE Revised Proposal Closing Date, Submitted

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS CONSULTING & ARCHITECTURAL SERVICES FOR NEW PUBLIC SAFETY FACILITY Date Issued: June 1, 2017 1. Request for Qualifications (RFQ) Instructions and General Scope of Services 1.1.

More information

Metro Gold Line Foothill Extension Construction Authority

Metro Gold Line Foothill Extension Construction Authority Metro Gold Line Foothill Extension Construction Authority REQUEST FOR PROPOSALS (RFQ) C2002 PHASE 2B ALIGNMENT DESIGN-BUILD PROJECT RFQ Issued November 8, 2017 QUESTIONS AND ANSWERS MATRIX 2 Issued December

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II El Paso, Texas EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL for the BUILDING CONCRETE GLASS AND GLAZING FIRE SPRINKLER MECHANICAL

More information

MARYLAND STADIUM AUTHORITY

MARYLAND STADIUM AUTHORITY MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS Warehouse at Camden Yards General Contractor for Warehouse Elevator Modernization Project MSA Project No. 18-061 ISSUE DATE: March 7, 2018 Contents

More information

The Center for Health Care Services

The Center for Health Care Services The Center for Health Care Services SUBJECT: FROM: Request for Proposal (RFP) for Electronic Health Record Consultant Services, RFP 2018-015, Scheduled to Open: July 16, 2018; Date of Issue: June 14, 2018

More information

PIEDMONT TRIAD AIRPORT AUTHORITY

PIEDMONT TRIAD AIRPORT AUTHORITY PIEDMONT TRIAD AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) for ON-CALL ENVIRONMENTAL CONSULTANT SERVICES at the PIEDMONT TRIAD INTERNATIONAL AIRPORT (GSO) The Piedmont Triad Airport Authority (PTAA)

More information

ADDITIONAL TYPES OF WORK REQUIRING PRE-QUALIFICATION:

ADDITIONAL TYPES OF WORK REQUIRING PRE-QUALIFICATION: CENTRAL FLORIDA EXPRESSWAY AUTHORITY NOTICE TO PROFESSIONAL ENGINEERING CONSULTANTS REQUEST FOR LETTERS OF INTEREST FOR GENERAL ENGINEERING CONSULTANT SERVICES CONTRACT NO. 001145 The Central Florida Expressway

More information

MARYLAND STADIUM AUTHORITY

MARYLAND STADIUM AUTHORITY MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) GENERAL CONTRACTOR RENOVATIONS TO OPERATIONS OFFICE M&T BANK STADIUM MSA Project No. 19-013 ISSUE DATE: October 9, 2018 MARYLAND STADIUM AUTHORITY

More information

Ohio Public Employees Retirement System. Request for Proposal

Ohio Public Employees Retirement System. Request for Proposal Ohio Public Employees Retirement System For: Consulting Services for Development of the Business Intelligence & Analytics Office Date: 9/11/2017 Project Name: Business Intelligence & Analytics Program

More information

ADDENDUM NO. 2. Kansas City Area Transportation Authority (KCATA) 1350 E. 17 th Street Kansas City, Missouri 64108

ADDENDUM NO. 2. Kansas City Area Transportation Authority (KCATA) 1350 E. 17 th Street Kansas City, Missouri 64108 ADDENDUM NO. 2 Kansas City Area Transportation Authority (KCATA) 1350 E. 17 th Street Kansas City, Missouri 64108 Issue Date: October 19, 2016 RFQ # 16-7026-25 This Addendum is hereby made a part of the

More information

Science Technology Engineering and Mathematics (STEM) Initiative

Science Technology Engineering and Mathematics (STEM) Initiative DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and

More information

Request for Qualifications Statements

Request for Qualifications Statements Request for Qualifications Statements BND WATER DISTRIBUTION AND WASTEWATER TREATMENT ENGINEERING STATEMENTS ENGINEERING DESIGN SERVICES FOR BND WATER DISTRIBUTION AND WASTEWATER TREATMENT The Brownsville

More information

Manhattan Greenway Harlem River Project 7394 / Contract Questions & Answers September 13 th, 2018

Manhattan Greenway Harlem River Project 7394 / Contract Questions & Answers September 13 th, 2018 Manhattan Greenway Harlem River Project 7394 / Contract 73940001 Questions & Answers September 13 th, 2018 In connection with the Request for Proposals relating to the Manhattan Greenway Harlem River released

More information

Addendum #02 New County Office Building Responses to RFP Questions

Addendum #02 New County Office Building Responses to RFP Questions Sam Lin Manager Project Development Unit 1402 Maple Street Redwood City, CA 94063 650-369-4766 September 22, 2017 slin@smcgov.org Addendum #02 New County Office Building Responses to RFP Questions To All

More information

Hillsborough City School District Window Covering Projects At 6 District Sites. Bid #19-01 ADDENDUM NO. 1

Hillsborough City School District Window Covering Projects At 6 District Sites. Bid #19-01 ADDENDUM NO. 1 Window Covering Projects At 6 District Sites Bid #19-01 ADDENDUM NO. 1 February 13, 2019 Owner: Project Manager: 300 El Cerrito Avenue Hillsborough, CA 94010 Capital Program Management, Inc. 1851 Heritage

More information

Environmental Monitoring of the Bedrock Landfill Sites

Environmental Monitoring of the Bedrock Landfill Sites Enterprise Resource Management Services 1815 Sir Isaac Brock Way, P.O. Box 1042, Thorold, ON L2V 4T7 Tel: 905-980-6000 Toll-free 1-800-263-7215 Fax: 905-682-8521 www.niagararegion.ca Page 1 of 6 Date:

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Request for Proposals CONTRACTED LANDSCAPE ARCHITECTURE SERVICES

Request for Proposals CONTRACTED LANDSCAPE ARCHITECTURE SERVICES Request for Proposals CONTRACTED LANDSCAPE ARCHITECTURE SERVICES Issued October 18, 2017 DEADLINE Noon Wednesday, November 15, 2017 CONTACT: KRISTINA HANDT CITY ADMINISTRATOR 3800 Laverne Ave N Lake Elmo,

More information

CITY OF BLUE ASH REQUEST FOR QUALIFICATIONS TO PROVIDE ARCHITECTURAL AND ENGINEERING SERVICES FOR THE DESIGN OF THE

CITY OF BLUE ASH REQUEST FOR QUALIFICATIONS TO PROVIDE ARCHITECTURAL AND ENGINEERING SERVICES FOR THE DESIGN OF THE PLEASE READ: If you are obtaining this RFQ document electronically from the City s web-site, please email jward@blueash.com or call Judi Ward at 745-8538 and request to be placed on the RFQ holder s list.

More information

STATEMENTS OF QUALIFICATIONS ARE DUE NO LATER THAN 5:00 P.M. FRIDAY, JUNE 23, 2017

STATEMENTS OF QUALIFICATIONS ARE DUE NO LATER THAN 5:00 P.M. FRIDAY, JUNE 23, 2017 RFQ 13-2017-01 REQUEST FOR QUALIFICATIONS FOR A CRITERIA ENGINEER TO PERFORM CERTAIN PROFESSIONAL SERVICES IN THE REPAIR AND/OR REPLACEMENT OF THE LOWER LAKE DAM AND POTENTIAL REPAIRS TO THE UPPER LAKE

More information

ENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project

ENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project VILLAGE OF LISLE REQUEST FOR QUALIFICATIONS ( RFQ ) #1267 ENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project DUE BY: FEBRUARY 5, 2018 @ 11:00

More information

CMU COLORADO MESA UNIVERSITY REQUEST FOR QUALIFICATIONS FOR

CMU COLORADO MESA UNIVERSITY REQUEST FOR QUALIFICATIONS FOR CMU-17-2585 COLORADO MESA UNIVERSITY REQUEST FOR QUALIFICATIONS FOR DESIGN, FABRICATION AND INSTALLATION OF GRAPHICS AND INTERACTIVE VIDEO IN THE COLORADO MESA UNIVERSITY BROWNSON ARENA LOBBY For: Colorado

More information

CONSTRUCTION DOCUMENTS Part 1

CONSTRUCTION DOCUMENTS Part 1 Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

NTA Metropolitan Mass Transit System

NTA Metropolitan Mass Transit System August 23, 2018 To: All Participants Re: Tender No.097/2018 - for Pre-Qualification to Participate in Tenders for the Green Line and Purple Line Addendum No. 1 Addendum no. 1 is issued for inclusion into

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE CAYUCOS SANITARY DISTRICT 200 Ash Avenue P.O. Box 333, Cayucos, California 93430-0333 www.cayucossd.org 805-995-3290 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED

More information

INTERNATIONAL INSTITUTE FOR DEMOCRACY AND ELECTORAL ASSISTANCE TENDER NOTICE

INTERNATIONAL INSTITUTE FOR DEMOCRACY AND ELECTORAL ASSISTANCE TENDER NOTICE INTERNATIONAL INSTITUTE FOR DEMOCRACY AND ELECTORAL ASSISTANCE TENDER NOTICE Tender Reference No: 258-18/102 Assignment Name: Engagement of an Executive Search and Recruitment Agency to select a new Secretary-General

More information

REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES

REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES QUALIFICATION SUBMITTAL DATE: Monday, February 18, 2019 RFQ Number 2019-01 City of McLendon-Chisholm 1371 W. FM 550 McLendon-Chisolm, Texas 75032 972-524-2077

More information

ADDENDUM No. 1 PROGRAM MANAGEMENT CONSTRUCTION MANAGEMENT SERVICES

ADDENDUM No. 1 PROGRAM MANAGEMENT CONSTRUCTION MANAGEMENT SERVICES DDENDUM No. 1 RF NUMBER: RF TITLE: LRT-11-173-PMCM PROGRM MNGEMENT CONSTRUCTION MNGEMENT SERVICES DDENDUM NO: 1 DTE: June 15, 2011 CLRIFICTIONS / CORRECTIONS The following clarifications and/or corrections

More information

Negotiating. Construction. Contracts STANDARD OPERATING PROCEDURES NJSDA NEW JERSEY SCHOOLS DEVELOPMENT AUTHORITY TRENTON, NEW JERSEY

Negotiating. Construction. Contracts STANDARD OPERATING PROCEDURES NJSDA NEW JERSEY SCHOOLS DEVELOPMENT AUTHORITY TRENTON, NEW JERSEY Negotiating Construction STANDARD OPERATING PROCEDURES Contracts NJSDA NEW JERSEY SCHOOLS DEVELOPMENT AUTHORITY TRENTON, NEW JERSEY INTRODUCTION Assembly Bill No. 4336, as amended and approved in August

More information

Student Government Office Renovations Design/Construction Administration Services Code Item 305

Student Government Office Renovations Design/Construction Administration Services Code Item 305 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, NC 28223 Telephone: 704-687-0615 PROJECT: UNC Charlotte Student Government Office

More information

Ipswich Public Schools

Ipswich Public Schools Ipswich Public Schools Executive Search Consultant Services for the position of Superintendent of Schools December 2016 I. RFQ Timeline and Decision to Use a Request for Quotes Time Line Superintendent

More information

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS 1. REQUEST FOR PROPOSALS. Clearwater Public Schools, Ewing Public Schools,

More information

August 31, To Whom It May Concern:

August 31, To Whom It May Concern: August 31, 2017 To Whom It May Concern: The Aerotropolis Atlanta Community Improvement Districts (AACIDs) is soliciting Statements of Qualifications (RFQ) from qualified firm(s) or organization(s) to develop

More information

MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK

MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK DATE ISSUED: January 10, 2018 DEADLINE FOR WRITTEN

More information

ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR. RFQ No. 16P3

ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR. RFQ No. 16P3 ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR RFQ No. 16P3 CHAFFEY COMMUNITY COLLEGE DISTRICT ARCHITECTURAL DESIGN SERVICES MEASURE L PROJECT RANCHO CUCAMONGA, CA July 30, 2015 CHAFFEY

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Village of La Grange Phase II Design Engineering Services for Submission Deadline: No later than 10:00 am on October 19, 2018 Published on: October 5, 2018 on the Village of

More information

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014:

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014: www.dot.state.pa.us Date: December 18, 2014 Subject: Questions and Answers Regarding RFQ Solicitation: CNG Fueling for Transit Agencies Partnership Project SOQ Due Date: No later than 11:00 a.m. Eastern

More information

Metropolitan Washington Airports Authority. Request for Qualifications Information. On-Call Consultant for Construction Claims Analysis Services.

Metropolitan Washington Airports Authority. Request for Qualifications Information. On-Call Consultant for Construction Claims Analysis Services. Request for Qualifications Information On-Call Consultant for Construction Claims Analysis Services For Dulles Corridor Metrorail Project Revised December 2, 2010 Revision Key: Additions Deletions METROPOLITAN

More information

Terminal D South Expansion - Construction Manager-At-Risk (CMAR)

Terminal D South Expansion - Construction Manager-At-Risk (CMAR) DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 3 FOR Terminal D South Expansion - Construction Manager-At-Risk (CMAR) CONTRACT NO. 9500647 August 30, 2018

More information

Allegheny County Sanitary Authority (ALCOSAN)

Allegheny County Sanitary Authority (ALCOSAN) Allegheny County Sanitary Authority (ALCOSAN) REQUEST FOR QUALIFICATIONS for PROFESSIONAL SERVICES WET WEATHER PLANT EXPANSION CONSTRUCTION MANAGEMENT CAPITAL PROJECT NO. S 430 January 2018 1.0 INTRODUCTION

More information

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT The Reno-Tahoe Airport Authority (RTAA) Reno, Nevada, is seeking

More information

MAY 19, 2017 ADDENDUM NO. 3 FOR

MAY 19, 2017 ADDENDUM NO. 3 FOR MAY 19, 2017 ADDENDUM NO. 3 FOR REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT AT-RISK SERVICES FOR O HARE 21 AT O HARE INTERNATIONAL AIRPORT SPECIFICATION NO. 376113 For which Statements

More information

Coordination of Consultants

Coordination of Consultants Coordination of Consultants Ontario Association of Architects Practice Tip PT.27 Version 1.0 May 21, 2012 2012 OAA, all rights reserved. Persons who are not members of the OAA must obtain written permission

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

UAF Combined Heat & Power Replacement (CPHR)

UAF Combined Heat & Power Replacement (CPHR) davis JV UAF Combined Heat & Power Replacement (CPHR) REQUEST FOR BIDS Limited 2015 Mechanical Scope PROPOSALS DUE: THURSDAY JULY 2 ND, 2015 2:00PM LOCAL ALASKA TIME Submit to: Haskell Corporation /Davis

More information

Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER

Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER The University of Arkansas Fayetteville, in accordance with the policies of the Board of Trustees, is soliciting responses

More information

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together This document printed Friday, 04/15/2016 Contracting Opportunity Title:

More information

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts

More information

REQUEST FOR QUALIFICATIONS. FOR THE PROVISION OF LEGAL SERVICES General Counsel. ISSUE DATE: December 11, DUE DATE: December 28, 2017

REQUEST FOR QUALIFICATIONS. FOR THE PROVISION OF LEGAL SERVICES General Counsel. ISSUE DATE: December 11, DUE DATE: December 28, 2017 REQUEST FOR QUALIFICATIONS FOR THE PROVISION OF LEGAL SERVICES General Counsel ISSUE DATE: December 11, 2017 DUE DATE: December 28, 2017 Issued by: Rahway Parking Authority NOTE: In the event an interested

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS AND ENVIRONMENTAL AFFAIRS DEPARTMENT SUITE 209S LOGAN OFFICE CENTER SUITE 209S ONE HARBOR SIDE DRIVE EAST BOSTON MA 02128-2909 REQUEST FOR QUALIFICATIONS L1557-S1,

More information

Request for Qualifications for Architectural Services

Request for Qualifications for Architectural Services Page 1 of 11 Capital Projects Office Request for Qualifications for Architectural Services University of Washington Request for Qualifications ARCHITECTURAL SERVICES FOR Computer Science & Engineering

More information

REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA

REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA GENERAL INFORMATION Greenwood School District 50 is

More information

SOLICITATION SCHEDULE RFP #91286

SOLICITATION SCHEDULE RFP #91286 DATE: June 3, 2015 TO: All Prospective Proposers FROM: Beth Kirk Sr. Buyer, Goods and Non-Technology Services 301-985-7618 RE: RFP 91286 On-Line and On-Site Sales Management for Branded and Promotional

More information

CONSTRUCTION MANAGEMENT SERVICES

CONSTRUCTION MANAGEMENT SERVICES DrAFTDRAFTdd EXHIBIT 1 CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS () SELECTION PROCESS School District of Lee County, Florida TABLE OF CONTENTS 1. INTRODUCTION 1 Lobbying 2 2. REQUEST

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE Memphis Cook Convention Center Renovation City of Memphis, Department of Housing and Community Development

More information

600 - Phase C Intermediate Review Checklist for the Architect- Engineer

600 - Phase C Intermediate Review Checklist for the Architect- Engineer 600 Phase C Intermediate Review Checklist for the Architect Engineer This checklist is to be used by the ArchitectEngineer during Phase C of the Project and shall be included in the Intermediate Review

More information

Chapter 6. Competitive Sealed Bidding: Elements of an Invitation for Bids

Chapter 6. Competitive Sealed Bidding: Elements of an Invitation for Bids Chapter 6. Competitive Sealed Bidding: Elements of an Invitation for Bids Summary This chapter identifies the minimum elements of an invitation for bids when procuring goods or services using the competitive

More information

REQUEST FOR EXPRESSIONS OF INTEREST 5006 EOI DETERRENT PROGRAM FOR SNOW GEESE CONTROL

REQUEST FOR EXPRESSIONS OF INTEREST 5006 EOI DETERRENT PROGRAM FOR SNOW GEESE CONTROL 5006 EOI REQUEST FOR EXPRESSIONS OF INTEREST 5006 EOI DETERRENT PROGRAM FOR SNOW GEESE CONTROL Responses to this Request for Expressions of Interest will be received at the Information Counter, Main Floor,

More information

ADDITIONAL TYPES OF WORK REQUIRED

ADDITIONAL TYPES OF WORK REQUIRED NOTICE TO PROFESSIONAL ENGINEERING CONSULTANTS REQUEST FOR LETTERS OF INTEREST FOR DESIGN CONSULTANT SERVICES FOR THE SUPPLEMENTAL DATA COLLECTION SENSOR AND CCTV DEPLOYMENT PROJECT PROJECT NO. 599-537,

More information

January 22, Table of Contents

January 22, Table of Contents January 22, 2014 PROCEDURES SINGLE SELECTION PROCUREMENT OF DESIGN AND CONSTRUCTION MANAGEMENT SERVICES (Section 30 of Chapter 193 of the Acts of 2004) Table of Contents 1.0 Introduction...3 1.1 Purpose

More information

REQUEST FOR PROPOSAL STRATEGIC PLANNING CONSULTANT. Proposals will be received until. FRIDAY, January 5, :00 p.m. ET

REQUEST FOR PROPOSAL STRATEGIC PLANNING CONSULTANT. Proposals will be received until. FRIDAY, January 5, :00 p.m. ET REQUEST FOR PROPOSAL STRATEGIC PLANNING CONSULTANT Proposals will be received until FRIDAY, January 5, 2018 5:00 p.m. ET This RFP is also available at our website: www.canadian-fairs.ca I. General Information

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

Official-Mail.Tenders@iaea.org ATTACHMENT 1 TO RFQ NO. 29868-AS - Cooling Water Heat Exchangers for Uzbekistan SPECIAL INSTRUCTIONS TO BIDDERS FOR PREPARATION OF THE PROPOSAL These Special Instructions

More information

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY Conventional Project Family A101 2007 (formerly A101 1997) Standard Form of Agreement Between Owner and Contractor where the basis of payment is

More information

Town of York, Maine Request for Qualifications

Town of York, Maine Request for Qualifications Town of York, Maine Request for Qualifications Historic Restoration Contractor The Town of York is accepting Statement of Qualifications from General contractors experienced in historic restoration, for

More information

Sr. Buyer, Goods and Non-Technology Services

Sr. Buyer, Goods and Non-Technology Services DATE: June 17, 2015 TO: FROM: RE: All Prospective Proposers Beth Kirk Sr. Buyer, Goods and Non-Technology Services 301-985-7618 RFP 91286 On-Line and On-Site Sales Management for Branded and Promotional

More information

Pre-Proposal Meeting January 23, #428 01/11/2019 RFQ Indefinite Delivery Contract for Engineering

Pre-Proposal Meeting January 23, #428 01/11/2019 RFQ Indefinite Delivery Contract for Engineering Pre-Proposal Meeting January 23, 2019 #428 01/11/2019 RFQ Indefinite Delivery Contract for Engineering 9 Water Resource Recovery Facilities 89 MGD Permitted Flow 40 MGD ADF 351 Miles of Sewer Interceptors

More information

Lincoln City Visitor and Convention Bureau. City of Lincoln City REQUEST FOR QUALIFICATIONS

Lincoln City Visitor and Convention Bureau. City of Lincoln City REQUEST FOR QUALIFICATIONS Lincoln City Visitor and Convention Bureau City of Lincoln City REQUEST FOR QUALIFICATIONS Visitor Center Concept Development and Designs Architectural Services Lincoln City, Oregon April 20, 2018 RFQ

More information

RFQ. Request for Qualifications Phase One. Renovation of City Owned Homes CITY OF BEREA, OHIO. Mayor Cyril Kleem

RFQ. Request for Qualifications Phase One. Renovation of City Owned Homes CITY OF BEREA, OHIO. Mayor Cyril Kleem RFQ Request for Qualifications Phase One Renovation of City Owned Homes CITY OF BEREA, OHIO Mayor Cyril Kleem City of Berea, Ohio Project: Renovation of City Owned Homes Criteria Engineer: Antonio C. Armagno,

More information

REQUEST FOR PROPOSAL SALT STORAGE BUILDING DESIGN AND CONSTRUCTION. August 18, 2017

REQUEST FOR PROPOSAL SALT STORAGE BUILDING DESIGN AND CONSTRUCTION. August 18, 2017 ADDENDUM NO. 1 PROJECT 00-17-01 REQUEST FOR PROPOSAL SALT STORAGE BUILDING DESIGN AND CONSTRUCTION August 18, 2017 Contractor shall list all addenda by number on the bid form to ensure conformity in the

More information

RFQ /ME - ADDENDUM 3

RFQ /ME - ADDENDUM 3 RFQ 150855/ME - ADDENDUM 3 RFQ Closing: November 3, 2015 at 2:00 PM (Local Time) Page 1 of 5_ RFQ Number: 150855/ME Date: October 26, 2015 RETURN SUBMITTALS AS SHOWN BELOW Copies of submittal required:

More information

RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework. 1. Attachment A: Answers to Questions from Prospective Offerors

RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework. 1. Attachment A: Answers to Questions from Prospective Offerors Procurement Department P.O. Box 2266 Woodbridge, Virginia 22195-2266 Fax (703) 335-7954 September 13, 2016 RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework Addendum #1

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Management Consulting and Auditing Services Pre-Response Conference. ITN No A August 23, :00 AM

Management Consulting and Auditing Services Pre-Response Conference. ITN No A August 23, :00 AM Management Consulting and Auditing Services Pre-Response Conference ITN No. 02-973-000-A August 23, 2012 9:00 AM What is the purpose of this meeting? During this meeting, the Department intends to provide

More information

REQUEST FOR PROPOSALS YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS

REQUEST FOR PROPOSALS YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS REQUEST FOR PROPOSALS GUTHRIE MEMORIAL LIBRARY ENVELOPE REHABILITATION YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS Table of Contents Section 1: Background...... 2 Section 2: Scope of Services... 2 Section

More information

Request for Qualifications Construction Manager at Risk (CMAR) Forsyth County Kaleideum Children s Museum and Science Center

Request for Qualifications Construction Manager at Risk (CMAR) Forsyth County Kaleideum Children s Museum and Science Center Request for Qualifications Construction Manager at Risk (CMAR) Forsyth County Kaleideum Children s Museum and Science Center Forsyth County, a North Carolina Local Government, ( Owner ) is seeking qualifications

More information

REQUEST FOR PROPOSAL. HRIS Human Resources Information Software Fort Morgan, Colorado

REQUEST FOR PROPOSAL. HRIS Human Resources Information Software Fort Morgan, Colorado REQUEST FOR PROPOSAL HRIS Human Resources Information Software Fort Morgan, Colorado October 7, 2014 Michael Boyer Director, Human Resources and Risk Management CITY OF FORT MORGAN P.O. BOX 100 FORT MORGAN,

More information

Department of Public Works Division of Engineering. Nassau County, New York

Department of Public Works Division of Engineering. Nassau County, New York TOWN OF OYSTER BAY Department of Public Works Division of Engineering Nassau County, New York REQUEST FOR PROPOSALS FOR CONSULTANT SERVICES SOLICITATION NO. 2017-12 NOTES: 1. ISSUANCE DATE: Thursday, October

More information

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS 10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS Engineering, Procurement and Construction Management (EPCM) costs for Balance of Plant (BOP) installations seriously

More information