Building Load and Energy Estimates Analysis. Instructor: Dr. Mumma. October 28, Thesis Building Sponsor s: INOVA Fairfax Hospital

Size: px
Start display at page:

Download "Building Load and Energy Estimates Analysis. Instructor: Dr. Mumma. October 28, Thesis Building Sponsor s: INOVA Fairfax Hospital"

Transcription

1 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute David J. Peterson Mechanical Option Mechanical Technical Report #2b The INOVA HEART INSTITUTE AT INOVA Fairfax Hospital, Falls Church, VA. Mechanical Technical Report #2b Building Load and Energy Estimates Analysis Instructor: Dr. Mumma October 28, 2003 Thesis Building Sponsor s: INOVA Fairfax Hospital and Turner Construction 3300 Gallows Road, Falls Church, VA

2 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute Table of Contents 1.0 Executive Summary 2.0 Design Load Estimates 3.0 Annual Energy Analysis Estimates 4.0 References 5.0 Appendix 2

3 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute 1.0 Executive Summary: The purpose of this report is to understand and model the load and energy consumption of the INOVA Heart Institute. The overall size of the new hospital is approximated at 410,000 sq.ft. The hospital is broken down into 3 wings, two of which serve the majority of the hospital and serve as recovery, patient, and general hospital office and recreation spaces. The third wing or CVOR (Cardio- Vascular-Operating-Rooms) serves as the critical care and operation wing. This wing contains a high quantity of supply air from the two 40,000cfm air handling units located in the penthouse above. The combined air handlers feed into one main duct that branches off and serves a 33,055 sq.ft space of the CVOR wing. The high quantity of air is associated with pressurization and other indoor air quality issues of the hospital. The focus of this report will be on the CVOR wing. This report contains the analysis of loads and energy consumption by the space using both a simple hand approach as well as a more derived computer approach. Through hand calculations a value of approximately 120 tons of cooling was obtained for the space. Through computer analysis with Carrier s HAP program a value of approximately 322 tons of cooling was obtained. Referencing the design documents it is shown that the engineers had intended for a value of approximately 360 tons of cooling. Discrepancies in the totaling cooling can be attributed to factors of safeties provided by the design engineer, very simplified hand solar calculations, as well as unforeseen equipment and their associated load. Calculating energy consumption for the building proved to be a more difficult task. The INOVA Heart Institute is an addition to the existing INOVA Fairfax Hospital. On the property there is a remote central plant which provides both steam and chilled water to the existing as well as to the new facilities. Due to restrictions by the owner and hospital, information about the existing chiller and steam plants was unattainable. For the purposes of gauging and approximate total energy consumption by the CVOR wing a chiller as well as a boiler was sized to meet the loads of the space. Through hand calculations a value of 2,435, KW-hrs per year (approximately: 8,309, K-BTU per year) was obtained for the total energy consumption of the space. Through the computer simulation method a value of approximately 21,636,344 K-BTU per year was obtained. Hand calculations differ from computer simulations because they do not take into account heating in general, more specifically the do not include steam humidification, terminal reheats or preheat coils in the air handlers. The total building operation cost was calculated in Hap to be approximately $76,384. This estimate of cost includes contributions from Air system fans, total cooling and heating needed, pumps, lights and electrical equipment. Cost s were based on Virginia Power s GS-3U rate schedule. The INOVA Heart Institute s Air Handler Penthouse is shown in the photo below courtesy of Turner Construction and is due to open in the Summer of INOVA Photo 1: AHU Penthouse Construction, August 12,

4 David Peterson Penn State AE, Mechanical 2.0 Design Load Estimates: INOVA Fairfax Hospital The INOVA Heart Institute Estimating the design cooling load by hand entails a rather tedious look at all the loads present with in the CVOR wing of the INOVA Heart Institute. A detailed break down of all loads and sources can be found in the hand calculated spreadsheets of Appendix A. The load sources present in area of interest include Lights, People, Medical Equipment, Office Equipment, and some typical Kitchen Equipment. 2.1 Analysis By Hand Mechanical Load Data Total Cooling Load Ft 2 /ton Supply Air 2.42 cfm/ft 2 Ventilation Air cfm/ft 2 INOVA Table 1: Hand Analysis Calculation The hand analysis which was done through a series of spread sheets calculated a value of approximately 120 tons of cooling. 2.2 Analysis By Computer Mechanical Load Data Total Cooling Load Ft 2 /ton Supply Air 2.42 cfm/ft 2 Ventilation Air 0.73 cfm/ft 2 INOVA Table 2: Computer Analysis Calculation The computer analysis done through Carrier s Hap program calculated a value of approximately 322 tons of cooling. 2.3 Original By the Designers Mechanical Load Data Total Cooling Load 92 Ft 2 /ton Supply Air 2.42 cfm/ft 2 Ventilation Air cfm/ft 2 INOVA Table 3: Designer s Calculations From the design documents it is evident that the designers intended for the CVOR wing to have approximately 360 tons of cooling. 4

5 David Peterson Penn State AE, Mechanical 2.3 Conclusions INOVA Fairfax Hospital The INOVA Heart Institute Discrepancies in the totaling cooling can be attributed to factors of safeties provided by the design engineer, more exact solar loads, as well as unforeseen equipment and the associated load. The hospital also contains area shell space for future expansion, over sizing of the equipment now (along with air damper control) may be attributed to such future anticipated loads. The hospital is still under construction and only approximations can be made regarding discrepancies in load. 3.0 Annual Energy Analysis Estimates Due to restrictions by the owner and hospital information about the existing chiller and steam plants was unattainable. For the purposes of gauging and approximate total energy consumption by the CVOR wing a chiller as well as a boiler was sized to meet the loads of the space. The chiller that was selected was an Aircooled packaged reciprocating electric chiller that met the design loads as schedule on the drawings (approximately 368 ton of cooling at 715gpm) The boiler that was selected to meet the heating requirements was an electric resistance boiler (approximately: 5512 MBH at 372gpm with an efficiency of approximately 87%). A Remote steam source was selected in the computer simulation for the purposes of humidifying the air in the AHU s. 3.1 Analysis By Hand Mechanical Energy Analysis per Year Chilled Water Pumps 116, KBTU Fans 4,854, KBTU Lights 2,710, KBTU Equipment 1,004, KBTU Total 8,686,510.9 KBTU INOVA Table 4: Hand Analysis Calculation Mechanical Energy Analysis per Year Chilled Water Pumps 94,350 KBTU Fans 4,836,564 KBTU Lights 2,856,093 KBTU Equipment 995,615 KBTU Cooling 2,491,749 KBTU Heating 10,361,974 KBTU Total 21,636,344 KBTU INOVA Table 4: Computer Analysis Calculation The hand analysis only looks at such equipment as the supply and return fans as well as the chilled water pumps. The Computer simulation is more through and includes the previously mention as well as all the heating and cooling aspects associated with the space. Both incorporate all; lighting, equipment, sensible and latent loads within the space. The above tables show the results for both 5

6 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute methods which are relatively close. Extensive energy hand calculations can be viewed in the Appendix B. 3.2 Annual Estimated Cooling Costs Component Annual Cost ($/ft²) Air System Fans 17, Cooling 8, Heating 35, Pumps Cooling Tower Fans HVAC Sub-Total 62, Lights 10, Electric Equipment 3, Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total 13, Grand Total 76, Conditioned Floor Area ft² INOVA Table 5: Annual Computer Generated Costs These values represent the system if it were entirely run on electricity in actuality it may be cheaper to run the systems equipment on gas or other forms of generation and it may be determined down the road provided access is made available that the equipment in the remote central plant is most definitely not electric. Electric driven equipment is not always the cheapest form of operation. But for the purposes of this report it was used to gauge a simple estimate on power consumption. A summary of the computer simulation and associated calculations can be view in Appendix C. 3.3 Electric Energy Rates The following charges were applied to the energy analysis in the previous section. Virginia Electric and Power Company Schedule GS-3U Distribution Service Charges Basic monthly: $ or $ annual Distribution Demand on all KW: $2.12 per KW Competitive Trans. On Peak Demand: $2.897 per KW Competitive Trans. On Peak KWH: $ per KWH INOVA Table 6: Cost Estimate Information 6

7 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute 3.4 Overall System Costs The following mechanical system costs, supply actual values for the all three wings of the hospital combined and they are further broken down into three main costs Mechanical/ Plumbing/Med.Gas (combined), Sprinklers and Electrical. The system cost represented show that the Mechanical overall cost is the most expensive per square foot of the building. This makes sense due to all the specialty equipment needed to maintain safety with in the critical care environment. System's Cost Type Cost Cost/sq.ft. Sprinkler 836, *Mechanical 17,200, Electrical 9,200, Total: 27,236, *(Includes all Mech., Plumbing, and Med. Gas ) INOVA Table 7: System s Cost At the present time due to security concerns the present information regarding the energy analysis was unattainable. Although requests for information concerning the Energy analysis are currently being reviewed and final confirmation should be supplied in the near future. Through conversations with the general contractor and on-site mechanical engineer it is believed that an entire energy analysis was done before the construction of the actual building. At this time the building is approximately 60 percent complete and is due to open in the Fall of Conclusions: The excluding ducting and piping the majority of the mechanical equipment is mainly located in the basement and penthouse floors. The Chiller and Steam Boilers are not located within the building but are on the property and are located in an existing central plant. For the purposes of this analysis and the inability to obtain information on the existing central plant a chiller and hot water boiler were sized to accommodate and gage an estimate on how much energy would be consumed and the overall cost s associated with running the system in CVOR wing. The mechanical systems for the INOVA Heart Institute can be characterized as non-typical and specialized and have higher amount of safety associated with them. Per square foot the mechanical systems make up approximately 21% of the overall cost of the entire building. 7

8 David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute 4.0 References: 1. ASHRAE Standard , Energy Standards for Buildings. 2. Penn State Architectural Engineering Department, Thesis Advisors Mechanical Option. 3. Turner Construction, Construction Drawings, Shop Drawings and Specifications. 4. Virginia Power, Schedule GS-3U /customer/pdf/va/vags3u.pdf 5.0 Appendix : The Appencies are included on my web page below the Mechancial Technical Report 2b 8

9 5.1 Appendix A: Hand Load Estimate Calculations

10 Inputs for the Hand Design Load Calculation Space Conditions Outdoor Air: 4% ASHRAE T (DB): 95 4% ASHRAE T (WB): 78 CVOR (Operating) Spaces: Room Air: T (DB): 65 Supply Air: T (DB): 43.5 Non Operating Spaces: Room Air: T (DB): 75 Supply Air: T (DB): 50.5 Occupant Data Sensible (Btu/hr): 245 Latent (Btu/hr): 205 GYM Sensible (Btu/hr): 295 Latent (Btu/hr): 455 U-Values (Btu/(hr-ft2-F)): Roof: Wall: Windows: 0.35 Window Data (Ft 2 ): Height: 6 Width: 6 Area: 36

11 Floor Analysis of CVOR Wing Space Area SQ. FT. Design SQ FT/ Person Occupant Load Occup Occupant Latent Load # of People Btu/hr Lighting Load 2 1 Special-Storage/Supply Special-Storage/Supply Special-Storage/Supply Special-Storage/Supply Special-Storage/Supply Special-Storage/Supply Corridor ,273 9, Corridor CVOR ,753 8, CVOR ,776 8, Clean Area ,558 12, Prep Area ,524 11, Toilets Toilets Data/Electric Lounge ,621 4, Storage/Supply low Storage/Supply low Special-Storage/Supply ,093 4, Special-Storage/Supply Office Office ,252 3, Office Gym ,115 11, Corridor ,306 8, Toilets Locker ,166 2, Locker ,994 7, Lounge ,650 5, Lounge ,511 6, Classroom ,870 3, Data/Elec Sleeproom Occup Sensible Load Btu/hr General Lights W/ft2 General Lights W Total Lights Btu/hr Equip. W/ft2 Electrical Equipment Load Total Equip W Total Equip. Btu/hr

12 Floor Space Wall Envelope Load Window Envelope Load Roof Envelope Exterior Walls Window Roof Wall Window Roof Wall North South East West Envelope Envelope Area Envelope N (feet) S (feet) E (feet) W (feet) Height Btu/hr Num Area Num Area Num Area Num Area Btu/hr FT 2 Btu/hr 2 1 Storage/Supply Storage/Supply Storage/Supply Storage/Supply Storage/Supply Storage/Supply Corridor Corridor CVOR CVOR Clean Area Prep Area Toilets Toilets Data/Electric Lounge Storage/Supply low Storage/Supply low Storage/Supply Storage/Supply Office Office Office Gym Corridor Toilets Locker Locker Lounge Lounge Classroom Data/Elec Sleeproom

13 Floor Space Occupant Latent Load Btu/hr Occupant Sensible Load Btu/hr Total Lights Btu/hr Total Equip. Btu/hr Wall Envelope Btu/hr Window Envelope Btu/hr Roof Envelope Btu/hr Total Load Btu/hr 2 1 Storage/Supply , Storage/Supply , Storage/Supply , Storage/Supply , Storage/Supply , Storage/Supply , Corridor 8,273 9, , Corridor , CVOR 6,753 8, , CVOR 6,776 8, , Clean Area 10,558 12, , Prep Area 9,524 11, , Toilets , Toilets Data/Electric , Lounge 3,621 4, , Storage/Supply low Storage/Supply low , Storage/Supply 4,093 4, , Storage/Supply , Office , Office 3,252 3, , Office , Gym 17,115 11, , Corridor 7,306 8, , Toilets Locker 2,166 2, , Locker 5,994 7, , Lounge 4,650 5, , Lounge 5,511 6, , Classroom 2,870 3, , Data/Elec , Sleeproom ,597

14 Design Loads Units Occupant Latent Load Occupant Sensible Load Total Lights Total Equip. Wall Envelope Window Envelope Roof Envelope Outdoor Air Load Btu/hr 105, , , ,690 11,285 16,632 10, ,357,059 Ton Total Load Total Envelope Load (Btu/hr): 38,165 Total Conditioned Square Footage: Total Supply Air (CFM) From Designer: 80,000 Total Ventilation Air (CFM) From Designer: 24,000 Overall breakdown of Tonage Occupant Latent Load Occupant Sensible Load 8% 10% Total Cooling Load (ft 2 /ton): Supply Air (cfm/ft 2 ): Ventilation Air (cfm/ft2): Outdoor Air Load 48% Roof Envelope 1% Window Envelope Wall Envelope Total Equip. 5% Total Lights 26% 1% 1%

15 5.2 Appendix B: Hand Energy Estimate Calculations

16 ENERGY INPUTS Square Footage Flow Rates (cfm): Supply Air 61,400 Ventilation Air 18,600 Occupant Data No. of occupants 471 Sensible (Btu/hr): 250 Latent (Btu/hr): 200 Air Conditions Supply Temp (F) 50.5 Space Temp (F) 75 W (gr/lb) 64.6 RH 50% h(btu/lbda) 28.1 Additional Parameters Lighting Load (Btu/hr) 321,733 Equipment Load (Btu/hr) 59,374 Overall Envelope (Btu/hr) 38,044

17 ENERGY LOAD CALCULATION HR Range (gr/lb) HR (gr/lb) BIN DATA DB (F) WB (F) h (BTU/lb) QOAsen (Btu) QOAlat (Btu) Lights (Btu) Equipemnt (Btu) Hrs 135 to to to E to E to E to E E to E E E to E E E E to E E to E E E to E E to E E to E E E to E E E to E E E to E E to E E to E E E E to E E E E to E E E E to E E E E to E E E E to E E E E to E E E E to E E E E to E E E E to E E E to People Sensible (Btu) LOADS People Latent (Btu) DAY QOAlat + PEOPLE LATENT (Btu) Envelope (Btu) TOTAL Btu TOTAL Tons

18 EQUIPMENT INFORMATION Supply Air Flow Rate 61,400 scfm Lights 2 W/sf Tdb 75 F OA Flow Rate 18,600 scfm Equipment 2 W/sf W 64.6 gr/lb Return Air Flow Rate 90,000 scfm Overall UA Btu/(hr F) RH 50% No. People 1200 h 28.1 Btu/(lbda) Satemp 55 F (DB) AHU 11 - FAN LOAD-SUPPLY FAN (40,000 CFM) AHU 12 - FAN LOAD-SUPPLY FAN (40,000 CFM) P inwg 8.5 Fan BHP: 68.4 BHP P inwg 8.5 Fan BHP: 68.4 BHP fan eff 0.75 Fan kw: kw fan eff 0.75 Fan kw: kw motor eff 0.95 motor eff 0.95 CFM 40,000 CFM 40,000 AHU 11 - FAN LOAD-RETURN FAN (32,000 CFM) AHU 12 - FAN LOAD-RETURN FAN (32,000 CFM) P inwg 3 Fan BHP: 40.6 BHP P inwg 3 Fan BHP: 40.6 BHP fan eff 0.75 Fan kw: kw fan eff 0.75 Fan kw: kw motor eff 0.95 motor eff 0.95 CFM 32,000 CFM 32,000 CHILLED WATER PUMPS for secondary system #1 Recirculation cooling coil pumps for AHU 11 GPM 120 Pump BHP: BHP GPM 130 Pump BHP: BHP head (ft) 45 Pump kw: kw head (ft) 20 Pump kw: kw pump eff 0.81 pump eff 0.81 motor eff 0.95 motor eff 0.95 SG 1 SG 1 CHILLED WATER PUMPS for secondary system #2 Recirculation cooling coil pumps for AHU 12 GPM 120 Pump BHP: BHP GPM 130 Pump BHP: BHP head (ft) 45 Pump kw: kw head (ft) 20 Pump kw: kw pump eff 0.81 pump eff 0.81 motor eff 0.95 motor eff 0.95 SG 1 SG 1

19 Evaluation of no Economizer system HR Range (gr/lb) HR (gr/lb) BIN DATA DB (F) WB (F) h (BTU/lb) LOAD FANS PUMPS CHILLED WATER TOTAL FANS PUMPS Tons (kw hr) (kw hr) Hrs 135 to to to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to , to Totals 332,

20 TOTALS Using Central Chilled Water Plant Data KWh/year Chilled Water Pumps 34, Supply/Return Fans 1,422, Lights 826, Equipment 152, Total 2,435,436.23

21 5.3 Appendix C: HAP Analysis

22 Air System Sizing Summary for Combined AHU (2) Project Name: INOVA HEART HAP 10/29/2003 Prepared by: psuae 07:49PM Air System Information Air System Name Combined AHU (2) Equipment Class CW AHU Air System Type CAV/RH Number of zones 2 Floor Area ft² Sizing Calculation Information Zone and Space Sizing Method: Zone CFM Sum of space airflow rates Space CFM Individual peak space loads Calculation Months Sizing Data Jan to Dec Calculated Central Cooling Coil Sizing Data Total coil load Tons Total coil load MBH Sensible coil load MBH Coil CFM at Jul CFM Max block CFM CFM Sum of peak zone CFM CFM Sensible heat ratio ft²/ton BTU/(hr-ft²) Water 15.0 F rise gpm Load occurs at Jul 1500 OA DB / WB 95.0 / 76.0 F Entering DB / WB 78.1 / 62.7 F Leaving DB / WB 46.5 / 44.3 F Coil ADP 38.6 F Bypass Factor Resulting RH 40 % Design supply temp F Zone T-stat Check 2 of 2 OK Max zone temperature deviation 0.0 F Preheat Coil Sizing Data No heating coil loads occurred during this calculation. Humidifier Sizing Data Max steam flow at Des Htg lb/hr Airflow Rate CFM Air mass flow lb/hr Moisture gain lb/lb Supply Fan Sizing Data Actual max CFM CFM Standard CFM CFM Actual max CFM/ft² 2.42 CFM/ft² Fan motor BHP BHP Fan motor kw kw Return Fan Sizing Data Actual max CFM CFM Standard CFM CFM Actual max CFM/ft² 2.42 CFM/ft² Fan motor BHP BHP Fan motor kw kw Outdoor Ventilation Air Data Design airflow CFM CFM CFM/ft² 0.73 CFM/ft² CFM/person CFM/person Hourly Analysis Program v.4.1 Page 1 of 1

23 Annual Cost Summary INOVA HEART HAP 10/29/2003 psuae 06:02PM Table 1. Annual Costs INOVA BLDG Component Air System Fans 17,380 Cooling 8,893 Heating 35,932 Pumps 339 Cooling Tower Fans 0 HVAC Sub-Total 62,544 Lights 10,263 Electric Equipment 3,578 Misc. Electric 0 Misc. Fuel Use 0 Non-HVAC Sub-Total 13,841 Grand Total 76,384 Table 2. Annual Cost per Unit Floor Area INOVA BLDG Component ($/ft²) Air System Fans Cooling Heating Pumps Cooling Tower Fans HVAC Sub-Total Lights Electric Equipment Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total Grand Total Gross Floor Area (ft²) Conditioned Floor Area (ft²) Note: Values in this table are calculated using the Gross Floor Area. Table 3. Component Cost as a Percentage of Total Cost INOVA BLDG Component ( % ) Air System Fans 22.8 Cooling 11.6 Heating 47.0 Pumps 0.4 Cooling Tower Fans 0.0 HVAC Sub-Total 81.9 Lights 13.4 Electric Equipment 4.7 Misc. Electric 0.0 Misc. Fuel Use 0.0 Non-HVAC Sub-Total 18.1 Grand Total Hourly Analysis Program v.4.1 Page 1 of 1

24 Billing Details - Electric - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 1. Component Charges Customer Billing Period Energy Charges Demand Charges Charges Taxes Total Charge Jan 1,270 3,596 1, ,304 Feb 1,102 3,588 1, ,127 Mar 1,164 3,748 1, ,349 Apr 1,229 3,723 1, ,390 May 1,247 3,852 1, ,536 Jun 966 3,914 1, ,317 Jul 1,081 3,957 1, ,475 Aug 978 3,993 1, ,408 Sep 1,013 3,967 1, ,417 Oct 1,300 3,738 1, ,475 Nov 1,120 3,706 1, ,263 Dec 1,278 3,606 1, ,322 Totals 13,746 45,387 17, , Totals Billing Period Total Charges Total Consumption (kwh) Avg Price ($/kwh) Jan 6, , Feb 6, , Mar 6, , Apr 6, , May 6, , Jun 6, , Jul 6, , Aug 6, , Sep 6, , Oct 6, , Nov 6, , Dec 6, , Totals 76,384 6,233, Consumption Totals Billing Period Peak (kwh) Mid-Peak (kwh) Normal Peak (kwh) Off-Peak (kwh) Overall (kwh) Jan 223, , ,936 Feb 194, , ,039 Mar 204, , ,145 Apr 216, , ,418 May 219, , ,008 Jun 170, , ,423 Jul 190, , ,782 Aug 172, , ,980 Sep 178, , ,716 Oct 228, , ,042 Nov 197, , ,395 Dec 224, , ,246 Totals 2,420, ,812,997 6,233,128 Hourly Analysis Program v.4.1 Page 1 of 2

25 Billing Details - Electric - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 4. Billing Demands Billing Period Peak (kw) Mid-Peak (kw) Normal Peak (kw) Off-Peak (kw) Overall (kw) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Maximum Demands Billing Period Peak (kw) Mid-Peak (kw) Normal Peak (kw) Off-Peak (kw) Overall (kw) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Time Of Maximum Demands Billing Period Peak (m/d/h) Mid-Peak (m/d/h) Normal Peak (m/d/h) Off-Peak (m/d/h) Overall (m/d/h) Jan 1/9/0900 n/a n/a 1/9/0100 1/9/0900 Feb 2/3/0900 n/a n/a 2/2/1500 2/2/1500 Mar 3/5/0700 n/a n/a 3/5/0600 3/5/0700 Apr 4/14/1500 n/a n/a 4/6/1600 4/6/1600 May 5/13/1400 n/a n/a 5/31/1900 5/31/1900 Jun 6/24/1200 n/a n/a 6/30/0900 6/24/1200 Jul 7/3/1300 n/a n/a 7/26/1500 7/3/1300 Aug 8/18/1200 n/a n/a 8/17/1300 8/17/1300 Sep 9/1/1200 n/a n/a 9/1/0900 9/1/1200 Oct 10/14/1600 n/a n/a 10/18/ /18/0100 Nov 11/28/0800 n/a n/a 11/28/ /28/0800 Dec 12/5/0800 n/a n/a 12/5/ /5/0600 Hourly Analysis Program v.4.1 Page 2 of 2

26 Monthly Energy Use by Energy Type - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 1. HVAC Energy Use Month Electric (kwh) Natural Gas (na) Fuel Oil (na) Propane (na) Remote HW (na) Remote Steam () Remote CW (na) Jan 420, ,733 0 Feb 379, ,700 0 Mar 422, ,881 0 Apr 411, ,126 0 May 432, ,366 0 Jun 430, Jul 455, Aug 451, Sep 432, Oct 432, ,605 0 Nov 412, ,788 0 Dec 423, ,710 0 Totals 5,104, , Non-HVAC Energy Use Electric Natural Gas Fuel Oil Propane Remote HW Remote Steam Month (kwh) (na) (na) (na) (na) () Jan 95, Feb 86, Mar 95, Apr 92, May 95, Jun 92, Jul 95, Aug 95, Sep 92, Oct 95, Nov 92, Dec 95, Totals 1,128, Hourly Analysis Program v.4.1 Page 1 of 1

27 Monthly Energy Use by Component - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 1. Monthly Energy Use by System Component Component Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Air System Fans (kwh) Cooling Electric (kwh) Natural Gas (na) Fuel Oil (na) Propane (na) Remote HW (na) Remote Steam () Remote CW (na) Heating Electric (kwh) Natural Gas (na) Fuel Oil (na) Propane (na) Remote HW (na) Remote Steam () Pumps (kwh) Clg. Tower Fans (kwh) Lighting (kwh) Electric Eqpt. (kwh) Misc. Electric (kwh) Misc. Fuel Natural Gas (na) Propane (na) Remote HW (na) Remote Steam () Hourly Analysis Program v.4.1 Page 1 of 1

28 Monthly Component Costs - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM Cost Air System Fans Cooling Heating Pumps Lights Electric Equipment Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month 1. HVAC Component Costs Air System Fans Cooling Heating Pumps Cooling Towers HVAC Total Month January 1, , ,133 February 1, , ,990 March 1, , ,175 April 1, , ,215 May 1, , ,349 June 1, , ,197 July 1,413 1,138 2, ,351 August 1,411 1,072 2, ,287 September 1, , ,285 October 1, , ,299 November 1, , ,113 December 1, , ,155 Total 17,380 8,893 35, , Non-HVAC Component Costs Month Lights Electric Equipment Misc. Electric Misc. Fuel Use Non-HVAC Total Grand Total January ,171 6,304 February ,139 6,129 March ,175 6,350 April ,175 6,390 May ,187 6,536 June ,120 6,317 July ,125 6,476 August ,123 6,410 September ,133 6,418 October ,176 6,475 November ,150 6,263 December ,167 6,322 Total 10,263 3, ,841 76,384 Hourly Analysis Program v.4.1 Page 1 of 1

29 Energy Budget by Energy Source - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 1. Annual Coil Loads Load Component (kbtu) (kbtu/ft²) Cooling Coil Loads 17,990, Heating Coil Loads 9,069, Grand Total 27,059, Energy Consumption by Energy Source Site Energy Site Energy Source Energy Source Energy Component (kbtu) (kbtu/ft²) (kbtu) (kbtu/ft²) HVAC Components Electric 17,415, ,198, Natural Gas Fuel Oil Propane Remote Hot Water Remote Steam 368, , Remote Chilled Water HVAC Sub-Total 17,784, ,567, Non-HVAC Components Electric 3,851, ,756, Natural Gas Fuel Oil Propane Remote Hot Water Remote Steam Non-HVAC Sub-Total 3,851, ,756, Grand Total 21,636, ,324, Notes: 1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads. 2. 'Heating Coil Loads' is the sum of all air system heating coil loads. 3. Site Energy is the actual energy consumed. 4. Source Energy is the site energy divided by the electric generating efficiency (28.0%). 5. Source Energy for fuels equals the site energy value. 6. Energy per unit floor area is based on the gross building floor area. Gross Floor Area ft² Conditioned Floor Area ft² Hourly Analysis Program v.4.1 Page 1 of 1

30 Energy Budget by System Component - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM 1. Annual Coil Loads Load Component (kbtu) (kbtu/ft²) Cooling Coil Loads 17,990, Heating Coil Loads 9,069, Grand Total 27,059, Energy Consumption by System Component Site Energy Site Energy Source Energy Source Energy Component (kbtu) (kbtu/ft²) (kbtu) (kbtu/ft²) Air System Fans 4,836, ,273, Cooling 2,491, ,899, Heating 10,361, ,058, Pumps 94, , Cooling Towers HVAC Sub-Total 17,784, ,567, Lights 2,856, ,200, Electric Equipment 995, ,555, Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total 3,851, ,756, Grand Total 21,636, ,324, Notes: 1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads. 2. 'Heating Coil Loads' is the sum of all air system heating coil loads. 3. Site Energy is the actual energy consumed. 4. Source Energy is the site energy divided by the electric generating efficiency (28.0%). 5. Source Energy for fuels equals the site energy value. 6. Energy per unit floor area is based on the gross building floor area. Gross Floor Area ft² Conditioned Floor Area ft² Hourly Analysis Program v.4.1 Page 1 of 1

31 Annual HVAC & Non-HVAC Cost Totals - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM HVAC 81.9% 18.1% Non-HVAC 1. Annual Costs Annual Cost Percent of Total Component ($/yr) ($/ft²) (%) HVAC 62, Non-HVAC 13, Grand Total 76, Note: Cost per unit floor area is based on the gross building floor area. Gross Floor Area ft² Conditioned Floor Area ft² Hourly Analysis Program v.4.1 Page 1 of 1

32 Annual Energy Costs - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM HVAC Electric 81.9% 18.1% Non-HVAC Electric 1. Annual Costs Annual Cost Percent of Total Component ($/yr) ($/ft²) (%) HVAC Components Electric 62, Natural Gas Fuel Oil Propane Remote Hot Water Remote Steam Remote Chilled Water HVAC Sub-Total 62, Non-HVAC Components Electric 13, Natural Gas Fuel Oil Propane Remote Hot Water Remote Steam Non-HVAC Sub-Total 13, Grand Total 76, Note: Cost per unit floor area is based on the gross building floor area. Gross Floor Area ft² Conditioned Floor Area ft² Hourly Analysis Program v.4.1 Page 1 of 1

33 Annual Component Costs - INOVA BLDG INOVA HEART HAP 10/29/2003 psuae 06:02PM Cooling 11.6% 22.8% Air System Fans 4.7% Electric Equipment Heating 47.0% 13.4% Lights 0.4% Pumps 1. Annual Costs Annual Cost Percent of Total Component ($/ft²) (%) Air System Fans 17, Cooling 8, Heating 35, Pumps Cooling Tower Fans HVAC Sub-Total 62, Lights 10, Electric Equipment 3, Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total 13, Grand Total 76, Note: Cost per unit floor area is based on the gross building floor area. Gross Floor Area ft² Conditioned Floor Area ft² Hourly Analysis Program v.4.1 Page 1 of 1

34 Annual Energy and Emissions Summary INOVA HEART HAP 10/29/2003 psuae 06:02PM Table 1. Annual Costs INOVA BLDG Component HVAC Components Electric 62,543 Natural Gas 0 Fuel Oil 0 Propane 0 Remote HW 0 Remote Steam 0 Remote CW 0 HVAC Sub-Total 62,543 Non-HVAC Components Electric 13,841 Natural Gas 0 Fuel Oil 0 Propane 0 Remote HW 0 Remote Steam 0 Non-HVAC Sub-Total 13,841 Grand Total 76,384 Table 2. Annual Energy Consumption Component INOVA BLDG HVAC Components Electric (kwh) 5,104,236 Natural Gas (na) 0 Fuel Oil (na) 0 Propane (na) 0 Remote HW (na) 0 Remote Steam () 368,910 Remote CW (na) 0 Non-HVAC Components Electric (kwh) 1,128,899 Natural Gas (na) 0 Fuel Oil (na) 0 Propane (na) 0 Remote HW (na) 0 Remote Steam () 0 Totals Electric (kwh) 6,233,135 Natural Gas (na) 0 Fuel Oil (na) 0 Propane (na) 0 Remote HW (na) 0 Remote Steam () 368,910 Remote CW (na) 0 Hourly Analysis Program v.4.1 Page 1 of 3

35 Annual Energy and Emissions Summary INOVA HEART HAP 10/29/2003 psuae 06:02PM Table 3. Annual Emissions Component INOVA BLDG CO2 (lb) 0 SO2 (kg) 0 NOx (kg) 0 Table 4. Annual Cost per Unit Floor Area INOVA BLDG Component ($/ft²) HVAC Components Electric Natural Gas Fuel Oil Propane Remote HW Remote Steam Remote CW HVAC Sub-Total Non-HVAC Components Electric Natural Gas Fuel Oil Propane Remote HW Remote Steam Non-HVAC Sub-Total Grand Total Gross Floor Area (ft²) Conditioned Floor Area (ft²) Note: Values in this table are calculated using the Gross Floor Area. Hourly Analysis Program v.4.1 Page 2 of 3

36 Annual Energy and Emissions Summary INOVA HEART HAP 10/29/2003 psuae 06:02PM Table 5. Component Cost as a Percentage of Total Cost INOVA BLDG Component ( % ) HVAC Components Electric 81.9 Natural Gas 0.0 Fuel Oil 0.0 Propane 0.0 Remote HW 0.0 Remote Steam 0.0 Remote CW 0.0 HVAC Sub-Total 81.9 Non-HVAC Components Electric 18.1 Natural Gas 0.0 Fuel Oil 0.0 Propane 0.0 Remote HW 0.0 Remote Steam 0.0 Non-HVAC Sub-Total 18.1 Grand Total Hourly Analysis Program v.4.1 Page 3 of 3

Sample Reports. for. HAP v4.80 Example Problem

Sample Reports. for. HAP v4.80 Example Problem Sample Reports for HAP v4.80 Example Problem October, 2013 Carrier Software Systems Copyright 2013 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using the

More information

Sample Reports. for. HAP v4.90 Example Problem

Sample Reports. for. HAP v4.90 Example Problem Sample Reports for HAP v4.90 Example Problem December, 2014 Carrier Software Systems Copyright 2014 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using

More information

COOLING COIL (35% ETHYLENE GLYCOL)

COOLING COIL (35% ETHYLENE GLYCOL) APPENDIX Contents A1.1 Existing Mechanical Equipment Schedules A1.2 Existing Mechanical System Schematic Drawings A2. Building Design Loads, Energy Loads and Cost Data Tables A3. Standard 62n-2001 Ventilation

More information

Building and Plant Energy Analysis Report. Instructor: Dr. Freihaut. October 6, Thesis Building Sponsor s: INOVA Fairfax Hospital

Building and Plant Energy Analysis Report. Instructor: Dr. Freihaut. October 6, Thesis Building Sponsor s: INOVA Fairfax Hospital David J. Peterson Mechanical Option Mechanical Technical Report #2a The INOVA HEART INSTITUTE AT, Falls Church, VA. Mechanical Technical Report #2a Building and Plant Energy Analysis Report Instructor:

More information

Ministerio Público Fiscal de la Ciudad de Buenos Aires Fiscalía General Departamento de Infraestructura y Apoyo Operativo

Ministerio Público Fiscal de la Ciudad de Buenos Aires Fiscalía General Departamento de Infraestructura y Apoyo Operativo Air System Design Load Summary for Zona 1 Project Name: Av. Cabildo 3076, 4 piso 04/05/2011 DESIGN COOLING DESIGN HEATING COOLING DATA AT Feb 1500 HEATING DATA AT DES HTG COOLING OA DB / WB 34.9 C / 23.8

More information

Technical Assignment 2 Building and Plant Energy Analysis

Technical Assignment 2 Building and Plant Energy Analysis Technical Assignment 2 Building and Plant Energy Analysis Des Places Residence Hall Duquesne University Pittsburgh, PA Peter Edwards Advisor: James Freihaut October 4, 2010 Table of Contents Executive

More information

Coppin State University Physical Education Complex - Technical Report 2

Coppin State University Physical Education Complex - Technical Report 2 Coppin State University Physical Education Complex - Technical Report 2 Building and Plant Energy Analysis Report Kaylee M Damico Advisor: Dr. Jelena Srebric Location: Baltimore, MD Table of Contents Contents

More information

Hourly Analysis Program v.4.1 Page 1 of 1

Hourly Analysis Program v.4.1 Page 1 of 1 Air System Design Load Summary for Zona 6 DESIGN COOLING DESIGN HEATING COOLING DATA AT Feb 1600 HEATING DATA AT DES HTG COOLING OA DB / WB 34.5 C / 23.7 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent

More information

Hourly Analysis Program v.4.1 Page 1 of 1

Hourly Analysis Program v.4.1 Page 1 of 1 Air System Design Load Summary for Zona 11 DESIGN COOLING DESIGN HEATING COOLING DATA AT Dec 1700 HEATING DATA AT DES HTG COOLING OA DB / WB 33.1 C / 23.5 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible

More information

Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN. Mechanical Appendix

Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN. Mechanical Appendix Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN Mechanical Appendix 131 Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN Wall System Summary For Happ Analysis Ceiling Systems Ceiling

More information

Hourly Analysis Program v.4.1 Page 1 of 1

Hourly Analysis Program v.4.1 Page 1 of 1 Air System Design Load Summary for Zona 3 Project Name: Av. Cabildo 3067, 4 piso 02/13/2011 DESIGN COOLING DESIGN HEATING COOLING DATA AT Feb 1500 HEATING DATA AT DES HTG COOLING OA DB / WB 34.9 C / 23.8

More information

Project Name: Example Building OFPC Project No.: 12345

Project Name: Example Building OFPC Project No.: 12345 Energy Impact Statement Project Name: Example Building OFPC Project : 12345 Building Description and Assumptions: The design professional shall provide a brief narrative describing various building related

More information

Hourly Analysis Program v.4.1 Page 1 of 1

Hourly Analysis Program v.4.1 Page 1 of 1 Air System Design Load Summary for Zona 9 DESIGN COOLING DESIGN HEATING COOLING DATA AT Jan 1400 HEATING DATA AT DES HTG COOLING OA DB / WB 34.5 C / 23.7 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent

More information

Hourly Analysis Program v.4.1 Page 1 of 1

Hourly Analysis Program v.4.1 Page 1 of 1 Air System Design Load Summary for Zona 8 DESIGN COOLING DESIGN HEATING COOLING DATA AT Dec 1700 HEATING DATA AT DES HTG COOLING OA DB / WB 33.1 C / 23.5 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent

More information

Mechanical Tech Report 2

Mechanical Tech Report 2 Mechanical Tech Report 2 Design Load Estimation and Energy Analysis M Resort Spa and Casino Tom M. Chirdon Faculty Advisor; William P. Bahnfleth October 24, 2008 Table of Contents 1.0 Executive summary

More information

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load. Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems

More information

Acknowledgements 4. Executive Summary 5

Acknowledgements 4. Executive Summary 5 Table of Contents Acknowledgements 4 Executive Summary 5 Building Overview.. 6 Building Summary.. 6 Site. 6 Evaluation of Existing Mechanical System. 7 Mechanical System Overview 7 Design Objective 7 Outdoor

More information

Freetown Elementary School

Freetown Elementary School Building and Plant Energy Analysis Technical Report 2 Freetown Elementary School Glen Burnie, MD Matthew R. Buda The Pennsylvania State University Architectural Engineering Mechanical Option Advisor: Dr.

More information

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

Energy 10/19/2011. Inc. New. Castle, DEE. Image. By: Skanska

Energy 10/19/2011. Inc. New. Castle, DEE. Image. By: Skanska Technical Report Two Building, Plant Energy and Emission Analysis Report 10/19/ New Castle Center for Delaware Hospice, Inc. New Castle, DEE Image By: Skanska Pennn State University Architectural Engineering

More information

NASA Langley Research Center Administration Office Building One Hampton, VA TECHNICAL REPORT 2. Building and Plant Energy Analysis Report

NASA Langley Research Center Administration Office Building One Hampton, VA TECHNICAL REPORT 2. Building and Plant Energy Analysis Report NASA Langley Research Center Administration Office Building One Hampton, VA TECHNICAL REPORT 2 Building and Plant Energy Analysis Report Valerie Miller Mechanical Dr. Freihaut 10/06/2014 TABLE OF CONTENTS

More information

Technical Report Three

Technical Report Three Technical Report Three Mechanical System Existing Conditions Evaluation Prepared by: Timothy Berteotti Prepared for: Date: November 16, 2011 Table of Contents Executive Summary...3 Design Objectives...3

More information

Technical Assignment 2: Building and Plant Energy Analysis Report. Jason Jones Mechanical Option Multipurpose Athletic Center West Long Branch, NJ

Technical Assignment 2: Building and Plant Energy Analysis Report. Jason Jones Mechanical Option Multipurpose Athletic Center West Long Branch, NJ Technical Assignment 2: Building and Plant Energy Analysis Report Jason Jones Multipurpose Athletic Center West Long Branch, NJ October 27, 2004 Table of Contents Table of Contents 1 Executive Summary

More information

Technical Report Two: Building and Plant Energy Analysis Report

Technical Report Two: Building and Plant Energy Analysis Report The American Swedish Institute Minneapolis, MN Technical Report Two: Building and Plant Energy Analysis Report Name: Option: Mechanical Advisor: Stephen Treado Date: 10.19.11 Table of Contents Executive

More information

SURNA Grow Facility: Systems Comparison - IEA

SURNA Grow Facility: Systems Comparison - IEA SURNA Grow Facility: Systems Comparison - IEA May 2016 SURNA Grow Facility This analysis provides the projected energy and associated cost comparison between the Surna proposed facility in comparison to

More information

Reed Berinato Mechanical Option. Building and Plant Energy Analysis Report October 27, Contents

Reed Berinato Mechanical Option. Building and Plant Energy Analysis Report October 27, Contents Contents Executive Summary... 3 LEED Green Building Rating Discussion... 4 ASHRAE Standard 90.1-1999... 5 Introduction to ASHRAE Standard 90.1-1999... 5 Envelope Compliance... 5 Lighting Compliance...

More information

Technical Report 2. Bellevue Ambulatory Care Pavilion New York, NY. Building and Plant Energy Analysis

Technical Report 2. Bellevue Ambulatory Care Pavilion New York, NY. Building and Plant Energy Analysis Technical Report 2 Building and Plant Energy Analysis Bellevue Ambulatory Care Pavilion New York, NY Prepared for: Dr. Jelena Srebric, PhD Department of Architectural Engineering The Pennsylvania State

More information

Mechanical Project Proposal

Mechanical Project Proposal Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18

More information

Condenser Water Heat Recovery"

Condenser Water Heat Recovery PLEASE MUTE CELL PHONES Condenser Water Heat Recovery" Julian de Bullet ASHRAE Distinguished Lecturer Director of Industry Relations McQuay International 703-395-5054 1 What Is Sustainability? sustainable

More information

Walter Reed National Military Medical Center Bethesda, MD

Walter Reed National Military Medical Center Bethesda, MD Walter Reed National Military Medical Center Bethesda, MD Technical Report Two: Building and Central Plant Energy Analysis Prepared For: Dr. James D. Freihaut Prepared By: Justin Herzing Date: 10/28/09

More information

SHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4

SHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4 Table of Contents 1 Executive Summary... 1 2 Building Summary 3 3 Existing Mechanical System. 4 4 Mechanical Design Objectives..... 4 5 Mechanical System Evaluation. 5 5.1 Air Distribution System Evaluation....

More information

The Mirenda Center for Sports, Spirituality, and Character Development

The Mirenda Center for Sports, Spirituality, and Character Development prepared by: Zachary Heilman MECHANICAL OPTION prepared for: James Freihaut, PhD Technical Report 2:() Due Date: October 27, 2010 The Mirenda Center for Sports, Spirituality, and Character Development

More information

University of Pennsylvania Pre K-8 th Grade School. James W. Meacham. Philadelphia, Pennsylvania. Construction Management Spring 2003 Senior Thesis

University of Pennsylvania Pre K-8 th Grade School. James W. Meacham. Philadelphia, Pennsylvania. Construction Management Spring 2003 Senior Thesis Outline Unique Aspects & Existing Conditions Thesis Approach Four Mechanical Redesigns Recommended Design issues 3D CAD & Mechanical Contractors Research Unique Aspects Educational Forces Involved University

More information

Analysis of the Energy Savings Potential in K-5 Schools in Hot and Humid Climates. Jeff S. Haberl, Ph.D., P.E.

Analysis of the Energy Savings Potential in K-5 Schools in Hot and Humid Climates. Jeff S. Haberl, Ph.D., P.E. Analysis of the Energy Savings Potential in K-5 Schools in Hot and Humid Climates Piljae Im Graduate Student Jeff S. Haberl, Ph.D., P.E. Professor Energy Systems Laboratory Texas Engineering Experiment

More information

Presentation Outline. Project Information & Background. Project Information & Background. Project Team. Boston, Massachusetts

Presentation Outline. Project Information & Background. Project Information & Background. Project Team. Boston, Massachusetts Project Team Owner Tufts Boston, Massachusetts Boston, Massachusetts Tufts $65 Million 8, sqft. Project Schedule Began in 995 Delayed from 997-2 Completed in 23 Architectural Firm Architectural Lead Architect

More information

AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries

AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER MICHAEL HALLENBECK, PE, CEM Southland Industries BRAC 133 OVERVIEW PROJECT OVERVIEW FAN POWERED INDUCTION UNIT CENTRAL UTILITY

More information

EMD SERONO RESEARCH CENTER EXISTING

EMD SERONO RESEARCH CENTER EXISTING EMD SERONO RESEARCH CENTER EXISTING BILLERICA, MA SHIYUN (SHARON) CHEN MECHANICAL AE SENIOR THESIS Building System Dedicated Outdoor Air System/ Systems Breadth Building Design Team Building: EMD Serono

More information

Water Bottling Facility

Water Bottling Facility TECHNICAL REPORT 2 Water Bottling Facility Mid-Atlantic, US Building and Plant Energy Analysis Report The Pennsylvania State University Author: Justyne Neborak Architectural Engineering Advisor: Dr. William

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

PV Generation Potential 17.1 kbtu/ft2/yr 15.4

PV Generation Potential 17.1 kbtu/ft2/yr 15.4 TOWNHOME PROTOTYPE HIGH PERFORMANCE 60 kbtu/sf/yr 50 kbtu/sf/yr 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 54.4 Baseline 21.8 kbtu/ 2/yr 15 MMBtu 12 MMBtu 9 MMBtu 6 MMBtu 3 MMBtu

More information

Technical Report 2. Building and Plant Energy & Emissions Analysis. Morton Hospital Expansion

Technical Report 2. Building and Plant Energy & Emissions Analysis. Morton Hospital Expansion Technical Report 2 Building and Plant Energy & Emissions Analysis Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth October 8, 214 Millett Technical Report

More information

Grunenwald Science and Technology Building

Grunenwald Science and Technology Building Grunenwald Science and Technology Building Clarion University- Clarion, PA AE 482 Mechanical Project Proposal: Proposal for Alternative Designs Shane Helm The Pennsylvania State University Architectural

More information

Existing Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne

Existing Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne Existing Building Cx: Processes & Results A Cultural Journey Barry Abramson Senior Vice President Servidyne AIA Quality Assurance Learning Objectives 1. Define the key steps in the process of retrocommissioning

More information

OSU Richardson and Peavy Hall Energy Study: Energy Conservation Measure Analysis. January 25, 2012 {Revised April 30, 2012}

OSU Richardson and Peavy Hall Energy Study: Energy Conservation Measure Analysis. January 25, 2012 {Revised April 30, 2012} OSU Richardson and Peavy Hall Study: Conservation Measure Analysis January 25, 2012 OSU Richardson and Peavy Hall Study: Conservation Measure Analysis CONTENTS 1.0 Executive Summary... 1 2.0 Building

More information

Indiana University Glick Eye Institute. LEED Measurement & Verification Plan

Indiana University Glick Eye Institute. LEED Measurement & Verification Plan Indiana University Glick Eye Institute LEED Measurement & Verification Plan April 10, 2012 1 Table of Contents General Introduction... 3 Facility Description... 4 M&V Objectives... 4 M&V Approach/Option...

More information

The Mirenda Center for Sports, Spirituality, and Character Development

The Mirenda Center for Sports, Spirituality, and Character Development prepared by: Zachary Heilman MECHANICAL OPTION prepared for: James Freihaut, PhD Technical Report 3: (Mechanical Systems Existing Conditions Evaluation) Due Date: November 29, 2010 The Mirenda Center for

More information

Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation

Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation 2900 Fairview Park Drive, Prepared By: Charles Haack Mechancial Option November 21, 2008 Prepared For: Dr. William P.

More information

Mechanical Systems Proposal

Mechanical Systems Proposal Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December

More information

Laboratory Building Energy Analysis

Laboratory Building Energy Analysis Laboratory Building Energy Analysis Course No: M4-11 Credit: 4 PDH Steven Liescheidt, P.E., CCS, CCPR Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 198 P: (877) 322-58

More information

ASHRAE. Wxá zç Performance Innovation Experience. Why Geothermal HVAC Systems Fill The Bill. Kirk Mescher, PE P PE. Education.

ASHRAE. Wxá zç Performance Innovation Experience. Why Geothermal HVAC Systems Fill The Bill. Kirk Mescher, PE P PE. Education. ASHRAE AEDG K-12K Why Geothermal HVAC Systems Fill The Bill Kirk Mescher, PE Education Wxá zç Performance Innovation Experience ENGINEERING Bright Solutions in Engineering P PE 1 Simply Efficient 1 2 3

More information

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 50 kbtu/sf/yr 45.1 PROJECT INFORMATION 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 13.0 kbtu/ft2/yr Baseline 10.8 kbtu/ft2/yr

More information

Mechanical Depth. Redesign and Analysis

Mechanical Depth. Redesign and Analysis Depth Redesign and Analysis 14 Analysis Scope The scope of my mechanical redesign will include the 2 nd and 3 rd floors of the SW hospital wing which includes Semi-Private, Private and Isolations rooms.

More information

Implications of Measured Commercial Building Loads on Geothermal System Sizing

Implications of Measured Commercial Building Loads on Geothermal System Sizing Implications of Measured Commercial Building Loads on Geothermal System Sizing ASHRAE Annual Meeting June 23, 1999 Hugh I Henderson, Jr.. P.E. CDH Energy Corp. Cazenovia,, NY www.cdhenergy.com Overview

More information

PROJECT NAME CLEVELAND CLINIC PROJECT #

PROJECT NAME CLEVELAND CLINIC PROJECT # CLEVELAND CLINIC PROJECT # [This is a sample of a general project M&V specification these specifications should be incorporated into the HVAC Control specifications and modified to the specific job requirements]

More information

Continuous Commissioning Leading Energy Project Process - An Industry Approach

Continuous Commissioning Leading Energy Project Process - An Industry Approach Continuous Commissioning Leading Energy Project Process - An Industry Approach Mingsheng Liu, Ph.D., P.E. Energy Systems Laboratory, University of Nebraska Jinrong Wang, P.E., Ken Hansen, P.E. Omaha Public

More information

Xavier University of Louisiana

Xavier University of Louisiana Annual Savings Report Year 2 May 1, 2012 to April 30, 2013 July 2013 For Marion Bracy Vice President Xavier University Facilities Planning 1 Drexel Drive New Orleans LA 70125 (504) 520 1056 Submitted By

More information

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 40 kbtu/sf/yr 35 kbtu/sf/yr 30 kbtu/sf/yr 25 kbtu/sf/yr 20 kbtu/sf/yr 15 kbtu/sf/yr 10 kbtu/sf/yr 5 kbtu/sf/yr 0 kbtu/sf/yr 11.9 kbtu/ft2/yr 36.0

More information

Depth: Mechanical Redesign

Depth: Mechanical Redesign Depth: Mechanical Redesign Redesign Objectives The most important objective of the mechanical redesign is to provide Greenbriar East with ventilation that meets the requirements of ASHRAE Standard 62-2001.

More information

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC LIBRARY ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance

More information

NWC District Energy Campus Energy - RFQ Supporting Documentation. April 25, 2018

NWC District Energy Campus Energy - RFQ Supporting Documentation. April 25, 2018 NWC District Energy Campus Energy - RFQ Supporting Documentation April 25, 2018 ESTIMATED ENERGY DEMAND BY BUILDING Facility Name Area Energy Use Intensity Goal Estimated Total Energy Total Average Peak

More information

Technical Report Three Mechanical Systems Existing Conditions Evaluation

Technical Report Three Mechanical Systems Existing Conditions Evaluation 09 10 Technical Report Three Mechanical Systems Existing Conditions Evaluation WESTINGHOUSE ELECTRIC CO. NUCLEAR ENGINEERING HEADQUARTERS CAMPUS Pittsburgh, PA Daniel P. Aughenbaugh Mechanical Dr. Bahnfleth

More information

Oklahoma University Children s Medical Office Building

Oklahoma University Children s Medical Office Building Oklahoma University Children s Medical Office Building Oklahoma City, O.K., BAE Advisor: Laura Miller Presentation Outline VRF System Dedicated Outdoor Air System Evaluation VRF Indoor Units Design Criteria

More information

NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS

NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS Hugh I. Henderson, Jr. P.E.*, Steven W. Carlson, P.E., and Adam C. Walburger CDH Energy Corp. Cazenovia, NY USA ABSTRACT This paper presents the

More information

PV Generation Potential 17.1 kbtu/ft2/yr 15.4

PV Generation Potential 17.1 kbtu/ft2/yr 15.4 TOWNHOME PROTOTYPE BASELINE 60 kbtu/sf/yr 50 kbtu/sf/yr 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 54.4 Baseline 54.4 kbtu/ 2/yr 21.8 High Performance 18.2 PHIUS - IES 60 MMBtu

More information

Amvic Building System. Presented to: Rick Stacey

Amvic Building System. Presented to: Rick Stacey Amvic Building System École Secondaire de Windsor Building Construction Comparative Energy Study Presented to: Rick Stacey Amvic Building System File: 11212245 4 162 Dickson Ave Kelowna, BC V1Y 9Y2 Contact:

More information

North Pocono High School

North Pocono High School Building System Integration Energy and Cost Analysis Architectural Engineering Senior Thesis Presentation Pennsylvania State University Presentation Outline Project Outline Existing System Design Conditions

More information

Ground-Coupled Heat Pump And Energy Storage

Ground-Coupled Heat Pump And Energy Storage Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system

More information

Gerald R. Ford Museum

Gerald R. Ford Museum Gerald R. Ford Museum Grand Rapids, Michigan Executive Summary Building and Plant Energy Analysis Report: Part I Brendan J. Cullen The Pennsylvania State University AE Senior Thesis Mechanical Option September

More information

Retro-Commissioning for Energy Efficiency

Retro-Commissioning for Energy Efficiency High Performance Buildings 2006 AABC Commissioning Group (ACG) April 6, 2006 Retro-Commissioning for Energy Efficiency Making buildings work. Better. Tom Poeling, P.E., CEM, LEED AP E M C Engineers, Inc.

More information

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan Energy Plan 1 EXECUTIVE SUMMARY SCORECARD RESULTS An assessment of current energy management efforts was performed; current performance falls into all categories on the SEP-Performance Scorecard (Appendix

More information

Baffled Openings at Chain Link Fencing: Design shall consist of two end-posts set 4 feet apart, and a 10 foot wide chain-link fence panel equal in height as the adjacent fence. Chain link fence panel shall

More information

Energy Analysis Construction Documents University of Wyoming Visual Arts Facility

Energy Analysis Construction Documents University of Wyoming Visual Arts Facility Energy Analysis Construction Documents University of Wyoming Visual Arts Facility January 03, 2011 Prepared for Malone Belton Abel 340 West Dow St Sheridan, Wyoming 82801 & THA Architecture 733 SW Oak

More information

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel Mechanical Option

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel  Mechanical Option EADQUARTERS 707 N. Calvert St. Mechanical System Renovation Construction Management & Lighting/Electrical Breadths Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option

More information

Timmins and District Hospital

Timmins and District Hospital Opportunity Assessment Timmins and District Hospital Draft Report December 10 th 2013 Submitted to: Tim Prokopetz, Manager, Materials - Biomedical Engineering Timmins and District Hospital Submitted by:

More information

Chilled Water Plant Redesign

Chilled Water Plant Redesign 17 Chilled Water Plant Redesign OVERVIEW The chilled water plant redesign includes the addition of a thermal energy storage system. This allows for economic and operational benefits for the facility by

More information

Low-Hanging Fruit Simple Steps Toward Energy Effective Building Operations

Low-Hanging Fruit Simple Steps Toward Energy Effective Building Operations Low-Hanging Fruit Simple Steps Toward Energy Effective Building Operations Roger Ebbage Northwest Water / Energy Education Institute Lane Community College May 7-9 Enzian Inn - Leavenworth, Washington

More information

Ventilation. Commercial Kitchen. What We Learned From MGM Grand Fire Airtight Buildings Benchmarking Building Energy Use Resetting Setpoints

Ventilation. Commercial Kitchen. What We Learned From MGM Grand Fire Airtight Buildings Benchmarking Building Energy Use Resetting Setpoints NOVEMBER 2015 ASHRAE JOURNAL THE MAGAZINE OF HVAC&R TECHNOLOGY AND APPLICATIONS ASHRAE.ORG Commercial Kitchen Ventilation What We Learned From MGM Grand Fire Airtight Buildings Benchmarking Building Energy

More information

THE NEW YORK TIMES BUILDING

THE NEW YORK TIMES BUILDING THE NEW YORK TIMES BUILDING 620 EIGHTH AVENUE NEW YORK, NEW YORK 10018 TECHNICAL REPORT ONE: AE 481-Comprehensive Senior Project I Building Mechanical & Energy Systems Option IPD / BIM Senior Thesis Prepared

More information

The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario

The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario Visionwall Technologies Inc. 14904-123 Avenue Edmonton, Alberta, Canada T5V 1B4 Tel: 403 451 4000 Fax:

More information

Optimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning

Optimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning Optimizing Energy Use in a HealthCare Setting Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning AIA Quality Assurance The Building Commissioning Association is a Registered

More information

Analysis II Energy Considerations for Green Roofs

Analysis II Energy Considerations for Green Roofs Analysis II Energy Considerations for Green Roofs 1099 New York Avenue Background As seen from the previous analysis, many of the credits for sustainability can be obtained through the materials and methods

More information

What s My Baseline? ASHRAE

What s My Baseline? ASHRAE 2010 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions (2010, vol 116,part 2). For personal use only. Additional reproduction,

More information

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin Thesis Proposal Photo by Fred Martin Clemson University Advanced Material Research Laboratory Anderson, SC David Anderson Mechanical Option Friday, December 15, 2006 Table of Contents 1. Executive Summary

More information

Retrocommissioning Investigation Study of the Sheraton Chicago Hotel

Retrocommissioning Investigation Study of the Sheraton Chicago Hotel Retrocommissioning Investigation Study of the Sheraton Chicago Hotel & Towers Cityfront Center Tracy Phillips May 4, 2007 May 4, 2007 You can go anywhere you want, if you look serious and carry a clip

More information

Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat Recovery VRF System)

Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat Recovery VRF System) Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat VRF System) (* Source: http://kr.lgeaircon.com/) Commercial Air-Conditioning Engineering Study ES-MultiVWaterIV_EnergyAnalysis-08-14

More information

Energy Management in Existing Buildings

Energy Management in Existing Buildings Energy Management in Existing Buildings Davor Novosel Chief Technology Officer National Energy Management Institute Committee Overview Why manage energy? Why existing buildings? How big is energy savings

More information

percent hours of the year heat rejected to loop percent hour building load on loop, Btuh percent hour building load on loop, Btuh

percent hours of the year heat rejected to loop percent hour building load on loop, Btuh percent hour building load on loop, Btuh HOBOKEN RESIDENTIAL C- Ground Loop Pump Calculations Central Geothermal System building load on loop, Btuh Bin - 5 5 25 35 45 55 hours of the year Count 3 35 48 64 79 89 96 96 3 32 3 6 5 7 274 292 86 46

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal : REVISION I

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal : REVISION I Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal : REVISION I Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System

More information

LEED Energy Performance Summary Report

LEED Energy Performance Summary Report Section 1.1 - General Information Simulation Program: Principle Source: Energy Code Used: Weather File: Climate Zone: New Construction Percent: Existing Renovation Percent: Quantity of Floors: Proposed:

More information

Farm Energy IQ. Future. Tom Manning, New Jersey Agricultural Experiment Station

Farm Energy IQ. Future. Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farms Farm Today Energy Securing Audits Our Energy Future Tom Manning, New Jersey Agricultural Experiment Station An energy audit is the process of determining energy consumption of a building

More information

Xavier Energy Initiative

Xavier Energy Initiative Xavier Energy Initiative By Ron Perkins Report of August Site Visit To paraphrase Blaise Pascal, if I had more time I would have written a shorter report. In deference to those who do not share my enthusiasm

More information

Senior Thesis Report Spring Appendix - A. HAP Calculations without Enthalpy Wheel Excel Graphs

Senior Thesis Report Spring Appendix - A. HAP Calculations without Enthalpy Wheel Excel Graphs Jason Jones Mechanical Option Senior Thesis Report Spring 2005 Appendix - A HAP Calculations without Enthalpy Wheel Excel Graphs Cooling Plant Sizing Summary for Chiller Plant Monmouth CD New Schedule1

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...

More information

THE PENNSYLVANIA STATE UNIVERSITY DEPARTMENT OF ARCHITECTURAL ENGINEERING THESIS NEW INDEPENDENCE HIGH SCHOOL/SHARED USE FACILITY

THE PENNSYLVANIA STATE UNIVERSITY DEPARTMENT OF ARCHITECTURAL ENGINEERING THESIS NEW INDEPENDENCE HIGH SCHOOL/SHARED USE FACILITY MECHANICAL TECHNICAL ASSIGNMENT 2B John Shaw EXECUTIVE SUMMARY The Mechanical Technical Assignment 2b involves an evaluation and comparison of the student thesis project cooling loads and energy costs.

More information

First Place: Health Care Facilities, New

First Place: Health Care Facilities, New First Place: Health Care Facilities, New Swedish Issaquah, Issaquah, Wash., is a 175 bed, 353,000 ft 2 (32 810 m 2 ) community hospital, where a 16,000 ft 2 central plant heat recovery system helped the

More information

AE 481W Thesis Proposal

AE 481W Thesis Proposal AE 481W Thesis Proposal I I Advisor: Dr. Treado UNIVERSITY OF CALIFORNIA SAN DIEGO RADY SCHOOL OF MANAGEMENT LA JOLLA, CA TABLE OF CONTENTS Executive Summary.3 Mechanical System Overview..4 Design Objectives,

More information

9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates

9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center September 21 st, 2011 4:15pm 5:15pm Terry Malloy P.E., Cxa, Project Manager, Teng & Associates Energy consumption (BTU/SF) in

More information

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:

More information

5.0 Mechanical Depth:

5.0 Mechanical Depth: 5.0 Mechanical Depth: Air-Side Systems The airside mechanical system for the Montgomery County Conference Center and Hotel consists of a combination of variable air volume and constant volume systems served

More information