THE ODAN/DETECH GROUP INC.
|
|
- Julia Ross
- 5 years ago
- Views:
Transcription
1 5230 SOUTH SERVICE ROAD, BURLINGTON, ONTARIO L7L 5K2 TELEPHONE: (905) FACSIMILE: (905) PROJECT No : FUNCTIONAL SERVICING REPORT FOR BOLTON DISTRIBUTION CENTRE, COLERAINE DRIVE & HEALEY ROAD TOWN OF CALEDON, ONTARIO CLIENT: CANADIAN TIRE JOHN KRPAN, MSCE, PEng August 8 th, 2011 DATE ORIGINAL: April 11, 2011 UPDATED: August 8, 2011 FILE No Bolton Distribution Center FSR (DRAFT Revision 2)doc
2 FUNCTIONAL SERVICING REPORT FOR BOLTON DISTRIBUTION CENTRE, COLERAINE DRIVE & HEALEY ROAD TOWN OF CALEDON, ONTARIO TABLE OF CONTENTS DESCRIPTION page 10 INTRODUCTION 1 20 SCOPE OF WORK 1 30 DESIGN CONSIDERATIONS 2 A) Sanitary Disposal 2 B) Water Distribution 4 C) Storm Water Management And Storm Drainage 8 D) Traffic 16 E) Soils Report Conclusions References 17 Appendix A 18 Existing Site Aerial view of Site and surrounding Site Appendix B Visual Otthymo Input/output Files Appendix C Site Plan Figure 1 Figure 2 Figure 3 Figure 4 Showing the proposed development Plan Showing Existing Services On adjacent Roads Plan Showing proposed sanitary service Plan Showing proposed water service Plan Showing proposed SWM and storm sewer system
3 1 April 11, 2011 FUNCTIONAL SERVICING REPORT FOR BOLTON DISTRIBUTION CENTRE, COLERAINE DRIVE & HEALEY ROAD TOWN OF CALEDON, ONTARIO 10 INTRODUCTION: The property under study is a 7167 ha (1771 acre) site at the north west corner of Coleraine Drive and Healey Road, Town of Caledon The development is bounded by open field to the west, Healey Road to the south, Coleraine Drive to the east and existing industrial to the north The site is presently agricultural field (see aerial view) There are two watercourses traversing the site The watercourses converge just before crossing under Healey Road It is proposed to redevelop the Site into a large scale distribution centre Refer to the Conceptual site plan (Glenn Piotrowski Architect) for further information regarding the proposed layout of the site including the building location, asphalt, and concrete curbing etc The property slopes from north to south with an approximate 10% slope 20 SCOPE OF WORK: was retained by, CANADIAN TIRE, to review the site, collect data, evaluate the site for the proposed industrial use and present the findings in a Functional Servicing Report in support of a Rezoning and Site Plan Application The scope of work in brief involves the following: a) Collecting existing servicing drawings from the Town of Caledon and Region of Peel in order to establish availability and feasibility of site servicing; b) Meetings/conversations with Town Planners & Engineers, TRCA and Town Consultants c) Evaluation of the data and presentation of the findings in a Functional Servicing Report
4 2 30 DESIGN CONSIDERATIONS: A) SANITARY DISPOSAL: The Table below shows the summary of the sanitary flow calculations The redevelopment of the Site will utilize the existing sanitary sewer on Coleraine Drive The existing servicing sewers are shown on Figure 2 Appendix A There are no existing sanitary sewer connections to the Site The proposed redeveloped site will consist of 14M ft 2 Distribution Centre with ancillary buildings, vehicle parking, trailer parking and outdoor storage This is the only land use proposed for the Site The above statistics were compiled by Glenn Piotrowski Architect The proposed land use sanitary flows were calculated using the Region of Peel Sanitary Design Guidelines See the following spread sheet below for more details of the calculations Note, not all of the Site area will contribute to infiltration We conservatively estimate 30 ha Based on table 1 below the maximum sanitary flow is 405 L/sec including infiltration For comparison the Mechanical consultant has estimated the water consumption (domestic) to be 400 usgm (25 L/sec) while table 1 shows 405 L/sec domestic sewage flow Thus this analysis can be considered conservative A 300 mm Ø sewer at 050% has a full flow capacity of 69 L/sec Refer to Figure 2 for the Sanitary sewer system to the site and through the site The minimum sewer slope will be 050% and end runs 10 %
5 3 Table 1 Expected Sanitary Flows SANITARY FLOW CALCULATIONS SCENERIO: 1) Industrial Warehouse This program calculates the sanitary discharge from various land use As per the Region of Peel Guideline FILL IN COLOURED CELLS AS REQUIRED INDUSTRIAL SITE AREA (ha) = 7167 RESIDENTIAL SITE AREA (ha) = 0 TOTAL SITE AREA for infiltration (ha) = 30 LAND USE NUMBER OF UNITS SITE AREA, (ha) GROSS FLOOR AREA, m2 TOTAL POPULATION TOTAL DAILY FLOW (LITERS) AVERAGE DAILY FLOW l/sec PEAKING FACTOR, M TOTAL FLOW FROM LAND USE, l/sec RESIDENTIAL Density 1, using 86 person/site area RESIDENTIAL Density 2, using 170 persons/site area RESIDENTIAL Density 3, using 270 persons/site area RESIDENTIAL Density 3, using 27 persons/unit RESIDENTIAL Density 4, using 400person/site area RESIDENTIAL Density 4, using 27 persons/unit COMMERCIAL, Using 136 persons/ha COMMERCIAL, Using 11 persons/100 m2 OFFICES, Using 33 persons/100 m2 INDUSTRIAL, Using 2 persons/100 m TOTAL V1= Q1= 000 Q2= 3446 Q = (MqP/86400) + A * I (L/sec) Qinfil 600 Qtot 4046 Q1= total flow from Residential Land Use (L/sec) where : P is population Q2= total flow from Industrial Land Use (L/sec) q = 303 L/person/day for residential and Qinfil = total flow from infiltration (L/sec) q = 303 L/person/day for INDUSTRIAL Qtot = total flow (Land use + infiltration) A = gross site area for infiltration i = 020 L/sec/ha (infiltration rate) V1= Total Volume from Land Use in liters Peaking Factor M = 1 + [14 / (4 + (P/1000,1/2))]
6 4 B) WATER DISTRIBUTION: DESIGN CONSIDERATIONS- The unit rate and peaking factors of water consumption, minimum pipe size and allowable pressure in line were established from the Region of Peel criteria The water distribution system is shown on Figure 3 The Water demands were calculated as follows: note that the Region water per capita is 300 while the Sanitary is 303 for Industrial They are almost the same a) Average Day domestic demand L/sec Refer to the Sanitary calculations (2837 persons) b) Peak day demand - 2 x daily demand 200 L/sec c) Peak hour demand - 30 daily demand 300 L/sec d) Fire Flow - to be calculated by Fire consultant For comparison the Mechanical consultant has estimated the water consumption (domestic) to be 400 usgm (25 L/sec) while above peak hour domestic flow shows 300 L/sec OK The following is an evaluation of fire fighting for the site as given by Civelec Consutants "WATER SUPPLY FOR FIRE FIGHTING ANALYSES BY CIVELEC CONSULTANTS: Civelec Consultants Inc was mandated to prepare a preliminary water supply analyses for fire protection purposes Water demand: The final water demand for fire-fighting will be depended on the types of products stored in the plant, the height of storage the storage configuration and the design of fire protection system We can assume that the water demand will be in the range of 3000 to 4000 us gpm As the plant will require relatively high pressures and fire pumps will be required for a cost effective design, the water supply of approximately 4000 us gpm should be available at 20 psi The preliminary study is based on AECON water supply study prepared for the Region of Peel The site is located on a major water supply line having a 750 mm diameter The water to this line is supplied by number of pumping stations A 300 mm distribution main is located parallel to the main line It should be possible to interconnect the main line to the distribution line near the plant to increase the water supply capacity if needed As the main distribution line is feeding the area the probability for a long period impairment is
7 5 minimal The distribution line is looped by distribution mains and should be relatively simple to isolate any impairment Based on the AECON report the water supply should be adequate to meet the psi demand Due to the configuration the water supply is considered reliable In addition a new pumping station/reservoir is planned to be installed near this location, that would increase the water system supply reliability The water supply is evaluated to be adequate and no major expenses are expected to be added to the construction due to inadequate water supply " Water Service for the Site : Refer to Figure 3 for the water distribution to the site The connecting watermain will be the existing 300 mm line on the east side of Coleraine Drive The premise of the water supply to the site is reliability Reliability means that if a particular line breaks or needs servicing a second line is available to service the site The service to the site will have mm lines At the connection with the Region watermain the two service lines will be separated by a control valve on the City main If the north section needs servicing the south section can supply the water In the site the two mains will be routed to the control building At the control building the system will be routed and looped around the site back to the control building In addition the water supply will be pumped to the desired pressure Again the loop will ensure a reliable supply The pressures and volumes must be sufficient for Peak hour conditions and under fire conditions as established by the Ontario Building Code The minimal residual pressure under fire conditions is 140 kpa (or 203 psi) Fire pumps will be required to lift the flow to the upper levels of the Plant DESIGN CRITERIA: The following data was used in the design of the system 10 Transient Pressures The proposed watermain will be designed to withstand pressures up to 1380 kpa (200 psi) which is sufficient to withstand the maximum operating pressure of 200 psi, plus any transient pressure it may be subjected to The pipes and joints have also been designed to withstand the maximum operating pressure plus the surge pressure that would be created by stopping a water column moving at 06 m/s The transient pressure surge in a PVC Class 200 DR 14 pipe for s 06m/s water column is 35 psi
8 6 20 Pipe Strength The proposed watermain pipe material is PVC Class 200 DR14 conforming to CSA B1373 and AWWA C900 Loading calculations for pipe strength are based on the internal pressures of the system The pipe stiffness values for the specified pipe class are relatively high; therefore deflection from static and/or live loads is not a critical design factor For watermain pipe material consisting of PVC Class 200 DR14 conforming to CSA B1373 and AWWA C900, the maximum internal pressure is 200 psi with a long term FS of 25 and 4 for short term surge pressures 30 Fire Hydrants All hydrants shall be 3-way hydrants and shall be spaced as detailed on the engineering drawings All hydrants shall be in accordance with the approved watermain materials list be dry-barrel type in accordance with AWWA C502: Dry-Barrel Fire Hydrants be 3-way, two nozzles which are 180 to each other and parallel to the street and a 100mm pumper STORZ connection facing the street open as per Region Standard All new hydrants that open left shall be painted with a black L symbol on the bonnet have a 25mm top operating nut size be painted as per Region Standard (barrel, bonnet and hose nozzle caps) and the STORZ connection painted black be controlled by a secondary valve close-coupled to the hydrant have a hydrant lead of 150mm from the watermain to the hydrant be installed plumb and in accordance with the Region Standard drawing which provides adequate thrust blocking to prevent movement caused by thrust forces The water table is not expected to rise above the hydrant drain ports 40 Valves The watermain has been designed such that there are minimum 2 gate valves at each T- intersection and 3 at cross intersections All gate valves shall be in accordance with the Region s approved watermain materials list which conforms to AWWA standards 50 Air Release and Vacuum Release Valves Not applicable 60 Valve, Meter and Blow-off Chambers Not applicable
9 7 70 Separation Distances from Contamination Sources The watermain has been located such that there is a minimum of 25m horizontal separation from the nearest sewer 80 Restraints Thrust blocks in accordance with Region Standard Drawings have been proposed at all tees, line valves, hydrants and bends The thrust forces have been calculated using the maximum pressure allowable for the pipe class (200 psi) Concrete for thrust blocks shall be 30 MPa poured on undisturbed ground Where thrust blocks cannot be laid to undisturbed ground due to excessive sewer excavation or fill conditions, mechanical joint restrainers shall be used in conjunction with concrete thrust blocks Any section of watermain that is not pressure tested against thrust blocks (eg connection pieces), shall be required to use mechanical joint restrainers at the tee connections in addition to the concrete thrust block We have reviewed the thrust block design based on Region Standard Drawing for a 200mm watermain at a 45 degree bends and plugs For the thrust force resulting from 200 psi pressure (max pressure for pipe class), the bearing strength of the undisturbed soil must be a minimum of 1935 lbs/sq ft using an inherent safety factor of 15 The bearing strength of the native material on the site is estimated to be a minimum of 3000 lbs/sq ft thereby providing the required bearing capacity for the minimum size of thrust block specified in the Region Standard drawing Other Design Considerations The watermains within the proposed site shall be installed in accordance with the current Region specifications and requirements If there is a crossing of the watermain and a sewer, the watermain shall cross above the sewer with sufficient vertical separation to allow for proper bedding and structural support of the watermain, (05m minimum) In cases where there is a conflict with the elevation of the sewer and the watermain such that the watermain cannot cross above the sewer, the watermain has been designed to cross below the sewer subject to the following conditions a) There shall be a minimum vertical separation of 05m between the bottom of the sewer pipe and the top of the watermain, b) The watermain shall be lowered below the sewer using vertical thrust blocks and restraining joints, c) The length of the watermain pipe shall be centered at the point of crossing so that the joints are equidistant and as far as possible from the sewer, and d) The sewer shall be adequately supported to prevent joint deflection and settling
10 8 C) STORM WATER MANAGEMENT AND STORM DRAINAGE: 10) INTRODUCTION The site is presently agricultural field (see aerial view) There are two watercourses traversing the site The watercourses converge just before crossing under Healey Road The property slopes from north to south with an approximate 10% slope The SWM for this site will follow the guidelines of the Bolton Community Plan, Employment Lands and North Hill Supermarket Site, Comprehensive Environmental Impact Study and Management Plan, Phase 2 report, Aquafor Beech Limited, September 17, 2010 To our knowledge the above mentioned Aquafor Beech report has not been adopted by the Town, Region or Conservation Authority 20) CRITERIA QUALITY CONTROL: Since the Site is 7167 ha (> 025 ha) water quality needs to be addressed A SWM Pond will be required Quality control will follow MOE 2003 guidelines The Aquafor Beech report suggests a SWM pond for this site located in approximately the same location as shown in our Figure 4 QUANTITY CONTROL: POST DEVELOPMENT: 1 Release into the water course flows from the Post developed Site at the predevelopment level for a 2 year to Regional Storm event 2 Utilize LID methods in the Landscape areas 3 Utilize roof top and parking lot storage to limit piping size and pond size 4 Utilize minor flow sewer system to the SWM Pond 5 Provide a suitable overland flow route to the SWM Pond for Regional storm DISCUSSION: As indicated on the Site Plan by Glenn Piotrowski Architect, this development will consist of a large Industrial building with ancillary buildings and the related parking/storage The site soil is a Clayey Silt Till and or a clay till This assumption is based on geotechnical study performed by Trow, Geotechnical Consultants The soils are not conducive to large scale infiltration, thus Infiltration was ruled out as a major means of Storm water Management
11 9 The Aquafor Beech report September 17, 2010 estimates the percolation rate at less than 2 mm/hr At this rate the LID are ineffective Based on the Trow report the soils are predominately Clayey Silt till which support the Aquafor Beech report The redevelopment of the Site will have multiple level roof system See Site Plan Appendix A The roofs will be used for storage The maximum storage depth will be limited to 150 mm in a sloped roof The roof areas will have emergency scuppers in case of blockage The detained flow will discharge to the storm sewer on site The site parking and Building roof areas will be utilized in the SWM of the site along with the SWM Pond 20) ANALYSIS RAINFALL DATA The following storm design data for the Town of Caledon will be used to evaluate the storm runoff: 2 Year to 100 year AES 6 hr storms created from data from the Lester B Pearson rainfall Gauge (Environment Canada Gauge # ) Regional Storm based on Hurricane Hazel PRE-DEVELOPMENT CONDITIONS VISUAL OTTHYMO PRE-DEVELOPMENT MODEL 1 Existing flow from north&east AREA = Flow from site (exist) AREA = flow to Healy Rd culvert AREA = 1470
12 10 TABLE 3 Catchment Characteristics for the Pre-Developed Site Watershed Description Area (ha) CN perv % Imperv % Imperv Directly Connected Imperv Length(m) perv Slope(%) imperv perv imperv Losses perv Tp (hr) Existing Site SEE INPUT 1 1 NASHYD Existing north and east External Area SEE INPUT 1 2 STANDHYD SCS - Total: 1470 Note: Tp= (2-1) 2 (Tc) = 05 x 108 = 054 hr (Aquafor Beech recommends n=2) Tc = L Vc = = 3929 sec = 65 min = 108 hr where L is length of drainage basin (m) and Vc is the velocity from "Uplands method for time of concentration" taken as 028 m/sec for 10% slope and cultivated row POST-DEVELOPMENT CONDITIONS VISUAL OTTHYMO POST-DEVELOPMENT MODEL 9 Existing Area to North AREA = channel area north AREA = 10 4 Roof Area AREA = Parking & Landscape area AREA = Roof top storage AREA = Parking storage AREA = AREA = SWM Pond AREA = 730 Channel area north east AREA = Existing Area to North-east AREA = Flow to culvert Healy Rd AREA =
13 11 Using Visual Otthymo Model (see below and output in Appendix B) Refer to table 4 for the post development catchment areas TABLE 4 Catchment Characteristics for the Post-Developed Site Watershed Description Area (ha) CN perv % Imperv % Imperv Directly Connected Imperv Length(m) perv Slope(%) imperv perv imperv Losses perv Tp (hr) Roofs SEE INPUT 1 1 STANDHYD SCS - Parking / storage Existing north External Area Existing north east External Area Channel northwest and north east SEE INPUT 1 1 STANDHYD SCS SEE INPUT 1 1 STANDHYD SCS SEE INPUT 1 1 STANDHYD SCS SEE INPUT 1 NASHYD 054 Total: 1470 The following is the roof top stage/volume/discharge relationship used in the Post Development Visual Otthymo model Relationship for Rooftop Control Devices Roof Drains Area of Roof = m 2 Number of Weirs = Head (m) Volume (m 3 ) Discharge (l/s) Based on 2 weirs per drain at 038 l/sec per 254mm of head per drain (Control-Flo Zurn ZCF-121 by Zurn)
14 12 MOE POND CALCULATIONS Bolton Distribution Center Quality/Quantity Pond Drainage Area: 73 ha % Impervious: 85 % Storage Volume for Impervious Level: 250 (m 3 /ha) Pond Volume: m 3 Extended Detention Volume: 2920 m 3 Permanent Pool Volume: m 3 Q weir = 18 x L x (head)^15 Stage Discharge orifice 1 orifice 2 Elevation Increment: 010 m 010 AREA OF POND (m2) = Orifice Coefficient: Orifice area Length of Weir L = 850 Orifice Size: 525 mm 600 Weir elevation = Orifice Invert 242 m nd orifice elev = Elevation Description Bottom Elevation (m) Top Elevation (m) Volume (m 3 ) Discharge orifice1 (m 3 /s) Discharge orifice2 (m 3 /s) Discharge weir (m 3 /s) Total Discharge (m 3 /s) Stage (m) Permanent Pool Top of Extended Pool Weir Top of Pond Summary Permanent Pool Volume (m 3 ) Extended Pool Volume (m 3 ) Required Provided Forebays Micropool Storm Event Storage Volume Required (m 3 ) HGL Elevation (m) 25 mm Regional
15 13 Table 5 Post-development Flows from Visual Otthymo Model Results and comparison to Predevelopment Flows: Bolton Warehouse Pond Outlet at Healey Road Design Event Note post is less than pre The low level orifice can be tweaked in the final design Water Quality: Q (predevelopment) (m3/sec) Q (post development) (m3/sec) Regional Table 6 SUMMARY OF POND DESIGN MOE 2003, TOWN & CONSERVATION DESIGN ELEMENT REQUIRED PROVIDED DRAINAGE AREA (ha) 10 ha (preferred) 73 ha PERMENANT STORAGE m m 3 EXTENDED STORAGE 1) Quality 2) Quantity (regional storm ) 2920 m m m m 3 FOREBAY DEPTH 10 m 10 m FOREBAY AREA < 33% OF TOTAL PERMANENT POOL 25 % PERMANENT POOL DEPTH MAX 30 m 13 m FREE BOARD FROM TOP OF POND TO 100 YR HGL 030 m 035 m OUTLET PIPE MIN 450 mm DIA 600 mm DIA ORIFICE MIN 100 mm DIA 525 mm DIA ACTIVE STORAGE DEPTH MAX FOR QUALITY 15 m 040 m FOREBAY SETTLING LENGTH 60 m 58 m DRAWDOWN TIME Minimum 12 hr Preferred 24 hr 25 hr CLEAN OUT FREQUENCY 10 YEARS -
16 14 FOREBAY SETTLING CALCULATIONS: DIST = r Q p V s = 2* = 163 m r = 2 Q p = 043 m 3 /sec from Otthymo or DIST = 8 Q d V f = 8*478 3 (05) = 11 m d=3 m V f = 05 m/sec Q=478 m 3 /sec (10 yr) Therefore the forebay length should be greater than 16 m, provided 80m ok See outflow hydrographs below for pond which will show the approximate draw down time Visual OTTHYMO Hydrograph Plots Post Development Run Number 1 NHYD= Precip(mm/hr) Flow(cms) Time(hours) TABLE 7: POST DEVELOPMENT STORAGE REQUIREMENTS FROM VISUAL OTTHYMO STORM EVENT ROOF STORAGE (m3) Required Max estimated PARKING LOT STORAGE (m3) Required Max estimated SWM POND STORAGE (m3) Required Max estimated 2 year year year year year year REGIONAL
17 15 DIVERSION OF CHANNELS: The two channels that traverse the site will need to be diverted The channel corridors will be 20 m as shown on Figure 4 appendix C The final channel slopes and grading will be determined at final design The east channel is presently 706 m in length at a slope of 059% The west channel is presently 1312 m in length at a slope of 093% The re-routed channel are as follows: East - 051% West % Q region = 705 m3/sec each channel (from Visual Otthymo 100 yr storm is highest) Profile east channel: trapezoidal min 3:1 sides with 15 m bottom depth using n = 040 & s=051% = 105 m With average v=131 m/sec Calculated max shear is 52 N/m2 At corners double the shear to 104 N/m2 With vegetation type B the permissible shear is 100 N/m2 which is > 52 N/m2 At corners rip-rap will be required D50 = 300mm or vegetation type A Profile west channel: trapezoidal min 3:1 sides with 20 m bottom depth using n = 040 & s=067% = 099 m With average v=144 m/sec Calculated average shear is 65 N/m2 At corners double the shear to 130 N/m2 With vegetation type B the permissible shear is 100 N/m2 which is > 65 N/m2 At corners rip-rap will be required D50 = 300mm or vegetation type A Notes: 1 The shear at bends is calculated as λ b = K b x λ d where λ b is shear on bend, λ d is maximum shear on straight and K b is a magnifying factor which is 20 max for minimum bend ratio of 20 The bend shear can be reduced in the final design 2 Rip-rap and or the proper vegetation will be decided with the Landscape Architect 3 Channel meander can be accomplished in select areas 4 Micro pools can be incorporated in select locations in the channel bottom 5 Channel corridor may be reduced upon final design 6 We are not in receipt of any document/report that instructs us how to handle the existing channels The channels must be relocated in order to proceed with this project
18 16 WATER HARVEST: Due to the soils having percolation rates less than 2mm/hr any LID in the parking/driveway area has to be ruled out LID in the landscape areas can be accomplished, however due to percolation rates as low as indicated the effectiveness of the LID is diminished We recommend water harvest Discussions with the project Mechanical Consultant led to a cistern which will take roof water and hold 40,000 usg (151 m3) which will be used for irrigation and possible truck washing The tank will be buried underground and have an overflow to the storm sewer system The rate of consumption will be determined upon final design RECOMMENDATIONS: The site should utilize roof top storage if at all possible If roof top storage is not utilized then a larger Pond will be required Parking area should be graded to maximize surface storage Overland flow route is to be utilized to the SWM Pond LID be utilized in the Landscape Area to meet the Master Drainage Plan criteria Water harvest cistern is to be used for landscape sprinkler system SWM Pond be utilized for water quality/quantity as detailed above Route existing channels as shown on the preliminary design drawings Utilize meanders and micro pools where possible D) TRAFFIC: A traffic impact study has been completed by the BA Group The Site Plan reflects this study F) SOILS REPORT: A geotechnical study has been performed by Trow, Geotechnical Consultants dated December 7th, CONCLUSIONS: From our investigation the Site is serviceable with sanitary and storm sewers & water supply for domestic and fire fighting purposes In addition gas and hydro services are available There is adequate access from Coleraine Drive and Healey Road The site is favourable for the proposed Development as shown on the Site Plan
19 17 50 REFERENCES: 1 Bolton Community Plan, Employment Lands and North Hill Supermarket Site, Comprehensive Environmental Impact Study and Management Plan, Phase 2 report, Aquafor Beech Limited, September 17, Regional Municipality of Peel, Bolton Urban Community Water and Wastewater Analysis, AECOM, Markham office, Revision 4, Final Report, March Storm water Management Planning and Design Manual, Ontario Ministry of the Environment, March Geotechnical Investigation, Coleraine Drive and Healey Road, Bolton, Ontario, Trow Associates Inc, December 7, 2010
20 18 APPENDIX A Existing Site Aerial view of Site and surrounding Site
21 Subject Site and Surrounding Area
22 APPENDIX B Visual Otthymo Input/output Files
23 VISUAL OTTHYMO INPUT/OUTPUT FILES 2 Year To 100 Year Storms And Regional Storm Pre-development Condition
24 ======= V V I SSSSS U U A L V V I SS U U A A L V V I SS U U AAAAA L V V I SS U U A A L VV I SSSSS UUUUU A A LLLLL OOO TTTTT TTTTT H H Y Y M M OOO O O T T H H Y Y MM MM O O O O T T H H Y M M O O OOO T T H H Y M M OOO Developed and Distributed by Clarifica Inc Copyright 1996, 2007 Clarifica Inc All rights reserved ***** D E T A I L E D O U T P U T ***** Input filename: C:\Program Files (x86)\visual OTTHYMO 232\voindat Output filename: C:\Users\John Krpan\Documents\PROJECTS\10232-CTC-Warehouse-Bolton\ Otthymo_Functional\Predevelopmentout Summary filename: C:\Users\John Krpan\Documents\PROJECTS\10232-CTC-Warehouse-Bolton\ Otthymo_Functional\Predevelopmentsum DATE: 4/4/2011 TIME: 3:31:02 PM USER: COMMENTS: **************************** ** SIMULATION NUMBER: 1 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\2Y6STM Ptotal= 3600 mm Comments: 2yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880
25 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 1406 (i) TIME TO PEAK (hrs)= 3350 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 427 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)=
26 over (min) Storage Coeff (min)= 1383 (ii) 2096 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm) ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY **************************** ** SIMULATION NUMBER: 2 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\5Y6STM Ptotal= 4781 mm Comments: 5yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN
27 hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 2266 (i) TIME TO PEAK (hrs)= 3350 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 511 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 1235 (ii) 1871 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)=
28 TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm) ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY **************************** ** SIMULATION NUMBER: 3 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\10Y6STM Ptotal= 5569 mm Comments: 10yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr
29 Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 2884 (i) TIME TO PEAK (hrs)= 3300 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 555 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 1162 (ii) 1760 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT
30 (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm) ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY **************************** ** SIMULATION NUMBER: 4 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\25Y6STM Ptotal= 6559 mm Comments: 25yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr
31 Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 3692 (i) TIME TO PEAK (hrs)= 3300 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 601 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 1088 (ii) 1649 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm)
32 ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY **************************** ** SIMULATION NUMBER: 5 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\50Y6STM Ptotal= 7300 mm Comments: 50yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr
33 Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 4314 (i) TIME TO PEAK (hrs)= 3300 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 629 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 1043 (ii) 1580 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm) ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY
34 **************************** ** SIMULATION NUMBER: 6 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\ Otthymo_Functional\100Y6STM Ptotal= 8031 mm Comments: 100yr/6hr TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr
35 Unit Hyd Qpeak (cms)= 3605 PEAK FLOW (cms)= 4939 (i) TIME TO PEAK (hrs)= 3300 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 653 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 7200 ID= 1 DT= 30 min Total Imp(%)= 7800 Dir Conn(%)= 7800 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 1004 (ii) 1521 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 870 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0003) = 3 AREA QPEAK TPEAK RV (ha) (cms) (hrs) (mm) ID1= 1 (0002): ID2= 2 (0001): ID = 3 (0003): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY **************************** ** SIMULATION NUMBER: 7 ** **************************** READ STORM Filename: C:\Users\John Krpan\Documents\PROJECTS \10232-CTC-Warehouse-Bolton\
36 10232-Otthymo_Functional\HAZELSTM Ptotal=21200 mm Comments: Hurricane Hazel for the last 12 hrs of t TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0002) Area (ha)= 7500 Curve Number (CN)= 880 ID= 1 DT= 30 min Ia (mm)= 400 # of Linear Res(N)= 200 UH Tp(hrs)= 54 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr
RETAIL UNITS GUELPH. November Prepared For: File No Engineering Report.docx F: (905) P: (905) BURLINGTON, ONTARIO
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED COMMERCIAL RETAIL UNITS GUELPH LINE AND UPPER MIDDLE
More informationSERVICING AND STORM WATER MANAGEMENT REPORT
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED BANK PLACE D ORLEANS MALL OTTAWA, ONTARIO SERVICING
More informationPROPOSED FOOD STORE 150 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For:
PROPOSED FOOD STORE 150 TORONTO STREET SOUTH Job No. 16227 ENGINEERING REPORT Prepared For: MAVERICK DEVELOPMENT CORPORATION 150 Woodbine Avenue Suite 3005 Toronto, Ontario Prepared By: The Odan/Detech
More informationSERVICING AND STORM WATER MANAGEMENT REPORT
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED MASTERMIND TOYS RETAIL BUILDING PLACE D ORLEANS
More informationP: (905) F: (905) PROPOSED BANK. Prepared For: ENT INC. JUNE Rev 0.docx
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED BANK PLACE D ORLEANS MALL OTTAWA, ONTARIO SERVICING
More informationPROPOSED COMMERCIAL DEVELOPMENT 217 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For:
PROPOSED COMMERCIAL DEVELOPMENT 217 TORONTO STREET SOUTH MARKDALE, ONTARIO Job No. 17232 ENGINEERING REPORT Prepared For: 219 Toronto Street South Developments Inc. 150 Woodbine Avenue Suite 3005 Toronto,
More informationTHE ODAN/DETECH GROUP INC.
THE ODAN/DETECH GROUP INC. 5230 SOUTH SERVICE ROAD, BURLINGTON, ONTARIO L7L 5K2 TELEPHONE: (905) 632-3811 FACSIMILE: (905) 632-3363 Email: detech@odandetech.com PROJECT No. : 13233 FUNCTIONAL SERVICING
More informationFUNCTIONAL SERVICING REPORT
PROPOSED DEVELOPMENT HIGHWAY 401 AND CONCESSION ROAD 7 PUSLINCH, ONTARIO FUNCTIONAL SERVICING REPORT Prepared For: FARHI HOLDINGS CORPORATION c/o ZELINKA PRIAMO Ltd Original February 12, 2016 Revised September
More informationPROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG
More informationPROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART. January 2016
The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG
More informationFunctional Servicing Report
Functional Servicing Report 4063 UPPER MIDDLE ROAD CITY OF BURLINGTON January 2017 SLA File: 16115 3228 South Service Road, Suite 105, East Wing Burlington, Ontario L7N 3H8 Tel. (905) 631-6978 Fax (905)
More informationFUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT
RESIDENTIAL DEVELOPMENT 174 LAKESHORE ROAD WEST TOWN OF OAKVILLE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT Prepared For: BIDDINGTON GROUP Original June 16, 2017 Revised September 12, 2017 Revised
More informationHALTON REGION PUBLIC WORKS YARD
HALTON REGION PUBLIC WORKS YARD Stormwater Management Report Project Location: 2195 North Service Road, Oakville, ON Prepared for: The Region of Halton 690 Dorval Drive Oakville, ON Prepared by: MTE Consultants
More informationSOVEREIGN STREET TOWNHOUSES
SOVEREIGN STREET TOWNHOUSES Functional Servicing and Stormwater Management Report Project Location: 2286-2298 Sovereign Street Oakville, Ontario Prepared for: MB1 Development Consulting Inc. 1489 Abbeywood
More informationD. B. G R A Y E N G I N E E R I N G I N C.
SERVICING BRIEF 406-408 Bank Street Ottawa, Ontario Report No. 10015-SB December 13, 2011 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading & Drainage - Storm & Sanitary Sewers
More informationCENTRE POINT SOUTH RESIDENTIAL DEVELOPMENT
CENTRE POINT SOUTH RESIDENTIAL DEVELOPMENT Municipality of Grey Highlands Stormwater Management Report prepared by: C.C. Tatham & Associates Ltd. 115 Sandford Fleming Drive, Suite 200 Collingwood, ON L9Y
More informationSITE SERVICING PRELIMINARY DESIGN BRIEF
855 Carling Avenue Proposed Redevelopment SITE SERVICING PRELIMINARY DESIGN BRIEF March 2010 March 23, 2010 RVA 081785 Arnon Corporation 1801 Woodward Dr. Ottawa, ON K2C 0R3 Attention: Mike Casey Re: 855
More informationStormwater Management Report Bachman Terrace Residential Development
Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document
More informationD. B. G R A Y E N G I N E E R I N G I N C.
SERVICING BRIEF 2200 Prince of Wales Drive Ottawa, Ontario Report No. 11068-SB February 3, 2012 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading & Drainage - Storm & Sanitary
More informationDunpar Developments Inc.
Dunpar Developments Inc. Proposed Townhouse Development 2158, 2168, 2180 and 2192 Trafalgar Road Oakville, Ontario Functional Servicing and Stormwater Management Report (in Support of a Re-Zoning and Site
More informationSt. Boniface Industrial Park Phase 2 Municipal Servicing Report
St. Boniface Industrial Park Phase 2 Municipal Servicing Report Prepared for: City of Winnipeg Prepared by: Stantec Consulting Ltd. File: 116809351 November 5, 2015 ST. BONIFACE INDUSTRIAL PARK PHASE 2
More informationSECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES
SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable
More informationD. B. G R A Y E N G I N E E R I N G I N C.
SERVICING BRIEF Mutchmor Public School Addition 185 Fifth Avenue Ottawa, Ontario Report No. 12073-SB February 15, 2013 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading & Drainage
More informationFUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE
FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY FOR CITY OF OTTAWA PROJECT NO.: 11-532 FOR TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Existing Conditions... 2 1.2 Required Permits / Approvals...
More informationOHM Groups. FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph August 5, Prepared By:
Prepared By: OHM Groups FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph 114169 August 5, 2015 Guelph Owen Sound Listowel Kitchener Exeter Hamilton GTA 650 Woodlawn Rd. W., Block C, Unit 2, Guelph
More informationPRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc.
PRELIMINARY MUNICIPAL SERVICING REPORT SUBDIVISION Prepared for: North Grassie Properties Inc. Prepared by: Stantec Consulting Ltd. 905 Waverley St. Winnipeg, MB R3T 5P4 July 2012 File: 116808030 SUBDIVISION
More informationFunctional Servicing Report. Winston Park West Proposed Business Park Development Project. Infrastructure Ontario (IO) September MU1
Functional Servicing Report Winston Park West Proposed Business Park Development Project (IO) September 2011 14-11208-001-MU1 Winston Park West 2 TABLE OF CONTENTS Page 1.0 INTRODUCTION... 3 1.1 SITE DESCRIPTION...
More informationSite Servicing & Stormwater Management Report for Site Plan Control Application. Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario
Site Servicing & Stormwater Management Report for Site Plan Control Application Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario Prepared for: Martin Clement Attention: Mr. Martin
More informationSTORMWATER MANAGEMENT REPORT. Dundas Square Gardens Inc. High Rise Residential/Commercial Development
STORMWATER MANAGEMENT REPORT Dundas Square Gardens Inc. Revised: April 6, 2016 Revised: January 12, 2016 Revised: July 10, 2015 OUR FILE: 14-RE-352 June 16, 2014 TABLE OF CONTENTS PAGE 1.0 Scope of work
More informationSilver Seven Corporate Centre Phase 1
SERVICING BRIEF Silver Seven Corporate Centre Phase 1 15 & 19 Frank Nighbor Place and 737 & 777 Silver Seven Road Kanata, Ontario Report No. 12022-SB May 31, 2012 Revised October 23, 2012 D. B. G R A Y
More informationSection H - Site Plan Guidelines
H1 GENERAL REQUIREMENTS The following is an outline of procedures and requirements for preparation and submission of Grading Plans, Site Alteration Plans (Erosion and Sediment Control Plans), Site Servicing
More informationRETENTION BASIN EXAMPLE
-7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary
More informationSump Pumps Office procedures for the Drainage & Grading section
County of Los Angeles Department of Public Works Building and Safety Division Grading and Drainage Section Sump Pumps Office procedures for the Drainage & Grading section Introduction This manual provides
More informationSection D Sanitary Drainage
D1 INTRODUCTION Sanitary drainage systems shall be designed on the basis of gravity flow under open channel conditions. Any variation from the Design Criteria, the use of pumping stations or siphons, and
More informationNew Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario
New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario Site Servicing and Stormwater Management Report By Mohamad Salame, P.Eng. Kamco Technique Ltee. 60 Grand Avenue North Cambridge, Ontario N1S
More informationTOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements
TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves
More informationFUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT ONTARIO INC. TOWNSHIP OF SOUTHGATE GLENELG RESIDENTIAL DEVELOPMENT
FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT 2358737 ONTARIO INC. TOWNSHIP OF SOUTHGATE GLENELG RESIDENTIAL DEVELOPMENT PREPARED BY: C.F. CROZIER & ASSOCIATES INC. 40 HURON STREET COLLINGWOOD,
More informationLow Impact Industrial Development
Low Impact Industrial Development CREDIT VALLEY CONSERVATION Low Impact Development in Action Conference October 4 th & 5 th, 2012 Presented by: Tim Gallagher, P.Eng., P.E. (Water Resources Engineer) next
More informationENGINEERING REVIEW CHECKLIST City of Mount Clemens
(To be completed by the Developer s & Submitted with ing Plans) DATE: PROJECT NAME: Site Plan Approved: Date DESIGN ENGINEERING COMPANY: ing Company Contact Information: Name: Phone: Email: Owner Contact
More informationWater Resources Management Plan
P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have
More informationWoodbury - Aurora Metro Station
Woodbury - Aurora Metro Station Master Utility Report Aurora, Colorado E. Centrepoint Dr. and E. Alameda Dr. Prepared By: Galloway 6162 S. Willow Drive, Suite 32 Greenwood Village, CO 8111 33.77.8884 POC:
More informationT a b l e o f C o n t e n t s
C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General
More informationvisual otthymo version 2.0
2 visual otthymo version 2.0 R E F E R E N C E M A N U A L Visual OTTHYMO v2.0 Reference Manual July 2002 Table of Contents PROGRAM REFERENCE...1 INTRODUCTION...1 VISUAL OTTHYMO FILES...1 Project Files...1
More informationINITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257
INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion
More informationPROPOSED THREE-STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 19 R-PLAN ROCKINGHAM AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT
PROPOSED THREE-STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 19 R-PLAN 149 1162 ROCKINGHAM AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT REPORT No. R-815-41 T. L. MAK ENGINEERING CONSULTANTS LTD. JUNE 2015
More informationSCHAEFFERS FUNCTIONAL SERVICING REPORT PROPOSED RESIDENTIAL DEVELOPMENT LAKESHORE ROAD WEST TOWN OF OAKVILLE
FUNCTIONAL SERVICING REPORT PROPOSED RESIDENTIAL DEVELOPMENT 346 362 LAKESHORE ROAD WEST TOWN OF OAKVILLE PROJECT 2016-4442 JULY 2017 REVISED: APRIL 2017 C O N S U L T I N G E N G I N E E R S 64 Jardin
More information10 LOUISA STREET - THORNBURY
10 LOUISA STREET - THORNBURY Town of The Blue Mountains Functional Servicing Report prepared by: C.C. Tatham & Associates Ltd. 115 Sandford Fleming Drive, Suite 200 Collingwood, ON L9Y 5A6 Tel: (705) 444-2565
More informationSTORM DRAINS AND IRRIGATION
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 STORM DRAINS AND IRRIGATION 105.1. STORM DRAINS... 105.1 105.2. METHODS OF ANALYSIS... 105.1 105.2.1. Rational Method... 105.1 105.2.2.
More informationSummary of Detention Pond Calculation Canyon Estates American Canyon, California
July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i
More informationCITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM
CITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM 2018 TABLE OF CONTENTS Section Four Water Distribution System SECTION PAGE NUMBER 1. Objective...1 2. Submissions
More informationAPPENDIX E Drainage and Stormwater Management Report
APPENDIX E Drainage and Stormwater Management Report Drainage and Stormwater Management Report Courtneypark Drive East Class EA & Preliminary Design Prepared for: City of Mississauga Prepared by: Stantec
More informationD. B. G R A Y E N G I N E E R I N G I N C.
STORMWATER MANAGEMENT REPORT 22 Perkins Street Ottawa, Ontario Report No. 13030-SWM February 6, 2015 D. B. G R A Y E N G I N E E R I N G I N. Stormwater Management - Grading & Drainage - Storm & Sanitary
More informationExtended Detention Basin Design
Extended Detention Basin Design 1 Extended Detention 2 Ohio Department of Transportation 1 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment 3 Extended Detention
More informationDERRY GREEN BUSINESS PARK WATER AND WASTEWATER SERVICING AREA SERVICING PLAN
DERRY GREEN BUSINESS PARK WATER AND WASTEWATER SERVICING AREA SERVICING PLAN Submitted to: Town of Milton Regional Municipality of Halton Submitted by: AMEC Earth & Environmental 3215 North Service Road
More informationTABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.
TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM SECTION TITLE PAGE 115.1 GENERAL 115.1 115.2 SIZING LINES 115.1 115.3 DISTRIBUTION SYSTEM 115.2 115.3.1 Layout
More informationJulia Bahen, Urban Strategies Inc.
THE MUNICIPAL INFRASTRUCTURE GROUP LTD. 8800 Dufferin Street, Suite 200 Vaughan, Ontario L4K 0C5 T 905.738.5700 F 905.738.0065 www.tmig.ca TECHNICAL MEMORANDUM DATE June 13, 2017 TO CC SUBJECT FROM PROJECT
More informationSTORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR:
Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT Proposed Row House Complex Clare and
More informationCHAPTER 5 WATER SYSTEM DESIGN STANDARDS
CHAPTER 5 WATER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS 5.00 Objective Page 1 5.01 Additional Referenced Standards Page 1 5.02 Special Design Problems Page 2 5.03
More informationPlanning Considerations for Stormwater Management in Alberta. R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013.
Planning Considerations for Stormwater Management in Alberta R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013 Photo Optional Purpose The purpose of urban stormwater management is to provide solutions
More informationCity of Logan Sanitary Sewer Design Standards
City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR
More informationPROPOSED FIVE STOREY MIXED USE BUILDING DEVELOPMENT SITE LOT 2 R PLAN M BANK STREET CITY OF OTTAWA STORM DRAINAGE REPORT
PROPOSED FIVE STOREY MIXED USE BUILDING DEVELOPMENT SITE LOT 2 R PLAN M 2 7 BANK STREET CITY OF OTTAWA STORM DRAINAGE REPORT REPORT R 81 41 (REV. 2) MARCH 2017 T.L. MAK ENGINEERING CONSULTANTS LTD. JULY
More informationExample 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)
Chapter 10 Design Examples Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Example 2: Filter Design in a commercial development
More informationAppendix J Conceptual Design of Watermain and Sanitary Sewer
City of Barrie - Hewitt's Secondary Plan Class Environmental Assessment (Phase 3 and 4) Study Environmental Study Report Appendix J Conceptual Design of Watermain and Sanitary Sewer Hatch 2017 All rights
More informationSECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1
CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1
More informationTHE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT
THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL
More informationTABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method
More informationSection V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES
Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES A. GENERAL 1. The following water system design guidelines are based on Federal, State and local health requirements and the Hilton Head No. 1 Public
More informationStorm Sewers, Page 2
Storm Sewers storm sewer systems are dendritic systems used to collect and direct stormwater runoff storm sewer systems are integral components of any urban infrastructure curbs, gutters and storm inlets
More informationPROCEDURE F-6-1 (formerly referenced by 08-02) Procedures to Govern Separation of Sewers and Watermains
PROCEDURE F-6-1 (formerly referenced by 08-02) Procedures to Govern Separation of Sewers and Watermains PROCEDURE F-6-1 PROCEDURES TO GOVERN THE SEPARATION OF SEWERS AND WATERMAINS 1. Sewers/sewage works
More informationDRAINAGE & DESIGN OF DRAINAGE SYSTEM
Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means
More informationMunicipal Stormwater Ordinances Summary Table
APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which
More informationCITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390
CITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390 ENGINEERING DESIGN STANDARDS Prepared by: Boss Engineering Howell, Michigan October 5, 2016 TABLE OF CONTENTS PART I. INTRODUCTION SECTION 1.0
More informationCity of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development
City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit
More informationDesign Example Residential Subdivision
Design Example Residential Subdivision Rhode Island Stormwater Design and Installation Standards Manual December 2010 Public Training March 22, 2010 Richard Claytor, P.E. 508-833-6600 Appendix D: Site
More informationWATER MAIN EXTENSION DESIGN REQUIREMENTS
This guideline provides minimum requirements for the design of new water main extensions. This guide is not to be used as a substitution for the detailed design of the water system. The Developer s Engineer
More informationSTORMWATER MANAGEMENT STRATEGIES REPORT FOR THREE SISTERS MOUNTAIN VILLAGE PROPERTIES LTD.
STORMWATER MANAGEMENT STRATEGIES REPORT FOR THREE SISTERS MOUNTAIN VILLAGE PROPERTIES LTD. SEPTEMBER 2016 STANDARD LIMITATIONS This report was prepared by MMM Group Limited (MMM) for the account of the
More informationHYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR
HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed
More informationFORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview
Chapter 5: Hydrology Standards Contents 1.0 Overview... 1 1.1 Storm Runoff Determination... 1 1.2 Design Storm Frequencies... 1 1.3 Water Quality Storm Provisions... 2 1.4 Design Storm Return Periods...
More informationFinal Drainage Report
Thornton Electric Substation Project Final Drainage Report December 14, 2016 DRAFT Prepared for: Xcel Energy, 1800 Larimer Street, Suite 400, Denver, Colorado 80202 Prepared by: 350 Indiana Street, Suite
More informationPART A4 STORM DRAINAGE SYSTEM
PART A4 STORM DRAINAGE SYSTEM DECEMBER 2015 PART A4 - STORM DRAINAGE SYSTEM Page 1 1 GENERAL... 2 2 DEFINITIONS... 2 3 SUBMISSIONS AND APPROVALS... 2 MASTER DRAINAGE PLAN... 2 SITE DRAINAGE PLAN... 3 4
More informationDESIGN BRIEF MIX-USE DEVELOPMENT ICON 505 PRESTON STREET OTTAWA, ONTARIO
CLARIDGE HOMES (PRESTON) INC. DESIGN BRIEF MIX-USE DEVELOPMENT ICON 505 PRESTON STREET OTTAWA, ONTARIO PROJECT: 31637-5.2.2 OCTOBER 2014 IBI GROUP PROJECT: 31637-5.2.2 TABLE OF CONTENTS 1. INTRODUCTION...
More informationWESTMINISTER WOODS EAST PHASE 10 (CLAIR/VICTORIA), GUELPH FUNCTIONAL SERVICING REPORT
WESTMINISTER WOODS EAST PHASE 10 (CLAIR/VICTORIA), GUELPH FUNCTIONAL SERVICING REPORT Prepared for: West Minister Woods Ltd. R.R. #2 6783 Wellington Road #34 Cambridge ON N3C 2V4 Prepared by: Stantec Consulting
More informationWinSLAMM v Program Modifications Final, 3/16/19
WinSLAMM v 10.4.1 Program Modifications Final, 3/16/19 1. Printing Set up a printing option for.pdf files for input data and output summary data. 2. Added the Pipe input data to the printing input data
More informationHYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS
HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review
More informationSTORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:
Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON
More informationPreliminary Drainage Analysis
Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue
More information6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON
6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON STORM WATER MANAGEMENT DESIGN BRIEF NEW DEVELOPMENT DRAINAGE SYSTEM REV 0 August 29, 2017 PREPARED BY: HALLEX PROJECT #170532 HALLEX NIAGARA HALLEX HAMILTON
More informationOrleans Family Health Hub
Orleans Family Health Hub Stormwater Management & Servicing Report Type of Document: Site Plan Application Project Name: Orleans Family Health Hub (OFHH) Project Number OTT-00240132-A0 Prepared By: exp
More informationJ.F. Sabourin and Associates Inc. WATER RESOURCES AND ENVIRONMENTAL CONSULTANTS
J.F. Sabourin and Associates Inc. WATER RESOURCES AND ENVIRONMENTAL CONSULTANTS 52 Springbrook Drive Ottawa, Ontario Canada K2S 1B9 TEL: (613) 836-3884 FAX: (613) 836-0332 WEB: www.jfsa.com August 4, 2009
More informationENGINEERING STANDARDS TOWN OF GRAND VALLEY
ENGINEERING STANDARDS TOWN OF GRAND VALLEY Date: November 2013 Consolidated May 2016 AMENDMENTS May 2015 Resolution #2015-05-09 Appendix A-3, Storm Sewer connections May 2016 Resolution #2016-05-14 Amends
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More information255 NORTHFIELD DRIVE EAST
255 NORTHFIELD DRIVE EAST Fire Flow/Water Demand Analysis Project Location: 255 Northfield Drive East Waterloo, Ontario Prepared for: Abbey Ridge Developments Inc. 22 King Street South, Suite 300 Waterloo,
More informationRiverside South Block 3/4, Richcraft Group of Companies Inc., City of Ottawa SERVICING REPORT
Riverside South Block 3/4, Richcraft Group of Companies Inc., City of Ottawa SERVICING REPORT Prepared by: Stantec Consulting Ltd. 1505 Laperriere Avenue Ottawa, ON K1Z 7T1 File: 160401004/83 January 17,
More informationMarianneville Developments Ltd.
Estates of Glenway Project No. L09-301 March 2012 Executive Summary Cole Engineering Group was retained by Marianneville Developments Limited to undertake a Functional Servicing Report in support of the
More informationPART VII - WATER SYSTEM DESIGN CRITERIA
PART VII - WATER SYSTEM DESIGN CRITERIA A. Water Distribution, General 1. The water system layout shall be approved by the City Engineer. The fire hydrant layout shall be approved by the Redwood City Fire
More informationPROPOSED THREE STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 47 R PLAN CROYDEN AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT REPORT R
PROPOSED THREE STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 47 R PLAN 348 351 CROYDEN AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT REPORT R 817 21 T.L. MAK ENGINEERING CONSULTANTS LTD. JUNE 2017 REFERENCE
More informationSTORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:
Civil Geotechnical Structural Environmental Industrial Health & Safety (613) 860-0923 210 Prescott Street P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE
More informationFunctional Servicing Report. Sorensen Court Townhouses. 25 Sorensen Court, Niagara-on-the-Lake, Ontario
Functional Servicing Report Sorensen Court Townhouses 25 Sorensen Court, Niagara-on-the-Lake, Ontario Prepared by: Quartek Group Inc. Engineers, Architects & Planners 89-91 St. Paul Street, Suite 100 St.
More informationSite Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario
Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario Prepared for The C and C Group of Companies Attention: Mr. Bob Cousins
More informationSTORM WATER MANAGEMENT REPORT
Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek
More information