FUNCTIONAL SERVICING REPORT

Size: px
Start display at page:

Download "FUNCTIONAL SERVICING REPORT"

Transcription

1 PROPOSED DEVELOPMENT HIGHWAY 401 AND CONCESSION ROAD 7 PUSLINCH, ONTARIO FUNCTIONAL SERVICING REPORT Prepared For: FARHI HOLDINGS CORPORATION c/o ZELINKA PRIAMO Ltd Original February 12, 2016 Revised September 9, 2016 (to reflect Team discussions and MOE comments) PROJECT No FILE No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

2 i TABLE OF CONTENTS 10 INTRODUCTION 1 20 SCOPE OF WORK 1 30 ON SITE SANITARY WASTE WATER DISPOSAL 2 40 POTABLE WATER SUPPLY AND SUPPLY FOR FIRE FIGHTING 7 50 STORM WATER MANAGEMENT 9 60 EROSION CONTROL GRADING CONSIDERATION PRELIMINARY GEOTECHNICAL AND GROUND WATER INVESTIGATION CONCLUSIONS REFERENCES 17 LIST OF TABLES TABLE 1 - Summary of Land Use Proposed for Sanitary Flow Calculations 3 TABLE 2 - Total Water Demand for Site 7 TABLE 3 - Catchment Characteristics for the Pre-Developed Site 10 TABLE 4 - PREDEVELOPMENT FLOWS 10 TABLE 5 - Catchment Characteristics for the Post-Developed Site 11 TABLE 6 - SUMMARY OF FLOWS FROM POST DEVELOPED SITE TO MILL CREEK 13 TABLE 7 - Summary of Storage Volumes (SWM POND) EXTENDED STORAGE 14 TABLE 8 - Summary of Storage Volumes (Parking surface and pipes) 14 LIST OF FIGURES Figure 1 PROCESS SCHEMATIC FOR ON-SITE SEWAGE SYSTEM 4 Figure 2 Visual Otthymo Predevelopment Model 9 Figure 3 Visual Otthymo Post Development Model 13 PROJECT No 15243

3 ii APPENDIX A Aerial Photo of Existing Site Concept Site Plan Summary of Building Statistics APPENDIX B Visual Otthymo Input & Output APPENDIX C Proposed Conceptual Site Servicing Concept Pre-development Storm Tributary Plan Post-development Storm Tributary Plan PROJECT No 15243

4 1 10 INTRODUCTION The property under study is a 1010 ha site on the north-west corner of Concession Road 7 and Highway 401 in Puslinch Township The site is bounded by existing Concession Road 7 and existing quarry to the north and east, the King s Highway # 401 to the south, existing Sideroad 25 and existing Slovenski Park to the west Currently, the site is vacant Running parallel with Concession Road 7 is a series of hydro poles contained within a hydro easement (see concept Site Plan in appendix A for details) The legal description of the Site is Part of Lot 26, Concession 2, Township of Puslinch and County of Wellington For detailed topography of the existing site conditions, as of October 6th, 2014 refer to the topographic survey prepared by Van Harten Surveying Inc, Land surveyors Based on the topographical map by Van Harten the land basically flows from south to north Mill Creek is located in the northern portion of the Site The site is triangular in shape The northern portion creates the apex of the triangle Towards the north of the Site Mill Creek traverses the site and flows from north east to south west A Preliminary Geotechnical and Groundwater Investigation for the Proposed Farhi Holdings Development was performed by Golder Associates See reference 11 This report gives guidance to the soil and groundwater characteristics of the Site The report gives guidance to on-site potable water supply and on-site waste water treatment It is proposed to construct a new multi-use development, including industrial, retail/restaurant/office space and related parking The site will have access from Concession Road 7 Please refer to the Concept site plan shown in appendix A for more details about the proposed site The site servicing will be contained on Site as outlined in this report This report will evaluate the serviceability of the site with respect to sanitary, water and storm runoff services and also evaluate the storm water management (SWM) strategy that will be implemented to meet the GRCA, MTO and Township requirements 20 SCOPE OF WORK was retained by FARHI HOLDINGS CORPORATION, to review the Site, collect data, evaluate the Site for the proposed mixed Industrial/commercial uses and present the findings in a Functional Servicing Report in support of a Rezoning Application The scope of work in brief involves the following: a) Discussions with the Township and GRCA in order to establish Flood Plain mapping and potential servicing criteria; b) Meetings/conversations with GRCA, Township, MOE and Design Team c) Evaluation of the data and presentation of the findings in a Functional Servicing Report in support of the Rezoning Application The site is zoned Agricultural It is proposed to extend the designation of the Puslinch Economic Development area PA7-1 to the subject lands This is the area intended to service the Township by providing economic activity and employment opportunities PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

5 2 The draft zoning by-law identified proposed for the Subject Site includes the following permitted uses: Bank Bakery A building or construction contractor s yard A business office or professional office A clinic A concrete plant A dry cleaner s distribution station A factory outlet A feed mill A grain storing, weighing and drying operation An industrial use A personal service shop A public use A retail lumber and building supplies yard A restaurant A service trade A transport terminal A veterinarian s clinic A warehouse Accessory retail use Refer to the concept Site Plan by Zelinka Priamo LTD for specific site statistics 30 ON SITE SANITARY WASTE WATER DISPOSAL There are no existing sanitary sewers near the site Any development will have to utilise on site sewage treatment In addition there is no specific development plans (users) in terms of sanitary waste water effluent It is assumed that private on site treatment systems will be incorporated into the effluent treatment Based on the Preliminary Geotechnical and Groundwater Investigation for the Proposed Farhi Holdings Development Highway 401 and Concession Road 7, Puslinch, Ontario, dated August 4, 2015 by Golder Associates indicates that the analysis of groundwater from two groundwater monitoring wells yielded nitrate concentrations between non-detectable (<025 mg/l and 084mg/L with an average of 045 mg/l The report calculates the maximum allowable groundwater nitrate concentration at the property boundary as 28 mg/l PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

6 3 Proposed Redevelopment Site The proposed development will consist of 50% retail/restaurant space and 50% office space The following Table 1 summarizes the proposed uses The following will be used to evaluate the expected population and peak sanitary flows for the site TABLE 1 - Summary of Land Use Proposed for Sanitary Flow Calculations Land Use Proposed Floor Area m 2 (ft 2 ) Retail/restaurant (50% of space) 9,710 (104,480) Office (50% of space) 9,710 (104,480) Based on OBC 2014 Part 8 the following are the expected daily sewage for the site based on the scenario above Restaurant use: assume 60 seats and 210 m2 area Not a 24 hour restaurant 60 seats 125 L/seat/day 125 x 60 = 7500 L/day Retails use: assume 9500 m2 Retails (store) 9500 m2 50L/m2/day 9500 x 5 = 47,500 L/day Office use: assume 9710 m2 or 100 employees Office 9710 m2 75L/93m2/day ) x 75 = L/day Or 100 employees 75L/employee/day 100 x 75 = 7500 L/day TOAL DAILY FLOW = = 133,310 L The conventional septic tank/septic tile field would require an enormous raised tile field bed The raised bed would be in the order of 33,500 m2 The above is a relatively large number In order to treat this large a flow a proprietary treatment system will have to be incorporated and discharged into a large body of water such as a water quality pond and eventually into nearby Mill Creek A potential treatment system is the Waterloo Biofilter system The Waterloo Biofilter system is a synthetic, absorbent filter medium that is configured as a freedraining, attached growth, biological trickling filter to treat sewage and process wastewaters The absorbent Waterloo Biofilter filter medium creates an ideal environment for microbial attachment Beneficial bacteria colonize the interior surfaces of the filter medium where they are protected from predators, desiccation, and freezing These microbes degrade and oxidize organic pollutants, coliform bacteria, ammonium, and other contaminants as the wastewater is retained in the filter medium by capillarity Air passively circulates throughout the filter medium providing an aerobic treatment environment without the need for forced aeration Refer to figure 1 for the process schematic for the Waterloo Biofilter and the accompanying narrative PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

7 4 Figure 1 PROCESS SCHEMATIC FOR ON-SITE SEWAGE SYSTEM Process Narrative: a All flow from the facility will flow by gravity to the ten septic tanks shown in figure 1 See Proposed Conceptual Site Servicing Concept for the on-site sewer lay-out The flow into the septic tanks settles the larger particulates The lighter particles and grease will float out of the septic tanks Septic tanks will provide anaerobic activity which will start the breakdown of the wastewater effluent b The septic tank effluent flows by gravity to four pump tanks The four tanks are joined at the bottom so as to act as one tank The pump tanks store the sewage so that the sewage can be pumped to the Waterloo Bio filter treatment units on an even basis throughout the day c The sewage is pumped from the pump tanks to the Bio filter tanks Each tank contains bio filter medium The treated effluent collects at the bottom and each tank is connected by bottom drains d Approximately ½ of the bio filter effluent is pumped to the inlet to the septic tanks The recirculating of treated effluent helps dilute the incoming sewage and helps in the denitrification process e The other half of the treated sewage is pumped to two ultra violet treatment units The UV units are housed in an above ground control building f The UV treated effluent is discharged to the SWM Pond PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

8 5 Nitrogen removal process with the Waterloo Bio filter system: The process of nitrogen removal is as follows: 1 Septic tank effluent which is high in TKN (Organic-N + NH3-N + NH4-N) flows into a pump chamber and is dosed to the Bio filter In this step TN ~ TKN because Nitrate and Nitrite (NO2-N and NO3-N) is usually very low 2 The Bio filter medium provides an aerobic environment (high in oxygen) where the aerobic microbes use O2 to convert TKN into Nitrate and Nitrite This step is called Nitrification Almost no TN is removed in this step; it is simply converted into different forms 3 Bio filter effluent which is high in Nitrate and Nitrite and low in TKN is re-circulated back to the septic tank 4 The septic tank which is high in organic carbon (BOD) allows anaerobic microbes to convert Nitrate and Nitrite into Nitrogen gas (N2) The Nitrogen gas is released into the atmosphere, thereby removing nitrogen (TN) from the system This step is called Denitrification The Ontario Building Code has no requirement for nitrogen removal However, in systems above 10,000 L/day that are under the jurisdiction of the MOE, nitrogen removal must be considered The Waterloo bio filter will achieve the following effluent parameters: 10 mg/l TSS 10 mg/l BOD 8 mg/l Dissolved oxygen 200 cfu/100ml EColi 10 mg/l nitrate 30 mg/l Ammonia 05 mg/l Total phosphorus Temperature note, because treated sanitary effluent will be attenuated within the proposed SWM pond, effluent temperatures will be assumed to equate to daily average air temperature as measured at the nearest EC weather station 73 ph ASSIMILATIVE CAPACITY STUDY: Since the effluent will discharge to a SWM pond and eventually into the nearby Mill Creek an Assimilative Capacity Study was requested by the MOECC to demonstrate that Mill Creek could absorb the discharge The Developer retained Golder Associates to conduct the Mill Creek Assimilative Capacity Study Refer to reference 12 The above noted effluent parameters were given to Golder by Odan/Detech as realistic discharge from the Waterloo bio filter wastewater treatment system The treated effluent shown above are a first iteration If the values work, we will use them in the final design as target values PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

9 6 The purpose of the study is to determine if Mill Creek has the available capacity to assimilate the treated sanitary effluent from the proposed development in order to meet Provincial Water Quality Objectives (PWQO s) The Study will recommend revised treatment objectives if required Based on the conducted study and the results it is Golder s opinion that the proposed design can proceed without any deleterious effects on the receiving watercourse (Mill Creek) WASTE WATER TREATMENT PLANT: The Waterloo Biofilter system (treatment plant) as explained above is shown in plan layout in the proposed Conceptual Site Servicing Concept drawing in appendix C This drawing shows the foot print of the Waterloo Biofilter treatment system located near the SWM pond at the north end of the developable area The internal collection pipes and manholes are shown collecting sewage from the various buildings The treatment plant foot print is a scaled version of figure 1 the process schematic The tanks, pumps, building etc should fit with in the foot print Additional foot print area has been provided to accommodate grading considerations in the treatment plant design The waste water treated effluent will then discharge to the SWM pond micro pool for additional dilution The flow to Mill Creek will be via a pond discharge pipe, then to a ditch system prior to release to Mill Creek PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

10 7 40 POTABLE WATER SUPPLY AND SUPPLY FOR FIRE FIGHTING There are no existing water mains near the site nor will any be available in the near future Any development will have to utilise on site drilled wells in order to supply potable water and fire flow water In addition there is no specific development plans (users) in terms of water use It is assumed that private on site drilled wells will be incorporated Based on the Preliminary Geotechnical and Groundwater Investigation for the Proposed Farhi Holdings Development Highway 401 and Concession Road 7, Puslinch, Ontario, August 4, 2015 by Golder Associates indicates that the nearby bedrock aquifer can supply an average of 50 L/min Golder further states that a test well is not required at the rezoning stage due to the well-established aquifer characteristics in the area A PTTW from the MOE will be required for quantities greater than 50,000 L/day TABLE 2 - Total Water Demand for Site Total Daily 134,000 L 35,399 usg Peak Day Demand 23 L/sec 124 usgm * Fire Flow Demand Flow rate 150 L/sec Vol = 1,439,440 L 2378 usgm 380,260 usg A Peak day factor of 15 will apply over a 12 hour period The peak hour factor for commercial type developments is not much different than the peak day *Based on OFM (Ontario Fire guideline the volume of fire water required is: Q = KVStot K = 19 Table 1 of the guide (Note assumed value based on assumed non-combustible but non fire resistant rating V = 15,152m2 x 5m height = 75,760 m3 S tot = 1+ [(S side1) + (S side2) + (S side3) etc] S tot = 10 There is no exposure for any building Q = 19 x x 10 = 1,439,440 L Minimum water flow rate From table 2 of the guide 9000 L/min (2377 usgm) PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

11 8 STORAGE REQUIREMENTS: A) POTABE WATER The volume for potable water will require a storage cistern to store and offset the peaking factor flows The size and location to be determined during final design B) FIRE FLOW WATER The volume required for fire flow is a onetime fill up and a jockey pump to maintain the required level If a storage cistern were to be used a potential size is 33 m x 15 m x 33 m inside dimensions this will give 1485 m3 with 03 m freeboard WELL DELIVERY Golder states that the bedrock aquifer can supply on average 50 L/min taking the conservative side that the entire potable water requirements will have to be replenished the time to replenish the tank is = 893 min = 15 hours The pumps from three wells can replenish the potable supply It should be noted that the well pumps could be activated during the day which would only require 2 wells FINAL DESIGN CONSIDERATIONS 1) If an internal firefighting system of pipes and hydrants were to be implemented it would follow the criteria set out by the Ministry of the Environment Design Guidelines for Drinking- Water Systems 2008 According to the MOE criteria the allowable pressures are as follows: Condition Allowable Pressures (kpa) min max 1) Min Hour ) Peak Hour ) Peak Day + Fire Flow ) Depending on the type of sanitary treatment system chosen and final uses, the SWM Pond permanent pool micro bay could be considered as a reservoir for Fire flow water A proper pond liner, ice formation consideration of 600 mm and evaporation rates will have to be addressed in the final design PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

12 9 50 STORM WATER MANAGEMENT Storm water management for the proposed development will follow the storm water criteria as defined by the GRCA as follows: 1 The allowable post-development peak flow for the proposed development will be limited to the predevelopment levels for storms from the 2 year up to the 100 year storm event 2 Storm run-off from the site would be required to achieve the enhanced level as per the MOE 2003 guidelines which means 80 % TSS removal 3 Water balance to mimic predevelopment conditions METHODLOLOGY: Visual Otthymo (VO2) will be used for modelling the pre and post development flows Design storm data for the City of Guelph 2 year to 100 year storms are shown below Using Visual Otthymo 232 to perform storm water runoff analysis, these storms will be used to show that the storm drainage up to the 100 year event will be accommodated on-site The 100 year storm will be used to determine the total storage required on site 2 year Storm: I 2 = 743 / (T+ 6) where: I = intensity (mm/hr) 5 year storm: I 5 = 1593 / (T + 11) T= time of concentration (minutes) 10 year storm: I 10 = 1593 / (T + 12) year storm: I 25 = 3158 / (T + 15) year storm: I 50 = 3886 / (T + 16) Year Storm: I 100 = 4688 / (T + 17) 9624 As shown in Pre Development Storm Tributary Areas in Appendix C, the majority of the existing site drains north to Mill Creek, with a smaller portion draining to Highway 401 The existing drainage pattern will be maintained PRE-DEVELOPMENT: Figure 2 Visual Otthymo Predevelopment Model Flow to Mill Creek 1 AREA = 691 Flow to Hwy AREA = 055 PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

13 10 TABLE 3 - Catchment Characteristics for the Pre-Developed Site Area Area (ha) Hydrograph Method % impervious imperviousnes s directly connected % Loss Method for Pervious Area CN for Pervious Area Initial Abstraction for Pervious (mm) Time to peak (Tp) (hr) Area 1 to Creek 691 NASHyd 0 - SCS Area 2 to NASHyd 0 - SCS TOTAL 746 Existing soil top 16 m is silty sand justifying the CN of 74 ALLOWABLE FLOW The following Table 4 summarizes the allowable release rate for the site TABLE 4 - PREDEVELOPMENT FLOWS Outlet Description Flow (L/sec) 2 year 5 year 10 year 25 year 50 year 100 year 1 North to Mill Creek South to HWY PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

14 11 Post Development Flow Analysis: For the purposes of post development analysis, the post development storm tributary areas of the subject site have been identified as shown in Appendix C In order to control the post development flows to the allowable flow rate, on-site drainage storage will be required Visual OTTHYMO 232 will be used to model and determine the detention volume required For drainage areas with significant imperviousness the calculation of effective rainfall in Visual OTTHYMO is accomplished using the Standhyd method This method is used in urban watersheds to simulate runoff by combining two parallel standard unit hydrographs resulting from the effective rainfall intensity over the pervious and impervious surfaces For pervious surfaces, losses are calculated using the SCS modified CN method The following Table 5 summarizes the parameters used in Visual OTTHYMO to characterize the post development catchment areas TABLE 5 - Catchment Characteristics for the Post-Developed Site Area Area (ha) Hydrograph Method % impervious imperviousness directly connected % Loss Method for Pervious Area CN for Pervious Area Initial Abstraction for Pervious (mm) Time to peak (Tp) (hr) Area 1 (roof) 023 StandHyd SCS Area 2 (roof) 019 StandHyd SCS Area 3 (roof) 152 StandHyd SCS Area 4 (parking) 354 StandHyd SCS Area 5 (Pond) 070 StandHyd SCS Area 6 (undeveloped) Area 7 undeveloped to MTO 401 TOTAL NASHyd - - SCS NASHyd - - SCS Note: pre and post areas match The other site areas are not to be disturbed PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

15 12 POND STAGE/STORAGE/DISCHARGE CHARACTERISTICS MOE POND CALCULATIONS Farhi-Puslinch Pond Drainage Area: 618 ha Flow to Pond % Impervious: 85 % Storage Volume for Impervious Level: 250 (m 3 /ha) Pond Volume: 1545 m 3 MOE table 32 Extended Detention Volume: 247 m 3 WEIR IS SHARP CRESTED Q weir = 18 x L x (head)^ year storm Stage Discharge AREA OF TOP POND (m2 orifice 1 orifice 2 Elevation Increment: 010 m 010 m AREA OF POND NWL (m2) = Orifice Coefficient: Orifice area m m2 Length of Weir L = - Orifice Size: 200 mm 450 mm Weir elevation = - Orifice Invert 309 m 310 m Outlet HGL= - Elevation Description Bottom Elevation (m) Top Elevation (m) Volume (m 3 ) Extended Volume (m 3 ) Discharge orifice1 (m 3 /s) Discharge orifice2 (m 3 /s) Discharge weir (m 3 /s) Total Discharge (m 3 /s) Stage (m) Pond Area (m2) Bottom of Pond Top of permanent pool level giving 030m freeboard Top of Pond From Civil 3D Summary Required Provided Forebays Micropool Permanent Pool Volume (m 3 ) From Civil 3D Extended Pool Volume (m 3 ) To 030m free board to top Storm Event Storage Volume Required (m 3 ) HGL Elevation (m) 25 mm year From Civil 3D From Otthymo or XPSWMM PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

16 13 Figure 3 Visual Otthymo Post Development Model 10 Flow to Mill Creek AREA = SWM Pond Storage AREA = Area 5 EXISTING Undeveloped AREA = Area 4 Pond Block AREA = Parking Lot Storage 2 AREA 2 ROOF AREA = AREA 2 ROOF AREA = AREA 3 PARKING AREA = AREA 3 ROOF AREA = Area 7 Flow to 401 Undeveloped AREA = 053 TABLE 6 - SUMMARY OF FLOWS FROM POST DEVELOPED SITE TO MILL CREEK Storm Event Post Developed Flow (L/s) TO MILL CREEK TO HWY 401 Allowable Flow (L/s) Post Developed Flow (L/s) Allowable Flow (L/s) 2 Year Storm Year Storm Year Storm Year Storm Year Storm Year Storm PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

17 14 Table 7 and 8 below demonstrates that the post development flows can be contained via the SWM Pond and parking lot storage TABLE 7 - Summary of Storage Volumes (SWM POND) EXTENDED STORAGE Storm Event Required (m 3 ) Provided (m 3 ) 2 year year year year year year TABLE 8 - Summary of Storage Volumes (Parking surface and pipes) Storm Event Required (m 3 ) Provided (m 3 ) 2 year year year year year year Water Quality Water Quality Targets Total Suspended Solids (TSS) (a) The target is the long term-average removal of 80% of the Total Suspended Solids (TSS) on an annual loading basis from all runoff leaving the proposed development site based on the post-development level of imperviousness This will be achieved via a Wet Pond Refer to pond calculations above PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

18 15 Water Balance: The Township of Puslinch target for water balance is to retain storm water on-site, to the extent practicable to achieve the same level of annual volume of overland runoff from the site in the pre-development (existing) condition, with that of the post development condition The difference is to be made up with LID methods such as on-site for infiltration basins such as soak away pits, evapo-transpiration and/or rainwater harvesting Note, during final design percolation tests will be taken at soak away pit locations The best way to achieve water balance is to use clean roof runoff and discharge into soak away pits The buildings are about 194 ha The following template calculates the approximate size of the soak away pit required Note the final design will more than likely have three soak-away pits, however the Vpit total will be similar to that shown below We are assuming a runoff capture from the roof of up to 20 mm of rain and a percolation rate of 50 mm/hr SOAK-AWAY PIT CALCULATION TEMPLATE PROJECT: FARHI- PUSLINCH SOAK-AWAY NAME: SOAKAWAY 1 PROJECT No : Location of soak-away pit: TBD UNIT DESCRIPTION A = 1,000V / (Pn t) d = P t/1000 P= 50 mm/hr Where: t = 48 hr d = 240 m A = Filter bed surface area (m2) n= V = Water volume (m3) t = time to drain (hr) n = void space ratio for aggregate used V= 388 m3 Atrib m2 (note: void space ratio of 04 to be used) runoff 20 mm d = P t/1000 Where: d = maximum soak-away depth (m) A = 1,000V / (Pn t) P= infiltration rate for native soils (mm/hr) t = time to drain (hr) Af= 404 m2 Af provided = 680 m2 Vpit req'd = V/n Vpit provided = L x W x d Vpit req'd = 970 m3 L = 40 m L = length of pit (m) Vpit provided = 1020 m3 W = 17 m W = width of pit (m) d = 15 m d = depth of pit (m) Atrib IS ROOF AREA PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

19 16 60 EROSION CONTROL Erosion and sediment controls for the site will be implemented according to The Ministry of Natural Resources Guidelines on Erosion and Sediment Control for Urban Construction Sites 70 GRADING CONSIDERATION Grading for the proposed site will be such that major overland flow will be directed toward the SWM Pond This will involve grading the Site from South east to north-west The grades as shown on the grading and servicing plan indicate the Site will spill to SWM Pond once 030 m of ponding occurs above the catch basins on site Note for spill to occur, a storm above the 100 year storm level will be required 80 PRELIMINARY GEOTECHNICAL AND GROUND WATER INVESTIGATION A Preliminary Geotechnical and Groundwater Investigation for the Proposed Farhi Holdings Development was performed by Golder Associates See reference 11 This report gives guidance to the soil and groundwater characteristics of the Site The report gives guidance to on-site potable water supply and on-site waste water treatment 90 CONCLUSIONS From our investigation the site is serviceable utilizing: 1 On-site sewage disposal as per this report 2 A well drilled on site into the existing aquifer for Potable water 3 Utilizing a pond or cistern for firefighting water 4 SWM as outlined in this report Storm water management can be accommodated with onsite storage as described in this report The post development 2 year and 100 year storm design has been maintained below the allowable flow rate for the site 5 Water balance can be utilized by infiltrating clean roof water into soak-away pits vertically connected to the native sand/gravel layer PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

20 REFERENCES 1 Storm water Management Planning and Design Manual, Ontario Ministry of the Environment, March New Jersey Storm Water Best Management Practices Manual, April MOEE Technical Guideline for Individual On-Site Sewage systems: Water Quality Impact Risk Assessment, Procedure D-5-4, August MOEE Technical Guideline B-7 Incorporation of the Reasonable Use Concept into MOEE Groundwater Management Activities, April Ministry of the Environment Design Guidelines for Drinking-Water Systems Ministry of the Environment Design Guidelines for Sewage Works Greater Golden Horseshoe Area Conservation Authorities EROSION & SEDIMENT CONTROL GUIDELINES FOR URBAN CONSTRUCTION, December Ontario Fire Marshall FIRE PROTECTION WATER SUPPLY GUIDELINE FOR PART 3 IN THE ONTARIO BUILDING CODE, October Ontario Building Code Visual OTTHYMO v20, a User s Guide and a Reference Manual 11 Golder Associates Preliminary Geotechnical and Groundwater Investigation, Proposed Farhi Holdings Development Highway 401 and Concession Road 7, Puslinch, Ontario, August 4, Golder Associates Technical Memorandum Mill Creek Assimilative Capacity Study, Proposed Farhi Holdings Development Highway 401 and Concession Road 7, Puslinch, Ontario, July 20, 2016 Respectfully Submitted; The Odan Detech Group Inc Mark Harris, CET John Krpan, PEng PROJECT No File No Farhi Holding-Puslinch-Functional Servicing Report-SEPT-2016doc

21 APPENDIX A Aerial Photo of Existing Site Concept Site Plan + Summary of Building Statistics

22 Aerial Photo of Existing Site Subject Site

23

24 APPENDIX B Visual Otthymo Input & Output Pre-development Post-development

25 PRE-DEVELOPMENT

26 =========================================================================================================== V V I SSSSS U U A L V V I SS U U A A L V V I SS U U AAAAA L V V I SS U U A A L VV I SSSSS UUUUU A A LLLLL OOO TTTTT TTTTT H H Y Y M M OOO O O T T H H Y Y MM MM O O O O T T H H Y M M O O OOO T T H H Y M M OOO Developed and Distributed by Clarifica Inc Copyright 1996, 2007 Clarifica Inc All rights reserved ***** D E T A I L E D O U T P U T ***** Input filename: C:\Program Files (x86)\visual OTTHYMO 233\voindat Output filename: C:\Users\John\Documents\PROJECTS\15243-FARHI HOLDINGS-PUSLINCH\OTTHYMO\EXISTINGout Summary filename: C:\Users\John\Documents\PROJECTS\15243-FARHI HOLDINGS-PUSLINCH\OTTHYMO\EXISTINGsum DATE: 9/9/2016 TIME: 3:57:23 PM USER: COMMENTS: **************************** ** SIMULATION NUMBER: 1 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 3654 mm B= 6000 C= 799 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr

27 Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 093 (i) TIME TO PEAK (hrs)= 2000 RUNOFF VOLUME (mm)= 8236 TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 225 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 013 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= 8234 TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 225 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY **************************** ** SIMULATION NUMBER: 2 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 4955 mm B= C= 879 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr

28 Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 188 (i) TIME TO PEAK (hrs)= 1950 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 299 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 026 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 299 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY **************************** ** SIMULATION NUMBER: 3 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 5862 mm B= C= 908 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr

29 Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 268 (i) TIME TO PEAK (hrs)= 1950 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 343 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 038 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 343 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY **************************** ** SIMULATION NUMBER: 4 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 7080 mm B= C= 936 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 379 (i)

30 TIME TO PEAK (hrs)= 1950 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 394 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 052 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 394 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY **************************** ** SIMULATION NUMBER: 5 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 8032 mm B= C= 950 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 475 (i) TIME TO PEAK (hrs)= 1950 RUNOFF VOLUME (mm)= 34473

31 TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 429 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 066 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 429 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY **************************** ** SIMULATION NUMBER: 6 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 8987 mm B= C= 962 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0001) Area (ha)= 691 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 50 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr Unit Hyd Qpeak (cms)= 528 PEAK FLOW (cms)= 578 (i) TIME TO PEAK (hrs)= 1950 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 460 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY

32 NASHYD (0002) Area (ha)= 55 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 20 Unit Hyd Qpeak (cms)= 105 PEAK FLOW (cms)= 080 (i) TIME TO PEAK (hrs)= 1550 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 460 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY FINISH ===========================================================================================================

33 POST-DEVELOPMENT

34 =========================================================================================================== V V I SSSSS U U A L V V I SS U U A A L V V I SS U U AAAAA L V V I SS U U A A L VV I SSSSS UUUUU A A LLLLL OOO TTTTT TTTTT H H Y Y M M OOO O O T T H H Y Y MM MM O O O O T T H H Y M M O O OOO T T H H Y M M OOO Developed and Distributed by Clarifica Inc Copyright 1996, 2007 Clarifica Inc All rights reserved ***** D E T A I L E D O U T P U T ***** Input filename: C:\Program Files (x86)\visual OTTHYMO 233\voindat Output filename: C:\Users\John\Documents\PROJECTS\15243-FARHI HOLDINGS-PUSLINCH\OTTHYMO\POSTout Summary filename: C:\Users\John\Documents\PROJECTS\15243-FARHI HOLDINGS-PUSLINCH\OTTHYMO\POSTsum DATE: 9/12/2016 TIME: 12:19:03 AM USER: COMMENTS: **************************** ** SIMULATION NUMBER: 1 ** **************************** CHICAGO STORM IDF curve parameters: A= Ptotal= 3654 mm B= 6000 C= 799 used in: INTENSITY = A / (t + B)^C Duration of storm = 400 hrs Storm time step = 1000 min Time to peak ratio = 33 TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr NASHYD (0009) Area (ha)= 75 Curve Number (CN)= 740 ID= 1 DT= 30 min Ia (mm)= 500 # of Linear Res(N)= 300 UH Tp(hrs)= 22 NOTE: RAINFALL WAS TRANSFORMED TO 30 MIN TIME STEP ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr hrs mm/hr hrs mm/hr

35 Unit Hyd Qpeak (cms)= 130 PEAK FLOW (cms)= 017 (i) TIME TO PEAK (hrs)= 1600 RUNOFF VOLUME (mm)= 8235 TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = 225 (i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0019) Area (ha)= 19 ID= 1 DT= 30 min Total Imp(%)= 9900 Dir Conn(%)= 9900 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 149 (ii) 297 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF IS SMALLER THAN TIME STEP! (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 990 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0018) Area (ha)= 354 ID= 1 DT= 30 min Total Imp(%)= 8500 Dir Conn(%)= 8500 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 359 (ii) 743 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 740 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0001) Area (ha)= 152 ID= 1 DT= 30 min Total Imp(%)= 9900 Dir Conn(%)= 9900 IMPERVIOUS PERVIOUS (i) Surface Area (ha)=

36 Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 279 (ii) 427 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF IS SMALLER THAN TIME STEP! (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 990 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0002) Area (ha)= 23 ID= 1 DT= 30 min Total Imp(%)= 9900 Dir Conn(%)= 9900 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 158 (ii) 253 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF IS SMALLER THAN TIME STEP! (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 990 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY STANDHYD (0011) Area (ha)= 70 ID= 1 DT= 30 min Total Imp(%)= 6000 Dir Conn(%)= 6000 IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep Storage (mm)= Average Slope (%)= Length (m)= Mannings n = MaxEffInten(mm/hr)= over (min) Storage Coeff (min)= 221 (ii) 874 (ii) Unit Hyd Tpeak (min)= Unit Hyd peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF IS SMALLER THAN TIME STEP! (i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 740 Ia = Dep Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY

RETAIL UNITS GUELPH. November Prepared For: File No Engineering Report.docx F: (905) P: (905) BURLINGTON, ONTARIO

RETAIL UNITS GUELPH. November Prepared For: File No Engineering Report.docx F: (905) P: (905) BURLINGTON, ONTARIO The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED COMMERCIAL RETAIL UNITS GUELPH LINE AND UPPER MIDDLE

More information

SERVICING AND STORM WATER MANAGEMENT REPORT

SERVICING AND STORM WATER MANAGEMENT REPORT The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED MASTERMIND TOYS RETAIL BUILDING PLACE D ORLEANS

More information

SERVICING AND STORM WATER MANAGEMENT REPORT

SERVICING AND STORM WATER MANAGEMENT REPORT The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED BANK PLACE D ORLEANS MALL OTTAWA, ONTARIO SERVICING

More information

PROPOSED FOOD STORE 150 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For:

PROPOSED FOOD STORE 150 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For: PROPOSED FOOD STORE 150 TORONTO STREET SOUTH Job No. 16227 ENGINEERING REPORT Prepared For: MAVERICK DEVELOPMENT CORPORATION 150 Woodbine Avenue Suite 3005 Toronto, Ontario Prepared By: The Odan/Detech

More information

PROPOSED COMMERCIAL DEVELOPMENT 217 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For:

PROPOSED COMMERCIAL DEVELOPMENT 217 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For: PROPOSED COMMERCIAL DEVELOPMENT 217 TORONTO STREET SOUTH MARKDALE, ONTARIO Job No. 17232 ENGINEERING REPORT Prepared For: 219 Toronto Street South Developments Inc. 150 Woodbine Avenue Suite 3005 Toronto,

More information

THE ODAN/DETECH GROUP INC.

THE ODAN/DETECH GROUP INC. THE ODAN/DETECH GROUP INC. 5230 SOUTH SERVICE ROAD, BURLINGTON, ONTARIO L7L 5K2 TELEPHONE: (905) 632-3811 FACSIMILE: (905) 632-3363 Email: detech@odandetech.com PROJECT No. : 13233 FUNCTIONAL SERVICING

More information

THE ODAN/DETECH GROUP INC.

THE ODAN/DETECH GROUP INC. 5230 SOUTH SERVICE ROAD, BURLINGTON, ONTARIO L7L 5K2 TELEPHONE: (905) 632-3811 FACSIMILE: (905) 632-3363 Email: detech@odandetechcom PROJECT No : 10232 FUNCTIONAL SERVICING REPORT FOR BOLTON DISTRIBUTION

More information

Functional Servicing Report

Functional Servicing Report Functional Servicing Report 4063 UPPER MIDDLE ROAD CITY OF BURLINGTON January 2017 SLA File: 16115 3228 South Service Road, Suite 105, East Wing Burlington, Ontario L7N 3H8 Tel. (905) 631-6978 Fax (905)

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT RESIDENTIAL DEVELOPMENT 174 LAKESHORE ROAD WEST TOWN OF OAKVILLE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT Prepared For: BIDDINGTON GROUP Original June 16, 2017 Revised September 12, 2017 Revised

More information

CENTRE POINT SOUTH RESIDENTIAL DEVELOPMENT

CENTRE POINT SOUTH RESIDENTIAL DEVELOPMENT CENTRE POINT SOUTH RESIDENTIAL DEVELOPMENT Municipality of Grey Highlands Stormwater Management Report prepared by: C.C. Tatham & Associates Ltd. 115 Sandford Fleming Drive, Suite 200 Collingwood, ON L9Y

More information

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR: Civil Geotechnical Structural Environmental Industrial Health & Safety (613) 860-0923 210 Prescott Street P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE

More information

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR: Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON

More information

SOVEREIGN STREET TOWNHOUSES

SOVEREIGN STREET TOWNHOUSES SOVEREIGN STREET TOWNHOUSES Functional Servicing and Stormwater Management Report Project Location: 2286-2298 Sovereign Street Oakville, Ontario Prepared for: MB1 Development Consulting Inc. 1489 Abbeywood

More information

P: (905) F: (905) PROPOSED BANK. Prepared For: ENT INC. JUNE Rev 0.docx

P: (905) F: (905) PROPOSED BANK. Prepared For: ENT INC. JUNE Rev 0.docx The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED BANK PLACE D ORLEANS MALL OTTAWA, ONTARIO SERVICING

More information

HALTON REGION PUBLIC WORKS YARD

HALTON REGION PUBLIC WORKS YARD HALTON REGION PUBLIC WORKS YARD Stormwater Management Report Project Location: 2195 North Service Road, Oakville, ON Prepared for: The Region of Halton 690 Dorval Drive Oakville, ON Prepared by: MTE Consultants

More information

PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART. January 2016

PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART. January 2016 The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG

More information

OHM Groups. FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph August 5, Prepared By:

OHM Groups. FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph August 5, Prepared By: Prepared By: OHM Groups FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph 114169 August 5, 2015 Guelph Owen Sound Listowel Kitchener Exeter Hamilton GTA 650 Woodlawn Rd. W., Block C, Unit 2, Guelph

More information

Planning Considerations for Stormwater Management in Alberta. R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013.

Planning Considerations for Stormwater Management in Alberta. R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013. Planning Considerations for Stormwater Management in Alberta R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013 Photo Optional Purpose The purpose of urban stormwater management is to provide solutions

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY FOR CITY OF OTTAWA PROJECT NO.: 11-532 FOR TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Existing Conditions... 2 1.2 Required Permits / Approvals...

More information

PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART

PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG ROAD OTTAWA, ONTARIO ENGINEERING REPORT SHOPPERS DRUG MART The Odan/Detech Group Inc. P: (905) 632-3811 F: (905) 632-3363 5230 SOUTH SERVICE ROAD, UNIT 107 BURLINGTON, ONTARIO, L7L 5K2 www.odandetech.com PROPOSED SHOPPERS DRUG MART RIVER ROAD AND EARL ARMSTRONG

More information

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario Site Servicing and Stormwater Management Report By Mohamad Salame, P.Eng. Kamco Technique Ltee. 60 Grand Avenue North Cambridge, Ontario N1S

More information

Best Practice in Sewage and Effluent Treatment Technologies

Best Practice in Sewage and Effluent Treatment Technologies Best Practice in Sewage and Effluent Treatment Technologies Contents 1 Wastewater - Introduction 1 1.1 Earth s ecological system 1 1.1.1 Water effect on ecology 2 1.1.2 Wastewater generation 3 1.2 Wastewater

More information

APPENDIX E Drainage and Stormwater Management Report

APPENDIX E Drainage and Stormwater Management Report APPENDIX E Drainage and Stormwater Management Report Drainage and Stormwater Management Report Courtneypark Drive East Class EA & Preliminary Design Prepared for: City of Mississauga Prepared by: Stantec

More information

STANLEY FARM SUBDIVISION

STANLEY FARM SUBDIVISION STANLEY FARM SUBDIVISION SERVICING OPTIONS AND STORMWATER MANAGEMENT REPORT BRIEF CITY OF OTTAWA PREPARED FOR: STANLEY FARM DEVELOPMENTS PREPARED BY: (November 2014 - Revision 0) LOT 9, CONCESSION 5 WATER

More information

WinSLAMM v Program Modifications Final, 3/16/19

WinSLAMM v Program Modifications Final, 3/16/19 WinSLAMM v 10.4.1 Program Modifications Final, 3/16/19 1. Printing Set up a printing option for.pdf files for input data and output summary data. 2. Added the Pipe input data to the printing input data

More information

WinSLAMM v Program Modifications Final, 12/12/17

WinSLAMM v Program Modifications Final, 12/12/17 WinSLAMM v 10.3.4 Program Modifications Final, 12/12/17 1. Corrected an error in the Biofilter caused by an improperly defined variable that caused an overflow during very long model runs. 2. Corrected

More information

PROPOSED THREE-STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 19 R-PLAN ROCKINGHAM AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT

PROPOSED THREE-STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 19 R-PLAN ROCKINGHAM AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT PROPOSED THREE-STOREY RESIDENTIAL APARTMENT BUILDING SITE LOT 19 R-PLAN 149 1162 ROCKINGHAM AVENUE CITY OF OTTAWA STORM DRAINAGE REPORT REPORT No. R-815-41 T. L. MAK ENGINEERING CONSULTANTS LTD. JUNE 2015

More information

Nitrogen Removal with the Waterloo Biofilter

Nitrogen Removal with the Waterloo Biofilter 1 of 4 October 15, 2004 Dear Engineer, The purpose of this letter is to provide supporting documentation that shows the nitrogen removal capabilities of the Waterloo Biofilter system. Introduction Nitrogen

More information

Biggars Lane Landfill Expansion Environmental Assessment Stormwater Management Assessment County of Brant

Biggars Lane Landfill Expansion Environmental Assessment Stormwater Management Assessment County of Brant R.J. Burnside & Associates Limited 17345 Leslie Street, Suite 200 Newmarket ON L3Y 0A4 CANADA telephone (905) 953-8967 fax (905) 953-8945 web www.rjburnside.com Technical Memorandum Date: Project Name:

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. SERVICING BRIEF 406-408 Bank Street Ottawa, Ontario Report No. 10015-SB December 13, 2011 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading & Drainage - Storm & Sanitary Sewers

More information

Stormwater Management Report Bachman Terrace Residential Development

Stormwater Management Report Bachman Terrace Residential Development Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 [ESS29] UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 Date: Monday 21 st May 2018 Time: 10:00 13:00 INSTRUCTIONS

More information

TABLE B.3 - STORMWATER BMP POLLUTANT REMOVAL EFFICIENCIES

TABLE B.3 - STORMWATER BMP POLLUTANT REMOVAL EFFICIENCIES BMPS DESCRIPTION p p p p TSS TP Sol P TN Stormwater Ponds**, 8 Stormwater Wetland** and extended detention, and some elements of a shallow marsh equivalent capable of treating the full water quality volume.

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

PROPOSED ONE-STOREY WAREHOUSE BUILDING SITE FOR SLAVKO INC. PART OF BLOCK 6 REGISTERED PLAN 4M-351 GREELY INDUSTRIAL PARK McKEOWN DRIVE

PROPOSED ONE-STOREY WAREHOUSE BUILDING SITE FOR SLAVKO INC. PART OF BLOCK 6 REGISTERED PLAN 4M-351 GREELY INDUSTRIAL PARK McKEOWN DRIVE PROPOSED ONE-STOREY WAREHOUSE BUILDING SITE FOR SLAVKO INC. PART OF BLOCK 6 REGISTERED PLAN 4M-351 GREELY INDUSTRIAL PARK 6828 McKEOWN DRIVE CITY OF OTTAWA SERVICEABILITY REPORT REPORT No. R-812-77A T.

More information

Low Impact Industrial Development

Low Impact Industrial Development Low Impact Industrial Development CREDIT VALLEY CONSERVATION Low Impact Development in Action Conference October 4 th & 5 th, 2012 Presented by: Tim Gallagher, P.Eng., P.E. (Water Resources Engineer) next

More information

STORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR:

STORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR: Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT Proposed Row House Complex Clare and

More information

Course: Wastewater Management

Course: Wastewater Management Course: Wastewater Management Prof. M. M. Ghangrekar Questions 1 1. Describe advantages and disadvantages offered by the water carriage system. 2. What are the possible adverse effects when untreated or

More information

The Wetland Biofilter System:

The Wetland Biofilter System: The Wetland Biofilter System: A vertical flow constructed wetland for treatment of manure compost pile leachate water What is the Wetland Biofilter System? Vertical flow constructed wetland Consists of

More information

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management Online ECode Available on Cheltenham Township Website at: http://ecode360.com/14477578 For all regulated

More information

Functional Servicing Report. Winston Park West Proposed Business Park Development Project. Infrastructure Ontario (IO) September MU1

Functional Servicing Report. Winston Park West Proposed Business Park Development Project. Infrastructure Ontario (IO) September MU1 Functional Servicing Report Winston Park West Proposed Business Park Development Project (IO) September 2011 14-11208-001-MU1 Winston Park West 2 TABLE OF CONTENTS Page 1.0 INTRODUCTION... 3 1.1 SITE DESCRIPTION...

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT ONTARIO INC. TOWNSHIP OF SOUTHGATE GLENELG RESIDENTIAL DEVELOPMENT

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT ONTARIO INC. TOWNSHIP OF SOUTHGATE GLENELG RESIDENTIAL DEVELOPMENT FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT REPORT 2358737 ONTARIO INC. TOWNSHIP OF SOUTHGATE GLENELG RESIDENTIAL DEVELOPMENT PREPARED BY: C.F. CROZIER & ASSOCIATES INC. 40 HURON STREET COLLINGWOOD,

More information

3.11 Sand Filter Basin

3.11 Sand Filter Basin 3.11 Sand Filter Basin Type of BMP Priority Level Treatment Mechanisms Maximum Drainage Area Flow-Through Treatment Priority 3 Treatment Control BMP Filtration 25 acres Description The Sand Filter Basin

More information

FUNCTIONAL SERVICING AND STORM WATER MANAGEMENT STUDY PROPOSED COMMERCIAL BUILDING 128 REIS ROAD, CARP CITY OF OTTAWA, ONTARIO PREPARED FOR:

FUNCTIONAL SERVICING AND STORM WATER MANAGEMENT STUDY PROPOSED COMMERCIAL BUILDING 128 REIS ROAD, CARP CITY OF OTTAWA, ONTARIO PREPARED FOR: Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 FUNCTIONAL SERVICING AND STORM WATER MANAGEMENT STUDY

More information

A Hybrid Constructed Wetland System for Decentralized Wastewater Treatment

A Hybrid Constructed Wetland System for Decentralized Wastewater Treatment A Hybrid Constructed Wetland System for Decentralized Wastewater Treatment C. Kinsley 1, A. Crolla 1, J. Rode 1,2, R. Zytner 2 1 Ontario Rural Wastewater Centre, Université de Guelph-Campus d Alfred 2

More information

MEMO. Date: July 4, 2018 Pages: 3 CCTA File: To: Ted Kruska CCTA Via: . Laura Goetz & Amanda Kellett

MEMO. Date: July 4, 2018 Pages: 3 CCTA File: To: Ted Kruska CCTA Via:  . Laura Goetz & Amanda Kellett MEMO Date: July 4, 208 Pages: 3 CCTA File: 3583 To: Ted Kruska CCTA Via: email From: Subject: Laura Goetz & Amanda Kellett Concession 7 Culvert Replacement Hydraulic Analysis C.C. Tatham & Associates Ltd.

More information

DRIP EMITTER SYSTEM STUDY GUIDE

DRIP EMITTER SYSTEM STUDY GUIDE DRIP EMITTER SYSTEM STUDY GUIDE Minimum Criteria for Pressurized Subsurface Absorption Fields Utilizing Emitters. Subsurface systems utilizing emitters may be used in lieu of conventional or other alternative

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe:

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to describe: The different approaches for estimating peak runoff for urban drainage network

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

Infiltration Trench Factsheet

Infiltration Trench Factsheet Infiltration Trench Factsheet Infiltration Trench is a practice that provides temporary storage of runoff using the void spaces within the soil/sand/gravel mixture that is used to backfill the trench for

More information

Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario

Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario Prepared for The C and C Group of Companies Attention: Mr. Bob Cousins

More information

6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON

6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON 6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON STORM WATER MANAGEMENT DESIGN BRIEF NEW DEVELOPMENT DRAINAGE SYSTEM REV 0 August 29, 2017 PREPARED BY: HALLEX PROJECT #170532 HALLEX NIAGARA HALLEX HAMILTON

More information

A Summary of the International Stormwater BMP Database

A Summary of the International Stormwater BMP Database A Summary of the International Stormwater Tuesday, February 12, 2013, 1:00PM Presented by: Katie Blansett, Ph.D., P.E. Pennsylvania Housing Research Center www.engr.psu.edu/phrc Objective The objective

More information

POTABLE WATER SUPPLY DEFINITIONS

POTABLE WATER SUPPLY DEFINITIONS Definitions POTABLE WATER SUPPLY DEFINITIONS AQUIFER. A porous, water-bearing geologic formation. Generally restricted to materials capable of yielding an appreciable supply of water. BASIN. A natural

More information

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage

More information

ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT. Sheldon Smith March 28, Photo Optional

ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT. Sheldon Smith March 28, Photo Optional ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT Sheldon Smith March 28, 2012 Photo Optional TWO BASIC TYPES OF CONSTRUCTED WETLANDS Stormwater (SW) Wetlands Treatment Wetlands A Stormwater

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l ATTACHMENT 1 GENERAL FACILITY INFORMATION 1. Facility Name: 2. Type of Facility: 3. Population Served: Present: Design: 4. Flow: Average Maximum Peak 5. Water Quality: Present Design Assumed Actual Source:

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING Question Bank CE2354 - ENVIRONMENTAL ENGINEERING - II Prepared By: Year: 3rd year Semester: 6th Semester R.THENMOZHI / A.P.Civil J.SHANMUGAPRIYA

More information

Stantec Consulting Ltd Hagey Boulevard, Waterloo ON N2L 0A4

Stantec Consulting Ltd Hagey Boulevard, Waterloo ON N2L 0A4 Stantec Consulting Ltd. 100-300 Hagey Boulevard, Waterloo ON N2L 0A4 November 17, 2017 File: 1614-13551/29 Attention: Ms. Nancy Shoemaker Black, Shoemaker, Robinson and Donaldson Ltd. Surveyors 351 Speedvale

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

APPENDIX D. Drainage and Stormwater Management Assessment Memoranda

APPENDIX D. Drainage and Stormwater Management Assessment Memoranda APPENDIX D Drainage and Stormwater Management Assessment Memoranda 610 Chartwell Road, Suite 300 Oakville, Ontario, L6J 4A9 Tel: (905) 823-8500 Fax: (905) 823-8503 Website: www.wspgroup.ca TECHNICAL MEMORANDUM

More information

Blackstone Community Phase 4-8 Functional Servicing Report

Blackstone Community Phase 4-8 Functional Servicing Report Blackstone Community Phase 4-8 Functional Servicing Report Project #160401130 Prepared for: 2129786 Ontario Inc. Prepared by: Stantec Consulting Ltd. Sign-off Sheet This document entitled Blackstone Community

More information

Ayrburn Farm Development Infrastructure Assessment Report

Ayrburn Farm Development Infrastructure Assessment Report Ayrburn Farm Development Infrastructure Assessment Report 1 EXECUTIVE SUMMARY Further to Clark Fortune McDonald & Associates correspondence dated 12 February 2015 please find below the assessment of foul

More information

APPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary

APPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary APPENDIX J-3 Orcem Stormwater Management and Treatment Facilities Design Summary Stormwater Management & Treatment Facilities Design Summary INTRODUCTION KPFF Consulting Engineers has compiled this report

More information

Shirley E. Clark, Ph.D., P.E. October 5, /30/2012

Shirley E. Clark, Ph.D., P.E. October 5, /30/2012 Shirley E. Clark, Ph.D., P.E. October 5, 2012 Prior development decisions have led to directly connected impervious areas and pervious areas with heavily-compacted soils. Prince Georges Cty, MD photo 1

More information

Rational Method vs OTTHYMO, Comparing Peak Discharge Rates By Alex Nichols, P.Eng.

Rational Method vs OTTHYMO, Comparing Peak Discharge Rates By Alex Nichols, P.Eng. Rational Method vs OTTHYMO, Comparing Peak Discharge Rates By Alex Nichols, P.Eng. Urban stormwater management for small site is becoming more complex. All of the methods rely upon statistically derived

More information

Hydrology 101. Impacts of the Urban Environment. Nokomis Knolls Pond Summer June 2008

Hydrology 101. Impacts of the Urban Environment. Nokomis Knolls Pond Summer June 2008 Hydrology 101 Nokomis Knolls Pond Summer 2002 Impacts of the Urban Environment Hydrologic Cycle; What is it? Geography, Topography, Geology, Land Cover and Climate determine the Amount and Behavior of

More information

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario Site Servicing and Stormwater Management Report By Mohamad Salame, P.Eng. Kamco Technique Ltee. 60 Grand Avenue North Cambridge, Ontario N1S

More information

Site Servicing & Stormwater Management Report for Site Plan Control Application. Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario

Site Servicing & Stormwater Management Report for Site Plan Control Application. Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario Site Servicing & Stormwater Management Report for Site Plan Control Application Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario Prepared for: Martin Clement Attention: Mr. Martin

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. SERVICING BRIEF 2200 Prince of Wales Drive Ottawa, Ontario Report No. 11068-SB February 3, 2012 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading & Drainage - Storm & Sanitary

More information

Onsite/Decentralized Treatment is Important Nationally

Onsite/Decentralized Treatment is Important Nationally TITLE 5 SOIL EVALUATOR CERTIFICATION TRAINING ON-SITE SYSTEM BASICS PAUL SPINA, NEIWPCC Prepared for: Commonwealth of Massachusetts Department of Environmental Protection In conjunction with the New England

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228 Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:

More information

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges Detention Pond Design Considering Varying Design Storms Land Development Results in Increased Peak Flow Rates and Runoff Volumes Developed area Robert Pitt Department of Civil, Construction and Environmental

More information

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-871-88-949 Prepared by: Table of Contents Section 1: Overview...

More information

Appendix I: Guidelines for Stormwater Management

Appendix I: Guidelines for Stormwater Management Appendix I: Guidelines for Stormwater Management 1.0 INTRODUCTION This document is Appendix I to the CRCA Environmental Planning Policies (2014). It should be read in conjunction with the CRCA Environmental

More information

Design Example Residential Subdivision

Design Example Residential Subdivision Design Example Residential Subdivision Rhode Island Stormwater Design and Installation Standards Manual December 2010 Public Training March 22, 2010 Richard Claytor, P.E. 508-833-6600 Appendix D: Site

More information

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

WASTEWATER & STORM WATER COLLECTION AND REMOVAL CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE

More information

STORMWATER MANAGEMENT AND IMPAIRED WATERS. Eric H. Livingston Watershed Management Services, LLC Crawfordville, FL

STORMWATER MANAGEMENT AND IMPAIRED WATERS. Eric H. Livingston Watershed Management Services, LLC Crawfordville, FL STORMWATER MANAGEMENT AND IMPAIRED WATERS Eric H. Livingston Watershed Management Services, LLC Crawfordville, FL Impaired Waters Not meet their WQS Loss of designated uses TOTAL MAXIMUM DAILY LOADS Section

More information

APPENDIX F DRAINAGE AND STORMWATER MANAGEMENT TECHNICAL MEMO

APPENDIX F DRAINAGE AND STORMWATER MANAGEMENT TECHNICAL MEMO APPENDIX F DRAINAGE AND STORMWATER MANAGEMENT TECHNICAL MEMO MEMO To: Emily Sangster Date: April 28, 2015 From: Bhavika Patel Job No.: 34-14015-000-B02 Subject: Stormwater Management Impact Assessment

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Landfill design General principles

Landfill design General principles Landfill design General principles Average height of a landfill should be at least 15 m Each section (cell) should accommodate waste to be landfilled during 5 years period Sections/cells should be hydraulically

More information

ST. GEORGE WATER POLLUTION CONTROL PLANT OPTIMIZATION STUDY TECHNICAL MEMORANDUM FLOODPLAIN MODELLING

ST. GEORGE WATER POLLUTION CONTROL PLANT OPTIMIZATION STUDY TECHNICAL MEMORANDUM FLOODPLAIN MODELLING ST. GEORGE WATER POLLUTION CONTROL PLANT OPTIMIZATION STUDY TECHNICAL MEMORANDUM FLOODPLAIN MODELLING GAMSBY AND MANNEROW LIMITED CONSULTING PROFESSIONAL ENGINEERS GUELPH OWEN SOUND LISTOWEL - KITCHENER

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. STORMWATER MANAGEMENT REPORT 22 Perkins Street Ottawa, Ontario Report No. 13030-SWM February 6, 2015 D. B. G R A Y E N G I N E E R I N G I N. Stormwater Management - Grading & Drainage - Storm & Sanitary

More information

Paraprofessional Training Session 1

Paraprofessional Training Session 1 Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor

More information

Appendix F. Flow Duration Basin Design Guidance

Appendix F. Flow Duration Basin Design Guidance Appendix F Flow Duration Basin Design Guidance Appendix F FINAL REPORT F:\SC46\SC46.31\HMP Mar 05\Appendices\Appendix F FLY_HMP.doc MARCH 2005 Appendix F Flow Duration Basin Design Guidance Prepared by

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011

More information

Wastewater treatment for single houses. D. O Dowd

Wastewater treatment for single houses. D. O Dowd Wastewater treatment for single houses 1 * In rural settings, connection to the local authority main sewer is not always possible, so each house has its own separate wastewater treatment system for the

More information

WSUD On-site Detention in xprafts 2013

WSUD On-site Detention in xprafts 2013 WSUD On-site Detention in xprafts 2013 Content 1. Introduction of ODS 2. General a. Impervious Area b. Pervious Area Capture c. Average Allotment Density d. Developed Area/Total Area 3. On-site Detention

More information

visual otthymo version 2.0

visual otthymo version 2.0 2 visual otthymo version 2.0 R E F E R E N C E M A N U A L Visual OTTHYMO v2.0 Reference Manual July 2002 Table of Contents PROGRAM REFERENCE...1 INTRODUCTION...1 VISUAL OTTHYMO FILES...1 Project Files...1

More information

Controlling runon and runoff:

Controlling runon and runoff: Chapter 8. Surface Water Management This chapter explores: runon and runoff what they are, and the risks associated with them. various management options runon reductions, runoff catchbasins, vegetated

More information