1 PROCEDURE FOR THE ISSUANCE (INITIAL AND RENEWAL) OF ENVIRONMENTAL PERMIT / NO OBJECTION CERTIFICATE (NOC) 1.0 PURPOSE This procedure specifies the process of securing Environmental Permit or No Objection Certificate (NOC). 2.0 SCOPE All projects or activities under the Ports, Customs and Free Zone Corporation (PCFC) and Dubai World jurisdiction areas with significant environmental concern. Please see table below for applicability of each type of Environmental Permit or NOC. # Type of Permit Applicability 1 Harbor / Open Sea Discharge Permit For project / activity disposing treated wastewater to harbor or open sea 2 Irrigation Permit For project / activity utilizing treated wastewater for irrigation purposes 3 Groundwater Discharge Permit For project / activity which intends to remove and dispose or reuse underground water 4 Air Emission Permit For project / activity utilizing process or fuel burning stacks with possible air emission or air pollution control equipment 5 Permit to Cut and/or Relocate Trees For project / activity which requires to cut / relocate trees 6 Marine Mammal Related Activity For a specific activity, as described by the permit, which involves marine mammal 6.1 Permit to Operate Captive Marine Mammal Facility 6.2 Permit to Transport Marine Mammal 6.3 Permit to Conduct Scientific Research Marine Mammal 6.4 Permit to Export / Import Marine Mammal For a specific activity, as described by the permit, 7 Aquatic Animal Related Activity which involves aquatic animal 7.1 Permit to Operate Public Aquarium Facility 7.2 Permit to Transport Aquatic Animal 7.3 Permit to Conduct Scientific Research Aquatic Animal REVISION: 02 February 2015 Page 1 of 6

2 7.4 Permit to Export / Import Aquatic Animal 8 No Objection Certificate (NOC) For project which intends to manage a marine area Marine Area Management with significant ecological value 9 Coral Translocation Permit For project which intends to perform coral translocation activity 10 No Objection Certificate (NOC) For project which intends to conduct dredging Dredging and/or Reclamation and/or reclamation activity For project which intends to conduct a certain 11 No Objection Certificate (NOC) activity, apart from those listed above and specified Conditional Environmental Activity in other procedures, with significant environmental concern 12 Permit to Transport Sand For activity that will shift sand from a construction site to another construction area / stockpile area 3.0 PROCEDURE 3.1 Procedure for Open Sea Discharge Permit, Groundwater Discharge Permit, Permit to Cut and/or Relocate Tree/s, Marine Mammal Related Activity Permits, Aquatic Animal Related Activity Permit, NOC Marine Area Management, Coral Translocation Permit, NOC Dredging and/or Reclamation, NOC Conditional Environmental Activity, Permit to Transport Sand; and new applications of Harbor Discharge Permit, Irrigation Permit and Air Emission Permit Submission of Application Form and Documentary Requirements The Client / Contractor shall submit a fully accomplished permit application form together with all other necessary documents listed on the relevant application form and as required during application. All submissions must be in electronic format and has to be submitted to EHS Main Office Reception (near Main Gate No. 3), Jebel Ali Free Zone or through to EHS.environment@trakhees.ae. Incomplete and paper submissions shall be rejected and will not be accepted Review of Environmental Permit / NOC Submission The submitted application form and all other supporting documents shall be reviewed by Environment Department. The Client / Contractor shall be notified of any deficiency, clarifications and/or requirements to be submitted for further review and assessment Site Inspection Site Inspection, as needed, shall be conducted by an Officer. Upon notification, the Client / Contractor shall agree with the Officer the time and date of the Site Inspection. The scope of Site Inspection shall include all facilities covered by the relevant Environmental Permit / NOC. REVISION: 02 February 2015 Page 2 of 6

3 3.1.4 Approval / Rejection of Environmental Permit / NOC Approval or rejection of the application shall be notified by the Environment Department to the Client / Contractor concern. Upon approval, appropriate permit shall be issued Payment Client / Contractor securing an Environmental Permit / NOC shall pay an amount as specified in Table 1. The payment can be settled at any Trakhees Cash Counters located at EHS Main Office (near Main Gate No. 3), Jebel Ali Free Zone or at Trakhees Main Office, Dragon Mart. In case of payment by check, the check shall be made payable to PCFC- Trakhees. Also, all transactions are required to pay the Knowledge Dirham fee at an amount of AED 10/-. Table 1 Environmental Permit / NOC Approval Fee # Type of Permit Amount Remarks 1 Harbor / Open Sea Discharge Permit 2 Irrigation Permit 3 Groundwater Discharge Permit 4 Air Emission Permit 5 Permit to Cut / Relocate Trees AED 1, No Objection Certificate (NOC) 7 Permit to Operate Captive Marine Mammal Facility / Public Aquarium Facility AED 5, Permit to Transport Marine Mammal / Aquatic Animal 9 Permit to Conduct Scientific Research on Marine Mammal / Aquatic Animal AED Permit to Export / Import Marine Mammal / Aquatic Animal 11 Coral Translocation Permit AED 10, No Objection Certificate (NOC) Dredging and/or Reclamation 13 Permit to Transport Sand Permit Fee per permit approval Application Fee Permit Fee for every 10 trees to be subject for cutting NOC Fee per NOC approval Permit / NOC Fees per approval Application Fee: AED 1, Resubmission Fee: Permit Fee per permit approval REVISION: 02 February 2015 Page 3 of 6

4 Payment advice for the relevant fee/s shall be forwarded by EHS Environment Department to the Client through . No issuance of Permit / NOC shall be given unless all fees are settled. 3.2 Procedure for renewal of Harbor Discharge Permit, Irrigation Permit and Air Emission Permit EHS Environment Department shall initiate the renewal process of Harbor Discharge, Irrigation and Air Emission Permits on an annual basis within forty five (45) to sixty (60) days prior to Permit s expiry date. Inspection by EHS Environment Department and sampling by EHS Laboratory shall be conducted at the same time without prior notice to the Client. Corresponding analysis report/s shall be released by EHS Laboratory within five (5) working days for air emissions, seven (7) working days for irrigation water and eight (8) working days for harbor water after sampling date As soon as the corresponding analysis report/s has been released, succeeding steps which will depend on the results of sampling shall be detailed by the EHS Environment Department. The steps shall include but not limited to compliance with the applicable standards, submission of documentary requirements and settlement of relevant fees (i.e. permit approval, laboratory analysis and financial penalty) Payment Client shall pay the relevant permit approval fee/s as detailed in the Table 1 and the corresponding laboratory analysis fee/s as specified in Table 2. Financial penalty (Table 3), as applicable, should be settled prior to permit issuance. The payment can be settled at any Trakhees Cash Counters located at EHS Main Office (near Main Gate No. 3), Jebel Ali Free Zone or at Trakhees Main Office, Dragon Mart. In case of payment by check, the check shall be made payable to PCFC-Trakhees. Also, all transactions are required to pay the Knowledge Dirham fee at an amount of AED 10/-. Table 2 Laboratory Analysis Fee # Type of Analysis Amount Remarks 1 Irrigation Water Analysis per water sample to be 2 Harbor Water Analysis 1, analyzed 3 Stack Emission Monitoring 1, per stack emission sample to be analyzed Table 3 Financial Penalty # Amount Remarks 1 Failure to meet relevant standards 2, amount per failed parameter REVISION: 02 February 2015 Page 4 of 6

5 Payment advice for the relevant fees shall be forwarded by EHS Environment Department to the Client through . No issuance of Permit / NOC shall be given unless all fees are settled. 3.3 Compliance to Permit / NOC Conditions Client shall adhere to all the conditions set in the approved Permit / NOC. 4.0 Attachments 4.2 Environmental Permit (Harbor / Open Sea Discharge, Irrigation and Air Emission) Application Form (ENF-03a) 4.3 Groundwater Discharge Permit Application Form (ENF-03b) 4.4 Permit to Cut and/or Relocate Trees Application Form (ENF-03c) 4.5 Permit to Operate Captive Marine Mammal and/or Public Aquarium Facility Application Form (ENF-03d) 4.6 Permit to Transport Marine Mammal and/or Aquatic Animal Application Form (ENF-03e) 4.7 Permit to Conduct Scientific Research Marine Mammal and/or Aquatic Animal Application Form (ENF-03f) 4.8 Permit to Export / Import Marine Mammal and/or Aquatic Animal Application Form (ENF-03g) 4.9 No Objection Certificate (NOC) Management of Marine Area Application Form (ENF-03h) 4.10 Coral Translocation Permit Application Form (ENF-03i) 4.11 No Objection Certificate (NOC) Dredging and/or Reclamation Activity Application Form (ENF-03j) 4.12 No Objection Certificate (NOC) Conditional Environmental Activity Application Form (ENF-03k) 4.13 Permit to Transport Sand Application Form (ENF-03l) REVISION: 02 February 2015 Page 5 of 6

6 5.0 Applicable Regulations 5.2 EHS Environmental Regulations 5.3 EHS Environmental Guidelines 6.0 EHS Contacts Milagros Amor V. Iligan EIA Officer / Wendell S. Acena Blue Community Officer / Zulfiqar Gulakbar Ali EIA Officer / REVISION: 02 February 2015 Page 6 of 6

CIVIL ENGINEERING DIVISION. Client s procedure for New Building System Approval

CIVIL ENGINEERING DIVISION. Client s procedure for New Building System Approval Client s procedure for New Building System Approval 1.0 Purpose: The purpose is to ensure that the New Building System is in line with the minimum requirements stipulated in Building Regulations and Design

More information

CIVIL ENGINEERING DIVISION

CIVIL ENGINEERING DIVISION 1.0 Purpose Title: CLIENT PROCEDURE FOR COMPLETION CERTIFICATE & DEWA NOC The occupancy of new / modified facilities within the jurisdiction of Trakhees shall take into account Civil Engineering Department

More information

Procedure for Accreditation & Training Registration

Procedure for Accreditation & Training Registration Procedure for Accreditation & Training Registration 01. Accreditation & Training Mission Statement The Accreditation & Training Program is in line with the Trakhees Mission to ensure adherence of rules

More information

CIVIL ENGINEERING DIVISION. Client s procedure for Mobilization NOC

CIVIL ENGINEERING DIVISION. Client s procedure for Mobilization NOC Client s procedure for Mobilization NOC 1.0 Purpose: The purpose allow client to prepare site prior construction. This procedure is required to ensure that the proposed fencing is within the plot limit,

More information

PRE-QUALIFICATION FORM ENVIRONMENTAL CONSULTANT PART A. EHS Health, Safety and Fire Protection Regulations and Standards

PRE-QUALIFICATION FORM ENVIRONMENTAL CONSULTANT PART A. EHS Health, Safety and Fire Protection Regulations and Standards PRE-QUALIFICATION FORM ENVIRONMENTAL CONSULTANT PART A To facilitate adherence and implementation of EHS Standards and Regulations, clients may require the services of HSE consultant engineers to carry

More information

Client Procedure for Prequalification (New Application) & Renewal GREEN BUILDING COMMISSIONING / ALLIED SPECIALIST

Client Procedure for Prequalification (New Application) & Renewal GREEN BUILDING COMMISSIONING / ALLIED SPECIALIST Revision: 06 Feb 2017 Page 1 of 5 Client Procedure for Prequalification (New Application) & Renewal GREEN BUILDING COMMISSIONING / ALLIED SPECIALIST 1. PURPOSE: Environment, Health and Safety (EHS) Department

More information

CIVIL ENGINEERING DIVISION. Client s procedure for Change of Consultant Contractor Procedures

CIVIL ENGINEERING DIVISION. Client s procedure for Change of Consultant Contractor Procedures Client s procedure for Change of Consultant Contractor Procedures 1.0 Purpose: The purpose is to attend the client request to change their consultant/contractor whether the change reason is normal or due

More information

CIVIL ENGINEERING DIVISION

CIVIL ENGINEERING DIVISION Title : Obtaining / Renewing Plot & Infrastructure Demarcation Certificate 1. PURPOSE CONTENTS 2. SCOPE 3. REFERENCES 4. DEFINITIONS 5. PROCEDURE 5.1 Plot Demarcation Certificate 5.1.1 Submit Request &

More information

Procedure for Accreditation & Training Registration

Procedure for Accreditation & Training Registration Procedure for Accreditation & Training Registration 01. Accreditation & Training Mission Statement The Accreditation & Training Program is in line with the Trakhees Mission to ensure adherence of rules

More information

ENVIRONMENT, HEALTH AND SAFETY

ENVIRONMENT, HEALTH AND SAFETY ENVIRONMENT, HEALTH AND SAFETY SUSTAINABILITY DEPARTMENT CIRCULAR: EHS/GB/06/10 TO : All EHS Pre Qualified Green Building Consultants, Commissioning Authorities, Clients and relevant stakeholders involved

More information

Permitting of Development and Infrastructure Projects in Abu Dhabi

Permitting of Development and Infrastructure Projects in Abu Dhabi Permitting of Development and Infrastructure Projects in Abu Dhabi EAD-EQ-PCE-SOP- Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General Originated By

More information

Warehousing Process - Sea

Warehousing Process - Sea High Level Process Pre-clearance Process 1 2 3 4 Ministries Departments and Agencies (MDA) Process Bond Process Shipping Agent Process Pre-clearance Movement Process Scans Bill of Lading (BL) and Commercial

More information

PRE-QUALIFICATION FORM GREEN BUILDING CONSULTANT / SPECIALIST

PRE-QUALIFICATION FORM GREEN BUILDING CONSULTANT / SPECIALIST PRE-QUALIFICATION FORM GREEN BUILDING CONSULTANT / SPECIALIST PART A Introduction The purpose of this document is to provide the applicant with necessary information required to complete the form and the

More information

YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA Phone (530) ; Fax (530)

YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA Phone (530) ; Fax (530) YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA 95618 Phone (530)757-3650; Fax (530)757-3670 AUTHORITY TO CONSTRUCT (ATC) APPLICATION A separate application must be

More information

130A Alternative process for wastewater system approvals. (a) Engineered Option Permit Authorized. A professional engineer licensed under

130A Alternative process for wastewater system approvals. (a) Engineered Option Permit Authorized. A professional engineer licensed under 130A-336.1. Alternative process for wastewater system approvals. (a) Engineered Option Permit Authorized. A professional engineer licensed under Chapter 89C of the General Statutes may, at the direction

More information

Warehousing Process - Land

Warehousing Process - Land High Level Process Pre-clearance Process 1 2 Ministries Departments and Agencies (MDA) Process Scans Commercial Invoice Unique Consignment Reference (UCR) Bond Process Removal Bond Premises Bond MDA Permit

More information

All Business Units, Consultants & Contractors

All Business Units, Consultants & Contractors To: Subject: Our Ref: Date: All Business Units, Consultants & Contractors CED Violation Procedures CIRCULAR- 42516/2008/sk 09-Nov-2008 Dear All, To ensure that all submissions to CED and works in construction

More information

Free Zone Process - Sea

Free Zone Process - Sea High Level Process Pre-clearance Process 1 2 3 4 Ministries Departments and Agencies (MDA) Process Free Zone eexemption Process Shipping Agent Process Pre-clearance Movement Process Scans Bill of Lading

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 6 EROSION CONTROL STANDARDS 6.1 INTRODUCTION The policies of this section shall apply during construction and until permanent measures are in place following construction as described herein, unless

More information

Client Procedure for Green Building Submissions During EHS-NOC Building Completion Certificate (NOC-BCC) (Projects following LEED)

Client Procedure for Green Building Submissions During EHS-NOC Building Completion Certificate (NOC-BCC) (Projects following LEED) Client Procedure for Green Building Submissions During EHS-NOC Building Completion Certificate (NOC-BCC) (Projects following LEED) 1. PURPOSE The Purpose of this document is to guide the client in putting

More information

Outline of the Revised Renewable Energy Act

Outline of the Revised Renewable Energy Act ENERGY PRACTICE LEGAL UPDATE August 2017 Outline of the Revised Renewable Energy Act Eiji Kobayashi / Kunihiro Yokoi / Kunitaro Yabuki On 1 April 2017 (the Effective Date ), the Act for the Partial Revision

More information

CONSTRUCTION SAFETY MAGAZINE Official supplement of Trakhees EHS, Construction Safety Department

CONSTRUCTION SAFETY MAGAZINE Official supplement of Trakhees EHS, Construction Safety Department CONSTRUCTION SAFETY MAGAZINE Official supplement of Trakhees EHS, Construction Safety Department Page 3 - Editorial Page 4 - Interview with Dubai World projects Page 5 - Water works Page 6 & 7 - Environment

More information

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary

More information

Utilities Department Capital Projects Contract Audit

Utilities Department Capital Projects Contract Audit City Auditor s Office Utilities Department Capital Projects Contract Audit Report Issued: March 3, 2017 Audit Report No. # 16 A 2 P O Box 150027 815 Nicholas Pkwy. Cape Coral, FL 33915-0027 Phone 239-242-3383

More information

Chapter 1, Introduction

Chapter 1, Introduction Chapter 1, Introduction CHAPTER CONTENTS 1.1 THE DESIGNERS MANUAL A. Purpose B. Contents 1.2 THE DIVISION OF FACILITIES PLANNING 1.3 THE UNIVERSITY AS OWNER A. The Owner B. Owner Agency 1.4 CAPITAL IMPROVEMENTS

More information

A. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663

A. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663 August 2013, Rev 00 01 7419 Construction Waste Management PART 1. GENERAL 1.01 Requirements Include: A. Each Contractor provide: 1. Participation in Construction Waste Management plan, including separation

More information

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL 150.270 STATUTORY AUTHORIZATION. This subchapter is adopted pursuant to the authorization and policies contained in M.S. Chs.

More information

Employment Services Request for Employee Residence Visa Cancellation

Employment Services Request for Employee Residence Visa Cancellation Application Guideline Employment Services Request for Employee Residence Visa Cancellation Table of Contents Introduction... 2 Service to Select on Portal... 2 Important Notes... 2 Steps... 3 Employment

More information

The Clean Water Act and 404/401 Process in Hawaii

The Clean Water Act and 404/401 Process in Hawaii The Clean Water Act and 404/401 Process in Hawaii Presented by: Robert Walker, PE Coastal Engineer Anchor QEA, LLC Clean Water Act (1972) Restore and maintain the chemical, physical, and biological integrity

More information

BLUETEL NETWORKS PTE LTD 180 Paya Lebar Road #06-03 Yi Guang Building Singapore Tel Fax

BLUETEL NETWORKS PTE LTD 180 Paya Lebar Road #06-03 Yi Guang Building Singapore Tel Fax BTN Ref. No. FOR BLUETEL S USE ONLY Date Received: Map Ref No. NCE Ref No. BLUETEL NETWORKS PTE LTD 180 Paya Lebar Road #06-03 Yi Guang Building Singapore 409032 Tel 6556 2221 Fax 6556 2777 www.bluetel.net.sg

More information

Connecticut Department of Energy and Environmental Protection. Connecticut Department of Energy and Environmental Protection

Connecticut Department of Energy and Environmental Protection. Connecticut Department of Energy and Environmental Protection Connecticut Department of Energy and Environmental Protection Connecticut Department of Energy and Environmental Protection What is LEAN? LEAN is a growth strategy Manufacturing process improvement approach

More information

IOWA ADMINISTRATIVE CODE SUMMARY

IOWA ADMINISTRATIVE CODE SUMMARY IOWA ADMINISTRATIVE CODE SUMMARY To explain and define details of legislation, departments in the executive branch of Iowa government adopt and publish rules. After prescribed public review and comments,

More information

Components Used: Septic Tank; Size Lagoon Packaged Sewage Treatment Plant Holding Tank; Size

Components Used: Septic Tank; Size Lagoon Packaged Sewage Treatment Plant Holding Tank; Size June 2016 Permit Issuance Please contact Lac Ste. Anne County at: 4928 Langston Street; Box 219 Sangudo, AB T0E 2A0 Ph. 780.785.3411 or Fax 780.785.2985 www.lsac.ca Email: devassistant@lsac.ca Inspection

More information

Municipal Engineering Standards Development Agreement Request Form

Municipal Engineering Standards Development Agreement Request Form Appendix A-1 Development Agreement Request Form Development Agreement Request Form To: Project Leader, Approvals and Technical Services : City of Spruce Grove, Planning and Infrastructure 315 Jespersen

More information

Customs-related aspects of the Rotterdam Convention Switzerland s experience. Secretariat of the Rotterdam Convention. Switzerland s experience

Customs-related aspects of the Rotterdam Convention Switzerland s experience. Secretariat of the Rotterdam Convention. Switzerland s experience ROTTERDAM CONVENTION Case study on the Customs-related aspects of the Rotterdam Convention Switzerland s experience 1 Secretariat of the Rotterdam Convention TABLE OF CONTENTS 1.0 BACKGROUND. page 1 2.0

More information

G04 Receiving and Accepting Applications for Building Consents and Code Compliance Certificates

G04 Receiving and Accepting Applications for Building Consents and Code Compliance Certificates G04 Receiving and Accepting Applications for Building Consents and Code Compliance Certificates Contents 1. INTRODUCTION... 1 2. DEFINITIONS FOR RECEIVING AND ACCEPTING APPLICATIONS FOR BUILDING CONSENTS,

More information

PROBLEMS AND CHALLENGES:

PROBLEMS AND CHALLENGES: In accordance with Law No. (21) For the year 2005 on waste management in the Emirate of Abu Dhabi, Law No. (24) For the year 1999 on the protection development of the environment, and the Executive Committee

More information

CHEMUNG COUNTY SANITARY CODE ARTICLE V ONSITE WASTEWATER TREATMENT SYSTEMS (OWTS)

CHEMUNG COUNTY SANITARY CODE ARTICLE V ONSITE WASTEWATER TREATMENT SYSTEMS (OWTS) CHEMUNG COUNTY SANITARY CODE ARTICLE V ONSITE WASTEWATER TREATMENT SYSTEMS (OWTS) SECTION 1. General A. Standards: Onsite Wastewater Treatment Systems (OWTS) shall be designed, constructed and maintained

More information

South Australian Public Health (Wastewater) Regulations 2013

South Australian Public Health (Wastewater) Regulations 2013 Version: 1.7.2017 South Australia South Australian Public Health (Wastewater) Regulations 2013 under the South Australian Public Health Act 2011 Contents Part 1 Preliminary 1 Short title 3 Interpretation

More information

Town of Whitby Public Works Department

Town of Whitby Public Works Department Town of Whitby Public Works Department Guide to Site Alteration Pre-Screening Questionnaire and Site Alteration / Haul Route Permit Application NOTE: FOR AN ACCESSIBLE VERSION OF THIS DOCUMENT PLEASE CONTACT

More information

Environmental Information Form

Environmental Information Form CITY OF MODESTO Community and Economic Development Department/Planning Division 1010 Tenth Street, Suite 3300, P.O. Box 642 Modesto, CA 95353 (209) 577-5267 (209) 491-5798 FAX This questionnaire will assist

More information

11.1 General Duty of Care Principle Waste Management Options Hierarchy Waste Classification General Waste

11.1 General Duty of Care Principle Waste Management Options Hierarchy Waste Classification General Waste 11.1 General 11.2 Duty of Care Principle 11.3 Waste Management Options Hierarchy 11.4 Waste Classification 11.5 General Waste 11.6 Industrial Waste 11.7 Construction and Demolition Waste 11.8 Horticultural

More information

PROCEDURE FOR GRANT OF DISTRIBUTION OPEN ACCESS PERMISSION AS PER MERC (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2014

PROCEDURE FOR GRANT OF DISTRIBUTION OPEN ACCESS PERMISSION AS PER MERC (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2014 PROCEDURE FOR GRANT OF DISTRIBUTION OPEN ACCESS PERMISSION AS PER MERC (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2014 Page 1 of 13 Contents 1.0 PREAMBLE:... 3 2.0 DURATION OF OPEN ACCESS:... 3 3.0 ELIGIBILITY

More information

Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management)

Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management) Environmental Management (1 st Issue-Apr 2004) Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management) Contents Page

More information

Technical Guidance Document for Operational Environmental Management Plan (OEMP)

Technical Guidance Document for Operational Environmental Management Plan (OEMP) Technical Guidance Document for Operational Environmental Management Plan (OEMP) EAD-EQ-PCE-TG-06 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General

More information

CROATIAN CHAMBER OF ECONOMY International Freight Forwarders Association of Croatia

CROATIAN CHAMBER OF ECONOMY International Freight Forwarders Association of Croatia CROATIAN CHAMBER OF ECONOMY International Freight Forwarders Association of Croatia GENERAL CONDITIONS (2005) OF THE INTERNATIONAL FREIGHT FORWARDERS ASSOCIATION OF CROATIA I. APPLICABILITY Article 1 These

More information

VARIANCE REQUEST FOR EXPANDED WATER USE FROM EXISTING WELL IN A STAY MANAGEMENT AREA OF THE LOWER PLATTE NORTH NRD (LPNNRD)

VARIANCE REQUEST FOR EXPANDED WATER USE FROM EXISTING WELL IN A STAY MANAGEMENT AREA OF THE LOWER PLATTE NORTH NRD (LPNNRD) VARIANCE REQUEST FOR EXPANDED WATER USE FROM EXISTING WELL IN A STAY MANAGEMENT AREA OF THE LOWER PLATTE NORTH NRD (LPNNRD) Updated Form: August 2012 NRD USE ONLY Date Received Paid: Cash or Check Initial

More information

Ministry of Environment & Forests NOTIFICATION. New Delhi, the 6 th January, 2000.

Ministry of Environment & Forests NOTIFICATION. New Delhi, the 6 th January, 2000. 1 of 9 10/1/2012 2:50 PM Ministry of Environment & Forests NOTIFICATION New Delhi, the 6 th January, 2000. S.O. 24(E).- Whereas a notification of the Government of India in the Ministry of Environment

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

NC General Statutes - Chapter 130A Article 11 1

NC General Statutes - Chapter 130A Article 11 1 Article 11. Wastewater Systems. 130A-333. Purpose. The General Assembly finds and declares that continued installation, at a rapidly and constantly accelerating rate, of septic tank systems and other types

More information

[THIS PAGE INTENTIONALLY LEFT BLANK]

[THIS PAGE INTENTIONALLY LEFT BLANK] 4-3 WASTEWATER [THIS PAGE INTENTIONALLY LEFT BLANK] TABLE OF CONTENTS 4-1 GOAL: TO PROVIDE COST EFFECTIVE ENVIRONMENTALLY ACCEPTABLE WASTEWATER TREATMENT FACILITIES TO SERVE THE EXISTING AND FUTURE DEVELOPMENT

More information

APPROVAL PROCESS FOR NEW SEWER SYSTEMS & LINE EXTENSIONS

APPROVAL PROCESS FOR NEW SEWER SYSTEMS & LINE EXTENSIONS APPROVAL PROCESS FOR NEW SEWER SYSTEMS & LINE EXTENSIONS Preliminary Plan Approval Owner/Developer Submits the Preliminary Maps to County/Town to identify the location of the nearest sewer line to the

More information

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR PROJECT BEING DEVELOPED

More information

MassDEP. Groundwater Permit Program. Requirements

MassDEP. Groundwater Permit Program. Requirements MassDEP Groundwater Permit Program Overview and Requirements Groundwater Advisory Task Force Hydrogeologists Engineers Local officials Environmental groups Development community MassDEP staff Changes to

More information

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE Environmental Management Chapter 335-6-9 ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE CHAPTER 335-6-9 SURFACE MINING RULES TABLE OF CONTENTS

More information

Dredging for Climate Change and Transport in the Netherlands

Dredging for Climate Change and Transport in the Netherlands Dredging for Climate Change and Transport in the Netherlands Dredging to survive Polite Laboyrie (Chairman of CEC and Head of Hydr&Env Eng RWS) Organisation Ministry of Transport Dredging for Climate Change

More information

meters (16 Inches) Transportation (T)

meters (16 Inches) Transportation (T) OFFICE USE ONLY Application # Town of Steady Brook BUILDING AND DEVELOPMENT APPLICATION {All Applications must include copy of Legal Survey, showing all measurements And distances required} {Processing

More information

Quality Assurance Policy and Procedures

Quality Assurance Policy and Procedures 650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance

More information

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application

More information

REPLIES TO QUERIES. Sr. Clause No Reference from RfQ cum RfP Queries Clarification. Developer. Bidder shall furnish the please.

REPLIES TO QUERIES. Sr. Clause No Reference from RfQ cum RfP Queries Clarification. Developer. Bidder shall furnish the please. REPLIES TO QUERIES ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) SERVICES FOR 1.00MW MODEL SOLAR POWER PROJECT AT NEEMRANA INDUSTRIAL AREA ON TURNKEY BASIS AND OPERATION & MAINTENANCE OF 1.00MW SOLAR

More information

NOTICE TO PROSPECTIVE BIDDERS REGARDING PRE-QUALIFICATION FOR CONTRACTS FOR ALISAL UNION SCHOOL DISTRICT. Revised February 11, 2015

NOTICE TO PROSPECTIVE BIDDERS REGARDING PRE-QUALIFICATION FOR CONTRACTS FOR ALISAL UNION SCHOOL DISTRICT. Revised February 11, 2015 NOTICE TO PROSPECTIVE BIDDERS REGARDING PRE-QUALIFICATION FOR CONTRACTS FOR ALISAL UNION SCHOOL DISTRICT Revised February 11, 2015 For Projects to be bid from February 12, 2015 to February 11, 2016 Alisal

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI - CoP 53.0 EHS Management During Construction Work Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude

More information

Acceptable Formats for EPEA Approval and Code

Acceptable Formats for EPEA Approval and Code Formatting Manual Records Management of Practice Records and Submission Coordinators Alberta Environment and Parks Record Name Format Suffix/ Municipal Municipal Groundwater Monitoring Proposals and Municipal

More information

WARREN COUNTY, IOWA CHAPTER 31 CHAPTER 31 ON-SITE WASTEWATER TREATMENT AND DISPOSAL SYSTEMS

WARREN COUNTY, IOWA CHAPTER 31 CHAPTER 31 ON-SITE WASTEWATER TREATMENT AND DISPOSAL SYSTEMS TITLE IV HEALTH ORDINANCES Final copy approved by BOS 3-6-12 CHAPTER 31 ON-SITE WASTEWATER TREATMENT AND DISPOSAL SYSTEMS 31.01 Purpose 31.07 Wells 31.02 Definitions 31.08 Variances 31.03 General Requirements

More information

HNL/EMCC/19/3486/T /03/2019 NOTICE INVITING TENDER

HNL/EMCC/19/3486/T /03/2019 NOTICE INVITING TENDER HNL/EMCC/19/3486/T-2471 26/03/2019 NOTICE INVITING TENDER Sealed and superscribed (Tender No & Name of work) ITEM RATE tenders are invited for executing the following work in accordance with the terms

More information

Deck Permit Information Revised 2/5/2015

Deck Permit Information Revised 2/5/2015 CITY OF GENEVA BUILDING DIVISION 109 JAMES STREET GENEVA, IL 60134 630/262.0280 630/262.0286 fax www.geneva.il.us Deck Permit Information Revised 2/5/2015 A building permit is required prior to installing

More information

Regulatory Guide 2.19

Regulatory Guide 2.19 Regulatory Guide 2.19 Issuance Date: December 1, 2011 Guide for Submission of Documents and Fees by Low Level Radioactive Waste Shippers and Transporters I. INTRODUCTION A. Approval Process Radiation Safety

More information

FORM 1 [See Rule 3(2), 5(2)(3)]

FORM 1 [See Rule 3(2), 5(2)(3)] FORM 1 [See Rule 3(2), 5(2)(3)] APPLICATION FOR OBTAINING AUTHORISATION FOR COLLECTION/RECEPTION/TREATMENT/TRANSPORT/STORATE/ DISPOSAL OF HAZARDOUS WASTES* From :... To, Sir,......... The Member Secretary,

More information

TAB 7 Payment Procedures Consultant Invoice Construction Payment Applications

TAB 7 Payment Procedures Consultant Invoice Construction Payment Applications TAB 7 Payment Consultant Invoice Construction Payment Applications TAB 7 - PAYMENT PROCEDURES - CONSULTANTS.DOC Page 1 of 7 CONSULTANT INVOICE INTRODUCTION In accordance with Article 11 Payments of the

More information

Milano Worldwide Corporation

Milano Worldwide Corporation Milano Worldwide Corporation TERMS AND CONDITIONS Product Order Upon placing an order for a Custom Milano Worldwide concept and prototype, Customer will pay specified set-up charge and receive: Line drawing

More information

PORT OF SAN FRANCISCO PLUMBING CODE. Based on the 2016 California Plumbing Code

PORT OF SAN FRANCISCO PLUMBING CODE. Based on the 2016 California Plumbing Code 2016 PORT OF SAN FRANCISCO PLUMBING CODE Based on the 2016 California Plumbing Code The complete 2016 Port of San Francisco Plumbing Code adopts and amends the 2016 edition of the California Plumbing Code.

More information

CHAPTER SURFACE MINING AND RECLAMATION PLAN REGULATIONS

CHAPTER SURFACE MINING AND RECLAMATION PLAN REGULATIONS CHAPTER 19.66 SURFACE MINING AND RECLAMATION PLAN REGULATIONS Section: 19.66.010 PURPOSE AND INTENT 19.66.020 INCORPORATION OF SMARA AND STATE REGULATIONS 19.66.030 APPLICABILITY 19.66.040 EXEMPTIONS 19.66.050

More information

ITN-DOT-15/ PM EXHIBIT A SCOPE OF SERVICES D4 RAPID INCIDENT SCENE CLEARANCE (RISC)

ITN-DOT-15/ PM EXHIBIT A SCOPE OF SERVICES D4 RAPID INCIDENT SCENE CLEARANCE (RISC) EXHIBIT A SCOPE OF SERVICES RAPID INCIDENT SCENE CLEARANCE (RISC) FOR DISTRICT FOUR 1. PROJECT OBJECTIVE 1.1 In an effort to provide the traveling public of the State of Florida a cost effective, high

More information

RESERVE BANK OF MALAWI PROCUREMENT REFERENCE NO. RBM/ADMN/SLVR/005/18

RESERVE BANK OF MALAWI PROCUREMENT REFERENCE NO. RBM/ADMN/SLVR/005/18 RESERVE BANK OF MALAWI PROCUREMENT REFERENCE NO. RBM/ADMN/SLVR/005/18 ENGAGEMENT OF A CONTRACTOR FOR THE REHABILITATION OF THE SILVER STADIUM FOOTBALL PITCH 1.0 Introduction The Reserve Bank of Malawi

More information

1. INTRODUCTION 1.1 Contents of Engineering Specifications The Engineering Specifications contains the following sections:

1. INTRODUCTION 1.1 Contents of Engineering Specifications The Engineering Specifications contains the following sections: Schedule H to Bylaw 7452, Subdivision Bylaw Page 1 1. INTRODUCTION 1.1 Contents of Engineering Specifications 1.1.1 The Engineering Specifications contains the following sections: 1. Introduction 2. General

More information

MANUAL QUALITY CONTROL & QUALITY ASSURANCE

MANUAL QUALITY CONTROL & QUALITY ASSURANCE MANUAL QUALITY CONTROL & QUALITY ASSURANCE METROTEC ENGINEERING LLC P.O. BOX: 26045, DUBAI U.A.E TEL : 043889771 FAX:043889772 E Mail: metrotecengg@yahoo.com info@metrotec.ae Web: www.metrotec.ae 2 TABLE

More information

CADTH COMMON DRUG REVIEW. Procedure for the CADTH Common Drug Review

CADTH COMMON DRUG REVIEW. Procedure for the CADTH Common Drug Review CADTH COMMON DRUG REVIEW Procedure for the CADTH Common Drug Review AUGUST 2014 RECORD OF UPDATES TO THE PROCEDURE FOR THE CADTH COMMON DRUG REVIEW Update Original June 2003 1 January 2005 2 July 2005

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT ENVIRONMENTAL LAW ASSOCIATION ENVIRONMENTAL LAW FACT SHEET NO. 1 ENVIRONMENTAL IMPACT ASSESSMENT INTRODUCTION This fact sheet was produced by the Environmental Law Association to provide a plain language

More information

Testing and Certification of Lifting Equipments Orpic-MAF Refinery

Testing and Certification of Lifting Equipments Orpic-MAF Refinery 1. INTRODUCTION. 2 2. SCOPE OF WORK 2 3. GENERAL TERMS & CONDITIONS.. 3 4. PAYMENT TERMS.... 4 5. TECHNICAL EVALUATION CRITERIA. 4 6. EQUIPMENT LIST. 5 Page 1 of 6 1 INTRODUCTION M/s. Oman Oil Refineries

More information

DOCUMENT PREPARATION UNDER LETTERS OF CREDIT

DOCUMENT PREPARATION UNDER LETTERS OF CREDIT There are some universal requirements, including those listed below: DOCUMENT PREPARATION UNDER LETTERS OF CREDIT Document: THE LETTER OF CREDIT it is the correct referenced letter of it is still valid

More information

VILLAGE OF BUFFALO GROVE

VILLAGE OF BUFFALO GROVE WWW.VBG.ORG 847 459 2530 (TYPE OR PRINT IN INK) FILE COPY DRIVEWAY & DRIVEWAY APRON PERMIT REQUIREMENTS CHECKLIST Permit Application. o Fully filled out as pertains to your project. Completed Contractor

More information

Dr B R AMBEDKAR NATIONAL INSTITUTE OF TECHNOLOGY G T Road By Pass, Jalandhar , Punjab (India) Tel: website

Dr B R AMBEDKAR NATIONAL INSTITUTE OF TECHNOLOGY G T Road By Pass, Jalandhar , Punjab (India) Tel: website Ref. No: NITJ/Pur/CH/103/17/ Date: NOTICE INVITING QUOTATION Sealed quotations are invited on behalf of Director, NIT, Jalandhar for the Supply of Various Equipment required for Chemical Technology & Energy

More information

APPLICATION FOR A PERMIT TO CONSTRUCT A WATER WELL IN THE LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT

APPLICATION FOR A PERMIT TO CONSTRUCT A WATER WELL IN THE LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT APPLICATION FOR A PERMIT TO CONSTRUCT A WATER WELL IN THE LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT DNR & NRD USE ONLY Permit No. Date Approved/Denied NRD Representative Permit Type: New, Replacement

More information

The Pharmacy Council under sections 93 and 95 of the Health Professions Regulatory Bodies Act, 2013 (Act 857), grant licences to Pharmacies

The Pharmacy Council under sections 93 and 95 of the Health Professions Regulatory Bodies Act, 2013 (Act 857), grant licences to Pharmacies 1.0 INTRODUCTION The Pharmacy Council under sections 93 and 95 of the Health Professions Regulatory Bodies Act, 2013 (Act 857), grant licences to Pharmacies The Pharmacy Council issues two types of pharmacy

More information

17 May FIDIC FORM OF CONTRACT DREDGING & RECLAMATION WORKS BY JURGEN DHOLLANDER, PR & PROJECT MANAGER

17 May FIDIC FORM OF CONTRACT DREDGING & RECLAMATION WORKS BY JURGEN DHOLLANDER, PR & PROJECT MANAGER 17 May FIDIC FORM OF CONTRACT DREDGING & RECLAMATION WORKS BY JURGEN DHOLLANDER, PR & PROJECT MANAGER AGENDA Introduction IADC FIDIC Form of Contract Update and major changes INTRODUCTION IADC Educating

More information

Joint Use. Guidelines and Construction Standards

Joint Use. Guidelines and Construction Standards Joint Use Guidelines and Construction Standards July 7, 2017 Table of Contents Page Definitions...3 Purpose and Scope...5 General Requirements...6 Joint Use Attachment Application Process...9 Pole Attachment

More information

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F.

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F. GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No Description Summary 1 Order Energy Deptt. letter no. F.20 (4) Energy/2004 dated 25.10.2004 and amended

More information

Guidelines for Design of Potable Water Distribution Facilities In New Developments

Guidelines for Design of Potable Water Distribution Facilities In New Developments Guidelines for Design of Potable Water Distribution Facilities In New Developments Prepared by: OUC Water Business Unit Water Resources and Engineering Division Latest Update: September 29, 2009 1. Development

More information

Putting It All Together

Putting It All Together Putting It All Together A Guide to Holly Springs Permitting Process for New & Expanding Businesses We re glad you re here! Town of Holly Springs May 2007 Table of Content Determine Zoning Compliance...Page

More information

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7.1 E-Permit and U-Permit Permit Description and Purpose The Excavation Permit (E-Permit) and the Utility Permit (U-Permit) are issued to allow construction,

More information

City of Guelph Transfer of Review Procedures 7 March, 2017

City of Guelph Transfer of Review Procedures 7 March, 2017 Step 1-Determine where the project is located on the City of Guelph Vulnerability Map If the project is found not to be located in a vulnerability area with a vulnerability score of 8 or higher (See Attachment

More information

CODING: Words stricken are deletions; words underlined are additions.

CODING: Words stricken are deletions; words underlined are additions. DRAFT RULE 2018 FEE STUDY RULES OF THE ENVIRONMENTAL PROTECTION COMMISSION OF HILLSBOROUGH COUNTY CHAPTER 1-6 SERVICES-FEE SCHEDULE 1-6.01 Declaration and Intent 1-6.02 Air Management 1-6.03 Waste Management

More information

SPECIAL CONDITIONS GENERAL PERMIT NO. WMGM016

SPECIAL CONDITIONS GENERAL PERMIT NO. WMGM016 1. The approval herein granted is limited to the processing and beneficial use of trees, tree stumps, limbs, clean pallets, untreated and unpainted scrap lumber, packing crates and brush, hereinafter referred

More information

31. POLLUTION CONTROL COMMITTEE

31. POLLUTION CONTROL COMMITTEE 31. POLLUTION CONTROL COMMITTEE 90 31.1 Consent to A Duly filled in application Form Establish XIII under Water Act. * days an Industry B Duly filled in application FORM 1 under Air Act * C Consent fee

More information

LIST OF PRICES AND SERVICES

LIST OF PRICES AND SERVICES LIST OF PRICES AND SERVICES Version 01/2019 1 Storage 1 st Period (5 days or fraction thereof): 0,58% of the CIF value (minimum charge of BRL 830,00 per container); From day 6: 0,33% (per day) of the CIF

More information

HAZARDOUS WASTES (MANAGEMENT AND HANDLING) RULES, 1989

HAZARDOUS WASTES (MANAGEMENT AND HANDLING) RULES, 1989 HAZARDOUS WASTES (MANAGEMENT AND HANDLING) RULES, 1989 1. Short title and commencement 2. Application 3. Definitions 4. Responsibility of the occupier for handling of wastes 5. Grant of authorisation for

More information

[Rev. 2012] CAP. 324 Plant Protection

[Rev. 2012] CAP. 324 Plant Protection [Rev. 2012] CAP. 324 PLANT PROTECTION (IMPORTATION OF PLANTS, PLANT PRODUCTS AND REGULATED ARTICLES) RULES, 2009 ARRANGEMENT OF RULES Rule 1. Citation. 2. Interpretations. 3. Importation to conform to

More information

SANITARY SEWER ELEMENT GOALS, OBJECTIVES, AND POLICIES

SANITARY SEWER ELEMENT GOALS, OBJECTIVES, AND POLICIES SANITARY SEWER ELEMENT GOALS, OBJECTIVES, AND POLICIES GOAL 1: To provide for the adequate collection, treatment, and disposal of sewage to meet the needs of the customers of North Port with a specific

More information

Unofficial Translation This translation is for convenience of those unfamiliar with Thai language Please refer to the Thai official version

Unofficial Translation This translation is for convenience of those unfamiliar with Thai language Please refer to the Thai official version Unofficial Translation This translation is for convenience of those unfamiliar with Thai language Please refer to the Thai official version Notification of the Electronic Transactions Commission Re: Rules,

More information

Town of Ashford, Cattaraugus County, New York Local Law #2 of the year 2006

Town of Ashford, Cattaraugus County, New York Local Law #2 of the year 2006 Town of Ashford, Cattaraugus County, New York Local Law #2 of the year 2006 A Local Law Providing for the Administration and Enforcement of the New York State Uniform Prevention and Building Code SECTION

More information