Base Level Engineering Elizabeth Savage, RPML, H2O Partners Diane Howe, FEMA Region 6. May 4, 2017
|
|
- Juliet Booth
- 6 years ago
- Views:
Transcription
1 Base Level Engineering Elizabeth Savage, RPML, H2O Partners Diane Howe, FEMA Region 6 May 4, 2017
2 What is Base Level Engineering Measuring stick to allow FEMA to assess its current flood maps. Cursory engineering analysis to provide predicted areas of flood risk. Flood risk data that provides a platform for broader risk communications. Engineering modeling that may be used and leveraged by local communities to review effect of development in and around the floodplain. 1
3 2
4 Base Level Engineering 1D Inventory Mileage Current (CNMS) 5,403 New (BLE) 2,355 Total 7,
5 Base Level Engineering 2D Three HUC8 Watersheds Low lying & complex hydraulics 2D Analysis 4 Region 6 works with State CTP partners to select modeling analysis approach
6 5 So What?
7 Region 6 CNMS Validation Status 6
8 It takes a village Internal FM&I Internal MSC SHMO Local Staff Internal Outreach USGS Internal MSC NFIP Coordinators CTPs USACE NWS Internal External Affairs Internal HMA Internal Risk Analysis Building Inspectors FMAs Local Planner 7
9 Region 6 Base Level Engineering 8
10 What is Base Level Engineering Minimum Data Purchase Hydraulic Modeling (10%, 4%, 2%, 1%, 1%+, 1%-, and 0.2%) 10%, 1% and 0.2% Floodplains 1% and 0.2% Water Surface Grids 1% and 0.2% Flood Depth Grids Hazus Level 2 9
11 Flood Inventory Maturity Flood prone, No SFHA Determined 4M miles of stream with a drainage area of 1 square mile or larger Current inventory is approximately 1.2M miles Numerous participating NFIP communities have no flood data Paper Inventory, Minimal SFHA Available 92% of population initiated Map Modernization project 62% of contiguous 48 states land mass was modernized 20% of existing inventory remains unmodernized Modernized FIRM, Miles Not Model Backed Flood prone areas with an identified SFHA, identified on modernized digital FIRM Technical data is lacking to back-up SFHA depicted on the FIRM Areas may be detailed or approximate study methods, engineering library no longer has technical data Modernized FIRM, Model Backed on LiDAR Current standard of FEMA s mapping program Tier 3 miles are identified on a modernized digital FIRM (available in database format) Analysis is supported by high quality topography and recent engineering analysis. Multiple flow frequencies and water-surface elevations are readily available for release Risk Based Analysis, Climate Informed Science Tier 4 areas represent an upgrade of information where the current flood hazard conditions have been analyzed and consideration for future conditions 10 have beendeveloped. These areas consider the consequences of the hazard to specific locations, such as structures, and the flood risk of the area can be understood.
12 Base Level Engineering is a Mindset Without data, how can communities make informed decisions? 11
13 Base Level Engineering is a Mindset Base Level Engineering results are available through the Estimated BFE Viewer. 12
14 Base Level Engineering is a Mindset Data visualization opens the conversation. 13
15 Base Level Engineering is a Mindset Detailed w/ Floodway Detailed Study Limited Detail Study Base Level Engineering Scalable models allow communities to maintain the inventory. 14
16 Base Level Engineering This approach teams: + High resolution ground elevation data + Regression equation based hydrology + Highly automated hydraulic modeling + Lessons learned in Map Modernization + Cross-section location and orientation review + Structure cross-sections included in modeling To create: + Baseline models equivalent to Zone A floodplains 15 + Scalable models that can be further refined
17 Refinement of Base Level Engineering Dams & Reservoirs (Before Overtopping) Base Level Engineering Refined Modeling Effort Water in model will stack up on the back of the dam Water will have to overtop the dam in order to have water and flow on the other side Larger floodplain upstream, smaller floodplain downstream Livestock ponds and Gravity dams (update unnecessary) 16 Water will stack up until it can flow into the outlet structure Water in model will be able to flow on the downstream side of the dam earlier Smaller floodplain upstream, LARGER floodplain downstream Rating curves, outlet as-builts and surveys assist this data entry
18 Refinement of Base Level Engineering Culverts Base Level Engineering Water in model will stack up on the back of the culvert crossing Water will have to overtop the culvert crossing in order to have flow on the other side Larger floodplain upstream, smaller floodplain downstream Small culverts (designed for 10, 25 yr event) will be significantly overtopped during 1% event 17 Refined Modeling Effort Water will stack up until it is able to enter the culvert Water in model will be able to flow on the downstream side of the structure earlier Smaller floodplain upstream, LARGER floodplain downstream Rating curves, outlet as-builts and field surveys assist the data collection and entry
19 Base Level Engineering When should we do it? BLE HERE No Additional Mapping: Local support for adoption of BLE information FIRM Map BLE Data (Zone A): FIRMs can be produced immediately following Discovery Refined Engineering & FIRM Update: Lengthens time to prelim, allows detailed studies 18
20 Does BLE replace our current FIRMs? Base Level Engineering (BLE) information does not replace your current Flood Insurance Rate Map (FIRM) This information can be adopted by locals without any FIRM The BLE results may be used in areas where no flood hazard information is shown on your FIRM Where BLE is similar OR more conservative it may be used to provide Estimated Base Flood Elevations to residents Where BLE is smaller than current FIRM, BLE should NOT be used to provide Estimated Base Flood Elevations Data may be used for local planning 19 purposes
21 Base Level Engineering Creates Scalable Flood Hazard Modeling 60.3a 60.3b 60.3c 60.3c & 60.3d No FIRM Large Scale Automated Engineering Non-Regulatory Base Level Engineering Regulatory Zone A (no structures) Limited Detail (Limited structure info) Detailed & with Floodway (Detailed Structure Information) Highly automated modeling, no cross-section review. Used for CNMS Review ONLY 20 Difference between BLE & Zone A is minimal Community test-drive Top of Road and stream invert based on LiDAR, Culvert size, type grouping based on visual inspection Detailed structure input based on asbuilt drawings or field survey. Floodways can be added to assist development regulation
22 Base Level Engineering Release Strategy Base Level Engineering Reviewed by Community Community adoption and use of Base Level Engineering for planning and floodplain management purposes Discovery meeting held to identify projects moving forward Select Zone A mileage moves unmapped/unmodernized 21 Counties/parishes to digital FIRMs Goal: Provide a flood hazard maps to support local floodplain management in an efficient manner Create Digital FIRMs for: - Current CNMS Inventory - Significant areas of change - Current/Future Development Areas - Other areas selected with input from community Paper Inventory Reduction Projects
23 Why? Zone A Maps First? Community Based Maps 22 County/Parishwide Maps
24 Base Level Engineering Release Strategy Modernized FIRM with stream coverage identified by FEMA and community input (Zone A model backed) & Base Level Engineering data Structure or other model refinement to raise above Zone A on FIRM Model refined to include development activity 23 Goal: Ownership at local level for FIRM maintenance & coordination for update LOMRs used to: - Include development changes within community - Raise level of detail above Zone A Physical Map Revisions are also possible in the Risk MAP process to provide additional detail
25 Where Modernized Countywide Maps Exist Stream not included in current FIRM Zone X Stream included in current FIRM Zone A Stream included in current FIRM Zone AE Stream included in current FIRM Zone AE w/ Floodway BLE Information: - May be refined (structures added) and submitted via LOMR to update FIRMs and include Zone AE (limited detail) for stream in question. - Local adoption is advantageous for floodplain mapping purposes, use data for hazard mitigation planning and other local planning purposes. BLE Information: - May be refined (structures added) and submitted via LOMR to update FIRMs and elevate existing Zone A to Zone AE (limited detail) on current FIRM. - May only be used locally if BLE floodplains are MORE conservative than the current FIRM panel. - May be used for BFE estimation if similar to effective FIRM BLE Information: - Should be reviewed in detail by community prior to use, review flow information, add structures to BLE modeling, review resultant floodplains against current FIRM. - Communities should use caution when reviewing BLE information in detailed study areas, use BLE models as a building block and add detail to review current flood risk BLE Information: - Must be elevated to a study level that includes floodway analysis, can be submitted through LOMR process to update FIRMs 24 - Communities should use caution when reviewing BLE information in detailed study areas, use BLE models as a building block and add detail to review current flood risk
26 PRELIMINARY ISSUANCE EFFECTIVE ISSUANCE EFFECTIVE ISSUANCE Future Study Timelines Enhanced LOCAL LOMR SUBMITTAL TO UPDATE FIRM BLE info available LOCAL MODEL REFINEMENT LOMR REVIEW PRELIM TIME (months) DISCOVERY RISK IDENTIFICATION PRELIM POST PRELIMINARY LFD FEMA INITIATES FLOOD RISK PROJECT TO UPDATE FIRM CCO MEETING APPEAL & COMMENT 25
27 Watershed Hydrology Assessments Trinity River Basin 26
28 Base Level Engineering Unlocking the Power of the BLE Datasets We wont get anywhere if we approach things like this We need more of this 27
29 Our Vision for Communities 28
30 Base Level Engineering Unlocking the Power of the BLE Datasets Public outreach and communication Updating local mitigation plans Taking mitigation action Community planning Response and recovery The REAL power comes from combining with local data parcels, buildings, and critical facilities! 29
31 Base Level Engineering Unlocking the Power of the BLE Datasets 30
32 Base Level Engineering Unlocking the Power of the BLE Datasets 31
33 Base Level Engineering Unlocking the Power of the BLE Datasets Higher Standards Possibilities Freeboard Grids 32
34 Base Level Engineering Unlocking the Power of the BLE Datasets Higher Standards Possibilities Freeboard Grids 33
35 Practical Uses for Flood Risk Products 34
36 What comes next? 35 Slide credit: David Key, ESP Associates
37 Questions? 36
Risk MAP Exploratory Innovation Projects. ASFPM 2017: Kansas City, MO Tuesday, May 2, 2017
Risk MAP Exploratory Innovation Projects ASFPM 2017: Kansas City, MO Tuesday, May 2, 2017 Project Themes and Focus Explore Build Finish 2 What are these Innovation Projects? A project (data analysis, research,
More informationWhat to Expect When You re Expecting A LOMR. Mark Seidelmann, PE, GISP ASFPM 2015, Atlanta Georgia
What to Expect When You re Expecting A LOMR Mark Seidelmann, PE, GISP ASFPM 2015, Atlanta Georgia Thursday, June 4 th, 2015 Agenda 1 Why File a Letter Of Map Revision (LOMR)? 2 Basic Requirements and Common
More informationRisk MAP in Louisiana Louisiana Floodplain Management Association. Shona Gibson, PE Risk Analysis FEMA Region VI April 29, 2010
in Louisiana Louisiana Floodplain Management Association Shona Gibson, PE Risk Analysis FEMA Region VI April 29, 2010 Overview Paradigm Shift Vision Program Goals and Measures Project Selection Process
More informationA Federal Family Comes Together Association of State Floodplain Managers Conference
A Federal Family Comes Together 2016 Association of State Floodplain Managers Conference Region 6 by the Numbers 5 States 5 USGS Offices 6 USACE Districts 6 HUC2 Regions 40 HUC4 Subregions 403 HUC8 Watersheds
More informationDRAINAGE MASTER PLAN FOR THE TOWN OF BLOOMING GROVE AND VILLAGES OF WASHINGTONVILLE AND SOUTH BLOOMING GROVE
DRAINAGE MASTER PLAN FOR THE TOWN OF BLOOMING GROVE AND VILLAGES OF WASHINGTONVILLE AND SOUTH BLOOMING GROVE PUBLIC MEETING March 8, 2017 LOGISTICS Meeting Agenda: Presentation (7:15 7:45 pm) [Auditorium]
More informationTechnical Assistance for Action Advancement: Indiana Success Stories. Session J4: Mitigation Project Successes 2 ASFPM Conference June 23, 2016
Technical Assistance for Action Advancement: Indiana Success Stories Session J4: Mitigation Project Successes 2 ASFPM Conference June 23, 2016 Presentation Outline Overview Map Mod vs. Risk MAP Phased
More informationLOMR/CLOMR (MT-2) Submittal and Review Process
LOMR/CLOMR (MT-2) Submittal and Review Process Bosulu Lokulutu Compass Region 6 MT2 Lead August 11, 2017 Overview Letter of Map Changes (LOMC) MT-2 Submittal and Review Process FEMA Process Timeline Common
More informationFlood Insurance Study
Flood Insurance Study Caddo Parish, Louisiana Kick-Off Meeting May 4, 2010 Presentation Overview Introduction FEMA Risk Map Update Levee Discussion Study Discussion Information Resources Review Contact
More informationFLOODPLAIN MANAGEMENT AREAS
FLOODPLAIN MANAGEMENT AREAS Evaluating the Costs and Benefits of Floodplain Protection Activities in Waterbury, Vermont and Willsboro, New York, Lake Champlain Basin, U.S.A. Presented by Roy Schiff, Milone
More informationCOOPERATING TECHNICAL PARTNER INFORMATION EXCHANGE. First Order Approximations
COOPERATING TECHNICAL PARTNER INFORMATION EXCHANGE First Order Approximations WELCOME ASFPM Mapping and Engineering Standards Committee CTP Sub committee Co chairs: Amanda Flegel, PE, CFM; Illinois State
More informationAirport Master Plan. Floodplain Report. Prepared by: Prepared for: Illinois Department of Transportation
Airport Master Plan Floodplain Report Prepared by: Prepared for: Illinois Department of Transportation July 10, 2013 Table of Contents Topic Page Number Cover Sheet... Cover Sheet Table of Contents...
More informationFEMA/USACE Coordination Plan
FEMA/USACE Coordination Plan Project: Fargo-Moorhead Metropolitan Feasibility Study ND Diversion Channel with upstream staging Federal Plan (Authorized WRRDA 2014) Project Design: Project Reach: U.S. Army
More informationWho s in Charge!? 8/9/2018. Houston Geological Society Presents. Peak Floods Brays Bayou
Houston Geological Society Presents An Informational Workshop Flooding and Floodplains in the Houston Area: Past, Present, and Future: Part 1 Presented May 18, 2018 Dr. William R. Dupre Professor Emeritus
More informationRisk MAP Highlights and Updates NAFSMA Annual Meeting 2014 Implementing New Water Resources Programs, Policies, and Responsibilities
Risk MAP Highlights and Updates NAFSMA Annual Meeting 2014 Implementing New Water Resources Programs, Policies, and Responsibilities Doug Bellomo Director, Risk Analysis Division, Federal Insurance and
More informationBrian Rast, PE, CFM, PMP Lead Silver Jackets Coordinator, Kansas and Missouri Kris Lander, PE, CFM Hydrologist. June 4, 2015
Presentation to the Association of State Floodplain Managers Interagency Partnering for Flood Forecast Inundation Maps Brian Rast, PE, CFM, PMP Lead Silver Jackets Coordinator, Kansas and Missouri Kris
More informationMargaret Walls. RFF First Wednesday Seminar. Green Infrastructure: Using Natural Landscapes for Flood Mitigation and Water Quality Improvements
THE ROLE OF LAND USE IN ADAPTATION TO INCREASED PRECIPITATION AND FLOODING Margaret Walls RFF First Wednesday Seminar Green Infrastructure: Using Natural Landscapes for Flood Mitigation and Water Quality
More informationWAVERLY FLOODPLAIN BACKGROUND INFORMATION
WAVERLY FLOODPLAIN BACKGROUND INFORMATION Who designates the floodplains in Waverly? The Federal Emergency Management Agency (FEMA) is responsible for delineating floodplains. The floodplain FEMA uses
More informationFEMA and Levees Levee Accreditation Reviews Proposed Changes to the FEMA Levee Policy
Agenda FEMA and Levees Levee Accreditation Reviews Proposed Changes to the FEMA Levee Policy Page 2 FEMA and Levees FEMA and Levees FEMA does NOT own or operate any levees Establishment of appropriate
More informationCHAPTER 3 FLOOD RELATED STUDIES
CHAPTER 3 FLOOD RELATED STUDIES Although the area has experienced regular flooding there have been few formal flood studies until more recently. There are a number of water quality studies in the basins.
More informationIT TAKES A VILLAGE A HISTORY OF CTP PARTNERSHIP IN NORTH CAROLINA. ASFPM Presentation. June 21, Concurrent Session C8 (3:45-5:15pm)
IT TAKES A VILLAGE A HISTORY OF CTP PARTNERSHIP IN NORTH CAROLINA ASFPM Presentation June 21, 2016 - Concurrent Session C8 (3:45-5:15pm) Tim Trautman, Charlotte-Mecklenburg Stormwater Services Tonda Shelton,
More informationUrban Study. Rocky Branch Watershed Columbia, South Carolina. June 1, Project No
Urban Study Rocky Branch Watershed Columbia, South Carolina Prepared for: City of Columbia 1136 Washington Street Columbia, SC 29217 Prepared by: AMEC Environment & Infrastructure, Inc. 720 Gracern Road
More informationPrepared for: City of Jeffersonville. November Prepared by
JEFFERSONVILLE STORMWATER MASTER PLAN HYDRAULICS APPENDIX JEFFERSONVILLE, INDIANA Prepared for: City of Jeffersonville November 2011 Prepared by Christopher B. Burke Engineering, Ltd. 115 W. Washington
More informationHey and Associates, Inc.
Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM
More informationFloodCast: A Framework for Enhanced Flood Event Decision Making for Transportation Resilience
NCHRP 20-59(53) FloodCast: A Framework for Enhanced Flood Event Decision Making for Transportation Resilience April 2017 Presenters: Mat Mampara, Caroline Whitehead & Alaurah Moss (Dewberry) Project Overview
More informationThe Iowa Watershed Approach
Larry Weber Director, IIHR Hydroscience & Engineering Larry-weber@uiowa.edu 1 North Kickoff Raccoon meeting River follow-up Watershed Project Update 2 Review: National Disaster Resilience Competition Funder:
More informationUpper Fox Watershed FEMA Risk MAP Action Discovery Meeting October 1, 2014
Upper Fox Watershed FEMA Risk MAP Action Discovery Meeting October 1, 2014 Glenn Heistand P.E., CFM Dan Gambill, P.E. Mary Richardson, CFM Pat Hubbartt, CFM Brad McVay, CFM Risk MAP Discovery Upper Fox
More informationWood-Pawcatuck Watershed Flood Resiliency Management Plan
Wood-Pawcatuck Watershed Flood Resiliency Management Plan Project Steering Committee Meeting May 21, 2015 Wood-Pawcatuck Watershed Association Meeting Agenda 10:00 10:05 Welcome and Opening Remarks 10:05
More informationEngineering Report Preliminary Floodplain Study. Executive Summary
Executive Summary Engineering Report Preliminary Floodplain Study The Federal Emergency Management Agency (FEMA) has updated the Flood Insurance Rate Maps (FIRM) for Finney County, including the City of
More informationBeaver Brook Flood Study
Alternatives Analysis Beaver Brook Flood Study Pelham, New Hampshire PREPARED FOR Town of Pelham 6 Village Green Pelham, NH 03076 PREPARED BY 101 Walnut Street PO Box 9151 Watertown, MA 02471 617.924.1770
More informationKansas Levee Certifications Assessments, Findings and Challenges. APWA Congress Denver, Co - Sept 18, 2011
Kansas Levee Certifications Assessments, Findings and Challenges APWA Congress Denver, Co - Sept 18, 2011 Introductions Presenters Doug Danaher, PE, CFM Wilson and Company Joe File, PE, CFM AMEC Brian
More informationCoordinated Hazard Assessment and Mapping Program
Coordinated Hazard Assessment and Mapping Program Mississippi River flood, 1993 A PREDICTABLE DISASTER Floods are the most common natural disaster in Illinois, accounting for well over 90% of declared
More informationCooperating Technical Partners Information Exchange. Flood Mapping for the Nation: How FEMA Tracks Progress and Validity Using CNMS
Cooperating Technical Partners Information Exchange Flood Mapping for the Nation: How FEMA Tracks Progress and Validity Using CNMS Audio and Web Settings Participation Open and hide your control panel
More informationHackensack River Flood Reduction Study Update
Township of River Vale Hackensack River Flood Reduction Study Update November 11, 2013 Purpose of Study To Analyze Where Frequent Flooding Is Impacting Property and How It Might Be Reduced Hackensack River
More informationProject Drainage Report
Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater
More information2. Potential Extreme Peak Discharge in Texas
2. Potential Extreme Peak Discharge in Texas This part of the work is focused on using GIS to apply the latest USGS peak discharge equations to create a 500m grid that stores the potential peak discharge
More informationModeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014
ASFPM 2014 Annual Conference Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014 Agenda Overview and Background Hydrology
More informationSECTION 11: REGULATORY FLOODWAYS
SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...
More informationFreight Street Development Strategy
Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed
More informationBridge Replacement Project. Preliminary Hydraulic Study. Lincoln, California BRLS-5089 (021) BRIDGE 19C Mcbean Park Drive at Auburn Ravine
Bridge Replacement Project Preliminary Hydraulic Study Lincoln, California BRLS-5089 (021) BRIDGE 19C 0059 Mcbean Park Drive at Auburn Ravine Prepared By: Prepared By: Date 11/25/2014 Thomas S. Plummer
More informationThe Land & Infrastructure Resiliency Assessment (LIRA) Project Economic Flood Hazard Assessment
The Land & Infrastructure Resiliency Assessment (LIRA) Project Economic Flood Hazard Assessment Robert Armstrong / Cameron Kayter Agri-Environment Services Branch LIRA Background Subcomponent of Climate
More informationTitle Advanced Hydraulic Modeling to Support Emergency Action Plans
Title Advanced Hydraulic Modeling to Support Emergency Action Plans Abstract Freese and Nichols, Inc. (FNI) developed an Emergency Action Plan (EAP) for a Levee Improvement District (LID) located in a
More informationMissouri River Flood Inundation Maps
State Risk Management Team Missouri 's hazard mitigation team Missouri River Flood Inundation Maps Which is more useful, inundation maps tied to the river stage or tied to flow? Percent Count River stage
More informationKentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map
Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map Michelle Meehan, PE Carey Johnson ASFPM 2013 Conference June 12, 2013 What We ll Talk About Today Overview of KDOW
More informationDiscovery Report Lake Ontario Irondequoit-Ninemile Watershed HUC Cayuga, Monroe, Ontario, Oswego, and Wayne Counties, New York*
Discovery Report Lake Ontario Irondequoit-Ninemile Watershed HUC 04140101 Cayuga, Monroe, Ontario, Oswego, and Wayne Counties, New York* *These counties span more than one watershed; please see following
More informationFloodplain Development
Floodplain Development Floodplain Regulations State: Part 31 of Public Act 451 Local: Federal: Building Codes, Zoning and Floodplain Management Ordinances National Flood Insurance Program Floodplain:
More informationPAPERWORK REDUCTION ACT A. GENERAL
U.S. DEPARTMENT OF HOMELAND SECURITY - FEDERAL EMERGENCY MANAGEMENT AGENCY RIVERINE STRUCTURES FORM O.M.B No. 1660-0016 Expires: 12/31/2010 PAPERWORK REDUCTION ACT Public reporting burden for this form
More informationQuestions & Responses from April 26, 2017 Public Presentation
Questions & Responses from April 26, 2017 Public Presentation Questions and comments were gathered on index cards collected at the Public Presentation by the Maumee Watershed Conservancy District and Stantec
More informationAPPLICATION FOR HAZARD MITIGATION GRANT
Project Number South Dakota Office of Emergency Management 118 W. Capitol Ave Pierre, SD 57501 605-773-3231 APPLICATION FOR HAZARD MITIGATION GRANT This application is for a Hazard Mitigation Grant under
More informationAPPENDIX 4 ARROYO MODELING
APPENDIX 4 ARROYO MODELING The existing HEC-HMS model can serve as a baseline for further development and analysis of major arroyos in the city. The model would need to be updated and expanded to consider
More informationThe following paragraphs provide a bulleted summary of the items discussed during the meeting:
minutes Flood Insurance Study Update Meeting City of Vacaville Public Works Conference Room #2 650 Merchant Street Vacaville, California June 22, 2011 10:00 a.m. 12:00 p.m. ATTENDEES: Tim Burke, Public
More informationKentucky Dam Safety and Floodplain Compliance
Kentucky Dam Safety and Floodplain Compliance Celebrating 10 years KAMM Conference September 10, 2014 Brian Shane Cook, PE, LSIT Kentucky Division of Water (502) 564-3410 ext 4822 Shane.Cook@ky.gov WHY
More informationPresentation at the Woodrow Wilson International Center for Scholars Charles Lawson and Willem Brakel July 23, 2009
Presentation at the Woodrow Wilson International Center for Scholars Charles Lawson and Willem Brakel July 23, 2009 40 percent of the border between the U.S. and Canada is water Over 300 lakes and rivers
More informationWatersheds, Hydrology and Flooding
Watersheds, Hydrology and Flooding Greg Karlovits, P.E., CFM Hydrologist US Army Corps of Engineers Rock Island District US Army Corps of Engineers Outline of Topics Before lunch: Watersheds and basics
More informationPresentation Overview
Little Dry Creek Restoration Deep River Flood Risk Management Final Presentation to LCRBDC June 10, 2015 Presentation Overview Project Overview & Background Information Data Collection Model Development
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationAppendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South
Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South Fork Dead Horse Slough in the, California Draft Location
More information4. Present Activities and Roles
4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified
More information3.3 Acceptable Downstream Conditions
iswm TM Criteria Manual - = Not typically used or able to meet design criterion. 1 = The application and performance of proprietary commercial devices and systems must be provided by the manufacturer and
More informationThe newly updated and comprehensive SWMP shall:
RFQ SCOPE OF SERVICES 2.1 Project Purpose The City of Miami, ( City ) is seeking professional engineering services from a qualified firm for the purpose of planning and developing a newly updated and comprehensive
More informationLouisiana Watershed Resiliency Study (LaWRS) Shona Gibson February 27, 2017
Louisiana Watershed Resiliency Study (LaWRS) Shona Gibson February 27, 2017 1 Background In response to flood events in 2016, watershed analysis and planning became a priority for state and local leaders
More informationSUMMARY OF BACKGROUND INFORMATION REVIEWED
TO: FROM: Mark Lobermeier, PE Ismael Martinez, PE Brad Woznak, PE, PH, CFM Tim Diedrich, PE DATE: RE: Kinni Corridor Plan - Hydrologic & Hydraulic Analysis Summary SEH No. RIVER 138553 14.00 This draft
More informationCHAPTER 3. Mitigation Strategy: Goals, Objectives, and Initiatives. 3.0 Introduction
CHAPTER 3 Mitigation Strategy: Goals, Objectives, and Initiatives 3.0 Introduction The mitigation strategy is this plan s call to action, serving as the blueprint for reducing losses and impacts from the
More informationiswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1
City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June 2010... Chapter 1 i CITY OF AZLE iswm CRITERIA MANUAL FOR SITE DEVELOPMENT AND CONSTRUCTION Incorporating the Regional NCTCOG Integrated
More informationRiparian Setback- What is that and what should I be doing? October 25th, 2016 Presented by: Anil Tangirala, PE, CFM, ENV SP
Riparian Setback- What is that and what should I be doing? October 25th, 2016 Presented by: Anil Tangirala, PE, CFM, ENV SP Agenda Introduction Stream and Riparian Impacts Ohio EPA Stormwater General Permit
More informationJACKSON COUNTY, GEORGIA AND INCORPORATED AREAS
Jackson County JACKSON COUNTY, GEORGIA AND INCORPORATED AREAS COMMUNITY NAME COMMUNITY NUMBER ARCADE, CITY OF 130597 BRASELTON, TOWN OF 130343 COMMERCE, CITY OF 130212 HOSCHTON, CITY OF 130344 JACKSON
More informationBasements and Crawlspaces: What s the Difference, and Who Cares?
Basements and Crawlspaces: What s the Difference, and Who Cares? Cadastral Consulting, LLC The difference between a basement and a crawlspace seems clear by common perception of what each one is. But when
More informationDAWSON COUNTY, GEORGIA
DAWSON COUNTY, GEORGIA AND INCORPORATED AREAS Dawson County COMMUNITY NAME COMMUNITY NUMBER DAWSON COUNTY 130304 (UNINCORPORATED AREAS) DAWSONVILLE, CITY OF 130064 SEPTEMBER 26, 2008 FLOOD INSURANCE STUDY
More informationIMPROVED MODELING OF THE GREAT PEE DEE RIVER: DOCUMENTATION IN SUPPORT OF FEMA APPEAL. Horry County, South Carolina
IMPROVED MODELING OF THE GREAT PEE DEE RIVER: DOCUMENTATION IN SUPPORT OF FEMA APPEAL Horry County, South Carolina July 15, 2016 CONTENTS 1 Introduction... 2 2 Hydrology... 3 3 HEC-RAS Model... 7 3.1 Cross
More informationPlan Rollout Presentation July 31, Michael G. Hahn, P.E., P.H. Chief Environmental Engineer. Southeastern Wisconsin Regional Planning Commission
Plan Rollout Presentation July 31, 2014 Michael G. Hahn, P.E., P.H. Chief Environmental Engineer Southeastern Wisconsin Regional Planning Commission # 219703 Racine County Flooding Recommendations and
More informationTipton Flood Resilience Plan - Strategies for Smart Growth and Long-Term Flood Risk Reduction
Tipton Flood Resilience Plan - Strategies for Smart Growth and Long-Term Flood Risk Reduction An Action Discovery Project as part of the Upper White River Watershed Discovery Report Presented by: Siavash
More informationBridge the Gap with RiskMAP. Ferrin P. Affleck, P.E. CFM, STARR David M. Ratté, P.E., FEMA Region X
Bridge the Gap with RiskMAP Ferrin P. Affleck, P.E. CFM, STARR David M. Ratté, P.E., FEMA Region X Introductions and Acknowledgments Authors Ferrin P. Affleck, P.E. CFM, STARR David M. Ratté, P.E., FEMA
More informationTECHNICAL GUIDANCE and CASE STUDY for INEFFECTIVE FLOW and CONVEYANCE SHADOW AREAS
Utilities electric stormwater wastewater water 700 Wood St. PO Box 580 Fort Collins, CO 80522 970.221.6700 970.221.6619 fax 970.224.6003 TDD utilities@fcgov.com fcgov.com/utilities TECHNICAL GUIDANCE and
More informationDRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E.
\ Memorandum SSPEED Center at Rice University Department of Civil & Environmental Engineering 6100 Main MS-317 Houston, Texas 77005-1827 sspeed.rice.edu tel: 713-348-4977 To Andy Yung, P.E. CFM; Lane Lease,
More informationCITY OF ANGLETON MASTER DRAINAGE PLAN PHASE I EVALUATION & PRELIMINARY REPORT
CITY OF ANGLETON MASTER DRAINAGE PLAN PHASE I EVALUATION & PRELIMINARY REPORT February 2008 Prepared by STOKES & ASSOCIATES, INC. 605 South Main Street, Suite 200 Henderson, Texas 75654 903-657-7558 TABLE
More informationUpper San Jacinto River Regional Watershed Flood Mitigation Plan Preliminary Scope of Services. July 2, 2018
INTRODUCTION BACKGROUND Upper San Jacinto River Regional Watershed Flood Mitigation Plan Preliminary Scope of Services In August 2017, Hurricane Harvey struck the Texas coast, bringing a historic amount
More informationRecord Keeping For Floodplain Managers
Record Keeping For Floodplain Managers Box of records in a closet Records kept digitally Why Do Communities Need To Maintain Records? To provide fast and accurate information after a disaster. To provide
More informationTraffic Impact Analysis (TIA) POLICY
Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed
More informationCHAPTER 3. The Mitigation Strategy: Goals, Objectives, And Initiatives. 3.0 Introduction
CHAPTER 3 The Mitigation Strategy: Goals, Objectives, And Initiatives 3.0 Introduction The mitigation strategy is this plan s call to action, serving as the blueprint for reducing losses and impacts from
More informationTechnical Memorandum No Basis of Comparison
Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.1 Basis of Comparison Task: Basis of Comparison To: PRWFPA Staff Working Group Prepared by: J. Schaaf Reviewed by: R. Raines
More informationHandout #1 Draft Action Plan City of Los Angeles Floodplain Management Plan 2015 Update
P-1 Maintain the City Tsunami Response Plan Annex and community education effort and participate in the Los Angeles County Operational Area Tsunami Mitigation Task Force. EMD, HD General, HD Low. Work
More informationAppendix VI: Illustrative example
Central Valley Hydrology Study (CVHS) Appendix VI: Illustrative example November 5, 2009 US Army Corps of Engineers, Sacramento District Prepared by: David Ford Consulting Engineers, Inc. Table of contents
More informationDRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA
DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA Prepared for: ConocoPhillips Alaska, Inc. Anchorage, AK March
More informationHEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification
HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification OFMA 2017 Annual Conference September 19, 2017 Presented by: Jeff Doudrick, PE, ENV SP Project Manager HNTB Corporation Agenda Project
More informationCombining a Conceptual Hydrologic Model (SWAT) and a Hydrodynamic Model (Telemac 3D) to Simulate Reservoir Dynamics in. Eagle Creek Reservoir, Indiana
Combining a Conceptual Hydrologic Model (SWAT) and a Hydrodynamic Model (Telemac 3D) to Simulate Reservoir Dynamics in Eagle Creek Reservoir, Indiana 1 Purpose of Modeling Effort Fate and Transport of
More informationAPPLICATION FOR HAZARD MITIGATION GRANT
Project Number South Dakota Office of Emergency Management 118 W. Capitol Ave Pierre, SD 57501 605-773-3231 APPLICATION FOR HAZARD MITIGATION GRANT This application is for a Hazard Mitigation Grant under
More informationOGLE COUNTY, ILLINOIS AND INCORPORATED AREAS
OGLE COUNTY, ILLINOIS AND INCORPORATED AREAS COMMUNITY NAME COMMUNITY NUMBER Ogle County ADELINE, VILLAGE OF 170835 BYRON, CITY OF 170526 *CRESTON, VILLAGE OF 171289 *DAVIS JUNCTION, VILLAGE OF 171076
More informationFlood Mitigation Plan
City of Huntsville, Alabama Flood Mitigation Plan 2001 Prepared by Flood Mitigation Planning Committee June 1, 2001 City of Huntsville, Alabama Flood Mitigation Plan Executive Summary 1973 1999 Prepared
More informationLocation Hydraulic Study Alisal Creek Bridge at Hartnell Road State Bridge Number 44C0110 County Bridge Number 209
Alisal Creek Bridge at Hartnell Road State Bridge Number 44C0110 County Bridge Number 209 Prepared for Monterey County RMA February 2017 10680 White Rock Road, Suite 100 Rancho Cordova, CA 95670-6165 Table
More informationSECTION III: WATERSHED TECHNICAL ANALYSIS
Trout Creek Watershed Stormwater Management Plan SECTION III: WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling An initial step this study of the Trout Creek watershed was the selection of a stormwater
More informationStorm Water System Improvements
IV Storm Water System Improvements A. General The purpose of this Section is to establish standard principles and practices for the design and construction of storm drainage facilities within the City
More informationDistributed Storage Alternative Screening Analysis February 17, 2015
Distributed Storage Alternative Screening Analysis February 17, 2015 Executive Summary The Distributed Storage Alternative (DSA) was conceptualized during the public comment and alternative screening process
More informationDRAINAGE STUDY CROWS LANDING INDUSTRIAL BUSINESS PARK. Stanislaus County. Prepared by:
DRAINAGE STUDY FOR CROWS LANDING INDUSTRIAL BUSINESS PARK Stanislaus County Prepared by: March, 2017 Revised November, 2017 Table of Contents EXECUTIVE SUMMARY... 1 1. INTRODUCTION... 2 2. HYDROLOGY...
More informationSWAP Risk Informed Methods for Stormwater Assessment and Prioritization
SWAP Risk Informed Methods for Stormwater Assessment and Prioritization Sara Hillegas Woida, Hydraulic Engineer US Army Corps of Engineers, Pittsburgh Thomas Maier, Biologist/Planner US Army Corps of Engineers,
More informationChapter 4. Drainage Report and Construction Drawing Submittal Requirements
4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for
More informationFlood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project
Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project US Army Corps of Engineers Zac Corum, PE, Hydraulic Engineer Travis Ball, PE, CFM, Hydraulic Engineer Seattle District
More informationAppendix M. Summary of Local Sea Level Rise Planning Efforts. Draft
Appendix M Summary of Local Sea Level Rise Planning Efforts Appendix M: Summary of Local Sea Level Rise Planning Efforts Summary of Local Sea Level Rise Planning Efforts Half Moon Bay SLR Planning Efforts
More informationSTATE MAPPING BUSINESS PLAN OUTLINE
STATE MAPPING BUSINESS PLAN OUTLINE good beginnings are not the measure of success. What matters in the end is completion. Performance. Results. Not just making promises, but making good on promises. George
More informationOCONEE COUNTY, GEORGIA
OCONEE COUNTY, GEORGIA AND INCORPORATED AREAS Oconee County Community Name Community Number *BISHOP, TOWN OF 130620 *BOGART, CITY OF 130490 NORTH HIGH SHOALS, TOWN OF 130368 OCONEE COUNTY 130453 (UNINCORPORATED
More informationAttachment H: Engineering Documentation
Attachment H: Engineering Documentation Part 2: Hydrologic and Hydraulic Consistency Worksheet Inland Water Resources Division Permit Activities This worksheet has four sections; only complete the section(s)
More information