THERMAL STORAGE FEASIBILITY STUDY
|
|
- August Bradford
- 6 years ago
- Views:
Transcription
1 THERMAL STORAGE FEASIBILITY STUDY SPRING 2005 NEW HOUSE RESIDENCE HALL
2 PRESENTATION OUTLINE GENERAL PROJECT DATA PROJECT TEAM MECHANICAL REDESIGN ELECTRICAL ANALYSIS ACOUSTICAL ANALYSIS CONCLUSIONS
3 GENERAL PROJECT DATA
4 GENERAL PROJECT DATA LOCATION Carnegie Mellon University Campus 1030 Moorewood Ave., Pittsburgh, PA SIZE 72,000 sq. ft. 6 Stories (5 floors above grade) OCCUPANCY TYPE 257 Bed Residential Dormitory
5 GENERAL PROJECT DATA CONSTRUCTION Began January 2002 Complete March 2003 ACTUAL COST $ 12 million PROJECT DELIVERY METHOD Design-Bid Bid-BuildBuild
6 PROJECT TEAM
7 PROJECT TEAM OWNER: ARCHITECT: MEP ENGINEER: STRUCTURAL ENGINEER: CONSTRUCTION MANAGER: COMMISSIONING: Carnegie Mellon University Bohlin Cywinski Jackson H.F. Lenz Company Atlantic Engineering Services Rycon Construction, Inc. LLI Technologies
8 MECHANICAL REDESIGN
9 MECHANICAL REDESIGN ORIGINAL DESIGN OBJECTIVES: 1. Green Design Principles 2. Individual Room Temperature Control 3. Exceed Code for Indoor Air Quality
10 MECHANICAL REDESIGN EXISTING DESIGN CONDITIONS: Indoor Outdoor Conditions Supply Winter Air 55 F 2 F F F db db (99.6%) 60% RH Zone Setpoints Summer F F db 30-60% 86 F F db RH 70 F wb (1%)
11 MECHANICAL REDESIGN EXISTING MECHANICAL CONDITIONS: AIR SIDE (5) Air Handling Units Constant Volume 1,000 12,000 cfm AHU-5 100% OA Make-Up Unit Air-to to-air Energy Recovery
12 MECHANICAL REDESIGN EXISTING MECHANICAL CONDITIONS: WATER SIDE (2) 60 ton Air-Cooled Screw Chillers Delivering Water Temperatures of 44 F 253 gpm Total System Four-Pipe Fan Coil Units Separate Ventilation System
13 MECHANICAL REDESIGN NEW DESIGN GOALS: 1. Reduce Peak Hour Energy Costs 2. Increase Mechanical System Efficiency
14 MECHANICAL REDESIGN HOURLY LOAD PROFILE: Chiller Load (tons) Data for July Total Cooling Load 2,241 ton-hrs Peak Hourly Load 103 tons Hour of Day
15 MECHANICAL REDESIGN DESIGN STRATEGY: PARTIAL STORAGE-DEMAND LIMITING SYSTEM Chillers & Storage Tanks Run in Parallel Equal Load to Original Design Capacity Use Same Discharge Temperature Operate Chiller at Reduced Capacity During On-Peak Hours Source: ASHRAE Design Guide for Cool Thermal Storage
16 MECHANICAL REDESIGN ADDITIONAL COMPONENTS: CALMAC 1098C STORAGE TANKS ton-hrs 25% Ethylene Glycol (1) 35 TON AIR-COOLED SCROLL CHILLER 26 tons) (1) 94 TON AIR-COOLED SCROLL CHILLER ADDITIONAL PUMP 107 gpm
17 MECHANICAL REDESIGN CHARGE/DISCHARGE CYCLES: Off-peak Hour Control On-peak Hour Control
18 MECHANICAL REDESIGN COOLING COSTS: Duquesne Light Company Time Total Charge Peak Demand On-Peak Off-Peak /kwh /kwh /kwh On-Peak Hours: 10:00 a.m. 9:00 p.m.
19 MECHANICAL REDESIGN COOLING COSTS: ORIGINAL DESIGN Monthly Average Cost: REDESIGN Monthly Average Cost: $20, $17, REDESIGN MONTHLY SAVINGS: $3,300.00
20 MECHANICAL REDESIGN EQUIPMENT COSTS: STORAGE TANKS EXTRA CHILLER CAPACITY ADDITIONAL PUMP $34, $5, $1, TOTAL EQUIPMENT COST: $41,300.00
21 MECHANICAL REDESIGN PAYBACK PERIOD: PAYBACK PERIOD = P / A P = INTIAL COST A = MONTHLY SAVINGS TOTAL PAYBACK PERIOD: 13 MONTHS
22 ELECTRICAL ANALYSIS Breadth Study
23 ELECTRICAL ANALYSIS OBJECTIVE: 1. Size New Equipment Feeds 2. Check Panelboard Capabilities
24 ELECTRICAL ANALYSIS BRANCH CIRCUITS: 2002 NATIONAL ELECTRIC CODE Table Full Load Current Breakers 250% Table Wire Sizing Tables of Chapter 9 Conduit Sizes
25 ELECTRICAL ANALYSIS BRANCH CIRCUITS: MECHANICAL EQUIPMENT ELECTRICAL SIZING Pump 2 hp, 460 V Chillers 41 hp, 460 V 150 hp, 460 V FLC 3.4A FLC 65A 180A Breaker 15A 2.44 ½, 4-#124 THW (Cu) Breaker 175A 450A kva kva Wire Size Wire Size 2, 4-#2/04 THW (Cu) 3, 4-#7004 THW (Cu)
26 ELECTRICAL ANALYSIS PANELBOARD: TOTAL PANEL SCHEDULE kva: = kva total = 355 kva MINIMUM AMPACITY: + (0.25)(kVA largest ) = Total kva / [(.480)(1.73)] = 427 A MAXIMUM AMPACITY: = [Total kva + (.75)(kVA largest ) / [(.480)(1.73)] = 505 A ACTUAL AMPACITY = 600 A OK
27 ACOUSTICAL ANALYSIS Breadth Study
28 ACOUSTICAL ANALYSIS OBJECTIVE: 1. Determine Relative Loudness of Mechanical Room 2. Check NC Levels with Adjacent Room
29 ACOUSTICAL ANALYSIS MECHANICAL ROOM CHARACTERISTICS: 125 Hz 15m x 7m x 3.24m (Basement) 8 CMU Block Walls 250 Hz 8 Concrete Slab Ceiling Absorption Characteristics 500 Hz (SI) freq 125 Hz 250 Hz 500 Hz 1000 Hz 2000 Hz 4000 Hz L w s α c α w α f freq 1000 S Hz c α c Hz Hz S w α w L w s S f α f ΣS i α i α sab R T s
30 ACOUSTICAL ANALYSIS DINING ROOM CHARACTERISTICS: 15m x 7m x 3.24m (1 Floor) Wood Parquet Floor Acoustical Ceiling Tile Absorption Characteristics (SI) freq 125 Hz 250 Hz 500 Hz 1000 Hz 2000 Hz 4000 Hz α c α w α g α f S c α c S w α w Gypsum Walls Glass Windows S f α f ΣS i α I α sab R T r
31 ACOUSTICAL ANALYSIS ANALYSIS: L p r Actual 62 Dining Room / Reading Room Desired NC freq 125 Hz 250 Hz 500 Hz 1000 Hz 2000 Hz 4000 Hz L p s TL TL 50 5 Safety factor NR ACTUAL NC 50 L p r Actual L p r Desired
32 ACOUSTICAL ANALYSIS ANALYSIS: Additional Materials 2 Thick, Porous Sound Absorbing Material Mechanical Room Ceiling freq Achievements Absorb Excessive Low Frequency 125 Hz Rumbling 250 Hz Did Not Disturb Dining Room ACTUAL NC Hz 1000 Hz 2000 Hz 4000 Hz L p r Actual L p r Desired
33 CONCLUSIONS
34 CONCLUSIONS RECOMMENDATIONS: INSTALL - PARTIAL STORAGE-DEMAND LIMITING SYSTEM Decreases Peak Hourly Load Costs Does Not Interrupt the Mechanical System Downstream Has Minimal Payback Period
35 ACKNOWLEDGEMENTS
36 ACKNOWLEDGEMENTS DEPARTMENT OF ARCHITECTURAL ENGINEERING CARNEGIE MELLON UNIVERSITY Tim Michael Peg Hart Brad Hochberg Steve Lee Rohini Brahme H.F. Lenz Company John Stewart Bob Stano AE FRIENDS The Roommates The Office The Woman
37 QUESTIONS
38 ACOUSTICAL EQUATIONS R T = ΣS i α i / [1-α sab ] α sab = ΣS i α i / ΣS i LP mech = LW mech 10Log[R Tmech ] + 6 NR = TL sf 10Log[S w / R Treceiver ] LP receiver = LP mech NR
NEW HOUSE RESIDENCE HALL CARNEGIE MELLON UNIVERSITY, OAKLAND, PA
Acoustical Analysis: Design Objective The primary acoustical goal of space planning is to place noisy equipment as far as possible from noise sensitive areas. New House did everything possible to achieve
More informationOklahoma University Children s Medical Office Building
Oklahoma University Children s Medical Office Building Oklahoma City, O.K., BAE Advisor: Laura Miller Presentation Outline VRF System Dedicated Outdoor Air System Evaluation VRF Indoor Units Design Criteria
More informationThe Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option
The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study
More informationGrunenwald Science and Technology Building
Grunenwald Science and Technology Building Clarion University- Clarion, PA AE 482 Mechanical Project Proposal: Proposal for Alternative Designs Shane Helm The Pennsylvania State University Architectural
More informationTable 39 - Mechanical Room Surfaces Surface Area (sf) Floor Ceiling Exterior Walls Interior Walls Total 5245.
Acoustical Analysis There are many different acoustical issues that could be studied and dealt with in a hotel similar to the BWI Hilton. But the new mechanical design work previously described in the
More information2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.
Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems
More informationPresentation Outline. Project Information & Background. Project Information & Background. Project Team. Boston, Massachusetts
Project Team Owner Tufts Boston, Massachusetts Boston, Massachusetts Tufts $65 Million 8, sqft. Project Schedule Began in 995 Delayed from 997-2 Completed in 23 Architectural Firm Architectural Lead Architect
More informationDarren Bruce Mechanical Option 1919 M St, Washington DC Primary Faculty Advisor: Prof. Bahnfleth December 5, Mechanical Systems Proposal:
Primary Faculty Advisor: Prof. Bahnfleth December 5, 2003 Mechanical Systems Proposal: Executive Summary: My senior thesis redesign will focus on the mechanical aspects of1919 M St. 1919 is an 8-story,
More informationMechanical Project Proposal
Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18
More informationThesis Final Presentation
Acoustical lanalysis Thesis Final Presentation Facility Information Mechanical Information Goals Facility Information Location: Total Cost: $56,000,000 Occupancy: Office, Media Center Delivery Method:
More informationEMD SERONO RESEARCH CENTER EXISTING
EMD SERONO RESEARCH CENTER EXISTING BILLERICA, MA SHIYUN (SHARON) CHEN MECHANICAL AE SENIOR THESIS Building System Dedicated Outdoor Air System/ Systems Breadth Building Design Team Building: EMD Serono
More informationCONSTRUCTION REQUIREMENTS
CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary
More informationIntegration of Mechanical System Redesign. The New Learning Center Lutheran Theological Seminary at Philadelphia
Integration of Mechanical System Redesign Geothermal Heat Pump Redesign The New Learning Center Lutheran Theological Seminary at Philadelphia Wesley S. Lawson Architectural Engineering Mechanical Option
More informationProject Proposal Proposal for Investigation of Alternative Systems
Project Proposal Proposal for Investigation of Alternative Systems 01.15.2010 Defense Media Activity Building Fort George G. Meade Penn State University Architectural Engineering Faculty Advisor: Dr. Treado
More informationCoppin State University Physical Education Complex - Technical Report 2
Coppin State University Physical Education Complex - Technical Report 2 Building and Plant Energy Analysis Report Kaylee M Damico Advisor: Dr. Jelena Srebric Location: Baltimore, MD Table of Contents Contents
More informationNorth Pocono High School
Building System Integration Energy and Cost Analysis Architectural Engineering Senior Thesis Presentation Pennsylvania State University Presentation Outline Project Outline Existing System Design Conditions
More informationGeorgetown University New Science Center
Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical
More informationThesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin
Thesis Proposal Photo by Fred Martin Clemson University Advanced Material Research Laboratory Anderson, SC David Anderson Mechanical Option Friday, December 15, 2006 Table of Contents 1. Executive Summary
More informationChilled Water Plant Redesign
17 Chilled Water Plant Redesign OVERVIEW The chilled water plant redesign includes the addition of a thermal energy storage system. This allows for economic and operational benefits for the facility by
More informationWESTINGHOUSE ELECTRIC NUCLEAR
WESTINGHOUSE ELECTRIC NUCLEAR ENGINEERING HEADQUARTERS DANIEL AUGHENBAUGH - MECHANICAL OPTION Daniel Aughenbaugh Mechanical Option PRESENTATION OUTLINE INTRODUCTION EXISTING MECHANICAL SYSTEM MY DESIGN
More informationGlen Burnie High School Glen Burnie, MD. Wade Myers Mechanical Option
I. I n t r o d u c t i o n II. Existing Mechanical System III. Proposed System Alterations IV. CM Breadth V. Conclusion School Background 6 building; campus style high school Located in Construction of
More informationRedland Tech Center Rockville, MD. Shawn Pepple Construction Management April 14, 2009
Rockville, MD Redland Tech Center Project Overview Two office buildings with stand alone parking garage Building II: 9 levels; 210,240 SF Building III: 6 levels; 136,430 SF Parking Garage: 6 levels; 310,600
More informationMechanical Systems Proposal
Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December
More informationMechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation
Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation 2900 Fairview Park Drive, Prepared By: Charles Haack Mechancial Option November 21, 2008 Prepared For: Dr. William P.
More informationThesis Proposal for Berks Classroom and Lab Building
Thesis Proposal for Berks Classroom and Lab Building Berks Classroom and Lab Building Berks Campus Reading, PA Authored by Julia Broskey Mechanical Option Prepared for Dr. William P. Bahnfleth PE 11 January
More informationSusquehanna Center Renovations and Expansion
Professors Houser and Dannerth Thesis Scope of Work Electrical Branch Circuit Redesign Electrical Depths Motor Control Center SKM Analysis Lighting Redesign Exterior Façade Main Lobby Fitness and Weight
More informationSouth Jefferson High School Huyett Road Charles Town, WV 25414
Thesis Proposal Mechanical System Redesign Report Charles Town, WV 25414 Prepared for Dr. Jelena Srebric The Pennsylvania State University By Jonathon Gridley Friday, December 15, 2006 1.0 Table of Contents
More informationTechnical Report Three Mechanical Systems Existing Conditions Evaluation
09 10 Technical Report Three Mechanical Systems Existing Conditions Evaluation WESTINGHOUSE ELECTRIC CO. NUCLEAR ENGINEERING HEADQUARTERS CAMPUS Pittsburgh, PA Daniel P. Aughenbaugh Mechanical Dr. Bahnfleth
More informationMatthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA
Matthew Kutzler Structural Option Spring 2004 Buildings C and D Campus Square, Lehigh University Bethlehem, PA Located at Lehigh University in Bethlehem, PA Complex consists of four dormitories and a parking
More informationEquipment Floor Plan. Page 138
Acoustical Breadth The acoustical breadth scope was to analyze the existing conditions in the wood shop classroom and surrounding areas on the lower level of the building. The criteria used to evaluate
More informationTechnical Assignment 2 Building and Plant Energy Analysis
Technical Assignment 2 Building and Plant Energy Analysis Des Places Residence Hall Duquesne University Pittsburgh, PA Peter Edwards Advisor: James Freihaut October 4, 2010 Table of Contents Executive
More informationDEA Clandestine Laboratory Training Center
DEA Clandestine Laboratory Training Center David M. Potchak Penn State University Architectural Engineering Mechanical Option Background Information Existing Mechanical Systems Redesign Objectives Alternate
More informationMechanical Systems Project Proposal
Mechanical Systems Project Proposal December 15, 2006 Table of Contents 1.0 Executive Summary... 2 2.0 Building Background... 3 3.0 Proposal Objectives... 5 4.0 Initial Considerations... 6 5.0 Proposed
More informationThesis Proposal. Park. Findlay 12/10/2010. Connor Blood
1 Park Place Corporate Center One Mechanical Senior Thesis Project Thesis Proposal Park Place Corporate Center One Findlay Township,, PA 12/10/2010 Proposal Connor Blood 2 Park Place Corporate Center One
More informationAnalysis and System Design of a Large Chiller Plant for Korea, with or without Thermal Storage
Analysis and System Design of a Large Chiller Plant for Korea, with or without Thermal Storage Christine Levin HVAC Designer Flack + Kurtz Consulting Engineers, LLP New York, New York Peter Simmonds Director
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using
More informationThe New RLPS Architects Office Building Lancaster, PA Brice Ohl Mechanical Option Presented on 4/10/13
The New RLPS Architects Office Building Lancaster, PA Brice Ohl Mechanical Option Presented on 4/10/13 Owner & Architects: RLPS Architects Ltd. General Contractor: Warfel Construction Mechanical & Electrical
More informationComparison of Air Distribution Systems
of Air Distribution s vs. s & s Presentation Outline & s Distribution Conclusion & s & s Project Team Owner - Capital One Financial Corporation Owner s Rep - Jones Lang LaSalle Architect - Ai Architecture
More informationSHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4
Table of Contents 1 Executive Summary... 1 2 Building Summary 3 3 Existing Mechanical System. 4 4 Mechanical Design Objectives..... 4 5 Mechanical System Evaluation. 5 5.1 Air Distribution System Evaluation....
More informationAir-Water Systems. Chilled Ceilings and Beams TROX USA. Principle of Operation. Radiant Effect on Occupants. Early 1980 s. Chilled Ceiling Panels
Air-Water Systems and Beams Early 1980 s 1980 1990 2005 Buildings well insulated for heating Advent of personal computers Need to remove heat from space Limited space available TROX USA 1 2 Principle of
More informationThe New Student Housing Building at The Mount St. Mary s s University Emmitsburg,, Maryland
The New Student Housing Building at The Mount St. Mary s s University Emmitsburg,, Maryland Erik Shearer Mechanical Presentation Outline Project Background Current Mechanical Systems Mechanical Alternatives
More informationGerald R. Ford Museum
Gerald R. Ford Museum Grand Rapids, Michigan Executive Summary Building and Plant Energy Analysis Report: Part I Brendan J. Cullen The Pennsylvania State University AE Senior Thesis Mechanical Option September
More informationHITT Contracting Headquarters
Existing Conditions Falls Church,, VA Existing Conditions Existing Conditions HITT Contracting Headquarters Site EEconomics i & Existing Conditions Existing Project Team Conditions Owner HITT General Contracting
More informationBRIDGESIDE POINT II BUILDING SYSTEM OPTIMIZATION PITTSBURGH, PA ANTONIO DESANTIS VERNE APRIL 14, 2008
BRIDGESIDE POINT II PITTSBURGH, PA BUILDING SYSTEM OPTIMIZATION IMAGE COUTESY OF THE FERCHILL GROUP THE DEPARTMENT OF ARCHITECTURAL ENGINEERING AT THE PENNSYLVANIA STATE UNIVERSITY DUCTION OPTIMIZATION
More informationIII. Economics. A. General Page III-2 B. Initial Capital Costs Page III-3 C. Life Cycle Costs Page III-4
III. Economics Use of AERCON resulted in 3-month schedule reduction on this $23 million, 245,000-sq. ft. Residence Hall Complex. A. General Page III-2 B. Initial Capital Costs Page III-3 C. Life Cycle
More informationThe Ed Roberts Campus
The Ed Roberts Campus Proposal Anderson Clemenceau Mechanical Option Advisor: Donghyun Rim December 12, 2014 2 Contents Executive Summary... 3 Building Overview... 4 Existing Mechanical System... 5 Airside
More informationLEED Energy Performance Summary Report
Section 1.1 - General Information Simulation Program: Principle Source: Energy Code Used: Weather File: Climate Zone: New Construction Percent: Existing Renovation Percent: Quantity of Floors: Proposed:
More informationIrvine CA MAE ROW ROW ROW. Office Lighting Plan. Page 93
MAE DEPTH DAYLIGH TING STUDY To complete the MAE additional depth requirement for thesis, a daylighting analysis for the third floor open office space has been performed. Three northern windows provide
More informationBuilding Load and Energy Estimates Analysis. Instructor: Dr. Mumma. October 28, Thesis Building Sponsor s: INOVA Fairfax Hospital
David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute David J. Peterson Mechanical Option Mechanical Technical Report #2b The INOVA HEART INSTITUTE AT INOVA Fairfax
More informationDavid H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option. Proposal
0 David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option Proposal David H. Koch Institute for Integrative Cancer Research Massachusetts Institute of Technology Cambridge,
More information04/04/2012. Inc. By: Skanska. Image. New. Castle, DEE
Final Report Mechanical Project Final Report 04/04/2012 New Castle Center for Delaware Hospice, Inc. Image By: Skanska New Castle, DEE Pennn State University Architectural Engineering Table of Contents
More informationAE 481W Thesis Proposal
AE 481W Thesis Proposal I I Advisor: Dr. Treado UNIVERSITY OF CALIFORNIA SAN DIEGO RADY SCHOOL OF MANAGEMENT LA JOLLA, CA TABLE OF CONTENTS Executive Summary.3 Mechanical System Overview..4 Design Objectives,
More informationChilled Beams. The new system of choice?
Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams
More informationGeothermal Systems. The Good, The Bad, and The Ugly. Presentation by. John Bender, P.E. MWSK Geothermal Inc.
The Good, The Bad, and The Ugly Presentation by John Bender, P.E. MWSK Geothermal Inc. Growing market for MEP firms Equipment vendors Used on my LEED projects Energy Savings Sustainability Reduces Carbon
More informationIECC 2006 with Hawaii Amendments
IECC 2006 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST ENVELOPE REQUIREMENTS Instructions RECOMMENDED: List performance values, note exceptions that were applied, or provide other notes to the reviewer.
More informationMechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion
Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:
More informationEnergyPro Building Energy Analysis. Single-story School Building
EnergyPro Building Energy Analysis Single-story School Building EnergyPro Building Energy Analysis for a single-story school bulding Project Scope The purpose of the EnergyPro energy model was to evaluate
More informationEADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel Mechanical Option
EADQUARTERS 707 N. Calvert St. Mechanical System Renovation Construction Management & Lighting/Electrical Breadths Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option
More informationAnalysis 4 Acoustical Analysis of Interior Partitions- Breadth
Analysis 4 - Breadth Background Good classroom acoustics are vital when the teaching and learning process relies strongly on verbal communication. Transmission of noise from one learning environment to
More informationFreetown Elementary School
Building and Plant Energy Analysis Technical Report 2 Freetown Elementary School Glen Burnie, MD Matthew R. Buda The Pennsylvania State University Architectural Engineering Mechanical Option Advisor: Dr.
More informationPassive House retrofit study for Carnegie Mellon 1950's dormitory in Pittsburgh
Towards Carbon Neutrality in existing buildings Passive House retrofit study for Carnegie Mellon 1950's dormitory in Pittsburgh Jimena Serra Callirgos Architect, CAP, LEED GA Master of Science in Sustainable
More informationDuBois Regional Medical Center West Wing Addition. Mechanical Breadth
Mechanical Breadth Introduction For the mechanical breadth work, an in-depth analysis will be performed on the integration of a Thermal Energy Storage (TES) system. A TES system dramatically reduces energy
More informationEvaluation of Underfloor Air Distribution
McCarran International Airport Terminal 3 L as Vegas, NV Evaluation of Underfloor Air Distribution and Displacement Ventilation Systems The Pennsylvania State University AESenior ThesisPresentation, Spring
More informationDCP Capacity Upgrade By Adding Thermal Ice Storage. Jelle Wagelmans Sales Manager EVAPCO Middle East DMCC
DCP Capacity Upgrade By Adding Thermal Ice Storage Jelle Wagelmans Sales Manager EVAPCO Middle East DMCC 1 Major Components of a District Cooling Plant 2 Major Components of a DCP Chillers Cooling Capacity
More informationCentral Chiller Plants
Central Chiller Plants Institute for Facilities Management New Orleans, LA January 18,2016 Course 319 Presenter: John Vucci Associate Director HVAC Systems University of Maryland College Park, Maryland
More informationCOOLING COIL (35% ETHYLENE GLYCOL)
APPENDIX Contents A1.1 Existing Mechanical Equipment Schedules A1.2 Existing Mechanical System Schematic Drawings A2. Building Design Loads, Energy Loads and Cost Data Tables A3. Standard 62n-2001 Ventilation
More informationMECHANICAL PROJECT PROPOSAL (Revised)
PSUAE MECHANICAL PROJECT PROPOSAL (Revised) REDESIGN PROJECT Nicholas B Scheib 2011 M e c h a n i c a l O p t i o n - IP Table of Contents The Sunshine Elementary School Executive Summary... 2 Project
More informationIntegrated Design. Architectural Design v/s HVAC Design. HVAC Design after Architectural design
Integrated Design A necessity for sustainable buildings Architectural Design v/s HVAC Design or HVAC Design after Architectural design or Integration of Concept, Location, Esthetic and Technical Design
More informationEquipment Noise Sources
MECHANICAL AND ELECTRICAL* EQUIPMENT NOISE CONTROL Three elements of concern: source path receiver *the electrical part may be premature, but that s OK Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik
More informationSample Reports. for. HAP v4.90 Example Problem
Sample Reports for HAP v4.90 Example Problem December, 2014 Carrier Software Systems Copyright 2014 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using
More informationSenior Thesis Report Spring Appendix - A. HAP Calculations without Enthalpy Wheel Excel Graphs
Jason Jones Mechanical Option Senior Thesis Report Spring 2005 Appendix - A HAP Calculations without Enthalpy Wheel Excel Graphs Cooling Plant Sizing Summary for Chiller Plant Monmouth CD New Schedule1
More informationpercent hours of the year heat rejected to loop percent hour building load on loop, Btuh percent hour building load on loop, Btuh
HOBOKEN RESIDENTIAL C- Ground Loop Pump Calculations Central Geothermal System building load on loop, Btuh Bin - 5 5 25 35 45 55 hours of the year Count 3 35 48 64 79 89 96 96 3 32 3 6 5 7 274 292 86 46
More informationThesis Cira Centre Philadelphia. Structural Redesign of Lateral Force Resisting System. Andrew Kauffman Structural Option
Thesis 2005 Cira Centre Philadelphia Structural Redesign of Lateral Force Resisting System Andrew Kauffman Structural Option Presentation Outline Introduction Building Description Structural System Problem
More informationDiane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN. Mechanical Appendix
Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN Mechanical Appendix 131 Diane Emert Senior Thesis 2005 Broadway Plaza, Rochester, MN Wall System Summary For Happ Analysis Ceiling Systems Ceiling
More informationASHRAE s LowDown Showdown
ASHRAE s LowDown Showdown Presented to the Building Energy Simulation Forum 14 February 2018 James Cullin, PhD, PE Overview Project Approach Existing Building Modeling/Calibration Proposed Design Proposed
More informationSURNA Grow Facility: Systems Comparison - IEA
SURNA Grow Facility: Systems Comparison - IEA May 2016 SURNA Grow Facility This analysis provides the projected energy and associated cost comparison between the Surna proposed facility in comparison to
More informationWEST VIRGINIA UNIVERSITY ALUMNI CENTER Morgantown, West Virginia
Senior Thesis Final Report Dedicated Outdoor Air and Ground Source Heat Pump System Redesign Analysis 4/7/09 WEST VIRGINIA UNIVERSITY ALUMNI CENTER Morgantown, West Virginia GREGORY SMITHMYER PENN STATE
More informationSample Reports. for. HAP v4.80 Example Problem
Sample Reports for HAP v4.80 Example Problem October, 2013 Carrier Software Systems Copyright 2013 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using the
More informationEquipment Noise Sources
MECHANICAL AND ELECTRICAL EQUIPMENT NOISE CONTROL Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 Equipment Noise Sources Chillers Pumps Cooling towers Exhaust fans Air-handling units (fans)
More informationMechanical Tech Report 2
Mechanical Tech Report 2 Design Load Estimation and Energy Analysis M Resort Spa and Casino Tom M. Chirdon Faculty Advisor; William P. Bahnfleth October 24, 2008 Table of Contents 1.0 Executive summary
More informationMechanical and Electrical Systems in Buildings Fourth Edition
Online Instructor s Manual to accompany Mechanical and Electrical Systems in Buildings Fourth Edition Richard R. Janis, P.E. William K. Y. Tao, P.E., ScD. Upper Saddle River, New Jersey Columbus, Ohio
More informationSpacePak Manual J Load Analysis Project Sheet
SpacePak www.spacepak.com Telephone: (413) 564-5530 Fax: (413) 564-5815 e-mail: presalesupport@spacepak.com This PDF has pull-down menus and text boxes that can be completed on your computer and either:
More informationAN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries
AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER MICHAEL HALLENBECK, PE, CEM Southland Industries BRAC 133 OVERVIEW PROJECT OVERVIEW FAN POWERED INDUCTION UNIT CENTRAL UTILITY
More informationSUMMARY SPECIFICATION
Seventy St. Mary Axe has been designed with the most exacting of occupiers in mind. The result is a world-class building with a robust specification and the highest quality finishes. Occupancy ratio of
More informationRay & Joan Kroc Corps Community Center. Mathias Kehoe Mechanical Option April 09, 2012
Ray & Joan Kroc Corps Community Center Mathias Kehoe Mechanical Option April 09, 2012 Outline Ray & Joan Kroc Corps Community Center Introduction DOAS GSHP Electrical Breadth Summary Owned by Salvation
More informationBroad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal
Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...
More informationWalter Reed National Military Medical Center Bethesda, MD
Walter Reed National Military Medical Center Bethesda, MD Mechanical Project Proposal Prepared For: Dr. James D. Freihaut Prepared By: Justin Herzing Date: 1/14/10 Table of Contents Executive Summary:...
More informationKeith Beidel Mechanical Option Centre Community Hospital East Wing Expansion State College, PA 9/30/02
BUILDING AND PLANT ENERGY ANALYSIS REPORT: Part A Keith Beidel Mechanical Option Centre Community Hospital East Wing Expansion State College, PA 9/30/02 Executive Summary Centre Community Hospital East
More informationNext Generation: High Efficiency Energy Recovery Ventilator (ERV) 11/14/11 Dais Analytic Corporation
Next Generation: High Efficiency Energy Recovery Ventilator (ERV) 11/14/11 Dais Analytic Corporation Why use an ERV? Required by code in many states (ASHRAE & IBC) Pre-condition incoming fresh air using
More informationCharacteristics of Energy Consumption by building type of a U.S. Navy Installation in Hot and Humid Climate
Purdue University Purdue e-pubs International High Performance Buildings Conference School of Mechanical Engineering 216 Characteristics of Energy Consumption by building type of a U.S. Navy Installation
More informationThe Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario
The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario Visionwall Technologies Inc. 14904-123 Avenue Edmonton, Alberta, Canada T5V 1B4 Tel: 403 451 4000 Fax:
More informationWalter Reed National Military Medical Center Bethesda, MD
Walter Reed National Military Medical Center Bethesda, MD Mechanical Project Proposal Prepared For: Dr. James D. Freihaut Prepared By: Justin Herzing Date: 12/14/09 Table of Contents Executive Summary:...3
More informationProject Name: Example Building OFPC Project No.: 12345
Energy Impact Statement Project Name: Example Building OFPC Project : 12345 Building Description and Assumptions: The design professional shall provide a brief narrative describing various building related
More informationProposal: Mechanical System Redesign
Proposal: Mechanical System Redesign The 959 Eighth Avenue 10019 Faculty Advisor: Dr. James Freihaut December 12, 2005 Table of Contents 1.0 Executive Summary 2.0 3.0 Proposal Obectives 4.0 Preliminary
More informationASHRAE 90.1 The evolution continues
ASHRAE 90.1 The evolution continues 4 March 2009 Mick Schwedler, PE ASHRAE SSPC 90.1 Chair Manager, Trane Applications Engineering Historical Timeline 90.1-1980 updated 90.1-1999 major rewrite 90.1-2001
More informationBUILDING SYSTEMS NOISE CONTROL
BUILDING SYSTEMS NOISE CONTROL Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 First An Acoustics Refresher from ARCH 273 Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 2 1 Sound conceptually
More informationAcknowledgements 4. Executive Summary 5
Table of Contents Acknowledgements 4 Executive Summary 5 Building Overview.. 6 Building Summary.. 6 Site. 6 Evaluation of Existing Mechanical System. 7 Mechanical System Overview 7 Design Objective 7 Outdoor
More informationTechnology and Business Innovation Building Penn State Berks, Reading PA. Geothermal Redesign of the Gaige Building
The Gaige Technology and Business Innovation Building Penn State Berks, Reading PA Geothermal Redesign of the Gaige Building Final Report: Architectural Engineering Senior Thesis THE PENNSYLVANIA STATE
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 9 DESIGN COOLING DESIGN HEATING COOLING DATA AT Jan 1400 HEATING DATA AT DES HTG COOLING OA DB / WB 34.5 C / 23.7 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent
More information