1 Virginia Avenue Tunnel Reconstruction Open House Exhibits April 23, 2015

2 WORK AREA AREA 1 AREA 2 AREA 3 AREA 4 AREA 5 AREA 6 AREA 7 Virginia Avenue Tunnel Reconstruc on First 120-Day Planned Construc on Ac vi es ACTIVITY DESCRIPTION Install Construc on Fence and Erosion and Sedimenta on Control (E&SC) Measures Install Support of Excava on for Retaining Wall Excavate West Retaining Wall and Install Pile Caps Relocate Public U li es Remove Trees along Virginia Avenue Install Temporary Sidewalk around 200 I Steet Relocate Public U li es Install Temporary Sidewalks and Driveways Remove Trees along Virginia Avenue Install Construc on Fence and E&SC Measures Remove Trees along Virginia Avenue Install Support of Excava on for Phase 1 Tunnel Relocate Public U li es Install 6 th Street Siphon Reduce Lanes of Virginia Avenue between 5 th Street and 7 th Street Install Support of Excava on for Phase 1 Tunnel Relocate Public U li es Remove Trees along Virginia Avenue Install Construc on Fence and E&SC Measures Virginia Avenue Park Install 12 th Street Sewer Install Support of Excava on at 11 th Street for Phase 1 Tunnel Install Construc on Fence and E&SC Measures Clear / Grade Area Install Support of Excava on for Retaining Wall Excavate / Build East Retaining Wall Permits Obtained MONTH 1 Permits Obtained 2015 MONTH 2 MONTH 3 MONTH 4

3 Virginia Avenue Tunnel ReconstrucƟon First 120-Day Planned ConstrucƟon AcƟviƟes th South Portal to 6 Street

4 Virginia Avenue Tunnel ReconstrucƟon First 120-Day Planned ConstrucƟon AcƟviƟes th 7 Street to North Portal

5 Sec on 106 Compliance Historic and Archaeological Resources Archaeological Work Plan approved by DC State Historic Preserva on Office (SHPO) on February 11, 2015 Archaeological Resources Protec on Act (ARPA) Permit in Na onal Park Service (NPS) review Construc on Protec on Plan approved by DC SHPO on April 14, 2015 Historic American Engineering Record (HAER) documenta on in 30-day review with MOA signatories and consul ng par es Interpre ve Signage for Virginia Avenue Tunnel Concept and Graphics in internal review Interpre ve Signage for L Enfant Plan and Paving Site Concept and Graphics in internal review No fica on of the Availability of the Portal Stones to Eligible En es on February 17, 2015; Friends of Garfield Park and DC Department of Parks and Recrea on submi ed requests CP Virginia Tower Na onal Register of Historic Places (NRHP) Nomina on Form and DC Inventory of Historic Sites Form in internal review Rehabilita on Plan in preliminary review with DC SHPO Addi onal Tasks Interpre ve Signage for the St. Paul AUMP Church in prepara on

6 Virginia Avenue Tunnel Reconstruction Environmental Compliance The Final Environmental Impact Statement and Record of Decision provided environmental commitments and mitigations to minimize the potential impacts of the proposed tunnel reconstruction. A Register of the Environmental Commitments is being used to track the environmental requirements as incorporated in the project s design and construction specifications. CSX and the contractor are obliged under the National Environmental Policy Act (NEPA) to comply with these commitments. To ensure full compliance of the commitments, detailed monitoring plans are being carried out for Air Quality, Noise and Vibration. These plans have been approved by DDOT and provide guidance for establishing existing baseline levels before construction; methodologies for monitoring levels during construction; and procedures for correcting work activities should intensities approach predicted impact levels. Environmental commitments also require the restoration of Virginia Avenue e and local parks to conditions exceeding current day, including landscaping, additional park amenities and improved access and traffic operations. The commitments also require that a Maintenance of Traffic Plan be implemented to minimize traffic disruptions, to the extent practical, during construction operations. All commitments will be continuously coordinated with DDOT, appropriate regulatory agencies and the local community.

7 Background Air Monitoring / Sampling Ac vi es Legend: = Air Monitoring Site Four (4) fixed air monitoring sta ons were deployed to document background condi ons. Two separate mul ple day sampling events indicate background condi ons are consistent with the NEPA documents. Addi onal monitors (up to 8) will be placed during specific construc on ac vi es as described in the air monitoring plan. When monitors are upwind of construc on ac vi es they will con nue to iden fy background condi ons throughout the project area. Air monitoring summary reports will be published on a monthly basis.

8 Background Noise and Vibra on Monitoring Legend: = Noise Monitoring Site = Vibra on Monitoring Site Sixteen (16) fixed monitoring loca ons (8 noise and 8 vibra on) were measured con nuously over a two-week period to document ambient noise and vibra on levels in the project area. Data was collected from late February through mid-march. Detailed analysis will be used to establish baseline levels for comparison to noise and vibra on levels generated by construc on ac vi es.

9 Virginia Avenue Tunnel ReconstrucƟon Vermin Control and Management Plan Vermin to be Controlled Mammals such as squirrels, raccoon, skunk, opossum, mice, and rats Birds such as crows RepƟles such as snakes and toads Insects such as mosquitoes, Ɵcks, spiders, bees, and cockroaches PreventaƟve Measures Maintaining a clean, organized work area Minimizing vegetaɵve habitat PrevenƟng standing water Monitoring Professional vermin control company to idenɵfy paʃerns of animal, vermin, or insect acɵvity Clark/Parsons onsite observaɵon to ensure compliance with preventaɵve measures CorrecƟve AcƟon (professional vermin control company ) Interior and exterior baiɵng methods Relevant insecɵcides Non-poisonous trapper glue boards Other convenɵonal traps RecordaƟon of each inspecɵon and/or eradicaɵon acɵvity

10 Residen al & Community Mi ga on Plans CSX is implemen ng mi ga on plans to reduce the impact of construc on and offset some of the inconveniences of the Virginia Avenue Tunnel reconstruc on project. Residen al Property Mi ga on Program 57 of 68 eligible Front Row residents have enrolled in the Residen al Property Mi ga on Program and will begin receiving monthly inconvenience payments in April. All 68 have acknowledged receipt of informa on. Pre-Construc on Inspec on Program 67 of 68 eligible Front Row residents requested Pre-Construc on Inspec ons as of April 14, non-front Row residences have been inspected. 11 businesses and other non-residen al proper es have been inspected. All are eligible for Post-Construc on Inspec ons once the tunnel project is completed. Arthur Capper Center Grant CSX is providing a $250,000 grant to the owners of the Arthur Capper Senior Center. These funds are intended to be used to offset temporary inconveniences and support community enhancements of the Senior Center. Community Fund CSX selected Near Southeast Community Partners to serve as third-party administrator for the $650,000 community fund specified in the Record of Decision. NSC Partners is solici ng community representa ves to serve on the volunteer board that will develop funding criteria, review proposals and grant funds.

11 Supplemental Community Mi ga on Fund CSX is providing a $650,000 Supplemental Community Mi ga on Fund to offset temporary inconveniences and to support neighborhood enhancements. A commi ee of local community representa ves will help decide how the Community Fund is allocated and Near Southeast Community Partners (NSC Partners), the third-party administrator, will disperse the funds in phases during project construc on. Process: 1. Establishing the Community Commi ee Applica ons were due from interested par es by April 17, The third-party administrator will select the best-qualified applicants to create a commi ee that represents the en re community. First commi ee mee ng is planned for the week of May 4, Criteria Development Community commi ee and administrator will develop evalua on criteria for community enhancements and temporary inconvenience payments for non-front Row residents. Dra evalua on criteria will be published for community feedback. 3. Applying for Funds Community organiza ons proposing community enhancements and non-front Row residents experiencing temporary inconveniences are encouraged to apply for funds. Applica ons will be submi ed online or via mail. The applica on will be available at nscpartners.org. 4. Review and No fica on Process The Community Commi ee will review and evaluate funding requests using the approved criteria through a fair, transparent and unbiased process. Applicants will be no fied about funding decisions within 10 business days of commi ee decision and payments will be distributed by the administrator.

12 CSX Claims Process The CSX team is commi ed to limi ng construc on impacts from the Virginia Avenue Tunnel project. Residents may s ll need to make a claim for property damage they believe is caused by the project. CSX has a straigh orward process for managing claims. Where can I file a claim? To make an ini al report: Call (800) Submit request via Visit CSX s Virginia Avenue Tunnel Community Office at 861 New Jersey Avenue SE What is the claims process? Make an ini al report. A claims inves gator will contact you to gather more informa on. A thorough inves ga on will be completed, which will take some me. The inves gator will keep you informed of progress. We will work as quickly as possible to address your claim. What informa on do I need? Some documents may be needed to support your claim: Pre-construc on inspec on report (for claims related to residences); inspec ons available from CSX Proof of property ownership and insurance Two es mates of repair costs or paid receipts Photos of damaged property/site of incident Any witness statements Who can I speak to if I have more ques ons? A CSX representa ve is available at the CSX Virginia Avenue Tunnel Community Office during posted mes. You can also call us at (800) or submit a request through

13 Safety is a Way of Life Safety is CSX s highest priority. Guided by a policy to ensure the safety of our employees, our customers and the communi es we serve, CSX works relentlessly to prevent injuries and accidents. The CSX team is commi ed to safety on the Virginia Avenue Tunnel project and will implement extensive efforts to ensure the safety of project workers and the surrounding community. CSX Safety Facts CSX was the safest Class 1 railroad in America in 2012 and 2013 according to the Federal Railroad Administra on. CSX has reduced accidents by 58% since In the last 10 years, over 200 construc on projects have occurred near ac ve CSX rail lines in the DC area with zero rail-related incidents. Train Opera ons During Construc on All trains will operate in enclosed tunnels in front of residences during construc on. Railroad Employee In Charge will control all train movements through site. Each train requires explicit permission to enter site; permission granted only when site is confirmed safe for passage of trains All train crews receive alerts explaining restric ons; dedicated radio channels used for communica on; addi onal track-side signs alert crews to control zone All opera ons conducted in accordance with Federal Railroad Administra on rules and requirements Ensuring Site Safety All workers receive site-specific safety briefing before being allowed access All trackside workers required to pass Roadway Worker Protec on Training program annually Onsite Safety Officer required during any construc on 8-foot perimeter fencing, security ligh ng and regular CSX Police patrols to protect public and workers Tunnel safety will be monitored through extensive camera and electronic security systems

14 Emergency Plans & Response Safety is CSX s highest priority. Our goal is zero accidents in all opera ons and projects. Accident preven on is the first objec ve of the project s safety plan. CSX also invests extensively to protect the public s safety in the event an incident does occur. Should an incident occur, we believe in providing a meaningful Standard of Care that an cipates the needs of people and communi es, focuses on their safety, restores their lives and protects the environment. Emergency Plans In the event of an emergency, CSX and our construc on contractor have extensive response plans that will be implemented to protect workers and the public. Response plans include: Coordina on with Metropolitan Police Department and U.S. Capitol Police on area security issues Site tours and briefings with DC emergency agencies Immediate coordina on with DC emergency agencies Site evacua on and security procedures Immediate ac va on of railroad emergency response procedures in the event of an incident involving a train CSX Standard of Care Program CSX is prepared to meaningfully address the cri cal health care, business and communica on needs of our communi es and employees in the event of an incident. Our program is based on best prac ces and the highest standards of service. Focused on the needs of people, families and communi es Empowered through communica on and collabora on with responders Conveyed with sincerity and empathy un l community is restored

15 Staying Connected CSX is commi ed to keeping the community informed throughout the tunnel reconstruc on project. Informa on is available through a variety of resources, including quarterly open houses, monthly morning coffees, a project-specific website and more. We encourage you to use these resources and channels to stay informed and contact the project team with any ques ons or concerns. Quarterly Mee ngs Courtyard Marrio, 140 L Street SE 4:30 p.m. 7:30 p.m. Thursday, August 13, 2015 Thursday, November 12, 2015 Thursday, January 28, 2016 Website Sign up to receive Virginia Avenue Tunnel project updates: Twi Contact Us (800) VAT@csx.com Coffee with Chuck Informal discussions with Chuck Gullakson, chief project engineer, 7:30 a.m. 9:30 a.m. Courtyard Marrio, 140 L Street SE Wednesday, May 20, 2015 Wednesday, June 17, 2015 Thursday, July 23, 2015 Wednesday, August 19, 2015 CSX Community Office 861 New Jersey Avenue SE Hours: Monday & Wednesday, 7 a.m. to noon; Tuesday & Thursday, noon to 8 p.m. Or call (800) to request an appointment. Please check the project website for the latest informa on about office hours. CSX Railroad Police CSX Railroad Police patrol the project area on bicycles, with the K-9 unit, and in marked vehicles. Special agents are happy to answer ques ons about the project whenever you see them.

COMPANY PROFILE YEARS O F E XC E L L E N C E W I T H P R I D E. Committed to uphold integrity in the running of our Business C E L E B R AT I N G

COMPANY PROFILE YEARS O F E XC E L L E N C E W I T H P R I D E. Committed to uphold integrity in the running of our Business C E L E B R AT I N G COMPANY PROFILE 2017 C E L E B R AT I N G YEARS O F E XC E L L E N C E W I T H P R I D E Committed to uphold integrity in the running of our Business THEWO ENGINEERING COMPANY PROFILE 2017 INDEX THEWO

More information

Guide to the Occupa onal Health and Safety Act. Information for Workers

Guide to the Occupa onal Health and Safety Act. Information for Workers Guide to the Occupa onal Health and Safety Act Information for Workers This guide provides practical information about the Occupational Health and Safety Act (OHS Act). A key part of a safe workplace is

More information

February 2017 Homes, schools, and neighborhoods influence community health in fundamental ways. In these places are opportuni es to influence and improve health, by ensuring that everyone has access to

More information

Aim of this Consulta on Event

Aim of this Consulta on Event We are pleased to welcome you to view and comment on the proposal for the construc on of a New Energy Plant (NEP) to be located back from the corner of Inchyra Road and Bo ness Road Grangemouth, on the

More information

Design Review Board Submi al Guidelines

Design Review Board Submi al Guidelines Design Review Board Submi al Guidelines The Design Review Board (DRB) is most effec ve when project design materials are prepared and presented to the DRB. Graphic material is generally preferred. Any

More information

How do we know which benefits are statutory?

How do we know which benefits are statutory? 1 Can help my business expand internationally? You can expand your business globally by plugging into the GPS eco-system. We help our clients expand globally to 150+ countries and are backed by a mix of

More information

Chapter 9: Congestion Management Process CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN

Chapter 9: Congestion Management Process CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN Chapter 9: Congestion Management Process CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN Conges on Management

More information

PRECONSTRUCTION BACKGROUND VIBRATION MONITORING SUMMARY REPORT

PRECONSTRUCTION BACKGROUND VIBRATION MONITORING SUMMARY REPORT PRECONSTRUCTION BACKGROUND VIBRATION MONITORING SUMMARY REPORT VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT WASHINGTON, DC Prepared for: CSX Transportation Prepared by: Gannett Fleming Inc. April 2015

More information

SURREY FA RECRUITMENT PACK

SURREY FA RECRUITMENT PACK SURREY FA RECRUITMENT PACK Chief Execu ve Officer March 2019 @surreyfa SurreyFA.com This is a fantastic opportunity to lead one of the most prestigious County FAs in the country. 2 ABOUT SURREY FA Surrey

More information

An -Bribery and An -Corrup on Policy

An -Bribery and An -Corrup on Policy An -Bribery and An -Corrup on Policy All ADT Africa Ltd employees and associated persons are required to: Comply with the na onal an -bribery and an -corrup on legisla on currently in force Act honestly,

More information

The County of San Bernardino invites candidates for the position of: Project Director, Consortium IV

The County of San Bernardino invites candidates for the position of: Project Director, Consortium IV The County of San Bernardino invites candidates for the position of: Project Director, Consortium IV Consor um IV The Mission of Consor um IV: Is to provide a client-based, fully integrated, on-line, user

More information

Governor s Council on Workforce Investment STRATEGIC PLAN

Governor s Council on Workforce Investment STRATEGIC PLAN Governor s Council on Workforce Investment 2018-2022 STRATEGIC PLAN Council on Workforce Investment 2018-2022 Strategic Plan Governor Sco Walker Room 115 East Wisconsin State Capitol Madison, WI 53703

More information

Monterey County Local Agency Management Program (LAMP) for Onsite Wastewater Treatment Systems FREQUENTLY ASKED QUESTIONS

Monterey County Local Agency Management Program (LAMP) for Onsite Wastewater Treatment Systems FREQUENTLY ASKED QUESTIONS Monterey County Local Agency Management Program (LAMP) for Onsite Wastewater Treatment Systems FREQUENTLY ASKED QUESTIONS Where can I learn more about the Monterey County LAMP? The Environmental Health

More information

State of Oregon Department of Forestry - Department of Revenue. No fica on: Opera on Name: Lake Creek South 2 H&S

State of Oregon Department of Forestry - Department of Revenue. No fica on: Opera on Name: Lake Creek South 2 H&S State of Oregon Department of Forestry - Department of Revenue No fica on Number: 2015-781-00102 Opera on Name: Lake Creek South 2 H&S This report is the processed informa on from the No fica on of Opera

More information

DRAFT. WHEREAS, FHWA, USMC, NPS, DDOT, DPR, DCSHPO and CSX are hereafter referred to as the Signatories to this MOA; and

DRAFT. WHEREAS, FHWA, USMC, NPS, DDOT, DPR, DCSHPO and CSX are hereafter referred to as the Signatories to this MOA; and MEMORANDUM OF AGREEMENT AMONG THE FEDERAL HIGHWAY ADMINISTRATION THE UNITED STATES MARINE CORPS THE NATIONAL PARK SERVICE THE DISTRICT DEPARTMENT OF TRANSPORTATION THE DISTRICT DEPARTMENT OF PARKS AND

More information

Limi ng Heights for Nonstructural Standard and EQ Wall Studs

Limi ng Heights for Nonstructural Standard and EQ Wall Studs TECH NOTE Publication 1, Version 1 March 2018 Limi ng Heights for Nonstructural Standard and EQ Wall Studs SUMMARY: This Technical Note addresses cold-formed steel studs in nonstructural interior wall

More information

CONSTRUCTION VIBRATION MONITORING SUMMARY REPORT OCTOBER 1 26, 2018

CONSTRUCTION VIBRATION MONITORING SUMMARY REPORT OCTOBER 1 26, 2018 CONSTRUCTION VIBRATION MONITORING SUMMARY REPORT OCTOBER 1 26, 2018 VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT WASHINGTON, DC Prepared for: CSX Transportation Prepared by: Gannett Fleming Inc. October

More information

Principles for Credible and Effec ve Sustainability Standards Systems. ISEAL Credibility Principles

Principles for Credible and Effec ve Sustainability Standards Systems. ISEAL Credibility Principles Principles for Credible and Effec ve Sustainability Standards Systems ISEAL Credibility Principles June 2013 ISEAL Credibility Principles Introduc on Voluntary sustainability standards systems are market-based

More information

Moonlight Fire Area Restoration

Moonlight Fire Area Restoration Planning Process NEPA (Na onal Environmental Policy Act) guides the Forest Service decisionmaking process and provides opportuni es for interested par es to give their ideas about resource management.

More information

Appendix B Section 106 Memorandum of Agreement

Appendix B Section 106 Memorandum of Agreement VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT NATIONAL ENVIRONMENTAL POLICY ACT RECORD OF DECISION Appendix B Section 106 Memorandum of Agreement THIS PAGE INTENTIONALLY LEFT BLANK. MEMORANDUM OF AGREEMENT

More information

FISCAL YEAR 2017 Annual Report

FISCAL YEAR 2017 Annual Report FISCAL YEAR 2017 Annual Report FISCAL YEAR 2017 ANNUAL REPORT Director s Message... 2 Department Descrip on. 3 Enterprise Funds & Facili es.. 5 Customer & Business Support... 7 Drought & Water Quality

More information

Railston Interiors Brochure FACILITY SERVICES

Railston Interiors Brochure FACILITY SERVICES Railston Interiors Brochure FACILITY SERVICES We have presence in Sydney, Melbourne and Brisbane. HQ in Sydney. SYDNEY, AUSTRALIA SGB Facility Services 1/19 Underwood Avenue Botany NSW 2019 t. 1300 55

More information

Types of Design Professionals Caitlyn Trepess

Types of Design Professionals Caitlyn Trepess SMALL BUSINESS RESOURCES Types of Design Professionals Caitlyn Trepess The size (physical and construc on cost), complexity, scope, and loca on of a project will dictate which types of design professionals

More information

QUADRAM INSTITUTE BIOSCIENCE CAREER PATHWAYS

QUADRAM INSTITUTE BIOSCIENCE CAREER PATHWAYS QUADRAM INSTITUTE BIOSCIENCE CAREER PATHWAYS INTRODUCTION Quadram Ins tute Bioscience (QIB) is at the forefront of a new interface between food science, gut biology and health. It develops solu ons to

More information

State of Oregon Department of Forestry - Department of Revenue. No fica on: Opera on Name: Browning Tract Release Spray 2015

State of Oregon Department of Forestry - Department of Revenue. No fica on: Opera on Name: Browning Tract Release Spray 2015 State of Oregon Department of Forestry - Department of Revenue No fica on Number: 2015-781-03211 Opera on Name: Browning Tract Release Spray 2015 This report is the processed informa on from the No fica

More information

n this guide you can find enrollment instruc ons, as well as ps and tricks for establishing a great rela onship with your mentor.

n this guide you can find enrollment instruc ons, as well as ps and tricks for establishing a great rela onship with your mentor. Mentee Guide ACOEP Mentor Program If you have any ques ons or concerns, contact Jaclyn Ronovsky, Member Services Assistant 312.445.5702 JRonovsky@acoep.org www.acoep.org Y our development as a physician

More information

Harvest Cleaning Services LIMITED Ensuring Tidiness Up To Your Doorstep!

Harvest Cleaning Services LIMITED Ensuring Tidiness Up To Your Doorstep! COMPANY PROFILE Harvest Cleaning Services LIMITED Synopsis We excel in providing cleaning and hygiene solu ons for commercial and residen al spaces as well as Factories and Learning Ins tu ons. The scope

More information

Essen al so ware for managing your fleet

Essen al so ware for managing your fleet ipad FleetWave CORE Essen al so ware for managing your fleet AWARDS2017 FLEET MANAGEMENT ISO/IEC 27001 BUREAU VERITAS Certification 1 Out of the box fleet management so ware With a compe ve entry-level

More information

Inland Intermodal Logistics Services Technology Solutions Division One Support Protocols Version 2.0

Inland Intermodal Logistics Services Technology Solutions Division One Support Protocols Version 2.0 Inland Intermodal Logistics Services Technology Solutions Division One Support Protocols Version 2.0 One Support Protocols One Support Hours: Hours of Operation for the One Support Service are between

More information

BERLIN, ALABAMA Incorporation Information

BERLIN, ALABAMA Incorporation Information BERLIN, ALABAMA Incorporation Information Quick Facts Established in the late 19th Century, Berlin is one of the oldest, most densely populated communi es in Cullman County which remains unincorporated.

More information

Infrastructure. A. Introduc on. B. Water System CHAPTER 7

Infrastructure. A. Introduc on. B. Water System CHAPTER 7 CHAPTER 7 Infrastructure A. Introduc on The purpose of this chapter is to summarize the exis ng and planned infrastructure facili es and provide recommended infrastructure upgrades for the Baldwin Park

More information

For Sellers. To locate your local SBDC advisor please visit wsbdc.org/contact an advisor

For Sellers. To locate your local SBDC advisor please visit wsbdc.org/contact an advisor Funded in part through a coopera ve agreement with the U.S. Small Business Administra on For Sellers You ve worked long and hard to build up a good business. Maybe the business is hugely profitable or

More information

14th JPC REMESA Naples, Italy 19 and 20 July 2017

14th JPC REMESA Naples, Italy 19 and 20 July 2017 14th JPC REMESA Naples, Italy 19 and 20 July 2017 The Single Window: a new approach to veterinary import controls Ministry of Health General Directorate for Animal Health and Veterinary Medicines Office

More information

SECTION I INVEST IN A CUTTING EDGE WORKFORCE

SECTION I INVEST IN A CUTTING EDGE WORKFORCE Our contract expires June 22, 2015. To achieve our goals of priori zing funding for cri cal public services, investment in a cu ng edge workforce, and accountability in government, we need to start organizing

More information

DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY

DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY SECTION 1.1. Pursuant to the Declaration of Covenants,

More information

RENEWAL FOR A CERTIFICATE OF AUTHORIZATION FOR A PROFESSIONAL CORPORATION

RENEWAL FOR A CERTIFICATE OF AUTHORIZATION FOR A PROFESSIONAL CORPORATION RENEWAL FOR A CERTIFICATE OF AUTHORIZATION FOR A PROFESSIONAL CORPORATION Date of submission of applica on: day month year SECTION A The address below is the primary address for the corpora on. Please

More information

Design Consultation: Non Technical Summary Triple Quest Micro Scale Gold Standard PoA Hydraid BioSand Water Filter Programme Central America

Design Consultation: Non Technical Summary Triple Quest Micro Scale Gold Standard PoA Hydraid BioSand Water Filter Programme Central America Design Consultation: Non Technical Summary Triple Quest Micro Scale Gold Standard PoA Hydraid BioSand Water Filter Programme Central America DESIGN CONSULTATION 1. Introduction to Micro Scale PoA 2.C/ME

More information

Technical Safety Management for INDUSTRIAL NATURAL GAS APPLICATIONS.

Technical Safety Management for INDUSTRIAL NATURAL GAS APPLICATIONS. Technical Safety Management for INDUSTRIAL NATURAL GAS APPLICATIONS 2 01 // TECHNICAL SAFETY MANAGEMENT TSM TSM // THE 3 PHASE PRINCIPLE Free your company from the reproach of organiza onal faults by introducing

More information

COUNTY OF KINGS Invites Applications For: ECONOMIC & WORKFORCE DEVELOPMENT DIRECTOR

COUNTY OF KINGS Invites Applications For: ECONOMIC & WORKFORCE DEVELOPMENT DIRECTOR COUNTY OF KINGS Invites Applications For: ECONOMIC & WORKFORCE DEVELOPMENT DIRECTOR ABOUT KINGS COUNTY Located in the heart of California's rich San Joaquin Valley, Kings County is 200 miles from the greater

More information

TRANSITION PLANNING GUIDE

TRANSITION PLANNING GUIDE TRANSITION PLANNING GUIDE AUSDAL FINANCIAL PARTNERS 220 NORTH MAIN ST., STE 400 DAVENPORT, IA 52801 563.326.2064 WWW.AUSDAL.COM WELCOME Congratula ons on your decision to join Ausdal Financial Partners

More information

PIRAMAL BUSINESS CODE OF CONDUCT

PIRAMAL BUSINESS CODE OF CONDUCT PIRAMAL BUSINESS CODE OF CONDUCT OUR VALUES AND STANDARDS FOR BUSINESS PIRAMAL BUSINESS CODE OF CONDUCT [EDITION II] JUN-2016 piramal.com 02 Piramal is commi ed to sustainability in all business ac vi

More information

Employee Rewards Program

Employee Rewards Program Employee Rewards Program August 2017 2 Ta bl e of Co n ten ts Welcome Le er...4 Program Descrip on...5 Program Eligibility...6 Points Guidelines...7 Metrics Measured...8 Gi Card Catalog...15 Points Redemp

More information

Addressing Climate Change

Addressing Climate Change Addressing Climate Change Developing and Applying the GHGProof Model in the Fraser Valley Regional District Fraser Valley Regional District Addressing Climate Change: Developing and Applying the GHGProof

More information

STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC

STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC PREPARED BY: Metropolitan Washington Airports Authority Washington Dulles International Airport Engineering

More information

INFRASTRUCTURE. For discussion of the town s roadways please refer to the transporta on sec on of this appendix and Chapter 7 Transporta on.

INFRASTRUCTURE. For discussion of the town s roadways please refer to the transporta on sec on of this appendix and Chapter 7 Transporta on. INFRASTRUCTURE Exis ng Town Infrastructure Sandisfield currently owns five major buildings and facili es including its main administra ve building located at the Town Hall Annex on Route 57. All wastewater

More information

Registra on Welcome Address and Opening Remarks. Is The USPTO Promo ng Innova on, Economic Growth And Global Compe veness?

Registra on Welcome Address and Opening Remarks. Is The USPTO Promo ng Innova on, Economic Growth And Global Compe veness? Sunday November 7th 11:00-1:30 1:30-1:45 Registra on Welcome Address and Opening Remarks 1:45-2:30 Is The USPTO Promo ng Innova on, Economic Growth And Global Compe veness? - Is the USPTO making it easier

More information

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri Operating Procedure SOP # Date: Page 1 of 10 Classifications: OCC Rail Dispatchers Maintenance of Way - Contractors Other Departments: Real Estate Operation Safety - Risk Management - Engineering & New

More information

Understanding OSHA s Crystalline Silica Rule

Understanding OSHA s Crystalline Silica Rule (TAKEN FROM ACPA TECHNICAL BULLETIN) Understanding OSHA s Crystalline Silica Rule The ACPA takes worker health and safety very seriously, and in that spirit, has prepared this technical bulletin to provide

More information

The Grain Elevator and Processing Society (GEAPS) Chief Staff Executive

The Grain Elevator and Processing Society (GEAPS) Chief Staff Executive The Grain Elevator and Processing Society (GEAPS) Chief Staff Executive Minneapolis, Minnesota YOUR PARTNER IN GROWTH Position Overview www.searchwideglobal.com 2018 SearchWide Global ABOUT THE GRAIN ELEVATOR

More information

Case Study: Cleveland Innerbelt (George V. Voinovich) Bridge Cleveland, OH

Case Study: Cleveland Innerbelt (George V. Voinovich) Bridge Cleveland, OH Case Study: Cleveland Innerbelt (George V. Voinovich) Bridge Cleveland, OH Lead Agency: Ohio Department of Transporta on INVEST Modules: Project Development Link: www.innerbelt.org INVEST helped the Ohio

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

The History of CDW s begreen Program

The History of CDW s begreen Program Our Commitment to the Environment 2018 1 The History of CDW s begreen Program CDW recognizes the need for responsible environmental management and conserva on of resources and has demonstrated its commitment

More information

Evalua ng a Job Offer

Evalua ng a Job Offer As you move through your career you will probably have opportuni es to take new jobs and possibly relocate to a different part of the country. These opportuni es can have a significant impact on your lifestyle

More information

January. 9th Avenue and Colorado Boulevard. Construc on Look Ahead

January. 9th Avenue and Colorado Boulevard. Construc on Look Ahead January 2019 9th Avenue and Colorado Boulevard Construc on Look Ahead A er months of discussion, the hear elt decision was made to tear down the bridge over 9th Avenue. This decision was discussed at the

More information

GEOTECHNICAL, HYDROTECHNICAL AND ENVIRONMENTAL SERVICES

GEOTECHNICAL, HYDROTECHNICAL AND ENVIRONMENTAL SERVICES Pipeline Services GEOTECHNICAL, HYDROTECHNICAL AND ENVIRONMENTAL SERVICES ABOUT US Klohn Crippen Berger Ltd. (KCB) is a leading engineering, geoscience and environmental consul ng firm with its head office

More information

Paralegal Career Insight

Paralegal Career Insight Paralegal Career Insight Emsi Q2 2017 Data Set Occupa on Summary for Paralegals and Legal Assistants 287,653 +1.1% $23.65/hr Jobs (2016) % Change (2016-2017) Median Hourly Earnings Emsi Q2 2017 Data Set

More information

CapaccioEnviro Line. As I write this ar cle, In This Issue. Regulatory Reminders. Environmental, Health and Safety Consulting and Engineering Services

CapaccioEnviro Line. As I write this ar cle, In This Issue. Regulatory Reminders. Environmental, Health and Safety Consulting and Engineering Services CapaccioEnviroLine Environmental, Health and Safety Consulting and Engineering Services Helping Industry and the Environment Prosper www.capaccio.com www.ems-hsms.com Winter 2015 Volume 23 Number 1 In

More information

REGION VI CHAPTER REGIONAL CONFERENCE

REGION VI CHAPTER REGIONAL CONFERENCE proudly presents 2018 REGION VI CHAPTER REGIONAL CONFERENCE Des Moines Marrio Downtown Hotel Des Moines, Iowa May 3 May 5, 2018 CONFERENCE SCHEDULE CONFERENCE SCHEDULE CONFERENCE SCHEDULE WELCOME PARTY

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

Executive Summary Regional Development Capacity Report

Executive Summary Regional Development Capacity Report Executive Summary Regional Development Capacity Report June 2012 2643 Gateway Drive State College, PA 16801 814-231-3050 www.crcog.net/planning EXECUTIVE SUMMARY The 2012 Regional Development Capacity

More information

MASTER PLAN Town of Otis, Massachusetts

MASTER PLAN Town of Otis, Massachusetts MASTER PLAN Town of Otis, Massachusetts Adopted by the Otis Planning Board on January 11, 2016 Prepared by: The Otis Master Plan Steering Committee & The Berkshire Regional Planning Commission MASTER PLAN

More information

Energy OutWest April 23-27, 2012 Boise Centre Boise, ID

Energy OutWest April 23-27, 2012 Boise Centre Boise, ID I T F Monday April 23rd Full Day G ' S! This hands on session will focus on ge ng duct system, repaired and sealed with a focus working efficiently Bruce Manclark & Vince Pacheco C C C C S F This course

More information

Community Services. Page Appropriation Total

Community Services. Page Appropriation Total Community Services Page Appropriation Total Community Services 57 Planning 70 $1,732,583 Building 71 $1,307,834 Environmental Health 72 $4,092,387 Public Works 73 $21,861,152 Integrated Waste Management

More information

The Hybrid Geoexchange Primer. August 2015

The Hybrid Geoexchange Primer. August 2015 The Hybrid Geoexchange Primer August 2015 The Hybrid Geoexchange Primer How to reduce costs, improve efficiency, and design more robust ground source hea ng and cooling systems GeoEx Analy cs, Sterling,

More information

CREDENTIALS

CREDENTIALS CREDENTIALS WHO WE ARE Sheesh was born from the idea to create a unique and dis nc ve approach in offering our clients the quality and service required to make a no ceable difference. Having experience

More information

Kingdom of Swaziland. Ministry of Health. In-Service Training Guidelines

Kingdom of Swaziland. Ministry of Health. In-Service Training Guidelines Kingdom of Swaziland Ministry of Health In-Service Training Guidelines November 2015 PUBLICATION NOTICE A publica on of the Human Resources Unit, Ministry of Health. Any enquiries regarding this publica

More information

MINIMUM DESIGN AND SITE REQUIREMENTS MEDIUM AND HIGH DENSITY RESIDENTIAL DISTRICTS

MINIMUM DESIGN AND SITE REQUIREMENTS MEDIUM AND HIGH DENSITY RESIDENTIAL DISTRICTS MINIMUM DESIGN AND SITE REQUIREMENTS MEDIUM AND HIGH DENSITY RESIDENTIAL DISTRICTS Purpose: Medium and high density housing is an important element in the overall housing choice in the. These types of

More information

Maitland Mills MAITLAND MILLS BUSINESS CONCEPT

Maitland Mills MAITLAND MILLS BUSINESS CONCEPT Maitland Mills G O R R I E & B R U S S E L S, O N TA R I O MAITLAND MILLS CONTENTS: Purpose of Maitland Mills: 3 The Proposed Maitland Mills Trust: 3 Organiza on: 3 Vision: 3 Strategic Aims: 4 Professional

More information

UN Global Compact. Communica on on progress 2015

UN Global Compact. Communica on on progress 2015 UN Global Compact Communica on on progress 2015 03 04 Commitment from our CEO About us in brief Scope of the report 05 08 People Planet 10 11 Profit About UN Global Compact COMMITMENT FROM OUR CEO Møbeltransport

More information

The History of CDW s begreen Program

The History of CDW s begreen Program Our Commitment to the Environment 2019 1 The History of CDW s begreen Program CDW recognizes the need for responsible environmental management and conserva on of resources and has demonstrated its commitment

More information

How to... Manage overlapping responsibili es on the job

How to... Manage overlapping responsibili es on the job Ho to... Manage overlapping responsibili es on the job August 2016 Shared orkplaces and HSWA A forestry ork site ill usually be a shared ork site ith more than one business orking as part of the opera

More information

Makna Translation AKNA

Makna Translation AKNA Makna Translation Makna Transla on Agency Jl.Lenteng Agung Timur No 13, Jakarta Selatan 021 8347 7723 0818 0619 2293 contact@makna.net www.makna.net Your TRUE Translation Partner Makna at a glance A subsidiary

More information

Governor s Council on Workforce Investment. November 15, 2018

Governor s Council on Workforce Investment. November 15, 2018 Raymond Allen, Executive Director Scott Walker 201 E. Washington Avenue, Rm. A400 Governor P.O. Box 7946 Madison, Wisconsin 53707-7946 Mark Tyler Telephone: (608) 267-1410 Chair Fax: (608) 266-1784 Web

More information

GENETICALLY MODIFIED ORGANISM LEGISLATIVE CONTROL IN GEORGIA

GENETICALLY MODIFIED ORGANISM LEGISLATIVE CONTROL IN GEORGIA POLICY BRIEF 1 Green Alterna ve s Policy Briefs are short analyses on some of the challenges to country s sustainable development. They are part of the broader Green Alterna ve s analy cal works; some

More information

The INNOVATOR. Significant FY19 Results To Date. Inside this issue: Special points of interest: An MC Innovations Publication. Key Program Successes

The INNOVATOR. Significant FY19 Results To Date. Inside this issue: Special points of interest: An MC Innovations Publication. Key Program Successes 1 February, 2019 Vol. 3 Issue 6 The INNOVATOR Significant FY19 Results To Date Workers Compensa on Services and MC Innova ons hit the ground running in the first year of the NEW contract! With half the

More information

The Maine State Capitol Building in Augusta, as well as most other state-managed buildings are subject to state IPM law.

The Maine State Capitol Building in Augusta, as well as most other state-managed buildings are subject to state IPM law. Ending Toxic Dependency: The State of IPM State laws allow broad dependency on toxic pes cides; four states call for pes cide reduc on and alterna ves by Jay Feldman and Laura Hep ng The Maine State Capitol

More information

Appendix G Draft Memorandum of Agreement

Appendix G Draft Memorandum of Agreement Appendix G Draft Memorandum of Agreement DRAFT MEMORANDUM OF AGREEMENT AMONG THE FEDERAL TRANSIT ADMINISTRATION, WASHINGTON STATE HISTORIC PRESERVATION OFFICER, AND THE CENTRAL PUGET SOUND REGIONAL TRANSIT

More information

Embedded versus Marginal Cost of Service Studies

Embedded versus Marginal Cost of Service Studies T R P Melissa Whited (Synapse), with contribu ons from Paul Chernick (Resource Insight) and Jim Lazar (RAP) July 2017 In order to con nue to operate, a u lity must have an opportunity to recover its prudently

More information

Quality Improvement Division Na onal HR. QPSD GL Larraine Gilligan, Quality Improvement Division, Co. Tipperary, Ireland.

Quality Improvement Division Na onal HR. QPSD GL Larraine Gilligan, Quality Improvement Division, Co. Tipperary, Ireland. Guidance Guidance on the Implementa on of the Health and Safety Authority Competent Authority Exemp on 03/2016 on the Carriage of Uncleaned Reusable Invasive Medical Devices by Road Reader Informa on Directorate:

More information

NORTH WHATCOM FIRE AND RESCUE STRATEGIC PLAN FY

NORTH WHATCOM FIRE AND RESCUE STRATEGIC PLAN FY NORTH WHATCOM FIRE AND RESCUE STRATEGIC PLAN FY 2016 2021 I am very pleased to present the North Whatcom Fire and Rescue Strategic Plan for 2016-2021. The Strategic Plan is a key founda onal document that

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

What is expected of TriStarr Associates?

What is expected of TriStarr Associates? Employee Handbook WELCOME! Thank you for choosing TriStarr. We have been serving the diverse communi es of Central Pennsylvania since 1989. We have been able to offer career opportuni es in a variety of

More information

Planning, Public Works and Environmental Services

Planning, Public Works and Environmental Services Planning, Public Works and Budget Unit Name BU No. Page Appropriation Total Planning & Public Works 83 Fleet Services 140-1 88 $1,915,452 County Surveyor 150-1 89 $70,000 Integrated Waste 194-1 90 $10,746,607

More information

Op mised inventory and produc on processes

Op mised inventory and produc on processes Inventory represents one of the largest expenses for many small and midsize businesses. Balancing accurate inventory management with cost-effec ve produc on is crucial for delivering on promise and keeping

More information

Hariyo Ban Program Phase I: Achievements and Learning

Hariyo Ban Program Phase I: Achievements and Learning FACTSHEET Hariyo Ban Program Phase I: Achievements and Learning Introduction This factsheet outlines the achievements and learning of the Hariyo Ban Program during its first five years. The Program is

More information

Analysis of Existing Drug Disposal Plans at Health Care Facilities in Suffolk County, NY

Analysis of Existing Drug Disposal Plans at Health Care Facilities in Suffolk County, NY Analysis of Existing Drug Disposal Plans at Health Care Facilities in Suffolk County, NY Background Informa on Locally and na onally our waters are becoming contaminated with trace amounts of pharmaceu

More information

Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO

Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO. 2017-031 WELCOME PUBLIC MEETING NO. 2 February 21, 2018 CITY OF ANN ARBOR RIVERVIEW DRIVE SANITARY SEWER AND WATER

More information

FINDING OF NO SIGNIFICANT IMPACT

FINDING OF NO SIGNIFICANT IMPACT FINDING OF NO SIGNIFICANT IMPACT Additional Storage Reservoir for the Non-Potable Water Supply System City of Santa Monica, California, United States September 2011 The U.S. Environmental Protection Agency

More information

A Framework to Increase SharePoint Adoption within your Organization

A Framework to Increase SharePoint Adoption within your Organization White Paper A Framework to Increase SharePoint Adoption within your Organization by Abishek Bhat O V E R C O M I N G L I M I T S Microso SharePoint provides a vast number of capabili es that empower business

More information

2018 Utility & Street Reconstruction

2018 Utility & Street Reconstruction 2018 Utility & Street Reconstruction Public Hearing On Proposed Special Assessments/Hookup Fees for Installation and Construction of Public Improvements Introduction of the Village technical staff Laura

More information

Lesser Prairie Chicken and Dunes Sagebrush Lizard Candidate Conserva on Agreement and Candidate Conserva on Agreement with Assurances

Lesser Prairie Chicken and Dunes Sagebrush Lizard Candidate Conserva on Agreement and Candidate Conserva on Agreement with Assurances Lesser Prairie Chicken and Dunes Sagebrush Lizard Candidate Conserva on Agreement and Candidate Conserva on Agreement with Assurances Monthly Report July 2017 Vegeta ve Monitoring July 2017 Dave Thomas

More information

ALAMEDA CORRIDOR EAST San Gabriel Valley

ALAMEDA CORRIDOR EAST San Gabriel Valley ALAMEDA CORRIDOR EAST San Gabriel Valley San Pedro Bay ports: 40% of nation s imports; 30% of exports. ACE Trade Corridor: 21% of waterborne containers entering/exiting the U.S. 81 trains/day (2009) 141

More information

Modular Buildings Are Our Business

Modular Buildings Are Our Business COMPANY PROFILE Modular Buildings Are Our Business NT Link is conveniently based in the Northern Territory. We provide our clients, in all kind of industries a diverse and comprehensive range of essen

More information

CIC Authorized Practical Examiner. Crane Institute. John Smith ISSUED: EXPIRES: ID: EX Crane Institute ID: CO

CIC Authorized Practical Examiner. Crane Institute. John Smith ISSUED: EXPIRES: ID: EX Crane Institute ID: CO TRAINING PROGRAMS FOR: Operators Managers & Supervisors Inspectors Riggers & Signalpersons Trainers CIC Prac cal Examiners ON SITE PROGRAMS: Li Director Assembly/Disassembly Director NATIONALLY ACCREDITED

More information

Capability Statement CORROSION CONTROL ENGINEERING. Our Experience Delivers Solu ons

Capability Statement CORROSION CONTROL ENGINEERING. Our Experience Delivers Solu ons CORROSION CONTROL ENGINEERING Capability Statement SPECIALISTS IN THE DESIGN, SUPPLY, INSTALLATION & MAINTENANCE OF CATHODIC PROTECTION SYSTEMS FOR BURIED OR IMMERSED METALLIC STRUCTURES Experience at

More information

CAPABILITY STATEMENT. s a f e t y q u a l i t y e n v i r o n m e n t

CAPABILITY STATEMENT. s a f e t y q u a l i t y e n v i r o n m e n t CAPABILITY STATEMENT s a f e t y q u a l i t y e n v i r o n m e n t 1 3 0 0 1 2 3 6 4 7 / w w w. s a f e t y z o n e. n e t. a u Consultation Services O v e r v i e w SafetyZone consultancy service delivers

More information

Workbook 2. South Kent Wind Community Liaison Committee. Objectives. Agenda. South Kent Wind Community Liaison Committee February 6, 2013

Workbook 2. South Kent Wind Community Liaison Committee. Objectives. Agenda. South Kent Wind Community Liaison Committee February 6, 2013 Our objec ves for the evening are as follows: Confirm func on of the CLC and our roles Con nue to learn about the Project and the construc on process Con nue an open dialogue rela ng to poten al community

More information

Community Development Department Council Chambers, 7:30 PM, September 7, 2017

Community Development Department Council Chambers, 7:30 PM, September 7, 2017 STAFF REPORT 2017-30P: Special Use Permit Community Development Department Council Chambers, 7:30 PM, September 7, 2017 To: From: Re: Paul Luke, Chairman, Skokie Plan Commission Mike Voitik, Planning Technician

More information

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017 Palo Alto Rail Committee Meeting November 29, 2017 Slide 1 Project Area Millbrae Station City Limits Existing Railroad Crossing at Broadway Caltrain Operational Constraint Major Constraints Millbrae Station

More information

The Current Situa-on of Off- site Clean- up in Japan

The Current Situa-on of Off- site Clean- up in Japan The Current Situa-on of Off- site Clean- up in Japan May 23, 2016 Kazumi Yoshikawa Director Ministry of the Environment, Japan 1.Current Situa-on of Off- site Decontamina-on 2. Interim Storage Facility

More information