MIC Core Pre-Schematic Program Analysis
|
|
- Eric Jordan
- 6 years ago
- Views:
Transcription
1 MIC Core Pre-Schematic Program Analysis April 2001
2 MIAMI INTERMODAL CENTER (MIC) PROGRAM Work Program Item No State Project No Financial Management Item No PRE-SCHEMATIC DESIGN STAGE PRELIMINARY PROGRAM & SPATIAL ANALYSIS Prepared For: FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT VI Prepared By: EARTH TECH INC. AND NGPUSA LIMITED April 30, 2001
3 TABLE OF CONTENTS CHAPTER PAGE PURPOSE AND INTRODUCTION ROADWAY ANALYSIS Option 1: Base Scheme Option Option Option Option Option 6: Preferred Option RAIL ANALYSIS Existing Site Diagram FEIS Rail Diagram Option Option Option PARKING ANALYSIS Option Option Option MDTA / GREYHOUND BUS TERMINAL ANALYSIS Option Option Option 3: Preferred Option BAGGAGE ANALYSIS Option 1 / Option 1: 3-D Schematic SECTIONAL ANALYSIS Option Option Option Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis Page i
4 TABLE OF CONTENTS CHAPTER PAGE 7.0 PRE-SCHEMATIC PROPOSAL Levels 1A, 1B, 1C: Parking, Bus Terminal & Rail Node Level 2: Arrivals & Departures by Car, Taxi and Shuttle-Bus Level 2: Arrivals & Departures by Cruise Line Buses Level 2/3: Departures by Rail & Bus Passengers / Pedestrian Access Level 3: Departures Passengers Level 3: Arrivals Passengers (Non-Cruise) Level 3: Arrivals Passengers (Cruise) Level 4: Retail and Commercial Upper Levels: Hotel / Commercial (MIC Roof Not Shown) PHASING OPTIONS MIC Phasing: MIC Phasing: MIC Phasing: MIC Phasing: Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis Page ii
5 APPENDIX TITLE A PRE-SCHEMATIC PROPOSAL DRAWINGS B PROGRAM REFERENCE DOCUMENTS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis Page iii
6 PURPOSE AND INTRODUCTION This report summarises preliminary program and spatial analysis studies undertaken as part of a broader pre-schematic / schematic stage effort for the Miami Intermodal Center Project (MIC). The accompanying work has been prepared by Nicholas Grimshaw & Partners USA Ltd, under the direction of the MIC Management Group (MMG) Facilities Team. Significant contributions to enable the evaluation of ideas in the areas of carparking and roadway design have been made by the MMG Roadways Team, and by sub-consultant firms Graelic Inc. and BHA Engineers. The overall MIC project study area is bounded by NW 46 th Street to the north, NW 11 th Street to the south, NW 27 th Avenue to the east and the landside terminal area of MIA with a section of SR 836 westward to NW 57 th Avenue to the west. The MIC is envisaged to provide a transportation hub that facilitates regional travel in Dade County. Its primary objective is to provide a safe, efficient and economical means of interchange between separate modes of transport in an attractive and truly integrated setting. The MIC Core program specifically comprises of the following key elements: Rail Node, including heavy rail transportation modes both at grade and elevated. Public Concourses connecting all transport modes to the MIC / MIA Connector. Bus Facilities: MDTA, Greyhound & Cruise Line. Airport Landside Program. Miami Intermodal Center and Miami International Airport APM Station (MIC-MIA Connector). Arrivals and departures roadways for the airport landside program. Parking. The analysis to-date has concentrated upon the planning and operational characteristics of each of the major program elements. Each component has been considered in terms of functionality and then spatially in combination with other elements. The format of this report has been structured in such a way as to reflect this process. Through this process a number of planning scenarios for the MIC Core project have emerged and are recorded here for more detailed future evaluation. Importantly, these scenarios have progressed within the context of the overall MIC project and have therefore been developed in tandem with the design of the adjacent Rental Car Facility and MTAR roadway scheme. Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
7 ROADWAY ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
8 NW 25th Street RCF MIC-MIA Connector Concourses Departures Arrivals NW 37th Avenue MTAR Level 2 MTAR Level 1 NW 21st Street OPTION 1: BASE SCHEME Pros: Cons: Conventional roadway configuration Clear, flexible arrangement of Departures and Arrivals facilities Arrivals concourse remote from MIC-MIA connector Roadway:curbside ratio not optimized Joint development has no presence at grade 3
9 NW 25th Street MTAR Level 2 Departures RCF MIC-MIA Connector Concourses NW 37th Avenue Arrivals MTAR Level 2 NW 21st Street OPTION 2 Pros: Cons: Single-level (elevated) Arrivals / Departures roadway Optimized roadway:curbside ratio Arrivals concourse remote from MIC-MIA connector Arrivals and Departures concourse geometry not optimal Joint development has no presence at grade 4
10 NW 25th Street MTAR Level 2 Joint Development Departures RCF MIC-MIA Connector Concourses NW 37th Avenue Arrivals NW 21st Street MTAR Level 2 Joint Development OPTION 3 Pros: Cons: Single-level (elevated) Arrivals / Departures roadway Ease of traffic flow Optimized roadway:curbside ratio North East and North West corners released for private joint development Arrivals concourse remote from MIC-MIA Connector Arrivals / Departures concourse space limited 5
11 NW 25th Street MTAR Level 2 Joint Development RCF MIC-MIA Connector Arrivals Departures NW 37th Avenue MTAR Level 2 Joint Development NW 21st Street OPTION 4 Pros: Cons: Single-level (elevated) Arrivals / Departures roadway Optimized roadway:curbside ratio North East and North West corners released for associated joint development Arrivals concourse close to MIC-MIA connector Arrivals and Departures traffic not segregated; recirculation required 6
12 NW 25th Street MTAR Level 2 RCF MIC-MIA Connector Arrivals Departures NW 37th Avenue MTAR Level 2 NW 21st Street OPTION 5 Pros: Cons: Single-level (elevated) Arrivals / Departures roadways Arrivals concourse close to MIC-MIA connector Optimized roadway:curbside ratio Joint development has no presence at grade Arrivals and Departures concourses separated by roadway 7
13 NW 25th Street MTAR Level 2 Joint Development RCF MIC-MIA Connector Arrivals Departures NW 37th Avenue MTAR Level 2 Joint Development NW 21st Street OPTION 6 (preferred option) Pros: Cons: Single-level (elevated) roadway design Arrivals concourse close to MIC-MIA connector Optimized roadway:curbside ratio Efficient Arrivals and Departures road system Ease of traffic flow North East and North West corners released for joint development Arrivals and Departures concourses separated by roadway 8
14 RAIL ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
15 TRI-RAIL NW 25TH STREET MIC SITE NW 37TH AVENUE NW 21ST STREET EXISTING SITE DIAGRAM 10
16 TRI-RAIL METRORAIL AMTRAK NW 25TH STREET MIC-MIA CONNECTOR MIC CORE NW 37TH AVENUE EAST-WEST RAIL NW 21ST STREET HIGH SPEED RAIL FEIS (FINAL ENVIRONMENTAL IMPACT STATEMENT) RAIL DIAGRAM 11
17 TRI-RAIL METRORAIL AMTRAK FUTURE HIGH SPEED RAIL FUTURE EAST-WEST RAIL NW 25TH STREET MIC-MIA CONNECTOR NW 21ST STREET MIC CORE NW 37TH AVENUE OPTION 1: ALL-MODE TERMINUS SOUTH OF 25TH STREET Pros: Fully integrated single intermodal facility Short transfer time between MIC-MIA connector and rail modes Ease of transfer between regional and local rail modes Cons: Involves re-routing NW 25th Street through tunnel below tracks High cost and program uncertainties Cannot be phased independently from MIC Diesel extract system limits rail concourse design Difficult to accommodate future expansion Elevated Metrorail penetration compromises elevated roadway designs East West Rail required to be elevated above MetroRail 12
18 TRI-RAIL AMTRAK FUTURE HIGH SPEED RAIL FUTURE EAST-WEST RAIL MIC-MIA CONNECTOR PASSENGER CONVEYOR METRORAIL NW 21ST STREET MIC CORE NW 25TH STREET NW 37TH AVENUE OPTION 2: SINGLE MODE SOUTH OF 25TH STREET / MIC RAIL NODE Pros: Accommodates rail program uncertainties and future expansion Can be phased independently from MIC (apart from Metrorail) No interruption of NW 25th Street Short transfer time between MIC-MIA Connector and Metrorail Cons: Some duplication of rail facilities required Sole Metrorail penetration reduces flexibility and efficiency of MIC concourses Favors Metrorail over other rail modes Compromised concept of single rail node Elevated Metrorail penetration compromises elevated roadway designs Passenger conveyors required for link to MIC-MIA Connector East West Rail required to be elevated above Metrorail 13
19 TRI-RAIL METRORAIL AMTRAK FUTURE HIGH SPEED RAIL FUTURE EAST-WEST RAIL MIC-MIA CONNECTOR PASSENGER CONVEYOR MIC CORE NW 21ST STREET NW 25TH STREET NW 37TH AVENUE OPTION 3: MIC RAIL NODE Pros: Clear, defined rail node concept Accommodates rail program uncertainties and future expansion Can be phased independently from MIC No interruption of NW 25th Street Ease of transfer between regional and local rail modes Common rail concourses and facilities East West Rail can be at same elevation as Metrorail Cons: Passenger conveyors required for link to MIC-MIA Connector 14
20 PARKING ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
21 RENTAL CAR FACILITY OPTION 1 - MULTIPLE ZONE / MULTIPLE ACCESS & EGRESS Pros: Cons: Very flexible/ divisible parking garages Automobile routing occurs outside envelope of building, enhancing efficiency Clear concept Parking traffic segregated from other traffic Likely to require dedicated access road carrying no through-traffic from MTAR 16
22 RENTAL CAR FACILITY OPTION 2 - SINGLE ACCESS & EGRESS Pros: Cons: Straightforward traffic entrance/ exit sequence Likely to create lowest impact on MTAR traffic flow Less flexible/ divisible parking garages Automobile routing within parking garages more complicated 17
23 RENTAL CAR FACILITY OPTION 3 - TWIN ZONE / TWIN ACCESS & EGRESS Pros: Cons: Flexible /divisible parking garages Can segregate parking types at early stage in MTAR approach Separate entrances could compromise user legibility Likely to create moderate impact on MTAR traffic flow 18
24 MDTA / GREYHOUND BUS ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
25 MIC PARKING NW 21ST STREET MIC PARKING COMBINED BUS DEPOT MIC PARKING NW 25TH STREET PEDESTRIAN ENTRANCE PLAZA GREYHOUND PASSENGER LOBBY NW 37TH AVENUE MDTA PASSENGER LOBBY OPTION 1 Pros: Cons: Centralized bus depot with primary access to upper MIC concourses No significant segregation of Greyhound and MDTA bus facilities /passengers MDTA buses remote from Rail Node 20
26 NW 21ST STREET MIC PARKING MIC PARKING PEDESTRIAN ENTRANCE PLAZA MIC PARKING COMBINED BUS DEPOT COMBINED PASSENGER LOBBY NW 25TH STREET NW 37TH AVENUE OPTION 2 Pros: Cons: MDTA buses close to Rail Node - good local intermodal connections No segregation of Greyhound and MDTA bus facilities /passengers Bus passengers remote from central MIC concourses Impacts on North East MIC parking entrance 21
27 MIC PARKING NW 21ST STREET NW 25TH STREET GREYHOUND BUS DEPOT AND PASSENGER LOBBY PEDESTRIAN ENTRANCE PLAZA NW 37TH AVENUE MDTA BUS DEPOT AND PASSENGER LOBBY OPTION 3 (preferred option) Pros: MDTA buses close to Rail Node - good local intermodal connections Good passenger access to upper MIC concourses Individual Greyhound and MDTA bus facilities Good presence and visibility from surface streets 22
28 BAGGAGE ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
29 BAGGAGE TUNNEL BAGGAGE MAKE-UP FACILITY MIA BAG CLAIM MIA CHECK-IN OPTION 1 BAGGAGE TUNNEL BAGGAGE MAKE-UP FACILITY MIA BAG CLAIM MIA CHECK-IN CRUISE BUS BAG HANDLING OPTION 2 24
30 MIA BAG CLAIM (EXPANSION DASHED) BAGGAGE TUNNEL MIA BAG CLAIM (EXPANSION DASHED) BAGGAGE MAKE-UP FACILITY MIA CHECK-IN (EXPANSION DASHED) MIA CHECK-IN (EXPANSION DASHED) 3D SCHEMATIC DIAGRAM The options are based on the assumption that cruise passenger baggage may be utilising the baggage tunnel for transport between the MIC and MIA. Option 1 scheme would be appropriate if cruise buses depart the MIC at or close to the Arrivals facility, which can be configured for cruise baggage segregation if required. Option 2 scheme is appropriate if cruise buses depart the MIC at a location remote from the Arrivals facility, in which case a dedicated baggage facility may be necessary. 25
31 SECTIONAL ANALYSIS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
32 RENTAL CAR FACILITY JOINT DEVELOPMENT ROOF MIC-MIA BAG CLAIM RAIL NODE CONCOURSE ARRIVALS BAG CHECK DEPARTURES 3 PARKING LEVELS COMBINED CRUISE / GREYHOUND / MDTA BUS DEPOT OPTION 1: PARKING AND INTEGRATED BUS FACILITY PLATFORM Pros: Cons: Single bus facility Accommodates program uncertainties No segregation of Cruise facilities from MDTA/ Greyhound facilities Less attractive location for Cruise facilities Cruise buses remote from MIC-MIA connector, arrivals and departures 27
33 RENTAL CAR FACILITY JOINT DEVELOPMENT CRUISE BUSES ROOF MIC-MIA BAG CLAIM RAIL NODE CONCOURSE ARRIVALS BAG CHECK DEPARTURES 3 PARKING LEVELS GREYHOUND / MDTA BUS DEPOT OPTION 2: PARKING PLATFORM WITH SPLIT BUS FACILITIES (CRUISE BUSES ON TOP LEVEL) Pros: Cons: Cruise facility completely segregated from other MIC facilities and modes Open-air parking for all cruise buses Requires helical ramps for bus access, which impact efficiency of other MIC functions Increased cost (probable) Inflexible 28
34 RENTAL CAR FACILITY JOINT DEVELOPMENT ROOF MIC-MIA BAG CLAIM CONCOURSE ARRIVALS CRUISE BUSES BAG CHECK DEPARTURES 3 PARKING LEVELS GREYHOUND / MDTA BUS DEPOT OPTION 3: PARKING PLATFORM WITH SPLIT BUS FACILITIES (CRUISE BUSES ON LEVEL 2) (preferred) Pros: Cons: Cruise facilities adjacent to arrivals and departures facilities Segregation of Cruise facilities from MDTA/ Greyhound facilities Attractive location for Cruise facilities Effectively exploits flexibility of arrivals and departures curbsides Increased traffic at Level 2 29
35 PRE-SCHEMATIC PROPOSAL Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
36 RENTAL CAR FACILITY NW 25TH ST RAIL NODE: (TRI-RAIL, AMTRAK). METRORAIL ABOVE SERVICE ZONE MULTI-LEVEL PARKING SERVICE ZONE MDTA BUS DEPOT SERVICE ZONE PEDESTRIAN ACCESS PLAZA NW 37TH AVE NW 21ST ST GREYHOUND BUS DEPOT POTENTIAL FUTURE COMMERCIAL DEVELOPMENT LEVELS 1A, 1B, 1C: PARKING, BUS STATIONS AND RAIL NODE 31
37 RENTAL CAR FACILITY ARRIVALS ARRIVALS CURB RETAIL TICKETING /BAGGAGE JOINT DEVELOP- MENT RETAIL TICKETING / BAGGAGE DEPARTURES DEPARTURES CURB JOINT DEVELOPMENT POTENTIAL FUTURE ASSOCIATED DEVELOPMENT LEVEL 2: ARRIVALS AND DEPARTURES BY CAR, TAXI AND SHUTTLEBUS 32
38 RENTAL CAR FACILITY ARRIVALS AND DEPARTURES CURB DEPARTURES RETAIL JOINT DEVELOP- MENT ARRIVALS RETAIL JOINT DEVELOPMENT POTENTIAL FUTURE ASSOCIATED DEVELOPMENT LEVEL 2: ARRIVALS AND DEPARTURES BY CRUISE BUS 33
39 RENTAL CAR FACILITY RAIL NODE MIC-MIA CONNECTOR FROM BUS DEPOTS FROM ADJACENT PROPERTIES (AT ELEVATED LEVEL) LEVEL 2/3: DEPARTURES BY RAIL AND BUS PASSENGERS/ PEDESTRIAN ACCESS 34
40 RENTAL CAR FACILITY RAIL NODE MIC-MIA CONNECTOR RETAIL JOINT DEVELOP- MENT RETAIL JOINT DEVELOPMENT LEVEL 3: DEPARTURES PASSENGERS 35
41 RENTAL CAR FACILITY RAIL NODE MIC-MIA CONNECTOR BAG CLAIM BAG CLAIM RETAIL JOINT DEVELOP- MENT RETAIL JOINT DEVELOPMENT LEVEL 3: ARRIVALS PASSENGERS (NON-CRUISE) 36
42 RENTAL CAR FACILITY MIC-MIA CONNECTOR RETAIL JOINT DEVELOP- MENT RETAIL JOINT DEVELOPMENT LEVEL 3: ARRIVALS PASSENGERS (CRUISE) 37
43 JOINT DEVELOPMENT (HOTEL / LEISURE) RAIL NODE JOINT DEVELOP- MENT JOINT DEVELOPMENT JOINT DEVELOPMENT (RETAIL) LEVEL 4: RETAIL AND OTHER COMMERCIAL 38
44 JOINT DEVELOPMENT (HOTEL / LEISURE) RAIL NODE JOINT DEVELOP- MENT JOINT DEVELOPMENT JOINT DEVELOPMENT (RETAIL) UPPER LEVELS: HOTEL /COMMERCIAL (MIC ROOF SHELLS NOT SHOWN) 39
45 MIC PHASING OPTIONS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
46 NW 25TH ST RENTAL CAR FACILITY MDTA BUS DEPOT EXISTING HERTZ GARAGE RETAINED FOR PARKING EXISTING TRI-RAIL STATION NW 21ST ST NW 37TH AVE GREYHOUND BUS DEPOT MIC PHASING:
47 NW 25TH ST JOINT DEVELOPMENT (HOTEL) RENTAL CAR FACILITY RAIL NODE MIC-MIA CONNECTOR 4-LEVEL PARKING GARAGE NW 21ST ST NW 37TH AVE JOINT DEVELOPMENT (OVER BUS FACILITIES) MIC PHASING:
48 NW 25TH ST JOINT DEVELOPMENT (HOTEL) RENTAL CAR FACILITY RAIL NODE JOINT DEVELOPMENT RETAIL CONCOURSES (PLUS STAGED MIA FACILITIES) MIC-MIA CONNECTOR 4-LEVEL PARKING GARAGE NW 21ST ST ARRIVALS CURB DEPARTURES CURB NW 37TH AVE JOINT DEVELOPMENT (OVER BUS FACILITIES) MIC PHASING:
49 NW 25TH ST RENTAL CAR FACILITY RAIL NODE JOINT DEVELOPMENT (HOTEL) MIC-MIA CONNECTOR FULL MIA PROGRAM / RETAIL CONCOURSES NW 21ST ST DEPARTURES CURB NW 37TH AVE JOINT DEVELOPMENT (OVER BUS FACILITIES) MIC PHASING:
50 APPENDIX Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
51 A - PRE-SCHEMATIC PROPOSAL DRAWINGS A 1 MIC CORE LEVEL 01-A PLAN A 2 MIC CORE LEVEL 01-B PLAN A 3 MIC CORE LEVEL 01-C PLAN A 4 MIC CORE LEVEL 02 PLAN A 5 MIC CORE LEVEL 03 PLAN A 6 MIC CORE LEVEL 04 PLAN A 7 MIC CORE SECTIONS Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
52 NW 25TH STREET PARKING A MDTA BUS DEPOT TRI-RAIL AMTRAK 1 AMTRAK 2 TICKETING RAIL NODE CONCOURSE MECHANICAL MECHANICAL PARKING B NW 37TH AVENUE MECHANICAL MECHANICAL PARKING C GREYHOUND BUS DEPOT NW 21ST STREET LEVEL 1A: PARKING / LOADING / MECHANICAL PLANT / BUS STATIONS
53 RAIL FACILITIES PARKING A OPEN TO BELOW OPEN TO BELOW OPEN TO BELOW PARKING B OPEN TO BELOW OPEN TO BELOW PARKING C OPEN TO BELOW LEVEL 1B: PARKING / MECHANICAL PLANT
54 RAIL FACILITIES PARKING A JOINT DEVELOP- MENT PARKING B PEDESTRIAN ACCESS PLAZA PARKING C JOINT DEVELOP- MENT LEVEL 1C: PARKING / COMMERCIAL
55 JOINT DEVELOP- MENT METRORAIL RAIL FACILITIES EAST WEST RAIL MIA TICKETING CRUISE TICKETING AND BAG CHECK ARRIVALS / BAG CLAIM AND DEPARTURES ARRIVALS CURBSIDE ARRIVALS CRUISE BUSES CRUISE TICKETING MIA TICKETING AND BAG CHECK DEPARTURES CURBSIDE JOINT DEVELOP- MENT LEVEL 2: DEPARTURES / ARRIVALS / RETAIL / COMMERCIAL
56 RAIL NODE CONCOURSE RAIL FACILITIES BAG CLAIM PASSENGER CONVEYOR RETAIL TICKETING RETAIL JOINT DEVELOP- MENT MIC-MIA CONCOURSE BAG CLAIM RETAIL RETAIL JOINT DEVELOP- MENT LEVEL 3: ARRIVALS (BAG CLAIM) / RAIL NODE / MIC-MIA STATION / RETAIL
57 JOINT DEVELOP- MENT HOTEL LOBBY /OTHER DINING/ RETAIL HOTEL LOBBY /OTHER DINING/ RETAIL JOINT DEVELOP- MENT LEVEL 4: COMMERCIAL / JOINT DEVELOPMENT
58 SECTION AA (NORTH - SOUTH) SECTION BB (NORTH - SOUTH THROUGH RAIL NODE) SECTION MM (EAST - WEST) MIC SECTIONS
59 B PROGRAM REFERENCE DOCUMENTS MIC Project Schematic Design Program rev: 04 date: MIC Draft Engineering Report Chapter 5 Design Controls and Standards pages: 5.1 to 5.20 date: MIC Final Environmental Impact Statement date: FPL Parcel Sketch date: Pre-Schematic Design Stage April Preliminary Program & Spatial Analysis
60 U.S. Department of Transportation Federal Highway Administration Florida Department of Transportation In Cooperation With: U.S. DOT Office of the Secretary Office of Intermodalism Federal Transit Administration Federal Railroad Administration Federal Aviation Administration Maritime Administration United States Coast Guard Toll Free: Local: Fax: NW 87 th Avenue, Suite 300 Miami, FL 33178
The Miami Intermodal Center Chairman John Mica Visit - October 23, 2012
The Miami Intermodal Center Chairman John Mica Visit - October 23, 2012 MIC History Concept conceived in 1980s Dade County Aviation Department developed Airport Survival Plan & other strategies to relieve
More informationAirport Development Plan Update
Airport Development Plan Update Prepared by: SAN DIEGO COUNTY REGIONAL AIRPORT AUTHORITY SDIA Planning Timeline 2 Where Is SDIA Today? The Airport is implementing the recommendations from the 2008 master
More informationMiami-Dade Transit. Alice N. Bravo, P.E. Director. Miami-Dade Transit 1
Miami-Dade Transit Alice N. Bravo, P.E. Director Miami-Dade Transit 1 Miami-Dade Transit MDT is the largest transit agency in the State of Florida, and one of the largest departments within Miami-Dade
More informationNorthern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?
WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities
More information6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES
6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES The projected activity levels at Sacramento International Airport as described in Chapter 3 are the basis for determining the terminal facilities that will be
More informationHigh-Speed Rail - Chicago to St. Louis Alton Regional Multimodal Transportation Center Project
High-Speed Rail - Chicago to St. Louis Alton Regional Multimodal May 2012 Draft Report: Alternatives Screening Version 1.0 1.0 Introduction This document outlines the alternatives screening process used
More informationAIRPORT SERVICES. the airport sector. Our people are experts at understanding and
airport services AIRPORT SERVICES Our SP+ Airport Services operating division focuses exclusively on the airport sector. Our people are experts at understanding and addressing the unique demands of an
More informationMDX Contract #: RFP MDX Work Program #: ETDM #: 11501
SR 874/Don Shula Expressway Ramp Connector Project Development & Environment (PD&E) Study PUBLIC HEARING December 8, 2011 MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 1 This Public
More informationCity of Kansas City AIRPORT COMMITTEE BRIEFING. New Terminal Evaluation for Kansas City International Airport. March 15, 2016
City of Kansas City AIRPORT COMMITTEE BRIEFING New Terminal Evaluation for Kansas City International Airport March 15, 2016 1 Agenda Process Overview Establishing Requirements & Identifying Issues Forecast
More informationInland Port Cargo Complex
Inland Port Cargo Complex Regional Approach for Ports A statewide improvement Connects five plus seaports Promotes connectivity utilizing existing transportation network Improves rail efficiencies Relocates
More informationI-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012
I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings Tier II June 11 th & 13 th, 2012 Agenda Introduction & Background Study Area Purpose & Need Project Status Tier Methodology & Tier I Evaluation
More informationTransit Service Guidelines
G R E AT E R VA N CO U V E R T R A N S P O RTAT I O N A U T H O R I T Y Transit Service Guidelines PUBLIC SUMMARY REPORT JUNE 2004 Greater Vancouver Transportation Authority TRANSIT SERVICE GUIDELINES
More informationAirport Ground Access Planning Reading the Crystal Ball
ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Airport Ground Access Planning Reading the Crystal Ball Gavin Duncan Associate Director LeighFisher gavin.duncan@leighfisher.com Why Should We Care? Ground access
More informationDraft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2
Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Prepared for: City of Phoenix Aviation Department and U.S. Department of Transportation Federal Aviation Administration
More informationEconomic Impacts of Greyhound Bus Passengers Visiting New York City
Economic Impacts of Greyhound Bus Passengers Visiting New York City SUBMITTED TO Greyhound Lines, Inc. SUBMITTED BY Nathan Associates Inc. Arlington, Virginia August 2, 2004 www.nathaninc.com Economic
More informationNovember 8, RE: Harrah s Station Square Casino Transportation Analysis Detailed Traffic Impact Study Review. Dear Mr. Rowe:
November 8, 2006 Mr. Glenn Rowe, P.E. Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering Commonwealth Keystone Building 400 North Street, 6 th Floor Harrisburg,
More informationAviation Lighting Fall Conference Tucson, Arizona October 22, 2013
Aviation Lighting Fall Conference Tucson, Arizona October 22, 2013 Richard Larivée, ing. P.Eng. Chair RP-37 IESNA RP-37 - Update Recommended Practice for Outdoor Lighting for the Airport Environment IESALC
More informationProspects and Challenges of the Proposed Intermodal Train Station at T.F. Green Airport in Rhode Island
Prospects and Challenges of the Proposed Intermodal Train Station at T.F. Green Airport in Rhode Island Farhad Atash Professor Community Planning Program University of Rhode Island 308 Lippitt Hall Kingston,
More informationCOMPREHENSIVE TRANSPORTATION REVIEW THE WHARF PHASE 2 PUD
COMPREHENSIVE TRANSPORTATION REVIEW THE WHARF PHASE 2 PUD WASHINGTON, DC September 18, 2017 Prepared by: 1140 Connecticut Avenue NW Suite 600 Washington, DC 20036 Tel: 202.296.8625 Fax: 202.785.1276 3914
More informationDallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009
Dallas/Fort Worth International Airport ASCE Presentation Terminal Development Program November, 2009 ASCE PRESENTATION, NOVEMBER 2009 Background Objective The objective of today s presentation 1. Review
More informationDavid King, Railway Procurement Agency 14 th November 2012
Bus Rapid Transit for Dublin Hugh Creegan, National Transport Authority David King, Railway Procurement Agency 14 th November 2012 Topics Core Dublin BRT Network System Concept BRT in the Transport System
More informationSouth Sounder Capital Improvements Program
South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Version Draft ST3 Plan Date Last Modified March 28, 2016
More informationSection 1 OBC FADS /13 Access to Parking Areas
Section 1 OBC 3.8.2.2 4.3.12/13 Access to Parking Areas A barrier-free path of travel is provided from: a) the entrance to the exterior parking area b) at least one parking level where a passenger elevator
More informationLong Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need
Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure
More informationKNOXVILLE REGIONAL TRANSIT CORRIDOR STUDY
KNOXVILLE REGIONAL TRANSIT CORRIDOR STUDY April 2013 Alignments Alignments Magnolia Ave Northeast corridor Knoxville Transit Center Hall of Fame Dr Magnolia Ave Prosser Rd. Corridor contains commercial,
More informationTRANSPORTATION FACTS. OUR CUSTOMERS: Travel Patterns
OUR CUSTOMERS: Travel Patterns TRANSPORTATION FACTS The more than 6.5 million people in the Commonwealth have many reasons to travel and several ways to get to their destinations. A recent statewide survey
More informationAppendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance
APPENDICES Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance D.1 Functional classification identifies the role a highway or street plays in the transportation
More informationNotice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report
Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,
More informationSOUTHEAST FLORIDA REGIONAL COMPACT CLIMATE CHANGE. Sustainable Communities & Transportation Planning
SOUTHEAST FLORIDA REGIONAL COMPACT CLIMATE CHANGE Draft Regional Climate Action Plan Sustainable Communities & Transportation Planning SP-1 Develop criteria in collaboration with municipal and county planning
More informationProject Evaluation Criteria
Project Evaluation Criteria Goals and Objectives were developed to guide Envision 35 Long Range Transportation Plan (LRTP) Update. These guiding principles were based on the requirements included in the
More informationEnvironmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017
Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives December 14, 2017 Today s Agenda Project Overview Project Schedule Purpose and Need Concept Screening Process Level
More informationSanta Clara Valley Transportation Authority Board of Directors. General Manager, Nuria I. Fernandez
8.1.C Date: Current Meeting: Board Meeting: December 6, 2017 December 7, 2017 December 7, 2017 BOARD MEMORANDUM TO: Santa Clara Valley Transportation Authority Board of Directors THROUGH: General Manager,
More informationCurbfront Case Studies
1 A Sharper Saw? Using Advanced Planning Tools and Data to Improve Your Planning Efforts Finding the Right Saw, Curbfront Case Studies Jill Capelli, P.E. Associate Kimley-Horn and Associates, Inc. jill.capelli@kimley-horn.com
More informationBijwasan: A World Class Station
Bijwasan: A World Class Station Presentation to Governing Body, UTTIPEC 19 th December, 2014 INDEX 1. AIMS & OBJECTIVE OF THE PROJECT 2. EXISTING CONDITIONS 3. MASTER PLAN - GENERAL LAYOUT 4. TRAFFIC STUDY
More informationMiami River Freight Improvement Plan Financial Management Number:
Miami River Commission January 8, 2018 Miami, FL Carlos A. Castro, District Freight Coordinator Miami River Freight Improvement Plan Financial Management Number: 437946-1-22-01 Agenda Study Background
More informationSPACE COAST TRANSPORTATION PLANNING ORGANIZATION
SPACE COAST TRANSPORTATION PLANNING ORGANIZATION DRAFT AUGUST 2015 This page intentionally left blank SPACE COAST TRANSPORTATION PLANNING ORGANIZATION DRAFT AUGUST 2015 prepared by: This page intentionally
More informationDEVELOPMENT OF A MASTER PLAN FOR
DEVELOPMENT OF A MASTER PLAN FOR AIRPORTS WITH VISSIM SUPPORT VISSIM USER S GROUP MEETING May 1 st 2009 Portland, Or Luis E. Maumejean Multiservicios Integrales de America S.A. de C.V. lmn@mia.com.mx OUR
More informationSalem MBTA Commuter Rail Station Intermodal Center Project September 1, Meeting Notes
Salem MBTA Commuter Rail Station Intermodal Center Project September 1, 2009 10.2 Meeting Notes M E E T I N G N O T E S PROJECT: Station and Parking Improvements for Salem Commuter Rail Station AECOM PROJ.
More informationHS1 Link The View from London
HS1 Link The View from London For HS2 Growth and Connectivity Conference 12 September 2014 Contents 1. TfL Position on HS2 & Hybrid Bill Petition 2. HS1 Link Issues & Possible Options 2 HS2 Progress To
More informationCaltrain Rapid Rail Plan
TRANSPORTATION RESEARCH RECORD 1677 Paper No. 99-1328 31 Caltrain Rapid Rail Plan ANDREW BUTLER NASH The results of Caltrain s Rapid Rail Study are described. The purpose of the study was to develop a
More informationNATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD
NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD September 18, 2013 District Department of Transportation Federal Railroad Administration AGENDA Vision History & Background Study Area Purpose & Need
More informationVertical Transportation Planning Retail/Mixed-Use
Fortune Consultants LTD Elevator Consulting Vertical Transportation Planning Retail/Mixed-Use This paper is to provide design guidance for the initial planning of vertical transportation in either a standalone
More informationValparaiso Transit Center
Valparaiso Transit Center Project History Site Location Valparaiso Transit Center Design Objectives Primary Task: Development of a Transit Hub on ANCO Property Supplemental Tasks: Long-Term Vision for
More informationDraft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements
JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN
More informationThe Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.
4 Goals & Objectives INTRODUCTION The 2015-2040 MTP preserves and promotes the quality of life and economic prosperity of the MAB by providing a transportation system consistent with the regional goals.
More informationINTEGRATED PUBLIC TRANSPORT INFORMATION SYSTEM FOR BAA SOUTHAMPTON AIRPORT
INTEGRATED PUBLIC TRANSPORT INFORMATION SYSTEM FOR BAA SOUTHAMPTON AIRPORT ITS FOR TRAVELLERS AND USERS CONNECTED TRAVELLER SERVICES Mr James L Mead* Mott MacDonald, Stoneham Place, Stoneham Lane, Eastleigh,
More informationFUTURE BUS RAPID TRANSIT PLANS
ATTACHMENT 1 Preferred Configuration Saskatoon Bus Rapid Transit - Preferred Configuration FUTURE BUS RAPID TRANSIT PLANS Plan For Growth Transportation Plan BRT Plan October 2017 saskatoon.ca/engage 1
More informationFreight Movement Element
Freight Movement Element Planning for mobility includes more than just moving people it means moving freight and services as well. The Salem Transportation System Plan places a greater emphasis on planning
More informationSUPPLEMENTARY ACCESSIBILITY REQUIREMENTS
SUPPLEMENTARY ACCESSIBILITY REQUIREMENTS (Not adopted by the State of Oregon) The provisions contained in this appendix are not mandatory unless specifically referenced in the adopting ordinance. SECTION
More informationMacau International Airport Environmental Optimization Design Competition Rules and Regulations
Macau International Airport Environmental Optimization Design Competition Rules and Regulations 1. Competition Objective Macau is a World Center of Tourism and Leisure. As a portal to Macau, Macau International
More informationSubarea Mobility Enhancements. 5.1 Transit and Pedestrian Improvements
Section Five Section 5: Subarea Mobility Enhancements 5.1 Transit and Pedestrian Improvements From the outset of the master planning process, one of the primary goals was to integrate transit and pedestrian-oriented
More informationTRANSPORTATION IMPACT STUDIES
January 28, 2009 POLICIES AND PROCEDURES FOR TRANSPORTATION IMPACT STUDIES Related to Highway Occupancy Permits Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering
More informationHelsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel February 2018
Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel February 2018 Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel 1 FREIGHT TERMINAL AND DEPOTS Helsinki Helsinki-Vantaa
More informationTECHNICAL MEMORANDUM
TECHNICAL MEMORANDUM High-Speed Train Passenger Station Site Design Guidelines TM 2.2.3 Prepared by: Signed document on file 06 Apr 09_ Cecily Way Date Checked by: Signed document on file 08 Apr 09_ John
More informationCanaveral Port Authority: Rail Extension Update
Rail Extension Update Canaveral Port Authority: Rail Extension Update Thursday, April 30, 2015 5:30 to 6:30 p.m. Port Canaveral Maritime Center John Walsh CEO, Canaveral Port Authority Jim Dubea Speakers
More informationIdentification and Evaluation of Alternatives Tier 1
Vanasse Hangen Brustlin, Inc. DRAFT 4 Identification and Evaluation of Alternatives Tier This chapter describes the initial set of alternatives that were identified to address the Purpose and Need of the
More informationWoodburn Interchange Project Transportation Technical Report
Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...
More informationTRANSPORTATION IMPACT ANALYSIS GUIDELINES FOR ENVIRONMENTAL REVIEW
TRANSPORTATION IMPACT ANALYSIS GUIDELINES FOR ENVIRONMENTAL REVIEW October 2002 The Planning Department City and County of San Francisco TABLE OF CONTENTS I. Introduction 1 II. Overview of Process and
More informationPentagon City PDSP Amendment. Site Plan #105 PenPlace
Pentagon City PDSP Amendment Site Plan #105 PenPlace County Board September 21, 2013 2 3 4 5 6 7 8 9 10 11 12 13 Actions 1. TDR Certification of Teardrop Parcel as a sending site 2. TDR Certification of
More informationJim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project
Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail
More informationS-09: Auburn Station Access Improvements
Project Number S-09 Subarea South King Primary Mode Commuter Rail Facility Type Infrastructure Improvements Length Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE
More informationTransportation 101. What We ll Cover
Transportation 101 getting from point A to B What We ll Cover An introduction to: the transportation system jobs in transportation 1 What is Transportation? --Brainstorm-- Transportation is the system
More informationVISION. 4. Vision. 31 Page
VISION 4. Vision The 2035 LRTP, branded as Transformation, is the Broward MPO s plan for change. Economic vitality for the region, a better environment, and enhanced quality of life are envisioned. This
More informationGARE DO ORIENTE: LISBON, PORTUGAL
GARE DO ORIENTE: LISBON, PORTUGAL TASK 2: TECHNOLOGY // 11516 COMPUTATIONAL ENVIRONMENTS TENEIL VAN DYCK 10449736 TRISTAN DAVISON 10448898 TASK 02 // TENEIL VAN DYCK + TRISTAN DAVISON // TECHNOLOGY 1.CP
More informationStockton Freight & Passenger Rail Mobility Enhancement
Stockton Freight & Passenger Rail Mobility Enhancement 2017 $10.34 million in 2017 FASTLANE Grant funding to complete engineering design, permitting, and construction of the Stockton Track Extension and
More informationTransit, Intercity Bus, Taxi 8-1
8-1 Introduction Public transit is a critical element of any transportation system. It both provides an alternative form of transportation to the traditional use of the automobile and provides mobility
More informationSoutheast Florida Freight and Goods Movement Update Treasure Coast Regional Planning Council September 16, 2011
Southeast Florida Freight and Goods Movement Update Treasure Coast Regional Planning Council September 16, 2011 For Questions on this Presentation, Please Contact: Jeff Weidner, Mobility Manager Florida
More informationENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7
ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT For ease of local identification this Environmental Impact Statement
More informationPublished by the Palm Beach Metropolitan Planning Organization (MPO) in coordination with Leftwich Consulting Engineers, Inc.
AMENDMENT #3 + Published by the Palm Beach Metropolitan Planning Organization (MPO) in coordination with Leftwich Consulting Engineers, Inc. Adopted October 16, 2014 by the Board of Directors Palm Beach
More informationKennedy Station Online Consultation
Kennedy Station Online Consultation 1 Surface Light Rail Transit 2 Metrolinx LRV 4 doors per car (2 single, 2 double) Up to 3 cars per consist 3 Light Rail Vehicles (LRVs) New LRVs will feature: 100% low
More informationAppendix B5 PT Model Validation
Appendix B5 PT Model Validation PT Model Validation Report Sheffield and Rotherham Public Transport Model Report for Sheffield City Council August 2009 Document Control Project Title: MVA Project Number:
More informationPPTA Project Pipeline
PPTA Project Pipeline Commonwealth of Virginia May 2012 Opening Remarks The Commonwealth of Virginia was developed in the 17 th century as a risky, but ultimately highly successful business venture between
More informationAirport Curbside Planning and Design
Transportation Research Record 840 1 Airport Curbside Planning and Design PETER B. MANDLE, E.M. WHITLOCK, AND FRANK LaMAGNA A method of estimating airport curbside demand and procedures for adjusting this
More informationstore for Buckshaw Village and Euxton
A new Aldi food store for Buckshaw Village Aldi, the premium discount food retailer, with local developer Primrose Holdings, is proposing to develop land off Ordnance Road,. The site is currently vacant
More informationo&i consulting: at a glance
s u p p l i e r o f a i r p o r t a r r i v a l & d e p a r t u r e o p e r a t i o n a l p l a n n i n g s e r v i c e s t o t h e L o n d o n 2 0 1 2 G a m e s aviation. logistics. services. o&i consulting:
More informationIntegrating Intermodalism and Multimodalism
Forest Hills Gardens, NY, station area, c.1916 Working Definitions Multimodal means multiple modes of transportation. Multimodal systems enhance capacity across modes. Linden Hills neighborhood, Mpls.
More informationSLC Terminal Redevelopment Program. Salt Lake City International Airport
SLC Terminal Redevelopment Program Salt Lake City International Airport Terminal Redevelopment Program Goals and Expectations Address Seismic Risk Provide Right-Sized Facilities Solve Operational Problems
More informationKeys Edge Community Development District. Engineer s Report Infrastructure Improvements
Keys Edge Community Development District Engineer s Report Infrastructure Improvements Prepared for Keys Edge Community Development District Board of Supervisors Miami-Dade County, Florida Prepared by
More informationCHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES
CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting
More informationPreparing our Roadways for Connected and Automated Vehicles. 70th Annual Ohio Transportation Engineering Conference Bob Edelstein
Preparing our Roadways for Connected and Automated Vehicles 70th Annual Ohio Transportation Engineering Conference Bob Edelstein Agenda Overview Intelligent Network Management Emerging Vehicle Technology
More informationTRANSPORTATION 101 Today and Tomorrow. Moving People and Goods
TRANSPORTATION 101 Today and Tomorrow Moving People and Goods What is the Transportation Commission? An independent, seven-member body of citizens appointed by the Governor for six-year terms and representing
More informationHong Kong International Airport Medium & Long Term Development Plans. The British Chamber of Commerce 18 July 2012
Hong Kong International Airport Medium & Long Term Development Plans The British Chamber of Commerce 18 July 2012 Connecting HK with the World More than 100 airlines serving 160 destinations worldwide
More informationBallard-Interbay MIC Summary Statistics
BallardInterbay MIC Founded in 1869, the City of Seattle is the leading commercial, cultural and advanced technology center of the U.S. Pacific Northwest, and a major port city for transpacific and European
More information6.2.2 Environmental Consequences and Mitigation Measures
6.2 6.2.1 Introduction The existing conditions, regulatory setting, and methods of analysis for transportation under CEQA are described in Chapter 3, NEPA and CEQA Analysis. Impacts that would result from
More informationIntroduction to Transportation Systems Analysis
Introduction to Transportation Systems Analysis Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew Contents 1 Goal of Transportation System Analysis 1 1.1 Characteristics...................................
More informationMULTIPLE NIGHTS AND CLASSES TRIP, PAGE 1
MULTIPLE NIGHTS AND CLASSES TRIP, PAGE 1 In this walkthrough we will be demonstrating how to process a travel that involves multiple days and multiple programs within the same trip. We ll also cover going
More informationAviation Capital Construction Program Update
Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance
More informationS. F. Municipal Transportation Agency Citizens Advisory Council City & County of San Francisco RECOMMENDATIONS / MOTIONS 2017
RECOMMENDATIONS / S 2017 / RECOMMENDATION STAFF RESPONSIBLE STATUS RESPONSE 170105.01 170202.01 170202.02 170302.01 OCSC 161011.01 OCSC 170110.01 EMSC 170125.01 WHEREAS, The City has a transit first policy
More informationFairfax County Countywide Transit Network Study
Fairfax County Countywide Transit Network Study Proposed High Quality Transit Network Concept Metropolitan Washington Council of Governments Travel Forecasting Subcommittee September 20, 2013 1 Presentation
More informationAppendix H. Millennium Hollywood Project Trip Cap and Mitigation Triggers
Appendix H Millennium Hollywood Project Trip Cap and Mitigation Triggers MILLENNIUM HOLLYWOOD PROJECT TRIP CAP AND MITIGATION TRIGGERS Crain and Associates Introduction The Millennium Hollywood Project
More informationPROLOGIS GEORGETOWN CROSSROADS
PROLOGIS CROSSROADS 600 EAST MARGINAL WAY SOUTH SEATTLE, WA 89,61 SF THE FUTURE OF URBAN INDUSTRIAL REAL ESTATE www.prologisgeorgetown.com PLANNED DESIGN Redmond 40 20 Downtown Seattle Bellevue 90 Port
More informationCity of Brantford Chapter 3 TABLE OF CONTENTS
Chapter 3 The Land Use & Transportation Connection TABLE OF CONTENTS 3.1 THE LAND USE & TRANSPORTATION LINK... 1 3.2 POPULATION & EMPLOYMENT GROWTH FORECASTS... 3 3.2.1 Proposed Places to Grow Plan Forecasts
More informationNEW OPPORTUNITY FOR MIDDLESEX COUNTY
Source: http://www.flickr.com/photos/scraparcs/3259040067/sizes/l/in/photostream/ RARITAN RIVER LIGHT RAIL NEW OPPORTUNITY FOR MIDDLESEX COUNTY This report studies the viability of a new transit line connecting
More informationRapid Transit in Winnipeg. Winnipeg TOD Summit November 17, 2014
Rapid Transit in Winnipeg Winnipeg TOD Summit November 17, 2014 Presentation Overview Rapid Transit (RT) in Winnipeg What is RT? What are our RT plans? Near term Longer term Comments re: TOD OurWinnipeg
More informationCHAPTER 26. REGIONAL MOBILITY AUTHORITIES SUBCHAPTER A. GENERAL PROVISIONS SUBCHAPTER B. CREATION OF A REGIONAL MOBILITY AUTHORITY
CHAPTER 26. REGIONAL MOBILITY AUTHORITIES 26.1 Purpose 26.2 Definitions SUBCHAPTER A. GENERAL PROVISIONS SUBCHAPTER B. CREATION OF A REGIONAL MOBILITY AUTHORITY 26.11 Petition 26.12 Public Hearing 26.13
More informationGO RAIL NIAGARA SERVICE EXTENSION
Business Case: Finch Avenue West Rapid Transit GO RAIL NIAGARA SERVICE EXTENSION INITIAL BUSINESS CASE Date: November, 2014 NOVEMBER 2015 Page 1 TABLE OF CONTENTS 1.0 Executive Summary...p.5 2.0 Introduction....p.6
More informationNews Release TRANSPORT MINISTER ANNOUNCES WINNING PROPOSAL FOR TORONTO AIR-RAIL LINK. No. H132/03 For release November 13, 2003
News Release No. H132/03 For release November 13, 2003 TRANSPORT MINISTER ANNOUNCES WINNING PROPOSAL FOR TORONTO AIR-RAIL LINK TORONTO -- Transport Minister David Collenette today announced that Union
More informationMEMORANDUM EXAMPLES FOR ILLUSTRATIVE PURPOSES NEXT STEPS. Item 3 Long-Range Plan Task Force May 17, 2017
Item 3 Long-Range Plan Task Force May 17, 2017 MEMORANDUM TO: TPB Long-Range Plan Task Force FROM: Kanti Srikanth, TPB Staff Director SUBJECT: Sample list of improvement initiatives for illustrative purposes
More information2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014
2040 Transportation Policy Plan Conversion to Performance Based Planning Basis 25 th Annual CTS Transportation Research Conference May 21, 2014 1 About the plan Long-range transportation plan for the Twin
More informationFY UNIFIED PLANNING WORK PROGRAM
FY 13-14 UNIFIED PLANNING WORK PROGRAM PALM BEACH METROPOLITAN PLANNING ORGANIZATION PALM BEACH URBAN STUDY AREA MIAMI URBANIZED AREA MAY 2012 GLOSSARY ADA Americans with Disabilities Act BCMPO Broward
More information