SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6

Size: px
Start display at page:

Download "SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6"

Transcription

1 SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6 October 2014

2 TABLE OF CONTENTS 1. Figure 1.A: Compendium of General Concerns 2. Figure 1.B: Supplemental Rendering 3. Evaluation Memorandum a. Potential Utility Impacts b. Potential Operational / Mobility Impacts c. Potential Right of Way Impacts d. Potential Infrastructure Impacts e. Potential Constructability Impacts f. Potential Design / Geometrical Concerns g. Potential I-395 Project Development & Environment (PD&E) Concerns h. Additional Alternative i. Cost Estimate Summary 4. Figure 2: Geometric Concerns 5. Figure 3: Traffic Circulation and Multimodal Concerns 6. Figure 4: Infrastructure, Maintenance of Traffic (MOT), Aesthetics, and Controversy Potential Concerns 7. Figure 5: Environmental & Utility Concerns 8. Figure 6: Additional Right of Way Impacts Appendix A: Right of Way Cost Estimates Appendix B: Contaminated Soil Disposal Cost Estimate Appendix C: Rendering received on September 3, 2014 Appendix D: I-395 Tunnel and Biscayne Tunnel Project Cost Estimate

3

4

5 Evaluation Memorandum The Florida Department of Transportation (FDOT) District 6 Design office was asked to evaluate a conceptual rendering involving depressing a portion of the I-395 freeway as well as a portion of SR 5/Biscayne Boulevard near downtown Miami provided by Miami-Dade County Commissioner Xavier Suarez (see Figure 1A and 1B). This concept was presented as an alternative option to the current Project Development & Environment (PD&E) study for the I-395. Below please find our comments; please note that these comments are based only on the conceptual rendering provided. Potential Utility Impacts: 1. Impact to existing Florida Gas Transmission (FGT) west/east lateral line that crosses Biscayne Blvd. just north of NE 15 th Street that feeds the Miami Beach Area (See Figure 5). As per the FGT Global Settlement Agreement with the State of Florida and FDOT the relocation of the permitted FGT facility will have to be performed at FDOT s expense and relocated to a suitable location as determined by FGT. One of the requirements for the suitable location is that the gas line has to accommodate an accessible width of 15 on both sides measured from the pipe edge plus 25 of temporary workspace on one of the sides. This entails rerouting the FGT line through an available side street north of NE 17 th Terrace to clear the tunnel and then rerouting the line south through N. Bayshore Drive to tap into the existing line prior to its crossing of Biscayne Bay. In addition to the relocation costs and traffic disruptions the FGT line is the sole supplier of TECO Gas Company which supplies gas services to the whole Miami Beach area. Hence, disruption of the FGT line will directly impact gas services to thousands of Miami Beach residents and businesses. Portions of costs associated with the relocation of the FGT line would be part of the overall cost for construction of this concept, but were not estimated as part of this analysis due to lack of information from the utility agency regarding preferred relocation routes at the time this report was developed. 2. Impacts to other underground utilities along Biscayne Blvd. include but are not limited to Miami Dade Water and Sewer and their regional pump station components and connecting lines, AT&T, and Florida Power & Light (FP&L) (See Figure 5). A preliminary ballpark estimate for the relocation of the Comcast, FPL, Level 3, Verizon, MDWASD, Teco Peoples Gas, and AT&T utilities along Biscayne Blvd. is approximately 58 Million. It should be noted that these costs, although additional with respect to the total cost of the project, should be borne by the utility agencies/owners if they are within the FDOT right of way by permit. 3. Impacts to overhead facilities in the I-395 vicinity including FP&L and AT&T. Potential Operational/Mobility Impacts: 1. Lock-down of the Biscayne Blvd. and I-395 tunnels during a hurricane event (for purposes of flood protection) will close two major thoroughfares in an already very congested area of coastal Miami-Dade County. These two facilities currently act as evacuation routes for the downtown area of Miami as well as the barrier island of Miami Beach. Closure of these two facilities would force traffic to seek alternate routes to evacuate the area which are not equipped to handle increased traffic in case of an emergency. 2. Loss of public parking, both on-street and public parking lots (See Figure 4). Page 1 of 6

6 3. The geometric requirements of both tunnels will greatly impact the circulation patterns of 10 bus routes affecting a high number of existing bus stops and inconveniences to many patrons. The tunnel along Biscayne Blvd. will force pedestrians to access bus stops along the frontage roads that are proposed at limited locations since the roadway would be underground in a two block area. 4. Impacts to the existing circulation of the Miami Dade Transit bus terminal located at the Biscayne Blvd. and NE 15 th Street intersection (See Figure 3). 5. Even though the intent of the tunnel concept is to provide a more pedestrian friendly connection, the portion of the roadway that would be depressed along Biscayne Blvd. actually eliminates approximately 14 existing crosswalks across Biscayne Blvd. currently located at signalized intersections and one upcoming mid-block crossing that is to be installed between NE 15 th Terrace and NE 16 th Street (See Figure 3). It is important to note that an independent connection between the Aarsht Center and Bicentennial Park is not being proposed with this concept as pedestrians would still have to cross surface roadways at the proposed roundabout location. 6. Impacts to the traffic connectivity between Biscayne Blvd. (south of I-395) and the proposed site for the Resort World Miami Project (See Figure 3). 7. The proposed interruption of NE 13 th Street between Bayshore Drive and NE 2 nd Avenue would create significant circulation problems and could create gridlock conditions along NE 14 th Street east of NE 2 nd Avenue (See Figure 3). 8. Impacts to the Biscayne Blvd. northbound access for all land uses between NE 11 th Street and NE 9 th Street and NE 2 nd Avenue and Biscayne Blvd. It will require vehicles in this area to first travel southbound along either NE 2 nd Avenue or the Biscayne Blvd. Frontage road to then use NE 8 th Street to access the Biscayne Blvd. northbound tunnel (See Figure 3). Potential Right of Way Impacts: 1. Based on the tunnel concept rendering, the proposed depressed typical section of roadway along Biscayne Blvd. was assumed to consist of four (4) 12 lanes, 14 median including 4 inside shoulders, 8 outside shoulders, and 2 concrete U-wall. The frontage roads consist of two (2) 11 lanes, 6 inside shoulder, curb & gutter on the outside, and 6 sidewalk which sums up to a total typical section width of 154. This section cannot be accommodated within the existing 100 right of way along Biscayne Blvd. north of the I- 395 without acquiring additional right of way and affecting the existing building structures along the corridor. Approximately 32 of additional right of way will be required on the west side and 22 of additional right of way on the east side (See Figure 6). Nine (9) private parcels will be impacted yielding a total acquisition cost of approximately 81 Million (See Appendix A). 2. At a minimum, the elevated profiles along N. Miami Avenue, NE 1 st Avenue and NE 2 nd Avenue as a consequence to the I-395 vertical alignment would have detrimental access and right of way impacts not only along these corridors but also along its intersecting side streets (NE 13 th Street, NE 13 th Terrace, NE 11 th Terrace and NE 11 th Street). Approximately 5 of additional right of way will be required along both the west and east sides, respectively (See Figure 6). Fifty (50) parcels will be impacted yielding a total acquisition cost of approximately 44 Million (See Appendix A). Page 2 of 6

7 Potential Infrastructure Impacts: 1. Impacts to the existing Miami Dade Transit Metro Mover structure (existing pier columns) at the NE 11 th Terrace and NE 15th Street intersections with Biscayne Blvd. Service will be temporarily disrupted between the School Board, Adrienne Arsht Center, and Museum Park to the rest of the downtown area (See Figure 2). For reference purposes, the cost for the Miami International Airport People Mover in 2013 was 270 Million for 1.25 miles which equals to 41, per linear foot. Hence, the approximate reconstruction cost of the impacted downtown people mover segments (Total of approximately 308 Feet) at the NE 11 th Terrace and NE 15th Street intersections with Biscayne Blvd will be approximately 13 Million. 2. Impacts to signals throughout the Biscayne Blvd. corridor as well as adjacent parallel roadways. Potential Constructability Impacts: 1. Maintenance of Traffic along Biscayne Blvd. during construction of this concept may require the complete shutdown of the corridor, which in this case would require diverting northbound traffic through NW 6 th Street, NE 1 st Avenue, NW 14 th Street, NE 2 nd Avenue, and NE 17 th Terrace to continue north along Biscayne Blvd. Biscayne Blvd. southbound traffic will be diverted through NE 17 th Terrace, NE 2 nd Avenue, and NW 7 th Street to continue south on Biscayne Blvd. The corridors to be used for the detours already operate at a high level of capacity and with the addition of the Biscayne Blvd. traffic severe gridlocks would be expected throughout the downtown Miami area for a substantial period of time (See Figure 4). 2. Construction of this project would take a substantial amount of time and would impact several communities in a very dense and urban area with many points of destination nearby. 3. Impact to residents and tourists with the limitation of staging areas, dirt, noise, restrictions in public life, and aesthetics would also be of concern for residents in this area. 4. Impact to businesses and economic sustainability of the area. 5. As per the Contamination Screening Evaluation Report prepared for the I-395 PD&E, two high risk contamination sites were identified near Biscayne Blvd. The high risk contamination sites are where the Perfect Service Station and the Belcher Oil Company Terminal & Tank Farm used to operate (See Figure 5). The construction of the tunnels will require a very detailed analysis and survey of the contaminated sites; just the study alone and obtaining the corresponding permits may take a couple of years. Based on the most recent information obtained from the environmental agencies files for the Belcher Oil and Perfect Oil sites, the contamination appears to extend approximately 1,300 feet along the proposed construction corridor for the subject project. It is estimated that the project cost to address the contaminated material will be approximately 27.3 Million (See Appendix B). It is also estimated that it will require approximately 106 days load-out and disposing of this contaminated material (approximately 526,000 tons) to a Class I Landfill. The cost of addressing the contaminated material does not include the construction and operation cost of a required temporary water treatment facility. Page 3 of 6

8 Potential Design/Geometrical Concerns: 1. The proposed tunnel concept Vertical alignment along I-395 will exceed the maximum grade requirements and not meet the minimum curve length for a freeway as per the FDOT standards and criteria. The restriction of having to maintain a minimum vertical clearance at the intersecting FEC railroad corridor and the limited distance to the west approach tunnel portals forces the I-395 profile to exceed the maximum allowable vertical grade. Furthermore, even with a substandard I-395 profile,n. Miami Avenue, NE 1 st Avenue and NE 2 nd Avenue would need to be raised to allow the I-395 tunnel to run underneath them (See Figure 2). 2. The new required N. Miami Avenue profile will interrupt the continuity of NW/NE 14 th Street. NW 14 th Street is the only east/west facility in the area connecting the Civic Center/Health District west of I-95 with Biscayne Blvd, therefore maintaining its connectivity is vital for linkage and emergency response reasons (See Figure 2). 3. It is our understanding that the concept presented involves raising the grade elevations to allow the top of the I-395 tunnel to be 10 feet above the current grade. This raised area would create grade changes along NE 1 st Avenue and NE 2 nd Avenue which can lead to deficiencies in stopping sight distance, special structural designs, and roadway vertical alignment concerns along these surface streets. Potential I-395 PD&E Concerns: 1. I-395 requires a Supplemental Environmental Impact Statement (EIS) that may require an additional five (5) years to complete. The Record of Decision issued on July, 2010 is for a bridge. Both a tunnel and an open cut tunnel were evaluated in PD&E and determined not to be feasible due to impacts to Overtown. The Supplemental EIS would need to mitigate impacts to Overtown for the tunnel to be considered a viable alternative (See Figure 4). Additional Alternative: On September 3, 2014, the Department was provided with an additional artistic rendering depicting a slightly modified layout of the proposed public space which, from a roadway and transportation standpoint, provided some changes from the rendering that was originally reviewed as part of this evaluation memorandum (See Appendix C). A cursory review was performed on this new alternative; the following are some concerns that were observed: It is unclear from the rendering whether the surface paths shown are intended to be for vehicular traffic or pedestrian traffic. Assuming that they are for pedestrian traffic, circulation patterns for vehicular traffic would be limited given that there would be no surface access for vehicles exiting the Downtown Miami area in the northbound direction to travel in the eastbound direction towards Miami Beach via the MacArthur Causeway. The roundabout originally proposed as part of the first rendering provided seems to have been replaced by a monument or sculpture; this elimination would limit the circulation pattern of vehicles exiting the Downtown Miami area and force vehicles north onto a network of local streets that may not be able to handle the additional traffic flows. It is unclear from this image where the exit point for the tunnel portion of Biscayne Blvd. would be located; it is assumed that it would be near the same location as that shown in the original rendering provided. Page 4 of 6

9 In short, more information would be needed regarding the depressed sections of roadways proposed as part of this alternative in order to be able to more accurately evaluate the impacts and costs associated with this concept. It should be noted that because of its artistic nature, this rendering was assumed to be a modified representation of the overall concept being evaluated by this report and in no way an engineering document meant to substitute the original rendering reviewed by FDOT. Cost Estimate Summary: As per the I-395 PD&E evaluation, the Signature Bridge was selected as the preferred alternative. Total cost for the entire Signature Bridge project was estimated at 600 Million with the Signature Bridge structure alone accounting for 70 Million. A conceptual cost estimate based on the rendering involving depressing a portion of the I-395 freeway as well as a portion of SR 5/Biscayne Boulevard near downtown Miami provided by Miami-Dade County Commissioner Xavier Suarez was prepared in order to evaluate net change in cost (See Appendix D). The net increase in cost between the I-395 /Biscayne Boulevard tunnel concept and the I-395 Signature Bridge Project evaluated the cost of both alternatives within the limits defined by the rendering (See Figure 1.A). A summary of the cost estimate is presented below: Table 1: Cost of I-395/Biscayne Boulevard Tunnel Concept No. Description Cost 1 2 Total Construction Cost for I-395 Tunnel and Biscayne Boulevard Tunnel Concept including roadway reconstruction of Miami Avenue, NE 1 st Avenue, NE 2 nd Avenue, and Biscayne Boulevard Frontage Road (As shown in Figure 2). Cost for additional impacts associated with the I-395 Tunnel and Biscayne Boulevard Tunnel Concept Utility Impacts: 58 Million (costs assumed not to be reimbursable; to be paid for by the utility agency/owner) Right of Way Acquisition: 125 Million Miami Dade Transit Metro Mover Infrastructure Impacts: 13 Million Contamination Mitigation: 27.3 Million 1,322,368, ,300,000 3 Grand Total 1,487,668,301* *Grand total does not include additional reimbursable costs associated with relocation of the FGT gas line Page 5 of 6

10 Table 2: Cost of I-395 Signature Bridge Project within Limits Defined by Rendering No. Description Cost 1 Cost for Signature Bridge Structure, I-395 Mainline / Ramp Connections, and local roads directly impacted and replaced by the proposed I-395 Tunnel concept. 171,518,658 Net Increase in cost = (Cost of I-395/Biscayne Boulevard Tunnel Concept) (Cost of I-395 Signature Bridge Project within Limits Defined by Rendering) 1,316,149,643* Based on the cost estimates shown above, the net estimated increase in cost of the I- 395/Biscayne Boulevard tunnel concept when compared to the I-395 signature bridge project amounts to a total of 1,316,149,643*. Page 6 of 6

11

12

13

14

15

16 Appendix A (Right of Way Cost Estimates)

17 PRELIMINARY

18 PRELIMINARY

19 Appendix B (Contaminated Soil Disposal Cost Estimate)

20 CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet Project Name: Biscayne Tunnel Assessment Task Description: Soil Load-out and Disposal LOA #, Task #: TBD FDOT Project No.: TBD FDOT Contract #: BDT36 WPCE Date: 7/30/2014 Revision No.: Work Duration: 106 days Work Week: 5 days Work Day: 10 hours Description SUMMARY NE 8th Street to NE 11th Street: Labor 951, Equipment 242, Construction and Heavy Equipment 279, Expendables 25, Analytical 117, Transport and Disposal 20,215, Pass-throughs 2, NE 14th Street to NE 17th Street: Labor Equipment 21,834, , , Construction and Heavy Equipment 69, Expendables 6, Analytical 30, Transport and Disposal 5,053, Pass-throughs TOTAL ESTIMATED AMOUNT TOTAL REQUESTED AMOUNT Subtotal Subtotal PRELIMINARY 5,460, ,295, ,295, of 7

21 CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet Project Name: Biscayne Tunnel Assessment (NE 8th St. to NE 11th St.) WPCE Date: 7/30/2014 Task Description: Soil Load-out and Disposal Revision No.: LOA #, Task #: TBD Work Duration: 85 days FDOT Project No.: TBD Work Week: 5 days FDOT Contract #: BDT36 Work Day 10 hours Item No. Direct Labor Item Description Item QTY Unit Type Unit QTY Total No. of Units Unit Rate Cost Project Management 1-2 Contract Manager 1 hour , Project Manager 1 hour , Task Manager 1 hour , Administrative Assistant 1 hour , Health & Safety Plan Preparation 1-2 Contract Manager 1 hour Project Manager 1 hour Certified Industrial Hygienist 1 hour Industrial Hygienist 1 hour Project Kick-off Meeting 1-2 Contract Manager 1 hour Project Manager 1 hour Task Manager 1 hour Project Scientist 1 hour Staff Scientist 1 hour Administrative Assistant 1 hour Supervisor 1 hour Field Foreman 1 hour Equipment Operator 5 hour , Truck Driver 4 hour Technician/Laborer 4 hour Soil Load-out and Disposal Activities* 1-7 Staff Scientist 1 hour , Supervisor 1 hour , Supervisor (OT) 1 hour , Field Foreman 1 hour , Field Foreman (OT) 1 hour , Equipment Operator (loaders) 4 hour , Equipment Operator (loaders) (OT) 4 hour , Equipment Operator (dozer) 1 hour , Equipment Operator (dozer) (OT) 1 hour , Truck Driver (dump trucks) 4 hour , Truck Driver (dump trucks) (OT) 4 hour , Technician/Laborer (flagmen) 4 hour , Technician/Laborer (flagmen) (OT) 4 hour , PRELIMINARY Source Removal Report 1-2 Contract Manager 1 hour Project Manager 1 hour Project Scientist 1 hour , Staff Scientist 1 hour , Draftsperson 1 hour , Administrative Assistant 1 hour Direct Labor Total 951, of 7

22 CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet Project Name: Biscayne Tunnel Assessment (NE 8th St. to NE 11th St.) WPCE Date: 7/30/2014 Task Description: Soil Load-out and Disposal Revision No.: LOA #, Task #: TBD Work Duration: 85 days FDOT Project No.: TBD Work Week: 5 days FDOT Contract #: BDT36 Work Day 10 hours Item No. Item Description Item QTY Unit Type Unit QTY Total No. of Units Unit Rate Cost 2-4 Pick-up Truck 8 day , Truck (dump, 15 CY) 4 day , Organic Vapor Analyzer (OVA)/ Flame Ionization Detector (FID) 1 day , , Construction/Excavation and Heavy Equipment 6-7 Dozer CAT D-6 1 day , Storage Trailer 1 day , Wheel Loader, (Cat 966) 4 day , , Expendables 8-28 Visqueen 4 roll/per day , , Analytical 9-3 Kerosene Analytical Group 610 each , Transport and Disposal Transportation & Disposal-petroleum Contaminated Soil (non-hazardous) 117, ton 421, , ,215, ,215, Pass-throughs Port-o-Let Rental 4 day , * = Estimated production of 5,000 tons per day and no night or weekend work FID = Flame Ionization Detector No = Number OT = overtime OVA = Organic Vapor Analyzer QTY = Quantity Equipment Equipment Total Construction/Excavation and Heavy Equipment Total Expendables Total Analytical Total Estimated Total Legend and Comments Section Transport and Disposal Total PRELIMINARY Pass-throughs Total 2, ,834, of 7

23 CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet Project Name: Biscayne Tunnel Assessment (NE 14th St. to NE 17th St.) WPCE Date: 7/30/2014 Task Description: Soil Load-out and Disposal Revision No.: LOA #, Task #: TBD Work Duration: 21 days FDOT Project No.: TBD Work Week: 5 days FDOT Contract #: BDT36 Work Day 10 hours Item No. Direct Labor Item Description Item QTY Unit Type Unit QTY Total No. of Units Unit Rate Cost Project Management 1-2 Contract Manager 1 hour , Project Manager 1 hour , Task Manager 1 hour , Administrative Assistant 1 hour , Health & Safety Plan Preparation 1-2 Contract Manager 1 hour Project Manager 1 hour Certified Industrial Hygienist 1 hour Industrial Hygienist 1 hour Project Kick-off Meeting 1-2 Contract Manager 1 hour Project Manager 1 hour Task Manager 1 hour Project Scientist 1 hour Staff Scientist 1 hour Administrative Assistant 1 hour Supervisor 1 hour Field Foreman 1 hour Equipment Operator 5 hour Truck Driver 4 hour Technician/Laborer 4 hour Soil Load-out and Disposal Activities* 1-7 Staff Scientist 1 hour , Supervisor 1 hour , Supervisor (OT) 1 hour , Field Foreman 1 hour , Field Foreman (OT) 1 hour , Equipment Operator (loaders) 4 hour , Equipment Operator (loaders) (OT) 4 hour , Equipment Operator (dozer) 1 hour , Equipment Operator (dozer) (OT) 1 hour , Truck Driver (dump trucks) 4 hour , Truck Driver (dump trucks) (OT) 4 hour , Technician/Laborer (flagmen) 4 hour , Technician/Laborer (flagmen) (OT) 4 hour , PRELIMINARY Source Removal Report 1-2 Contract Manager 1 hour Project Manager 1 hour Project Scientist 1 hour , Staff Scientist 1 hour , Draftsperson 1 hour Administrative Assistant 1 hour Direct Labor Total 239, of 7

24 CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet Project Name: Biscayne Tunnel Assessment (NE 14th St. to NE 17th St.) WPCE Date: 7/30/2014 Task Description: Soil Load-out and Disposal Revision No.: LOA #, Task #: TBD Work Duration: 21 days FDOT Project No.: TBD Work Week: 5 days FDOT Contract #: BDT36 Work Day 10 hours Item No. Item Description Item QTY Unit Type Unit QTY Total No. of Units Unit Rate Cost 2-4 Pick-up Truck 8 day , Truck (dump, 15 CY) 4 day , Organic Vapor Analyzer (OVA)/ Flame Ionization Detector (FID) 1 day , , Construction/Excavation and Heavy Equipment 6-7 Dozer CAT D-6 1 day , Storage Trailer 1 day Wheel Loader, (Cat 966) 4 day , , Expendables 8-28 Visqueen 4 roll/day , , Analytical 9-3 Kerosene Analytical Group 1 each , Transport and Disposal Transportation & Disposal-petroleum Contaminated Soil (non-hazardous) 30, ton 105, , ,053, ,053, Pass-throughs Port-o-Let Rental 4 day * = Estimated production of 5,000 tons per day and no night or weekend work FID = Flame Ionization Detector No = Number OT = overtime OVA = Organic Vapor Analyzer QTY = Quantity Equipment Equipment Total Legend and Comments Section Construction/Excavation and Heavy Equipment Total Expendables Total Analytical Total Transport and Disposal Total PRELIMINARY Pass-throughs Total Estimated Total ,460, of 7

25 Biscayne Tunnel Assessment I. Volume of excavation from NW 8th St. to NE 11th St.: W (ft.) D (ft.) L (ft.) V (CF) V (CY) F (Tn/CY) Wt (Tn) ,423, , ,152 Legend: CF = Cubic Feet CY = Cubic Yard F = Conversion Factor ft. = Feet D = Depth ft. = Feet L = Length Tn = Ton V = Volume W = Width Wt = Weight II. Volume of excavation from NE 14th St. to NE 17th St.: W (ft.) D (ft.) L (ft.) V (CF) V (CY) F % W (Tn) ,423, , ,288 Legend: % = Percent estimated for disposal CF = Cubic Feet CY = Cubic Yard F = Conversion Factor ft. = Feet D = Depth ft. = Feet L = Length Tn = Ton V = Volume W = Width Wt = Weight III. CB&I Field Personnel: Staff Scientist 1 Supervisor 1 Field Foreman 1 Operators 5 Truck Drivers 4 Laborers 4 Total 16 PRELIMINARY 6 of 7 CB&I Environmental & Infrastructure, Inc.

26 Biscayne Tunnel Assessment IV. CB&I Construction Equipment Pickup Trucks 8 Dump Trucks 4 OVA 1 Dozer 1 Storage Trailer 1 Loader 4 Port o let 4 V. Assumptions: a. Soil to be excavated by the contractor b. Soil to be loaded into dump trucks by the contractor c. Production estimated at 5,000 tons per day d. No hazardous waste is encountered e. No night or weekend work f. 10 hour work days; 5 days per week; estimate 106 total days g. Staging area to be provided by the contractor h. Minimum staging area of approximately 3 to 5 acres required i. No dewatering and/or groundwater treatment is included in this cost estimate VI. CB&I Scope: a. Provide equipment and personnel to truck the soils to the staging area b. Provide equipment and personnel to manage the staging area c. Provide equipment and personnel to load put and dispose petroleum contaminated soils d. Provide equipment and personnel to sample and analyze the soils per the requirements of FAC PRELIMINARY 7 of 7 CB&I Environmental & Infrastructure, Inc.

27 Appendix C (Rendering Received on September 3, 2014)

28

29 Appendix D (I-395 Tunnel and Biscayne Tunnel Project Cost Estimate)

30 PRELIMINARY

31 PRELIMINARY

32 PRELIMINARY

33 PRELIMINARY

34 20 SIGNALIZATION 20 PI 400,000 8,000,000 TOTAL ITEM 20 8,000, FIRE PREVENTION SYSTEM 1 LS 5,000,000 5,000,000 TOTAL ITEM 21 5,000,000 SUB-TOTAL 166,815,000 Total 734,649,056 ITS 5% 36,732,453 LIGHTING 5% 36,732,453 SPM 2% 14,692,981 MOT 20% 146,929,811 Mobilization 15% 110,197,358 Contingencies 10% 73,464,906 CEI 8% 58,771,924 Eng/Admin/Legal 15% 110,197,358 Total 1,322,368,301 PRELIMINARY T:\DesignGroup_Manso\_DDE_Support\Tunnel_Analysis\Tunnel Section_Construction Cost_ _revised_GP_comments 2

LOCATION HYDRAULIC REPORT

LOCATION HYDRAULIC REPORT Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID

More information

Final Air Quality Report

Final Air Quality Report Florida Department of TRANSPORTATION Final Air Quality Report PD&E Study From East of Babcock Street (SR 507) to US 1 Brevard County, Florida Financial Project ID: 430136-1-22-01 ETDM Project Number: 13026

More information

Mendocino Forest Products Grading For Industrial Land Improvements

Mendocino Forest Products Grading For Industrial Land Improvements Mendocino Forest Products Grading For Industrial Land Improvements Technical Memorandum #10 CEQA Evaluation of Environmental Impacts Prepared for: Mendocino Forest Products Company, LLC Consulting Engineers

More information

Overview of Prior Studies

Overview of Prior Studies FLORIDA DEPARTMENT OF TRANSPORTATION PORT OF MIAMI TUNNEL STUDY Overview of Prior Studies This summary was provided on July 29, 2003 by Jeff V. Easley, PE, Vice President of Reynolds, Smith and Hills as

More information

FTBA 2018 Construction Conference Major Projects Update

FTBA 2018 Construction Conference Major Projects Update FTBA 2018 Construction Conference Major Projects Update Bill Jones, P.E. FDOT District 7 Director of Transportation Development 1 2 3 FUNDED PROJECTS Howard Frankland Bridge Industry Forum September 2018

More information

PUBLIC HEARING LOOP 9

PUBLIC HEARING LOOP 9 PUBLIC HEARING LOOP 9 From Interstate (I)-35E to I-45 Dallas and Ellis Counties, Texas CSJ: Loop 2964-10-005 9: I-35E to I-45 Tuesday, June 20, 20, 2017 2017 Public Hearing Introductions ELECTED & PUBLIC

More information

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS SECTION PAGE NO. SECTION TITLE NO. EXECUTIVE SUMMARY -------------------------------------------------------------------- ES-1 1.0 INTRODUCTION

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

I-395 Reconstruction. Project Advisory Group Meeting A1. PRESENTATION November 15, 2011

I-395 Reconstruction. Project Advisory Group Meeting A1. PRESENTATION November 15, 2011 I-395 Reconstruction Project Advisory Group Meeting A1 PRESENTATION November 15, 2011 1 Meeting A1 Agenda Project Overview Project Evolution Sample of VQ Process Small group exercise Next Step Meeting

More information

Central Manatee Network Alternatives Analysis

Central Manatee Network Alternatives Analysis District One CMNAA Central Manatee Network Alternatives Analysis Central Manatee Network Alternatives Analysis The Florida Department of Transportation (FDOT) is conducting the Central Manatee Network

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

MDX Contract #: RFP MDX Work Program #: ETDM #: 11501

MDX Contract #: RFP MDX Work Program #: ETDM #: 11501 SR 874/Don Shula Expressway Ramp Connector Project Development & Environment (PD&E) Study PUBLIC HEARING December 8, 2011 MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 1 This Public

More information

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W District One CMNAA Central Manatee Network Alternatives Analysis December 12, 2017 5:00 pm - 7:00 pm First Baptist Church 1306 Manatee Ave. W, Bradenton, FL 34205 Central Manatee Network Alternatives Analysis

More information

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0 SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information

I-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction

I-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction I-395 Reconstruction MDX SR 83611 Improvements I-95 Concrete Pavement Reconstruction FTBA Conference February 10, 2016 Presentation Outline Project Overview I-395 Reconstruction MDX SR 83611 I-95 Pavement

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG

More information

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,

More information

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee MEMORANDUM Date: July 14, 2006 Project #: 6389 To: US 97 & US 20 Refinement Plan Steering Committee From: Sonia Hennum, P.E., Andrew Cibor, E.I.T., & Julia Kuhn, P.E. Project: US 97 & US 20 Refinement

More information

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

DRAFT AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM PROJECT DEVELOPMENT AND ENVIRONMENT STUDY STATE ROAD 60 GRADE SEPARATION OVER CSX RAILROAD Polk County, Florida Financial Project ID: 436559-1-22-01 Prepared for: Florida

More information

Frequently Asked Questions Connecting Palo Alto

Frequently Asked Questions Connecting Palo Alto Frequently Asked Questions Connecting Palo Alto www.cityofpaloalto.org/connectingpaloalto General Project Questions Q1: What is Connecting Palo Alto? A1: Connecting Palo Alto (formerly the Palo Alto Rail

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! FEBRUARY 12, 2014 FTBA CONSTRUCTION CONFERENCE PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner Operator Federal

More information

Final Recommendations Identification of Improvements, Strategies, and Solutions

Final Recommendations Identification of Improvements, Strategies, and Solutions Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...

More information

Alternatives Evaluation Methodology

Alternatives Evaluation Methodology Alternatives Evaluation Methodology www.vision54 56.com B 1 Phase 2 Alternatives Evaluation Methodology PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014 New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the

More information

CHAPTER 3 SCOPE SUMMARY

CHAPTER 3 SCOPE SUMMARY CHAPTER 3 SCOPE SUMMARY GENERAL The SDDOT is an active member of AASHTO to share common national design standards for the state highway system. The AASHTO Task Force on Geometric Design has completed the

More information

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199)) 11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

NW 47TH AVENUE PROJECT DEVELOPMENT & ENVIRONMENTAL

NW 47TH AVENUE PROJECT DEVELOPMENT & ENVIRONMENTAL VALUE ENGINEERING STUDY OF NW 47TH AVENUE PROJECT DEVELOPMENT & ENVIRONMENTAL FM Number: 430637-1-22-01 STUDY NUMBER: 1400601 MIAMI, FLORIDA October 21-25, 2013 FINAL REPORT In Association With: THE FLORIDA

More information

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 INTERCHANGE MODIFICATION REPORT FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 PREPARED BY: VIRGINIA DEPARTMENT OF TRANSPORTATION STAUNTON DISTRICT DECEMBER 13, 2006

More information

Chapter 4: Transportation and Circulation

Chapter 4: Transportation and Circulation Chapter 4: Transportation and Circulation 4.1 Introduction Circulation improvements constructed for the West Valley Logistics Center will improve the functional efficiency of the circulation system in

More information

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project 06/2014 PROJECT STUDY REPORT (Cal Poly Pomona Senior Project) For Conceptual Approval of an Interchange Improvement And Cooperative Agreement with The City of Lake Elsinore for completion of Project Approval

More information

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 CHAPTER 1: INTRODUCTION... 5 1.1 Study Purpose and background... 5 1.2 Study Approach... 6 1.3 Study Area... 6 CHAPTER 2: DESCRIPTIONS OF ALTERNATIVES... 7 2.1

More information

Chapter 4 Construction Effects and Mitigation

Chapter 4 Construction Effects and Mitigation Chapter 4 Construction Effects and Mitigation This chapter discusses the direct and indirect s of project related construction on the elements of the built and natural environments. Direct s are s caused

More information

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS

More information

DRAFT Geotechnical Technical Memorandum

DRAFT Geotechnical Technical Memorandum DRAFT Geotechnical Technical Memorandum US 19 (SR 55) Reevaluation from 66 th Avenue North to SR 690/118 th Avenue North Work Program Item Segment No. 435914-1 Project Development and Environment Study

More information

175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS

175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS 175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS June 2012 Prepared by: Public Works Department City of Overland Park, KS EXECUTIVE SUMMARY... 2 INTRODUCTION...

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

Community Advisory Committee Meeting No. 2. June 22, 2006

Community Advisory Committee Meeting No. 2. June 22, 2006 Community Advisory Committee Meeting No. 2 June 22, 2006 Introductions The Study Team KDOT Wichita Partners Consultants CAC members Overview Today s Agenda Opinion Survey Study Status Starting Concept

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 TRANSPORTATION INTERSTATE 87 INTERCHANGE 11A TOWN OF MALTA SARATOGA COUNTY, NY DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 PROJECT REPORT NEW YORK STATE DEPARTMENT OF TRANSPORTATION JOSEPH

More information

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE The Existing Roadway Condition Assessment Report (ERCAR) should include the evaluation of all elements against new construction criteria.

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017 Palo Alto Rail Committee Meeting November 29, 2017 Slide 1 Project Area Millbrae Station City Limits Existing Railroad Crossing at Broadway Caltrain Operational Constraint Major Constraints Millbrae Station

More information

TAMPA BAY NEXT MAJOR PROJECTS UPDATE

TAMPA BAY NEXT MAJOR PROJECTS UPDATE TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023

More information

APPENDIX Methodology Letter of Understanding (MLOU) and Agency Correspondence

APPENDIX Methodology Letter of Understanding (MLOU) and Agency Correspondence APPENDIX 21 1 Methodology Letter of Understanding (MLOU) and Agency Correspondence Question 21 Transportation This document reflects the transportation study methodology to be utilized in preparing responses

More information

OPTIONAL STATIONAVIATION/MANCHESTER

OPTIONAL STATIONAVIATION/MANCHESTER CRENSHAW/LAX TRANSIT CORRIDOR PROJECT FEIS/FEIR OPTIONAL STATIONAVIATION/MANCHESTER Aviation and Manchester, Looking East Aviation/Manchester Station (Optional) The Optional Aviation/Manchester Station

More information

Alternatives Development Report. Twin Ports Interchange Reconstruction Project

Alternatives Development Report. Twin Ports Interchange Reconstruction Project Alternatives Development Report Twin Ports Interchange Reconstruction Project SP 6982-322 and SP 6980-60 City of Duluth St. Louis County, Minnesota Prepared for: Minnesota Department of Transportation

More information

Utility Undergrounding Feasibility Assessment

Utility Undergrounding Feasibility Assessment 043251005.17 Utility Undergrounding Feasibility Assessment SUMMARY As an independent agency of the City of Miami, funded by tax levies on properties within its boundaries, the Miami Downtown Development

More information

INTERCHANGE MODIFICATION REPORT

INTERCHANGE MODIFICATION REPORT INTERSTATE 75 AND STATE ROAD 884 (COLONIAL BOULEVARD) INTERCHANGE LEE COUNTY, FLORIDA INTERCHANGE MODIFICATION REPORT Prepared for: Florida Department of Transportation District One May 2017 Interchange

More information

Standard Performance Attributes for Transportation Projects

Standard Performance Attributes for Transportation Projects Standard s for Transportation Projects Mainline Operations Local Operations Maintainability Construction Impacts Environmental Impacts Project Schedule An assessment of traffic operations and safety on

More information

Project Initiation Form

Project Initiation Form Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination

More information

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD To: Steve Gramm, SDDOT Memo From: HDR Project: SDDOT I-190 Silver Street Interchange Study Rapid City, SD HDR Project No. 000000000137390 Date: December 27, 2011 RE: Replacement of Existing I-190 Twin

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

4.0 CONSTRUCTION METHODS AND ACTIVITIES

4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential

More information

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination 4-65 Interstate 73 FEIS: I-95 to the Myrtle Beach Region 4-66 Comment noted. The use of existing roadways was considered during alternative development (refer to Chapter 2, Section 2.1, page 2-1 and the

More information

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO.

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. 5 Agenda: 1. Welcome/Introductions 2. Progress & Updates Since Previous

More information

FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT

FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT District 2 1109 South Marion Avenue Lake City, FL 32025-5874 INTERSTATE 10 (SR 8) / SR

More information

Construction Engineering and Inspection Services Pembroke Road from Dykes Road to Silver Shores Boulevard Broward County, FL

Construction Engineering and Inspection Services Pembroke Road from Dykes Road to Silver Shores Boulevard Broward County, FL Construction Engineering and Inspection Services to Silver Shores Boulevard Broward County, FL R L I N O. R 2 11 4 0 8 0 P 1 I. Experience and Qualifications with Roadway Construction a. Eisman & Russo

More information

EXECUTIVE SUMMARY. The IP developed the following purpose and need statement for the Part B I-71 Access Improvement Study.

EXECUTIVE SUMMARY. The IP developed the following purpose and need statement for the Part B I-71 Access Improvement Study. EXECUTIVE SUMMARY The Ohio-Kentucky-Indiana Regional Council of Governments (OKI) has conducted the with the following purpose: Develop a comprehensive transportation plan for the Uptown area that serves

More information

NOISE TECHNICAL MEMORANDUM. Inland Rail Trail Project Cities of San Marcos and Vista, San Diego County DISTRICT 11 SD CML 5381(003)

NOISE TECHNICAL MEMORANDUM. Inland Rail Trail Project Cities of San Marcos and Vista, San Diego County DISTRICT 11 SD CML 5381(003) NOISE TECHNICAL MEMORANDUM Inland Rail Trail Project Cities of San Marcos and Vista, San Diego County DISTRICT 11 SD CML 5381(003) Attention: Kevin Hovey, Environmental Branch Chief, Caltrans District

More information

Final Air Quality Report

Final Air Quality Report Florida Department of Transportation - District VII County Line Road (C.R. 578) Project Development and Environment Study From U.S. 19 (S.R. 55) to U.S. 41 (S.R. 45) Work Program Item Segment Number: 257298

More information

4.12 Public and Emergency Services

4.12 Public and Emergency Services 4.12 Public and Emergency Services Public services include schools, community centers, cemeteries, and social service providers. Emergency services include fire and police stations and services, hospitals,

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

Grottoes. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

Grottoes. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation 2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration

More information

Going/Greeley Interchange Enhancements for Truck Operations

Going/Greeley Interchange Enhancements for Truck Operations Going/Greeley Interchange Enhancements for Truck Operations City of Portland Table of Contents What Is The Problem?.1 What Is The Purpose Of The Study?...1 Review Of Alternatives.1 Table: Estimated Cost

More information

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015.

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015. CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA Our Mission: To provide a supplemental financial mechanism for the revitalization of Crystal City, Potomac Yard, and Pentagon

More information

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014 SR 29 Project Development & Environment Study Presentation to SR 29 Stakeholders Advisory Committee January 23, 2014 Purpose and Need Enhancing Economic Competitiveness Improving Emergency Evacuation Capabilities

More information

Federal Way Transit Center to Tacoma Dome Light Rail

Federal Way Transit Center to Tacoma Dome Light Rail Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project

More information

MEMORANDUM: INITIAL CONCEPTS SUMMARY

MEMORANDUM: INITIAL CONCEPTS SUMMARY MEMORANDUM: INITIAL CONCEPTS SUMMARY INTRODUCTION This memo presents a summary of initial concepts that have been identified as development of the project study has progressed, along with a recommendations

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL

US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL JOINT MEETING OCTOBER 12, 2018 Future Corridors Auburndale Winter Haven ILC (CSX Rwy) Tampa Airport

More information

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas.

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas. Affected Environment, Environmental 2.1.4 Utilities and Service Systems This section addresses the potential impacts to public utilities and service systems within the project area as a result of project

More information

M D 355 [FR E D E R IC K R O A D] OVER

M D 355 [FR E D E R IC K R O A D] OVER M D 355 [FR E D E R IC K R O A D] OVER LITTLE BENNETT CREEK MAINTENANCE OF TRAFFIC ALTERNATIVE ANA LYSIS Prepared by: INTRODUCTION The purpose of this report is to present the results of traffic analyses

More information

Peninsula Widening. Project Description. Overview of Project Status. Estimated Total Project Cost $4.7 - $7.3 Billion

Peninsula Widening. Project Description. Overview of Project Status. Estimated Total Project Cost $4.7 - $7.3 Billion Peninsula Widening SYSTEM: Interstate FROM: I-664 (Hampton Roads) TO: I-95 (Richmond) DESCRIPTION OF WORK: Provide for increased capacity, improve safety standards and minimize roadway geometric and structural

More information

Attachment E. Logistics. Ridge Road Extension Alternatives Analysis

Attachment E. Logistics. Ridge Road Extension Alternatives Analysis Attachment E Logistics for: Ridge Road Extension Alternatives Analysis PREPARED FOR: Pasco County Engineering Services Department PREPARED BY: NV5, INC. 6989 E. FOWLER AVENUE TAMPA, FLORIDA 33617 April

More information

AIR QUALITY TECHNICAL MEMORANDUM

AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision

More information

Presented by: Frank Guyamier

Presented by: Frank Guyamier FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal

More information

IH 30/IH 35E Reconstruction Project Pegasus Final Technical Memorandum - Evaluation of Conceptual Alternatives Task 7.5

IH 30/IH 35E Reconstruction Project Pegasus Final Technical Memorandum - Evaluation of Conceptual Alternatives Task 7.5 MEMO TO: Timothy Nesbitt, P.E. DATE: August 26, 2002 FROM: SUBJECT: Sandy Wesch-Schulze, P.E., AICP IH 30/IH 35E Reconstruction Project Pegasus Final Technical Memorandum - Evaluation of Conceptual Alternatives

More information

Executive Summary. How to Use this Document

Executive Summary. How to Use this Document How to Use this Document In the Final Environmental Impact Statement (EIS) and this Executive Summary: Text from the Draft EIS that remains substantially unchanged, including minor edits such as correction

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

VISION STATEMENT, MISSION STATEMENT, AND GOALS AND OBJECTIVES

VISION STATEMENT, MISSION STATEMENT, AND GOALS AND OBJECTIVES VISION STATEMENT, MISSION STATEMENT, AND GOALS AND OBJECTIVES Vision Statement: Our vision is to provide a high quality, safe, efficient, and cost-effective multi-modal transportation system that supports

More information

3.1.3 Horizontal and Vertical Alignments Intersections and Signalization Conditions Access Management Classification...

3.1.3 Horizontal and Vertical Alignments Intersections and Signalization Conditions Access Management Classification... US 27 MULTIMODAL PLANNING AND CONCEPTUAL ENGINEERING (PACE) STUDY FM Number 428662-1-12-01 FINAL REPORT December 2012 Florida Department of Transportation District Four Prepared by: VOLUME 1 TABLE OF CONTENTS

More information

6.2.2 Environmental Consequences and Mitigation Measures

6.2.2 Environmental Consequences and Mitigation Measures 6.2 6.2.1 Introduction The existing conditions, regulatory setting, and methods of analysis for transportation under CEQA are described in Chapter 3, NEPA and CEQA Analysis. Impacts that would result from

More information

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS Section Title Page 12.1 General... 12-1 12.2 Design Standards... 12-1 12.2.1 General Requirements...12-1 12.2.2 Minimum Depth...12-1

More information

2.1.4 PROJECT CONSTRUCTION

2.1.4 PROJECT CONSTRUCTION Alignment 2C Alignment 2C is the preferred alternative. The new 36-inch force mains would follow the existing alignment along the existing utility road within the OCSD easement from the Bitter Point Pump

More information

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Pensacola Bay Bridge Replacement Design Build Industry Forum Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Project Location 2 GENERAL PROJECT INFORMATION Replacement of the structurally

More information

CHAPTER 8 TRANSPORTATION ELEMENT

CHAPTER 8 TRANSPORTATION ELEMENT CHAPTER 8 TRANSPORTATION ELEMENT Section 8.01 Purpose: The purpose of this Chapter (element) is to establish the desired and projected transportation system within Niceville and to plan for future motorized

More information

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units)

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) 10/16/2014 Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) July 2002 Prepared by Construction Cost Estimating Unit Program Support Services 10/16/2014 Table of Contents

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information