1 Tuesday, February 10, 2015 Minutes Los Angeles County Metropolitan Transportation Authority RIITS Configuration Management Committee One Gateway Plaza Monterey Conference Room 17th Floor Members present: Joe Butler (PATH) via phone Monica Castellanos (Parsons) via phone George Chen (LADOT) Chuck Gendry (Iteris) via phone Kali Fogel (Metro) Vo Lam (Montebello Bus) via phone Heather Liang (Caltrans) Glenn Murphy (Parsons) Jones Reinland (Metro) Rahul Simlote (Torrance Transit) Doug Sing (Metro) David Tsuen via phone Carri Sabel via phone 1
2 1) Called to Order (Kali Fogel) The meeting was called to order at 1:48 p.m. Introductions of everyone present. 2) Approved Previous Minutes (Committee) Minutes of October 21, 2014 meeting were approved. KF HL GC Y Y Y 3) Data Access Agreements Discussion (Committee) Clear Path agreement: Approved with the condition City of LA transportation data won t be released at this time. Restricted access to the ISP agreement only. Carole Cleary working on it. Do not release Department of Transportation data. 4) Agency/ISP Applications Action (Committee) New application, SkedGo.com, requested ISP data without Department of Transportation data. Approval for Skedgo application The agreement will be the same as the Clear Path agreement. Australian company. Legal looking into it. Approval obtained for Clear Path. KF HL GC Y Y Y 5) RIITS Maintenance Status Discussion (Glenn Murphy) a. System monitoring Recently migrated to Op Manager. Demo of dashboard provided to participants. Monitors host servers, network switches for RIITS Monitors stale data, monitors time stamps in the xml file. Monitors refreshing of data Generates reports for Metro (performance, availability). Reports have been tailored to Metro s request. 2
3 Links to the Trouble Ticket system, to monitor outages allows for better tracking and response to issues. b. Foothill Transit Upgrade FHT upgrade to their system. RIITS only to query the database to get transit data. In the process of analyzing what needs to be done to modify the RIITS interface. Coordination with FHT c. Metro bus and rail upgrade under RIITS Maintenance Transit database updated to a later version of Oracle. Interface needs to be updated for RIITS. Working to let Metro know what tables RIITS needs to access. Metro agreed to provide: real time data, schedule data and passenger counts. d. Multi-interface Project The purpose is to retrieve: o traffic flow information from express lanes, o upgrade Caltrans HQ data feed (network modification) throughout backbone o lane-by-lane traffic data from Caltrans o Caltrans events planned and unplanned (i.e. collision info) Kali would like to know what work will be completed before the end of the contract (end of March. Glenn to provide dates when integration of the above items will occur. Kali would like to know if Caltrans would be interested in modifying the existing MOU to obtain a sub-license agreements. Iteris (Chuck G) asked if the Port of Long Beach will be part of the integration. o PoLB is doing an analysis of their system o Contractor on board around March or so they need time to do an analysis. o Not part of the multi-interface project at this time. Caltrans D8 Interface contingent in getting the firewalls set up. o Improvements will be done on how data is routed o D8 data will come through fiber. Request to get the work done by Friday, at this time it looks like it would be pushed one-two weeks. 3
4 Request for new line for Caltrans D7 TMC to Metro. Existing T1 is too small. Higher capacity line has been requested. 6) Other Items Discussion (Committee) Coordination about future projects: City of LA waiting for Metro funding agreement on I-5 corridor projects to be executed before projects start. Caltrans does not have any agreements for the measure R-Fund tied to RIITS Physical route will be out through Caltrans D7 LARTMC and then rerouted to desired location. City of LA - There is a pull box close to the freeway / close to both parties. This will be share access, dedicated bandwidth but not dedicated fiber. Looking for spots on ideal locations to conduct investigation in the field, to determine how the physical fiber is going to be re-routed and how construction will occur. Kali is looking for 4 locations One location can be Eagle Rock area City of LA: Kali is looking to hire a consultant on board for communications plan. Demonstrate how RIITS can make an agency connection City of LA requests 1-2 weeks to think about bringing a contractor on board RIITS needs to coordinate with Caltrans to do work for modification of ATMS for Express Lanes and lane by lane data TrafficLand would like to modify agreement and have access to more Caltrans cameras. Meeting notice sent for this Friday to discuss. Looking for TrafficLand to stream data for D8 and D12. No agreement with those two districts yet. Budget due Feb 26. Transit working with Montebello Bus Lines RIITS form Discussed options for incorporating video from buses 4
5 Currently getting session timeouts upgrade the firewall to allow free flow of the data Power infrastructure work complete; Kali getting UPCs for 220V to connect all on redundant power November 6 th Metro/Waze meeting at 10:30 November 7 th Metro Open Session how the public will be better served by the data LADOT: DHS brought in to review network security There is an agency switch sitting outside the firewall; may need to upgrade; waiting for report from DHS RITSI project was the result of an audit; If Caltrans is okay with sharing the data, then Kali can get LADOT the information 7) Next Meeting Date and Time Action (Committee) a. Next meeting for Tuesday, March 10 at 10 a.m. 8) Action Items Action (Committee) No new actions required at this time. 9) Adjournment Action (Committee) The meeting was adjourned at 3:00 p.m. Prepared by: Monica Castellanos Parsons 5
Connected Corridors: I-210 Pilot Integrated Corridor Management System
PARTNERS FOR ADVANCED TRANSPORTATION TECHNOLOGY INSTITUTE OF TRANSPORTATION STUDIES UNIVERSITY OF CALIFORNIA, BERKELEY Connected Corridors: I-210 Pilot Integrated Corridor Management System System Integration
More informationMinutes. Thursday, January 10, Los Angeles County Metropolitan Transportation Authority. RIITS Configuration Management Committee
Thursday, January 10, 2013 Minutes Ls Angeles Cunty Metrplitan Transprtatin Authrity RIITS Cnfiguratin Management Cmmittee One Gateway Plaza 7 th Flr Scheduling Cnference Rm Members Present: Allen Chen
More informationINTELLIGENT TRANSPORTATION SYSTEMS APPENDIX
INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX Southern California Association of Governments ADOPTED APRIL 2012 INTELLIGENT TRANSPORTATION SYSTEMS Introduction 1 Existing System Description 1 Existing System
More informationLos Angeles Region s Connected/Automated Vehicle Efforts
Los Angeles Region s Connected/Automated Vehicle Efforts Regional TSMO and NOCoE Webinar Ed Alegre, PTP Los Angeles County Metropolitan Transportation Authority (LA Metro) Los Angeles Region 4,083 square
More informationPlan Helps LA s ExpressLanes Meet Expectations
Plan Helps LA s ExpressLanes Meet Expectations Presented by: Ken Wissel ITE Western District 2013 Annual Meeting Los Angeles Traffic LA drivers know traffic congestion 10 million + residents in LA County
More informationLos Angeles County Service Authority for Freeway Emerge 2 ~n~=~r~t'ts;s. l~f? ~~~ VV2`f Y'aZ3-05 ~1n5ai2S, t llii~rt?{~ ~ilv ~?_)YJ,P.~'.
Los Angeles County Service Authority for Freeway Emerge 2 ~n~=~r~t'ts;s l~f? ~~~ VV2`f Y'aZ3-05 ~1n5ai2S, t llii~rt?{~ ~ilv ~?_)YJ,P.~'. "i3.47% bb'2 I i~58`?.net LA ~ ~~ SAFE BOARD OCTOBER 24, 2013 SUBJECT:
More informationConnected Corridors Face-to-Face Meeting. Tuesday, Sept 13th, :30 3:30 pm Caltrans D7 HQ
Connected Corridors Face-to-Face Meeting Tuesday, Sept 13th, 2016 1:30 3:30 pm Caltrans D7 HQ Sept 13th, 2016 Agenda 2 Introductions Schedule Update Outreach Presentation by Lyft High Level Design Lane
More informationLos Angeles County One Gateway Plaza zi3.gzz.zooo Tel Metropolitan Transportation Authority Los Angeles, CA gooiz-2952 rnetro.net
Los Angeles County One Gateway Plaza zi3.gzz.zooo Tel Metropolitan Transportation Authority Los Angeles, CA gooiz-2952 rnetro.net EMAC 1 5 EXECUTIVE MANAGEMENT AND AUDIT COMMITTEE November 18,2010 SUBJECT:
More informationCALIFORNIA HIGHWAY PATROL AGREEMENT
18 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MAY 15, 2013 SUBJECT: ACTION: CALIFORNIA HIGHWAY PATROL AGREEMENT EXECUTE AN AGREEMENT WITH
More informationLunch. Raffle Prizes. Raffle. Date. and Timee. Wednesday. Place. Wedgewoo. Emerald Room. Fresno, CA Program. Business Meeting. infrastructure.
INSTITUTE OF TRANSPORTATION ENGINEERS CENTRAL CALIFORNIA SECTION Lunch Meeting Date and Timee Wednesday y, October 28, 2015 12 Noon 2:00 PM Place Wedgewoo od Banquett Center http://wedgewoodbanquet.com/
More informationTHANK YOU TO ALL THE I-210 PILOT STAKEHOLDERS FOR YOUR COMMITMENT TO THE PROJECT
Summer 2015 Welcome Samson! Call for Projects Application Recommended For Funding Caltrans is pleased to announce Samson Teshome as the first Corridor Manager under Caltrans innovative reorganization plan.
More informationINNOVATIVE CONCEPTS AND NEW TECHNOLOGIES FOR REGIONAL MULTI-JURISDICTIONAL INTEGRATED TRAFFIC MANAGEMENT
INNOVATIVE CONCEPTS AND NEW TECHNOLOGIES FOR REGIONAL MULTI-JURISDICTIONAL INTEGRATED TRAFFIC MANAGEMENT Joseph K. Lam, P.Eng., President, Systems Business Perry Craig, P.Eng., Principal, Systems Business
More informationIntelligent Movement of Goods Will Trucks/Trains be able to Operate More Efficiently?
Intelligent Movement of Goods Will Trucks/Trains be able to Operate More Efficiently? UCLA Lake Arrowhead Symposium October 2008 Lawrence Jesse Glazer FHWA Calif. Division Office Jesse.Glazer@fhwa.dot.gov
More informationStrategic Transportation Plan FOCUS ON TRANSIT
Strategic Transportation Plan FOCUS ON TRANSIT Presented to: Gateway Cities Service Council Presented by: Jerry Wood, GCCOG Director of Transportation and Engineering COG2013\2013 - POWER POINTS for JRW
More informationOptical Wavelength Service (OWS)
Optical Wavelength Service (OWS) The EIS Optical Wavelength Service (OWS) is a fiber optic based service that provides dedicated, point-to-point, single-fiber data transport at speeds ranging from 1 to
More informationRTMC-D3 - Traffic Operations Caltrans District 3 SACOG Data Repository. Sacramento Region (Partnership) County Sheriff Communications Centers
Archived Data Management Subsystem California HPMS Caltrans HQ Caltrans Performance Monitoring System (PeMS) UC Berkeley City of Sacramento TOC Regional Traffic Count Archive SACOG SACOG Data Repository
More informationCounty Wide CCTV Interoperability Project Orange County, California
County Wide CCTV Interoperability Project Orange County, California ITE Western District San Francisco Bay Area Section Carlos A. Ortiz, PE, TE, PTOE September 18, 2014 San Francisco Los Angeles & Ventura
More informationEXAMPLE - TECHNICAL AGREEMENT PROPOSAL INTEGRATION THROUGH LAUNCH
CALTRANS DIVISION OF TRAFFIC OPERATIONS EXAMPLE - TECHNICAL AGREEMENT PROPOSAL INTEGRATION THROUGH LAUNCH CONNECTED CORRIDORS I-210 PILOT IMPLEMENTATION SYSTEM INTEGRATION, SYSTEM DEPLOYMENT AND OPERATIONAL
More informationTMC Reconfiguration to Accommodate Express Lanes. 15 th International Conference on Managed Lanes Session No. 6 Bob Edelstein, ITS Practice Leader
TMC Reconfiguration to Accommodate Express Lanes 15 th International Conference on Managed Lanes Session No. 6 Bob Edelstein, ITS Practice Leader Agenda Partnerships Consoles, Video Walls Systems Operations
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Interagency Meeting June 19, 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Interagency Meeting June 19, 2017 Agenda > Welcome and Introductions > Purpose of Interagency Scoping > Timeline and Process > Agency Coordination
More informationFunding Intelligent Transportation Systems in the Los Angeles Region
Funding Intelligent Transportation Systems in the Los Angeles Region 2017 ITS California Annual Meeting Ed Alegre, PTP Los Angeles County Metropolitan Transportation Authority (Metro) Los Angeles Region
More informationComparison of I-210 and I-710 as Potential ICM Corridors
Comparison of I-210 and I-710 as Potential ICM Corridors Positive Aspects Traffic sensors Very good PeMS coverage of freeway mainline, HOV lanes, and ramps Many intersections within Pasadena already equipped
More informationConnected/Autonomous Vehicles in a
Connected/Autonomous Vehicles in a Freight Corridor: Implementation Issues and Assumptions presented to ITS 3C Summit 2014 Mobile, AL presented by Cambridge Systematics, Inc. Kenny Voorhies, PE, PTOE September
More informationrequirements, we developed an MNS foundation that is adaptable to different requirements for size, bandwidth, and complexity.
General Services Administration (GSA) Enterprise Infrastructure Solutions (EIS) requirements, we developed an MNS foundation that is adaptable to different requirements for size, bandwidth, and complexity.
More informationBrendon Hemily, PhD
Brendon Hemily, PhD Agenda Transit ITS: Functionalities and Evolution Benefits and Challenges Strategic Approach Latest Developments in Transit ITS The Future: Connected Vehicle
More informationConnected Corridors. I-210 Pilot Project. Advancing Traffic Control through Big Data & Connectivity. IPAM Program UCLA.
Connected Corridors I-210 Pilot Project Advancing Traffic Control through Big Data & Connectivity IPAM Program UCLA October 7, 2015 Samson Teshome, P.E., PMP Pilot TMS Corridor Manager California DOT,
More informationHigh Level Design Review. High Level Design v1.1 Release
High Level Design Review High Level Design v. Release Agenda Scope Review Key Elements and Concepts Design Walkthrough Comments and Responses Questions? Scope High Level vs. Detailed Design 4 High Level
More informationSouth Bay Measure R Highway Program (SBHP) Strategic Transportation Element. Planning & Programming Committee Meeting
South Bay Measure R Highway Program (SBHP) Strategic Transportation Element Planning & Programming Committee Meeting July 17, 2013 Strategic Transportation Element (STE) What is STE? STE is to provide
More informationPresentation to the Streets and Freeways Subcommittee
Presentation to the Streets and Freeways Subcommittee Michael Cano, Deputy Executive Officer March 2019 LA County Goods Movement: Updates 2 2018: Highly successful year for Goods Movement in LA County
More informationGE Security. NavLogix. Mobile Resource Management System
GE Security NavLogix Mobile Resource Management System NavLogix simplifies fleet management No matter what kind of fleet you re responsible for, you ll find NavLogix can help you enhance efficiency, reduce
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Meeting June 2017 Agenda > Welcome and Introductions > Purpose of Scoping > Timeline and Process > Environmental Approach and Methodology >
More informationTransit Signal Priority in the Denver Metro. Bart Przybyl, P.E., PTOE
Transit Signal Priority in the Denver Metro Bart Przybyl, P.E., PTOE BACKGROUND DRCOG Denver Regional Council of Governments RTD Regional Transportation District (Transit Authority) 2007 DRCOG/RTD Transit
More informationSUBJECT: STATUS REPORT ON PROJECT MANAGEMENT INFORMATION SYSTEM IMPLEMENTATION
0 Metro Metropolitan Transportation Authority One Gateway Plaza 213.922.~~~ let Los Angeles, CA 90012-2952 rnetro.net MEASURE R PROJECT DELIVERY COMMITTEE SEPTEMBER 16,2010 SUBJECT: STATUS REPORT ON PROJECT
More informationWelcome High Desert Corridor
Los Angeles County Metropolitan Transportation Authority Welcome High Desert Corridor Open House Meetings 6 8pm Monday, July 15, Lake Los Angeles Elementary School Tuesday, July 16, Stater Bros Stadium
More information3.6 GROUND TRANSPORTATION
3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to
More informationUC Berkeley Research Reports
UC Berkeley Research Reports Title ITS Hardware Maintenance Management Systems: White Paper for MORIP Pooled Fund Study Permalink https://escholarship.org/uc/item/8h18686z Authors Kuhn, Beverly T. Durkop,
More informationSAN BENITO COUNTY COUNCIL OF GOVERNMENTS REGULAR MEETING. September 18, 2014, 3:00 P.M. FINAL MINUTES
Agenda Item: SAN BENITO COUNTY COUNCIL OF GOVERNMENTS REGULAR MEETING September 18, 2014, 3:00 P.M. FINAL MINUTES MEMBERS PRESENT: Chair Gomez, Director Boch, Director Botelho, Director Muenzer, and Director
More informationThe Complete Outsourcer s Billing Solution
HOST-bill The Complete Outsourcer s Billing Solution One single bill, per customer account, that combines all services, equipment and payments into the next generation of bill presentment that all demanding
More informationRestoration of Historic Streetcar Service in Downtown Los Angeles
Restoration of Historic Streetcar Service in Downtown Los Angeles Environmental Scoping Meeting January 23, 2013 Agenda 1. Welcome 2. Purpose of Scoping Meeting 3. Project Background and Description 4.
More informationDenver Traffic Management Center - Using Technology to Increase Operational Capabilities
Denver Traffic Management Center - Using Technology to Increase Operational Capabilities Jim Fox, PE City and County of Denver Western ITE and Texas ITE Joint Conference June 26, 2018 Background Traffic
More informationI-95 / I-395 Integrated Corridor Management. Hari Sripathi, P.E. Regional Operations Director
I-95 / I-395 Integrated Corridor Management Hari Sripathi, P.E. Regional Operations Director Purpose of ICM Initiative Address real time demand management in I-95/I- 395 corridor Identify tools to provide
More informationHOW DOES GOODS MOVEMENT AFFECT GATEWAY CITIES? 7/9/2013
GATEWAY CITIES TECHNOLOGY PLAN FOR GOODS MOVEMENT LAEDC e-mobility Task Force July 9, 2013 Jerry R. Wood Director of Transportation and Engineering Gateway Cities Council of Governments Jerry@jrwoodconsultant.com
More informationIntent to Prepare an Environmental Impact Statement for the South Bay Metro
DEPARTMENT OF TRANSPORTATION Federal Transit Administration Intent to Prepare an Environmental Impact Statement for the South Bay Metro Green Line Extension Transit Corridor, Southwestern Portion of Los
More informationPeople First Portal Upgrade
People First Portal Upgrade (March 01, 2018) Erin Rock, Secretary 1 Objectives To ensure everyone understands what is occurring over the next 60 days the sequence of events To make sure everyone has key
More informationM E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview
DTR Toll Collection Overview 1 The Dulles Toll Road A Traditional Tolling Facility * Payment Options * EZ Pass * Exact Change (all coins) * Full Service (but no Credit Card capability) * Some higher (but
More informationI-90 Smart Road: Operational Features. October 18th, 2017 Scott Lee, P.E., TIMS Project Manager, Parsons Amarpal Matharu, P.E.
I-90 Smart Road: Operational Features October 18th, 2017 Scott Lee, P.E., TIMS Project Manager, Parsons Amarpal Matharu, P.E., Illinois Tollway Tollway ITS History Up To 2016 Over 1050 CCTV Cameras 45
More informationTraffic Engineering Projects. Ashley Golden, Development Services Director Jason Samonte, Traffic Engineer
Traffic Engineering Projects Ashley Golden, Development Services Director Jason Samonte, Traffic Engineer City 1 Council Meeting, May 10, 2016 Overview Projects: Intelligent Transportation System (ITS)
More informationSession 2A (11:45-12:30) Topic Covered Overview Of National Urban Transport Helpline (NUTH) NUTH Applications And Concepts Planning And Design
Session 2A (11:45-12:30) Topic Covered Overview Of National Urban Transport Helpline (NUTH) NUTH Applications And Concepts Planning And Design Considerations National Urban Transport Helpline Overview
More informationVoIP Solution How to Make the Best Choice for Your Business
Choosing the Right VoIP Solution How to Make the Best Choice for Your Business Section Title - 1 TABLE OF CONTENTS Introduction 3 CH. 1 What is VoIP? Why Do I Need It? 4 CH. 2 What Type of VoIP Solutions
More informationCalifornia Department of Conservation Office of Technology Services. Video Conference Infrastructure Upgrade & Endpoint Expansion RFQ# 4D841081
A. SCOPE AND DESCRIPTION The Department of Conservation (DOC) currently has a basic Video Conference setup, with data sharing capability, consisting of (2) two Polycom High Definition (HD), dual screen,
More informationS203: The Caltrans Performance Measurement System (PeMS) An Introduction to PeMS and a Demonstration of its Multimodal Tools
S203: The Caltrans () An Introduction to and a Demonstration of its Multimodal Tools Presented By: Ellison Alegre, San Diego Association of Governments Jane Berner, Caltrans APA s 2012 National Planning
More informationNew Jersey Transit Rail Stoppage Forum February 18, 2016 Summary of Key Points
New Jersey Transit Rail Stoppage Forum February 18, 2016 Summary of Key Points The goal of the New Jersey Transit Rail Stoppage forum was to discuss the potential risk of a rail stoppage, the impacts such
More informationImplementing ICM: Scan Findings, Updates and Next Steps California Connected Corridors
NCHRP 20-68A U.S. Domestic Scan Program Scan 12-02: Advances in Strategies for Implementing Integrated Corridor Management (ICM) Implementing ICM: Scan Findings, Updates and Next Steps California Connected
More informationTransportation Data Potpourri in Frisco Part 2
Transportation Data Potpourri in Frisco Part 2 TexITE Joint Dallas-Fort Worth Section Meeting May 11, 2018 Curtis Jarecki, P.E. Brian Moen, P.E. City of Frisco Overview Signal Performance Measures Signal
More informationLos Angeles County Congestion Reduction Demonstration Project
Los Angeles County Congestion Reduction Demonstration Project frequently asked questions update #1 /august 2008 Los Angeles County Metropolitan Transportation Authority (Metro), California Department of
More informationSolution. With the development of communication technologies and growing user demand for
Solution 1.1 HD Video Dispatch Solution With the development of communication technologies and growing user demand for video application, GHT pioneers the industry by introducing the 720P HD video dispatch
More informationPlans, Programs, and Projects Update
TES Conference October 2018 IDOT Intelligent Transportation Systems Plans, Programs, and Projects Update IDOT ITS Staff Central Office Bureau of Operations Terry Heffron ITS Unit Manager Kevin Price -
More informationExhibit 1 - MyFloridaNet-2 Services - Service Level Agreements Financial Consequence for non-performance
Core Network Availability: the amount of time the core network is accessible to the customers. Outage restored within 60 seconds, with time Core Network Availability and Performance Degradation Credit
More informationITS NEWS. Building Southern California s Goods Movement System for the Next Century. Gateway Cities. I-710 Zero Emissions Freight Corridor
Building Southern California s Goods Movement System for the Next Century Gateway Cities ITS NEWS Summer 2013 I-710 Zero Emissions Freight Corridor PAGE 4 FRATIS Demonstration Advances PAGE 10 ALSO IN
More informationDear Mr. Huerta, A hard copy will follow via US Mail. Best Regards,
From: Alejandro Huerta [mailto:alejandro.huerta@lacity.org] Sent: Wednesday, November 18, 2015 1:41 PM To: Heidi Mekkelson; Stephanie Eyestone-Jones Subject: Fwd: Crossroads Hollywood_NOP_DEIR_Metro Comments
More informationRegional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report
Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!
More informationStrategic Transportation Plan. Presented to: ECO-Rapid Transit Board of Directors Presented by: Gill V. Hicks, Cambridge Systematics, Inc.
Strategic Transportation Plan Presented to: ECO-Rapid Transit Board of Directors Presented by: Gill V. Hicks, Cambridge Systematics, Inc. June 11, 2014 1 Local Solutions for all Gateway Cities Communities
More informationState Route 710 North Environmental Study Update Online Media Briefing July 12, 2013
State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013 Frank Quon, P.E. Executive Officer, Metro Highway Program Michelle Smith, P.E. Project Manager, Metro Highway Program
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationProject Budget and Schedule Status Report
Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX
More informationLEE COUNTY BOARD OF EDUCATION WIDE AREA NETWORK (WAN) CONNECTIVITY BID OPENING: February, 8 th :00 P.M C.S.T.
LEE COUNTY BOARD OF EDUCATION WIDE AREA NETWORK (WAN) CONNECTIVITY BID OPENING: February, 8 th 2018 2:00 P.M C.S.T. I. MISCELLANEOUS A. Specifications are not intended to eliminate any reputable manufacturer,
More informationNCTCOG Existing and Planned Systems/Deployments NATALIE BETTGER NOVEMBER 27, 2018
NCTCOG Existing and Planned Systems/Deployments NATALIE BETTGER NOVEMBER 27, 2018 Agenda Regional Planning Activities Organizational Structure Regional TSMO Projects Operations Travel Demand Management
More informationGateway Cities Technology Plan for Goods Movement
final report Gateway Cities Technology Plan for Goods Movement Business and Implementation Plan prepared for LA Metro Gateway Cities Council of Governments prepared by Cambridge Systematics, Inc. 555 12th
More informationStaffing Request for Expo Line Phase 2 and Gold Line Foothill Phase 2A - Systems Integration
Los Angeles County Metropolitan Transportation Authority Staffing Request for Expo Line Phase 2 and Gold Line Foothill Phase 2A - Systems Integration System Safety and Operations Committee July 17, 2014
More informationSaaS Maintenance & Customer Support Terms
SaaS Maintenance & Customer Support Terms The following terms and conditions apply for Actiance SaaS Hosted Services Solutions. Maintenance Actiance shall offer product upgrades to Customers hosted environment
More informationRichard Clarke Executive Director Program Management. Capital Program Management
Richard Clarke Executive Director Program Management Capital Program Management Department Overview > Transit, Highway Programs, and Regional Rail o Transit Deliver construction projects on-time and within
More informationMetro. Board Report. File #: , File Type: Contract Agenda Number: 25.
Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #: 2015-0690, File Type: Contract Agenda Number: 25. AD-HOC CONGESTION
More informationTHIS PAGE INTENTIONALLY LEFT BLANK.
THIS PAGE INTENTIONALLY LEFT BLANK. DRAFT ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT LEAD AGENCIES: Federal Transit Administration, U.S. Department of Transportation and Los Angeles County
More informationimvision System Manager Infrastructure Management Software
imvision System Manager Infrastructure Management Software imvision System Manager Vision imvision System Manager can provide a complete view of your physical infrastructure, including panels, faceplates,
More informationCalifornia Connected Corridors: Vehicles, Information, and People Pilot
California Connected Corridors: Vehicles, Information, and People Pilot Alex x (Skabardonis + Bayen) Electrical Engineering and Computer Science Civil and Environmental Engineering UC Berkeley http://traffic.berkeley.edu
More informationAn Evidence-Based Approach for the Planning and Development of Transportation Investments
An Evidence-Based Approach for the Planning and Development of Transportation Investments Michael J. Shiffer, Ph.D. Vice President, Planning & Policy TransLink November, 2011 TransLink and the Metro Vancouver
More informationProgress Meeting 3: Deployment Site Selection
Progress Meeting 3: Deployment Site Selection Sponsored by: California Air Resources Board Performed by: Institute of Transportation Studies University of California, Irvine November 4 th, 2014 Outline
More informationITS Architecture Workshop
Austin Regional ITS Architecture and Deployment Plan Update ITS Architecture Workshop July 22, 2014 Workshop Overview Welcome and Introductions Presentation and Discussion on the Regional ITS Architecture
More informationSustainable Communities Planning Framework Project Briefing October 5th, 2011
Los Angeles County Metropolitan Transportation Authority Sustainable Communities Planning Framework Project Briefing October 5th, 2011 Sarah Jepson Sustainability Manager - Countywide Planning and Development
More informationPreliminary Pricing. June 14, New York Dallas Los Angeles Europe Asia. Michael Camp
Preliminary Pricing June 14, 2018 New York Dallas Los Angeles Europe Asia Michael Camp VP of Business Development Synergy Business Solutions Seattle Portland Boise Findlay, Ohio 206-859-6507 George Megre
More informationConnected Corridors I-210 Pilot Project. User Needs Workshop
Connected Corridors I-210 Pilot Project User Needs Workshop Feb 27, 2014 2 Agenda Introduction Project Overview, Schedule, Corridor Description User Needs Workshop I-210 Project Definition Operational
More informationProject 5.6 Facilitating the Use of Open Source Software Goal: Introduce and discuss opportunities for open source software use
Project 5.6 Facilitating the Use of Open Source Software Goal: Introduce and discuss opportunities for open source software use May 9, 2012 Agenda Welcome and introductions North/West Passage and project
More informationCUSTOMER EXPERIENCE TECHNOLOGY IMPROVEMENTS RECEIVE AND FILE STATUS REPORT
One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel m etro. net 52 EXECUTIVE MANAGEMENT COMMITTEE NOVEMBER 6, 2014 SUBJECT: ACTION: CUSTOMER EXPERIENCE TECHNOLOGY IMPROVEMENTS RECEIVE AND FILE
More informationNALEO ANNUAL CONFERENCE JUNE 24, Hasan Ikhrata, Executive Director Southern California Association of Governments
NALEO ANNUAL CONFERENCE JUNE 24, 2016 Hasan Ikhrata, Executive Director Southern California Association of Governments What is SCAG? Nation s Largest Metropolitan Planning Organization (MPO) 38,000 Square
More informationGateway Cities Council of Governments Intelligent Transportation Systems Implementation Plan for Goods Movement
Gateway Cities Council of Governments Intelligent Transportation Systems Implementation Plan for Goods Movement Streets and Freeways Subcommittee July 14, 2011 The Regional Problem Southeast Los Angeles
More informationINTEGRATED PUBLIC TRANSPORT INFORMATION SYSTEM FOR BAA SOUTHAMPTON AIRPORT
INTEGRATED PUBLIC TRANSPORT INFORMATION SYSTEM FOR BAA SOUTHAMPTON AIRPORT ITS FOR TRAVELLERS AND USERS CONNECTED TRAVELLER SERVICES Mr James L Mead* Mott MacDonald, Stoneham Place, Stoneham Lane, Eastleigh,
More informationUSACE IT/IM Migration Strategy
USACE IT/IM Migration Strategy Decision Briefing Board of Directors 5 February 1998 t:\coord.doc\briefing\it\strategy.ppt Report Documentation Page Report Date 05 Feb 1998 Report Type N/A Dates Covered
More informationMETRO MANAGEMENT RESPONSES TO FISCAL 2005 FISCAL 2008 STATE REQUIRED PERFORMANCE AUDIT OF THE METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS
I. INTRODUCTION Pursuant to Chapter 451, Section 451.454 of the Texas Transportation Code, METRO must have an independent auditor perform a management audit every four years. The audit must include three
More informationMetro. Board Report. File #: , File Type: Contract Agenda Number: 39.
Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #: 2015-1651, File Type: Contract Agenda Number: 39. SYSTEM SAFETY,
More informationProject Budget And Schedule Status Report
Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project
More informationRequest for Proposals for Real Time Passenger Information System
Request for Proposals for Real Time Passenger Information System Overview The Tuscaloosa County Parking and Transit Authority (TCPTA) is seeking request for proposals from a qualified web and mobile application
More informationInternet Protocol Voice Service (IPVS)
Internet Protocol Voice Service (IPVS) Internet Protocol Voice Service (IPVS) allows users to make phone calls using a high-speed IP transport connection instead of a traditional, circuit-switched phone
More informationAppendix B. Newspaper Articles
Appendix B Newspaper Articles http://www.thedailyworld.com/articles/2006/09/27/local_news/06news.prt Page 1 of 2 9/27/2006 Print Page Local agencies looking for consensus on future projects for Highway
More informationTMC of the Future. Dr. Bob Edelstein, PE, PTOE Senior Vice President
TMC of the Future Dr. Bob Edelstein, PE, PTOE Senior Vice President Overview Traffic Operations Centers Transportation Management Centers TMCs are transforming to be more proactive in addressing recurring
More informationProject and Change Management Challenges Faced and Overcome
Project and Change Management Challenges Faced and Overcome ATCO Pipelines Maximo project Maximo WCMUG November 19, 2013 WCMUG Meeting Vancouver, BC Asset Management at the North Pole Santa's Bank Manager
More informationCENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY Prior Audit Recommendations Follow-Up August 31, 2017 Internal Audit, Risk, Business & Technology Consulting TABLE OF CONTENTS 3 Executive Summary 5 Status of Past
More informationWhere s the bus? Real-Time Info & Service Alerts
Where s the bus? Real-Time Info & Service Alerts Presented by Stephen Tu Manager, Operations & Service Delivery Digital Cities Smarter Transportation 7 th Annual UCLA Downtown LA Forum Japanese American
More informationWelcome High Desert Corridor
Los Angeles County Metropolitan Transportation Authority Welcome High Desert Corridor Open House Meeting December 2012 Agenda for Today s Meeting Introduction Project Background Major Updates HDC Strategic
More informationEXAMPLE - TECHNICAL AGREEMENT PROPOSAL PROJECT SELECTION THROUGH AMS
CALTRANS DIVISION OF TRAFFIC OPERATIONS EXAMPLE - TECHNICAL AGREEMENT PROPOSAL PROJECT SELECTION THROUGH AMS CONNECTED CORRIDORS I-210 PILOT IMPLEMENTATION PROJECT MANAGEMENT, OUTREACH, SYSTEM ENGINEERING,
More informationNew Caltrans Team Members Join CC Efforts
Fall 2017 New Caltrans Team Members Join CC Efforts Over the last few months, the I-210 Project welcomed some new team members, including three Caltrans District 7 engineers: Mr. Morteza (Mort) Fahrtash,
More information