DGeo. Cap Sante Boat Haven M, N, O-Dock Maintenance Dredge Project Anacortes, Washington. June 7, for Port of Anacortes

Size: px
Start display at page:

Download "DGeo. Cap Sante Boat Haven M, N, O-Dock Maintenance Dredge Project Anacortes, Washington. June 7, for Port of Anacortes"

Transcription

1 DGeo Cap Sante Boat Haven M, N, O-Dock Maintenance Dredge Project Anacortes, Washington for Port of Anacortes June 7, 2012 Earth Science + Technology

2 Geotechnical Engineering Services Snoqualmie Switch Station Snoqualmie, Washington for Puget Sound Energy March 25, 2013 Plaza 600 Building 600 Stewart Street, Suite 1700 Seattle, Washington

3

4 Table of Contents INTRODUCTION AND SCOPE... 1 FIELD EXPLORATION AND LABORATORY TESTING... 1 Field Explorations... 1 SITE CONDITIONS... 1 Sensitive Areas... 1 Geology... 2 Surface Conditions... 2 Subsurface Conditions... 2 CONCLUSIONS AND RECOMMENDATIONS... 2 Seismic Design... 2 IBC Design Parameters... 2 Shallow Foundations and Mat Foundations... 3 Allowable Soil Bearing Pressure... 3 Embedment... 3 Settlement... 3 Lateral Resistance... 4 Construction Considerations... 4 Retaining Walls... 4 General... 4 Design Parameters... 5 Wall Drainage... 5 Global Stability Analyses... 5 Storm Drain Pipe... 5 Slope Stability... 5 Steep Slope Construction Recommendations... 6 Earthwork... 7 Excavation Considerations... 7 Clearing and Grubbing... 7 Subgrade Preparation... 7 Erosion and Sedimentation Control... 7 Structural Fill... 8 Weather Considerations... 9 Temporary Slopes Permanent Slopes LIMITATIONS REFERENCES March 25, 2013 Page i File No

5 Table of Contents (continued) LIST OF FIGURES Figure 1. Vicinity Map Figure 2. Site Plan Figure 3. Global Stability Analysis Static and Seismic Conditions APPENDICES Appendix A. Field Explorations Figure A-1. Key to Exploration Logs Figures A-2 through A-8. Logs of Borings Appendix B. Report Limitations and Guidelines for Use Page ii March 25, 2013 GeoEngineers, Inc. File No

6 SNOQUALMIE SWITCH STATION Snoqualmie, Washington INTRODUCTION AND SCOPE This report summarizes the results of our geotechnical engineering services for the proposed improvements to the existing Puget Sound Energy (PSE) Snoqualmie Switch Station. The site is located east of Salish Lodge off Railroad Avenue in Snoqualmie, Washington. The site is shown in relation to the surrounding area on the Vicinity Map, Figure 1, and the Site Plan, Figure 2. We previously issued a draft of this report dated March 15, 2015; this report supersedes our previous report. We understand that the proposed improvements include bringing in underground feeder lines from Snohomish County Public Utility District run-of-the-river hydroelectric projects at Hancock Creek and Calligan Creek. These underground feeders will enter from the north and tie into the existing PSE switch station using a new regulator, transformer, and breaker switch, which will be located at the east end of the existing station. The improvements will require expansion onto the steep slope to the east, including a new retaining wall that will be approximately 2 to 9 feet high. Due to space limitations, the retaining wall will likely be a reinforced concrete wall. The proposed improvements will include modifications to the existing storm drainage system, including a new catch basin behind the retaining wall and a new drain pipe extending south down the steep slope and connecting to an existing catch basin that discharges into the Snoqualmie River. The approximate locations of the proposed improvements are shown on the attached Site Plan, Figure 2. Our geotechnical engineering services were completed in general accordance with our proposal dated February 12, Our scope of service includes: Completing four borings and three hand-augered borings at the site; Providing geotechnical conclusions and recommendations for the proposed improvements, and Preparing this report. FIELD EXPLORATION AND LABORATORY TESTING Field Explorations The subsurface conditions at the site were evaluated by completing four borings (B-1 through B-4) to depths ranging from 11½ to 14 feet below existing site grades, and three hand-augered borings (HA-1 through HA-3). The approximate locations of the explorations are shown on the Site Plan, Figure 2. A detailed description of the field exploration program is presented in Appendix A. SITE CONDITIONS Sensitive Areas We reviewed the available sensitive areas maps published online by King County. The maps include identification of areas with significant landslide, seismic, erosion, and coal mine hazards. No geologic sensitive areas are mapped in the vicinity of the proposed switch station improvements; however, based on the slope inclination, the steep slope would be characterized as an erosion and steep slope hazard area. March 25, 2013 Page 1 File No

7 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Geology Geologic information for the project area (Dragovich, Joe D., Littke, Heather A., Anderson, Megan L., et al., 2009) indicates that surficial soils mapped at the site consist of glaciolacustrine deposits and alluvium underlain by bedrock. Glaciolacustrine deposits generally consist of silt, clayey or sandy silt, and silty sand, typically with scattered dropstones and occasional layers and lenses of sand and/or gravel. Alluvium generally consists of well sorted/stratified sand and silt with lesser gravelly sand, sandy pebble gravel, peat, and organic sediments. The glaciolacustrine deposits or alluvium is underlain by bedrock (Volcanic rocks of Snoqualmie Falls - Miocene). Surface Conditions The site is bounded by Railroad Avenue to the north, Salish Lodge to the west, a paved surface parking lot to the east, and a construction access road to the south. The ground surface slopes down from the north where it is about Elevation 446 feet, to about Elevation 416 feet at the south margin of the site. The area of the proposed improvements is currently undeveloped and forested with deciduous and coniferous trees and brush. Subsurface Conditions Based on the explorations performed at the site, the subsurface conditions generally consist of topsoil and fill overlying glaciolacustrine deposits. We observed approximately 4 to 6 inches of topsoil in most of the explorations. The topsoil generally consists of forest duff and organic soil. Below the topsoil, we observed fill consisting of loose to medium dense silty sand/sandy silt with organics (fine roots, charcoal) and varying gravel content to a depth of approximately 3 to 7 feet. Below the fill, we observed glaciolacustrine deposits consisting of very stiff to hard silt with variable amounts of gravel. The glaciolacustrine deposits extended to the depths explored. Bedrock was not encountered in the explorations. No groundwater was observed during drilling. These observations may or may not be representative of the long-term groundwater conditions at the site. CONCLUSIONS AND RECOMMENDATIONS Seismic Design IBC Design Parameters We recommend the 2012 International Building Code (IBC) parameters for Site Class, short period spectral response acceleration (SS), one-second period spectral response acceleration (S1) and Seismic Coefficients FA and FV presented in the following table. Page 2 March 25, 2013 GeoEngineers, Inc. File No

8 SNOQUALMIE SWITCH STATION Snoqualmie, Washington 2012 IBC SEISMIC PARAMETERS 2012 IBC Parameter Recommended Value Site Class C Short Period Spectral Response Acceleration, SS (percent g) Second Period Spectral Response Acceleration, S1 (percent g) 0.43 Seismic Coefficient, FA 1.0 Seismic Coefficient, FV 1.37 We evaluated the site for seismic hazards including liquefaction, lateral spreading, fault rupture and earthquake-induced slope instability. Our evaluation indicates that the site does not have liquefiable soils present and therefore also has no risk of liquefaction-induced lateral spreading. In addition, the site has a low risk of fault rupture. Shallow Foundations and Mat Foundations Allowable Soil Bearing Pressure The proposed switch station equipment may be supported on conventional shallow spread footings or mat foundations bearing either on the native soils or on properly compacted structural fill placed over the native soils. The mat foundations and spread footings, where required, may be designed using an allowable soil bearing pressure of 4,000 pounds per square foot (psf). The allowable soil bearing value applies to the total of dead and long-term live loads and may be increased by up to one-third when considering total loads including transient loads such as wind or seismic forces. A subgrade modulus of 200 pounds per cubic inch (pci) may be used for the design of mat foundations. The retaining wall footing can be designed using the same parameters presented above, except we recommend the footing bear on undisturbed native soils or controlled density fill (CDF) placed over the native soils. Embedment In general, we recommend that the bottom of foundations be embedded at least 18 inches below the lowest adjacent grade for frost protection. The foundation embedment depth may be reduced to 12 inches for small, lightly loaded footings where frost action will not affect equipment performance, or an additional 6-inch-thick layer of gravel that is not susceptible to frost may be placed below the foundations to achieve an embedment of 18 inches. The retaining wall embedment is discussed separately in the Retaining Walls section. Settlement Provided all loose soil is removed and the subgrade is prepared and evaluated as recommended below in the Construction Considerations section, we estimate that the total settlement of shallow and mat foundations will be on the order of ½ to 1 inch. Differential settlements are expected to be less than ½ inch. March 25, 2013 Page 3 File No

9 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Lateral Resistance Lateral foundation loads can be resisted by passive resistance on the sides of foundations and by friction on the base of the foundations. For foundations supported on native soils or on structural fill placed and compacted in accordance with our recommendations, the allowable frictional resistance can be computed using a coefficient of friction of 0.35 applied to vertical dead-load forces. The allowable passive resistance can be computed using an equivalent fluid density of 300 pounds per cubic foot (pcf) (triangular distribution) if these elements are poured directly against compacted native soils or surrounded by structural fill. The structural fill should extend out from the face of the foundation element for a distance at least equal to three times the height of the element and be compacted to at least 95 percent of the maximum dry density (MDD) estimated in general accordance with American Society for Testing and Materials (ASTM) D For the retaining wall footing, due to the descending slope in front of the wall, passive resistance should be neglected. The above coefficient of friction and passive equivalent fluid density values incorporate a factor of safety of about 1.5. Construction Considerations If soft soil areas are present at the foundation bearing surface elevation, the soft soils in these areas must be removed and replaced with structural fill. In such instances, the zone of structural fill must extend laterally beyond the footing edges for a horizontal distance that is at least equal to the depth of overexcavation. For the retaining wall footing, soft soil areas below the foundation subgrade elevation must be removed and replaced with CDF. The overexcavated areas must be neat-cut to limit the extent of the excavation and limit disturbance of the soils at the face of the retaining wall. We recommend that a representative from our firm observe the condition of all footing excavations to evaluate whether the work is completed in accordance with our recommendations and whether the subsurface conditions are as anticipated. Retaining Walls General The proposed improvements will require expansion onto the steep slope to the east, and the grade transition will be accomplished by using a reinforced concrete retaining wall up to 9 feet in height. Based on our explorations, we anticipate overexcavation will be required in some areas below the retaining wall footing. Loose soils must be overexcavated and backfilled with CDF, as discussed in the previous section. Retaining walls must be backfilled with a 12-inch wide zone of drainage aggregate, with weep pipes extending to the face of the wall. The retaining wall must have a minimum of 24 inches of embedment at the face of the wall for wall heights up to 4 feet and a minimum of 36 inches of embedment at the face of the wall for wall heights greater than 4 feet. Page 4 March 25, 2013 GeoEngineers, Inc. File No

10 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Design Parameters We recommend the retaining wall be designed using the parameters presented in the table below. The retaining wall foundations may be designed using the recommendations previously presented in the Shallow Foundations and Mat Foundations section. The parameters listed below assume drainage is provided as described in the Wall Drainage section below. Soil Parameters Unit Weight (pcf) 125 Friction Angle (degrees) 35 Seismic Coefficient, Kh 0.15 Active Earth Pressure (pcf) triangular distribution Seismic Pressure (psf) uniform distribution Retained Soils 31H 6H Wall Drainage We recommend drainage for the retaining wall be provided by placing a 12-inch-wide zone of free-draining soil behind the wall (base course or yard course meet this requirement) and installing weepholes. Permanent drainage systems must intercept surface water runoff at the top and/or bottom of cut and fill slopes to prevent the surface water from flowing in an uncontrolled manner across the wall. Global Stability Analyses We performed slope stability analyses to evaluate the global static and seismic (pseudostatic) stability of the proposed retaining wall. For our analyses, we used the slope stability program Slope/W Soil strength parameters for the slope stability analysis were selected by reviewing the exploration logs and from our professional judgment based on the geologic origin of the soil units. A ground acceleration of 0.15g (where g is the gravitational constant) was used for seismic (pseudostatic) analysis. This ground acceleration corresponds to 50 percent of the effective IBC design ground acceleration, which is assumed equal to the design spectral response acceleration (SDS) divided by 2.5, per Section of the IBC, where SDS is determined in accordance with Section of the IBC. Figure 3 presents the modeled soil strength parameters and slope geometry, along with the static and seismic factors of safety and resulting critical failure surface. The global factor of safety for the slopes is at least 1.5 for static conditions and at least 1.1 for seismic conditions. Based on our slope stability analyses and geotechnical evaluation, it is our opinion that the proposed retaining wall has adequate factors of safety for global stability. Storm Drain Pipe Slope Stability Based on our field observations, subsurface explorations, and experience, it is our opinion that the steep slope is susceptible to surficial soil movement. It is our opinion that the upper weathered soil layer on the slope may move slowly downslope via raveling and soil creep. Instability of this nature is confined to the upper weathered or disturbed zone of soil, which typically has lower March 25, 2013 Page 5 File No

11 SNOQUALMIE SWITCH STATION Snoqualmie, Washington strength than the underlying unweathered soil. This process is more significant on steeper slopes than on flatter slopes. Significant weathering typically occurs in the upper 2 to 3 feet and is the result of oxidation, root penetration, wet/dry and freeze/thaw cycles, and gravity. Erosion of the soils on the steep slope can be managed and effectively reduced through proper erosion control practices and surface restoration methods that are described in the Earthwork section of this report. We recommend that the storm drain pipe be installed aboveground to limit potential impacts from slope movement. Recommendations for construction of the storm drain pipe in the steep slope area are presented below. Steep Slope Construction Recommendations The aboveground portion of the pipe should extend from an anchor point behind the retaining wall onto the face of the slope. The pipe should be butt-fuse welded into a continuous section of pipe, without joints. Because the soils surrounding the pipe can experience movement, we recommend that the pipe be straight and oriented perpendicular to the contours on the face of the slope. This will reduce the loads that the soil movement could impose on the pipe, as compared with a pipe running cross-slope. In addition, the pipe will likely experience some loss of support from surficial soil movement. Therefore, we recommend that the pipe be anchored securely at the top of the slope. We recommend against mid-slope anchorage of the pipe because any soil movement near the midslope anchors could cause distress to the pipe at the anchorage points. In our opinion, high density polyethylene (HDPE) pipe is appropriate for this project because the flexibility of the pipe will enable the pipe to withstand bending stresses if there is some loss of support. The HDPE pipe should be anchored at the top of the slope with a structure designed to restrain the full weight of the pipe, plus the full weight and hydrodynamic loads of the designed stormwater contained within the pipe. We recommend that the anchorage be achieved by means of a structure of sufficient size or a structure plus a dead-man block of concrete. A manhole can be used for this structural anchorage, provided that the manhole has sufficient face area and the structural capacity to transmit the loads from the pipe into the ground. The pipe anchorage should be positioned behind the retaining wall. The anchor should be fully embedded in undisturbed dense native soil or structural fill. It may be possible to design the retaining wall as the anchorage, provided the retaining wall is properly designed for the increased lateral loads. The capacity of the pipe anchorage can be evaluated using the parameters presented in the Shallow Foundations and Mat Foundations section. Lateral loads can be resisted by a combination of friction between the base of the anchor and the supporting soil, and by the passive lateral resistance of the soil at the face of the anchor. Page 6 March 25, 2013 GeoEngineers, Inc. File No

12 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Earthwork Excavation Considerations Topsoil, fill, and glaciolacustrine deposits were observed in the explorations. We anticipate that these soils can be excavated with conventional excavation equipment, such as trackhoes or dozers. Cobbles and boulders were encountered in the soils at the site, and the contractor should be prepared to remove them where necessary. Bedrock is anticipated to be present below the glaciolacustrine deposits, although explorations at the site did not extend to the bedrock. Clearing and Grubbing Trees, brush, and other vegetation, including topsoil with roots, should be stripped and removed from areas where structural fill will be placed. The stripped material should be placed in landscaping areas or transported off-site for disposal. Subgrade Preparation In areas where structural fill is to be placed, the upper 12 inches of existing subgrade soils must be evaluated prior to fill placement. This can be done by probing. Likewise, the bearing surface in the proposed foundation areas for structures and retaining walls must be evaluated after site grading is complete. Soft zones noted during probing must be overexcavated and replaced with compacted structural fill or CDF. Erosion and Sedimentation Control Potential sources or causes of erosion and sedimentation depend upon construction methods, slope length and gradient, amount of soil exposed and/or disturbed, soil type, construction sequencing and weather. The project impact on erosion-prone areas can be reduced by implementing an erosion and sedimentation control plan. The plan should be designed in accordance with applicable city and/or county standards. The plan should incorporate basic planning principles, including: Scheduling grading and construction to reduce soil exposure; Retaining existing vegetation whenever feasible; Revegetating or mulching denuded areas; Directing runoff away from denuded areas; Minimizing the length and steepness of slopes with exposed soils; Decreasing runoff velocities; Confining sediment to the project site, and; Inspecting and maintaining control measures frequently. We recommend that graded and disturbed slopes be tracked in place with the equipment running perpendicular to the slope contours so that the track marks provide a texture to help resist erosion and channeling. Some sloughing and raveling of slopes with exposed or disturbed soil should be expected. March 25, 2013 Page 7 File No

13 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Temporary erosion protection must be used and maintained in areas with exposed or disturbed soils to help reduce the potential for erosion and reduce transport of sediment to adjacent areas. Temporary erosion protection must include the construction of a silt fence around the perimeter of the work area prior to the commencement of grading activities. Permanent erosion protection must be provided by reestablishing vegetation using hydroseeding and/or landscape planting. Until the permanent erosion protection is established and the site is stabilized, site monitoring must be performed by qualified personnel to evaluate the effectiveness of the erosion control measures and repair and/or modify them as appropriate. Provisions for modifications to the erosion control system based on monitoring observations must be included in the erosion and sedimentation control plan. Structural Fill MATERIALS Materials used to raise site grades, placed to support structures or pavements, or used for utility trench backfill are classified as structural fill for the purpose of this report. Structural fill material quality varies depending upon its use as described below: On-site soils must not be used as structural fill to support switch station equipment. On-site soils may be considered for use as structural fill for other purposes during dry weather. On-site soils may also be used during wet weather provided that they can be moisture-conditioned to meet compaction specifications. If on-site soils cannot be moisture-conditioned, imported gravel borrow must conform to Puget Sound Energy Base Course Aggregate Specification as described in the following table: US Standard Sieve Size 3 inches 100 ¾ inch ⅜ inch ¼ inch U.S. No. 40 < 30 U.S. No. 200 Percent Passing (by weight) 5 maximum Structural fill placed as yard course crushed aggregate surfacing material must be angular crushed rock conforming to Puget Sound Energy Specification as described in the following table: US Standard Sieve Size 1½ inches inch 60 to 100 ¾ or ⅝ inch 0 to 35 ⅜ inch 0 to 5 Percent Passing (by weight) Page 8 March 25, 2013 GeoEngineers, Inc. File No

14 SNOQUALMIE SWITCH STATION Snoqualmie, Washington FILL PLACEMENT AND COMPACTION CRITERIA Structural fill must be mechanically compacted to a firm, non-yielding condition. In general, structural fill must be placed in loose lifts not exceeding 8 to 10 inches in thickness. Each lift must be conditioned to the proper moisture content and compacted to the specified density before placing subsequent lifts. Structural fill must be compacted to the following criteria: Structural fill placed below foundations and roadways or to establish yard grades must be compacted to at least 95 percent of the MDD estimated in general accordance with ASTM D Structural fill placed to form finished slopes must also be compacted to at least 95 percent of the MDD. Structural fill (including utility trench backfill) placed outside of areas where foundations, roadways, parking and yard areas are to be located must be compacted to at least 90 percent of the MDD estimated in general accordance with ASTM D We recommend that a representative from our firm be present during proof-rolling and/or probing of the exposed subgrade soils in structure areas prior to the placement of structural fill and also during the placement of structural fill. Our representative will evaluate the adequacy of the subgrade soils and identify areas needing further work, perform in-place moisture-density tests in the fill to evaluate whether the work is being done in accordance with the compaction specifications, and advise on any modifications to procedures that may be appropriate for the prevailing conditions. Weather Considerations The native soils contain a sufficient percentage of fines (silt) and are moisture-sensitive. When the moisture content of these soils is appreciably above the optimum moisture content, these soils become muddy and unstable, operation of equipment on these soils will be difficult and it will be difficult to meet the required compaction criteria. Additionally, disturbance of these near-surface soils should be expected if earthwork is completed during periods of wet weather. The wet weather season in the Puget Sound region generally begins in October and continues through May; however, periods of wet weather can occur during any month of the year. The optimum earthwork period for these types of soils is typically June through September. If wet weather earthwork is unavoidable, we recommend that: Stockpiles of on-site soils that will be used as structural fill during wet weather be covered with plastic sheeting to protect them from rain. If on-site soils cannot be moisture-conditioned to meet compaction requirements during wet weather, imported gravel borrow must be used as discussed previously in the Structural Fill section of this report. The ground surface in and around the work area be sloped so that surface water is directed away from the work area. The ground surface must be graded such that areas of ponded water do not develop. The contractor must take measures to prevent surface water from collecting in excavations and trenches. Measures must be implemented to remove surface water from the work area. March 25, 2013 Page 9 File No

15 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Temporary Slopes The soils encountered at the site are classified as Type C soil in accordance with the provisions of Title of the Washington Administrative Code (WAC), Part N, Excavation, Trenching, and Shoring. We recommend that temporary slopes in excess of 4 feet in height be inclined no steeper than 1H:1V. Flatter slopes may be necessary if localized sloughing occurs. For open cuts at the site, we recommend that: No traffic, construction equipment, stockpiles or building supplies be allowed at the top of cut slopes within a distance of at least 5 feet from the top of the cut. Exposed soil along the slope be protected from surface erosion using waterproof tarps or plastic sheeting. Construction activities be scheduled so that the length of time that the temporary cut is left open is kept as short as possible. Erosion control measures be implemented as appropriate such that runoff from the site is reduced to the extent practicable. Surface water be diverted away from the excavation. The general condition and stability of the slopes be visually assessed periodically by a geotechnical engineer. Because the contractor has control of the construction operations, the contractor must be made responsible for the stability of all temporary slopes, as well as the safety of the excavations. All shoring and temporary slopes must conform to applicable local, state and federal safety regulations. Permanent Slopes We recommend that permanent cut and fill slopes be constructed no steeper than 2H:1V. To achieve uniform compaction, we recommend that fill slopes be overbuilt slightly and subsequently cut back to expose properly compacted fill. Fill placed on existing slopes that are steeper than 5H:1V must be properly keyed into the native soil slope surface. This can be done by constructing the fill in a series of 6- to 8-foot-wide horizontal benches cut into the slope. Bench surfaces must be thoroughly compacted prior to placing the fill soils. To reduce erosion, newly constructed slopes must be planted or hydroseeded shortly after completion of grading. Until the vegetation is established, some sloughing and raveling of the slopes should be expected. This may require localized repairs and reseeding. Temporary covering, such as clear heavy plastic sheeting, jute fabric, loose straw or excelsior matting must be used to protect the slopes during periods of rainfall. Page 10 March 25, 2013 GeoEngineers, Inc. File No

16 SNOQUALMIE SWITCH STATION Snoqualmie, Washington LIMITATIONS We have prepared this report for the exclusive use of Puget Sound Energy and their authorized agents for the proposed Snoqualmie Switch Station Improvements in Snoqualmie, Washington. Within the limitations of scope, schedule and budget, our services have been executed in accordance with generally accepted practices in the field of geotechnical engineering in this area at the time this report was prepared. No warranty or other conditions, express or implied, should be understood. Any electronic form, facsimile or hard copy of the original document ( , text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record. Please refer to Appendix B, Report Limitations and Guidelines for Use, for additional information pertaining to use of this report. REFERENCES International Code Council, International Building Code Dragovich, Joe D., Littke, Heather A., Anderson, Megan L., et al., 2009, Geologic map of the Snoqualmie 7.5-minute quadrangle, King County, Washington, Washington Division of Geology and Earth Resources Geologic Map GM-75. King Country GIS database. URL: United States Geological Survey, U.S. Seismic Design Maps, 2008 data, accessed on 3/12/13 at: March 25, 2013 Page 11 File No

17 Type Name of Services Here Name of Project Here for Type Client Name Here Type Date of Report Here Earth Science + Technology

18 SE Tokul Rd SE 47Th St 358Th Ave SE Mud C SE 49Th St rreek SE David Powell Rd 365Th Ave SE Fish Hatchery Rd SE 47Th Pl 371St Ct SE 372Nd Ave SE UV202 Tokul Creek SE 53Rd St SE 56Th St Office: Redmond Path: \\red\projects\0\ \gis\ _f1_vicinitymap.mxd Map Revised: 3/14/2013 EL Kitsap Pierce Seattle Bellevue UV Th Ave SE Snohomish King 90 Preston Snoqualmie Trl SE 80Th St Snoqualmie River SE Gravenstein Ct SE 82Nd St SE 86Th St Kittitas 372Nd Pl SE Coa 376Th Ave SE ll C r reek SE 88Th St Notes: 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. 3. It is unlawful to copy or reproduce all or any part thereof, whether for personal use or resale, without permission. Data Sources: ESRI Data & Maps, Street Maps 2005 Transverse Mercator, Zone 10 N North, North American Datum 1983 North arrow oriented to grid north Site 378Th Ave SE SE 77Th St K imba l l l l C rree kk i Stearns Rd 382Nd Ave SE Railroad Pl SE SE Cedar St SE 85Th St 384Th Ave SE 4Th St Silva St SE 60Th St King St 2Nd Ave NW Mill Pond Rd Snoqua l lm i ie R Railroad Pl SE ive rr i River View Park Alpha St Falls Ave SE µ Vicinity Map SE Park St Snoqualmie Switch Station Snoqualmie, Washington Borst Lake 2, ,000 Feet 402Nd Ave SE SE 60Th St 396Th Ave SE SE 70Th Dr Figure 1 396Th Dr SE Three Forks P Meadowbrook S

19 Legend B-1 HA-1 Boring by GeoEngineers Hand Auger by GeoEngineers B-3 B-4 N B-1 B-2 W S E HA-3 FEET HA-1 HA-2 Notes 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. Reference: CAD file "SK dwg" provided by PSE on Site Plan Snoqualmie Switch Station Snoqualmie, Washington Figure 2

20 SharePoint Working\Figure 3 Slope Stability Analyses.ppt HPD:tb2 03/08/13 Not to Scale Global Stability Analysis Static and Seismic Conditions Snoqualmie Switch Station Snoqualmie, Washington Figure 3

21 Type Name of Services Here Name of Project Here for Type Client Name Here Type Date of Report Here Earth Science + Technology

22 APPENDIX A Field Explorations

23 SNOQUALMIE SWITCH STATION Snoqualmie, Washington APPENDIX A FIELD EXPLORATIONS Field Explorations Subsurface conditions were explored at the site by completing four borings (B-1 through B-4), and three hand-augered borings (HA-1 through HA-3). The borings were completed by Geologic Drill Exploration Inc of Bellevue, Washington, on February 22, The locations of the explorations were estimated in the field by measuring distances from site features through taping and pacing. The approximate locations of the explorations are shown on the Site Plan, Figure 2. Exploration elevations were estimated based on a site plan (SK dwg) provided by Puget Sound Energy on March 4, Borings The borings were drilled using a hand-portable hollow-stem auger drill rig. The borings were continuously observed by a geotechnical engineer from our firm who examined and classified the soils encountered, collected soil samples, observed groundwater conditions and prepared a detailed log of each boring. The soils encountered in the borings were sampled with a 2-inch outside diameter split-barrel standard penetration test (SPT) sampler or with a 3-inch diameter Shelby tube sampler. The SPT samples were obtained by driving the sampler 18 inches into the soil with a 140-pound hammer free-falling 30 inches. The number of blows required for each 6 inches of penetration was recorded. The blow count ("N-value") of the soil was calculated as the number of blows required for the final 12 inches of penetration. This resistance, or N-value, provides a measure of the relative density of granular soils and the relative consistency of cohesive soils. Where very dense soil conditions precluded driving the full 18 inches, the penetration resistance for the partial penetration was entered on the log. The blow counts are shown on the boring logs at the respective sample depths. The Shelby tube sampler was pushed into the soft peat to collect relatively undisturbed samples for laboratory consolidation testing. Soils encountered in the borings were visually classified in general accordance with the classification system described in Figure A-1. A key to the exploration log symbols is also presented in Figure A-1. The logs of the borings are presented in Figures A-2 through A-4. The logs reflect our interpretation of the field conditions and the results of laboratory testing and evaluation of samples. They also indicate the depths at which the soil types or their characteristics change, although the change might actually be gradual. The borings were backfilled in accordance with Department of Ecology standards. No groundwater was observed during drilling. These observations may or may not be representative of the longterm groundwater conditions at the site. Hand-Augered Borings Hand-augered borings were completed using hand tools. The hand-augered borings were completed by GeoEngineers, Inc on February 22, 2013 and were continuously monitored by a representative from our firm who examined and classified the soils encountered, obtained representative soil samples, observed groundwater conditions and prepared a detailed log of each exploration. March 25, 2013 Page A-1 File No

24 SNOQUALMIE SWITCH STATION Snoqualmie, Washington Soils encountered in the hand-augered borings were visually classified in general accordance with the classification system described in Figure A-1. A key to the hand-augered boring log symbols is also presented in Figure A-1. The logs of the borings are presented in Figures A-5 through A-7. The hand-augered boring logs are based on our interpretation of the field data, and indicate the various types of soils encountered. No groundwater was observed during excavation of the hand-augered borings. These observations may or may not be representative of the long-term groundwater conditions at the site. Page A-2 March 25, 2013 GeoEngineers, Inc. File No

25 MAJOR DIVISIONS SOIL CLASSIFICATION CHART SYMBOLS GRAPH LETTER TYPICAL DESCRIPTIONS ADDITIONAL MATERIAL SYMBOLS SYMBOLS TYPICAL GRAPH LETTER DESCRIPTIONS GRAVEL AND GRAVELLY SOILS CLEAN GRAVELS (LITTLE OR NO FINES) GW GP WELL-GRADED GRAVELS, GRAVEL - SAND MIXTURES POORLY-GRADED GRAVELS, GRAVEL - SAND MIXTURES AC CC Asphalt Concrete Cement Concrete COARSE GRAINED SOILS MORE THAN 50% RETAINED ON NO. 200 SIEVE FINE GRAINED SOILS MORE THAN 50% OF COARSE FRACTION RETAINED ON NO. 4 SIEVE SAND AND SANDY SOILS MORE THAN 50% OF COARSE FRACTION PASSING NO. 4 SIEVE SILTS AND CLAYS GRAVELS WITH FINES (APPRECIABLE AMOUNT OF FINES) CLEAN SANDS (LITTLE OR NO FINES) SANDS WITH FINES (APPRECIABLE AMOUNT OF FINES) LIQUID LIMIT LESS THAN 50 GM GC SW SP SM SC ML CL OL SILTY GRAVELS, GRAVEL - SAND - SILT MIXTURES CLAYEY GRAVELS, GRAVEL - SAND - CLAY MIXTURES WELL-GRADED SANDS, GRAVELLY SANDS POORLY-GRADED SANDS, GRAVELLY SAND SILTY SANDS, SAND - SILT MIXTURES CLAYEY SANDS, SAND - CLAY MIXTURES INORGANIC SILTS, ROCK FLOUR, CLAYEY SILTS WITH SLIGHT PLASTICITY INORGANIC CLAYS OF LOW TO MEDIUM PLASTICITY, GRAVELLY CLAYS, SANDY CLAYS, SILTY CLAYS, LEAN CLAYS ORGANIC SILTS AND ORGANIC SILTY CLAYS OF LOW PLASTICITY CR TS Crushed Rock/ Quarry Spalls Topsoil/ Forest Duff/Sod Groundwater Contact Measured groundwater level in exploration, well, or piezometer Measured free product in well or piezometer Graphic Log Contact Distinct contact between soil strata or geologic units Approximate location of soil strata change within a geologic soil unit Material Description Contact MORE THAN 50% PASSING NO. 200 SIEVE SILTS AND CLAYS LIQUID LIMIT GREATER THAN 50 MH CH OH INORGANIC SILTS, MICACEOUS OR DIATOMACEOUS SILTY SOILS INORGANIC CLAYS OF HIGH PLASTICITY ORGANIC CLAYS AND SILTS OF MEDIUM TO HIGH PLASTICITY Distinct contact between soil strata or geologic units Approximate location of soil strata change within a geologic soil unit HIGHLY ORGANIC SOILS NOTE: Multiple symbols are used to indicate borderline or dual soil classifications 2.4-inch I.D. split barrel Standard Penetration Test (SPT) Shelby tube Piston Direct-Push Bulk or grab Blowcount is recorded for driven samplers as the number of blows required to advance sampler 12 inches (or distance noted). See exploration log for hammer weight and drop. A "P" indicates sampler pushed using the weight of the drill rig. PT Sampler Symbol Descriptions PEAT, HUMUS, SWAMP SOILS WITH HIGH ORGANIC CONTENTS %F AL CA CP CS DS HA MC MD OC PM PI PP PPM SA TX UC VS NS SS MS HS NT Laboratory / Field Tests Percent fines Atterberg limits Chemical analysis Laboratory compaction test Consolidation test Direct shear Hydrometer analysis Moisture content Moisture content and dry density Organic content Permeability or hydraulic conductivity Plasticity index Pocket penetrometer Parts per million Sieve analysis Triaxial compression Unconfined compression Vane shear Sheen Classification No Visible Sheen Slight Sheen Moderate Sheen Heavy Sheen Not Tested NOTE: The reader must refer to the discussion in the report text and the logs of explorations for a proper understanding of subsurface conditions. Descriptions on the logs apply only at the specific exploration locations and at the time the explorations were made; they are not warranted to be representative of subsurface conditions at other locations or times. KEY TO EXPLORATION LOGS FIGURE A-1

26 Drilled Start 2/22/2013 Surface Elevation (ft) Vertical Datum End 2/22/2013 Total Depth (ft) Logged By Checked By Hammer Data ZAS HPD Driller Geologic Drill Exploration, Inc. Rope & Cathead 140 (lbs) / 30 (in) Drop Drilling Equipment Drilling Method Hollow-stem Auger Hand Portable AckerSoil Mechanic Drill Easting (X) Northing (Y) Notes: System Datum Groundwater Date Measured Depth to Water (ft) Not encountered Elevation (ft) FIELD DATA Elevation (feet) Depth (feet) Interval Recovered (in) Blows/foot Collected Sample Sample Name Testing Water Level Graphic Log Group Classification MATERIAL DESCRIPTION Moisture Content, % Dry Density, (pcf) REMARKS 0 CR Quarry spalls 3½ feet excavated by hand 445 SM Brown silty fine to medium sand with gravel and organics (fine roots) (loose to medium dense, moist to wet) (fill) 6 1 Rough drilling Grades to medium dense Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_GEOTECH_STANDARD 435 ML Notes: See Figure A-1 for explanation of symbols. Brownish-gray silt with trace sand and orange mottling (very stiff, moist) Grades to hard Project: Log of Boring B-1 Project Location: Project Number: Snoqualmie Switch Station Snoqualmie, Washington Easier drilling Figure A-2 Sheet 1 of 1

27 Drilled Start 2/22/2013 Surface Elevation (ft) Vertical Datum End 2/22/2013 Total Depth (ft) Logged By Checked By Hammer Data ZAS HPD Driller Geologic Drill Exploration, Inc. Rope & Cathead 140 (lbs) / 30 (in) Drop Drilling Equipment Drilling Method Hollow-stem Auger Hand Portable AckerSoil Mechanic Drill Easting (X) Northing (Y) Notes: System Datum Groundwater Date Measured Depth to Water (ft) Not encountered Elevation (ft) FIELD DATA Elevation (feet) Depth (feet) Interval Recovered (in) Blows/foot Collected Sample Sample Name Testing Water Level Graphic Log Group Classification MATERIAL DESCRIPTION Moisture Content, % Dry Density, (pcf) REMARKS 0 SM Dark brown silty fine to medium sand with trace gravel and organics (fine roots) (loose to medium dense, moist) (fill) ML Brownish-gray silt with trace sand, occasional gravel, and orange mottling (very stiff, moist) ML Brownish-gray silt with trace sand and orange mottling (hard, moist) Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_GEOTECH_STANDARD /5.5" /5" 4 Notes: See Figure A-1 for explanation of symbols. Grades to moist to wet Log of Boring B-2 Project: Snoqualmie Switch Station Project Location: Snoqualmie, Washington Project Number: Figure A-3 Sheet 1 of 1

28 Drilled Start 2/22/2013 Surface Elevation (ft) Vertical Datum End 2/22/2013 Total Depth (ft) Logged By Checked By Hammer Data HPD HPD Driller Geologic Drill Exploration, Inc. Rope & Cathead 140 (lbs) / 30 (in) Drop Drilling Equipment Drilling Method Hollow-stem Auger Hand Portable AckerSoil Mechanic Drill Easting (X) Northing (Y) Notes: System Datum Groundwater Date Measured Depth to Water (ft) Not encountered Elevation (ft) FIELD DATA Elevation (feet) Depth (feet) Interval Recovered (in) Blows/foot Collected Sample Sample Name Testing Water Level Graphic Log Group Classification MATERIAL DESCRIPTION Moisture Content, % Dry Density, (pcf) REMARKS 0 CR SM Gravel Dark brown silty fine to coarse sand with gravel and organics (fine roots) (loose, moist) (fill) Gravels/cobbles SM Brown/yellow silty fine to coarse sand with gravel and organics (fine roots and charcoal) (very loose, moist) Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_GEOTECH_STANDARD 440 ML ML /6" 4 Notes: See Figure A-1 for explanation of symbols. Greenish-gray silt with trace sand and orange mottling (very stiff, moist) Grayish-brown silt with trace sand (hard, moist) Project: Log of Boring B-3 Project Location: Project Number: Snoqualmie Switch Station Snoqualmie, Washington Figure A-4 Sheet 1 of 1

29 Drilled Start 2/22/2013 Surface Elevation (ft) Vertical Datum End 2/22/2013 Total Depth (ft) Logged By Checked By Hammer Data ZAS HPD Driller Geologic Drill Exploration, Inc. Rope & Cathead 140 (lbs) / 30 (in) Drop Drilling Equipment Drilling Method Hollow-stem Auger Hand Portable AckerSoil Mechanic Drill Easting (X) Northing (Y) Notes: System Datum Groundwater Date Measured Depth to Water (ft) Not encountered Elevation (ft) FIELD DATA Elevation (feet) Depth (feet) Interval Recovered (in) Blows/foot Collected Sample Sample Name Testing Water Level Graphic Log Group Classification MATERIAL DESCRIPTION Moisture Content, % Dry Density, (pcf) REMARKS 0 TS 6 inches topsoil SM Dark brown silty fine to coarse sand with gravel (medium dense, moist) (fill) Rough drilling ML Grayish-brown silt with trace sand (hard, moist) Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_GEOTECH_STANDARD Notes: See Figure A-1 for explanation of symbols. Becomes moist to wet With orange mottling Log of Boring B-4 Project: Snoqualmie Switch Station Project Location: Snoqualmie, Washington Project Number: Figure A-5 Sheet 1 of 1

30 Date Excavated: Equipment: 2/22/2013 Hand Auger Logged By: Total Depth (ft) ZAS 1.0 SAMPLE Elevation (feet) Depth (feet) Testing Sample Sample Name Testing Graphic Log Group Classification Encountered Water MATERIAL DESCRIPTION Moisture Content, % REMARKS 1 2 SM Dark brown silty fine to coarse sand with gravel and organics (fine roots) (loose to medium dense, moist to wet) (fill) Increasing gravel content, becomes medium dense Hand auger refusal at 1 foot due to gravel No groundwater seepage observed No caving observed Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTEC Notes: See Figure A-1 for explanation of symbols. The depths on the hand auger logs are based on an average of measurements across the hand auger and should be considered accurate to 0.5 foot. Log of Hand-Augered Boring HA-1 Project: Project Location: Project Number: Snoqualmie Switch Station Snoqualmie, Washington Figure A-6 Sheet 1 of 1

31 Date Excavated: Equipment: 2/22/2013 Hand Auger Logged By: Total Depth (ft) ZAS 0.5 SAMPLE Elevation (feet) Depth (feet) Testing Sample Sample Name Testing Graphic Log Group Classification Encountered Water MATERIAL DESCRIPTION Moisture Content, % REMARKS 1 GP-GM Gray fine to coarse gravel with silt and sand (medium dense, moist) Hand auger refusal at ½ foot No groundwater seepage observed Significant caving observed Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTEC Notes: See Figure A-1 for explanation of symbols. The depths on the hand auger logs are based on an average of measurements across the hand auger and should be considered accurate to 0.5 foot. Log of Hand-Augered Boring HA-2 Project: Project Location: Project Number: Snoqualmie Switch Station Snoqualmie, Washington Figure A-7 Sheet 1 of 1

32 Date Excavated: Equipment: 2/22/2013 Hand Auger Logged By: Total Depth (ft) ZAS 3.0 SAMPLE Elevation (feet) Depth (feet) Testing Sample Sample Name Testing Graphic Log Group Classification Encountered Water MATERIAL DESCRIPTION Moisture Content, % REMARKS TS 6 inches topsoil SM Dark brown silty fine to medium sand with organics (fine roots) (loose, moist) (fill) ML Brownish-gray silt with sand and orange mottling (soft, moist) Hand auger completed at 3 feet No groundwater seepage observed No caving observed Becomes denser, cobble at 3 feet Seattle: Date:3/18/13 Path:W:\REDMOND\PROJECTS\0\ \GINT\ GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTEC Notes: See Figure A-1 for explanation of symbols. The depths on the hand auger logs are based on an average of measurements across the hand auger and should be considered accurate to 0.5 foot. Log of Hand-Augered Boring HA-3 Project: Project Location: Project Number: Snoqualmie Switch Station Snoqualmie, Washington Figure A-8 Sheet 1 of 1

33 APPENDIX B Report Limitations and Guidelines for Use

34 SNOQUALMIE SWITCH STATION Snoqualmie, Washington APPENDIX B REPORT LIMITATIONS AND GUIDELINES FOR USE 1 This appendix provides information to help you manage your risks with respect to the use of this report. Geotechnical Services Are Performed for Specific Purposes, Persons and Projects This report has been prepared for the exclusive use of Puget Sound Energy and their authorized agents. This report may be made available to prospective contractors for their bidding or estimating purposes, but our report, conclusions and interpretations should not be construed as a warranty of the subsurface conditions. This report is not intended for use by others, and the information contained herein is not applicable to other sites. GeoEngineers structures our services to meet the specific needs of our clients. For example, a geotechnical or geologic study conducted for a civil engineer or architect may not fulfill the needs of a construction contractor or even another civil engineer or architect that are involved in the same project. Because each geotechnical or geologic study is unique, each geotechnical engineering or geologic report is unique, prepared solely for the specific client and project site. Our report is prepared for the exclusive use of our Client. No other party may rely on the product of our services unless we agree in advance to such reliance in writing. This is to provide our firm with reasonable protection against open-ended liability claims by third parties with which there would otherwise be no contractual limits to their actions. Within the limitations of scope, schedule and budget, our services have been executed in accordance with our Agreement with the Client and generally accepted geotechnical practices in this area at the time this report was prepared. This report should not be applied for any purpose or project except the one originally contemplated. A Geotechnical Engineering or Geologic Report Is Based on a Unique Set of Project- Specific Factors This report has been prepared for the proposed improvements to the Snoqualmie Switch Station located on Railroad Avenue in Snoqualmie, Washington. GeoEngineers considered a number of unique, project-specific factors when establishing the scope of services for this project and report. Unless GeoEngineers specifically indicates otherwise, do not rely on this report if it was: not prepared for you, not prepared for your project, not prepared for the specific site explored, or completed before important project changes were made. 1 Developed based on material provided by ASFE, Professional Firms Practicing in the Geosciences; March 25, 2013 Page B-1 File No

FIGURES Printed By: aday Print Date: 3/23/2011 12:48:08 PM File Name: \\geodesign.local\files\jobs\m-r\penskeauto\penskeauto-1\penskeauto-1-01\figures\cad\penskeauto-1-01-vm01.dwg Layout: FIGURE 1 VICINITY

More information

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1 PUBLIC WORKS DEPARTMENT David A. Jones, P.E., Director April 7, 2017 Webster Street Sub-Surface Stormwater Storage System Bid No. 2017-022 Bid Date: 4/13/17 ADDENDUM NO 1 Please make the following changes

More information

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS Highway 99 and Kelly Street TABLE OF CONTENTS PROJECT INFORMATION... 1 FIELD EXPLORATION... 1 SITE CONDITIONS... 2 Surface Conditions:... 2 Subsurface Conditions:... 2 FILL.... 2 Topsoil.... 2 Clay Alluvium....

More information

May 2, Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC Washington Street Raleigh, NC

May 2, Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC Washington Street Raleigh, NC Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC. 1030 Washington Street Raleigh, NC 27605-1258 May 2, 2017 Re: Report of Subsurface Investigation Westfield Rehabilitation & Health Care Additions

More information

Appendix A - Vicinity Map Vicinity Map: Palm Beach Gardens City Hall Additions, 000 N Military Trail, Palm Beach Gardens, FL Proposed Location of Police Dept. Attached Addition Proposed Location of New

More information

CONTRACT 5E-2 APPENDIX A - TEST HOLE LOGS DYREGROV ROBINSON INC. PORTAGE AVE WINSTON DR BOURKEVALE CAVELL PARKSIDE DR ASSINIBOINE AVE

CONTRACT 5E-2 APPENDIX A - TEST HOLE LOGS DYREGROV ROBINSON INC. PORTAGE AVE WINSTON DR BOURKEVALE CAVELL PARKSIDE DR ASSINIBOINE AVE APPENDIX A - TEST HOLE LOGS PORTAGE AVE TH -9 CONTRACT E- DR DR BOURKEVALE CAVELL WINSTON DR PARKSIDE DR ASSINIBOINE AVE AUTHORIZED BY: DATE: CONSULTING GEOTECHNICAL ENGINEERS AUTHORIZED /0/ CLIENT DRAWING

More information

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan Site Location 0606 1771 North Dixie Highway Monroe, Michigan 48162 Tel: 734-289-2200 Fax: 734-289-2345 www.manniksmithgroup.com Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

GEOTECHNICAL ENGINEERING REPORT

GEOTECHNICAL ENGINEERING REPORT GEOTECHNICAL ENGINEERING REPORT Project: NW Bucklin Hill at Silverdale Way NW Project Number: 12023 Prepared for: Barber Development P.O. Box 473 Redmond, WA 98073 Prepared by: South Sound Geotechnical

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Pavement Subgrade Survey State Highway 125 over Hudson Creek Ottawa County, Oklahoma September 23, 21 Terracon Project No. 415121 Prepared for: Guy Engineering Services,

More information

EXHIBIT G GEOTECHNICAL REPORT (DRAFT)

EXHIBIT G GEOTECHNICAL REPORT (DRAFT) EXHIBIT G GEOTECHNICAL REPORT (DRAFT) APPENDIX 1 PROJECT SITE 'B' B-1 B-2 I-2 B-3 B-4 B-5 I-1 PROJECT LOCATION LEGEND B-1 = APPROXIMATE BORING LOCATION I-1 = APPROXIMATE INFILTRATION

More information

Typical Subsurface Profile. November 28, 2016

Typical Subsurface Profile. November 28, 2016 November 28, 2016 RSCCD Facility Planning, District Construction and Support Services 2323 N. Broadway, Suite 112, Santa Ana, CA 92706 Attn: Re: Ms. Allison Coburn Facilities Project Manager P: (714) 480-7530

More information

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois AGI Project No. -11 Subsurface Investigation Report For the Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois Prepared for Mr. Steve Panko Key Development Partners, LLC North State Street,

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET. Revised Soil Survey Report November 24, 2015 Matthew G. Moore, P.E.

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET. Revised Soil Survey Report November 24, 2015 Matthew G. Moore, P.E. LD-0 /12/09 DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET Revised Soil Survey Report November 2, 201 Matthew G. Moore, P.E. VDOT (Division) or Company Name Insert Location, Virginia

More information

SECTION FILL AND BACKFILL

SECTION FILL AND BACKFILL PART 1 GENERAL 1.1 SECTION INCLUDES A. Filling, backfilling, and compacting for building volume below grade, footings, slabs-on-grade, paving, site structures, and utilities within the building. B. Backfilling

More information

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA 73171 JANUARY 06 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION GEOTECHNICAL REPORT I-15

More information

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section

More information

WILLMER ENGINEERING INC. Willmer Project No Prepared for. Clark Patterson Lee Suwanee, Georgia. Prepared by

WILLMER ENGINEERING INC. Willmer Project No Prepared for. Clark Patterson Lee Suwanee, Georgia. Prepared by SOIL SURVEY REPORT (Revised March 6, 2013) New Hospital Connector Road GDOT Project No. CSSTP-0006-00(276), PI No. 0006276 Duluth, Gwinnett County, Georgia WILLMER ENGINEERING INC. Willmer Project No.

More information

TRENCH EXCAVATION AND BACKFILL

TRENCH EXCAVATION AND BACKFILL TRENCH EXCAVATION AND BACKFILL PART 1 - GENERAL 1.01 SECTION INCLUDES A. Trench Excavation for Pipe Systems B. Trench Foundation Stabilization C. Pipe Bedding and Backfill 1.02 DESCRIPTION OF WORK A. Excavate

More information

ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 6 SANFORD, FLORIDA

ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 6 SANFORD, FLORIDA PRELIMINARY GEOTECHNICAL STUDY ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 6 SANFORD, FLORIDA November 9, 2015 Prepared For: Ms. Diane H. Crews, A.A.E. Sanford Airport Authority 1200 Red Cleveland

More information

SECTION SOILS REPORT

SECTION SOILS REPORT SECTION 02300 SOILS REPORT 1. GENERAL: 1.1 All work included under this heading shall be subject to the General Conditions of the entire operation. This Contractor is required to refer especially thereto.

More information

REPORT OF GEOTECHNICAL EXPLORATION PEPSI PLACE WATER MAIN REPLACEMENT JACKSONVILLE, FLORIDA E&A PROJECT NO CLIENT ID: 4784

REPORT OF GEOTECHNICAL EXPLORATION PEPSI PLACE WATER MAIN REPLACEMENT JACKSONVILLE, FLORIDA E&A PROJECT NO CLIENT ID: 4784 REPORT OF GEOTECHNICAL EXPLORATION PEPSI PLACE WATER MAIN REPLACEMENT JACKSONVILLE, FLORIDA E&A PROJECT NO. 35-55 CLIENT ID: 78 Prepared for: Construction & Engineering Services Consultants, Inc. 93 Baymeadows

More information

June i TABLE OF CONTENTS

June i TABLE OF CONTENTS June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description

More information

APPENDIX A DRAINAGE STUDY PHASE 2 ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE 4C IMPROVEMENTS LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC

APPENDIX A DRAINAGE STUDY PHASE 2 ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE 4C IMPROVEMENTS LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC DRAINAGE STUDY PHASE ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE C IMPROVEMENTS ` FOR: LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC APPENDIX A J-.000 Prepared by: Savannah, GA Charleston, SC Myrtle

More information

SECTION 500 STRUCTURES

SECTION 500 STRUCTURES SECTION 500 STRUCTURES 500.1 GENERAL This section defines the various construction items that are associated with the completion of a concrete, steel, timber, or masonry unit structures, or a combination

More information

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois AGI Project No. 13-276 Subsurface Investigation Report For the Proposed New Retail Center 9601 South Pulaski Road Evergreen Park, Illinois Prepared for Mr. Feras Sweis FHS Design + Build LLC 2010 West

More information

REPORT OF GEOTECHNICAL EXPLORATION GLYNN COUNTY DETENTION CENTER GLYNN COUNTY, GEORGIA E&A PROJECT NO

REPORT OF GEOTECHNICAL EXPLORATION GLYNN COUNTY DETENTION CENTER GLYNN COUNTY, GEORGIA E&A PROJECT NO REPORT OF GEOTECHNICAL EXPLORATION GLYNN COUNTY DETENTION CENTER GLYNN COUNTY, GEORGIA E&A PROJECT NO. - Prepared for: IPG Architects, Inc. Northwood Park Drive Valdosta, Georgia Prepared by: Ellis & Associates,

More information

Civil Geotechnical Surveying

Civil Geotechnical Surveying Civil Geotechnical Surveying Mr. David Burnett Cabarrus County Schools 4425 Old Airport Road Charlotte, North Carolina 28025 May 16, 2017 Reference: Geotechnical Engineering Evaluation Future PLC Site

More information

REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO A CLIENT ID: 0199

REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO A CLIENT ID: 0199 REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO. 3-6187-A CLIENT ID: 0199 Prepared for: JEA 1 West Church Street Jacksonville, Florida

More information

GEOTECHNICAL REPORT US 93 WILDLIFE UNDERCROSSINGS North of Wells, Nevada E.A July 2009

GEOTECHNICAL REPORT US 93 WILDLIFE UNDERCROSSINGS North of Wells, Nevada E.A July 2009 GEOTECHNICAL REPORT US 93 WILDLIFE UNDERCROSSINGS North of Wells, Nevada E.A. 73523 July 2009 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION GEOTECHNICAL

More information

SECTION UTILITY BACKFILL MATERIALS

SECTION UTILITY BACKFILL MATERIALS SECTION 31 23 23 UTILITY BACKFILL MATERIALS PART 1: GENERAL 1.01 SECTION INCLUDES A. Material Classifications B. : 1. Concrete sand 2. Gem sand 3. Pea gravel 4. Crushed stone 5. Crushed concrete 6. Bank

More information

SUBSURFACE INVESTIGATION & GEOTECHNICAL RECOMMENDATIONS PROPOSED MONOPOLE CELL TOWER INDIANAPOLIS, INDIANA A&W PROJECT NO: 15IN0464

SUBSURFACE INVESTIGATION & GEOTECHNICAL RECOMMENDATIONS PROPOSED MONOPOLE CELL TOWER INDIANAPOLIS, INDIANA A&W PROJECT NO: 15IN0464 SUBSURFACE INVESTIGATION & GEOTECHNICAL RECOMMENDATIONS PROPOSED MONOPOLE CELL TOWER INDIANAPOLIS, INDIANA A&W PROJECT NO: 15IN0464 PREPARED FOR: AAA DEVELOPMENT AND CONSULTING, INC GREENFIELD, INDIANA

More information

PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT

PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT Converse Project No. 15-81-177-01 Prepared For: David Evans and Associates, Inc. 17782 17th Street, Suite 200 Tustin, California 92780 Prepared By: 10391

More information

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA AREHNA PROJECT NO. B-15-008 March 11, 2015 Prepared For: City of Tampa Stormwater Division 306 W. Jackson Street, 6N Tampa, Florida

More information

5.0 SITE CONDITIONS. 5.1 Surface Conditions

5.0 SITE CONDITIONS. 5.1 Surface Conditions 5.0 SITE CONDITIONS 5.1 Surface Conditions The project site is located at approximately along Ashdown Forest Road and Nichols Canyon Road in the Fiddlers Canyon Area of Cedar City, Utah. At the time of

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 May 10, 2016 Banner Associates, Inc. 2307 W. 57 th Street, Suite

More information

Geotechnical Investigation Report

Geotechnical Investigation Report Geotechnical Investigation Report Proposed,000-Gallon Water Storage Tank Fagasa Pass Tank Upper Pago Pago, American Samoa Prepared for: ASPA Water Engineering Division Tafuna, American Samoa PO Box PPB

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

Page 4 Blythe Municipal Airport Project County of Riverside, California December 7, 2015 CTE Job No G

Page 4 Blythe Municipal Airport Project County of Riverside, California December 7, 2015 CTE Job No G Geotechnical Investigation Page 4 Blythe Municipal Airport Project County of Riverside, California December 7, 2015 CTE Job No. 40-3264G Laboratory CBR Tests Laboratory CBR tests were performed on samples

More information

Geotechnical Engineering Report Proposed Communications Tower Spain Park Site Hoover, Alabama

Geotechnical Engineering Report Proposed Communications Tower Spain Park Site Hoover, Alabama Geotechnical Engineering Report Proposed Communications Tower Spain Park Site Hoover, Alabama July 24, 2014 Terracon Project No. E1145095 Prepared for: The City Of Hoover Hoover, Alabama Prepared by: Terracon

More information

GEOTECHNICAL REPORT US 95 WIDENING ANN ROAD

GEOTECHNICAL REPORT US 95 WIDENING ANN ROAD GEOTECHNICAL REPORT US 95 WIDENING ANN ROAD to KYLE CANYON ROAD Package 2 E.A. 73627 January 212 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Milepost 210 to 218 Drainage Structure Pipe Jacking Creek County, Oklahoma July 1, 2016 Terracon Project No. 04165017 Prepared for: Benham Tulsa,

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

March 10, 2017 SITE AND PROJECT INFORMATION

March 10, 2017 SITE AND PROJECT INFORMATION March 10, 2017 Derek Hawkes, PE NASH COUNTY 120 W. Washington Street - Suite 2004 Nashville, NC 27856 Re: Report of Subsurface Investigation Middlesex Corporate Park, Lot 3 Middlesex, North Carolina GeoTechnologies

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 September 8, 2016 City of Viborg 101 N. Main Street 57070 Attn:

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Milepost 203 to 210 Drainage Structure Pipe Jacking Creek County, Oklahoma June 1, 2016 Terracon Project No. 04155197 Prepared for: Garver, LLC

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF

More information

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE 4 3 2 1 D D C C B B A A 4 3 2 1 Thrust Restraint Design Equations and Soil Parameters These equations and soil

More information

GEOTECHNICAL STUDY PROPOSED CONCRETE ROADWAY TIKI ISLAND COMMUNITY GALVESTON COUNTY, TEXAS PROJECT NO E

GEOTECHNICAL STUDY PROPOSED CONCRETE ROADWAY TIKI ISLAND COMMUNITY GALVESTON COUNTY, TEXAS PROJECT NO E GEOTECHNICAL STUDY PROPOSED CONCRETE ROADWAY TIKI ISLAND COMMUNITY GALVESTON COUNTY, TEXAS PROJECT NO. 15-945E TO VILLAGE OF TIKI ISLAND TIKI ISLAND, TEXAS BY SERVICING TEXAS, LOUISIANA, NEW MEXICO, OKLAHOMA

More information

REPORT OF GEOTECHNICAL EXPLORATION AND ENGINEERING ANALYSIS

REPORT OF GEOTECHNICAL EXPLORATION AND ENGINEERING ANALYSIS FIGURE 3 Geotechnical Report (2) REPORT OF GEOTECHNICAL EXPLORATION AND ENGINEERING ANALYSIS RIVER TOWER RESTORATION RIVER TOWER PARK TAMPA, FLORIDA AREHNA PROJECT NO. B-13-002 February 22, 2013 Prepared

More information

GEOTECHNICAL EXPLORATION FOR PROPOSED PAVEMENT IMPROVEMENTS, SIERRA MIDDLE SCHOOL, 4950 CENTRAL AVENUE, CITY OF RIVERSIDE, CALIFORNIA.

GEOTECHNICAL EXPLORATION FOR PROPOSED PAVEMENT IMPROVEMENTS, SIERRA MIDDLE SCHOOL, 4950 CENTRAL AVENUE, CITY OF RIVERSIDE, CALIFORNIA. GEOTECHNICAL EXPLORATION FOR PROPOSED PAVEMENT IMPROVEMENTS, SIERRA MIDDLE SCHOOL, 4950 CENTRAL AVENUE, CITY OF RIVERSIDE, CALIFORNIA Prepared for: RIVERSIDE UNIFIED SCHOOL DISTRICT 3070 Washington Street

More information

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133 GEOTECHNICAL EXPLORATION AND ENGINEERING SERVICES REPORT CONDUCTED FOR: Immokalee Stormwater Master Plan Implementation Immokalee, Collier County, Florida PREPARED FOR: Mr. Marc Stonehouse, P. E. Project

More information

Geotechnical Exploration and Evaluation Report

Geotechnical Exploration and Evaluation Report Geotechnical Exploration and Evaluation Report Nassau Reclaimed Water Main From Radio Avenue to Harts Road Nassau County, Florida CSI Geo Project No.: 71-17-329-04 Client Project No.: JEA 09302-049-01

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 November 2015 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT TABLE OF CONTENTS D 422.01 D 422.02 D 422.03

More information

Subsurface Environmental Investigation

Subsurface Environmental Investigation Subsurface Environmental Investigation Lake Development East Lake and 21 st Avenue South February 23, 201 Terracon Project No. MP14738A Prepared for: Minneapolis Public Schools Prepared by: Terracon Consultants,

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 November 1, 2016 City of Viborg PO Box 56 57070-0056 Attn: Lori

More information

Thi_ Qar University College of Engineering/Civil Engineering Department. Highway Lectures. Fourth Class. Part #2: - Subgrade Soil

Thi_ Qar University College of Engineering/Civil Engineering Department. Highway Lectures. Fourth Class. Part #2: - Subgrade Soil Thi_ Qar University College of Engineering/Civil Engineering Department Highway Lectures Fourth Class Part #2: - Subgrade Soil Lecture #2 Soil Classification DAS, Chapter 4, Engineering Classification

More information

Geotechnical Investigation for Navajo Gallup Water Supply Project Reach 26.3

Geotechnical Investigation for Navajo Gallup Water Supply Project Reach 26.3 Geotechnical Investigation for Navajo Gallup Water Supply Project Reach 26.3 Geo-Test Geotechnical Engineering Services Report No. 1-718 for Reach 26.3 Tank Site Geo-Test Job No. 1-718, Addendum No. 1

More information

GEOTECHNICAL ENGINEERING REPORT. KU Parking Lot 300E Southeast of Lied Center Lawrence, Kansas. Project No. D16G1696. KU No. Lz_n/11062.

GEOTECHNICAL ENGINEERING REPORT. KU Parking Lot 300E Southeast of Lied Center Lawrence, Kansas. Project No. D16G1696. KU No. Lz_n/11062. GEOTECHNICAL ENGINEERING REPORT KU Parking Lot 300E Southeast of Lied Center Lawrence, Kansas April 1, 2016 Prepared for: University of Kansas Bartlett & West Prepared by: GeoSource, LLC April 1, 2016

More information

GFA INTERNATIONAL FLORIDA S LEADING ENGINEERING SOURCE

GFA INTERNATIONAL FLORIDA S LEADING ENGINEERING SOURCE GFA INTERNATIONAL FLORIDA S LEADING ENGINEERING SOURCE Report of Geotechnical Exploration Addie s Corner Entry Bridge and Lake Areas 8799 Immokalee Road Naples, Collier County, Florida October 26, 2016

More information

ADDENDUM NO. 1. Clarification/Question/Answer/Updated Plan Sheets

ADDENDUM NO. 1. Clarification/Question/Answer/Updated Plan Sheets ADDENDUM NO. 1 DATE: July 20, 2016 INVITATION FOR BID: IFB K160021767 Bellemeade Park Pedestrian Trails and Bridge Project (UPC 107531) DATED: June 28, 2016 RECEIPT DATE: July 28, 2016 @ 2:30 P.M. OPENING

More information

Results of Onsite Percolation Testing Ellis Commons Senior Housing Development APN City of Perris, California

Results of Onsite Percolation Testing Ellis Commons Senior Housing Development APN City of Perris, California Lansing Companies 12671 High Bluff Drive, Suite 150 San Diego, California 92130 April 18, 2017 Project No. 11607.001 Attention: Subject: References: Mr. Casey Malone Results of Onsite Percolation Testing

More information

LETTER OF TRANSMITTAL AS REQUESTED FOR REVIEW AND COMMENT FOR APPROVAL PLEASE RECYCLE

LETTER OF TRANSMITTAL AS REQUESTED FOR REVIEW AND COMMENT FOR APPROVAL PLEASE RECYCLE 199 Highland Vista Dr., Suite 170 (703) 726-8030 www.geoconcepts-eng.com TO: LETTER OF TRANSMITTAL Mr. Rob McGinnis FASLA FROM: Rebecca L. Smith-Zakowicz, CPG 108 Second Street, SW, Unit #36 Charlottesville,

More information

April 21, Odom Investments, Inc. Attn: Mr. Jerry Odom 7100 Westwind Dr., Suite 230 El Paso, TX 79912

April 21, Odom Investments, Inc. Attn: Mr. Jerry Odom 7100 Westwind Dr., Suite 230 El Paso, TX 79912 April 21, 2016 Odom Investments, Inc. Attn: Mr. Jerry Odom 7100 Westwind Dr., Suite 230 El Paso, TX 79912 Re: GEOTECHNICAL ENGINEERING REPORT Proposed San Elizario Retail Center Socorro Road & Chicken

More information

GEOTECHNICAL ENGINEERING REPORT

GEOTECHNICAL ENGINEERING REPORT GEOTECHNICAL ENGINEERING REPORT PROJECT MINECRAFT ACCESS ROAD BOYDTON PLANK ROAD DINWIDDIE COUNTY, VIRGINIA JOB NUMBER: 37775.003 PREPARED FOR: DINWIDDIE COUNTY PO BOX 70 DINWIDDIE COUNTY, STATE 23841

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Parking Lot Evaluation & Physical Plant Additions Rogers State University Claremore, Oklahoma May 20, 2015 Terracon Project No. 04155080 Prepared for: Rogers State University

More information

ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 1 SANFORD, FLORIDA

ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 1 SANFORD, FLORIDA PRELIMINARY GEOTECHNICAL STUDY ORLANDO SANFORD INTERNATIONAL AIRPORT OUTPARCEL 1 SANFORD, FLORIDA November 9, 2015 Prepared For: Ms. Diane H. Crews, A.A.E. Sanford Airport Authority 1200 Red Cleveland

More information

B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form.

B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form. City of Casper Baler Building / MRF Expansion DOCUMENT 9113 ADDENDUM.1 ADDENDUM NUMBER: 1.2 PROJECT INFORMATION A. Project Name: Baler Building / MRF Expansion B. Owner: City of Casper C. Architect: Hein

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 October 28, 2016 City of Vermillion 25 Center Street 57069 Attn:

More information

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit

More information

August 3, 2018 TTL Project No Supplemental Test Borings Cleveland Bulk Terminal Cleveland, Ohio

August 3, 2018 TTL Project No Supplemental Test Borings Cleveland Bulk Terminal Cleveland, Ohio 1915 North 12 th Street Toledo, OH 43604-5305 T 419-324-2222 F 419-241-1808 www.ttlassoc.com August 3, 2018 TTL Project No. 1706701 Mr. Vito Melilli Coastal Engineer KS Associates, Inc. 260 Burns Road,

More information

Geotechnical Engineering Study

Geotechnical Engineering Study Geotechnical Engineering Study SAWS Service Road Brackish Desalinization Production Well Services Package I Bexar County, Texas Arias Job No. 09-1122 Prepared For LBG Guyton & Associates March 9, 11 TABLE

More information

REPORT GEOTECHNICAL STUDY PROPOSED 8-WARD YSA MEETINGHOUSES APPROXIMATELY 1345 EAST 1100 NORTH LOGAN, UTAH LDS PROPERTY NUMBER:

REPORT GEOTECHNICAL STUDY PROPOSED 8-WARD YSA MEETINGHOUSES APPROXIMATELY 1345 EAST 1100 NORTH LOGAN, UTAH LDS PROPERTY NUMBER: REPORT GEOTECHNICAL STUDY PROPOSED 8-WARD YSA MEETINGHOUSES APPROXIMATELY 1345 EAST 1100 NORTH LOGAN, UTAH LDS PROPERTY NUMBER: 500-6455 Submitted To: The Church of Jesus Christ of Latter-Day Saints Butler

More information

GEOTECHNICAL REPORT B-1942

GEOTECHNICAL REPORT B-1942 GEOTECHNICAL REPORT TUSCARORA BRIDGE REPLACEMENT B-1942 E.A. 73561 March 2011 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION GEOTECHNICAL SECTION GEOTECHNICAL REPORT

More information

GEOTECHNICAL SUBSURFACE DATA REPORT

GEOTECHNICAL SUBSURFACE DATA REPORT GEOTECHNICAL SUBSURFACE DATA REPORT SC-41 REPLACEMENT BRIDGE OVER MAIDEN DOWN SWAMP MARION COUNTY, SOUTH CAROLINA PREPARED FOR Mr. Joshua Meetze, E.I.T. RPG-2 GDS South Carolina Department of Transportation

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering DATE: August 31, 2000 Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM EMI PROJECT NO: 99-136 PREPARED FOR: COPIES: PREPARED BY: Tayfun Saglam / Parsons Brinckerhoff Juan

More information

DIVISION 4100 SITEWORK

DIVISION 4100 SITEWORK DIVISION 4100 SITEWORK SECTION 4115 EARTHWORK PART 1 - GENERAL 1.01 SCOPE This section covers the grading and compaction of excavations, embankments, structural foundations, and planted areas. 1.02 REFERENCES

More information

Subsurface Investigation and Geotechnical Engineering Report Proposed Volvo Dealership 1022 Hingham Street Rockland, Massachusetts

Subsurface Investigation and Geotechnical Engineering Report Proposed Volvo Dealership 1022 Hingham Street Rockland, Massachusetts HML ASSOCIATES Geotechnical and Civil Engineers March 31, 17 19 Rockwood Road Hingham, MA 43 (Phone/Fax)781-74-9999 Mr. Joe Rose Prime Motor Group 42 Providence Highway Westwood, MA 9 RE: Subsurface Investigation

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

Report of Geotechnical Study

Report of Geotechnical Study Report of Geotechnical Study Albemarle County, Virginia F&R Project No. 71T0082 Prepared For: Office of Facilities Development 401 McIntire Road, Room 228 Charlottesville, Virginia 22902-4596 Prepared

More information

Report of Exploratory Test Pits

Report of Exploratory Test Pits Report of Exploratory Test Pits UNF Transportation Projects Stockpile Investigation Osprey Ridge Road Extension Jacksonville, Florida CSI Geo Project No.: 71-17-135-20 Arcadis Project No.: JK017002.0001

More information

PRELIMINARY GEOTECHNICAL INVESTIGATION UCCS ACADEMIC OFFICE BUILDING COLORADO SPRINGS, COLORADO

PRELIMINARY GEOTECHNICAL INVESTIGATION UCCS ACADEMIC OFFICE BUILDING COLORADO SPRINGS, COLORADO PRELIMINARY GEOTECHNICAL INVESTIGATION UCCS COLORADO SPRINGS COLORADO Prepared for: UNIVERSITY OF COLORADO AT COLORADO SPRINGS Facilities Services 1420 Austin Bluffs Parkway Colorado Springs Colorado 80918

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 Interstate 235 between N.W. 50th Street and Interstate 44 Oklahoma City, Oklahoma May 8, 2014 Terracon Project No. 03145071 Prepared for:

More information

Geotechnical Engineering Report

Geotechnical Engineering Report The Residence at Yukon Hills Cornwell Drive and Vandament Avenue Yukon, Oklahoma May 20, 2016 Terracon Project No. 03165108 Prepared for: Jones Gillam Renz Architects, Inc. Salina, Kansas Prepared by:

More information

Geotechnical Investigation

Geotechnical Investigation REVISED Geotechnical Investigation Pueblo Pintado Tank Site Includes NGWSP Reaches 26.1 & 26.2 Pueblo Pintado in New Mexico Prepared for: Souder, Miller & Associates Project No.: 15-1-057 June 9, 2016

More information

November 13, Eckas Water 1514 Ambrosia Court Fort Collins, Colorado Attn: Mr. Wayne Eckas

November 13, Eckas Water 1514 Ambrosia Court Fort Collins, Colorado Attn: Mr. Wayne Eckas November 13, 2018 Eckas Water 1514 Ambrosia Court Fort Collins, Colorado 80526 Attn: Mr. Wayne Eckas (wayne@eckaswater.com) Re: Geotechnical Subsurface Exploration Walker Recharge Pipeline Project Morgan

More information

GEOTECHNICAL ENGINEERING REPORT

GEOTECHNICAL ENGINEERING REPORT GEOTECHNICAL ENGINEERING REPORT GRAND AVENUE PEDESTRIAN BRIDGE RELOCATION ROARING FORK RIVER GLENWOOD SPRINGS, COLORADO April 18, 2016 Prepared By: Prepared For: Mr. Bob Pattillo, P.E. Pattillo Associates

More information

Geotechnical Engineering Services Report

Geotechnical Engineering Services Report Geotechnical Engineering Services Report Firgrove Elementary School Puyallup, ashington for Puyallup School District November 17, 16 Earth Science + Technology Geotechnical Engineering Services Report

More information

GEOTECHNICAL INVESTIGATION

GEOTECHNICAL INVESTIGATION GEOTECHNICAL INVESTIGATION SHEETZ CONVENIENCE STORE FREEPORT ROAD AND CALIFORNIA AVENUE NATRONA HEIGHTS, PENNSYLVANIA Prepared For: Mr. David J. Mastrostefano, P.E. Sheetz Incorporated 817 Brookfield Drive

More information

GEOTECHNICAL ENGINEERING REPORT

GEOTECHNICAL ENGINEERING REPORT GEOTECHNICAL ENGINEERING REPORT 58.6 ROAD (KIMBALL CREEK) 58.9 ROAD TO 58.7 ROAD MESA COUNTY, COLORADO February 9, 2018 Prepared By: Prepared For: Mr. Eric Krch, P.E. SGM, Inc. 744 Horizon Court, Suite

More information

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA 14-3001 - Construct Bin Wall at HERD Eglin AFB, Florida MTEC Project Number 2014-101 November 10, 2014 Revised: January 5, 2015 Prepared For: Peterson Engineering,

More information

March 28, Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625

March 28, Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625 11917 NE 95 th Street, Vancouver, Washington 98682 Phone: 360-823-2900, Fax: 360-823-2901 March 28, 2014 Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625 Re: Construction

More information

SEPA Environmental Checklist Mercer Island Center for the Arts. Attachment F Geotechnical Supplemental Memo

SEPA Environmental Checklist Mercer Island Center for the Arts. Attachment F Geotechnical Supplemental Memo SEPA Environmental Checklist Mercer Island Center for the Arts Attachment F Geotechnical Supplemental Memo January 2017 MEMORANDUM DATE: May 6, 2015 TO: FROM: RE: CC: Katie Oman, Mercer Island Center for

More information

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL Bay County Solid Waste 11411 Landfill Rd. Panama City Beach, Florida 32413 Telephone: (850) 236-2212 Fax: (850) 233-5053 Board of County Commissioners www.baycountyfl.gov Sepetember 27, 2018 Florida Department

More information

SITE GEOTECHNICAL INVESTIGATION UCCB PRODUCTION PLANT SECTION 14 & 23, T9N/R33W CAT CANYON, SANTA BARBARA COUNTY GSI SOILS INC.

SITE GEOTECHNICAL INVESTIGATION UCCB PRODUCTION PLANT SECTION 14 & 23, T9N/R33W CAT CANYON, SANTA BARBARA COUNTY GSI SOILS INC. GEOTECHNICAL INVESTIGATION UCCB PRODUCTION PLANT SECTION 14 & 23, T9N/R33W CAT CANYON, SANTA BARBARA COUNTY September 14, 2015 PROJECT 15-7159 SITE PREPARED BY: PREPARED FOR: GSI SOILS INC. ERIC VASQUEZ

More information

Geotechnical Investigation Spring Filling Station Mantua, Utah

Geotechnical Investigation Spring Filling Station Mantua, Utah 8143 South 2775 East, South Weber, Utah Phone (801) 814-1714 Geotechnical Investigation Spring Filling Station Mantua, Utah Christensen Geotechnical Project No. 112-001 June 8, 2017 Prepared for: Brigham

More information

Woodhaven Retirement Community Addition Wentworth Street Livonia, Michigan 48154

Woodhaven Retirement Community Addition Wentworth Street Livonia, Michigan 48154 Report of Geotechnical Investigation Woodhaven Retirement Community Addition 9 Wentworth Street Livonia, Michigan 81 Latitude.08 N Longitude 8.898 W Prepared for: Fusco, Shaffer & Pappas, Inc. 0 E. Nine

More information

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants SUBSURFACE SOIL EXPLORATION ANALYSIS AND RECOMMENDATIONS PROPOSED WEIRS AT STATIONS 130+00 AND 16+00 DRAINAGE IMPROVEMENTS TO THE FOUR CORNERS MSBU HENDRY COUNTY, FLORIDA Ardaman & Associates, Inc. Geotechnical,

More information

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL ENGINEERING SERVICES Elizabeth City, North Carolina G E T Project No: EC14-188G May 30, 2014 PREPARED FOR: 106 Capital Trace, Unit E Elizabeth City,

More information