Resource Center. Holy Redeemer Hospital Meadowbrook, PA

Size: px
Start display at page:

Download "Resource Center. Holy Redeemer Hospital Meadowbrook, PA"

Transcription

1 Holy Redeemer Hospital Brad Pietropola Architectural Engineering Construction Management Option Spring 2004

2 Holy Redeemer Hospital Project Team Owner Holy Redeemer Health System Occupant Holy Redeemer Hospital Architect Francis, Cauffman, Foley, Hoffmann Contractor P. Agnes Inc. MEP Engineer Wick, Fisher, White Mechanical One new AHU added on roof 19,000 cfm for present use 24,000 cfm for future use Some mechanical risers remaining and need to be coordinated with new construction. Variable Air Volume system. Project Overview Meadowbrook, Pa Renovation of areas of an existing hospital 20,000 sq ft 1.7 million dollars Expected completion date May story project Hospital will remain open during construction, so many codes need to be followed. (ICRA) Electrical Switchgear reduces power to 480/277V 10 new panelboards added 5 are 480/277V 3 wire 4 phase 5 are 208/120V 3 wire 4 phase Plumbing 3 pumps added One has 140 gpm capacity One has 290 gpm capacity Pipes need to be relocated to coordinate with new mechanical equipment All plumbing fixtures to be replaced Brad Pietropola Construction Management Current Hospital Courtesy of Holy Redeemer Hospital Lighting Fluorescent and incandescent lighting Combination wall and ceiling mounted as well as direct and indirect fixtures Structural Steel Structure Non-Bearing Brick and glass Façade

3 Table of Contents Executive Summary... 4 Acknowledgements... 5 Proposal Letter... 6 Introduction and Project Background. 7 Existing Conditions 9 Estimate Summary.. 12 Summary Schedule. 13 Cash Flow Curve. 15 Investigation Areas.. 16 Depth: Re-Phasing.. 16 Breadth: Mechanical Redesign Breadth: Construction Coordination Conclusions References Appendix A Construction Management 3 Senior Thesis

4 Executive Summary Enclosed is my thesis project on the at Holy Redeemer Hospital in Meadowbrook PA. This is phase one of a master plan to update the hospital facilities and bring it into the technology age. Holy Redeemer Health Services selected Francis, Cauffman, Foley, Hoffmann as the architect on the project. P. Agnes was selected as the general contractor of the project. The project is a 1.7 million dollar project and is scheduled to be completed in 10 months. This report represents a yearlong study into the construction of this project. The first section outlines the parameters in which the project was planned, designed and constructed. This section is the existing conditions of the construction project. The second section analyzes the project in terms of cost, constructability, schedule, and minimal disruption to the operating hospital. These areas were investigated and compared to the existing conditions and construction procedures in the first section. Topics Research and applied to this thesis: Infection Control Risk Assessment (ICRA). Re-Phasing the project VAV boxes compared to remote reheat coils Better construction Coordination Plan I chose to re-phase the project to help with the ICRA steps that must be taken. This rephasing created a cost savings of $26,827, as well as a 12-day reduction in the project s duration. I next took a look into re-designing the mechanical system. I chose to replace the some of the re-heat coils with variable air volume boxes. Although the cost of materials and installation are very similar with the two materials, I believe a greater comfort level can be achieved with the VAV boxes. The final analysis in this report looks into a construction coordination plan. The current productivity of the project is below what they expected. I believe this is due to a lack of coordination. With a better coordination contractors will no longer have to work around other contractors materials on the site, which will result in a cost and time savings. Construction Management 4 Senior Thesis

5 Acknowledgements I would like to thank the following people. Without their help and support thesis would not be possible. Penn State Faculty o Dr. David Riley o Dr. Moses Ling P. Agnes. o Joe Osifchok o Sue Harkins o Kevin Cahill Holy Redeemer Health Services o Jack Dempster o Gail Latimer o Esther Malazita Francis, Cauffman, Foley Hoffmann o Ken Granderson Wick, Fisher, White o Bruce Gessner My family for their love and support throughout my educational career. My friends in and out of AE for being there when I needed them. Construction Management 5 Senior Thesis

6 Brad Pietropola 709 W. College Ave. State College, PA April 5, 2004 Jack Dempster Holy Redeemer Hospital 1648 Huntingdon Pike Dear Mr. Jack Dempster: Proposal Letter I appreciate the opportunity to submit these proposed alternatives for the Resource Center project. Many considerations were taken when analyzing the schools current system. The analysis began with a look into the Infection Control Risk Assessment requirements and steps. I look into providing a different phasing plan to reduce the steps that need to be taken on this project. During the analysis I took into account the hospital operations. I found that by re-phasing the project you could reduce the cost of the project as well as shorten the duration of the project. I also looked into providing more comfort for the hospital employees, patients and visitors of the hospital. This was achieved by redesigning the mechanical system of the hospital. Variable air volume boxes instead of the current reheat coils will provide individual control for each room. Although the cost of the proposed system is a bit higher I believe it will be offset with the added comfort and control of the system. Finally I analyzed the construction on the project. I believe a construction coordination plan will increase the workers productivity. This plan will require a couple of easy steps, as well as all the contractors cooperation. This plan will increase the productivity, which in turn will save time and money on the project. I hope you are pleased with the thoroughness of this report, and take into consideration my proposed alternatives. If you have any questions please do not hesitate to contact me. I look forward to working with you and Holy Redeemer Hospital. I want to thank you again for considering these alternatives Sincerely Brad W Pietropola Brad Pietropola Construction Management 6 Senior Thesis

7 Building Name Holy Redeemer Hospital Project Name Location Meadowbrook, Pennsylvania Introduction and Background Site The is a renovation of an area of a hospital. Holy Redeemer hospital is located on an urban site outside of Philadelphia. There is also a medical center located on the site, which is connected to the hospital. The renovation area is located in the current hospital. Occupancy The building contains a hospital. The project is a renovation of an old kitchen and cafeteria that are no longer in use, and areas surrounding it. They are constructing many different spaces in this area. The main areas they are constructing are a resource center, which can be used for research. They are also constructing a medical library for the hospital, and a computer room for use by visitors and patients. Another area of the project includes renovating an existing auditorium. They will also remodel the preamble to the auditorium. Size 20,000 sf will be remodeled Dates of construction November 2003 August 2004 Actual Cost Information Total project cost approximately 1.7 million. Project Delivery Method Design-Bid-Build Design and Functional Components The purpose of the renovation is to provide some areas that the hospital is currently lacking as well as upgrade some current areas. The auditorium will be upgraded with a new stage and new seats. The walls and floors will also be renovated. In the other areas of renovation, a resource center, computer rooms, and a medical library will be constructed. These areas are made with materials such a cherry wood trim, cherry wood Construction Management 7 Senior Thesis

8 doors and cherry panels in many areas. The hospital wants this area to look very elegant and nice. Codes ICRA (Infection Control) Since the area to be renovated is part of the building many precautions must be taken so that the hospital doesn t become contaminated. One of the major precautions taken to insure infection control is that at all times during the project the area being renovated will be at negative pressure compared to the hospital. This prevents the air from the renovation area to move into the hospital. Some other requirements during the renovation are minimal noise and to minimize vibration. Project Team Owner Holy Redeemer Health Services Jack Dempster Purchase Order Stipulated Sum Basis: AIA B141 Basis: AIA A The bidders were narrowed down to two firms then the final price was negotiated Architect Francis, Cauffman, Foley, Hoffman Ken Granderson General Contractor P. Agnes Inc Joe Osifchok MEP Engineer Wick, Fisher, White Bruce Gessner Construction Management 8 Senior Thesis

9 Existing conditions This project is the renovation of an existing hospital. The project is a renovation of an old kitchen and cafeteria that are no longer in use, and areas surrounding it. They are constructing many different spaces in this area. The main areas they are constructing are a resource center, which can be used for research. They are also constructing a medical library for the hospital, and a computer room for use by visitors and patients. Another area of the project includes renovating an existing auditorium. They will also remodel the preamble to the auditorium. The project is currently a 3-phase project. The project also has a phased occupancy by the hospital. This makes staying on the schedule very important. They have many activities that can t be rescheduled and will need the use of the facilities in the construction area. Phase 1 Phase 1 consists on renovation of the hallway areas. There are many offices that can only be accessed by these hallways being renovated. The intention of the hospital is to have all these offices occupied. Some of the offices along this hallway to be renovated will be receiving minor modifications. An example of this is one of the offices is having a wall reconfigured. This will require the office to have new carpet ceiling and a new coat of paint. During phase 1 of the construction, hospital personnel will occupy Phase 2 and Phase 3. Personnel working inside the construction area, which includes the phase 2 and phase 3 as well all of the offices along the hallways being renovated, have a lot of issues with the construction. These scheduling issues will be worked out on a case-by-case basis. Figure #1: Phase 1 in yellow. Construction Management 9 Senior Thesis

10 Phase 2 Phase 2 consists of construction the resource center and medical library for the hospital. This phase will begin construction after Phase 1 is complete. This area consists of a total renovation. Figure #2: Phase 2 in yellow. Construction Management 10 Senior Thesis

11 Phase 3 Phase 3 consists of the remodeling of the hospital auditorium. Along with this remodeling they will be destroying a brick wall, which was the exterior wall of the original hospital. They will also be removing the steel stage that is currently in place and replacing the current chairs. The stretch fabric system that is being installed on the walls must be watched carefully because if dust is present it can be caught in the fabric and jeopardize the IAQ of the hospital. Figure #3: Phase 3 in yellow. Infection Control Risk Assessment Since the project is a renovation of an existing hospital, infection control becomes a major concern of the project. Most patients are very susceptible to disease due to their weakened immune systems. Steps must be taken to ensure that these patients are not affected by the construction taking place in areas of the hospital. They can t be coming in contact with the air-borne dust or other air-borne bacteria generated from the construction activities. There are special regulations that all hospital renovations must follow to ensure the patients safety. The Department of Health (D.O.H.) has established an Infection Control Risk Assessment (ICRA) rating that is used on all hospital renovations. This rating determines the amount Construction Management 11 Senior Thesis

12 of precautions that must be taken due to a number of circumstances. The area of the hospital where the construction is to take place, the type of patients in the area, and the type of construction activities determines the rating class assign to the renovation. Once the class of the project is determined there are certain regulations that must be completed for each class of project. These regulations require certain steps to be taken before construction can start, during construction, and when construction is complete. Estimate Summary Chart #1: Estimate Summary Description Of work Value General Conditions $162,834 Demolition $77,500 Architectural Woodwork $116,010 Roofing $7,339 Caulking $1,420 Doors/Frames/Hardware $52,075 Glazing $13,000 Drywall $170,450 Ceramic Tile $98,480 Carpet $31,700 Painting $11,300 Toilet Partitions $2,875 Toilet Accessories $1,700 Floor Mat $985 Wall Protection $52,301 Blinds $2,790 Marker Boards $1,550 Projection Screen $2,050 Folding Partitions $11,438 Fabric Panels $20,675 Cut/Patch $5,000 HVAC $542,000 Sprinkler $20,158 Electrical $264,000 Patching - Allowance $2,500 Seating - Allowance $5,000 Elevator Doors - Allowance $7,500 Permit $26,670 TOTAL $1,711,300 Construction Management 12 Senior Thesis

13 Summary Schedule Figure #4: Summary Schedule. Construction Management 13 Senior Thesis

14 Figure #4: Summary Schedule (cont d) Construction Management 14 Senior Thesis

15 Cash Flow Curve Figure #5: Cash Flow Curve The cash flow has a spike during the month of January. The main reason for this is because the air-handling unit is being delivered during this month. This adds extra costs to the construction activities going on. This is also the month where most of the work for Phase 1 is taking place. March is a low month because during this month one phase is being completed and the next one started. Construction Management 15 Senior Thesis

16 Investigation Areas Depth Study: Re-Phasing The Project is a Phased project. The main focus of this analysis is rephasing the project with ICRA requirements in mind. I am looking to reduce the cost of these ICRA requirements by re-phasing the project. Currently the project is a three-phase project with all phases being Class III. With my analysis I am going to make the project a two-phase project with one phase remaining Class III while the other will be reduced to a Class II. This will allow for both a cost savings and a schedule reduction. When rephasing the project I also took into account hospital operations and activities as well as minimizing disruptions. Infection control has become a very important issue in the renovations of hospitals and other healthcare facilities. Some patients with weakened immune system have a high death rate when they come into contact with certain bacteria. The cost of the ICRA steps is very minimal to the costs that would be inferred due to the lost of a life of a patient at the hospital. Infection Control Risk Assessment Since the project is a renovation of an existing hospital, infection control becomes a major concern of the project. Most patients are very susceptible to disease due to their weakened immune systems. Steps must be taken to ensure that these patients are not affected by the construction taking place in areas of the hospital. They can t be coming in contact with the air-borne dust or other air-borne bacteria generated from the construction activities. There are special regulations that all hospital renovations must follow to ensure the patients safety. The Department of Health (D.O.H.) has established an Infection Control Risk Assessment (ICRA) rating that is used on all hospital renovations. This rating determines the amount of precautions that must be taken due to a number of circumstances. The area of the hospital where the construction is to take place, the type of patients in the area, and the type of construction activities determines the rating class assign to the renovation. Once the class of the project is determined there are certain regulations that must be completed for each class of project. These regulations require certain precautions to be completed before construction can start, during construction, and when construction is complete. ICRA Class and Precautions There are four different classes that a project can be. The higher number the project the more steps that must be taken to ensure infection control. To help determine which class a project will be there is a matrix of charts that can be used. With these charts there are a Construction Management 16 Senior Thesis

17 number of steps to determine what class your project is and what precautions must be taken. Step #1: Use Chart #2 to identify the type of construction project activity. Step #2: Use Chart #3 to identify the patient risk groups that will be affected. Step #3: Use Chart #4 to match the type of construction project activity with the patient risk group to find the construction project type. Step#4: Use Chart #5 to determine the required Infection Control precautions by Class. Step #1: Type of Construction Project Activity. Chart #2: Use the following chart to identify the Type of construction Project Activity The Project is a complete renovation. They are replacing both the floor and ceiling tiles. They are also demolishing the walls and construction new ones. They are also installing a new AHU and the ducts that will serve the area. With these activities taking place the Project is a Type C project. Construction Management 17 Senior Thesis

18 Step #2: Patient Risk Group Chart #3: Use the following chart to determine the Patient Risk Group *If more than one risk group will be affected, use the higher risk group. The resource center is renovating an office area. There are no patients located in the area. This makes most of the project a Low Risk Patient Group. However on the first floor where the construction project is taking place is the hospital s Cancer Care Unit where patients are located and treated. Since this area borders one part of the construction project that area of the project is considered a High Risk Patient group. Therefore the project has 2 different risk groups and the higher risk group must be used. Step #3: Construction Project Type Chart #4: Use the following chart to match the type of construction project activity with the patient risk group to find the construction project type. The Project is a Type C project. It also has HIGH Risk Group located next to the one area. If you match these two up in the chart it says the project will be a Class III or Class IV project. Since the High Risk patients are bordering the project and not located in the construction area, the Project was classified as a Class III project. Construction Management 18 Senior Thesis

19 Step #4: Infection Control Precautions Chart #5: Use the following chart to determine the required Infection Controlled precautions. This chart lets you determine the precautions you must take on your construction project depending on what class your project is. Since the is a Class III project there are many projects that must be taken during and after construction. Construction Management 19 Senior Thesis

20 Infection Control Construction Permit For Class III and Class IV projects, the Department of Health must be notified about the details of the renovation. To notify the D.O.H. you must submit an Infection Control Construction Permit (Figure #6) to the Department of Health. It is also required that they come inspect that the proper precautions are taken on the site before construction can start. During this inspection they determine that all required precautions listed in Chart #4 are completed. If all precautions are fulfilled the inspector will sign the permit. This permit must be completed and approved by the D.O.H. before the construction project can begin. Figure #6: The permit that must be submitted to notify the Department of Health of the construction project that will be taking place. Construction Management 20 Senior Thesis

21 Current Phasing Plan Currently the is a 3-phase project. The project is going to have a phased occupancy. When one phase is finished it will be opened up for use by both hospital employees as well as visitors. The renovation is a complete renovation with all the floors, walls, and ceilings being replaced. There is also a new AHU being install, which will serve the area. The air ducts in the area are also being replaced. Phase 1 Phase 1 mainly consists off all the hallways in the area. In this phase the new AHU will also be replace. Most of the work completed in this phase is the ductwork that is running through the hallways. Many of the offices along these hallways will remain occupied by employees of the hospital. Their doors will remain shut to minimize dust spreading into the offices. Phase 2 Phase 2 consists of constructing a new resource center and medical library. This area used to be an old kitchen that served the hospital cafeteria. There are many windows and wood finishes that must be installed during this phase. Phase 3 Phase 3 consists of renovating an existing auditorium as well as the break out area. The main operation taking place in this area is breaking through a wall, which used to be the exterior of the hospital, to create a door into the auditorium. They are also installing a new high tech audio/visual system in the area. As with the resource center area, the auditorium will also have a lot of elegant wood finishes. ICRA There are many steps that must be taken for the entire project in terms of the ICRA requirements. Figure #7: 6-Mil polyethylene sheeting Steps taken during Construction: Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system. o On the resource center project they must cap the ductwork as it passes between a phase that is completed and one that is still under construction. Complete all critical barriers, i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins. Construction Management 21 Senior Thesis

22 o For the project they are using 2 sheets of 6-mil clear polyethylene sheeting, which is run from floor to ceiling and completely sealed around the edges. They must place this barrier around the current phase to completely enclose the construction area (Figure #7). Doors that won t be used must also be sealed with duct tape to ensure that no air-borne particles pass by it. Maintain negative air pressure within work site utilizing HEPA-equipped air filtration units. o The project has CFM HEPA filter exhaust fans, which are run to keep the project at the required negative pressure. Contain construction waste before transport in tightly covered containers. Cover transport receptacles or carts. Tape covering unless solid lid. Steps taken after construction is complete: Do not remove barriers from work area until completed project is inspected by the owner s Safety Department and Infection Control Department and thoroughly cleaned by the owner s Environmental Services Department. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction. Vacuum work area with HEPA-filtered vacuums. Wet mop area with disinfectant. Remove isolation of HVAC system in areas where work is being performed. Figure #8: Current Phasing Plan Construction Management 22 Senior Thesis

23 Proposed Phasing Plan Phase 1 The main reason for the re-phasing of my project is the ICRA requirements. The proposed phasing plan is a 2-phased project. The first phase will consist of phase 2 of the old phasing plan as well as half of phase 1. This phase of the project contains all areas close to the cancer care unit. This unit will still be a Class III ICRA project and will require all the precautions for that class. Phase 2 This phase of the project contains the auditorium, which is phase-3 of the current plan as well as most of the hallways. It was split up this way because this area has a lower patient risk group. Since the Cancer Care Unit or any other patients are located near this area the Patient Risk group is now a low risk group. If you go back to Chart #3 you can now see that this phase can be classified as a Class II project. This will require fewer precautions to be taken during this phase. Figure #9: Proposed Phasing Plan Construction Management 23 Senior Thesis

24 ICRA The requirements that must be fulfilled during phase 1 of the proposed phasing plan are the same that must be fulfilled during the entire project in the current phasing plan. The advantages for the ICRA requirements are very numerous during phase 2 of the project. Since phase 2 is only a Class II project there are less requirements. With the proposed new phasing plan the ICRA steps must be fulfilled. The two attached floor plans for phase 1 and phase 2 show the ICRA precautions for each phase. Steps taken during construction: Provide active means to prevent airborne dust from dispersing into atmosphere. o The use of 1 sheet of polyethylene sheeting from the floor to the ceiling in various locations will be enough to prevent airborne dust from spreading throughout the hospital. Water mist work surfaces to control dust while cutting. Seal unused doors with duct tape. o Although most of the doors will be in use by employees or visitors there are a few that will be sealed shut with duct tape. Block off and seal air vents. o On the resource center project they must cap the ductwork as it passes between a phase that is completed and one that is still under construction. Place dust mat at entrance and exit of work area Remove or isolate HVAC system in areas where work is being performed. o On the resource center project they must cap the ductwork as it passes between a phase that is completed and one that is still under construction. Steps taken after construction is complete: Wipe work surfaces with disinfectant. Contain construction waste before transport in tightly covered containers. Wet mop and/or vacuum with HEPA-filtered vacuum before leaving work area. Remove isolation of HVAC system in areas where work is being performed. Construction Management 24 Senior Thesis

25 Figure #10: ICRA steps for proposed phase 1 Construction Management 25 Senior Thesis

26 Steps no longer required during phase 2: The airtight barriers around the construction site that are required in a Class III project are no longer required. This will save on both time and money to install and maintain these. The project area doesn t need to be kept at a negative air pressure. The HEPA filter exhaust fans will no longer need to be run for this phase of construction. These fans require constant monitoring. The filters also must be changed frequently depending on the type of activities being performed and how much dust they generate. Figure #11: ICRA steps for proposed phase 2 Construction Management 26 Senior Thesis

27 Advantages There are many advantages that will result from my proposed phasing plan The reduction from 3-phases to 2-phases will reduce the number of inspections that must take place. This is turn will be a result of a schedule reduction. With the ICRA requirements there are a number of inspections that must take place before and after all phases of construction and having them only occur twice instead of 3 times will result in a reduction The current phasing plan has most of the mechanical ducts and piping run during phase 2. This will allow the mechanical contractor to get most of his work done continuously which will be more effective than having him come back during all phases of construction. Although he will still have mechanical work to do in other stages he will get the long duct runs and connecting to the AHU done during one mobilization. The effect on visitor and employee traffic is less extreme. With the current phasing plan all the elevators in the section of the hospital where the construction is taking place will be closed during phase 1. Along with the elevators all of the hallways are also being renovated during the same time. With the new phasing plan at least two of the elevators will be able to stop on the floor of the construction. This will ease the visitor and employee circulation throughout the floor. In the new phasing plan all of the hallways aren t being completed at the same time so the pedestrians will be able to circulate more. When most of the hallways are being complete the project is only a Class II project. In a Class II project the project doesn t have to be completely closed off and people are able to walk through the project, which will allow visitors to continue to use these hallways although they are under construction. This may be detrimental to the workers of the construction project, but minimal disruption to the hospital operations is the number one objective. Construction Management 27 Senior Thesis

28 Cost Comparison The analysis of cost savings is mainly going to focus on the ICRA precautions that must be taken. This cost analysis will also only look into the bigger cost savings items. The new phasing plan will result in small cost savings with the polyethylene sheeting required around the construction site. With the project being reduced from a 3 phase to a 2-phase project, there will be less sheeting to be placed and removed. Also in a Class II project you only need one layer of sheeting and it doesn t need to be maintain and watched as closely as a phase 3 project. The cost of a 10 x 100 of clear polyethylene sheeting costs $ With a 2 million dollar project these material cost savings are very minimal. There will also be saving occurred due to other steps that won t be required. These savings will mainly occur in timesavings due to not having to complete the tasks. These tasks include covering all material before transporting as well as changing the filters in the HEPA exhaust fans. HEPA Vacuums On an ICRA regulated project the site is required to be vacuumed by an HEPA filtered vacuum. Class III projects the construction area is required to be vacuumed daily. Class II projects the construction area is only required to be vacuumed at the completion. The HEPA vacuum used on this project is a 55-galloon wet/dry vacuum. The rental costs of these vacuums are: Figure #8: HEPA filter exhaust fan Daily...$36 Weekly..... $108 Monthly $325 HEPA Filter Exhaust Fans A class III ICRA project requires the project to be kept at negative pressure throughout the construction project. On the resource center project this is done using 2 HEPA Filter Exhaust Fans. These fans are 2000 CFM units. The rental cost for these units are $450/month each plus the cost of the pre filter and HEPA filter. The cost of a pre-filter is $30/each. The cost of a HEPA filter is $180/each. Construction Management 28 Senior Thesis

29 Depending on the demo/type of project that is being done the filters get changed out often. It is hard to estimate per job the change out schedules. For this cost analysis I estimated they would get changed once per week. Chart #6: Cost comparison for the ICRA precautions. Total Current Phasing Plan.. $30,310 Total Proposed Phasing Plan...$9663 Total ICRA Savings with Proposed Plan..$20,647 These cost savings by changing phase 2 to a Class II project are very significant. Most of these savings are occurred because the HEPA filter exhaust fans are no longer needed. It is a major cost to keep the project at a negative pressure. Construction Management 29 Senior Thesis

30 Schedule Comparison This comparison is going to look into the timesavings of reducing the project from a 3- phase project to a 2-phase project. There are a lot of extra steps that must be completed during an ICRA regulated job. These steps add duration onto the project length Each phase requires Temporary Protection and ICRA requirements to be set up. o This setup is 5 days in length for each phase to be started. Each phase requires inspections by the hospital before construction can begin o The hospital inspections duration is 2 days. Each phase requires inspections by the Department of Health to ensure ICRA precautions before construction can begin. o These inspections take a day to complete The D.O.H must also inspect the project after a phase is complete and the area must be turned over to the owner o This inspection and owner turnover takes 1 day. Each phase also requires a thorough cleanup at the end of each phase to prepare for the D.O.H. inspections. During this cleanup time no work can be completed. o The final cleaning depends on the size and type of work taking place in the phase. Construction Management 30 Senior Thesis

31 Figure #9: Current Schedule. Construction Management 31 Senior Thesis

32 Figure #9: Current Schedule (cont d). Construction Management 32 Senior Thesis

33 Figure #10: New phasing plan schedule. Construction Management 33 Senior Thesis

34 Figure #10: New phasing plan schedule (cont d). Construction Management 34 Senior Thesis

35 Total duration during each phase for ICRA regulations Temporary Protection.5 days Hospital Inspection 2 days D.O.H. Inspection before construction.. 1 day DOH Inspection after completion.. 1 day Phase Cleanup 3 days Total Time Saved. 12 days The time saved due to reducing the number of phases from 3 to 2 is over 2 workweeks. Since this project is only an 8-month project this schedule reduction is very significant. This timesaving of 2 weeks will also result in a cost savings for the general conditions. The general conditions total cost is $132,824 without the ICRA equipment and precautions included. I am not including these in this cost savings because the cost savings of them is already discussed in the previous section. The general conditions can be broken down into a weekly cost of $3090/week. The cost savings of this reduction will then be $6180. Construction Management 35 Senior Thesis

36 Additional Reduction The new proposed schedule also includes more schedule reduction. The current project schedule has a completion date of August 27 th 2004 The proposed project schedule has a completion date of July 29 th 2004 With these two dates the project schedule also has been reduced by an extra 9 days above the ICRA savings. This reduction is due to the changing of the critical path. The areas of the hospital are now included in different phase, which cause the critical path to change for the better. These savings are not as guaranteed due to the uncertainty of the percentages of work completed in each stage. I have just estimated the amount of work that will be done in each stage from the drawing and the current schedule. Although these are certain there is a strong possibility that some of this reduction will be realized. Timesavings might also occur due to the fact that contractors will only have to mobilize 2 times instead of 3 times. They will be able to increase the amount of work done each time they are on site, which will result in better productivity and possibly a schedule reduction. Recommendation My recommendation for the project is to adopt the proposed phasing plan. The new plan realized both a cost and schedule reduction. The total cost savings are $26,827, which includes the savings from both the ICRA precautions as well as the schedule reduction. The schedule reduction solely due to the decrease in the amount of inspections and ICRA steps is 12 days. Cost Savings.. $26,827 Schedule Reduction Days Although there is both a cost savings and schedule reduction with the proposed phasing plan there are other issues that may cause this phasing plan not to work. One of the main issues is the hospital operations. Switching the time frame that the different areas will be able to be occupied may conflict with the hospital operations. The auditorium is used often by the hospital for presentations and guest speakers. Since some of the people that are speaking come in from all over the world their schedule must be adhered too. Another issue with my proposed phasing plan is the two different classes of phases. To allow one phase to be a Class III, while the other is a Class II they have to be submitted as two separate construction projects. This requires more paperwork to be submitted to the D.O.H. as well as many other organizations and companies. Construction Management 36 Senior Thesis

37 Breadth Study: Mechanical Redesign The current Mechanical system has a constant volume Air Handling Unit being installed. The area of the construction, except for the auditorium, will be connected into this AHU. The auditorium is served from an AHU that is located on the floor below and will not be included in the analysis. The mechanical system is a re-heat system. It has remote reheat coils located throughout the construction area to provided comfort to the different rooms of the hospital. These reheat coils are supplied with hot and cold water pipes. I am proposing that these re-heat coils be replaced with Variable air volume (VAV) boxes with re-heat coils and electronic controls. There are already 2 VAV boxes in the break out area of the hospital. I believe this switch won t result in any cost increases for the hospital, but will greatly increase the individual comfort for the individuals occupying the different areas. The cost of some of the VAV boxes will also be less that the cost of the reheat coils. This will help offset the high costs of the larger VAV boxes. Replacement Areas Since some areas would not be advantageous to change because they are not well suited for VAV boxes, there are only certain areas that I am changing. Some of the areas I am not changing are: The corridors. o VAV boxes don t work well in these circulation spaces and will be better served by the re-heat coils. o It is tough to analyze these spaces because you can t assign an area or volume to the individual box will supply. Areas with exterior exposure o With exterior spaces you have to be very cautious with over cooling do to heat loss to the outside. The entrance area to the hospital is one of these rooms where you have to be greatly concerned with overcooling. Replacement System Currently on the resource center project there are two VAV boxes. These boxes are Carrier model 35E. This model is a single duct unit with hot water reheat and electronic controls. The unit also has an attenuator to help reduce the sound of the system. I believe this is a very important feature due to the patients that will be on the floors above as well as to the comfort of the individuals occupying the room. Attached in Appendix A are some specifications on the Carrier 35E model along with some sizing information. Construction Management 37 Senior Thesis

38 The areas that are going to be served have a variety of different requirements. If you refer to the attached Mechanical Plan you can see the re-heat coils I plan on replacing. I have marked these units with numbers to correspond to Chart #6 and Chart #7. Chart #7: Room requirements for areas that are going to be switched to VAV boxes Room Requirements Room Area SQ. FT Room Volume (CU.FT) Actual Supply (CFM) Room Room Designation Replacement VAV Number Min. Supply Requirements Office None 425 Help Desk None & None 1220 IT Office None 175 IT Training None 1050 Medical Library 1020 & None 600 Meeting Room None 1000 Bathroom 1018 & None 90 The rooms have a variety of different supply needs. Each room varies in dimensions and supply requirements. Although none of these areas have a minimum supply requirement if necessary the 35E boxes can be set to have a minimum supply volume above zero. Chart #8: Carrier VAV boxes sizes that will be used in the various areas. VAV Boxes Max CFM Location Inlet Size 230 3, 4, , Construction Management 38 Senior Thesis

39 Cost Comparison Chart #9: Cost of Re-heat coils. Re-Heat Coils Size Quantity Material Installation Programming Total: All 8 $200 $175 $350 $5,800 Total: $5,800 The total cost of the re-heat coils that are to be replaced is $5,800. This includes the unit itself as well as $175 dollar to pay the sheet metal subcontract to hang the units. It also costs $350 dollars to program the units during air balancing tests. Chart #10: Cost of VAV boxes. VAV Boxes Size Quantity Material Installation Programming Total $175 $350 $2, $175 $350 $ $175 $350 $ $175 $350 $1, $175 $350 $775 Total: $5,970 The total cost of the re-heat coils that are to be replaced is $5,970. This includes the unit itself as well as $175 dollar to pay the sheet metal subcontract to hang the units. It also costs $350 dollars to program the units during air balancing tests. Advantages/Disadvantages There are advantages and disadvantages between the two different systems. The owner must decide which of these areas are most important to him to make the decision between the two costs. VAV Box Advantages Individual zone comfort More ability to provide individual comfort for the room Less energy costs than reheat coils o Not as much air has to be re-heated. Reheat coil reheats 100% of the air at all times where with a VAV box if its only 20% open then the reheat coil in the system only reheats 20 % of the air. See Appendix B for sketch of this condition. Construction Management 39 Senior Thesis

40 VAV Box Disadvantages The cost of the VAV system is slightly higher The VAV boxes don t work for all areas so you will have a mixed system in the hospital, which may create problems. Other areas of the hospital contain the remote reheat coils so the owner is familiar with that system. The mixed system requires the air balancing of two different systems, which will take longer and may add additional time and costs to the schedule. Recommendation I believe that the VAV boxes provide more individual comfort for the areas they are serving. Since most of these areas are individual rooms or offices I believe the occupant will achieve greater comfort with the VAV boxes. Although the cost to install and balance the mixed system will be greater, the owner has expressed that they wants a higher end area. They have wood casework and panels throughout the area. I believe these additional costs will be offset in the long run by the advantages that the VAV system provides. Construction Management 40 Senior Thesis

41 Breadth Study: Coordination Plan Currently on the resource center project there is no construction coordination plan. There is also not a site coordination plan that show s lay down areas as well as storage and work areas. There has been a major problem with remaining on schedule because of the productivity of the worker. I believe that with a construction coordination plan these problems will be eliminated. This coordination plan will include lay down and work areas during all times of the project. These laydown areas will change often as contractors move throughout the area. A weekly coordination meeting will help the contractors on the site work together and be more productive. During this meeting you can also determine areas that no contractor will be working in and other contractors can store materials in those areas. ICRA regulations The sloppiness of the materials on site is bad for dust control on the project. Since the area has to be vacuumed daily, it would be best if the hallways were free of materials. While these materials are being stored in the hallway they are also gathering dust. As you can see in Figure #9, there are ducts stored throughout the hallway with contractors working in the distance. These ducts are supposed to be dust free when they are being installed. Not only are they collecting dust being generated, but they also have not plastic or other form of protection to keep dust from getting inside them. Site Congestion Figure #11: Materials store in hallways The site for each of the phases is very congested. Since the other areas of the hospital are still in operation all the materials must be stored in the phase area that is being constructed. As you can see in the figures the materials are being placed throughout the site and causing congested. Lay down Area The project currently has no lay down area. Contractors are storing their materials in the hallways close to where they will be completing their work. One major problem arising is that the areas where contractors are storing their materials, is the other contractors need to be working in this area. These workers are not performing well due to the fact that they must either work around the materials or take time to move these materials before they start. When these contractors move the materials they are only concerned about themselves, and move the materials into an area where another contractor Construction Management 41 Senior Thesis

42 will soon be working. The contractor in that area then is required to move the material as well. The double or triple handling of materials is causing not only productivity delays, but it has contractors not working together for the good of the project. This situation is also causing materials to get misplaced. Contractors have to take time to find their materials because they have been moved at least once by contractors trying to work in an area. Although each of these delays is minimal, with a 9-month project they add up to be very important. Coordination Meeting They currently have no coordination meetings between the contractors working on the site. A coordination meeting will be beneficial for all the contractors working on the project. This project can take place either Friday afternoon or Monday mornings. Contractors who will be working on the project during the upcoming week will be required to attend this meeting. During this meeting each contractor will have to submit a schedule of where they will be working during that week. After it is determined where each contractor will be working, it will be possible to set up a site plan and assign areas where each contractor can lay down their materials with minimal disruption to the other workers. Construction Management 42 Senior Thesis

43 Phase 1 I am proposing that they use the entrance area as well the attached atrium area as a storage/work area. This area can be used to both store materials as well as contractors can set up small machines they need to perform their operations. There is also a mechanical room, which will be used to access the AHU on the roof and also house some of the ducts running throughout the area. This room is currently empty and can be used as a storage area for certain contractor materials. Since these areas aren t big enough for all contractors to store their materials, the weekly coordination plans will be very important Figure #12: Proposed coordination plan for phase 1 Construction Management 43 Senior Thesis

44 Phase 2 Phase 2 is the most restricted of the three phases. There will be many contractors working in this area at one time. If the coordination between the contractors working in this area is not good the time to complete this phase can be greatly increased. The entrance area and attached atrium area can also be used as a storage/work area during this phase too. This area can be used to both store materials as well as contractors can set up small machines they need to perform their operations. The coordination meeting will be essentially important during this phase because of the restricted area. For this phase it will be very important for contractors to try to have their materials delivered to site when they will need them. Contractors can t be storing a month s worth of materials on the site. Figure #13: Proposed coordination plan for phase2 Construction Management 44 Senior Thesis

45 Phase 3 For the auditorium phase the area outside the auditorium can be used for a work area. During the day the contractors can set up their machines outside and conduct their work out there. This area is under cover so the weather won t affect their machines or materials. The weather will also be warmer during this phase. This will be beneficial during this stage because their will be many different trades in the room. During this phase the entrance/atrium will be used solely as storage space for the materials of the contractors. Figure #14: Proposed coordination plan for phase 3 Construction Management 45 Senior Thesis

46 Deliveries Since the project is on a very constricted site, the general contractor should restrict the amount of materials a contractor stores on site. Currently contractors have materials stored that won t be needed for weeks in advance. The sheet metal contractor had all the ducts that were required for phase 1 there very early in the project and had them stored throughout the halls. I believe that each contractor should have no more than a week's worth of materials on the site at one time. If it is possible for a contractor to get more frequent deliveries of materials, then it should be recommended. Recommendations The coordination plan will be a very good idea for this project. Since the schedule is so short in duration, all delays become more important. There isn t as much time or profit on this project to offset the delays. The only step that this plan requires is a weekly meeting between all the contractors. This meeting will only last a couple hours at the most, but will benefit the project hourly. The assigned work/storage areas will also be beneficial to the project. This will give the contractors a specified placed where they know they will be able to set up their equipment. Construction Management 46 Senior Thesis

47 Conclusions My recommendation for the project is to adopt the proposed phasing plan. The new plan realized both a cost and schedule reduction. The total cost savings are $26,827, which includes the savings from both the ICRA precautions as well as the schedule reduction. The schedule reduction solely due to the decrease in the amount of inspections and ICRA steps is 12 days. Although there is both a cost savings and schedule reduction with the proposed phasing plan there are other issues that may cause this phasing plan not to work. One of the main issues is the hospital operations. Switching the time frame that the different areas will be able to occupied may conflict with the hospital operations. The auditorium is used often by the hospital for presentations and guest speakers. Since some of the people that are speaking come in from all over the world their schedule must be adhered too. Another issue with my proposed phasing plan is the two different classes of phases. To allow one phase to be a Class III, while the other is a Class II they have to be submitted as two separate construction projects. This requires more paperwork to be submitted to the D.O.H. as well as many other organizations and companies. I believe that the VAV boxes provide more individual comfort for the areas they are serving. Since most of these areas are individual rooms or offices I believe the occupant will achieve greater comfort with the VAV boxes. Although the cost to install and balance the mixed system will be greater, the owner has expressed that they wants a higher end area. They have wood casework and panels throughout the area. I believe these additional costs will be offset in the long run by the advantages that the VAV system provides. The coordination plan will be a very good idea for this project. Since the schedule is so short in duration, all delays become more important. There isn t as much time or profit on this project to offset the delays. The only step that this plan requires is a weekly meeting between all the contractors. This meeting will only last a couple hours at the most, but will benefit the project hourly. The assigned work/storage areas will also be beneficial to the project. This will give the contractors a specified placed where they know they will be able to set up their equipment. Construction Management 47 Senior Thesis

48 References Bruce Stewart, Pinchin Environmental Ltd, Health Canada Issues Standard for Construction Precautions in Hospitals. Carrier HVAC Systems 49,00.html Health Risk Technologies Inc, PERMIT. Judene, Mueller, Bartley, APIC Guidelines Committee, APIC State-of the art Report: The role of infection control during construction in health care facilities. Infection Control Risk Assessment: Matrix of Precaution for Construction and Renovation Wendes, H. Variable Air Volume Manual. Linburn GA. Fairmount Press. Prentice Hall William Turner. HPAC Interactive Engineering, Controlling Ventilation During Construction. Construction Management 48 Senior Thesis

49 Appendix A Construction Management 49 Senior Thesis

50 Construction Management 50 Senior Thesis

51 Construction Management 51 Senior Thesis

52 Construction Management 52 Senior Thesis

53 Construction Management 53 Senior Thesis

54 Construction Management 54 Senior Thesis

55 Construction Management 55 Senior Thesis

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Figure 3-6. Sample ICRA Matrix of Precautions Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step 1: Using the following table, identify the Type of Construction

More information

INFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION

INFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION INFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION Evelyn Cook SPICE.unc.edu 919 966 1304 I want to begin with the premise that patients can leave the hospital sicker than they arrived if construction

More information

Risk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration:

Risk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration: Risk Assessment and Preventive Measures Checklist for Construction and Renovation Location of Construction: Project Start Date: Estimated Duration: Project Manager (PM): Contractor(s): Infection Prevention

More information

To establish criteria for construction, renovation and maintenance regarding infection prevention and control measures.

To establish criteria for construction, renovation and maintenance regarding infection prevention and control measures. TITLE/DESCRIPTION: Construction, Renovation and Maintenance, Infection Prevention and Control Measures DEPARTMENT: All Departments PERSONNEL: All Personnel EFFECTIVE DATE: 2/08, REVISED: 2/09, 2/10, 6/11,

More information

Chilled Beams. The new system of choice?

Chilled Beams. The new system of choice? Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Josh Raphael CM Dr. Riley. Technical Report 3. Holiday Inn Express Absecon, NJ

Josh Raphael CM Dr. Riley. Technical Report 3. Holiday Inn Express Absecon, NJ Josh Raphael CM Dr. Riley Technical Report 3 Holiday Inn Express Absecon, NJ Table of Contents Executive Summary....... 2 Constructability Challenges....... 3-4 New Entry.... 3 Existing Facility..... 3-4

More information

Construction Indoor Air Quality (IAQ) Management Plan

Construction Indoor Air Quality (IAQ) Management Plan Denver School of Science & Technology Middle School 2000 Valentia Street Denver, CO 80238 Telephone: 303-643-5775 Main Fax: 303-673-5776 Construction Indoor Air Quality (IAQ) Management Plan Denver School

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

Section Asbestos Containment Procedures

Section Asbestos Containment Procedures Section Cover Page Section 02 82 05 2017-10-01 Use this Section where full containment will be required, or if a Contractor option, may be required, depending on the removal method(s) selected by the Contractor.

More information

Devin Learn Construction Management AE Senior Thesis

Devin Learn Construction Management AE Senior Thesis Devin Learn Construction Management AE Senior Thesis 5 th and 6 th Floor Fit-Out & Cardiac Elevator Addition Introduction Vs. Retro- Pre-Cast Floor System s at ICRA Partitions and Conclusions Questions

More information

Before You Start Renovating Your Bathroom

Before You Start Renovating Your Bathroom Before You Start Renovating Your Bathroom Renovating your bathroom is a great way to add value to your home both for your family s daily living and for future resale. Before you decide to go ahead with

More information

Kelly Village Apartments 3118 Green Houston, Texas 77020

Kelly Village Apartments 3118 Green Houston, Texas 77020 Kelly Village Apartments 3118 Green Houston, Texas 77020 Houston Housing Authority J. Allen Management Managing Agent Scope for Kelly Village Unit #1125 Overall Scope: Demolition, Renovation, and Restoration

More information

EPA s Lead Program Rule At-A-Glance

EPA s Lead Program Rule At-A-Glance EPA s Lead Program Rule At-A-Glance FLOW CHART 1: Do the Requirements Apply to the Renovation? If you will be getting paid to do work that disturbs painted surfaces in a pre-1978 home, apartment building,

More information

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING WWW.STOPWASTE.ORG New Addition Consider the following green remodeling options in a new addition.

More information

Element Z General Design Requirements Existing Facilities Information

Element Z General Design Requirements Existing Facilities Information Anderson Central 100B, PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

TENANT CRITERIA MANUAL INSERT PHOTO HERE

TENANT CRITERIA MANUAL INSERT PHOTO HERE G TENANT CRITERIA MANUAL GREENWOOD MALL INSERT PHOTO HERE General Growth Properties, Inc. 110 N. Wacker Drive Chicago, IL 60606 (312)-960-5000 Tenant shall supply and install an electrical meter

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Mueller Laboratory Renovation

Mueller Laboratory Renovation Mueller Laboratory Renovation Technical Report #1 By Mark Jackson Construction Management Option 9/19/14 Executive Summary The Mueller Laboratory building on the Penn State University Park campus was built

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

Mission Bernal Campus

Mission Bernal Campus Mission Bernal Campus Weekly Construction Bulletin #150 Construction Update March 6, 2017 March 12, 2017 The Mission Bernal Campus Weekly Bulletin intendeds to help inform members of the community about

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Kitchen Remodel Estimator. Contact Info: Project Summary: Design. Demo

Kitchen Remodel Estimator. Contact Info: Project Summary: Design. Demo Kitchen Remodel Estimator Thinking about remodeling your kitchen? If you would like a free bid from Excel Builders, we have provided a list of questions that will need to be filled out with detail in order

More information

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Minnesota Healthcare Engineers Association, Fall Conference Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Categories of Rehabilitation Work in Healthcare Facilities Bob Dehler, P.E. robert.dehler@state.mn.us

More information

New Montgomery County Elementary School. Construction Indoor Air Quality Management Plan IEQc3.1 IAQ Plan During Construction

New Montgomery County Elementary School. Construction Indoor Air Quality Management Plan IEQc3.1 IAQ Plan During Construction New Montgomery County Elementary School Construction Indoor Air Quality Management Plan IEQc3.1 IAQ Plan During Construction LEED certification promotes environmentally friendly buildings and sites through

More information

Executive Summary. References. TSM 371Lecture Remodeling. Why Remodel? Areas To Remodel Pitfalls Associated Costs Finished Products

Executive Summary. References. TSM 371Lecture Remodeling. Why Remodel? Areas To Remodel Pitfalls Associated Costs Finished Products TSM 371Lecture Remodeling Executive Summary Why Remodel? Areas To Remodel Pitfalls Associated Costs Finished Products References Course Textbook House Planning Handbook, MWPS-16, Second Edition, 1988.

More information

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet FLANDERS ELEMENTARY SCHOOL Located at 167 Boston Post Road, East Lyme, Connecticut the school s original structure was built in 1964 and replaced the Central Office Building as the elementary school. Two

More information

Corporate Environments

Corporate Environments Acoustics and the Impact on Corporate Environments falconproducts.com Achieving High-Quality Acoustics in Corporate Settings Knowledge is power. Here s what you need to know about sound, noise and creating

More information

FACILITIES MAINTENANCE WORKER

FACILITIES MAINTENANCE WORKER FACILITIES MAINTENANCE WORKER Summary Statement: Under supervision, is responsible for performing routine building maintenance tasks and assisting Building Maintenance Supervisor with the performance of

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

DIVISION 11 - EQUIPMENT FOOD SERVICE EQUIPMENT LABORATORY FUME HOODS. A. Design Considerations

DIVISION 11 - EQUIPMENT FOOD SERVICE EQUIPMENT LABORATORY FUME HOODS. A. Design Considerations DIVISION 11 - EQUIPMENT 11400 FOOD SERVICE EQUIPMENT A. Design Considerations 1. The A/E shall use the services of a food service equipment specialist in preparation of kitchen areas and other food preparation

More information

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

New Beautifully Designed Office Condominium Complex. Heading

New Beautifully Designed Office Condominium Complex. Heading FOR SALE DOYLESTOWN EXECUTIVE QUARTERS COMMERCIAL INDUSTRIAL INVESTMENT 2003 Lower State Road Doylestown, Bucks County, PA New Beautifully Designed Office Condominium Complex Heading PRESENTED BY: Kurt

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

Minitab Headquarters

Minitab Headquarters Minitab Headquarters State College, PA Erin E. Hess www.arche.psu.edu/thesis/eeh124 Consultant: Dr. David Riley This project delivery evaluation report researches and analyzes the agreements and commitments

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

Budget Estimate Basic Tenant Improvement

Budget Estimate Basic Tenant Improvement Building work rules, conditions and insurance: 1. Review the work rules. If they are not available no budget should be provided. 2. Hours available for construction 3. Insurance requirements 4. Entities

More information

37% 100% 100% PROJECT HIGHLIGHTS LEED Facts. Wiener Auditorium

37% 100% 100% PROJECT HIGHLIGHTS LEED Facts. Wiener Auditorium Taubman Building, 15 Eliot St., Cambridge, MA, 02138 LEED CI V2009 GOLD The is a 2,943 square foot space located in the Taubman Building of the Harvard Kennedy School of Government. The project scope includes

More information

Applying the Building Code During Design

Applying the Building Code During Design Applying the Building Code During Design A Step-By-Step Process AIA Learning Units The Salt Lake City CSI Chapter is a Registered Provider with The American Institute of Architects Continuing Education

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

PROFESSIONAL DESIGN MANUAL INDEX

PROFESSIONAL DESIGN MANUAL INDEX PROFESSIONAL DESIGN MANUAL INDEX DIVISION A--GENERAL PROJECT REQUIREMENTS... A2-A15 A.1 INTRODUCTION... A-2 A.2 CODES COMPLIANCE (VERIFY CITY REQUIREMENTS)... A-5 A.3 SPECIAL SUBSURFACE AND LAND CONDITIONS...

More information

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210)

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210) Quality Inspection 8618 London Heights San Antonio, TX 78254 Phone: (210) 240-0476 PRE DRYWALL INSPECTION REPORT Prepared For: DELETED (Name of Client) Concerning: DELETED, San Antonio, TX 78258 (Address

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Velma F Thomas Early Childhood Center

Velma F Thomas Early Childhood Center Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Draft Indoor Air Quality Regulations

Draft Indoor Air Quality Regulations Department of Environment and Labour Occupational Health and Safety Division Draft Indoor Air Quality Regulations May, 2001 These draft regulations are being distributed for public comment. They do NOT

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

Gaige. Thesis Project Proposal. The. December 13 th, 2013 Matthew Neal, Mechanical Option Stephan Treado, Advisor. Proposed System Changes

Gaige. Thesis Project Proposal. The. December 13 th, 2013 Matthew Neal, Mechanical Option Stephan Treado, Advisor. Proposed System Changes The Gaige Technology and Business Innovation Building Penn State Berks, Reading PA Thesis Project Proposal Proposed System Changes Stephan Treado, Advisor Table of Contents Executive Summary... 2 Building

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Offering the best price-performance in the industry. 1 (800) Presto Tape is a proud USA Manufacturer.

Offering the best price-performance in the industry. 1 (800) Presto Tape is a proud USA Manufacturer. Offering the best price-performance in the industry. 1 (800) 331-1373 Presto Tape is a proud USA Manufacturer. what can a company expect when choosing constant innovation? 1) Innovative ideas and technical

More information

Lead Based Paint Policy

Lead Based Paint Policy Lead Based Paint Policy 1. Guidance for the removal or maintenance of lead-based paint has undergone changes that affect the painting industry. The U.S. Department of Housing and Urban Development (HUD)

More information

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

Is Yours? Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards

Is Yours? Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards Is Yours? A home buyers guide to the energy efficiency requirements of the 2012 International Energy Conservation

More information

The Consumer s Guide to. Basement Renovations. The Consumer s Guide to Basement Remodeling Total Renovations

The Consumer s Guide to. Basement Renovations. The Consumer s Guide to Basement Remodeling Total Renovations The Consumer s Guide to Basement Renovations What Do I Create With My Basement s Space? Renovating your basement is a popular and cost-effective way to maximize existing square-footage. It is your blank

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

Building Codes and Ordinances ARC 227

Building Codes and Ordinances ARC 227 Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive

More information

CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION

CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION Chapter 1: Overview of Energy Efficient Construction 1 CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION Chapter 1 is a quick reference guide that discusses the key components and features of energy

More information

Acoustic Design Criteria

Acoustic Design Criteria Apartment Acoustics Apartment Buildings Acoustic Design Criteria Building Code of Australia: - Intertenancy walls and floors - Corridor walls and doors - Floor impact isolation - Lift, stair and core walls

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012

HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012 HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012 0 On May 16,, 2012 Hot Springs Firefighters conducted an evaluation

More information

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,

More information

Demolition Plan A1 A3. Scale: 3/32" = 1'-0" Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender.

Demolition Plan A1 A3. Scale: 3/32 = 1'-0 Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender. inc. 400-7 avenue edmonton, alberta, canada tr y t: (780) 48 47 f: (780) 48 00 e: lesnider@shaw.ca 4 door to North Common Corridor doors to door to F. H. C. Men Women ELEC/TEL UP Stairs DN F. H. C. DN

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

Dear Home Owner: Certificate Holder: Mr. xxxxxx Unit yyyyyy 3410 N. Lake Shore Drive Chicago, IL ADDITIONAL INSURED LANGUAGE:

Dear Home Owner: Certificate Holder: Mr. xxxxxx Unit yyyyyy 3410 N. Lake Shore Drive Chicago, IL ADDITIONAL INSURED LANGUAGE: Dear Home Owner: For your information, construction work can be done in the unit Monday through Saturday, during the hours of 8:00 am to 6:00 pm. Deliveries and equipment must be taken through the back

More information

Asbestos. Asbestos is a naturally occurring fibrous mineral that is mined from the earth and

Asbestos. Asbestos is a naturally occurring fibrous mineral that is mined from the earth and Asbestos What is asbestos? Asbestos is a naturally occurring fibrous mineral that is mined from the earth and found in many parts of the world. Its composition is such that it can be separated into smaller

More information

B. Protection of concrete mosaic, metals, stone, and other adjacent materials during all other work activities in related sections, below.

B. Protection of concrete mosaic, metals, stone, and other adjacent materials during all other work activities in related sections, below. GUIDELINE FOR WRITING SPECIFICATIONS WHEN USING CSP Paint Strippers Select Relevant Section Division 09900 Paints and Coatings Part 1 GENERAL 1.1 RELATED DOCUMENTS A. Work of this section shall be governed

More information

Analysis 2: Mechanical System

Analysis 2: Mechanical System Background and problem Analysis 2: Mechanical System Outpatient Medical center is a medical center for children and adolescences with developmental disabilities. It therefore requires the building to have

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information

KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner

KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner McLean, Virginia Brooke Helgesen Advisor: Dr. Chimay Anumba Construction Management PRESENTATION OUTLINE Cost/ Schedule Impact KAISER PERMANENTE

More information

Attachment 3 Statement of Work Statement PROJECT NUMBER MA DIRECTORATE OF PUBLIC WORKS FORT BRAGG, NORTH CAROLINA

Attachment 3 Statement of Work Statement PROJECT NUMBER MA DIRECTORATE OF PUBLIC WORKS FORT BRAGG, NORTH CAROLINA Request for Task Order Proposal Number: Attachment 3 Statement of Work Statement PROJECT NUMBER MA-00006-15 DIRECTORATE OF PUBLIC WORKS FORT BRAGG, NORTH CAROLINA PROJECT TITLE: Restore one Men s and one

More information

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017 Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins

More information

Presented by The National Association of Certified Home Inspectors Chicago Chapter

Presented by The National Association of Certified Home Inspectors Chicago Chapter Top 10 Defects Found in New Homes Presented by The National Association of Certified Home Inspectors Chicago Chapter - The National Association of Certified Home Inspectors 1 Top 10 New Home Defects New

More information

Building Systems and Design Elements included in SliDeRulE

Building Systems and Design Elements included in SliDeRulE Building Systems and Design Elements included in SliDeRulE No. System Subsystem Design Element 1.1.1 Foundation Deep Foundation Steel H-pile 1.1.2 Foundation Deep Foundation Steel pipe pile 1.1.3 Foundation

More information

KITCHEN REMODELS CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA (949)

KITCHEN REMODELS CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA (949) CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA 92691 (949) 470-3054 KITCHEN REMODELS A permit is required for kitchen remodels that include removal and replacement

More information

Noise Control. Commercial, Industrial, and Environmental Products and Solutions.

Noise Control. Commercial, Industrial, and Environmental Products and Solutions. Noise Control Commercial, Industrial, and Environmental Products and Solutions www.kineticsnoise.com Commercial Duct Silencers Kinetics Noise Control offers the design and engineering assistance to integrate

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

Research Analysis: Building Envelope and LEED Credits Introduction

Research Analysis: Building Envelope and LEED Credits Introduction : Building Envelope and LEED Credits Introduction Green buildings are no longer a new idea and are quickly becoming the trend in the slowly changing industry of building construction. Even though the essence

More information

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

Contracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare.

Contracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare. Contracted Scope Provide a detailed description of your scope for this project. Responses should include: type of construction; size of project; contract value; length of project; and percentage of labor

More information

BRADDOCK ROAD YOUTH CLUB

BRADDOCK ROAD YOUTH CLUB BRADDOCK ROAD YOUTH CLUB P.O. Box 2084 Fairfax Virginia 22031 July 25. 2015 Re: Request for Proposals for Kings Park Shopping Center Community Center Dear Prospective Contractor: Braddock Road Youth Club

More information

BASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS

BASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS BASEMENT FINISH REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS A construction permit is required. A homeowner may perform the construction work on his own property where he resides, without a

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018 Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as

More information