Buildings Construction Procurement Strategy

Size: px
Start display at page:

Download "Buildings Construction Procurement Strategy"

Transcription

1 Buildings Construction Procurement Strategy Update August 2015 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_2NAKWC 1

2 Table of Contents 1. Overview of the ITER Buildings 2. Packaging Strategy 3. Overview of the Procurement Packages 4. Description of remaining Procurement Packages I. Scope II. Procurement process III. Key dates IV. Criteria 2

3 1. Overview of the ITER Buildings Hot Cells Tokamak Complex Cooling Towers Magnet Power Conversion Cryoplant Assembly Hall 3

4 2. Packaging Strategy Procurement of large packages Scope of supply Buildings & associated services Scope in line with design complexity: Simple buildings and most services: Design & Build Most buildings: Build from Tender Design Main Nuclear structures: Build from Construction Design Schedule driven by Ready for Equipment Dates: Preliminary Works: Foundation Tokamak & Site Adaptation Works Initial Phase: Infrastructure, buildings & services Subsequent Phase: Hot Cells complex (21, 23, 24), Neutral Beam Power (34, 37) and Safety power supply buildings (44, 45) 4

5 3. Overview of the Procurement Packages Initial Phase Subsequent Phase 5

6 3. Overview of the Procurement Packages Preparatory Phase: TB00 - Construction of the Tokamak Complex Seismic Isolation Pit, Supply and Installation of Anti- Seismic Bearings Contracts signed TB01 - Site Adaptation Contract signed Initial Phase: TBAlpha Galleries and drainage works Contract signed TB02 Long Lead Mechanical Handling Contract signed TB03 Main Civil & Finishing Contract signed TB04 Main M&E/Services Contract signed TB05 D&B Package Contract signed TB06 HV Electrical Equipment Contract signed TB07 D&B Package Contract signed TB08 Site Infrastructure Works Contract terminated TB16 Site Infrastructure Works (re-launch of part of the TB08 scope) Call For Tender on-going Subsequent Phase: TB09 Hot Cells Civil Postponed until 2019 TB10 Hot Cells M&E Handling Postponed until 2019 TB11 Completion Works Planned in 2016 TB12 Buildings 24, 34 and 37 Planned in 2015 TB13 Electrical equipment and Buildings Procurement procedure cancelled 6

7 4. Description of remaining Procurement Packages The remaining procurement packages listed below are described in the subsequent pages: Initial Phase: TB16 Site Infrastructure Works Call for Tender on-going Subsequent Phase: TB12 Buildings 24, 34 and 37 Planned in 2015 TB11 Completion Works Planned in

8 TB16 Site Infrastructure Works (Re-Launch of part of the TB08 scope) (Initial Phase) Scope of Supply: < 50m Execution Design and Construction of: Concrete service trenches (galleries) - Internal dimensions (width in mm x height in mm) ranging from: smallest 2200 x 1650, largest 2700 x 5500 and 4300 x Average thickness of the walls: 300 mm - Length of service trenches to be implemented: 3000 lm Precipitation Drainage (concrete pipe works) Special Foundations: - Reinforced concrete foundations for load centers including blast walls - Reinforced concrete slabs for tanks or other equipment - Inclusions expected: rails, embedded plates or others - Example of dimensions to be considered (width in mm x length in mm): e.g. Laydown area 17 slab: x Procurement Process: Restricted Procedure Input: Construction Design Type of contract: FIDIC Contractual Conditions 8

9 TB12 - Design & Build of Buildings 24, 34 & 37 (Subsequent Phase) Scope of Supply: < 50m Design and Build of Buildings: - 24 (Personnel Access Control Building), concrete and steel building; - 34 (NB Power Supply Building) and 37 (NB High Voltage Power Supply Building), steel buildings. 9

10 TB12 - Design & Build of Buildings 24, 34 & 37 (Subsequent Phase) Scope of Supply: < 50m Design and Build of Buildings: - 24 (Personnel Access Control Building), concrete and steel building; - 34 (NB Power Supply Building) and 37 (NB High Voltage Power Supply Building), steel buildings. Procurement Process: Restricted Procedure Type of contract: FIDIC Contractual Conditions 10

11 TB12 - Design & Build of Buildings 24, 34 & 37 (Subsequent Phase) Key Dates: TB12 Issue of Call For Expressions of Interest Q3-15 Receipt of Expressions of Interest Q4-15 Publication of selected candidates Q1-16 Issue of Call For Tender Q2-16 Receipt of Tenders Q3-16 Contract Award Q4-16 Contract Signature Q

12 TB11 Completion Works (Subsequent Phase) Scope of Supply: < 50m Buildings 11, 13-17, 36, 42-47, 51-53, 61, 71, 74, 75, 32, 33, 35, 38, 39, 41, 21, 23, 24, 34, 37 12

13 TB11 Completion Works (Subsequent Phase) Scope of Supply: Final fixings and finishing Fire seals/ stopping Final paint / cleaning Attendance of M&E and commissioning Procurement Process: Restricted Procedure Type of contract: FIDIC Contractual Conditions 13

14 TB11 Completion Works (Subsequent Phase) Key Dates: TB11 Issue of Call For Expressions of Interest Q3-16 Receipt of Expressions of Interest Q4-16 Publication of selected candidates Q4-16 Issue of Call For Tender Q4-16 Receipt of Tenders Q1-17 Contract Award Q2-17 Contract Signature Q

15 For further information please contact us at mentioning Buildings in subject of your Follow us on:

Status of ITER Buildings construction and next procurement steps

Status of ITER Buildings construction and next procurement steps Status of ITER Buildings construction and next procurement steps Laurent Schmieder Site, Buildings and Power Supplies Project Manager IBF/15 DIRECTORY IBF/15 March 25-27 March 25-27, 2015 Palais du Pharo

More information

Fusion for Energy The European Domestic Agency for ITER. F4E Contracts & Procurement Unit

Fusion for Energy The European Domestic Agency for ITER. F4E Contracts & Procurement Unit Fusion for Energy The European Domestic Agency for ITER F4E Contracts & Procurement Unit Market Policy Group Agenda 1. Fusion Energy 2. ITER 3. Europe in ITER: F4E Fusion for Energy 4. F4E Contractual

More information

Fusion: the fundamental principle

Fusion: the fundamental principle The ITER Project The ITER Project The ITER Project aims to demonstrate the scientific and technological feasibility of fusion power for peaceful purposes. Iter project is an international cooperation between

More information

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1 ITER Organization Françoise Flament Head of Procurement Arrangements & Contracts Division Page 1 1. Overview of the IO Procurement System 2. Business Opportunities 3. IO Procurement Processes and Procedures

More information

ITER: Another Way for the Nuclear Industry

ITER: Another Way for the Nuclear Industry ITER: Another Way for the Nuclear Industry Fusion for Energy, the European Domestic Agency for the ITER Project June 9th 2015 Anthony Courtial Market Intelligence & Supply Chain Analysis Outline 1. The

More information

Decommissioning Group Ketut Kamajaya

Decommissioning Group Ketut Kamajaya Decommissioning Group Ketut Kamajaya Contents of presentation Briefly history of Bandung TRIGA reactor Location of the facility Decommissioning options Characterization of System, Structure and Component

More information

GENERAL PROVISIONS: Furnish and install one steel platform motor truck scale and associated electronic controls.

GENERAL PROVISIONS: Furnish and install one steel platform motor truck scale and associated electronic controls. GENERAL PROVISIONS: Furnish and install one steel platform motor truck scale and associated electronic controls. The scale shall have a clear and unobstructed weighing surface of not less than 70 feet

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

Barilla Cogeneration Power Plant main tips

Barilla Cogeneration Power Plant main tips main tips Client Location Total contract Scope of work Fenice SpA Contract value 13.3 M$ Contract period 2007-2010 The Plant has been built within the premises of the Barilla factory in Parma (IT), at

More information

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

Technical Summary for TCC0 Global overview of the scope for TCC0 contract IDM UID V89YJN VERSION CREATED ON / VERSION / STATUS 06 Oct 2017 / 2.0 / Signed EXTERNAL REFERENCE / VERSION Technical Specification Technical Summary for TCC0 Global overview of the scope for TCC0 contract

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

RESIDENTIAL CONSTRUCTION New Dwellings and Additions How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:

More information

1. FROM (Bidder): (Name)

1. FROM (Bidder): (Name) Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3

More information

CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES 9.2 TYPES OF STAIR CASES

CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES 9.2 TYPES OF STAIR CASES CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES Stair cases are provided for connecting successive floors. It is comprised with flights of steps with inter mediate landings which provides rest to the user and

More information

Technical summary - supply and install racks and other associated equipment in the warehouse of the logistics

Technical summary - supply and install racks and other associated equipment in the warehouse of the logistics IDM UID Q7NTMT VERSION CREATED ON / VERSION / STATUS 30 Jan 2015 / 1.1 / Approved EXTERNAL REFERENCE Technical Specifications (In-Cash Procurement) Technical summary - supply and install racks and other

More information

INFORMATION DAY. Fusion for Energy (F4E)

INFORMATION DAY. Fusion for Energy (F4E) INFORMATION DAY 26th November 2013, Zagreb Fusion for Energy (F4E) Part 2 Status of the ITER Project and Achievements Jesus Izquierdo Technical Coordination and Integration 1 THE ITER PROJECT MAIN SYSTEMS

More information

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00 Description Page No Summary Amount Summary 1/7 230,694.60 22,019.25 22,642.65 2/6 96,801.30 80,150.60 114,056.00 Total Per Unit (MYR) 327,495.90 102,169.85 136,698.65 Total Unit(s) X 1 2 2 Total Per Type

More information

Inverted Double T BEAMS and SLABS Applications

Inverted Double T BEAMS and SLABS Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Inverted Double T BEAMS and SLABS Applications Inverted Double T Beams U Panels Inverted Double T Slabs Inverted Triple

More information

Invitation to Tender. Reference: IOSVSP4P-Metal

Invitation to Tender. Reference: IOSVSP4P-Metal 1 Invitation to Tender Metal fabrication / installation works at Plot 4, Porthmellon Industrial Estate, St Marys, Isles of Scilly Reference: IOSVSP4P-Metal 1 2 1 Background/Introduction Plot 4 Porthmellon

More information

Underground Exhaust System

Underground Exhaust System Operation and Maintenance Manual Underground Exhaust MONOXIVENT - SOURCE CAPTURE SYSTEMS - info@ Oct. - 2015 Underground Duct Construction Standards 1. Dig trench depth to allow for minimum distance from

More information

DIVISION: CONCRETE SECTION: CONCRETE ACCESSORIES SECTION: REINFORCING STEEL REPORT HOLDER: PJ S REBAR INC.

DIVISION: CONCRETE SECTION: CONCRETE ACCESSORIES SECTION: REINFORCING STEEL REPORT HOLDER: PJ S REBAR INC. 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 42 687 (62) 699 04 www.icc es.org ESR 82 Reissued 0/207 This report is subject to renewal 0/209. DIVISION: 0 00 00 CONCRETE

More information

STORMCAPTURE. Installation Manual

STORMCAPTURE. Installation Manual STORMCAPTURE Installation Manual Introduction Site Preparation Delivery & Installation LinkSlabs Backfill Introduction StormCapture (shown in Figure 1) is a total stormwater management system. The highly-configurable

More information

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks CONSTRUCTION PROCEDURES AWWA D110 Type I Prestressed Concrete Tanks 2-3 4-5 6-7 8-9 10-11 12-13 14-15 16-17 Site Preparation Floor & Footings Wall Construction Roof Options Vertical Prestressing Abrasive

More information

DICTATOR Lift Shaft System

DICTATOR Lift Shaft System DICTATOR Lift Shaft System The Modular Lift Shaft System, also for Retrofitting Certified According to EN 1090 A lift is becoming more and more important for daily life, not only in newly constructed buildings

More information

Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group

Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group INTRODUCTION EMPLOYER S CORE PRINCIPLES OF PROCUREMENT Value for money / Economy Efficiency / Fit for purpose

More information

Best practices for preparing vessel internals segmentation projects

Best practices for preparing vessel internals segmentation projects Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign

More information

Lecture 3-1: Hull production - Product hierarchy and block division

Lecture 3-1: Hull production - Product hierarchy and block division Kul-24.4130 Shipyard engineering Lecture 3-1: Hull production - Product hierarchy and block division Applied Mechanics Marine Technology Lecture in course contents Production planning Introduction Shipbuilding

More information

Fast Corrosion Screening Technique Saturation Low Frequency Eddy Current

Fast Corrosion Screening Technique Saturation Low Frequency Eddy Current Summary The inspection of ferromagnetic and non-ferromagnetic material components is an attractive and efficient method due to its fast screening of large areas with low surface preparations. Already qualified

More information

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

More information

DIVISION: CONCRETE SECTION: CONCRETE ACCESSORIES SECTION: REINFORCING STEEL REPORT HOLDER: TENDON SYSTEMS, LLC

DIVISION: CONCRETE SECTION: CONCRETE ACCESSORIES SECTION: REINFORCING STEEL REPORT HOLDER: TENDON SYSTEMS, LLC 0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 42-6587 (562) 699-054 www.icc-es.org ESR-900 Issued 08/2017 This report is subject to renewal 08/2018. DIVISION: 0 00 00 CONCRETE

More information

Hollow Core Slabs Applications

Hollow Core Slabs Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Hollow Core Slabs Applications Hollow Core Slabs Technology for the Precast and Prestressed Concrete Industry HOLLOW RESIDENTIAL,

More information

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette ArcelorMittal Europe - Long Products Sections and Merchant Bars Office Building ArcelorMittal in Esch Alzette Location the country, at the heart of the iron and steel region. It has good access to the

More information

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017 Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins

More information

Foundation/Site Work Code Requirements

Foundation/Site Work Code Requirements Q: What is a Foundation Only permit and why did I receive one when I filed for a full Building Permit? All Building Permits for new construction and additions are reviewed for zoning compliance. This review

More information

2013 VIRGINIA CONCRETE CONFERENCE LESSONS LEARNED / CHALLENGES NOVA MEGAPROJECTS PROGRAM STRUCTURE AND BRIDGE FIELD PERSPECTIVE. Fawaz K. Saraf, P.E.

2013 VIRGINIA CONCRETE CONFERENCE LESSONS LEARNED / CHALLENGES NOVA MEGAPROJECTS PROGRAM STRUCTURE AND BRIDGE FIELD PERSPECTIVE. Fawaz K. Saraf, P.E. 2013 VIRGINIA CONCRETE CONFERENCE LESSONS LEARNED / CHALLENGES NOVA MEGAPROJECTS PROGRAM STRUCTURE AND BRIDGE FIELD PERSPECTIVE Fawaz K. Saraf, P.E. CHALLANGES Poor Detailing a challenge on some bridge

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9080 - Concrete Steps, Handrails, and Safety Rail CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART - GENERAL.0 SECTION INCLUDES

More information

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING Route de Vinon-sur-Verdon - CS 90 046-13067 St Paul Lez Durance Cedex - France ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING CALL FOR NOMINATION Ref. IO/CFN/14/11176/PMT SUMMARY

More information

PEER Tall Building Seismic Design Guidelines

PEER Tall Building Seismic Design Guidelines PEER Tall Building Seismic Design Guidelines Preliminary Design Recommendations & Performance Studies John Hooper Principal & Director of Earthquake Engineering Magnusson Klemencic Associates SEAW November

More information

MOBILE SUBSTATIONS TRAILER AND SKID. tgood.com. Energy, Fast!

MOBILE SUBSTATIONS TRAILER AND SKID. tgood.com. Energy, Fast! MOBILE SUBSTATIONS TRAILER AND SKID tgood.com Energy, Fast! Global leader in E-House and prefabricated substation solutions PRODUCT OVERVIEW Custom configurable skid-mounted and trailer-mounted designs.

More information

DESIGN CRITERIA. Allowable Stress Design (ASD) AISC-1999.

DESIGN CRITERIA. Allowable Stress Design (ASD) AISC-1999. DESIGN CRITERIA 1. INTRODUCTION This appendix summarizes the codes, standards, criteria, and practices that are generally used in the design and construction structural engineering system for the Sarker

More information

UNIT III Earthwork Estimation & Reinforcement Estimation

UNIT III Earthwork Estimation & Reinforcement Estimation SIDDHARTH GROUP OF INSTITUTIONS :: PUTTUR Siddharth Nagar, Narayanavanam Road 517583 QUESTION BANK (DESCRIPTIVE) Subject with Code : ECV(13A01605) Year & Sem: IV-B.Tech & I-Sem Course & Branch: B.Tech

More information

Slab Track Austria. System ÖBB-PORR elastically supported slab

Slab Track Austria. System ÖBB-PORR elastically supported slab Slab Track Austria System ÖBB-PORR elastically supported slab 5. 2. 3. 4. 7. 6. Five holes for spindles 2. ÖBB-PORR slab 3. elastomeric layer 4. concrete joint sealing compound 5. rail support seat 6.

More information

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL CENTRE FZE. BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL CENTRE FZE. BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016 OCD59 UNIVERSITY OF BOLTON WESTERN INTERNATIONAL CENTRE FZE BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016 ADVANCED STRUCTURAL ANALYSIS AND DESIGN MODULE NO: CIE6001 Date: Tuesday 12

More information

Design and analysis of T and inverted L beams- Theory and Examples

Design and analysis of T and inverted L beams- Theory and Examples Design and analysis of T and inverted L beams- Theory and Examples - Dr. E. R. Latifee Reference Book: Design of Reinforced Concrete by Jack C. McCormac and Russell H. Brown, Clemson University, 9 th Edition,

More information

TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS

TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS GETCO/E/TS-MS024/R0DT01-04-2008

More information

Overview of the Standard for Seismic Design of Cold-formed Steel Structural Systems - Special Bolted Moment Frames

Overview of the Standard for Seismic Design of Cold-formed Steel Structural Systems - Special Bolted Moment Frames Missouri University of Science and Technology Scholars' Mine International Specialty Conference on Cold- Formed Steel Structures (2008) - 19th International Specialty Conference on Cold-Formed Steel Structures

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

Operations and Civil Engineering Services Construction Operations (Construction)

Operations and Civil Engineering Services Construction Operations (Construction) Qualification Title: Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Pathway 1: Level 2 NVQ Diploma in Construction Operations (Modular

More information

SECTION PREFABRICATED PIPE BRIDGE(s)

SECTION PREFABRICATED PIPE BRIDGE(s) SECTION 13135 - PREFABRICATED PIPE BRIDGE(s) PART 1 - GENERAL 1.01 Scope A. The Contractor is responsible for all engineering design, detailing, fabricating, installation including foundations for the

More information

Council on Tall Buildings

Council on Tall Buildings Structure Design of Sino Steel (Tianjin) International Plaza Xueyi Fu, Group Chief Engineer, China Construction Design International 1 1 Brief of Project 2 Location: Tianjin Xiangluowan Business District

More information

Roofgard Paving Support System

Roofgard Paving Support System Roofgard Paving Support System CI/SfB (47) January 2007 Adjustable paving support system for paved and raised deck applications One of a range of Roofgard accessories specially designed to meet the exacting

More information

NUCu STEEL ASTM A-710 GRADE B. High Performance Copper-Precipitation-Strengthened Steel With Low Carbon Equivalent

NUCu STEEL ASTM A-710 GRADE B. High Performance Copper-Precipitation-Strengthened Steel With Low Carbon Equivalent High Performance Copper-Precipitation-Strengthened Steel With Low Carbon Equivalent NUCu STEEL ASTM A-710 GRADE B 70 ksi Grade Low Temperature Tough Improved Weldability Improved Weatherability Life Cycle

More information

KSK COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING CE 2505-DESIGN OF RC ELEMENTS QUESTION BANK

KSK COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING CE 2505-DESIGN OF RC ELEMENTS QUESTION BANK KSK COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING CE 2505-DESIGN OF RC ELEMENTS QUESTION BANK PARTA UNIT I 1. What are the advantages of limit state method over working stress and

More information

Folie 2 ISM 2006, 7 th International Workshop on Micropiles May 3-7, 2006, Schrobenhausen, Germany Design Guide for TITAN Micropile Heads Dipl.-Ing. E

Folie 2 ISM 2006, 7 th International Workshop on Micropiles May 3-7, 2006, Schrobenhausen, Germany Design Guide for TITAN Micropile Heads Dipl.-Ing. E Folie 1 Standard Micropile Heads FE-Modelling of Micropile Heads Design Guide Harbour City Hamburg Micropile TITAN 103/78 for Sheet Pile Wall Folie 2 ISM 2006, 7 th International Workshop on Micropiles

More information

Last Updated March 15, 2016

Last Updated March 15, 2016 CASS COUNTY, MISSOURI BUILDING CODES, ENVIRONMENTAL HEALTH AND ZONING DEPARTMENT 30508 S. West Outer Road, Harrisonville, MO 64701 P- (816) 380-8134 F- (816) 380-8130 Last Updated March 15, 2016 Information

More information

ST IMPLICATIONS IN THE CNGS PROJECT

ST IMPLICATIONS IN THE CNGS PROJECT EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN - ST Division CERN-ST-2000-012 February, 2000 ST IMPLICATIONS IN THE CNGS PROJECT M. Wilhelmsson Abstract

More information

B. Modular House. Feature: Installation Procedure:

B. Modular House. Feature: Installation Procedure: B. Modular House Feature: All manufacturing work and decoration are finished at factory, the onsite work is to install the modules and connect the municipal pipe network. The Wallboard is sandwich panel

More information

DEPARTMENT OF CIVIL ENGINEERING

DEPARTMENT OF CIVIL ENGINEERING DEPARTMENT OF CIVIL ENGINEERING VII SEMESTER CE 2402 - ESTIMATION AND QUANTITY SURVEYING Two Marks 1. What are methods to be adopted for volume calculating? 2. Define analysis of rates. 3. Define a tender.

More information

SEISMIC BEHAVIOR OF MULTI-STORY STRUCTURE WITH DIFFERENT TYPES OF SLABS

SEISMIC BEHAVIOR OF MULTI-STORY STRUCTURE WITH DIFFERENT TYPES OF SLABS International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 507 517 Article ID: IJCIET_08_04_057 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4

More information

MCCARTY ARCHITECTS, P.A. POST OFFICE BOX 440 / 533 WEST MAIN STREET TUPELO, MS / FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON

MCCARTY ARCHITECTS, P.A. POST OFFICE BOX 440 / 533 WEST MAIN STREET TUPELO, MS / FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON ADDENDUM NUMBER FROM: MCCARTY ARCHITECTS, P.A. POST OFFICE BOX 0 / 533 WEST MAIN STREET TUPELO, MS 3880 / 3880 FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON PHONE: -8-00 PROJECT: ACADEMIC STUDENT

More information

MR 120/2015. SUPPLY OF 2 X 2MVA 415V/11kV 3 PHASE TRANSFORMERS

MR 120/2015. SUPPLY OF 2 X 2MVA 415V/11kV 3 PHASE TRANSFORMERS MR 120/2015 SUPPLY OF 2 X 2MVA 415V/11kV 3 PHASE TRANSFORMERS TRANSFORMER DETAILS: 2 x 2MVA 3Phase 11-6.3kV/415V YNd11 Transformer Voltage ratios: 11000-6.35/415volts Off circuit tapchanger, with tappings

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

RETAINING WALL LEVEL BACKFILL

RETAINING WALL LEVEL BACKFILL City of Poway Development Services Department Building Division (858) 668-4645 (858) 668-4646 (Inspection Line) building@poway.org RETAINING WALL LEVEL BACKFILL Construction of retaining walls, except

More information

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project. SECTION 14651 FREE STANDING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial

More information

Finite Element Analysis for Structural Reinforcements in Concrete Railway Bridges

Finite Element Analysis for Structural Reinforcements in Concrete Railway Bridges Finite Element Analysis for Structural Reinforcements in Concrete Railway Bridges PRESENTATION TOPICS Company Overview Problem Description Methodology Results Conclusion Company Overview Carlos Alberto

More information

Apparel Gallery Ltd.

Apparel Gallery Ltd. Apparel Gallery Ltd. 147-148, Norshinghpur, Asulia, Savar, Dhaka (23.929985N,90.304914E) 23 March 2014 1 2 Observations Building 1 Heavy loading due to raised floor area on Ground Floor 3 Building 1 Raised

More information

Poland Nuclear Program EPR Flamanville 3

Poland Nuclear Program EPR Flamanville 3 Poland Nuclear Program EPR Flamanville 3 Project Organization Design & Manufacturing activities On Site activities What We Are Learning from New Construction Experience September 29 th, 2010 Gilles Zask

More information

GENERAL PROVISIONS: Furnish and install one steel deck platform motor truck scale and associated electronic controls.

GENERAL PROVISIONS: Furnish and install one steel deck platform motor truck scale and associated electronic controls. GENERAL PROVISIONS: Furnish and install one steel deck platform motor truck scale and associated electronic controls. The scale shall have a clear and unobstructed weighing surface of not less than 70

More information

SEISMIC DESIGN OF STEEL FRAMES CONSIDERING STRUCTURAL WEIGHT AND FABRICATION COST

SEISMIC DESIGN OF STEEL FRAMES CONSIDERING STRUCTURAL WEIGHT AND FABRICATION COST October -,, Beijing, China SEISMIC DESIGN OF STEEL FRAMES CONSIDERING STRUCTURAL WEIGHT AND FABRICATION COST K.Sawada,H.Shimizu,A.Matsuo,T.Sasaki,T.Yasui,A.Namba,T.Takamatsu,H.Tamai Assistant Professor,

More information

ACTION OF GLUED STEEL PLATES IN STRENGTHENING OF STRUCTURES

ACTION OF GLUED STEEL PLATES IN STRENGTHENING OF STRUCTURES ACTION OF GLUED STEEL PLATES IN STRENGTHENING OF STRUCTURES Seppo Huovinen ABSTRACT Rakenteiden Mekaniikka, Vol.29 Nro 3-4, 1996, s. 69-74 The strengthening of reinforced concrete and steel beams with

More information

K-FLEX K-FLEX ST 74 A NEW GENERATION OF INSULATION MATERIALS

K-FLEX K-FLEX ST 74 A NEW GENERATION OF INSULATION MATERIALS K-FLEX 74 A NEW GENERATION OF INSULATION MATERIALS /SK pre-cut pipe insulation with adhesive sheets tubes Elastomeric insulation for all applications, both civil and industrial. Applications: Air-conditioning

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

Freight Elevator Series GFM-T

Freight Elevator Series GFM-T Freight Elevator Series GFM-T Mitsubishi Freight Elevators Can Improve our Goods-Handling Ability Elevator Selection 1. Rated capacity and car size What is the maximum weight or size of goods to be transported

More information

TOWN OF PHIPPSBURG REQUEST FOR BIDS Meadowbrook Landing Finger Float Project

TOWN OF PHIPPSBURG REQUEST FOR BIDS Meadowbrook Landing Finger Float Project TOWN OF PHIPPSBURG REQUEST FOR BIDS Meadowbrook Landing Finger Float Project The Town of Phippsburg is accepting bids for a finger float project at the Meadowbrook Landing located at the end of Bushy Isle

More information

Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises

Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises Kochi Metro Rail Ltd (KMRL), Invites quotation for Supply, Installation, Testing and Commissioning of decorative cast

More information

Design and Estimation of Reinforced Building: A Case Study

Design and Estimation of Reinforced Building: A Case Study Design and Estimation of Reinforced Building: A Case Study Akshay Chaudhary 1, Payal Sachdeva 2, Maninderpal Singh 3 1, 2 (Assistant Professor, Department of Civil Engineering, CGC Technical Campus, Jhanjeri,

More information

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,

More information

Building Program Example. Eric Anderson

Building Program Example. Eric Anderson Building Program Example Eric Anderson MINIMUM SPATIAL/FUNCTIONAL REQUIREMENTS SPACE NUMBER OF OCCUPANTS USE TYPE Activity Room 100-200 Assembly Meeting Rooms (5) Referenced at Room Descriptions Business

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

READY TO TILE HAMMAMS HAMMAMS. < Hammams: Well-being at Home >

READY TO TILE HAMMAMS HAMMAMS. < Hammams: Well-being at Home > READY TO TILE HAMMAMS HAMMAMS < Hammams: Well-being at Home > 44 Hammams Well-being at home now knocking at your door The "Hammam" has its origins in the Roman baths. The Hammam, long used throughout the

More information

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

Grafe Beton incorporates custom-made wet cast, monolithic manhole bases into the comprehensive product range

Grafe Beton incorporates custom-made wet cast, monolithic manhole bases into the comprehensive product range Schlüsselbauer Technology GmbH & Co KG, 4673 Gaspoltshofen, Austria Grafe Beton incorporates custom-made wet cast, monolithic manhole bases into the comprehensive product range An innovation has occurred

More information

US Pool Lift Model #114 (Independence) Installation Guide

US Pool Lift Model #114 (Independence) Installation Guide US Pool Lift Model #114 (Independence) Installation Guide This manual has been provided to assist with lift installation. For further assistance please contact your authorized US Pool Lift dealer. Toll

More information

TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3

TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3 TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3 PROJECT MANAGER S REPORT NO. 15 TO PLANNING AND DEVELOPMENT COMMITTEE Prepared by February 2001 TWEED HEADS HOSPITAL STAGE 3 REDEVELOPMENT PROJECT MANAGER S REPORT

More information

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction...

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction... TABLE OF CONTENT Equipment kit.... 6 Description of the technology.... 8 Installation of equipment.... 10 Start of construction.... 14 Erection of walls and partitions.... 17 Second floor printing....

More information

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS Diagram 1: Standard Membrane Continuation 150 mm Overlap Ensure Membrane to Membrane Contact Diagram 2: Membrane Continuation

More information

The designer shall also submit additional information required by the University as described and underlined below.

The designer shall also submit additional information required by the University as described and underlined below. I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design

More information

PIPEWORK INSULATION. 14/ Page 1 of 10 Pipework Insulation Rev D

PIPEWORK INSULATION. 14/ Page 1 of 10 Pipework Insulation Rev D PIPEWORK INSULATION 14/10-2014 Page 1 of 10 Pipework Insulation Rev D Contents INTRODUCTION General Scope Surfaces to be Insulated Pumps, Turbines etc Performance Minimum Pipe Insulation Thickness Physical

More information

Short Span Steel Bridges

Short Span Steel Bridges Short Span Steel Bridges MINK 2015 Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation SSSBA & espan140 Design Competitiveness of Steel Bridges Economics

More information

Session 2: Basic Load Rating Calculations

Session 2: Basic Load Rating Calculations Agenda Day 1 8:00 am 8:15 am Introductions and House Keeping 8:15 am 8:45 am Session 1: Load Rating Basics 8:45 am 9:30 am Session 2: Basic Load Rating Calculations 9:30 am 9:45 am Break 9:45 am 11:45

More information

PRECAST CEMENT PRODUCTS

PRECAST CEMENT PRODUCTS Profile No.: 30 NIC Code: 23959 PRECAST CEMENT PRODUCTS 1. INTRODCUTION: Reinforced cement concrete products are becoming popular as modular house and apartment buildings are based on standard designs.

More information

PRESENTATION CENTER SURREY, BC CANADA

PRESENTATION CENTER SURREY, BC CANADA PRESENTATION CENTER SURREY, BC CANADA 1 VIEW OF THE PROPOSED OPTIMA 3 TOWERS (AFTER OBTAINING THE HIGH DENSITY THAT IS UNDER STUDY) ALONG WEST WHALLEY RING ROAD 2 3 IHI WILL BUILD THE OPTIMA PRESENTATION

More information

Superstructure Guidelines

Superstructure Guidelines Superstructure Guidelines The following are additional guidelines on using the following types of superstructure. Pre-stressed Concrete Beams To check beam size use the beam size chart. The chart was created

More information

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS BRIDGE PREVENTIVE MAINTENANCE STRATEGY Approved January 3, 2007 BLANK Purpose To maximize the non-deficient service life of local bridges in the Erie-Niagara region, members of the Greater Buffalo-Niagara

More information

AREMA UNLOADING PIT CALCULATIONS

AREMA UNLOADING PIT CALCULATIONS AREMA UNLOADING PIT CALCULATIONS AUTHORS Steven P. Lorek, PE (Principal Author) HDR Engineering, Inc. 9987 Carver Road, Suite 200 Cincinnati, OH 45242 Phone: 513.984.7557 Fax: 513.984.7580 Email:Steve.Lorek@hdrinc.com

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved. Sri Ganesha Temple HTNT Construction Update (June, 2016) With Lord Ganesha s Blessing We start everything Architect View of the Ganesha Temple at Finish Sri Ganesha Temple HTNT Construction Milestones

More information