Screening Level Risk Assessment for Low Hazard Dams

Size: px
Start display at page:

Download "Screening Level Risk Assessment for Low Hazard Dams"

Transcription

1 Screening Level Risk Assessment for Low Hazard Dams 2014 ASFPM Annual Conference Laurie Carrette Zook, PE, CFM 2014 HDR, Inc., all rights reserved.

2 Screening Level Risk Assessment (SLRA) Why SLRA for Low Hazard Dams? o Identify and Better Understand Risk and Benefits o Document o Make Decisions o Provide Basis for Prioritization o Communicate

3 Initial Screening of Low Hazard Dams 10 sites at GTE, YELL, ROMO, CHIC (3 sites), CHAT, and LAVO Deliverables: o Checklist Examination Report o Screening Level Risk Assessment (SLRA) Report Work Completed in 2012

4 Methodology Specific to National Park Service (NPS) mission and values Based on best practices for high and significant hazard dams Semi-Quantitative Scalable To preserve unimpaired the natural and cultural resources and values of the national park system for the enjoyment, education, and inspiration of this and future generations

5 Risk Matrix Low Hazard vs. High Hazard (typ.) Very High Likelihood Very High High Moderate Low Remote Probability Category High Moderate Seismic right abutment sliding Consequences Level Multi-attribute Low Level 1 Level 2 Level 3 Level 4 Consequence Category Life Loss

6 Steps and Process Desktop Review & Potential Failure Mode Analysis (PFMA)- lite Site Inspection Checklist Examination Report Simplified Engineering Evaluations Risk Workshop Risk Screening Report

7 Desktop Review Review of available information Generation of available mapping Preliminary identification of failure consequences Interviews with Park staff

8 PFMA Lite Failure Mode Category Static Hydrologic Seismic PFM Description Credible PFM Highlighted PFMs Embankment piping/internal erosion X PFM 1 Foundation piping/internal erosion X PFM 2 Abutment piping/internal erosion X Considered as part of PFM 2 Piping along outlets or service spillway X PFM 3 Piping of material into open rock joints Slope instability X Wave erosion of upstream slope Large landslide creating seiche waves in reservoir Channel erosion/back cutting due to underseepage Increased threat of seepage-related failure during flood Spillway damage due to toe erosion and/or headcutting X Dam breach due to overtopping X PFM 4 Earthquake-induced embankment cracking/damage leading to seepagerelated failure X Seismic slope instability with excessive deformations and failure by overtopping X PFM 5 Embankment/foundation liquefaction leading to slope instability, excessive deformations and failure by overtopping X

9 Site Inspection Verify PFMs and identify any new modes of failure for consideration Confirm failure consequences Collect field data to support simplified analyses

10 Site Inspection Manzanita Dam

11 Site Inspection Manzanita Dam

12 Site Inspection Manzanita Dam

13 Checklist Examination Report Document credible PFMs Summarize current conditions Summary failure consequences => Serves as Reference Document for the Risk Workshop

14 Simplified Engineering Evaluations Static PFMs Hydrologic PFMs Seismic PFMs Estimated Flood Hazard, Manzanita Lake Dam Estimated Seismic Hazard, Manzanita Lake Dam Earthquake Return Period in years Peak Ground Acceleration g g 1, g 2, g 5, g 10, g Source: USGS, 2012 Flood Return Period (years) Peak Flow (cfs) ,290 1,000 1,785 5,000 3,775 10,000 5,215 Source: USGS StreamStats, 2012 Source: Estimated using linear extrapolation from the values above

15 Risk Matrix Likelihood Very High High Moderate Low Remote Likelihood Est. Annual Probability of Failure: VERY HIGH greater than 1E 02 HIGH 1E 03 to 1E 02 MODERATE 1E 04 to 1E 03 LOW 1E 05 to 1E 04 REMOTE less than 1E Consequences Level Consequences Level Level 0 minor or no damage Level 1 minor damage confined to NPS property Level 2 moderate damage/ less than 1 year recovery Level 3 significant damage/2 5 year recovery Level 4 extensive, some permanent, damage/ long recovery Confidence Estimates Good Rating is high; it is unlikely that additional information would change the rating. Poor Rating is low; additional information could very well result in a change to the rating. Medium In between Good and Poor

16 Consequences Categories LEVEL Level 0 Level 1 Level 2 Level 3 Level 4 DESCRIPTION Dam breach discharge would result in no resource, property, or environmental damage. Re-construction costs are expected to be minor. Minor property or environmental damage would be limited to NPS property No permanently occupied structures, roads, or bridges are damaged. Repair costs < $50K No or minor impact on visitation or park resources Damage would be limited to a few permanently occupied structures, recreation areas, roadways, and non-critical bridges in low lying areas on NPS property only Moderate property damage (~$100K). Moderate environmental damage or loss of park resources Moderate impact to recreation/visitation Costs associated with re-constructing the project features and negative publicity associated with a dam failure would also be incurred. Less than 1 year recovery. Significant environmental damage or impacts to historical and cultural park resources. Damages possible or expected to extend off NPS property Dam breach discharge would results in significant damage to permanently occupied structures, recreational areas, roadways, and bridges within the inundation zone ($500K -$1M) Moderate impact to recreation Visible negative impact to scenic beauty Multi-year recovery 2-5 years. Long-term damage to threatened and endangered species and species habitat Significant negative publicity expected Extensive damage to park infrastructure (campgrounds, structures, utilities, roads, trails, picnic areas, bridges etc) in excess of $5Million including possible impacts off of NPS property. Damage to critical infrastructure (water supply, hospitals, schools etc) Major impacts to historical and/or cultural park resources. Loss of heavily visited/iconic park resource. Life loss or injury due to dam failure is unlikely but plausible. Recovery over very long time (5-10 years)

17 Risk Workshop

18

19

20

21 Final Screening Report Documents Risk Workshop Summarizes PFMs and respective risks, consequences, and confidence Provides recommendations for safety of dam and operation and maintenance actions

22 Lessons Learned Great Communication Tool Metrics Need to be Consistent with the Mission Small Experienced Team Value of Process

23 Questions? 2014 HDR, Inc., all rights reserved.

24 2014 HDR Architecture, 2014 HDR, Inc., all rights reserved.

Regulation No July Engineering and Design REPORTING EARTHQUAKE EFFECTS TABLE OF CONTENTS

Regulation No July Engineering and Design REPORTING EARTHQUAKE EFFECTS TABLE OF CONTENTS DEPARTMENT OF THE ARMY *ER 1110-2-1802 U.S. Army Corps of Engineers CECW-EG Washington, DC 20314-1000 Regulation No. 1110-2-1802 28 July 2017 Engineering and Design REPORTING EARTHQUAKE EFFECTS Paragraph

More information

Dam Safety Program. Managing Risk to Support the Core Mission. Karen Weghorst, P.E. Manager, Flood Hydrology and Consequences Group

Dam Safety Program. Managing Risk to Support the Core Mission. Karen Weghorst, P.E. Manager, Flood Hydrology and Consequences Group Dam Safety Program Managing Risk to Support the Core Mission Karen Weghorst, P.E. Manager, Flood Hydrology and Consequences Group Reclamation manages 476 dams and dikes in the Western 17 United States

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

Looking at Dam Safety from a Resiliency Perspective. February 23, 2017

Looking at Dam Safety from a Resiliency Perspective. February 23, 2017 Looking at Dam Safety from a Resiliency Perspective February 23, 2017 1 Discussion Outline Dam Safety 101 (10 min) Fort Hood Overview (5 min) Resiliency Framework (5 min) Fort Hood Dam Safety Program (15

More information

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects References: EIS Guidelines Sec. 23.2; EIS Vol. 5, Section 37.2; EIS, Vol. 6, Technical Memo Dam Safety; Meeting Notes BC Hydro,

More information

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the

More information

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams BIA Summer Water Resources Training Dam Safety Inspections Part 4 - Inspections July 28, 2012 Presented by Michael Johnson, Ph.D., P.E. Types of Inspections Periodic Inspections A comprehensive visual

More information

Classification and Inflow Design Flood Criteria

Classification and Inflow Design Flood Criteria Classification and Inflow Design Flood Criteria Technical Bulletin Ontario Ministry of Natural Resources This publication is available online at: Ontario.ca/dams Ces documents sont offerts en anglais seulement

More information

MSHA s Review of Impoundment Plans

MSHA s Review of Impoundment Plans MSHA s Review of Impoundment Plans Kelvin K. Wu, Ph.D, P.E. Harold L. Owens, P.E. John W. Fredland, P.E. Chief, Mine Waste and Geotechnical Engineering Division, Pittsburgh, PA Supervisory Civil Engineer,

More information

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per

More information

Dam Maintenance Fact Sheet

Dam Maintenance Fact Sheet C O L O R A D O P A R K S & W I L D L I F E Dam Maintenance Fact Sheet 5-YR PARKS AND WILDLIFE FUNDING PROPOSAL FOR DAMS Colorado Parks and Wildlife (CPW) owns and operates over 110 dams (100 Wildlife,

More information

Tailings Design and Operation Safety!

Tailings Design and Operation Safety! Tailings Design and Operation Safety! 1 January 13, 2016 You may have heard about: Mount Polley Buenavista de Cobre KUC Pinto Valley 2 January 13, 2016 Recent Case Events! August 4, 2014-Imperial Metals,

More information

DAM SAFETY PRESENTATION REGULATORY REQUIREMENTS FOR DAM ENGINEERING ASSESSMENTS IN NEW YORK Allan Estivalet, PE

DAM SAFETY PRESENTATION REGULATORY REQUIREMENTS FOR DAM ENGINEERING ASSESSMENTS IN NEW YORK Allan Estivalet, PE Lower Hudson Regional Conference Carmel, NY DAM SAFETY PRESENTATION REGULATORY REQUIREMENTS FOR DAM ENGINEERING ASSESSMENTS IN NEW YORK Allan Estivalet, PE July 24, 2015 NEW YORK STATE DAM SAFETY REGULATIONS

More information

DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety

DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety NAME OF DAM: Milltown Dam DEPDAMNO.: 15-146 LOCATION: Municipality: East Goshen Township

More information

Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map

Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map Michelle Meehan, PE Carey Johnson ASFPM 2013 Conference June 12, 2013 What We ll Talk About Today Overview of KDOW

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

14 NATURAL HAZARDS Background Resource Management Issues

14 NATURAL HAZARDS Background Resource Management Issues 14 NATURAL HAZARDS 14.1 Background The particular geology, hydrology and topography of the Hutt Valley make Upper Hutt vulnerable to a variety of natural hazards. Earthquakes and flooding are the most

More information

RISK ASSESSMENT FOR DAMS AND LEVEES

RISK ASSESSMENT FOR DAMS AND LEVEES RISK ASSESSMENT FOR DAMS AND LEVEES Nate Snorteland, P.E. Director, Risk Management Center Golden, CO 1 October 2011 US Army Corps of Engineers Outline Dams and Levees Decisions Screening Non-Routine Example

More information

DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia DRAFT. Submitted to: Imperial Metals Corporation Hornby Street Vancouver, BC

DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia DRAFT. Submitted to: Imperial Metals Corporation Hornby Street Vancouver, BC DAM SAFETY REVIEW Mount Polley Mine Likely, British Columbia DRAFT November 2006 Submitted to: Imperial Metals Corporation 200 580 Hornby Street Vancouver, BC Submitted by: AMEC Earth & Environmental Limited

More information

Outlet Structure Modeling

Outlet Structure Modeling Watershed Modeling using HEC-RAS Outlet Structure Modeling Jeff Wickenkamp, P.E., CFM, D.WRE Patrick Lach, P.E. Hey and Associates, Inc. Water Resources, Wetlands and Ecology Outline of Presentation Why

More information

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update United States Army Corps of Engineers Addicks and Barker Dam Safety Update COL Richard P. Pannell District Commander, Galveston District U.S. Army Corps of Engineers March 9, 2016 US Army Corps of Engineers

More information

Mike Jastremski, CFM Watershed Conservation Director

Mike Jastremski, CFM Watershed Conservation Director Planning for Flood Resilient and Fish Friendly Road-Stream Crossings in CT s Northwest Hills Mike Jastremski, CFM Watershed Conservation Director Presentation Outline Project area Climate threats Field

More information

Design of buildings using EC8

Design of buildings using EC8 Design of buildings using EC8 Philosophy of seismic design (Performance requirements and compliance criteria) The next generation of seismic codes 1 Philosophy of seismic design The scope of EC8 EC8 applies

More information

Preliminary Analysis of Potential Vibration Impact to Old Hickory Lock & Dam from Proposed Quarry Operations

Preliminary Analysis of Potential Vibration Impact to Old Hickory Lock & Dam from Proposed Quarry Operations Technical Paper U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG Preliminary Analysis of Potential Vibration Impact to Old Hickory Lock & Dam from Proposed Quarry Operations Old Hickory Lock and Dam, located

More information

Developments in the Safety and Security of Mining Industry Dams

Developments in the Safety and Security of Mining Industry Dams Developments in the Safety and Security of Mining Industry Dams John W. Fredland, P.E. Civil Engineer / Dam Safety Officer Mine Safety and Health Administration Tailings and Mine Waste `08 Conference Dam-Safety

More information

Mr. Paul Dunlap, California Department of Water Resources

Mr. Paul Dunlap, California Department of Water Resources Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction

More information

Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study

Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study Informational Meeting- March 31, 2016 Boxelder B-2/B-3 Watershed Planning Study Agenda Introductions Work Completed to Date Phase 1 Evaluations Alternatives Evaluations Economic Evaluations Draft Watershed

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

DTE Energy St. Clair Power Plant

DTE Energy St. Clair Power Plant DTE Energy St. Clair Power Plant Unit 6 Scrubber Basins CCR Rule Compliance Project Annual Inspection Report - 2017 Project Number: 60546402 June 30, 2017 Prepared by: 27777 Franklin Road, Suite 2000 Southfield,

More information

Seismic Design and Performance Criteria for Large Storage Dams

Seismic Design and Performance Criteria for Large Storage Dams Seismic Design and Performance Criteria for Large Storage Dams Blank line 11 pt Blank line 11 pt M. Wieland Chairman, Committee on Seismic Aspects of Dam Design, International Commission on Large Dams

More information

Dams Safety Program. SAME Industry January 28, Douglas Crum, PE BUILDING STRONG

Dams Safety Program. SAME Industry January 28, Douglas Crum, PE BUILDING STRONG Dams Safety Program SAME Industry Day @UMKC January 28, 2009 Douglas Crum, PE 1993 Flood 1993 1997 & 2001 Floods 1997 & 2001 Floods Katrina Contents 1. Historic Dam Failures 2. Dam Safety Program Essential

More information

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM PLAN FORMULATION ADDENDUM Non-Structural Measure Descriptions Elevate Critical Infrastructure This measure would raise at-risk critical structures above the design inundation level. Elevation would be

More information

Visual Inspection Checklist

Visual Inspection Checklist APPENDIX Q. Visual Inspection Checklist Thispageintentionallyleftblank. VISUAL INSPECTION CHECKLIST CITY OF AUBURN PUBLIC WORKS DEPARTMENT INSPECTION YEAR: TYPE OF INSPECTION: (Informal, Regular, Formal):

More information

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No May 2016

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No May 2016 DEPARTMENT OF THE ARMY ER 1110-2-1806 U.S. Army Corps of Engineers CECW-CE Washington, DC 20314-1000 Regulation No. 1110-2-1806 31 May 2016 Engineering and Design EARTHQUAKE DESIGN AND EVALUATION FOR CIVIL

More information

Dam Safety Inspection Checklist

Dam Safety Inspection Checklist Dam Safety Inspection Checklist Complete All Portions of This Section (Pre-inspection) Date of Inspection: Name of Dam: EAP: (yes, no) OM&I: (yes, no) File Number: Review Inventory - Highlight missing

More information

A Review of the San Clemente Dam Removal & Carmel River Reroute Project

A Review of the San Clemente Dam Removal & Carmel River Reroute Project A Review of the San Clemente Dam Removal & Carmel River Reroute Project Kevan Urquhart, Senior Fisheries Biologist & Carmel River Watermaster MPWMD Project Roles: 1) CDFW rep 2001-2006; 2) Technical Advisory

More information

Kentucky Dam Safety and Floodplain Compliance

Kentucky Dam Safety and Floodplain Compliance Kentucky Dam Safety and Floodplain Compliance Celebrating 10 years KAMM Conference September 10, 2014 Brian Shane Cook, PE, LSIT Kentucky Division of Water (502) 564-3410 ext 4822 Shane.Cook@ky.gov WHY

More information

Coal Combustion Facility Assessment Report. October 20, 2010

Coal Combustion Facility Assessment Report. October 20, 2010 Coal Combustion Facility Assessment Report October 20, 2010 Introduction Stantec Consulting Services Inc. North American Consulting Firm 10,000 Engineers, Geologists, Architects, Scientists and Technicians

More information

Take Me to the Other Side:

Take Me to the Other Side: Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional

More information

The Afton TSF, situated approximately 12 km west of Kamloops, BC has been under care and maintenance since 1997.

The Afton TSF, situated approximately 12 km west of Kamloops, BC has been under care and maintenance since 1997. November 27, 2014 KGHM Ajax Mining Inc. Ajax Project Suite 200-124 Seymour Street Kamloops, BC V2C 2E1 ISSUED FOR USE FILE: V15103098-01 via Email: kate.parsons@kghm.com Attention: Subject: Kate Parsons,

More information

Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project

Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project US Army Corps of Engineers Zac Corum, PE, Hydraulic Engineer Travis Ball, PE, CFM, Hydraulic Engineer Seattle District

More information

County of Calaveras Department of Planning

County of Calaveras Department of Planning Date: July 18, 2013 To: From: Project: Advisory Agencies Amy Augustine, AICP - Planner County of Calaveras Department of Planning Rebecca L. Willis, AICP ~ Planning Director Phone (209) 754-6394 Fax (209)

More information

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND

More information

Review Plan U.S. Army Corps of Engineers Northwestern Division Kansas City District. Tuttle Creek Stilling Basin Wall Drain Repair Manhattan, Kansas

Review Plan U.S. Army Corps of Engineers Northwestern Division Kansas City District. Tuttle Creek Stilling Basin Wall Drain Repair Manhattan, Kansas Review Plan U.S. Army Corps of Engineers Northwestern Division Kansas City District Tuttle Creek Stilling Basin Wall Drain Repair Manhattan, Kansas March 2016 1. PURPOSE AND REQUIREMENTS 1.1 PURPOSE This

More information

by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006

by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006 Principles of Earthquake Engineering of Bridges Part 1: Principles & Approach by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006 Presentation

More information

Geotechnical Design and Factors of Safety

Geotechnical Design and Factors of Safety Geotechnical Design and Factors of Safety Technical Bulletin Ontario Ministry of Natural Resources This publication is available online at: Ontario.ca/dams Ces documents sont offerts en anglais seulement

More information

Resources are available to assist you in completing this analysis in the Risk Analysis Resources section.

Resources are available to assist you in completing this analysis in the Risk Analysis Resources section. Hazard Risk Analysis Dam Failure and Structural Collapse Dam Failure Structural Collapse Buildings Structural Collapse - Transportation Dam Failure and Structural Collapse This section covers both dam

More information

FERC DAM SAFETY PROGRAM

FERC DAM SAFETY PROGRAM National Hydropower Association Hydraulic Power Committee April 28, 2010 Meeting Washington, DC FERC DAM SAFETY PROGRAM FERC Presenters Daniel J. Mahoney, Director William H. Allerton, Deputy Director

More information

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp Geneva Dam Design of a Steep, Temporary, Riprap Ramp A Run-of of-river Dam Analysis for Geneva Dam Credit to: Yu-Chun Su, Ph.D., P.E., CFM David T. Williams. Ph.D., P.E, CFM Presentation Purpose History

More information

DAM SAFETY INSPECTION REPORT GLENWOOD LAKE DAM CLASS B, INTERMEDIATE HAZARD DAM

DAM SAFETY INSPECTION REPORT GLENWOOD LAKE DAM CLASS B, INTERMEDIATE HAZARD DAM May 1, 2013 DAM SAFETY INSPECTION REPORT GLENWOOD LAKE DAM CLASS B, INTERMEDIATE HAZARD DAM Name of Dam: Glenwood Lake Dam Westchester County, NY, NYSDEC ID No. 215-0184 NATDAM ID No. NY13618 Hazard Potential:

More information

2017 ANNUAL DAM AND DIKE INSPECTION REPORT

2017 ANNUAL DAM AND DIKE INSPECTION REPORT 2017 ANNUAL DAM AND DIKE INSPECTION REPORT ASH PONDS WELSH POWER PLANT CASON, TEXAS November, 2017 Prepared by: American Electric Power Service Corporation 1 Riverside Plaza Columbus, OH 43215 GERS-17-067

More information

Freight Street Development Strategy

Freight Street Development Strategy Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed

More information

Plan Rollout Presentation July 31, Michael G. Hahn, P.E., P.H. Chief Environmental Engineer. Southeastern Wisconsin Regional Planning Commission

Plan Rollout Presentation July 31, Michael G. Hahn, P.E., P.H. Chief Environmental Engineer. Southeastern Wisconsin Regional Planning Commission Plan Rollout Presentation July 31, 2014 Michael G. Hahn, P.E., P.H. Chief Environmental Engineer Southeastern Wisconsin Regional Planning Commission # 219703 Racine County Flooding Recommendations and

More information

Mill Pond Dam Modifications Feasibility Study

Mill Pond Dam Modifications Feasibility Study May 1, 2013 Mill Pond Dam Modifications Feasibility Study Village of Goodrich, MI Table of Contents 1. Background...1 1.1 Michigan Department of Environmental Quality (MDEQ) Regulation Dam Safety Unit

More information

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello

More information

REPORT. Giant Nickel Tailings Dams INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT. November 26, 2014

REPORT. Giant Nickel Tailings Dams INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT. November 26, 2014 INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT Giant Nickel Tailings Dams Submitted to: Barrick Gold Inc. PO Box 788 Penticton, BC V2A 6Y7 Attention: Robbin Harmati REPORT Reference Number: 1412161-003-R-Rev1-2000

More information

NOTICE OF PREPARATION

NOTICE OF PREPARATION NOTICE OF PREPARATION Date: June 12, 2014 To: From: Subject: Governor s Office of Planning and Research/State Clearinghouse Unit, Responsible Agencies, Trustee Agencies, and Interested Parties Announcement

More information

Prepared for Urban Drainage and Flood Control District

Prepared for Urban Drainage and Flood Control District BERM FAILURE TECHNICAL ANALYSES SOUTH PLATTE GRAVEL PIT EVALUATION CRITERIA Prepared for Urban Drainage and Flood Control District Wright Water Engineers, Inc. January 2013 121-030.000 TABLE OF CONTENTS

More information

PANAMA CANAL BORINQUEN DAMS AND THIRD SET OF LOCKS OPERATIONS AND MAINTENANCE STRATEGY

PANAMA CANAL BORINQUEN DAMS AND THIRD SET OF LOCKS OPERATIONS AND MAINTENANCE STRATEGY PANAMA CANAL BORINQUEN DAMS AND THIRD SET OF LOCKS OPERATIONS AND MAINTENANCE STRATEGY Rachael V. Bisnett, P.E. 1 Wonnie Kim, P.E. 2 Donald J. Montgomery, P.E. 3 ABSTRACT The new Third Set of Locks for

More information

Dam Failure Hazard Profile

Dam Failure Hazard Profile Appendix F Dam Failure Hazard Profile F-1 THIS PAGE INTENTIONALLY LEFT BLANK F-2 4.3.12. Dam Failure 4.3.12.1. Location and Extent Dam failures most often occur during or after a massive rainfall, flooding,

More information

Information for File # PRH

Information for File # PRH Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County

More information

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall SWM MD-378 Pond Checklist Training 10/17/07 Ken Wolfe Warren Johnson USDA, NRCS Frederick, Maryland ROLES AND RESPONSIBILITIES Small Pond Approval MDE, WMA, Dam Safety Division Authority (COMAR 26.17.04.03)

More information

DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA

DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA Prepared for: ConocoPhillips Alaska, Inc. Anchorage, AK March

More information

Fort Leonard Wood, Missouri. September 2013

Fort Leonard Wood, Missouri. September 2013 Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch

More information

ERDC/GSL TN-14-2 August 2014 Review of Instrumentation and Monitoring for USACE Levees

ERDC/GSL TN-14-2 August 2014 Review of Instrumentation and Monitoring for USACE Levees Review of Instrumentation and Monitoring for USACE Levees By Joseph B. Dunbar, Gustavo Galan-Comas, Lucas A. Walshire, Ronald E. Wahl, Donald Yule, Maureen K. Corcoran, Jose Llopis, and Amber L. Bufkin

More information

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band 11 August 2014 Presentation Outline General Introduction

More information

HAZARD IDENTIFICATION AND RISK ASSESSMENT Revision Date: 04/2017

HAZARD IDENTIFICATION AND RISK ASSESSMENT Revision Date: 04/2017 HAZARD IDENTIFICATION AND RISK ASSESSMENT 23.1 PURPOSE 23.1.1 The purpose of this policy is to help employees identify, analyze and apply control strategies to eliminate or reduce hazardous conditions

More information

Adaptation to Extreme Weather Events and Climate Change

Adaptation to Extreme Weather Events and Climate Change Office of Planning, Environment and Realty Office of Infrastructure Adaptation to Extreme Weather Events and Climate Change SASHTO Meeting Robert Kafalenos, FHWA August 25, 2014 1 Planning for the Future

More information

POND CONSTRUCTION. Woodland Steward Series

POND CONSTRUCTION. Woodland Steward Series POND CONSTRUCTION Woodland Steward Series BOB TWOMEY DISTRICT CONSERVATIONIST USDA NATURAL RESOURCES CONSERVATION SERVICE COURSE OUTLINE DEFINITION OF A POND OR LAKE TYPES OF PONDS GEOLOGIC CONSIDERATIONS

More information

Regulatory Requirements for Site Approval Permit of Nuclear Power Plants

Regulatory Requirements for Site Approval Permit of Nuclear Power Plants Regulatory Requirements for Site Approval Permit of Nuclear Power Plants By Prof. Dr. Abdel-Hamid Nada Chairman of Radiation Control Division NRRA-EGYPT National Center for Nuclear Safety and Radiation

More information

Factors affecting health of Ash Dyke and Preventive Measures. Kukreti RC Chowdhury Ujjwal Naresh D N

Factors affecting health of Ash Dyke and Preventive Measures. Kukreti RC Chowdhury Ujjwal Naresh D N Factors affecting health of Ash Dyke and Preventive Measures Kukreti RC Chowdhury Ujjwal Naresh D N 1 1 ENVIRONMENTAL REGULATIONS Before any construction activity - MOEF clearance is a must MOEF stipulation

More information

DAM AND CANAL SAFETY GUIDELINES

DAM AND CANAL SAFETY GUIDELINES WATER ACT WATER (MINISTERIAL) REGULATION PART 6 DAM AND CANAL SAFETY GUIDELINES Prepared by: Dam Safety and Water Projects Branch Alberta Environmental Protection 8th Floor, Oxbridge Place 9820-106 Street

More information

Aging Outlet Conduits Through Earthen Dams John Harrison, PE Schnabel Dam Engineering, Inc.

Aging Outlet Conduits Through Earthen Dams John Harrison, PE Schnabel Dam Engineering, Inc. Aging Outlet Conduits Through Earthen Dams John Harrison, PE Schnabel Dam Engineering, Inc. PA AWWA Annual Conference April 23, 2015 The Most Important Length of Pipe in your System..is the one through

More information

1. Regulation Requirements

1. Regulation Requirements 16644 est Bernardo Drive, Suite 301 San Diego, CA 92127 Phone: 858.674.6559 Fax: 858.674.6586 www.geosyntec.com STRUCTURAL STABILITY AND FACTOR OF SAFETY ASSESSMENT ASH POND 2 JOLIET 29 STATION OCTOBER

More information

IMPLANT LEVEE. Highly Resilient Disaster Prevention Levee

IMPLANT LEVEE. Highly Resilient Disaster Prevention Levee IMPLANT LEVEE Highly Resilient Disaster Prevention Levee Levee Upgrading Work in Japan Implant Levee Embedded Resilient Structure Twin Steel Sheet Pile Wall System Steel sheet piles are installed into

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

Practical Needs and Approaches for Water Resources Adaptation to Climate Uncertainty

Practical Needs and Approaches for Water Resources Adaptation to Climate Uncertainty Practical Needs and Approaches for Water Resources Adaptation to Climate Uncertainty Rolf Olsen, PhD Senior Lead, Climate Change Institute for Water Resources U.S. Army Corps of Engineers Alexandria, Virginia

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Presentation Overview

Presentation Overview Little Dry Creek Restoration Deep River Flood Risk Management Final Presentation to LCRBDC June 10, 2015 Presentation Overview Project Overview & Background Information Data Collection Model Development

More information

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES April 28, 2016 Table of Contents 3.1 Introduction... 2 3.1.1 Purpose of Chapter 3... 2 3.1.2 Policy vs. Design

More information

Appraisal of the Safety of the Tiga and Challawa Gorge dams, Nigeria APPRAISAL OF THE SAFETY OF THE TIGA AND CHALLAWA GORGE DAMS, NIGERIA.

Appraisal of the Safety of the Tiga and Challawa Gorge dams, Nigeria APPRAISAL OF THE SAFETY OF THE TIGA AND CHALLAWA GORGE DAMS, NIGERIA. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Appraisal of the Safety of the Tiga and Challawa Gorge dams, Nigeria World Bank / Lake

More information

2017 Annual Dam and Dike Inspection Report

2017 Annual Dam and Dike Inspection Report 2017 Annual Dam and Dike Inspection Report Bottom Ash Pond Complex Mitchell Plant Wheeling Power Company & Kentucky Power Company Marshall County, West Virginia October 20, 2017 Prepared by: American Electric

More information

# of Pages Purpose of Calculation 1

# of Pages Purpose of Calculation 1 Project/Plant: Unit(s): Plant Wansley Ash Pond Units 1-2 Title/Subject: Slope Stability Analyses of Ash Pond Separator Dike Purpose/Objective: Analyze slope stability of Ash Pond Separator Dike System

More information

Mining Waste Directive - Risk Assessment requirements

Mining Waste Directive - Risk Assessment requirements Mining Waste Directive - Risk Assessment requirements Jörg Frauenstein Federal Environment Agency (UBA) Dessau-Roßlau Recommendations for a Risk Based Inventory of closed / abandoned waste facilities Scope

More information

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water The diversion works for the Cua Dat CFRD in Vietnam Michel Ho Ta Khanh, Dinh Sy Quat, Prof Pham Hong Giang VNCOLD No 95/10 Chua Boc Street Dong Da District Hanoi Vietnam Abstract The Cua Dat CFRD is constructed

More information

Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District. Kanopolis Dam Emergency Gate Replacement

Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District. Kanopolis Dam Emergency Gate Replacement Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District Kanopolis Dam Emergency Gate Replacement April 2015 1. PURPOSE AND REQUIREMENTS 1.1 PURPOSE This Review Plan is intended

More information

CCR Certification: Initial Structural Stability Assessment (d)

CCR Certification: Initial Structural Stability Assessment (d) Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 CCR

More information

STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES DIVISION OF WATER RESOURCES GUIDELINES FOR DAM BREACH ANALYSIS

STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES DIVISION OF WATER RESOURCES GUIDELINES FOR DAM BREACH ANALYSIS STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES DIVISION OF WATER RESOURCES OFFICE OF THE STATE ENGINEER DAM SAFETY BRANCH GUIDELINES FOR DAM BREACH ANALYSIS February 10, 2010 Telephone (303) 866-3581

More information

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Sub-sector Guideline: (1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Basic Concept A. General Concept Climate change will increase

More information

Jacobi, Toombs, and Lanz, Inc.

Jacobi, Toombs, and Lanz, Inc. Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Volume 2, Chapter 10 - Storage

Volume 2, Chapter 10 - Storage Volume 2, Chapter 10 - Storage Users Guidance: If a UDFCD Section number in this chapter is skipped: It was adopted as is; please refer to that Section in the corresponding UDFCD Manual, Volume, Chapter

More information

ENGINEERING AND CONSTRUCTION BULLETIN

ENGINEERING AND CONSTRUCTION BULLETIN ENGINEERING AND CONSTRUCTION BULLETIN No. 2017-15 Issuing Office: CECW-CE Issued: 14 Jul 17 Expires: 14 Jul 19 SUBJECT: Managed Overtopping of Levee Systems CATEGORY: Guidance APPLICABILITY: The U.S. Army

More information

Modeling Climate Change Impacts on Flooding in Alaska

Modeling Climate Change Impacts on Flooding in Alaska Modeling Climate Change Impacts on Flooding in Alaska Thursday, June 5, 2014 Presented by: Shane Parson, PhD, PE, CFM Kimberley A. Pirri, PE, CFM R. Scott Simmons, CFM, CPM Agenda Project Background Seward,

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Anchorage Port Modernization Concept for Seismic Resiliency

Anchorage Port Modernization Concept for Seismic Resiliency May 9, 2017 State of Alaska DHS-EM EQ Workshop Anchorage Port Modernization Concept for Seismic Resiliency Presented by: Todd Cowles, P.E. Port Engineer PRESENTATION OVERVIEW Port of Anchorage Overview

More information

SECTION 11: REGULATORY FLOODWAYS

SECTION 11: REGULATORY FLOODWAYS SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...

More information

FINAL REPORT DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia. Submitted to:

FINAL REPORT DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia. Submitted to: AMEC Earth & Environmental a division of AMEC Americas Limited 2227 Douglas Road, Burnaby, BC Canada V5C 5A9 Tel +1 (604) 294-3811 Fax +1 (604) 294-4664 www.amec.com FINAL REPORT DAM SAFETY REVIEW Mount

More information

Recommended Specifications, Commentaries, and Example Problems

Recommended Specifications, Commentaries, and Example Problems Draft Final Report Volume 2 to the NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM (NCHRP) on Project 12-70 Seismic Analysis and Design of Retaining Walls, Buried Structures, Slopes, and Embankments Recommended

More information