Design and performance of a 15m deep excavation for a wagon tippler

Size: px
Start display at page:

Download "Design and performance of a 15m deep excavation for a wagon tippler"

Transcription

1 Design and performance of a deep excavation for a wagon tippler S.R. Gandhi Professor in Dept. of Civil Engineering Indian Institute of Technology Madras, India srg@civil.iitm.ernet.in bstract: s a part of bulk handling facility at one of the major ports on the east coast of India, a deep excavation was carried out for construction of a wagon tippler and belt conveyor tunnel. RCC diaphragm wall has been provided as a temporary support for x 70m excavation. During execution, the dewatering system provided was found to be inadequate in view of the high permeability of cohesionless strata. To meet construction schedule, direct pumping of water was adopted from the excavation which resulted in large quantity of seepage into the excavation and settlement of the diaphragm wall panels. This also resulted in considerable subsidence of the surrounding area resulting in severe distresses to a building adjacent to the diaphragm wall. This paper describes the details of the structure, strata condition, design of excavation, problems faced during execution and the remedial measures adopted. INTRODUCTION t Paradip Port on the east coast of India, mechanized bulk handling system has been created which includes a wagon tippler with hopper and belt conveyor below the ground level to receive bulk material from railway wagon. The structure is located within the harbour where ground water table is very close to the ground level and strata is essentially cohesionless with high permeability. picture of the excavation is shown in Fig.. The main facility measures x 70m x deep and a perpendicular tunnel to carry the product to surface through a belt conveyor. The entire perimeter of this T shaped facility required a temporary support for excavation. fter construction of the diaphragm wall, dewatering was carried out followed by excavation of soil. Each stage of excavation was for m depth and horizontal struts were provided m c/c before excavating to the next stage. fter 0m depth, it was noticed that deep wells provided around the excavation were not adequate and the water level inside the excavation could not be lowered. To meet the construction schedule, the water level within excavation was lowered by placing 6 pumps into the excavation in small sumps. Direct removal of water within the excavation created a gradient between the outside ground water level and the water level within the diaphragm wall. This resulted in large quantity of seepage of water into the excavation. long with seepage, large quantity of silt and fine sand seems to have entered the excavation resulting in loss of frictional resistance for the diaphragm wall and subsidence of some of the diaphragm wall panels. This also resulted in significant settlement of the surrounding area. Due to excessive seepage into the excavation, following consequences were noticed: i) Settlement of some of the diaphragm wall panels. ii) Slippage of struts and buckling of the members of strut due to eccentricity and iii) Severe cracks in the control building adjacent to the excavation. Fig.. Picture of excavation Foundation execution for such excavation required RCC diaphragm wall as temporary wall in view of the large depth and to reduce the number of struts for the construction convenience. In view of the stringent requirement of waterproofing, use of RCC diaphragm wall itself as vertical wall of the facility was not possible. It was therefore planned to complete the excavation with strutted diaphragm wall and then build the main structure within the excavated area. The base raft and vertical walls were cast-in-situ against formwork and provided with water proofing treatment.. DETILS OF EXCVTION The wagon tippler requires RCC watertight chamber measuring 70m x. The depth upto bottom of raft is about 7m for the central x area, whereas the depth at either end is about 8m. Plan of the structure is shown in Fig. and typical cross sections at shallow and deep portion are shown in Fig. and Fig. respectively. The penetration of 600mm thick diaphragm wall is generally m beyond the excavation level. This penetration was considered adequate in view of the steel struts provided m centre to centre. mong the tunnel wall the depth of diaphragm wall was gradually varied to ensure m

2 0 m 70m CONVEYOR TUNNEL C D E F Fa G H J K L M N P 600 THK DIPHRGM WLL OPEN PIT m m IN-SITU CONCRETE WLL Fig.. Plan of Wagon Tippler FSL.0 FILL RL.00 NGL FSL RL-9.00 RL-5.60 Fig.. Typical Section of THK DIPHRGM WLL centre to centre. mong the tunnel wall the depth of diaphragm wall was gradually varied to ensure m penetration below the excavation level. No diaphragm was provided at the junction between tunnel and the wagon tippler chamber. The ground level at the time of construction was +.0m which is to be raised to +.m after completion of the structure. The water table is almost at +.0m level.. STRT CONDITION The site area is fairly leveled having average elevation of +.m above mean sea level. The strata comprises essentially of silty fine to medium sand with an average permeability of 5.5X0-5 m/sec up to the explored depth of 8m. No rock or impervious layers has been encountered. The ground water table is about m below the ground level. Soil profile comprises of the following layers: Layer : From +.m to.m is clayey silt / silty clay having SPT(N) value in the range of to. Layer : From.m to 0.m is gray color silty fine to medium sand occasionally with clay binders. The (N) value in this layer varies from 5 to 0. Layer : From 0.m to 8.9m, the strata is clayey silt to silty clay having SPT(N) value in the range of 6 to 0. Layer : From 8.9m to explored depth of 8m, the strata is silty medium to coarse sand with traces of a mica and kankars. The SPT(N) value in this layer varies from 5 to 5.. DEWTERING SCHEME For the purpose of lowering ground water table, 8 deep wells were provided at location shown in fig.5. The depth of well varies from to m. Details of well depth, size of pump and discharge recorded is shown in Table. The size of pump varied to make use of the available equipments. The peak discharge of all the pumps together is about 78 m /hour. ased on the subsoil investigation carried out, the permeability of the silty sand strata is estimated as 5.5x0-5 m/sec. s per known theories of dewatering, the total discharge required for lowering the ground water table below is estimated as follows: πk q = l ( H h ) n R where, q = Total rate of discharge required in m /hour. k = Permeability constant in m/sec(5.5x0-5 ) H = Hydrostatic head of ground water level above the impervious layer () h = Hydrostatic head in the bore well after dewatering (m) R = Radius of influence for the given drawdown.

3 = Equivalent radius of the excavation = F = m π F =rea of excavation in m (800 m ) Table Dewatering well discharge details Sl. No. Depth of Well (m) Capacity verage Discharge Per Hr. (Ltrs) Remarks FSL.0 LL RL.00 FSL RL-9.00 RL RL-0.60 FLEXILE PIPE OPEN PIT 600 THK DIPHRGM WLL Fig.. Typical Section of - Substituting values the total discharge required for a drawdown upto works out to 65 m /hour. This is much higher compared to the total discharge achieved by the 8 deep wells provided around the excavation. The water level outside the wall could not be lowered below 5.0m level. To meet the construction schedule, it was decided to provide 6 pumps in open sumps made within the excavation to pump out the water directly from the excavation. This resulted in large seepage into the excavation and inflow of fine soil particles into the excavation. fter noticing the large subsidence in the surrounding areas and settlement of some of the wall panels, the direct pumping from the 6 wells within the excavation was discontinued. The programme of dewatering was reviewed to avoid such subsidence. 5. REMEDILMESURES s can be seen from Table, out of the 8 wells provided 5 wells were not operating due to various reasons. It was therefore decided to commission all the 8 wells. Some of the wells were found to be blocked due to the seepage of fines which were cleared by flushing and made operational. The capacity of pumps were increased in some of the wells from or 5 horse power to 5 horse power. With above changes it was possible to achieve a total discharge of 5 m /hour. No diaphragm wall was provided at the junction between the wagon tippler chamber and the conveyor tunnel. This area was considered to be a zone of heavy seepage due to lack of impervious barrier. It was therefore decided to provide a curtain grout by insitu injection of cement slurry. The grouting was carried out at the junction over the entire width of the tunnel between the excavated level of upto 7.. The width of the grouted area was -m. In addition, the outer side of the diaphragm wall, particularly along the X central area was grouted between elevation 0m to 9m to ensure plugging of any cavity that might have taken place around the diaphragm wall due to the seepage. lso, grouting pipes were inserted at the 5.00 m 0 No 0 0 HP HP 7 6 HP 5 0 No 6 HP HP HP COMP COMP HP 69 0 COMP 0 5 HP 800 No installed Not operating Not 0 HP HP Not 6 0 COMP HP COMP Not joints of diaphragm wall panels to ensure no seepage of water / soil through the joint. With enhanced pumping capacity the ground water table outside the diaphragm wall was lowered up to 9m (instead of achieved earlier). With reduced water table outside, it was then possible to adopt direct pumping within the excavation. This is because the hydraulic gradient now available was less and hence safe to prevent sand boiling. The settlement of diaphragm wall panels were continuously monitored and were found to have stabilized with the enhanced pumping. Dewatering through all the wells were continued till the completion of construction of the inner RCC chamber of the wagon tippler and back filling of the gap between the diaphragm wall and the wall of the wagon tippler. The backfilling was carried out after completion of water proofing treatment on the outerside of the wagon tippler walls. In view of the limited space available, back filling was done with clean sand placed in 00mm thick layers and compaction was achieved using surface vibrator. 6. DMGE TO DJCENT UILDING The subsidence created by heavy seepage into the excavation resulted in several cracks in the adjacent RCC uilding.

4 m.0 (NO PUMP) R 8mm P 56mm N 66mm (PUMP 0HP) NOTE:- (NEW ORE) (PUMP-HP) CONTROL UILDING 0 CONVEYOR TUNNEL (PUMP 0HP) (PUMP HP) m (PUMP 6HP) LL DIMENSIONS R m Q I 8mm m O G mm mm M E 7mm m C mm m 9mm 8.8 (PUMP-HP) 0.8 EXCVTION LEVEL EXCVTION LEVEL -.6 EXCVTION LEVEL (PUMP H J 5m 59mm H 9mm F 9mm D (PUMP 6 HP) (PUMP HP) (NEW ORE) (PUMP 6 HP) m (PUMP 5HP) 7 59mm K m L Fig.5. Lay-out of Dewatering Wells The two-storied RCC building is meant for housing of the control panels for the mechanized operation. The building measures about x0m in plan and supported on RCC piles with founding level upto m. The plan of the building with observed settlements of various columns is shown in Fig.6. s can be seen, the settlements are not uniform and due to the differential settlements the RCC framed building had severe cracks in the wall panel and RCC structure. picture with typical damage is shown in Fig.7. The settlements of the RCC building columns as well as of the diaphragm wall panels were recorded using surveying equipments. Target points were marked with oil paint on the structure and the RL of the target point were monitored with reference to a fixed bench mark about 00m away from the excavation. Similarly, the settlement in the adjoining ground were monitored using surveying staff. Ideally, the structure should have been built only after completion of the wagon tippler and backfilling of the same. However, due to the tight construction schedule, it was decided to take up the building construction along with the wagon tippler construction. In spite of improved dewatering system, it was feared that some more subsidence may take place. Therefore no repair was carried out till the entire wagon tippler construction was completed and the sides of the wall were backfilled. Even after the cracks, the structure was found to be otherwise safe for use with suitable strengthening. Grouting was carried out in soil strata with minimum points around each pile group of a column. The average depth of grout was 8-0m below the ground level. The cement consumption in each grout hole varied from 50 to 500 kg. fter completion of the grouting, the settlements of the column were found to have stabilized Fig.7. Picture Showing Typical Damage and thereafter the building repair was taken up. The building could be put to operation and has been functioning satisfactorily. Fig.6. Settlements in Control Room (in mm) construction. Unless adequate precautions are taken, uncontrolled seepage into the excavation can create lot of problems in excavation, construction and can also create large subsidence in the surrounding area. If the excavation is adjacent to existing structure, the design has to be carefully made to ensure no damage to the structure on account of subsidence. Whenever diaphragm wall is used as temporary support for the excavation, the water tightness of the joint plays an important role. The end stopper shall be designed such a way that the joint is fairly water tight. In case of doubt it is better to grout the joint prior to excavation and dewatering. lso penetration of the wall below excavation line shall be safe both for the passive resistance required as well as for reducing the hydraulic gradient to avoid soil boiling. 7. SUMMRY The execution of deep excavation for the wagon tippler revealed the importance of proper dewatering scheme for such Fig.7. Picture Showing Typical Damage

5 5

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

Ground Improvement Techniques

Ground Improvement Techniques GRD Journals Global Research and Development Journal for Engineering Recent Advances in Civil Engineering for Global Sustainability March 2016 e-issn: 2455-5703 Ground Improvement Techniques 1 Nimisha

More information

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 The Institution of Engineers of Ireland Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 MODULE 4 RETAINING STRUCTURES DEEP EXCAVATIONS

More information

Lecture 11. WATER PUMPING EQUIPMENT and DEWATERING SYSTEM

Lecture 11. WATER PUMPING EQUIPMENT and DEWATERING SYSTEM Lecture 11 WATER PUMPING EQUIPMENT and DEWATERING SYSTEM TSP-308 MPK Ferdinand Fassa dewatering The purpose is to remove water from an excavation without causing instability in either the side slopes or

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

Compaction and Jet Grouting

Compaction and Jet Grouting Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

Building Construction

Building Construction Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When

More information

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel

More information

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5 .364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. Due: Friday December 2. This question concerns the stability of an open slope cutting that will be used to provide construction access for a 3.2m deep

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

Advanced Construction Techniques. Underpinning. Underpinning

Advanced Construction Techniques. Underpinning. Underpinning is the installation of temporary or permanent support to an existing foundation to provide either additional depth or an increase in bearing capacity. There are several existing conditions which may lead

More information

Risk Management of the Restoration of Shanghai Metro Line 4

Risk Management of the Restoration of Shanghai Metro Line 4 ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu

More information

Underpinning. Underpinning

Underpinning. Underpinning is the installation of temporary or permanent support to an existing foundation to provide either additional depth or an increase in bearing capacity. There are several existing conditions which may lead

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Contents. Glossary 9. Foreword 10

Contents. Glossary 9. Foreword 10 Glossary 9 Foreword 10 1 Design considerations 11 1.1 Introduction 11 1.2 Client's general requirements 11 1.3 The ground 11 1.3.1 The concept of effective stress 11 1.3.2 Ground profile 13 1.3.3 Groundwater

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION 01 content 1.DEFINITION 2. CONSTRUCTION CONSIDERATION 3. DESIGN REQUIREMENT 4.METHOD OF CONSTRUCTION a. Open Cut Construction

More information

Foundation Engineering

Foundation Engineering Foundation Engineering P.C. Varghese Foundation Engineering P.C. VARGHESE Honorary Professor, Anna University, Madras Formerly, Professor and Head, Department of Civil Engineering Indian Institute of Technology

More information

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more. TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported

More information

Figure (12.1) Foundation Grouting

Figure (12.1) Foundation Grouting Chapter 12 - Foundation Grouting 12. Foundation Grouting 12.1. Introduction: The construction of structures on weak ground often requires the soil to be improved in order to ensure the safety and the stability

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

ALMEDA TUNNEL PAST, PRESENT AND FUTURE

ALMEDA TUNNEL PAST, PRESENT AND FUTURE ALMEDA TUNNEL PAST, PRESENT AND FUTURE Ravi Kaleyatodi, P.E., CPM Senior Assistant Director, City of Houston Ravi.kaleyatodi@cityofhouston.net Paul C. Wallick, P.E., Senior Project Manager Patricia Frayre,

More information

An Introduction to Spread Footings and Mat Foundations

An Introduction to Spread Footings and Mat Foundations An Introduction to Spread Footings and Mat Foundations J. Paul Guyer, P.E., R.A. Editor Paul Guyer is a registered civil engineer, mechanical engineer, fire protection engineer, and architect with over

More information

Comparison of dewatering schemes for foundation pits under complex hydrogeological conditions

Comparison of dewatering schemes for foundation pits under complex hydrogeological conditions IOP Conference Series: Earth and Environmental Science PAPER OPEN ACCESS Comparison of dewatering schemes for foundation pits under complex hydrogeological conditions To cite this article: H M Wu et al

More information

Grouting for Freezing

Grouting for Freezing Grouting for Freezing Joseph A. Sopko, Ph.D., P.E. M.ASCE 1, Adam T. Curry, P.E. M.ASCE, 2 and Gregory T. Ziegler, P.E., M.ASCE 3 1 Moretrench American Corporation, 100 Stickle Ave., Rockaway, NJ 07866;

More information

Foundation Engineering ECIV 4352

Foundation Engineering ECIV 4352 Foundation Engineering ECIV 4352 Instructor : Dr. Jehad Hamad 2016-2015 Chapter (11) Deep Foundation Chapter 11 Pile Foundation Foundation- Design Considerations Factors to be taken into consideration

More information

Slurry Trench / Diaphragm Walls

Slurry Trench / Diaphragm Walls UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Slurry Trench / Diaphragm Walls CM 420 TEMPORARY

More information

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Michigan Department Of Transportation 3703F (11/06) SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Page 1 of 5 1 Materials 1.1 Pipe (a) Pipe shall be specifically designed and certified for microtunneling

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment rotary drill hydro-mill backhoe Clamshell + Kelly bar VERTICAL BARRIERS SLURRY

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

Forensics by Freezing

Forensics by Freezing Forensics by Freezing Joseph A. Sopko, Ph.D., P.E., M.ASCE Moretrench American Corporation, 100 Stickle Avenue, Rockaway, NJ 07866, e-mail: jasopko@moretrench.com ABSTRACT Subsurface conditions in water

More information

SECTION PRECAST CONCRETE MANHOLES

SECTION PRECAST CONCRETE MANHOLES SECTION 02601 PRECAST CONCRETE MANHOLES PART 1 GENERAL 1.1 The work specified in this section shall include the furnishing, hauling, and placing of all precast manholes shown on the drawings and as specified

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad -00 03 CIVIL ENGINEERING QUESTION BANK Course Name : GROUND IMPROVEMENT TECHNIQUES Course Code : A012 Class : III B. Tech IISemester

More information

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT 325.0 957 100.130 F.L.=99.780 12205 2300 2300 2300 2720 125 EXPANSION GAP 125 EXPANSION GAP OUTER COVER PLATE 640X40X1070 938.5 1350 1350 1350 1282.5 1350 1350 1122.5 1350 1356.5 1356.5 1350 1122.5 1350

More information

A. Section includes temporary excavation support and protection systems.

A. Section includes temporary excavation support and protection systems. SECTION 31 50 00 - EXCAVATION SUPPORT AND PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Reyn Hashiro 1, P.E., M. ASCE, Devin Nakayama 2, P.E. M. ASCE, and James Kwong 3, Ph.D., P.E., M. ASCE 1 Associate, Yogi Kwong

More information

Groundwater Monitoring Plan. Table of Contents

Groundwater Monitoring Plan. Table of Contents Table of Contents 1.0 Introduction... 3 2.0 Definitions and Acronyms... 5 3.0 Graving Dock Site... 6 3.1 Site Investigation... 6 3.2 Excavation... 7 4.0 Dewatering... 7 4.1 Deep Wells... 8 4.2 Cut-Off

More information

Foundations. Foundations form the major part of a buildings substructure (along with the rising walls, hardcore and ground floors)

Foundations. Foundations form the major part of a buildings substructure (along with the rising walls, hardcore and ground floors) Foundations Foundations form the major part of a buildings substructure (along with the rising walls, hardcore and ground floors) Once the substructure is complete the building is out of the ground and

More information

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high 1 2 Demand for space in cities often makes it essential to use space below buildings. The concept of deep basement technology has been employed since the middle of last century, but is becoming more popular

More information

Golder Associates Innovative Applications (GAIA) Inc.

Golder Associates Innovative Applications (GAIA) Inc. Golder Associates Innovative Applications (GAIA) Inc. Environmental and Geotechnical Applications of Cutter Soil Mixing RemTech October, 2007 Presented by: Brian Wilson www.gaiacontractors.com What is

More information

SECANT PILE. Introduction:

SECANT PILE. Introduction: SECANT PILE Introduction: Over the last few decades construction of retaining walls in urban areas has grown significantly, as a result of territorial and economical development of the cities. In most

More information

Dewatering Fly Ash for Remediation: Two Approaches

Dewatering Fly Ash for Remediation: Two Approaches 2015 World of Coal Ash (WOCA) Conference in Nasvhille, TN - May 5-7, 2015 http://www.flyash.info/ Dewatering Fly Ash for Remediation: Two Approaches Gregory M. Landry, P.E. Moretrench American Corporation,

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 November 2015 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT TABLE OF CONTENTS D 422.01 D 422.02 D 422.03

More information

IGC. 50 th INDIAN GEOTECHNICAL CONFERENCE CONSTRUCTION PRACTICES OF DEEP BASEMENTS ANIL JOSEPH 1, A MURALIKRISHNA 2 ABSTRACT

IGC. 50 th INDIAN GEOTECHNICAL CONFERENCE CONSTRUCTION PRACTICES OF DEEP BASEMENTS ANIL JOSEPH 1, A MURALIKRISHNA 2 ABSTRACT CONSTRUCTION PRACTICES OF DEEP BASEMENTS ANIL JOSEPH 1, A MURALIKRISHNA 2 1 ANIL JOSEPH, Geostructurals (P) Ltd, Cochin, Kerala, India. E-mail:aniljoseph@geostructurals.com 2 A MURALIKRISHNA, Associate

More information

Typical flow net for the flow beneath the dam with heel cutoff wall [Lambe & R.V. Whitman (1979)]

Typical flow net for the flow beneath the dam with heel cutoff wall [Lambe & R.V. Whitman (1979)] Typical flow net for the flow beneath the dam with heel cutoff wall [Lambe & R.V. Whitman (1979)] Typical flow net for the flow beneath the dam with toe cutoff wall [Lambe & R.V. Whitman (1979)] Exit gradient

More information

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...

More information

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2 Table of Contents 1. Introduction... 1 1.1 Site Information... 1 1.2 Site Characteristics... 1 1.3 Hydrogeologic Setting... 2 2. Closure Plan... 5 2.1 Closure Description... 5 2.2 Closure Timeframe...

More information

IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY WATER MANAGEMENT OF CONSTRUCTION SITE Patil V.A*, Gawade S.

IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY WATER MANAGEMENT OF CONSTRUCTION SITE Patil V.A*, Gawade S. IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY WATER MANAGEMENT OF CONSTRUCTION SITE Patil V.A*, Gawade S.L * Asst.prof. sant gajanan maharaj college of engineering, mahagon

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

Atterberg limits Clay A Clay B. Liquid limit 44 % 55% Plastic limit 29% 35% Natural water content 30% 50%

Atterberg limits Clay A Clay B. Liquid limit 44 % 55% Plastic limit 29% 35% Natural water content 30% 50% CE 6405 SOIL MECHANICS UNIT I INTRODUCTION Part A 1. Distinguish between Residual and Transported soil. 2. Give the relation between γ sat, G, γ w and e 3. A compacted sample of soil with a bulk unit weight

More information

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services COMPANY PROFILE Soil Services position in the industry of Special Subterranean and Deep Foundations is based on the successful combination of skills, knowledge and experience of its employees and partners.

More information

July 2011 BUREAU OF INDIAN STANDARDS. Draft Indian Standard

July 2011 BUREAU OF INDIAN STANDARDS. Draft Indian Standard FOR COMMENTS ONLY DOC: WRD 8 (551)C July 2011 BUREAU OF INDIAN STANDARDS Draft Indian Standard GUIDELINES FOR DESIGN OF UNDER-SEEPAGE CONTROL MEASURES FOR EARTH AND ROCKFILL DAMS (FIRST REVISION OF IS

More information

reinforced besser block retaining walls

reinforced besser block retaining walls reinforced besser block retaining walls Preface The designs shown in the brochure are based on limit state design in accordance with the provisions of AS4678-2002 Earth retaining structures standard including

More information

Tunnelling and Underground. Construction Technology

Tunnelling and Underground. Construction Technology Construction Technology Course Lectures Part 2.2 Ground Improvement Dr Ákos TÓTH 1 Ground Treatment and Improvement In order to improve the construction process when tunnelling through poor ground, a double

More information

TIDAL EROSIONAL EFFECTS ON A BULKHEAD SYSTEM by Ronald M. Noble 1, M. ASCE, Wolfgang H. Roth 2, M.ASCE and Uday K. Patil 3, M.ASCE

TIDAL EROSIONAL EFFECTS ON A BULKHEAD SYSTEM by Ronald M. Noble 1, M. ASCE, Wolfgang H. Roth 2, M.ASCE and Uday K. Patil 3, M.ASCE TIDAL EROSIONAL EFFECTS ON A BULKHEAD SYSTEM by Ronald M. Noble 1, M. ASCE, Wolfgang H. Roth 2, M.ASCE and Uday K. Patil 3, M.ASCE ABSTRACT In the design and construction of waterfront bulkhead systems,

More information

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1 DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE6502 - FOUNDATION ENGINEERING Subject Code: CE6502 UNIT 1 1. What are the informations obtained

More information

Soil Improvement by Compaction Grouting

Soil Improvement by Compaction Grouting CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 31-3223.12 Soil Improvement by Compaction Grouting Part 1 - General 1.01 Introduction

More information

August 1, 2013 Reference No S048 Page 1 of 5

August 1, 2013 Reference No S048 Page 1 of 5 August 1, 2013 Reference No. 1201-S048 Page 1 of 5 Caledon Villas Corp. 55 Blue Willow Drive Woodbridge, Ontario L4L 9E8 Attention: Mr. John Spina Re: Addendum to Soil Investigation for Proposed Residential

More information

UNIT V RETAINING WALLS RETAINING WALL 2.5. Retaining walls are structures used to retain earth or water or other materials such as coal, ore, etc; where conditions do not permit the mass to assume its

More information

Lesson Learned. Collapse of Diaphragm Wall Trench. Case study. Suez Canal Syphon Project

Lesson Learned. Collapse of Diaphragm Wall Trench. Case study. Suez Canal Syphon Project Lesson Learned Collapse of Diaphragm Wall Trench Case study Suez Canal Syphon Project Bauer Egypt Ashraf Wahby June, 2016 List of Contents 1. Introduction 3 2. Project Description 3 3. Collapse 4 4. Known

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS Peter, BAUER Spezialtiefbau GmbH, Schrobenhausen, Germany, +49 8252 974266, +49 8252 971496, peter.banzhaf@bauer.de

More information

FINITE ELEMENT ANALYSIS OF DEEP BASEMENT CONSTRUCTION OF BANK OF THAILAND ALONG CHAO PHRAYA RIVER CLOSED TO HISTORICAL PALACES

FINITE ELEMENT ANALYSIS OF DEEP BASEMENT CONSTRUCTION OF BANK OF THAILAND ALONG CHAO PHRAYA RIVER CLOSED TO HISTORICAL PALACES FINITE ELEMENT ANALYSIS OF DEEP BASEMENT CONSTRUCTION OF BANK OF THAILAND ALONG CHAO PHRAYA RIVER CLOSED TO HISTORICAL PALACES Abstract Wanchai Teparaksa Department of Civil Engineering, Chulalongkorn

More information

SECTION VI SANITARY SEWERS

SECTION VI SANITARY SEWERS SECTION VI SANITARY SEWERS VI-1. DESIGN GUIDELINES Sewer collection lines and appurtenant structures within the jurisdiction of City of Paso Robles shall be constructed in accordance with plans prepared

More information

Advanced Construction Techniques. Ground Freezing

Advanced Construction Techniques. Ground Freezing Ground freezing is used for groundwater cutoff, for earth support, for temporary underpinning, for stabilization of earth for tunnel excavation, to arrest landslides and to stabilize abandoned mineshafts.

More information

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) #47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) by Michael J. Carey Michael J. Fisher Steven R. Day Presented at: International Containment Technology

More information

Large-diameter bored piles and Large-hole drillings Applications

Large-diameter bored piles and Large-hole drillings Applications Large-diameter bored piles and Large-hole drillings Applications Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(4):69-74 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Deformation monitoring and analysis of deep foundation

More information

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 2004 Specifications CSJ 1062-04-047 SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 1. Description. Repair, rehabilitate, or replace deteriorated, leaking, or structurally unsound existing sanitary sewer

More information

CE 6012 Ground Improvement Techniques Question Bank

CE 6012 Ground Improvement Techniques Question Bank CE 6012 Ground Improvement Techniques Question Bank Unit I INTRODUCTION Role of ground improvement in foundation engineering - methods of ground improvement Geotechnical problems in alluvial, laterite

More information

August 13, Geotechnical Recommendations, New Physical Education Building, Chabot College, Hayward, California

August 13, Geotechnical Recommendations, New Physical Education Building, Chabot College, Hayward, California August 13, 2008 003-09176-17 Douglas Horner, AIA Chabot Las Positas Community College District 25555 Hesperian Boulevard Hayward, California 94545 Subject: Geotechnical Recommendations, New Physical Education

More information

Construction Risk Management of Deep Braced Excavations in Cairo

Construction Risk Management of Deep Braced Excavations in Cairo Australian Journal of Basic and Applied Sciences, 1(4): 506-518, 2007 ISSN 1991-8178 Construction Risk Management of Deep Braced Excavations in Cairo Ahmed Hosny Abdel-rahman Associate Prof., Civil Eng.

More information

Capstone C O N S U L T A N T S

Capstone C O N S U L T A N T S Ultrasonic Pulse Velocity Tests These tests are primarily done to establish: the homogeneity of concrete presence of cracks, voids and other imperfections changes in quality of concrete over time this

More information

CSI SPECIFICATIONS SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section

CSI SPECIFICATIONS SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section 07 16 16 This section includes Krystol T1 crystalline waterproofing, applied to new or existing concrete substrates, above or below grade, on either dry

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SPECIAL SPECIFICATION 4653 Polypropylene Pipe 2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene

More information

MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION

MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION Juha Forsman, M.Sc.(Civ.Eng.) Ramboll Finland Oy MASS STABILISATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION 1. GEOTECHNICAL

More information

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT By John Kvinsland Malcolm Drilling Company, Kent, Washington Bob Plum ASCE, P.E., Principal Kleinfelder Consultants, Seattle

More information

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras PRESTRESSED CONCRETE STRUCTURES Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras Module 01: Introduction, Prestressing Systems and Material Properties Lecture

More information

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

Prepared by Elie F. Issa, Eng. D.E.C. August 2016 Prepared by Elie F. Issa, Eng. D.E.C. August 2016 SAMA BEIRUT Sama Beirut is the tallest reinforced concrete tower in Lebanon soaring at a height of 220m from ground level Project Entities Owner Antonios

More information

GEO ENGINEERING COMPANY PRIVATE LIMITED FOR STRONG FOUNDATIONS AND STABLE STRUCTURES

GEO ENGINEERING COMPANY PRIVATE LIMITED FOR STRONG FOUNDATIONS AND STABLE STRUCTURES GEO ENGINEERING COMPANY PRIVATE LIMITED FOR STRONG FOUNDATIONS AND STABLE STRUCTURES Regd. Office: 108-E-3, 6 th MAIN ROAD, 3 RD PHASE, PEENYA INDUSTRIAL AREA, BANGALORE - 560 058 INDIA Tel: 080 28392170/71

More information

Ching Guan Kee ABSTRACT

Ching Guan Kee ABSTRACT Japanese Geotechnical Society Special Publication The 15th Asian Regional Conference on Soil Mechanics and Geotechnical Engineering Effects of base grouting and deep cement mixing on deep foundation bored

More information