1 EXISTING CONDITIONS REPORT 84 AUSTIN ROAD, SEAFORD JULY 2016
2 INTRODUCTION This report has been prepared to assist with the review of the existing conditions at the existing St Anne s Catholic Church at. The report primarily focuses on the current inadequacies of the existing facility and the proposed works that that could be adopted to remedy the building deficiencies. SITE ANALYSIS The subject site is located in a Residential 1 Zone that fronts Austin Road along the northern boundary, while Brunel Road forms the boundary along the west, with reserve parkland to the south. The site is rectangular in shape and forms part of the larger St Anne s Religious Parish and Education Facilities. The Church was constructed in the early 1980s and materials consist mainly of face brickwork, aluminium framed windows and a fabric roof. The approximate building footprint is 670 m2. SITE CONTEXT PHOTO The image below shows the site context of the church, parish centre and school buildings.
3 EXISTING CONDITIONS There are a number of serious deficiencies that are both structural and superficial with the current building. The plan below outlines the 3 main areas of concern: 1. the fabric roof 2. the aluminium windows 3. the internal fitout. (note North is to the south of the page in this plan image)
4 1. EXISTING ROOF STRUCTURE The existing roof structure has reached the end of its life cycle. Although perhaps successful in other climates, the current roof is a poor design choice for the climate of Victoria. It is cold in Winter (zero insulation) and hot in Summer. Supports are also compromised & rusted. Use of a new material is worth considering, Colorbond ultra steel or a thicker gauge product that will allow some insulation - note significant cost implications Major issues leaks in areas where fabric falling fixing to the building has pulled away original design did not work like it was intended (wrong climate) cold/hot existing tension cables have commenced oxidization EXISTING CONDITION PHOTOGRAPHS The existing ties for the connection of the roof to the brickwork have failed Existing Roof is covered in stains & leaks in areas
5 2. THE WINDOWS The existing windows are bronzed anodized windows. Many of the windows have also become weathered and are now in a state beyond fixing. The doors do not open which is dangerous in an emergency. The exits are compromised. There is no protection from the roof from weathering. The sills on many of the windows have rusted out, doors have swelled and require immediate attention. Solution / Recommendation Replacement majority of windows will need to replaced A patch repair band aid approach will not resolve the issue EXISTING CONDITION PHOTOGRAPHS
6 3. THE CONDITION OF THE INTERNAL FINISHES There are several key areas that require remedial works Leaks at the rear Toilets are in poor condition & Disabled Toilet is non-compliant Kitchen is poorly designed and has broken elements Storage is poorly designed Meeting room also has a poor layout Lack of storage options It is due for renovation to improve serviceability Refurbish The kitchen WCS: Compliance Internals refresh mission brown brick aesthetic is quite tired Lighting and power review required Heating and cooling required to be upgraded EXISTING CONDITION PHOTOGRAPHS Leaks to the ex Hall
7 4. EXTERNAL WORKS The eternal elements of the original church are also problematic. The original concept that the roof drains to the moat is both dangerous and no longer compliant. The potential risk of a child drowning is here is probable. As well as this, the structure is beginning to show signs of rust and will eventually fail due to stress, and pavements are cracked and need replacing. EXISTING CONDITION PHOTOGRAPHS
8 ST. ANNE'S CATHOLIC CHURCH, SEAFORD OPINION OF PROBABLE COSTS BUILDING COSTS FOR REFURBISHMENT OF EXISTING CHURCH ITEM / TRADE BREAKDOWN area unit cost Notes DEMOLITION $40,000 ITEM Covers the removal of the existing roof while supporting the structure NEW ROOF STRUCTURE $250, ITEM requires new NEW ROOFING MATERIAL $350, ITEM superstructure (Fabric or metal deck) WINDOWS $99, $600 double glazed New windows to replace the existing INTERNAL WORKS KITCHEN REFURBISHMENT $35,000 ITEM TOILET REFURBISHMENT $25,000 ITEM DISABLED TOILET REFURBISHMENT $18,000 ITEM FLOOR FINISHES $40, $60 the existing floor will be compromised when the roof is removed GENERAL INTERNAL WORKS $45,000 walls will be damaged when roof is removed & will need new painting, skirting etc ITEM HEATING AND COOLING $60,000 new heating and cooling system throughout EXTERNAL WORKS TO IMMEDIATE CHURCH $75,000 ITEM * not the entire site, allow to landscape the moat, repair footpaths DESIGN CONTINGENCY $25,000 CONTINGENCY (5%) $60,000 SUB TOTAL $1,122,800 FEES & PERMITS $138,714 SUB TOTAL $1,261,514 EX GST GST $126,151 TOTAL COST OF PROJECT INCL GST $1,387,665 ESTIMATED CONSULTANTS FEE SUMMARY ARCHITECTURAL STRUCTURAL & CIVIL MECHANICAL ELECTRICAL HYDRAULIC SOIL REPORT QUANTITY SURVEYOR ASBESTOS REPORT LAND SURVEY LANDSCAPE ARCHITECT Energy Rating Assessments GROUND TESTING FOR CONTAMINATION SERVICES LOCATION PLANNING CONSULTANT BUILDING SURVEYOR Notes $75,000 estimate $25,000 estimate $6,500 estimate $5,000 estimate $5,000 estimate $2,500 estimate $5,500 estimate $0 *TBA if required $1,500 estimate $4,500 estimate $0 *TBA if required $0 not required $2,000 estimate $0 estimate $3,500 estimate SUB TOTAL $136,000 AUTHORITIES FEES PLANNING PERMIT APPLIC $714 PLANNING ADVERTISING $350 BUILDING PERMIT LEVY FEE $1,650 SUB TOTAL $138,714
BUDGET ESTIMATE - ISSUE No. 2
REPAIRS & ESSENTIAL UPGRADING WORK AT WINGERWORTH PARISH HALL NEW ROAD, WINGERWORTH DERBYSHIRE, S42 6TB BUDGET ESTIMATE - ISSUE No. 2 OCTOBER 2016 GENERAL NOTES Patrick Meeds & Associates were asked to
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT STRUCTURAL FOR CUSTOMS HOUSE JULY 2014 i P a g e Table of Contents 1. INTRODUCTION 3 1.1 Design Criteria and Specifications..
More informationINSPECT DIRECT Pty Ltd
Web Page: www.inspectdirect.com.au INSPECT DIRECT Pty Ltd Property Address: Sample.Dilapidation.Report Victoria Building Status / Dilapidation Report This is not a Pest Inspection The Building Status /
More informationREMEDIAL WORKS REQUIRED. Allow to clean down brickwork and repoint/repair brick elevations.
2.0 SCHEDULE OF DILAPIDATIONS External Areas 2.1 Rear elevation 2.1.1 Rear brickwork elevations 3.5 Brickwork is lightly soiled and stained at low level with some minor repointing required. Allow to clean
More informationSCHEDULE OF CONDITION
SCHEDULE OF CONDITION Buckinghamshire Marketing by: CONTENTS SCHEDULE OF CONDITION Elevations page 4 Internal Rooms page 10 GROUND FLOOR FIRST FLOOR Other Matters page 28 FIRE REGULATIONS DISABILITY AND
More informationVICTOR BUILDING SERVICES PL
Introduction Who we are Our Company has specialised in building repairs since 1959 when it first began as Victor House Repairs Service. The early 1980 s saw the Company expand to include Carl Victor s
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationArchitectural Design Guidelines. Zandwyk Industrial Park
Architectural Design Guidelines Zandwyk Industrial Park 1. INTRODUCTION It is the intention of this document to act as an aesthetic guideline to all Property owners in the design and development of their
More informationSTRUCTURAL BUILDING CONDITION SURVEY
STRUCTURAL BUILDING CONDITION SURVEY Our Project No. 140565 Prepared For: Mayfair Hotel Development Corporation Date: 3 December 2014; Revised: 15 December 2014 15 December 2014 Mayfair Hotel Development
More informationArts Center- Building needs
Arts Center- Building needs Built in 1928 Last renovated in 1986 Priority 1- fascia repair Loose, rotting and missing fascia needs to be replaced to prevent water intrusion. There are seven different pieces
More informationCENTENNIAL SCHOOL DISTRICT
CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites
More informationReliance House Investors Report. IR11 September 2018
Reliance House Investors Report IR11 September 2018 Extension & Conversion of Reliance House to Create 139 Luxury Apartments The 3 storey extension, refurbishment, adaptation and the sub-division works
More information109 S. MARKET CURTIS ARCHITECTURE & DESIGN PC SITE MAP EXISTING PHOTOGRAPH PROPOSED RENDERING
HISTORIC PHOTOGRAPH EXISTING PERSPECTIVE PROPOSED PERSPECTIVE TUCKPOINT ENTIRE BUILDING FACADE WITH MORTAR MATCHING ORIGINAL, REMOVE ALL FASTENERS, BRACKETS & MISC. METAL. REPAIR STAINED GLASS ABOVE EACH
More informationArchitectural Design Guidelines
ANNEXURE A Architectural Design Guidelines Zandwyk Industrial Park 1. INTRODUCTION It is the intention of this document to act as an aesthetic guideline to all Property owners in the design and development
More informationBUILDING CONDITION ASSESSMENT
BUILDING CONDITION ASSESSMENT 500 MacNab Street North, Hamilton ID. No.: EBE 16-0153 Prepared for Corporation By Effective Building Engineering Ltd.. Final Report: July 2016 Project No. 16-0153 Table of
More informationHILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School
HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story
More informationTrinity Episcopal Church Saint Louis. South Parish Hall Renovation campaign
Trinity Episcopal Church Saint Louis South Parish Hall Renovation 2012 2013 campaign OVERVIEW The South Parish Hall ( SPH ) at Trinity Episcopal Church in St. Louis Central West End is essential to the
More informationCITY OF NOVI. Police Department
CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master
More informationINDICATIVE FEASIBILITY BUDGET (RIBA STAGE 1) for ST JAMES'S CHURCH : WEYBRIDGE SURREY. June 2016
INDICATIVE FEASIBILITY BUDGET (RIBA STAGE 1) for INTERNAL REPAIRS AND REDECORATIONS OF THE CHURCH HALL at ST JAMES'S CHURCH : WEYBRIDGE SURREY June 2016 SAWYER & FISHER (EPSOM) LTD THOMAS FORD & PARTNERS
More informationDesign and Access Statement in support of the Planning Application for the Victoria Public House, 56 Middlesbrough Road, South Bank, Middlesbrough,
Design and Access Statement in support of the Planning Application for the Victoria Public House, 56 Middlesbrough Road, South Bank, Middlesbrough, TS6 6LZ, to obtain permission for a Change of Use to
More informationSNAGGING REPORT. Plot 19 Snag Close Unfinished Avenue Oxford OX90 1AB. for. Mr T & Mrs N Sample
SNAGGING REPORT on Plot 19 Snag Close Unfinished Avenue Oxford OX90 1AB for Mr T & Mrs N Sample Prepared By: Marshalls Chartered Surveyors Rochester House The Grange Farm Eynsham Road Oxford OX2 9NH Tel:
More informationCABONNE COUNCIL DEVELOPMENT CONTROL PLAN NO. 15 RELOCATABLE AND TRANSPORTABLE HOMES
CABONNE COUNCIL DEVELOPMENT CONTROL PLAN NO. 15 RELOCATABLE AND TRANSPORTABLE HOMES As approved by Council at the meeting of 20 June 2005 Came into effect on 14 July 2005 I, G. L. P. Fleming, General Manager,
More informationPresentation of Detailed Proposals. Existing Floor Plan Proposed Ground Proposed 1st
Presentation of Detailed Proposals. Existing Floor Plan Proposed Ground Proposed 1st Floor Plan Floor Plan The layout of the proposed plan keeps the main core of the building and the front and rear wall
More informationCB04. Outback House. Case Study. Creative Spaces Australia. by Casey Brown Architecture
CB04 Case Study Outback House by Casey Brown Architecture Creative Spaces Australia E : info@creativespacesaustralia.com.au www.creativespacesaustralia.com.au Introduction Inspired by the big sheds of
More informationDueldiDg. eport. Oldhamstocks Village Hall Oldhamstocks TD135XN. September 2015 t.!chard. 2 Golden Square DIms Berwicksbire TDI13AW Tel :
DueldiDg eport Oldhamstocks Village Hall Oldhamstocks TD135XN September 2015 t.!chard 2 Golden Square DIms Berwicksbire... -n..mosltd TDI13AW Tel : 01361882599 CONTENTS Section Page No. 1.0 INFORMATION
More informationMoonlight Architecture, Inc. Architecture Interior Design Site Planning
Moonlight Architecture, Inc. Architecture Interior Design Site Planning 22 May 2018 18057 Mr. Michael J. Petit de Mange, County Administrator Kent County Levy Court 555 Bay Road Dover, DE 19901 RE: Facilities
More informationInterior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT:
REV 2 CONCEPTUAL ESTIMATE FOR: Interior Architects, P.C Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY AT: BY: GARDINER AND THEOBALD INC Issued: 6/20/2013 BROOKLYN HEIGHTS LIBRARY, BROOKLYN
More informationEastern Cape Development Corporation invites developers to submit proposal calls with concept, designs and funding. and Motor Town Land
REQUEST FOR PROPOSAL Eastern Cape Development Corporation invites developers to submit proposal calls with concept, designs and funding. RFP Reference Number Description Briefing Meeting Closing Date/Time
More informationSt Michael s Parish Church Kirk Session Cross House Improvement Programme Report from Property and Business Teams December 2018
St Michael s Parish Church Kirk Session Cross House Improvement Programme Report from Property and Business Teams December 2018 Introduction 1 This paper returns to Kirk Session s aspirations to provide
More informationHOUSING QUALITY STANDARDS (HQS) INSPECTIONS
HOUSING QUALITY STANDARDS (HQS) INSPECTIONS Before the PHA can make payments to you on behalf of a tenant family, the unit must meet HUD s minimum Housing Quality Standards (HQS). These standards have
More informationEASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923
INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationHoly Trinity Construction Project Sanctuary Repairs Transepts Social Hall General Assembly Presentation May 29, 2016
Holy Trinity -- 2016 Construction Project Sanctuary Repairs Transepts Social Hall General Assembly Presentation May 29, 2016 The 2016 Construction Project contractual start date was on April 4, 2016. The
More informationAn affordable sustainable designer home. telephone
An affordable sustainable designer home Awar A Aw war ards ds www.lifehousedesign.com.au info@lifehousedesign.com.au telephone 03 5470 5584 What is a LiFEHOUSE? LiFEHOUSES A flexible, sustainable, designer
More informationDenis Creedon, B.E., MIEI. CONSULTING ENGINEER
Denis Creedon, B.E., MIEI. CONSULTING ENGINEER PROPERTY INSPECTION REPORT PROPERTY: CLIENT: DATE: Denis Creedon, B.E., MIEI, CONSULTING ENGINEER Tel: 02221157, 0868072327 N0.6 Chapel Lane, Mallow, Co.
More informationGarage Conversions. Technical Issues
Garage Conversions Introduction: if you need more space and you do not want to move house you may wish to consider converting your garage. Your home is probably your most valuable asset so it is important
More informationSCHEDULE OF CONDITION XXXXXXXXXXXX XXXXXXX XXXXXXXXXXX XXXXXXXX XXXXXX
JOB REFERENCE: XXXXXXXXXX SCHEDULE OF CONDITION XXXXXXXXXXXX XXXXXXX XXXXXXXXXXX XXXXXXXX XXXXXX FOR XXXXXXXXXXX Prepared by: INDEPENDENT CHARTERED SURVEYORS Marketing by: CONTENTS SCHEDULE OF CONDITION
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More informationTrade Licensing Guide Victoria. Use this guide to verify which licensed trade you need for your home improvement job
Trade Licensing Guide Victoria Use this guide to verify which licensed trade you need for your home improvement job Is Your Tradesperson Licensed? Have you ever asked a tradesperson for their licence?
More informationHERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School
HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has
More informationRODINNÉ DOMY STODŮLKY. Standards
RODINNÉ DOMY STODŮLKY Standards BUILDING Floors in residential rooms Entrance hall Kahrs Linnea 3-layer veneer floor, 3-parquet, finished with a moulding, a selection from natural oak and bleached oak
More informationCollins Middle School
Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0
More informationLOMBARDY ESTATE ARCHITECTURAL GUIDELINES RESIDENTIAL SECTOR
LOMBARDY ESTATE ARCHITECTURAL GUIDELINES RESIDENTIAL SECTOR 1. INTRODUCTION Lombardy Estate is a unique residential, commercial and nature development situated to the East of Pretoria. The development
More informationDr. Edward Livingston Trudeau Building. 118 Main Street, Saranac Lake, NY. Building Systems Report. June 24, 2018
G2 Gordon + Gordon Architecture. LLC Dr. Edward Livingston Trudeau Building 118 Main Street, Saranac Lake, NY Building Systems Report June 24, 2018 Harry Gordon, FAIA 164 Otter Slide Road Saranac Lake
More informationEcoSteel Pre-Engineered Steel Buildings provide the world s most advanced Eco friendly construction systems.
System Overview EcoSteel Pre-Engineered Steel Buildings provide the world s most advanced Eco friendly construction systems. In our ever extensive product line, we offer solutions for Commercial, Residential,
More informationSCHEDULE OF FINISHES FOR THE AGREEMENT BETWEEN ZOTOS BROTHERS (PTY) LTD AND
SCHEDULE OF FINISHES FOR THE AGREEMENT BETWEEN ZOTOS BROTHERS (PTY) LTD Zotos Place, 37 Old Kilcullen Road, Bryanston P O Box 68012, Bryanston, 2021 Tel: 011 463 2124 Fax: 011 463 2129 AND ERF: TOWNSHIP:
More informationAccommodation Solutions
Accommodation Solutions Staff Accommodation Solutions GMS specializes in remote location projects and what has become evident is that remote location projects are only successful when paired with accommodation
More informationAdministration Building Needs Assessment
Town Hall Meeting with the Habersham County Board of Commissioners Administration Building Needs Assessment JUNE 13, 2016 Detailed Evaluation Performed in 2015 Engineering Evaluation Site/Civil Architectural
More informationInspection details. Subfloor. Subfloor. Before You Buy property inspection
Before You Buy 254 Richmond Rd, Auckland, 1011, Auckland info@beforeyoubuy.co.nz www.beforeyoubuy.co.nz 29th Sep, 2015 Inspection details Property owner Joe Bloggs Address 36 Bloggs st Date 03 Jul 2015
More informationEXECUTIVE SUMMARY INTRODUCTION Terms of Reference Building Description Documents Reviewed SUMMARY OF FIELD DATA 4
Abbott Place Wood Framed Window Condition Assessment May 30, 2012 TABLE OF CONTENTS EXECUTIVE SUMMARY 1 1.0 INTRODUCTION 2 1.1 Terms of Reference 2 1.2 Building Description 3 1.3 Documents Reviewed 3 2.0
More informationFacility Improvements
AL-SI-02 ASPHALT PLAY AREA UPGRADE AL-SI-09 CURB RAMP ADDITIONS Asphalt improvements needed around building and playshed to provide a safe play area. Curb ramps needed to provide wheelchair access and
More informationSCHEDULE OF CONDITION. Fulham, London SW6 FOR. Mr S Of XXXX Limited. Prepared by: INDEPENDENT CHARTERED SURVEYORS
SCHEDULE OF CONDITION Fulham, London SW6 FOR Mr S Of XXXX Limited Prepared by: INDEPENDENT CHARTERED SURVEYORS Marketing by: CONTENTS SCHEDULE OF CONDITION Elevations page 4 Internal Rooms page 12 GROUND
More informationTABLE OF CONTENTS. Calgary School District No. 19 March Page. Executive Summary. Facility Profile and Summary 1. Section 1 Site Conditions 4
TABLE OF CONTENTS Executive Summary Page i Facility Profile and Summary 1 Section 1 Site Conditions 4 Section 2 Building Exterior 7 Section 3 Building Interior 11 Section 4 Mechanical Systems 14 Section
More informationMAJOR DEFECTS BUILDING SURVEY REPORT
MAJOR DEFECTS BUILDING SURVEY REPORT XXXXXX Road Bedminster Bristol BS3 XXX Prepared for Mr XXXXXXX July 2017 T J Maggs MRICS MAGGS AND ALLEN 22 Richmond Hill Clifton Bristol BS8 1BA 0117 973 4049 survey@maggsandallen.co.uk
More informationWELCOME & PURPOSE. Overford Farm, Wytham - Conversion of Outbuildings to Form Dwellings. Welcome - we are delighted you are attending the event today.
WELCOME & PURPOSE 1 Welcome - we are delighted you are attending the event today. The property at Overford Farm has been within the ownership of the University of Oxford since 1943 when it was acquired
More information100 S Ashley Dr Suite 600 Tampa, FL Phone: Fax:
9/21/2017 https://buildertrend.net/proposals/proposalprint.aspx?&proposalid=368319&logintype=1&masterpagebuilderid=10096 100 S Ashley Dr Suite 600 Tampa, FL 33602 Phone: 813 400 1058 Fax: 8134001058 Ben
More informationStructural Condition Assessment
108 6 th Street, Garland, Texas Engineering Report Date: September 29, 2016 RLG No. : 16729 Prepared for: Mr. Jeff D. Bulls III AIA 3030 LBJ Freeway, Suite 1220 Dallas, TX 75234 PM: Harold F. Phillips
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT STRUCTURAL FOR CORNER HOUSE AUG 2014 i P a g e Table of Contents 1. INTRODUCTION... 3 1.1 Design Criteria and Specifications...
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More information43. CONSERVATORY. Conservatory. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle
Classification: Cluster: Location: Total Area: No. of Stories Acreage Owned: Acquired: 1904 Most Recent Improvements: THE CONSERVATORY Conservatory Close to junction of Inselrhue and Loiter Way, Belle
More informationCONSULTING CIVIL AND STRUCTURAL ENGINEERS. Preben Naidoo And Associates. Tel: (033) , Fax: (033) , E mail:
CONSULTING CIVIL AND STRUCTURAL ENGINEERS Preben Naidoo And Associates Tel: (033) 342 2705, Fax: (033) 342 6480, E mail: preben@pnaengineers.co.za STATUS QUO REPORT: COGTA: WHITBY LODGE Prepared For: DEPARTMENT
More informationDRAFT September 26th, 2003
Harrelson Hall Renovation and Replacement Study DRAFT September 26th, 2003 Summary of Renovation Issues As part of the 2000 Capital Bond Program, funds were allocated for the renovation of Harrelson Hall
More informationCounty of Santa Barbara, California Facility Condition Assessment 2014
Project Number: D42000.001 Building Number: D42000 Goleta Beach Grounds Project Description: Repair Asphalt Pavements Background: The site comprises asphalt pavement for the parking areas and travel lanes
More informationAdvanced Building Technologies
Advanced Building Technologies 1 Contents Temporary Housing Panel Type FLATTS - Rapid Deployment Permanent Housing Leight Weight Steel Framing Commercial
More informationDISTRICT SERVICES BUILDING
DISTRICT SERVICES BUILDING BUILDING DATA DISTRICT SERVICES BUILDING 1100 Longhorn Dr., Weatherford, TX 76086 Year Built 1993 No. of Buildings 1 No. of Portables 0 Approx. Total Square Footage Grades Served
More informationPassivTEN - Scottish Tenements and the Passivhaus Standard
PassivTEN - Scottish Tenements and the Passivhaus Standard Alan Benson Milnbank HA Matt Bridgestock John Gilbert Architects Tenements stats that influenced the study.. 23% of Scottish housing stock 35%
More informationStage 6. Annexure 3. October 2015 Development Conditions and Building Guidelines
Stage 6 Annexure 3 October 2015 Development Conditions and Building Guidelines INTRODUCTION In order to encourage the attainment of a consistent building standard and to encourage home design excellence
More informationSchedule of Condition
Schedule of Property Address: Outlet Number: 201780 Document Reference: The Bowling Green Tavern 164 Church Path Deal CT14 9UD N/A Document Date: 6th May 2018 Rev. Contents Page 2 A. Document Control Sheet
More informationSTRUCTURAL EVALUATION
SMELTER BUILDINGS STRUCTURAL EVALUATION Resolution Copper Mining, LLC West Plant Area September 7, 2016 Safety Share Preventable Motor Vehicle Accidents 1. Aim High in Steering. 2. Get The Big Picture.
More informationHOME INSPECTION CHECKLIST
CLOSING.COM LEARNING CENTER HOME INSPECTION CHECKLIST CONTENTS Attic 1 Balconies 1 Basement 1 Bathroom 2 Ceiling, Floors and Walls 2 Crawlspace 3 Decks and Porches 3 Doors and Windows 4 Drainage 4 Driveways
More informationWhat you need to know about 6 Star. 6 Star. for new homes, home renovations, alterations, additions and relocations
What you need to know about 6 Star 6 Star for new homes, home renovations, alterations, additions and relocations Introduction From 1 May 2011, all new homes, home renovations, additions, alterations and
More informationSCHEDULE OF CONDITION. xxxxxxxxxxxxxxxxx xxxxxxxxxxxxx xxxxxxxxxxxx xxxxxxxxxxxxxxxx Wandsworth xxxxxxxxxxxxx
JOB REFERENCE: EX41535/SOC3/MH/MB3 SCHEDULE OF CONDITION xxxxxxxxxxxxxxxxx xxxxxxxxxxxxx xxxxxxxxxxxx xxxxxxxxxxxxxxxx Wandsworth xxxxxxxxxxxxx xxxxxxxxxxxxxxxx FOR xxxxxxxxxxxxxxx Prepared by: xxxxxxxxxxxxxxxxxxxxxxx
More informationBEFORE THE TIMARU DISTRICT COUNCIL. IN THE MATTER OF the Resource Management Act 1991
BEFORE THE TIMARU DISTRICT COUNCIL IN THE MATTER OF the Resource Management Act 1991 AND IN THE MATTER OF An application for Resource Consent by Bayhill Developments Limited STATEMENT OF EVIDENCE OF ROSS
More informationBENSON CITY HALL/POLICE DEPARTMENT FACILITY ASSESSMENT AND FEASIBILITY STUDY
BENSON CITY HALL/POLICE DEPARTMENT FACILITY ASSESSMENT AND FEASIBILITY STUDY Prepared for the City of Benson, Minnesota by Widseth Smith Nolting May 2016 City of Benson, Minnesota CITY HALL/POLICE STATION
More informationMinistry of Education St Albans Primary School. Asbestos Assessment 7 th of October 2015
South Island Head Office PO Box 28147, Beckenham, Unit 24, 105 Bamford Street, Woolston, Christchurch Tel: 03 384 8966 Mobile: 0274 33 78 72 Email: info@k2.co.nz North Island Office Unit 23, 203 Kirkbride
More informationKEVIN BURNS BUILDING INSPECTIONS REGISTERED BUILDER PRE-PURCHASE VISUAL STRUCTURAL INSPECTION REPORT No. 822
KEVIN BURNS BUILDING INSPECTIONS REGISTERED BUILDER 6163 PRE-PURCHASE VISUAL STRUCTURAL INSPECTION REPORT No. 822 CLIENT: Talavera PROPERTY ADDRESS: Mindarie DATE: 20 April 2017 TIME: 9.00am WEATHER: Fine
More informationNEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY CIP SUMMARY
PROJECT: Exterior Masonry JOB NO: D012259 SCHOOL: PS 189 K (Brooklyn) EXHIBIT 5 DATE: 2/13/2009 BUILDING ID: K189 REV: CONSULTANT: Goshow Architects FINAL ESTIMATE CIP SUMMARY GENERAL CONDITIONS $ 105,076
More informationPlanning Applications Received
1 - South East Application Number 0056/14 Irene Connolly Location 32, Lombard Street West, Dublin 8 EXPP: (1) Removal of existing window and wall below, strip pebble dash from wall and repair any bricks
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More informationOwner Builder Inspection Report
www.sherspec.com Owner Builder Inspection Report PREPARED FOR USE IN ASSESSING A PROPOSAL FOR WARRANTY INSURANCE TO BE ISSUED UNDER SECTION 137B (2)(a) OF THE BUILDING ACT 1993 INSPECTION DETAILS Registered
More informationBathrooms. Custom cabinetry INCLUDED
Designer Inclusions Kitchen Stone bench tops INCLUDED 20mm Caesarstone kitchen bench tops A large choice of colours Bathrooms Custom cabinetry INCLUDED Note: wall hung vanity and stone bench top not included
More informationBuilding regulations now in force
BCA Section J: Guide to compliance Publication date July 2008 Building regulations now in force BCA SECTION J: Mandatory energy efficiency measures for non-residential construction The new BCA Section
More informationVerve Inclusions. 3 Corporate Avenue Rowville VIC T 1800 SIENNA E
Verve 3 Corporate Avenue Rowville VIC T 1800 SIENNA E info@siennagroup.com.au Kitchen B F K C I E D J A G Kitchen A: Laminated finish to kitchen benchtops with 32mm thick square edge, selected from the
More informationFairfield Board of Education Proposed Capital Non-Recurring Projects
Fairfield Board of Education Proposed Capital Non-Recurring Projects 2014-2015 Fairfield Public Schools Capital Non-Recurring Project Overview 2014-2015 Location Project Estimated Cost Page Mill Hill
More informationPROCUREMENT AND CONTRACTING DOCUMENTS GROUP
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders
More informationSUNCHASER VACATION VILLAS FAIRMONT RESORT FAIRMONT HOT SPRINGS, BC
FAIRMONT RESORT FAIRMONT HOT SPRINGS, BC INITIAL REPORT April 2 nd, 2013 LTA Consultants Inc. Professional Quantity Surveyors & Construction Cost Consultants 905 1708 Dolphin Avenue Kelowna, BC V1Y 9S4
More informationProject #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50
Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed
More informationBenefited Land means all the lots created when the Land is subdivided in accordance with the Deposited Plan;
TAYLOR PRIVATE ESTATE STAGE 15B RESTRICTIVE COVENANT 1. Definitions 1.1 In this Deed: Benefited Land means all the lots created when the Land is subdivided in accordance with the Deposited Plan; Benefited
More informationSite and Building Rehabilitation / West Wall Infill Catholic Pastoral Center 601 Grand Avenue, Des Moines, Iowa
Site and Building Rehabilitation / West Wall Infill Catholic Pastoral Center 601 Grand Avenue, Des Moines, Iowa City of Des Moines Urban Design Review Board City of Des Moines Landmark Review Board December
More informationBuilding Repairs Report. Sefton Road, Crewe, WA11 9QD
Your Address Your Town County, Post Code Email: youremail@yourdomain.com Web: your.web.site Tel: Your Phone Number This report took 5 SECONDS to produce & a few MINUTES to collect the data on site! Download
More informationHOME INSPECTION REPORT Prarie Circle
HOME INSPECTION REPORT 6245 Prarie Circle Mississauga Prepared for: Kevin Alvarez Prepared by: Bob Papadopoulos P.Eng., RHI * Inspection Date: April 23 2015 www.redbrickinspections.ca bob@redbrickinspections.ca
More informationINTERNATIONAL BUILDING CODE
INTERNATIONAL BUILDING CODE MODEL BUILDING CONDITIONS ASSESSMENT The Reid and Hughes building is a four-story, four-bay, brick building, constructed in 1869 with a later addition known as the Williams
More informationProperty Condition Assessment
Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072
More informationExecutive Summary. ABSA Building October Project Brief. Introduction
Executive Summary ABSA Building October 2014 Project Brief The project brief requested that the professional team conduct a visual only, conditional assessment of the building condition, services and structural
More informationBuilding Guidelines. No development is to be commenced on any lot without the plans having been approved in writing as set out above.
Building Guidelines INTRODUCTION In order to encourage the attainment of a consistent building standard and to encourage home design excellence at Lakeside Success Private Estate, these Building Guidelines
More informationFOREST PLACE 59 UNITS ERF 5586 PARKLANDS
ANNEXURE "C" MATERIAL AND FINISHES SPECIFICATION FOREST PLACE 59 UNITS ERF 5586 PARKLANDS 1. FOUNDATIONS AND STRUCTURE Foundation walls are to be built in strict accordance with the municipal building
More informationPrimary School Retrofit Project
Primary School Retrofit Project Final Design Proposal Ian Black DIT D12124703 Passiv Haus Design Criteria PHI ENERPHIT CRITERIA EnerPHit Certification based on the requirement for heating demand Heating
More informationCommercial Remodel Permit
Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each
More informationEMERGENCY SERVICES & LOCAL AUTHORITY BROCHURE
EMERGENCY SERVICES & LOCAL AUTHORITY BROCHURE Hare Park Mills Hare Park Lane Hightown Liversedge WF15 8EP Ascot House Trident Business Park Daten Avenue Birchwood Warrington WA3 6BX Tel: 01274 874772 Tel:
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationAPPENDIX 3E HAZELWOOD HOTEL SPECIFICATIONS
APPENDIX 3E HAZELWOOD HOTEL SPECIFICATIONS 1. GENERAL 1.1 Refer to Section 2.1 of Schedule 3 [Design and Construction Specifications] regarding compliance with Schedule 3 and this Building Specification.
More information