1 CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016
2 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites 2. Engaged Decision Insite (DI) for Enrollment Projection Study 3. Developed Middle School Programming with District Administration 4. Created Options with the District Administration then refined those Options for further feedback from District Administration 5. Developed graphic representations of those Options as solutions on each site 6. Produced Budget Estimates to support the various options 7. Went through several iterations of Options and budgeting to arrive at this presentation 2
3 project sites enrollment projections programming options budgets discussion 3
4 discussion project sites enrollment projections programming options budgets 4
5 Eugene Klinger Middle School Opportunities 637 students today, have had as many as 1,200 Large auditorium for 720 including mezzanine Built 1965, pool added a year later Cafeteria has three seatings of approximately 220 Several HVAC upgrades over recent years Layout - Originally set up as team structure with team rooms, now used as special ed and support Bleachers in gym replaced several years ago 5
6 Eugene Klinger Middle School Challenges Environmental remediation Central plant one boiler replaced, one original, cooling tower is three years old HVAC air handlers replaced last year, terminal units original, need building controls Electrical service and generator Fire protection and fire alarm replacement required Pool filter issues etc., Replace all plumbing fixtures ADA issues, Doors and hardware Finishes mostly original, auditorium needs replacement Roof - New roof over gym, and pool but not cafeteria, Balance is twenty five years old Windows are original Walls have veneer brick issues Structure - Steel frame with masonry infill 6 Original kitchen equipment
7 Log College Middle School Opportunities Large site, Township uses some of the property 640 students today, have had as many as 1,200 Large auditorium for 1000 including mezzanine Built 1966, pool added a year later Cafeteria has three seatings of approximately 250 Layout - Originally set up as team structure with team rooms, now used as special ed and support Bleachers in gym replaced several years ago. Has held up to 1,200 students Bussing school, no walkers 7
8 Log College Middle School Challenges Environmental remediation HVAC replace system in entirety Electrical service and generator Lighting retrofit through ESCO recently Fire protection and fire alarm replacement required Pool filter issues etc. Replace all plumbing fixtures ADA issues Doors and hardware Finishes mostly original, auditorium needs replacement Roof - New roof over gym, and pool but not cafeteria, Balance is twenty five years old Windows are original Walls have veneer brick issues Structure - Steel frame with masonry infill Original kitchen equipment 8
9 Existing Admin/HS Campus Centennial Road Opportunities Shared use of spaces Shared use of playing fields Central location within the district Possibility of shared parking and driveways Possible sharing of bussing routes Centralized staff model 9
10 Existing Admin/HS Campus Centennial Road Challenges Limited acreage (this changes with the use of the property across the street) Potential challenging circulation patterns (changes with property across the street) Potential congestion for pick up and drop off (changes with property across the street) Enough playing fields for both programs? 10
11 discussion project sites enrollment projections programming options budgets 11
12 Eugene Klinger CONSERVATIVE PROJECTIONS HIGH PROJECTIONS CURRENT CALCULATED ENROLLMENT 10 YR PROJECTION 12
13 Log College CONSERVATIVE PROJECTIONS HIGH PROJECTIONS CURRENT CALCULATED ENROLLMENT 10 YR PROJECTION 13
14 Eugene Klinger MODERATE PROJECTIONS HIGH PROJECTIONS CURRENT CALCULATED ENROLLMENT 10 YR PROJECTION 14
15 Log College MODERATE PROJECTIONS HIGH PROJECTIONS CURRENT CALCULATED ENROLLMENT 10 YR PROJECTION 15
16 discussion project sites enrollment projections programming options budgets 16
17 Eugene Klinger 650 STUDENT PROGRAM TOTAL PROGRAM CAPACITY W/90% UTILIZATION FACTOR AREA PER PROGRAM 17
18 Log College 650 STUDENT PROGRAM TOTAL PROGRAM CAPACITY W/90% UTILIZATION FACTOR AREA PER PROGRAM 18
19 Concept Facility 1300 STUDENT PROGRAM TOTAL PROGRAM CAPACITY W/90% UTILIZATION FACTOR AREA PER PROGRAM 19
20 discussion project sites enrollment projections programming options budgets 20
21 Log College Centennial Road Klinger 21
22 Log College Centennial Road Klinger 22
23 Klinger Upper Southampton Township Zoned R-1 Residential Schools are permitted By right Parking 1 per faculty and employee and 1 per 2 CR and offices 23
24 Klinger Option A MATERIAL DEFICIENCY REPAIRS Items from the Property Condition Report provided by Barry Isett & Associates May 16, 2014 including: Repair of deteriorating site items Window replacement Roof replacement Mechanical, electrical and plumbing system upgrades, repairs, replacement Pool filter equipment replacement Life safety/fire Protection Cost escalation to 2018 to be consistent with other estimates Soft Costs added 24
25 Klinger Option B MATERIAL DEFICIENCY REPAIRS PLUS COSMETIC RENOVATIONS Items from the Property Condition Report provided by Barry Isett & Associates May 16, 2014 Building upgrades intended to make the building feel like it was renovated to current cosmetic standards including all ADA. Note that this includes no major moving of walls. Replacement includes: Flooring Ceilings New casework, cabinetry New door systems throughout (all ADA upgrades) New paint and finishes throughout New lighting throughout New marker and tack boards throughout Asbestos removal Elevator Site upgrades Cost escalation to 2018 to be consistent with other estimates Soft Costs added 25
26 Klinger Option C BUS DROP OFF PARENT DROP OFF Indicates addition area 26
27 BUS DROP OFF Klinger Option C first floor plan PARENT DROP OFF 27
28 Klinger Option C second floor plan 28
29 Klinger Option D PARENT DROP OFF BUS DROP OFF Indicates addition area 29
30 BUS DROP OFF PARENT DROP OFF Klinger Option D first floor plan 30
31 Klinger Option D second floor plan 31
32 Klinger Option E BUS DROP OFF PARENT DROP OFF 32
33 Klinger Option E first floor plan PARENT DROP OFF BUS DROP OFF 33
34 Klinger Option E second floor plan 34
35 Log College Centennial Road Klinger 35
36 Warminster Township Zoned R-1 Residential Schools are permitted as Conditional Use Parking is permitted in buffer yards exclusive of the outer 50 Parking allowed in front, side and rear yard areas Parking 1 per faculty and employee and 1 per 3 CR Log College 36
37 Log College Option A MATERIAL DEFICIENCY REPAIRS Items from the Property Condition Report provided by Barry Isett & Associates May 16, 2014 including: Repair of deteriorating site items Window replacement Partial roof replacement Mechanical, electrical and plumbing system upgrades, repairs, replacement Pool filter equipment replacement Life safety/fire Protection Cost escalation to 2018 to be consistent with other estimates Soft Costs added 37
38 Log College Option B MATERIAL DEFICIENCY REPAIRS PLUS COSMETIC RENOVATIONS Items from the Property Condition Report provided by Barry Isett & Associates May 16, 2014 Building upgrades intended to make the building feel like it was renovated to current cosmetic standards including all ADA. Note that this includes no major moving of walls. Replacement includes: Flooring Ceilings New casework, cabinetry New door systems throughout (all ADA upgrades) New paint and finishes throughout New lighting throughout New marker and tack boards throughout Asbestos abatement Full sprinkler system Elevator Site upgrades Cost escalation to 2018 to be consistent with other estimates Soft Costs added 38
39 Log College Option C BUS DROP OFF PARENT DROP OFF Indicates addition area 39
40 Log College Option C BUS DROP OFF first floor plan PARENT DROP OFF 40
41 Log College Option C second floor plan 41
42 Log College Option D BUS DROP OFF PARENT DROP OFF Indicates addition area 42
43 Log College Option D BUS DROP OFF first floor plan PARENT DROP OFF 43
44 Log College Option D second floor plan 44
45 Log College Option E BUS DROP OFF PARENT DROP OFF 45
46 Log College Option E first floor plan PARENT DROP OFF BUS DROP OFF 46
47 Log College Option E second floor plan 47
48 Log College Centennial Road Klinger 48
49 Centennial Road Site Warminster Township Zoned R-1 Residential Schools are permitted as Conditional Use Parking is permitted in buffer yards exclusive of the outer 50 Parking allowed in front, side and rear yard areas Parking 1 per faculty and employee and 1 per 3 CR 49
50 Centennial Road Option BUS DROP OFF PARENT DROP OFF DISTRICT ADMIN. FIRST FLOOR 50
51 Centennial Road Option BUS DROP OFF PARENT DROP OFF DISTRICT ADMIN ENTRY first floor plan 51
52 Centennial Road Option second floor plan 52
53 Centennial Road Option third floor plan 53
54 discussion project sites enrollment projections programming options budgets 54
55 Eugene Klinger OPTION A Material Deficiency Repairs Construction Repairs per BIA Study $ 12,480,000 Escalation to 2018 (4% per year) $ 2,121,600 Subtotal $ 14,601,600 Design Costs Subtotal $ 1,072,112 Miscellaneous Costs Subtotal $ 654,064 Contingency Subtotal $ 1,224,583 TOTAL $ 17,552,359 55
56 Eugene Klinger OPTION B Material Deficiency Repairs + General Renovation Construction Repairs per BIA Study (w/escalation) $ 14,601,600 Other Construction Costs $ 17,637,466 Subtotal $ 32,239,066 Design Costs Subtotal $ 2,225,691 Miscellaneous Costs Subtotal $ 1,626,873 Contingency Subtotal $ 2,706,872 TOTAL $ 38,798,502 56
57 Eugene Klinger OPTION C Full Renovation/Alternation Construction Building Construction $ 31,674,558 Site Construction $ 4,932,120 Subtotal $ 36,606,678 Design Costs Subtotal $ 2,680,079 Miscellaneous Costs Subtotal $ 3,784,267 Contingency Subtotal $ 3,230,327 TOTAL $ 46,301,352 57
58 Eugene Klinger OPTION D Addition/Renovation Construction Building Construction $ 39,245,966 Site Construction $ 4,932,120 Subtotal $ 44,176,086 Design Costs Subtotal $ 3,134,244 Miscellaneous Costs Subtotal $ 4,091,139 Contingency Subtotal $ 3,855,110 TOTAL $ 55,256,580 58
59 Eugene Klinger OPTION E New Construction/ Demolition of Existing Construction Building Construction $ 40,719,814 Site Construction $ 5,264,240 Subtotal $ 45,984,054 Design Costs Subtotal $ 3,239,401 Miscellaneous Costs Subtotal $ 4,165,138 Contingency Subtotal $ 4,004,144 TOTAL $ 57,392,737 59
60 Log College OPTION A Material Deficiency Repairs Construction Repairs per BIA Study $ 7,000,000 Escalation to 2018 (4% per year) $ 1,189,010 Subtotal $ 8,189,010 Design Costs Subtotal $ 623,231 Miscellaneous Costs Subtotal $ 397,560 Contingency Subtotal $ 690,735 TOTAL $ 9,900,536 60
61 Log College OPTION B Material Deficiency Repairs + General Renovation Construction Repairs per BIA Study (w/escalation) $ 8,189,010 Other Construction Costs $ 19,024,901 Subtotal $ 27,213,911 Design Costs Subtotal $ 1,894,614 Miscellaneous Costs Subtotal $ 1,426,206 Contingency Subtotal $ 2,290,105 TOTAL $ 32,824,836 61
62 Log College OPTION C Full Renovation/Alternation Construction Building Construction $ 30,105,606 Site Construction $ 4,980,938 Subtotal $ 35,086,544 Design Costs Subtotal $ 2,588,383 Miscellaneous Costs Subtotal $ 3,723,462 Contingency Subtotal $ 3,104,879 TOTAL $ 44,503,268 62
63 Log College OPTION D Addition/Renovation Construction Building Construction $ 38,652,606 Site Construction $ 4,980,938 Subtotal $ 43,633,544 Design Costs Subtotal $ 3,101,203 Miscellaneous Costs Subtotal $ 4,069,967 Contingency Subtotal $ 3,810,354 TOTAL $ 54,615,067 63
64 Log College OPTION E New Construction/ Demolition of Existing Construction Building Construction $ 40,719,814 Site Construction $ 5,361,875 Subtotal $ 46,081,689 Design Costs Subtotal $ 3,244,283 Miscellaneous Costs Subtotal $ 4,169,893 Contingency Subtotal $ 4,012,190 TOTAL $ 57,508,054 64
65 Centennial Road Site (1300 student) New Middle School Construction Construction Building Construction $ 72,378,653 Site Construction $ 5,175,000 Subtotal $ 77,553,653 Design Costs Subtotal $ 5,174,469 Miscellaneous Costs Subtotal $ 6,942,146 Contingency Subtotal $ 6,725,270 TOTAL $ 96,395,538 65
66 Project Cost Comparison REPAIR/ UPDATE ADDITION/PROGRAM MOD NEW CONST. OPTION A OPTION B OPTION C OPTION D OPTION E Deficiency Repairs Deficiency Repairs & Renovations Renovations/ Alterations Additions/ Renovations New Construction INDIVIDUAL Klinger $ 17,552,359 $38,798,502 $46,301,352 $ 55,256,580 $ 57,392,737 Log College $ 9,900,536 $32,824,836 $44,503,268 $ 54,615,067 $ 57,508,054 COMBINED Klinger + $27,452,895 $71,623,338 $90,804,620 $109,871,647 $114,900,791 Log College Cent. Rd $ 96,395,538 Double School 66
67 CENTENNIAL SCHOOL DISTRICT Partnering to create the best learning experience for the students of the District! THANK YOU!
NALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationMAURY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationProject Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope
Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope
More informationDENNIS TOWNSHIP FEASIBILITY STUDY
DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More informationSTUART-HOBSON MIDDLE SCHOOL
INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture
FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More information2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014
2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationLEWIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationEvansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data
Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School
More informationDarien Public Schools. Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018
Darien Public Schools Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018 BACKGROUND MASTER PLAN REPORT SUBMITTED DECEMBER 2016 DOCUMENTED DISTRICT-WIDE INFRASTRUCTURE
More informationHealth Life Safety Survey and Master Facilities Plan
Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master
More informationLASALLE - BACKUS EDUCATION CAMPUS
INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMCER Study for Little Powder K-8
MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives
More informationLECKIE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationHartsville Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: West Hartsville Elementary Observed By: Cannon/Carter Principal:
More informationBARNARD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationUpper Adams School District Facility Study Presentation Part 2 November 17, 2016
Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationSITE ASSESSMENT REPORT Addendum #2
SITE ASSESSMENT REPORT Addendum #2 Board of Education Fall Retreat September 28, 2013 Executive Summary In September 2012, Operations Staff presented Phase 1 of the 10 Year Facilities Master Plan, which
More informationSchool Assessment Report
School Assessment Report School: Humphries Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:35:17 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationStevens High School Pre Bond Presentation Claremont, NH
Stevens High School Pre Bond Presentation Claremont, NH Existing Conditions Existing Conditions Existing Conditions Existing Conditions Proposed site features New main entry that is ADA accessible New
More informationSHEPHERD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCupertino Union School District
Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationSchool Assessment Report
School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationNOYES EDUCATION CAMPUS
INITIAL YEAR BUILT 1930 BUILDING AREA 49,700 SF CURRENT PROGRAM CAPACITY 321 ENROLLMENT 2008 337 WARD 5 PROPOSED PROGRAM CAPACITY 450 Site Plan NOYES - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-8
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationSchool Assessment Report
School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report
More informationBOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project
BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCITY OF NOVI. Police Department
CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master
More informationSchool Without Walls
INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationPOWELL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 38,500 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 319 WARD 4 PROPOSED PROGRAM CAPACITY 325 Site Plan POWELL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-3
More informationFEASIBILITY STUDY SEPTEMBER 1 8,
FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study
More informationGFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1
GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept
More information2019 Construction
2019 Construction Estimates @ 18 10 01 1 Oak Flat Elementary IDENTIFIED BASE BID SCOPE ITEMS Project BSSD replace door hardware to meet ADA, including re-key to master system $ 75,000 Shelter Lockdown
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationAddendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN
GREENWICH PUBLIC SCHOOLS Greenwich, CT November 27, 2017 Addendum to Agenda Item: 2018-2019 SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN Please note edited pages should replace original sheets in
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationSchool Assessment Report
School Assessment Report School: Cascade Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:55 AM FOR OFFICIAL USE ONLY Final School Assessment
More information90% Draft - NOT FINAL. A Presentation For: the architectural studio. By Principals: George Moore & Curt Santee October 28th 2014
A Presentation For: By Principals: George Moore & Curt Santee October 28th 2014 1 the architectural studio 2014 District Exterior Wall Forensic Study Warrior Run School Brick Study Completed on High School
More informationFacilities Feasibility Study Frederick Douglass HS Condition Assessment
Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab
More informationHERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School
HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has
More informationEASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923
INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationBOARD OF TRUSTEES OCTOBER 13, 2014
Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property
More informationSuperintendent Proposed Capital Improvements Program. Fiscal Years
Superintendent Proposed Capital Improvements Program Fiscal Years 2016-2025 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-7 Capital Projects Description Pages 8-16 SUPERINTENDENT PROPOSED CAPITAL
More informationWILKINSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationArchitectural Services Consultant Registration Form
Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,
More informationBUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION
I. PURPOSE BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION To ensure the proper process to request and obtain approval for all renovation or new construction projects within Bucknell
More informationThe Knox County Recommended 5 million PPU FY11 by needs
The Knox County Recommended 5 million PPU FY11 by needs Electrical D W/O Request Description Budgeted GREEN MAGNET 1 60848 Install new intercom system $19,000 BELLE MORRIS ELEMENTARY 2 60850 Install new
More informationPATTERSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationSchool Board Work Session Dec. 13, 2016
School Board Work Session Dec. 13, 2016 POPULATIONS AND FACILITIES USE ASSESSMENT Dinwiddie High School Dinwiddie Middle School Dinwiddie Elementary School Midway Elementary School Southside Elementary
More informationHartsville Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: Southside Early Childhood Observed By: Cannon/Carter Principal: Grade
More informationSCARSDALE PUBLIC SCHOOLS Bond Project Planning
SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning October 23, 2017 2017 Bond Project Planning - Overview 1) December 2014 Bond (2013-2014) Work in this bond included for Heathcote, Edgewood, Middle School,
More informationMinuteman Regional Vocational Technical School
Minuteman Regional Vocational Technical School List of Recommendations L1 AAB compliance: Improvements to front entrance (concrete ramps, railings, etc.) Required by AAB cost trigger L2 AAB compliance:
More informationCheldelin Middle School
Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Dec 15, 2014 Condition Assessment: Suitability Assessment: Generated: 12/15/2014 12:11:31 PM FOR OFFICIAL USE ONLY Final School Assessment
More informationInterior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT:
REV 2 CONCEPTUAL ESTIMATE FOR: Interior Architects, P.C Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY AT: BY: GARDINER AND THEOBALD INC Issued: 6/20/2013 BROOKLYN HEIGHTS LIBRARY, BROOKLYN
More informationAZUSA UNIFIED SCHOOL DISTRICT
AZUSA UNIFIED SCHOOL DISTRICT BOARD STUDY SESSION June 9, 2014 EVALUATION OF STATUS OF FACILITES AND FUTURE NEEDS NEEDS vs. FUNDING SETTING PRIORITIES 5) OTHER ADDITIONAL IMPROVEMENTS 4) OTHER ARCHITECTURAL
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationCOMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry
GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets
More informationFeasibility Site Report
Required Document for HomeStyle: Total rehabilitiation cost exceeds 15,000 OR At the recommendation of the HomeBridge Renovation Concierge Feasibility Site Report (AKA Feasibility Study) SUBJECT PROPERTY
More information10 Year Plan. Facilities Planning Guide. December 15, 2014
10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)
More informationLa Conner School District
hoarch.com La Conner School District Capital Bond Planning Meeting 4 - Master Plan Options / Budget Estimates July 18th, 2012 4010 Lake Washington Blvd, NE, Suite 320 Kirkland, Wa 425 828 8948 Agenda Meeting
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationPigeon Lake Regional High School Falun, Alberta
Pigeon Lake Regional High School School Facilities Evaluation Project Pigeon Lake High Wetaskiwin Regional District No.11 Pigeon Lake High EXECUTIVE SUMMARY In November 1999 Alberta Infrastructure engaged
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More informationSpringfield High School Master Plan Presentation Town Hal Meeting 3 Phasing / Traffic and Parking
1 3.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 3 Phasing / Traffic and Parking December 11th, 2014 2 3.2 Town Hall Meetings
More information0B MAGNOLIA HALL. Scale: 1:110. Date: Feb Time: 7:40 pm. User: brady. 10 ft
0B 2 m 1:110 7:40 pm. 01 5 m 1:230 7:38 pm. 02 5 m 1:230 7:38 pm. 03 5 m 1:230 7:45 pm. Facility Profile ( FP-1 ) City: State: Country: Address: Stories: Attic: Basement: Glassboro New Jersey United States
More informationHampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects
2018 High School Feasibility Study Final Feasibility Study Presentation January 28, 2019 1 Study Updates I. Latest HS Concepts for Academic / Wellness Redesign II. Associated Conceptual Construction Costs
More informationCompleted projects. Projects in progress. Program developments
1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site
More informationSchool Assessment Report
School Assessment Report School: KIPP Vision Report: Dec 15, 14 Condition Assessment: Suitability Assessment: Generated: 12/15/14 12:33:33 PM Final School Assessment Report - Charter Schools, KIPP Vision
More information3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000
More informationWhat is a Master Plan
What is a Master Plan Master planning A long-term, comprehensive approach to facilities planning (10-12 years) Align facilities plan with mission, vision, strategic goals and community values Recognizes
More informationdate: 10 july 2012 the pennsylvania state university: burrowes building
the pennsylvania state university: burrowes building. faculty/staff committee project overview introductions goals of the renovation critical considerations exterior envelope mechanical systems interior
More informationOBJECTIVE 1.1: To establish the acceptable use and capacity of each building.
GOAL 1: To implement planned and routine maintenance programs which will extend the useful life of all buildings and prevent premature capital outlay for replacement. Through managed maintenance, Facilities
More informationOverbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %
8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior
More informationNew Hall High School Project Summary Report to the Board of Education June 3, 2015
New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete
More informationAl Behrman Elementary School
Mulberry Street Al Behrman Elementary School Relocate reception and principal s office to be adjacent to main entrance doors; provide secure entrance sequence and increase transparency to the exterior
More informationROD Grant Round 4 Presentation June 9, 2014
ROD rant Round 4 Presentation June 9, 2014 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 2 Agenda NJDOE Application
More informationDesign Advisory Committee Meeting #5. December 19, 2017
Design Advisory Committee Meeting #5 December 19, 2017 1 Meeting Agenda 1. Agenda / Attendance Sheet 5 minutes 2. BEST Grant Recap 3. Review Funding Options additional information 4. Master Plan Summary
More informationKEY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationBoard Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016
Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation June 13, 2016 Schedule/Major Milestones 2015 November December Data Collection Board Meeting- Update 2016 January
More informationSCARSDALE PUBLIC SCHOOLS Bond Project Planning Update
SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning Update November 6, 2017 2018 Bond Project Scope Review 1) District-wide Improvements 2) Greenacres Spatial 3) Security Vestibules 4) Summary Totals 2017
More information