Jonathan Nelson Construction Management Dr. Messner DC Youth Center Laurel, MD 29 September 2008 Technical Assignment 1 Submission 1
|
|
- Edwin Fox
- 5 years ago
- Views:
Transcription
1 Jonathan Nelson Construction Management Dr. Messner DC Youth Center Laurel, MD 29 September 2008 Technical Assignment 1 Submission 1
2 DISTRICT OF COLUMBIA YOUTH CENTER LAUREL, MD PROJECT TEAM OWNER DC Office of Property Management CLIENT Department of Youth Rehabilitation Services ARCHITECT DMJMH&N STRUCTURAL ENGR DMJMH&N CIVIL ENGINEER Delon Hampton & Associates MEP ENGINEER Schlenger/Pitz CONSTRUCTION MGR Temple Group GENERAL CONTRACTOR Tompkins Builders / Hardie Industries J.V. LANDSCAPE ARCHITECT Lee & Associates The DC Youth Center is a $42 Million, 88,000 SF juvenile rehabilitation facility which will be able to provide a full range of education and health services for up to 60 students. The campus fosters learning and development with open, shared spaces for students, a colored CMU and stucco façade, windows and storefronts. The five building facility includes: Academic & Vocational Dept. Health and Social Services Kitchen and Cafeteria Administration Wing 120 Seat Theater Central Courtyard 150 Parking Spaces STRUCTURAL SYSTEMS Strip Footings and SOG Steel Columns and Load Bearing CMU Walls Metal Deck on Open Web Joists Pre-Engineered Steel Structure Exposed Wood Trusses and Decking ELECTRICAL SYSTEMS Centrally Controlled Electronic Security Uninterrupted Power Supply Motion Sensitive Surveillance System Metal Detector & Sally Ports 3 PH 277 V Fluorescent Lighting Freestanding Gymnasium Outdoor Basketball Court Football Field Baseball Diamond Outdoor Track Warehouse 3 Housing Units CONSTRUCTION LSDB Requirements Minority Requirements LEED Silver Rating Bullet and Impact Resistant Assemblies Institutional Fixtures and Assemblies Sloped Metal and Flat PVC Roof MECHANICAL SYSTEMS Roof Mounted AC Units Energy Recovery Ventilator Gas Fired Furnace with DX Cooling Full commercial kitchen VAV Terminal Units Dental Exam Room JONATHAN NELSON CONSTRUCTION MANAGEMENT ENGR.PSU.EDU/AE/THESIS/PORTFOLIOS/2009/JKN119
3 Executive Summary The District of Columbia Youth Center is a $42 Million rehabilitation facility for youth offenders. The campus will comprise of 5 buildings and include educational, recreational, medical, social and food services for up to 60 students. A Campus Administration building houses all the non security staff and services. A Gym / Warehouse provides an indoor basketball court, storage and a garage for maintenance. Three housing units provide the youth with their own room and common spaces for use during the day. The Department of Youth Services (DYRS) will occupy the space and in order to fulfill their mission, requested the campus be an open atmosphere that promotes its mission. The combination of security and accessibility for the facility created a unique project. A design build delivery, LEED Silver certification, large scale abatement and extensive security system make the project worth investigating further, specifically its schedule, cost and construction methods. The design build delivery was chosen to complete the project as quickly as possible because the existing facility is inadequate for DYRS to fulfill its mission. A slow abatement process forced the GC to excavate and pour concrete in the winter months and compress the remainder of the schedule. The total hard bid of the project was $42 Million. Each of the buildings serves a different purpose and the finishes and costs per square foot are very different. The project has a little bit of everything office spaces, medical rooms, sally ports, a theatre, gym, cafeteria, a track and ball field, and a technology center. Pinning the number down with a rough order of magnitude estimate is difficult. Because of the security that must be in place, the facility has assemblies that would not typically be encountered on other projects. High impact drywall, fully grouted interior CMU walls, bullet proof glass, detention windows, fixtures and fences are a few of the uncommon elements seen in the one story buildings. Page 1 of 15
4 Table of Contents Cover Page Project Abstract Executive Summary 1 Table of Contents 2 Project Schedule Summary Milestone Schedule Narrative 3 4 Building Systems Summary 5 Project Cost Summary D4 Estimate R.S. Means Estimate Actual Cost Evaluation Existing Conditions Narrative Site Plans Local Conditions 13 Client Information 13 Project Delivery System 14 Staffing Plan 15 Page 2 of 15
5 Jonathan Nelson ID Task Name Duration Start Finish 1 Procurement of Construction Service 0 days 11/29/ /29/ Program Design 36 days 11/29/2006 1/17/ Design Development 300 days 1/18/2007 3/12/ Construction Documents 309 days 2/15/2007 4/22/ Notice To Proceed 0 days 1/11/2007 1/11/ Abatement of Existing Buildings 152 days 3/21/ /18/ Clear Site & Demolition 133 days 10/4/2007 4/7/ Site Utilities 177 days 1/3/2008 9/5/ Site Finishes 237 days 3/7/2008 2/2/ Excavation 75 days 11/19/2007 2/29/ Campus Administration 302 days 11/27/2007 1/22/ CA 113 days 11/27/2007 5/1/ CA 52 days 3/18/2008 5/28/ CA 197 days 2/7/ /7/ CA Watertight 0 days 7/17/2008 7/17/ CA 173 days 4/8/ /4/ Interior CA 195 days 3/18/ /15/ Testing & CA 86 days 8/28/ /25/ CA Complete 0 days 1/22/2009 1/22/ Housing Units 272 days 1/8/2008 1/22/ HO 69 days 1/8/2008 4/11/ HO 41 days 6/2/2008 7/28/ HO 148 days 2/22/2008 9/16/ HO Watertight 0 days 8/29/2008 8/29/ HO 153 days 4/14/ /12/ Interior HO 156 days 4/3/ /6/ Testing & HO 110 days 8/4/2008 1/2/ HO Complete 0 days 1/22/2009 1/22/ Gym / Warehouse 319 days 2/20/2008 5/11/ G/W 56 days 2/20/2008 5/7/ G/W 33 days 6/24/2008 8/7/ G/W 155 days 4/4/ /6/ G/W Watertight 0 days 10/7/ /7/ G/W 188 days 4/16/2008 1/2/ Interior G/W 79 days 10/16/2008 2/3/ Testing & G/W 69 days 2/4/2009 5/11/ G/W Complete 0 days 2/2/2009 2/2/2009 DC Youth Center Project Milestone Schedule 2008 Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Procurement of Construction Services Program Design Design Development Construction Documents Notice To Proceed Abatement of Existing Buildings Clear Site & Demolition Site Utilities Campus Administration Housing Units Gym / Warehouse Excavation CA CA CA Watertight CA Technical Assignment 1 29 September 2008 CA Interior CA Testing & CA CA Complete HO HO HO HO Watertight HO Interior HO Testing & HO HO Complete Gym / Wa G/W G/W G/W G/W Watertight G/W Interior G/W Testing & G/W Complete Critical Path Split Milestone Project Summary External Milestone Task Progress Summary External Tasks Deadline Page 3
6 Schedule Narrative The project began design in November of 2006 when the general contractor came on board to assist with the program design. Wanting a quick turnaround, the owner chose a design build delivery. The project will replace an existing facility and required removal of hazardous materials and demolition of three buildings and utilities. Each building is only one level and required minimal excavation however winter conditions slowed the excavation and SOG pour. Once the foundation was down, the load bearing masonry walls controlled the schedule. Water tight for the Campus Administration and the Housing Units came in July and August respectively. The Gym / Warehouse was designed as a pre engineered steel structure for quick erection so the building could serve as storage to procure materials in a timely manner. Anchor bolt misplacements and an underperforming subcontractor have pushed the watertight date for the Gym / Warehouse to October. The MEP schedule is tight because of the complexity of the systems. The electrical work includes an extensive security system with closed circuit television and 7 control stations. The nature of the project calls for trades to have multiple crews in different buildings. Subcontractors must work in spaces as they become available, not after they finish one section. The original completion date was set for December of 2008 but with abatement and permit delays in the beginning of the project, it is now expected to finish in January. Page 4 of 15
7 Building Systems Summary Demolition The project site was at the same location of an existing, unused facility that includes many buildings. The new rehabilitation center is placed at the center of the property requiring demolition of three buildings. Prior to demolition each building had to be abated for lead and asbestos. The buildings once served as an aquatic center, school and housing. It took seven months to remove the hazardous materials before the buildings could be removed and excavation could begin. Structural Steel Frame A combination of structural steel and load bearing masonry was used for the facility. Steel was used for clerestories support, columns and girders for the mid span of flat roofs, joists for the Campus Administration (CA) building and storefront framing in the housing units (HO). A 90 ton mobile crane was sufficient for erection at CA and a 30 ton mobile crane at HO. The Gym/Warehouse (G/W) used an all steel structural system. A 115 ton mobile crane was used to erect columns and rafters while a lull and scissor lift was used to place purlins and bracing. Because of the great accessibility of the site, cranes were able to easily move along the outside of the buildings to make the picks. Cast In Place Concrete Cast in place concrete was used for the strip footings, foundation walls, slab on grade, mezzanine floors and roof slab. Formwork for slab on grade and the foundation was wood and mezzanine and flat roofs had a metal deck with pour stop. SOG and footings were directly placed and elevated slabs were pumped. Precast Concrete Project had no substantial precast members. A few window lintels. Mechanical System Each building has its own mechanical room and is accessible from the exterior of the facility. Systems include gas fired furnace, direct exchange cooling, propane, roof top units. Heating and cooling is forced air. Fire suppression is a wet sprinkler system. Electrical System Main transformer 480V 3PH 2000A Uninterrupted Power Supply with 5000KW Diesel Generator 180 / 270 V 3PH distribution for all lighting and equipment 108 / 120 V 3 PH for receptacles Over 100 CCTV surveillance cameras and centrally controlled electronic locks Page 5 of 15
8 Masonry Fully grouted, reinforced load bearing back up wall with colored CMU façade was designed for CA and HO. Grouted connections to steel and SOG. Pipe scaffolding used with lull to feed block. On the curved façade of CA there is a glass block wall supported by angles that allow for daylight into the Student Commons area. Exterior Wall Assemblies 4x8 colored CMU façade up to 10 4 from SOG and stucco on dens glass and metal stud above Glass storefronts at major entrances. Clerestories are located at the South and North of CA. The G/W has the same colored CMU but it joins a metal siding panel rather than stucco. Excavation Deepest excavation went to 2 6 below grade. No excavation protection was needed for the foundation. Utility lines went as deep as 15. For these holes, the excavation was tiered to provide a safety from collapse. Dewatering system used was simple sump pumps in existing SWM drains and in newly excavated areas. Water runoff was a contiguous problem on site because of the large, unseeded areas and frequent rain. Page 6 of 15
9 Project Cost Summary D4 Cost Estimate Statement of Probable Cost Project Information Prepared By Jonathan Nelson Prepared For Tech. Assignment 1 AE 481W 29-Sep-08 Projected Size Projected Location MD - Annapolis Building Height Varies Projected Date Jan-08 Building Use Civic/Gov. Foundation SOF No. of Buildings 5 Exterior Wall CMU Site Size Interior Wall GYP 1st Floor Size Roof Type MET 1st Floor Height 0 Floor Type CON Number of Floors 1 Project Type NEW Building Costs Division # Label Projected % Projected Sq. Cost Projected 0 Bidding Requirements ,323 1 General Requirements ,317,533 2 Existing Conditions ,739 3 Concrete ,431,247 4 Masonry ,349,965 5 Metals ,841,872 6 Wood, Plastics, and Composites ,704 7 Thermal and Moisture Protection ,892 8 Openings ,362 9 Finishes ,341, Specialties , Equipment ,041, Furnishings , Special Construction , Conveying Systems , Mechanical ,874, Electrical ,910, Fire Suppression , Plumbing , HVAC , Electrical ,105, Earthwork , Exterior Improvements , Utilities ,689 Total Building Costs ,702,631 Page 7 of 15
10 R.S. Means Estimate Building Cost Description SF LF Housing Units Base Cost Perimeter Adj. Height Adj. Cost Unit QTY Face Brick w/ CMU Back Up, Steel Joists CCTV EA Dryer EA Total $2,361,430 x3 per SF Gym / Warehouse $7,084,290 Face Brick w/ CMU Back per Up and Rigid Steel Frame SF Up to 15 Tier Manual Telescoping Seats Seat Gym Divider SF Scoreboard EA 1.5" Wall Mats SF Lockers EA Locker Bench LF Amplifier EA Speaker EA CCTV EA Total $3,936,016 Campus Admin. Office Medical Office Elementary School Brick on Block, Steel Deck Roof per SF Brick on Block, Steel Deck per Roof SF Brick on Block, Bearing per Walls SF CCTV EA Flag Poles EA Broiler EA Walk In Cooler EA Walk In Freezer EA Dishwasher EA Food Warmer Counter EA Range EA Lockers EA Bench LF Seating (auditorium) EA Seating (classroom) EA Examining Table EA $7,171,937 Sub Total $18,192,243 City Index Annapolis, MD x 0.9 Assume 2008 Costs x 1 $16,373,019 Page 8 of 15
11 Actual Project Costs Cost Cost / SF % of Project Cost Design $ 3,541,670 $ % Site work $ 7,265,890 $ % Structural $ 3,480,751 $ % Mechanical $ 7,329,472 $ % Electrical $ 8,980,814 $ % Campus Administration $ 16,625,919 $ % Housing Units $ 8,772,738 $ % Gym / Warehouse $ 6,084,112 $ % Building Construction $ 31,482,770 $ % Project $ 42,069,216 $ The estimates for the project came very far under the actual cost. This was expected because not only is it a rough order of magnitude estimate, but also it is an uncommon project that combines different types of buildings. R.S. Means was furthest off because it could not account for the high cost per square foot of mechanical and electrical systems. D4 was a little more accurate because of the averaging function. A combination of a school, small medical office and another, presumably similar facility was used to model the cost. After all that though, the project is not common enough to be matched on this level because of the combined security and accessibility of the facility. An assemblies method will prove to much more accurate. Page 9 of 15
12 Site Plan Narrative The satellite photo shows existing conditions prior to Notice to Proceed. The entire facility is mostly unused and rundown. A few buildings at the southern end are used by DYRS and North of the site, not shown is the current Oak Hill Youth Center accessible by River Road. The existing conditions require considerable demolition but the site is very accessible in terms of deliveries and equipment and parking for workers was not an issue. The spread out site allowed for multiple crews to be working simultaneously without interfering with each other s work. Page 10 of 15
13
14
15 Local Conditions Laurel, MD is located half way between Washington, DC and Baltimore, MD. As such, there was plenty subcontractors available and this did not place any restrictions on construction methods. Tipping fees for the area were XX and parking for the site was not an issue. Subsoil have not obtained reports yet. Track is built just off the 100 year flood plain, wetlands nearby. Client Information The owner of the project is District of Columbia Office of Property Management (OPM). They oversee maintenance and construction of all the district s property regardless of which agency uses it. The agency to occupy the DC Youth Center is the Department of Youth Rehabilitation Services (DYRS). The DC Youth Center is being built so that DYRS may better fulfill its mission of providing educational, therapeutic, recreational and cultural enrichment programs to detained juvenile offenders. The existing facility (Oak Hill Youth Center) is not conducive to their mission. Expectations for the project are to receive a building that is durable and minimizes maintenance. Because the facility will be inhabited by juvenile offenders, it is likely the building will receive a lot of abuse throughout the years. Using durable materials such as detention rated glazing, high impact drywall and interior CMU partitions will minimize the replacement of materials. The schedule of the facility is important but flexible as the existing facility is still operational. The original project completion date was June 5 th 2008 and is now projected to be January 22 nd Milestones of interest to the owner, other than completion is bringing the security system online and substantial completion. DYRS must have each security guard become familiar with the buildings systems before they can bring any youth into it. The sooner the system is online, the sooner the switch can be made. At substantial completion, office personnel will begin moving equipment, etc. into the space. Page 13 of 15
16 Project Delivery System The DC Youth center is being delivered as a Design Build project with a construction manager. Using a construction manager is typical for OPM s projects to assure quality and timely completion but the CM is not at risk and holds no contracts with the GC or any other players. A design build, hard bid delivery was decided upon in interest of time to replace the existing, inadequate facility. The contractor was selected based on best value. A joint venture for the general contractor is to fulfill minority participation requirements by the owner. Hardie Industries is the minority partner. A single MEP contractor was selected to ease coordination issues. Awaiting bond and insurance information. Page 14 of 15
17 Staffing Plan The design build delivery called for increased general conditions cost to process submittals in a timely manner. The joint venture divided responsibilities at each level but Tompkins Builder s had more experience overall and filled the top positions. On site each person reports directly to the Senior Project Manager or General Superintendent but among the different disciplines, there are more informal lines of communication. Page 15 of 15
Section 4 - Design and Construction Overview
Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationTechnical Assignment 1 Construction Project Management
Technical Assignment 1 Construction Project Management Technical Assignment 1-1 - Table of Contents A. Executive Summary.3 B. Project Summary Schedule.4 C. Building Systems Summary 5 D. Project Cost Evaluation..8
More informationTech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey
Tech Assignment 1 University Medical Center of Princeton Plainsboro Road, Township of Plainsboro, New Jersey David Bodnar CM Chris Maget 10/5/2009 Table of Contents Executive Summary...3 Project Schedule
More informationBuilding Architecture
The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L
More informationSchool Assessment Report
School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report
More informationDOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.
DOCUMENT 00 43 36B EXPANDED SUBCONTRACTORS LISTING TO: CLARK COUNTY SCHOOL DISTRICT hereinafter called "Owner" FROM: ~AU;)"''"-' Oeve\,(;p,-...e,.,,... IA... t. ~o~ t>.m..e>u,i-j (Print Company Name) Pe-Mo1..,,,-t,:;>.tJ
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationConstruction Project Management
Technical Assignment 1 Construction Project Management Cathy Neiderer Pasadena Elementary School Technical Assignment 1 Table of Contents Executive Summary... 3 Project Schedule Summary... 4 Building Systems
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationTechnical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction
Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building
More informationIntroduction & Project Background
Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationProject Estimate Summary
Project Estimate Summary Project Cost Evaluation Table 4 shows the Construction Cost, CC/SF, Total Cost, TC/SF, the Building Systems Cost, and Building Systems Cost/SF based on the budget for. Table 4
More informationField House Proposal
Field House Proposal For Experienced Dependable Resourceful 5802 Akron Cleveland Rd. Hudson, OH 44236 Table Of Contents Cost Projection 3 Funding Summary 4 Site Plan 5 Field House Layout 6 Field House
More informationSchool Assessment Report
School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School
More informationPROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction
More informationTABLE OF CONTENTS Public Safety Building
DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationMills Elementary School Site Summary
1 Mills Elementary School Site Summary Address 6201 Davis Lane Austin, TX 78749 Number of Permanent Campus Facilities 1 Original Year of Construction 1998 Total Campus Building Area (combined) 81,368 SF
More informationBorough of Doylestown Building and Zoning Department
Borough of Doylestown Building and Zoning Department 57 West Court Street, Doylestown, PA 18901 215.345.4140 RESIDENTIAL BUILDING AND ZONING PERMIT APPLICATION PACKAGE BACKGROUND A building permit is required
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationProject Manual Index of Specifications Shenandoah Schools Concession Building
INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions
More informationTimberglen Recreation Center Summary
Timberglen Recreation Center Summary Address Building Purpose 3810 Timberglen Road Dallas, TX 75287 Recreation Center Original Year of Construction 2003 Building Area 15,000 SF Inspection Date August 2,
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Dec 15, 2014 Condition Assessment: Suitability Assessment: Generated: 12/15/2014 12:11:31 PM FOR OFFICIAL USE ONLY Final School Assessment
More informationOverbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %
8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior
More informationSchool Assessment Report
School Assessment Report School: Humphries Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:35:17 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationTECHNICAL ASSIGNMENT #1: CONSTRUCTION PROJECT MANAGEMENT. Philip J. Corrie Construction Management AE Faculty Advisor: Dr. Horman
TECHNICAL ASSIGNMENT #1: CONSTRUCTION PROJECT MANAGEMENT Construction Management AE Faculty Advisor: Dr. Horman Aloft & Element Hotels at Arundel Mills Hanover, Maryland October 5, 2007 Table of Contents
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationLEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies
MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules
More informationTown of Pawling Residential Building Permit Application
Town of Pawling Residential Building Permit Application Property Address: Street: City: Zip: Grid Number: Zoning District: Project Description: Owners Name: Phone: H W/C Address: Street: City: State: Zip:
More informationCITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS
CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS Update April 29, 2013 12 Permit application forms and contact information can be found on our website under Inspection Department
More informationProject Design Overview
Project Design Overview Architecture: is just one step Washington DC is taking to uplift many of its neighborhoods. In an area where graffiti is a common sight, this building will provide a center for
More informationConstruction Summary
Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationTECHNICAL ASSIGNMENT #2
DEREK C. BAUER CONSTRUCTION MANAGEMENT DR. MICHAEL HORMAN TECHNICAL ASSIGNMENT #2 OFFICE/RETAIL BUILDING WASHINGTON, D.C. SUBMITTED: NOVEMBER 2, 2007 TABLE OF CONTENTS Executive Summary... 2 Detailed Project
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More informationCARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationTown of Pawling Residential Building Permit Application
Town of Pawling Residential Building Permit Application Property Address: Street: City: Zip: Grid Number: Zoning District: Project Description: Owners Name: Phone: (H) (W) Address: Street: City: State:
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationDelco Activity Center Site Summary
1 Site Summary Address 4601 Pecan Brook Austin, TX 78724 Number of Permanent Campus Facilities 1 Original Year of Construction 2003 Total Campus Building Area (combined) 60,294 SF Introduction The is located
More informationSection 5 - Project Logistics
Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,
More informationKatie Sennett. Dec. 18, Baltimore, Maryland. Proposal. Page 2. Page 1
Table of Contents o Executive Summary......... Page 2 o Building Introduction..........Page 4 o Analysis 1.................. Page 8 o Analysis 2................. Page 10 o Analysis 3.................Page
More informationResearch Facility Core and Shell 2012
Research Facility Core and Shell 2012 Technical Report 2 Timothy Maffett Construction Management Advisor: Dr. Messner San Anto, California Submitted: October 12, 2012 Executive Summary Design for Research
More informationLake Highlands North Recreation Center Summary
Lake Highlands North Recreation Center Summary Address Building Purpose 9940 White Rock Trail Dallas, TX 75238 Recreation Center Original Year of Construction 1971 Building Area 33,036 SF Inspection Date
More informationFACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY
FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY DATE: November 20, 2012 SDSU requests approval of this Facility Design Plan to continue planning the
More informationTechnical Report #2. Matthew R Peyton
Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationLASALLE - BACKUS EDUCATION CAMPUS
INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 Y DATE: December 6-8, 2016 ****************************************************************************** SUBJECT: SDSU Student Wellness
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationGabriela Perez. Forest Peterson Hossein Nasseri. Plamen Ivanov. Jaclyn Lee. Henning Roedel. Ridge Winter Presentation EP A
Jaclyn Lee Gabriela Perez Forest Peterson Hossein Nasseri Henning Roedel Plamen Ivanov Ridge 2010 Winter Presentation EJ EP A C Site - University of Nevada, Reno Challenges Earthquakes Gusts from the Sierra
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationDr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4
Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS Executive Summary.1 Detailed Project Schedule..2 3 Site Layout Planning 4 Assemblies Estimate 5 Detailed Structural Estimate..6 7 General Conditions
More informationTracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management
Tracy Lo Terrell Place 575 7 th Street NW Washington DC November 4, 2002 Construction Management Alternate Systems and Methods Analysis Executive Summary Studies on the following subtopics are helpful
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationUCC Permit Application Procedures
How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.
More informationPHASE 1 Foundation & Drainage New Construction Phased Inspection Report John & Mary Doe 5237 Clinton Street, Denver, CO 80238
PHASE 1 Foundation & Drainage New Construction Phased Inspection Report John & Mary Doe 5237 Clinton Street, Denver, CO 80238 PHASE 1 Foundation & Drainage New Construction Phased Inspection Report Buyers
More informationHeritage High School
Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery
More informationExisting Construction Conditions
Tracy Lo Terrell Place 575 7 th Street NW Washington DC September 23, 2002 Construction Management Existing Construction Conditions Executive Summary For this assignment, I have sent out an email to gather
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationMinitab Headquarters
Minitab Headquarters State College, PA Erin E. Hess www.arche.psu.edu/thesis/eeh124 Consultant: Dr. David Riley This project delivery evaluation report researches and analyzes the agreements and commitments
More informationVoigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1.
Voigt 1 Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1 Executive Summary Located in northwest Washington, D.C. at the corner of
More informationSERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS
SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,
More informationShow how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality
Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge
More informationPage(s)
Robert M. Leicht Construction Management Option Advisor: Dr. John Messner Bldg: Smithsonian Institution Patent Office building Washington, DC 10/4/04 Technical Assignment 1 Executive Summary: The Smithsonian
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More information1 AND 2 FAMILY DWELLING REQUIREMENTS
PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationSchool Assessment Report
School Assessment Report School: Cascade Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:55 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationMinneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C
2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM
More informationFACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017
FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationSchool Assessment Report
School Assessment Report School: KIPP Vision Report: Dec 15, 14 Condition Assessment: Suitability Assessment: Generated: 12/15/14 12:33:33 PM Final School Assessment Report - Charter Schools, KIPP Vision
More informationTech Report 1. The Duffy School. Jeremy Drummond. Construction Management. Anumba. The Duffy School. Florence, NJ
Tech Report 1 The Duffy School Jeremy Drummond Construction Management Anumba The Duffy School Florence, NJ 9/19/2014 P a g e 1 Executive Summary Client Information The owner of The Duffy School renovation
More informationTechnical Assignment #1 VA State Capitol Thesis
Eric Fritz Construction Management Dr. Messner VA State Capitol Extension and Renovation Richmond, VA October 4, 2004 Technical Assignment #1 Technical Assignment #1 VA State Capitol Thesis By Eric Fritz
More informationThesis Technical Assignment #1
Written By: Brenton Decker Option: Construction management Faculty Advisor: Chimay Anumba Date of Submission: Sept. 29, 2008 Thesis Technical Assignment #1 Construction Project Management George Mason
More information2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities
More informationFacilities Feasibility Study Frederick Douglass HS Condition Assessment
Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationProperty Condition Assessment
Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072
More informationMANHATTAN COLLEGE STUDENT COMMONS
MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons
More informationTechnical Assignment 1
Westinghouse Electric Company Nuclear Power Engineering Campus Technical Assignment 1 Construction Project Management Mark Speicher Advisor: Dr. David Riley October 5 th, 2009 09 TABLE OF CONTENTS EXECUTIVE
More informationBuilding Inspection Report
Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941
More informationCafeteria Modernization
United States Department of the Interior Cafeteria Modernization Michael Gorman Construction Management Dr. RILEY Department of the Interior Cafeteria Modernization 1849 C Street NW, Washington D.C. October
More information4. Technical Report #3: Alternate System and Methods Analysis
4. Technical Report #3: Alternate System and Methods Analysis 4.1. Executive Summary This technical assignment covers the analysis of various building system cost, scheduling, site planning, and general
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationTaylor Hall. Technical Assignment 1. Summary Slides. George Mason University. Brad Williams Construction Management Faculty Consultant: Ed Gannon
Taylor Hall George Mason University Fairfax, VA Technical Assignment 1 Summary Slides Brad Williams Construction Management Faculty Consultant: Ed Gannon Technical Assignment 1 September 16, 2013 Taylor
More informationWatercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS
Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING
More informationAPPLICATION AND CERTIFICATE FOR PAYMENT
AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More information