1 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012
2 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown Independent School District 2
3 2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Original: $25,574,000 CATE Addition $2,121,338 Baseball & Softball Turf - $880,000 Total - $28,575,338 I I J H H New Athletic Addition F G H J First Floor J Bid Package 1 A B Existing East View High School J D CR E J B C ay hw Hig A. B. C. D. E. F. G. H. New Athletic Addition New Fine Arts Addition New Academic Addition New CTE Building New ROTC Addition (Alt.) New Tennis Courts New Tennis Building New Baseball/Softball Fieldhouse, Bleachers, Lighting & Pressbox I. New Practice Fields J. New Parking (1,070 spaces) New Fine Arts Addition New Academic Addition New Academic Addition CTE Building Second Floor Academic Wing Softball Field House Georgetown Independent School District New CTE/ROTC Addition 3
4 EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Addition Interior partition installation is nearing completion. Exterior masonry veneer is currently being installed around the academic wing. Roof structure, decking and insulation are in place. Finished metal roof panels will start being installed next. Athletic Addition Exterior masonry veneer is complete at the locker room addition Ceiling installation and wall painting has begun at the locker rooms. Exterior masonry veneer is currently being installed around the gym and is nearing completion. Veneer installation at the gym enrty will begin next. Roof installation is complete at the gym roof. Roof installation at the gym entry will begin next. Painting and lighting inside the gym will begin next. CATE/ROTC Steel super-structure is in place for both east and west sides of the CATE. Masonry walls at the exterior are being constructed. Masonry walls for the storage mezzanine are being constructed. Once these are complete the slab for the storage mezzanine will be poured. Academic Corridor Georgetown Independent School District 4
5 EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Wing Gym & Locker Rooms Georgetown Independent School District 5
6 Gym Entry CATE Georgetown Independent School District 6
7 2010 BOND PROGRAM UPDATE Construction Manager GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS BAIRD WILLIAMS CONSTRUCTION BAIRD WILLIAMS CONSTRUCTION GEORGETOWN HIGH SCHOOL 3D Rendering Project Manager Front Entry Boards.indd 4 CTE Wing 7/26/11 8:55 AM Cafeteria Athletics Academic Athletics Athletics Auditorium Computer Labs Science Labs Library Athletics Academic Special Education Fine Arts Georgetown Independent School District 7
8 GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS Phase I CAFETERIA/CLASSROOM ADDITION Steel super-structure is in place. Steel roof decking is being installed. Perimeter and interior masonry walls are being constructed. ATHLETICS ADDITION Masonry wall construction has begun. The remaining slab for the locker rooms is set to pour next. KITCHEN RENOVATION Utility rough-in at existing slab is complete. Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen slab can be poured. New steel structure supporting the existing roof is in place. EXISTING GYM & LOCKER ROOM RENOVATION Demolition of existing wood floor at lower gym is complete. Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in these areas is complete, utility rough-in for new locker rooms and restrooms can begin. Cafeteria Interior Georgetown Independent School District 8
9 georgetown high school additions and renovations Cafeteria Exterior Locker Room Addition Georgetown Independent School District 9
10 Kitchen Renovation Locker Room Demolition Georgetown Independent School District 10
11 GEORGETOWN HIGH SCHOOL AND RENOVATIONS Athletic Addition Kitchen Expansion Cafeteria Expansion Greenhouse Classroom Addition Aerial Georgetown Independent School District 11
12 COMPLETED PROJECTS EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1 Contract Amount: $5,321,000 Substantial Completion Date: August 19, 2011 General Contractor: Charter Builders NEW WAREHOUSE FACILITY Contract Amount: $641,000 Substantial Completion Date: November 9, 2011 General Contractor: CSS, Inc. ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION Contract Amount: $229,000 Substantial Completion Date: August 12, 2011 General Contractor: Saratoga Field House Locker Room Interior View of Warehouse New HVAC Unit and Roofing Field House Weight Room Storage Shed New Ceiling and Light Fixtures Georgetown Independent School District 12
Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi
Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationLOVEJOY Independent School District
Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationLANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent
RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCENTENNIAL SCHOOL DISTRICT
CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites
More informationMADISON HIGH SCHOOL // Executive Summary
MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationLEWIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMadison School District. Strategic Five-Year Facility Maintenance Plan
Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since
More informationWILKINSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationPortsmouth Middle School Additional Funding Request
City Council Work Session Portsmouth Middle School Additional Funding Request Monday March 18, 2013 Project Background School Board selected Parrott Avenue site after lengthy, comprehensive and public
More informationLOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN
INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS
More informationLECKIE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationFACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture
FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement
More informationCheldelin Middle School
Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:
More informationYardmen Arena Expansion & Renovation Project Update
For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville
More informationSubject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3
MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape
More informationScripps Ranch High School
Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic
More informationFACILITY NEEDS ASSESSMENT CURRENT PRIORITY ONE PROJECTS
9 - MARCH - 2015 Professional Team TMP Architecture, Inc. Peter Basso Associates, Inc. Integrated Design Solutions SUMMARIES SUMMARIES District Totals ELEMENTARY SCHOOLS Beverly Bingham Farms Greenfield
More informationLASALLE - BACKUS EDUCATION CAMPUS
INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationExhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number
Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationMaterial Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5
Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00
More informationSTUART-HOBSON MIDDLE SCHOOL
INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSECTION ALTERNATES
SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationFacility Study Update
Facility Study Update January 18, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Focus Groups Forums Surveys Revise / Refine Engagement Strategic
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction March 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim
More informationStructural Inspection
General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationBRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING
PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING
More informationRebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.
FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information
More information2451 Bert Drive, Hollister, CA
PROPERTY FOR LEASE OR SALE Overview: Located on 15.37 acres (8.35 acres are developed), this well-maintained, ±170,144 SF, Class C light industrial manufacturing facility features office, manufacturing
More informationFacilities Systems Upgrades
Facilities Systems Upgrades 1 Facility Assessment Background Information: In 2006, The Spring Branch Independent School District created a Long Range Facilities Planning (LRFP) Committee, charging it to
More informationThe parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.
EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building
More informationCONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.
More informationCreative Performing Media Arts Middle School
Dawne St Kilkee St Enelra Pl Creative Performing Media Arts Middle School 5050 Conrad Ave. San Diego, CA 92117 Sub-district: A Cluster: Madison Year School Opened: 2002 Grades: 6-8 Arlene Pl 3 2 Conrad
More informationProjects Currently in Planning, Design and Construction. April 12, 2017
Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space
More informationSchool Without Walls
INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMontrose Community Recreation Center Update & MRD Outdoor Facility Plan
Montrose CRC and Park Montrose Community Recreation Center Update & MRD Outdoor Facility Plan September 23 rd, 2015 Trails, Pickleball Courts, Playgrounds, Natural Areas, Picnic Areas, Water Play, Tennis,
More information90% Draft - NOT FINAL. A Presentation For: the architectural studio. By Principals: George Moore & Curt Santee October 28th 2014
A Presentation For: By Principals: George Moore & Curt Santee October 28th 2014 1 the architectural studio 2014 District Exterior Wall Forensic Study Warrior Run School Brick Study Completed on High School
More informationSection 4 - Design and Construction Overview
Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationNEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER
SUMMARY OGDENSBURG, NY The New York Main Street program (NYMS) is administered by the Office of Community Renewal (OCR) under the direction of the New York State Housing Trust Fund Corporation (HTFC).
More informationSTRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225
GENERAL NOTES DESIGN NOTES (CONTINUED) FOUNDATION NOTES STRUCTURAL ABBREVIATIONS CONCRETE MASONRY NOTES DESIGN NOTES S-001 CONCRETE NOTES COLD-FORMED STEEL FRAMING NOTES PRE-ENGINEERED METAL BUILDING NOTES
More informationStevens & Associates, Inc. Building Construction Projects. Fact Sheets
Stevens & Associates, Inc. Building Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Mount Washington Resort Spa & Conference
More informationRESIDENTIAL CONSTRUCTION PERMIT FEES
RESIDENTIAL CONSTRUCTION PERMIT FEES R-1 Building Permit: One- or Two-Family New Construction (Complete Permit Packet) Combination permit to include Building, Electrical, Mechanical, Plumbing (to include
More informationCONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.
CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS AUBURN. GARDEN OF MEMORY AUBURN MEMORIAL STUDENT AFFAIRS HOLCOMBE NORTON PARTNERS LANDSCAPE SERVICES The Auburn Memorial wall includes excerpts from the Auburn
More informationCATAMARAN TOWER - 1 Seef Area Plot 19, 20
STATUS REPORT NO 18 [As on September 30, 2017] This report is intended as a status report and covers only the activities completed till date, non-completed works and work-in-progress. A. Project Details
More informationINSPIRE each student to develop a strong
DEL PASO MANOR ELEMENTARY SCHOOL Valuing a culturally and academically DIVERSE COMMUNITY, Del Paso Manor Elementary School s Mission is to EDUCATE and INSPIRE each student to develop a strong A C A D E
More informationOctober 26, 2017 Ref.: Newfoundland & Labrador English School District 95 Elizabeth Avenue St. John s, NL A1B 1R6
October 26, 2017 Ref.: 351-1 Newfoundland & Labrador English School District 95 Elizabeth Avenue St. John s, NL A1B 1R6 Attention: Mr. Jim Sinnott Director of Facilities & Custodial Management Dear Sir:
More informationDivision 09 FINISHES TABLE OF CONTENTS
Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING
More informationLEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies
MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationKENTUCKY STATE UNIVERSITY
KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000
More information1. Sign-in sheet from the Pre-Proposal Conference on April 19, 2017 at Atherton Elementary.
DATE: April 20, 2017 ARLINGTON INDEPENDENT SCHOOL DISTRICT 1203 W. Pioneer Parkway Arlington, Texas 76013 ADDENDUM II FROM: Tammy Craig Director Purchasing RE: CSP 17-79 Amos & Atherton Elementary Renovations
More informationCONSTRUCTION UPDATE SEPTEMBER 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE SEPTEMBER THIS IS AUBURN. JORDAN-HARE STADIUM VIDEO BOARD INSTALLATION ATHLETICS DEPARTMENT ENGINEER: LBYD, INC. CONSTRUCTION MANAGER: BRASFIELD & GORRIE $13.9 AUGUST The video board
More informationWINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016
Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ WINNER 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Ivey Lane Elementary
More informationKingsborough Community College
Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2018-19 through FY 2022-23 Project Funding Type Five - Year Plan Total ( $ 000 s ) Performing Arts Renovations
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationSt. Germain Facility Study
Prepared for: Town of St. Germain Presented on: April 4, 2107 Prepared by: Funktion Design Studio, LLC 207 Windtree Drive Wausau, WI 54401 207 Windtree Drive Wausau, WI 54401 Melody 715-571-8122 Rick 920-379-7133
More information2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-
1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905
More informationOffice of Design & Construction State University Plaza Albany, New York
Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and
More informationDIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS
DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate
More informationFacility Assessment Report, Montgomery Independent School District
NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2
More informationFEASIBILITY STUDY SEPTEMBER 1 8,
FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study
More informationMount Vernon Elementary School Grades PK 5
Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount
More informationSCHOOL BASED ASSESSMENT RESULTS - QUESTION RESPONSES
SCHOOL BASED ASSESSMENT RESULTS QUESTION RESPONSES ANDREW JACKSON MIDDLE APOLLO ASTRONAUT SENIOR HIGH ATLANTIS AUDUBON BAYSIDE SENIOR HIGH CAMBRIDGE CAPE VIEW CENTRAL MIDDLE CHALLENGER 7 CHRISTA MCAULIFFE
More informationSchematic Design Report Johnson City ISD Football Stadium
Schematic Design Report Johnson City ISD Football Stadium March 30, 2015 Fromberg Associates, Ltd :: Architecture 2406 Lake Austin Blvd. Austin, Texas 78703 512.495.9171 Issued under the authority of Randall
More informationThe following shall be incorporated into the Contract Documents dated 26 MAR 2018.
ADDENDUM NO. 2 DATE: April 12, 2018 PROJECT: OWNER: BID DATE: Munising Public Schools Mather Elementary Renovation Munising Public Schools Friday, April 20, 2018 at 10:00 a.m. The following shall be incorporated
More informationThe Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage
The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco
More informationEasthampton High School Building Project. Public Information Forum #3
Building Project Public Information Forum #3 May 4, 2010 CAOLO & BIENIEK ASSOCIATES, INC. Architecture Planning Interior Design Presentation Agenda Introduction - Michael Buehrle, Chair EHS Building Committee
More informationREQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES
REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will
More informationCITY OF NOVI. Police Department
CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master
More informationBid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School
ADDENDUM No. 002 For Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School DALLAS INDEPENDENT SCHOOL DISTRICT September 24, 2014 The following items modify the Project
More informationCONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN.
CONSTRUCTION UPDATE June THIS IS AUBURN. RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Lobby of the Risk Management and Safety
More informationEnergy Efficiency / Renewable Energy (EE/RE) Projects in Texas Public Schools
Energy Efficiency / Renewable Energy (EE/RE) Projects in Texas Public Schools Jeff Haberl, Hyojin Kim, Jaya Mukhopadhyay, Juan-Carlos Baltazar-Cevantes, Sung Lok Do, Kee Han Kim, Cyndi Lewis, Bahman Yazdani
More informationA PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM
A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register
More informationThis addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.
Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,
More informationM-DCPS DESIGN CRITERIA Table of Contents
M-DCPS DESIGN CRITERIA Table of Contents TITLE Page No. Division 0: General Considerations 1.1 General... 0-1 1.2 Sustainability... 0-2 1.3 Site (Rev. 6/20/16)... 0-3 1.4 Buildings (Rev. 1/29/16)... 0-6
More informationImplementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and
More informationRESIDENTIAL COMPONENT TECHNOLOGY Mobile Manufactured Housing
RESIDENTIAL COMPONENT TECHNOLOGY Mobile Manufactured Housing GENERAL INFORMATION Policy Number: Insured Name: Property Address: Property Zip: Agent: Branch: Current Coverage: _ Account Number: _ PROPERTY
More informationMonthly Progress Report November 1, 2011
LOS ANGELES MISSION COLLEGE PROPOSITION A/AA BOND PROGRAM & PROPOSITION J BOND PROGRAM Monthly Progress Report November 1, 2011 Health & PE Fitness Center Lobby Page 1 of 14 THIS PAGE IS LEFT INTENTIONALLY
More informationThe Inspection Process. Waxhaw N.C.
The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT BOND PROGRAM REPORT NOVEMBER 4, 2003 BALLOT
SAN FRANCISCO UNIFIED SCHOOL DISTRICT BOND PROGRAM REPORT NOVEMBER 4, 2003 BALLOT TABLE OF CONTENTS Introduction 2 A Nuts and Bolts Bond Program 2 School of the Arts 4 Bungalow Replacement with New Construction
More informationSTRUCTURAL ASSESSMENT OBSERVATION REPORT
Consulting Engineers THORSON BAKER & Associates, Inc. 3030 West Streetsboro Road (330) 659-6688 phone Richfield, Ohio 44286 (330) 659-6675 fax www.thorsonbaker.com STRUCTURAL ASSESSMENT OBSERVATION REPORT
More informationCopyrighted Home Plan 2011 Natural Element Homes, LLC
29'-0" SQUARE FOOTAGE 6'-0" PORCH 3'-0" 6'-0" 2'-0" 3'-6" 8'-0" 2'-4" 3'-8" 6'-7" 3'-11" BCD3756-2 BCA2420T 3-0 9LITE BATH WOOD STOVE 10'-0" 2-4 15'-10 1/2" 3'-11" 6'-0" 11'-9 1/2" 15 R. @ 7 5/8" 14 T.
More informationBoard of Education Meeting
Geneva Community Unit School District #304 Operations and Maintenance 7 Year Capital Improvement Plan Board of Education Meeting December 8 th, 2014 O&M 7 Year Capital Improvement Plans Fall 2014 Page
More informationAlterations, disproportionality, and the 20% rule
Alterations, disproportionality, and the 20% rule By M. Bradley Gaskins, AIA, CASp and Ellis L. McIntosh Jr., AIA, LEED AP The MCintosh group 1850 South Boulder Avenue Tulsa, OK 74119 918.585.8555 tmgada.com
More informationEast Los Angeles College Project Priority List Occupancy Date
East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media
More informationBUILDING FOR OUR FUTURE
MIDDLE TOWNSHIP PUBLIC SCHOOLS BOND REFERENDUM March 8, 2016 Bond Referendum BUILDING FOR OUR FUTURE ADDRESSING THE DISTRICT S CRITICAL FACILITY AND SITE NEEDS CURRENTLY THE BAND-AID APPROACH COSTS MONEY
More informationCollege of the Desert Athletics Facilities
College of the Desert Athletics Facilities C13-005-PID-01 The LEED Gold project will include a new gymnasium, new tennis courts, renovation of an existing shower and locker building, and an upgrade of
More information