SIEMENS Year 3 Annual Energy Performance Report for Jackson County School District April 2010 May 2011
|
|
- Jasmin Goodman
- 6 years ago
- Views:
Transcription
1 SIEMENS Year 3 Annual Energy Performance Report for Jackson County School District April 2010 May 2011 Submitted by: Siemens Industry, Inc. Building Technologies Division 150 Teal St. Suite 100 St. Rose, LA May 31, 2011
2 Table of Contents 1.0 Executive Summary 1.1 Project Background 1.2 Summary of Predicted and Measured Energy and Cost Savings 2.0 Discussion of Installed ECRMs ECRM 1: Energy Management Control System ECRM 2: Lighting Systems Upgrade ECRM 3: Chiller Replacement/HVAC Improvements ECRM 4: Water Conservation ECRM 5: Vending Misers 3.0 Detailed Facility Improvement Measures 1.1 Vancleave Schools 1.2 St. Martin Schools 1.3 East Central Schools Appendix: Detailed Savings Calculation Worksheets
3 1.0 Executive Summary 1.1 Project Background Jackson County School District has partnered with Siemens Industry, Inc to perform an Energy Conservation project on its facilities. This report presents the energy cost savings resulting from projects installed by Siemens for the months of April 2010 through May The resulting savings are presented and compared to the contractual guaranteed savings by Siemens. The mechanical and control systems installed by Siemens are functioning properly and have resulted in savings to the Jackson County School District in the amount of $454,425 for this contract year. The Siemens annual guaranteed savings of $396,065 have been met and exceeded by $58,360. A summary of actual and proposed savings is presented on the following page for each Energy Cost Reduction Measure (ECRM) in tables 1a, 1b and 1c. Both the measured energy savings and the resulting cost savings are presented. Siemens will strive to maintain an excellent performance throughout the years ahead. We thank for their confidence in Siemens and look forward to another successful year of reducing operating costs and improving the environment in the district s school facilities. 2
4 1.2 Summary of Predicted and Measured Energy and Cost Savings Table 1a - Summary of Energy Cost Reduction Measures / Measured and Verified Savings for Year 3 ECRM No. ECRM Title Annual Savings Operational Electric Energy (kwh/yr) Demand (kw/yr) Natural Gas (ccf/yr) Water (kgal/yr) Cost ($/yr) Savings ($) (stipulated) Total Savings ($) 1 Lighting 1,757,674 5,264 $135,737 $22,728 $158,465 2 Water Conservation 4,119 3,627 $23,378 $3,183 $26,561 3 EMCS 874,656 5,379 $58,997 $2,652 $61,650 4 Vendmiser 117,788 $7,421 $0 $7,421 5 HVAC 82,671 $5,208 $79,568 $84,776 6 Mechanical TSP 1 $115,553 $115,553 TOTAL 2,832,788 5,264 9,498 3,627 $230,741 $223,684 $454,425 1 Savings based on cancellation of Mechanical TSP Table 1b - Predicted/Guaranteed Savings for Year 3 (From Siemens Contract) ECRM No. ECRM Title Annual Savings Electric Energy (kwh/yr) Demand (kw/yr) Natural Gas (ccf/yr) Water (kgal/yr) 1 Lighting 1,120,918 3,365 $85,598 $22,728 $108,325 2 Water Conservation 20,844 3,894 $20,363 $3,183 $23,545 3 EMCS 894,429 5,379 $54,351 $2,652 $57,004 4 Vendmiser 133,000 $6,718 $0 $6,718 5 HVAC 326,202 $20,119 $79,568 $99,687 6 Mechanical TSP $0 $100,786 $100,786 TOTAL 2,495,393 3,365 9,273 0 $187,149 $208,916 $396,065 Cost ($/yr) Operational Savings ($) Total Savings ($) Table 1c - Annual Contract Reconciliation Actual Measured Savings $454,425 Guaranteed Savings for Current Year $396,065 Excess Savings / (Shortfall) $58,360 3
5 2.0 Discussion of Installed ECRMs The following Energy Cost Reduction Measures (ECRMs) were implemented by Siemens: ECRM 1: Energy Management and Control Systems (EMCS) Upgrade ECRM 2: Lighting Systems Upgrade ECRM 3: Heating, Ventilation & Air Conditioning (HVAC) Upgrade ECRM 4: Water Conservation Upgrade ECRM 5: Vending Miser Installation ECRM 1: Energy Management and Control Systems Upgrade This measure involved the expansion of the existing Siemens Apogee Energy Management and Control System to control the time of day scheduling function and monitoring of the HVAC equipment. The following facilities were included: Vancleave Attendance Center St. Martin Attendance Center East Central Attendance Center ECRM 2: Lighting Systems Upgrade The lighting retrofit, consisted of a complete district wide interior energy efficiency lighting retrofit and or replacement of fixtures in all spaces including ofiices, classrooms, auditoriums, gyms and corridors. The following facilities were included: Vancleve Schools St. Martin Schools East Central Schools ECRM 3: Heating, Ventilation & Air Conditioning (HVAC) Upgrade This project consisted of replacing 123 Water Source Heat Pumps and repairing the piping loops for the WSHP systems at the three high schools. Also, preventive and corrective maintenance labor services at all school sites were performed. Those facilities included: Vancleave High School St. Martin High School East Central High School 4
6 ECRM 4: Water Conservation Upgrade This project consisted of retrofitting and replacing many toilets, restroom faucets, urinal flush valves and pedal valves on sinks as well as the installation of various water-conserving devices of specific equipment. The following facilities were included in the water scope project: St. Martin High School St. Martin North Elementary St. Martin East Elementary ECRM 5: Vending Miser Installation This measure involved the installation of 43 VendingMiser devices on soft drink machines located at various schools located throughout the school district. The devices reduce energy consumption on the soft drink vending machines during times of inactivity. 5
7 3.0 Detailed Facility Improvement Measures The following detailed FIMS were implemented by Siemens: JACKSON COUNTY SCHOOL DISTRICT VANCLEVE SCHOOLS Vancleve High School (approx. 91,000 sqft.) Lighting (approx. 839 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. In the newer areas of the building that currently utilize T-8 technologies relamp with lower wattage lamps. Building HVAC The buildings heating and cooling requirements are provided by a water source heat pump system including heat pumps, plate & frame heat exchanger, cooling tower, boiler, pumps, and associated piping. Most of the original water source heat pumps are still functioning, a new cooling tower has been installed and some of the PVC distribution piping has been replaced. 13 split D/X Heat Pump units serve the classrooms in the newer areas of the building. Four 20-ton rooftop package D/X cooling units with gas heat serve the Gym. 6
8 One new 20-ton package rooftop D/X cooling unit has been installed to serve the cafeteria. Approximately 11 split systems serve outer buildings including field houses. Replace the original water source heat pumps with high efficiency heat pumps since they are at the end of their expected useful life. This can be done now or in the next few years, but for efficiency and economy purposes, the energy and maintenance savings will justify replacing them sooner rather than later. The piping for the water-source heat pump systems was installed using PVC. High temperature water has been run through these pipes due to inoperative safety controls resulting in the failure of the piping in some instances causing flooding in the schools. Many lengths of the existing PVC piping are deformed from overheated water flowing through it and are subject to additional failures at any time. Replace the original PVC piping with a combination of steel and copper piping. This cost cannot be supported through energy or operational savings in this project, but it is recommended that the district consider budgeting for this in the near future to avoid failures of these piping systems. Currently the heat loop system is designed as a constant flow system. Water flows through each heat pump regardless of weather the individual units are in the heating mode, cooling mode or off. Installing a variable frequency drive, in conjunction with isolation valves on each heat pump, will allow the system to optimize water flow as building heating and cooling requirements change. This reduction in pump speed has a cubic relation with the energy required to operate the pump. Siemens will remove and replace the original loop pump and motor (40 HP) and install a VFD with associated monitoring devices. In addition Siemens will install isolation valves at each water source heat pump. Building Automation The existing building automation system (Singer) is no longer functional. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will replace the existing building automation system and non-programmable thermostats with a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. 7
9 Vending Machines (approx. 5 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 5 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating the vending machines are reduced and product integrity is maintained Vancleve Middle School (6 buildings, approx 60,000) Lighting (approx. 531 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. In the newer areas of the campus, like Tech Prep, that currently utilizes T-8 technologies relamp with lower wattage lamps. Building HVAC 46 split D/X cooling units serve the cooling needs of the campus. Heating is provided largely by gas furnaces with the exception of the cafeteria which uses a hydronic heating loop 8
10 Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Vending Machines (approx. 5 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 5 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating the vending machines are reduced and product integrity is maintained VANCLEVE UPPER ELEMENTARY SCHOOL (6 BUILDINGS, APPROX 78,000 SQFT) Lighting (approx. 837 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. 9
11 Building HVAC 42 window units, 7 split D/X cooling units, and 6 Package rooftop units serve the cooling needs of the campus. Heating is provided primarily gas unit heaters and furnaces as well as electric heat strips in a few areas. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Vending Machines (1 machine) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the vending machine that allows the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. Vancleve Lower Elementary (approx. 63,000 sqft.) 10
12 Lighting (approx. 760 fixtures) The school has new efficient lighting technologies including T-8 s and Compact Fluorescents. There are approximately 6 fixtures to retrofit at this school. Building HVAC 43 split D/X heat pump units provide the buildings heating and cooling requirements. The school is new and the equipment appears to be well maintained. Building Automation There is currently a Johnson Control building automation system installed at the school. However the seven system zones were in bypass, which prevents the system from performing its intended function. Recommission, if possible, or replace the existing automation system. Vending Machines (1 machine) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the vending machine that allows the product temperature to rise, within an expectable 11
13 range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. TECHNOLOGY CENTER Lighting (approx. 558 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the facility. Building HVAC 8 Package rooftop units and one split D/X system serve the cooling needs of the campus. The package roof top units and gas unit heaters provide heating. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. 12
14 Vending Machines (2 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the two vending machines that allows the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. ALTERNATIVE EDUCATION Lighting (approx. 60 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the building. 13
15 Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Jackson County School District Saint Martin Schools Saint Martin High School (grades 9-12) (approx 95,500 sqft) Lighting (approx fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. 14
16 Building HVAC The buildings heating and cooling requirements are provided by a water source heat pump system including heat pumps, plate & frame heat exchanger, cooling tower, boiler, pumps, and associated piping. Approximately 12 of the original heat pumps have been replaced, a new cooling tower has been installed and some of the PVC distribution piping has been replaced. 6 split D/X units with gas heat serve the newer area of the school. Replace the remaining water source heat pumps with high efficiency heat pumps since they are at the end of their expected useful life. This can be done now or in the next few years, but for efficiency and economy purposes, the energy and maintenance savings will justify replacing them sooner rather than later. The piping for the water-source heat pump systems was installed using PVC. High temperature water has been run through these pipes due to inoperative safety controls resulting in the failure of the piping in some instances causing flooding in the schools. Many lengths of the existing PVC piping are deformed from overheated water flowing through it and are subject to additional failures at any time. Replace the original PVC piping with a combination of steel and copper piping. This cost cannot be supported through energy or operational savings in this project, but it is recommended that the district consider budgeting for this in the near future to avoid failures of these piping systems. 15
17 Currently the heat loop system is designed as a constant flow system. Water flows through each heat pump regardless of weather the individual units are in the heating mode, cooling mode or off. Installing a variable frequency drive, in conjunction with isolation valves on each heat pump, will allow the system to optimize water flow as building heating and cooling requirements change. This reduction in pump speed has a cubic relation with the energy required to operate the pump. Siemens will remove and replace the original loop pump and motor (40 HP) and install a VFD with associated monitoring devices. In addition Siemens will install isolation valves at each water source heat pump. Replace the 6 split D/X cooling units with high efficiency units Building Automation The existing building automation system (Singer) is no longer functional. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will replace the existing building automation system and non-programmable thermostats with a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. 16
18 Water Conservation (approx. 163 fixtures effected between both buildings) Currently the schools located in the Saint Martin district utilize well water and are scheduled to place these schools on city water. Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. Vending Machines (approx. 9 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install nine Vendmiser controls on the vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. Saint Martin High School (grades 8-9) (approx. 75,000 sqft) 17
19 Lighting (approx. 804 fixtures) The school has new efficient lighting technologies including T-8 s and Compact Fluorescents. Retrofit or replace approximately 19 fixtures. Building HVAC 50 split D/X cooling units with hot water coils and a hydronic heating system provide the buildings heating and cooling requirements. The system is approx 5 years old and is in good condition. Building Automation The existing CSI automation system has thirteen zones of which two zones were in override. Recommission or replace the existing automation system. Add hot water reset control to the hydronicheating loop. Water Conservation Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. Vending Machines (approx. 11 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 11 vending machines that allow the product temperature to rise, within an 18
20 expectable range, during non-school hours. Energy costs associated with operating the vending machines are reduced and product integrity is maintained. Saint Martin Middle School (approx 77,000 sqft, 8 buildings) Lighting (approx. 857 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. Building HVAC 28 split D/X cooling units, 27 window units serve the cooling needs of the campus. Heating is provided by a combination of gas unit heaters and gas furnaces. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a 19
21 new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Water Conservation (approx. 96 fixtures effected) Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. Vending Machines (approx. 8 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 8 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. SAINT MARTIN UPPER ELEMENTARY SCHOOL (APPROX 45,000 SQFT) Lighting (approx. 482 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. 20
22 Building HVAC 17 split D/X cooling units, 29 window units and one roof top package unit serves the cooling needs of the campus. Heating is provided by a combination of gas unit heaters and gas furnaces. Replace the older cooling and heating systems with higher efficiency units. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Water Conservation (approx. 89 fixtures effected) Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. Vending Machines (approx. 5 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 5 vending machines that allow the product temperature to rise, within an 21
23 expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. Saint Martin East Elementary School (approx 46,000 sqft) Lighting (approx. 627 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. Building HVAC 7 split D/X cooling units, 45 window units, and r package unit serves the cooling needs of the campus. Heating is provided by a combination of gas unit heaters and gas furnaces. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Water Conservation (approx. 80 fixtures effected) Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. 22
24 Vending Machines (approx. 2 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 2 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. Saint Martin North Elementary School ( approx 48,000 sqft) Lighting (approx. 615 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. 23
25 Building HVAC Six split D/X cooling units (3 with multiple evaporators) and 30 window units serve the cooling needs of the campus. Heating is provided by a combination of gas unit heaters and gas furnaces. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Water Conservation (approx. 96 fixtures effected) Siemens proposes to install water conserving plumbing fixtures (water closets, urinals, sinks, dishwasher) or in some cases retrofit the existing fixtures to minimize water consumption, where appropriate, throughout the high school. These retrofits will reduce future costs associated with water and sewer charges as well as the energy required to heat water where applicable. Vending Machines (approx. 3 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 2 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. 24
26 Jackson County School District East Central Schools East Central High School (approx 110,000 sqft) Lighting (approx fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. Building HVAC The buildings primary heating and cooling requirements are provided by a water source heat pump system including heat pumps, plate & frame heat exchanger, cooling tower, boiler, pumps, and associated piping. Approximately 12 of the original heat pumps have been replaced with split D/X cooling only units. A new Evapco cooling tower has been installed. Twenty-one split D/X heat pump units serve the classrooms in the newer areas of the building. Four 20-ton rooftop package D/X cooling units with gas heat serve the Gym. Approximately 6 split systems and 8 window units provide cooling to areas such as field houses and press boxes. Replace the remaining water source heat pumps with high efficiency heat pumps since they are at the end of their expected useful life. This can be done now or in the next few years, but for efficiency and economy purposes, the energy and maintenance savings will justify replacing them sooner rather than later. The piping for the water-source heat pump systems was installed using PVC. High temperature water has been run through these pipes due to inoperative safety controls resulting in the failure of the piping in some instances causing flooding in the schools. Many lengths of the existing PVC piping are deformed from overheated water flowing through it and are subject to additional failures at any time. Replace the original PVC piping with a combination of steel and copper piping. This cost cannot be 25
27 supported through energy or operational savings in this project, but it is recommended that the district consider budgeting for this in the near future to avoid failures of these piping systems. Currently the heat loop system is designed as a constant flow system. Water flows through each heat pump regardless of weather the individual units are in the heating mode, cooling mode or off. Installing a variable frequency drive, in conjunction with isolation valves on each heat pump, will allow the system to optimize water flow as building heating and cooling requirements change. This reduction in pump speed has a cubic relation with the energy required to operate the pump. Building Automation The existing building automation system (Singer) is no longer functional. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will replace the existing building automation system and non-programmable thermostats with a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Vending Machines (approx. 4 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install Vendmiser controls on the 4 vending machines that allow the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating the vending machines are reduced and product integrity is maintained 26
28 East Central Middle School (10 buildings, approx. 87,000 sqft) Lighting (approx. 762 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. Building HVAC 39 window units and 25 split D/X cooling units serve the cooling needs of the campus. Primarily gas unit heaters and furnaces provide heating with the exception of D/X heat pumps and electric heat strips that are utilized in some areas. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. 27
29 Vending Machines (approx. 1 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the vending machine that allows the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. Kitchen Hood. Kitchen hood systems, that do not include a designated make up air (MUA) system, are notorious for not only wasting energy but also creating an uncomfortable work environment for employees. When there is no designated MUA system conditioned air form the kitchen and surrounding spaces (typically the cafeteria) is exhausted out of the building via the kitchen hood. Siemens proposes to replace the existing kitchen hood with an integrated MUA system. Costs associated with conditioning the kitchen and cafeteria will be reduced. EAST CENTRAL UPPER ELEMENTARY SCHOOL (9 BUILDINGS, APPROX. 52,000 SQFT) Lighting (approx. 547 fixtures) Retrofit or upgrade existing lighting fixtures to new technologies to both reduce energy and maintenance costs as well improve lighting levels throughout the campus. 28
30 Building HVAC 38 window units, 12 split D/X cooling units, and 6 Package rooftop units serve the cooling needs of the campus. Primarily gas unit heaters and furnaces provide heating. Building Automation Currently there is no building automation system in this school. Room thermostats control space temperatures, however, monitoring or controlling building conditions during unoccupied periods is not currently possible. This is causing the HVAC equipment to run unnecessarily and the costs, including maintenance and utilities, associated with operating this equipment to be excessive. Siemens will install a new BAS system that will monitor space temperatures and provide start/stop, setback, and scheduling functions for associated HVAC equipment. Vending Machines (1 machine) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the vending machine that allows the product temperature to rise, within an expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. 29
31 EAST CENTRAL LOWER ELEMENTARY (APPROX. 61,000 SQFT) Lighting (approx. 782 fixtures) The school has new efficient lighting technologies including T-8 s and Compact Fluorescents. There are approximately 40 fixtures to be retrofitted or replaced. Building HVAC 41 split D/X heat pump units provide the buildings heating and cooling requirements. The school is new and the equipment appears to be well maintained. Building Automation There is currently a CSI building automation system installed at the school. However the system was in bypass, which prevents the system from performing its intended function. According to school personal this system has not been functional since it s installation. Recommission, if possible, or replace the existing automation system. Vending Machines (approx. 2 machines) Vending machines are designed to maintain a constant product temperature regardless of the building occupancy schedule. There is a cost associated with maintaining this temperature. Siemens will install a Vendmiser control on the two vending machines that allows the product temperature to rise, within an 30
32 expectable range, during non-school hours. Energy costs associated with operating this vending machine is reduced and product integrity is maintained. APPENDIX A Detailed Savings Calculation Worksheets 31
33 , Year 3 Annual Savings Report Jackson County, Mississippi Table 1a - Summary of Energy Cost Reduction Measures / Measured and Verified Savings for Year 3 ECRM No. ECRM Title Annual Savings Operational Electric Energy (kwh/yr) Demand (kw/yr) Natural Gas (ccf/yr) Water (kgal/yr) Cost ($/yr) Savings ($) (stipulated) Total Savings ($) 1 Lighting 1,757,674 5,264 $135,737 $22,728 $158,465 2 Water Conservation 4,119 3,627 $23,378 $3,183 $26,561 3 EMCS 874,656 5,379 $58,997 $2,652 $61,650 4 Vendmiser 117,788 $7,421 $0 $7,421 5 HVAC 82,671 $5,208 $79,568 $84,776 6 Mechanical TSP 1 $115,553 $115,553 TOTAL 2,832,788 5,264 9,498 3,627 $230,741 $223,684 $454,425 1 Savings based on cancellation of Mechanical TSP Table 1b - Predicted/Guaranteed Savings for Year 3 (From Siemens Contract) ECRM No. ECRM Title Annual Savings Electric Energy (kwh/yr) Demand (kw/yr) Natural Gas (ccf/yr) Water (kgal/yr) Cost ($/yr) Operational Savings ($) Total Savings ($) 1 Lighting 1,120,918 3,365 $85,598 $22,728 $108,325 2 Water Conservation 20,844 3,894 $20,363 $3,183 $23,545 3 EMCS 894,429 5,379 $54,351 $2,652 $57,004 4 Vendmiser 133,000 $6,718 $0 $6,718 5 HVAC 326,202 $20,119 $79,568 $99,687 6 Mechanical TSP $0 $100,786 $100,786 TOTAL 2,495,393 3,365 9,273 0 $187,149 $208,916 $396,065 Table 1c - Annual Contract Reconciliation Actual Measured Savings $454,425 Guaranteed Savings for Current Year $396,065 Excess Savings / (Shortfall) $58,360 Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 1 Submitted May 31, 2011
34 , Year 3 Annual Savings Report Jackson County, Mississippi Table 2 - Total Project Savings Summary Year Measured Savings Guaranteed Savings Excess Savings / (Shortfall) Total Accumulated Project Measured Savings Total Accumulated Project Guaranteed Savings Total Accumulated Project Excess Savings / (Shortfall) Construction Period $0 $0 $0 $0 $0 $0 1 $441,584 $376,805 $64,779 $441,584 $376,805 $64,779 2 $447,910 $386,310 $61,600 $889,494 $763,115 $126,379 3 $454,425 $396,065 $58,360 $1,343,919 $1,159,180 $184, Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 2 Submitted May 31, 2011
35 , Year 3 Annual Savings Report Jackson County, Mississippi Table 3 - Base Year Energy Consumption Data (January December 2004) Electrical Natural Gas Month Consumption (kwh) Demand Demand Total Cost ($) Consumption Cost ($) Metered Charged (ccf) (kw) (kw) Propane Total Consumption Cost ($) Total Cost ($) (gals) January 585,904 2,996 2,996 $53,563 10,048 $10,068 8,900 $10,184 $73,815 February 664,648 3,104 3,104 $57,950 9,424 $8,932 6,056 $6,420 $73,302 March 654,145 2,901 2,901 $56,192 7,779 $7,255 5,240 $5,607 $69,054 April 663,849 2,828 2,828 $51,815 4,533 $3,972 $55,787 May 678,858 2,941 2,941 $53,018 3,219 $3,074 5,800 $6,274 $62,366 June 778,146 2,644 2,644 $57,256 1,436 $1,321 $58,577 July 814,762 2,469 2,469 $58,267 1,315 $1,243 $59,510 August 994,253 3,394 3,394 $94,320 3,075 $2,842 6,863 $7,412 $104,574 Setember 1,184,065 3,958 3,958 $90,045 3,547 $3,266 $93,311 October 1,001,951 3,680 3,680 $77,926 4,445 $4,133 3,400 $3,672 $85,731 November 903,246 3,472 3,472 $70,914 4,338 $4,441 1,919 $2,072 $77,427 December 662,436 3,177 3,177 $55,492 10,776 $11,071 2,490 $2,689 $69,252 Total 9,586,263 37,564 37,564 $ 776,758 63,935 $ 61,618 40,668 $ 44,330 $882,706 (1) Billing history month is based on utility statement date, not billing period. Company Name: Company Rate Schedule: Electricity Singing River GS Natual Gas/Propane Water /Sewer Centerpoint Energy W. Jackson County Utililty Dist. Commercial Commercial Blossman & Niel Commercial Table 4 - Baseline Year Average Utility Rates (Used to calculate dollar savings) Electric ($/kwh) Electric ($/kw) Water ($/kgal) Sewer ($/kgal) $ $4.75 $ $ Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 3 Submitted May 31, 2011
36 , Year 3 Annual Savings Report Jackson County, Mississippi Table 5 - Siemens Guaranteed Savings (from Exhibit C of Contract) Year Energy/Utility Savings Operational Savings Total Savings Year 1 $179,882 $196,923 $376,805 Year 2 $183,480 $202,831 $386,310 Year 3 $187,149 $208,916 $396,065 Year 4 $190,892 $215,183 $406,075 Year 5 $194,710 $221,639 $416,349 Year 6 $198,604 $228,288 $426,892 Year 7 $202,576 $235,136 $437,713 Year 8 $206,628 $242,190 $448,818 Year 9 $210,760 $249,456 $460,217 Year 10 $214,976 $256,940 $471,915 Year 11 $219,275 $264,648 $483,923 Year 12 $223,661 $272,587 $496,248 Year 13 $228,134 $280,765 $508,899 Year 14 $232,697 $289,188 $521,885 Year 15 $237,350 $297,864 $535,214 Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 4 Submitted May 31, 2011
37 , Year 3 Annual Savings Report Jackson County, Mississippi Weather Conditions Weather data for the Jackson County area is from the National Weather Service, PQL Airport. The outdoor air temperature is used to calculate Pre-Retrofit consumption for the buildings receiving retrofits. A summary of collected temperature data is listed below. Month Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Degree Days (65F) Heating Degree Days (65F) Avg Temperature (F) Avg Daily Max Temp (F) Avg Daily Min Temp (F) Maximum Temperature (F) Minimum Temperature (F) Average Daily Temperatures (F) Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 5 Submitted May 31, 2011
38 , Year 3 Annual Savings Report Jackson County, Mississippi SOUTHERN ENERGY TECHNOLOGIES, INC. Lighting Systems Analysis Report Jackson County School District Lighting Upgrade Ver 1.4 Existing Lighting System Proposed Lighting System Annual Savings Existing Fixture Qty AOH Watts kw kwh/yr Watts kw kwh/yr kwh/yr kwhac kwh/ac ECM Qty AOH kwhac TotalkWh kw TotalkWh 2X4 2 LAMP T12 1, , , , , , ,140 TROFFER , , ,134 2LX 2X4 2 LAMP T , , , , , ,862 1,167 6,029 TROFFER , ,653 1,117 5,770 2LX 2X4 2 LAMP T , , , ,592 4,577 36, ,912 7,418 38,330 TROFFER , ,592 7,102 36,694 2LX 2X4 2 LAMP WRAP , , , , ,331 2LX , ,232 2X4 3 LAMP T , , , ,076 2,464 6, ,304 1,272 6,576 TROFFER , ,076 1,218 6,294 2LX 2X4 4 LAMP T LOUVERED LX 2X4 4 LAMP T , , , ,506 15, , ,400 20, ,884 TROFFER , ,224 2,454 12,678 2HSS 4LX , ,546 15,251 78,797 4SX , ,736 3,297 17,033 2X4 4 LAMP T , , , ,096 15, , ,300 19,264 99,564 TROFFER , ,454 2,509 12,963 2HSS 4LX , ,642 17,434 90,076 2X4 4 LAMP T12 2, , ,896 2, , ,319 82, , , , ,930 TROFFER 2HSS , ,781 9,787 50,568 2LX , ,607 2SX , , ,762 4LX , ,867 84, ,555 4LX , ,535 8,048 41,584 2X4 4 LAMP T , , , , , , ,839 WRAP , , ,077 4LX 2X4 4 LAMP T WRAP LX 2X4 4 LAMP T , , , ,680 1,930 13, ,200 2,448 12,648 WRAP , ,680 2,563 13,243 4LX 2X4 4 LAMP T , , , , , ,590 1,101 5,691 WRAP , ,806 1,153 5,959 4LX 1X4 1 LAMP STRIP , , , ,776 1LX LX X4 2 LAMP T , , , ,035 5,106 28, ,480 4,437 22,917 INDUSTRIAL LX 4LTX , ,387 5,373 27,760 1X4 2 LAMP T INDUSTRIAL LX 1X4 2 LAMP T , , , ,120 1, , ,400 35, ,545 LOUVERED 2LX , ,830 1,879 9,709 2SX LTX , ,160 1,478 7,638 F20HS , ,450 5,148 26,598 F20SS , ,600 23, ,504 F20XLS , ,207 1X4 2 LAMP T , , , ,039-19,929 29, ,180 29,078 55,258 Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 6 Submitted May 31, 2011
39 , Year 3 Annual Savings Report Jackson County, Mississippi SOUTHERN ENERGY TECHNOLOGIES, INC. Lighting Systems Analysis Report LOUVERED 2LX LTX , ,970 1,673 8,642 F20HS , ,674 4,002 20,676 1X4 2 LAMP T , , , , ,740 1,359 3,099 STRIP , , ,790 2LX 1X4 2 LAMP T , , , , ,234 2,512 5,746 STRIP , , ,156 2LX 1X4 2 LAMP T , , , , ,528 2,740 6,268 STRIP , ,536 1,089 5,625 2LX 1X4 2 LAMP T , , ,492 STRIP , ,339 2LX 1X4 2 LAMP T , , , , ,146 2,452 5,598 TROFFER , , ,033 2LX 1X4 2 LAMP T TROFFER LX 1X4 2 LAMP T VAPOR TIGHT LX 1X4 2 LAMP T , , , ,694 1,316 3,010 VAPOR TIGHT , ,701 2LX 1X4 2 LAMP T , , , ,920-5,152 32, ,136 15,658 35,794 VAPOR TIGHT , ,920 6,221 32,141 2LX 1X4 2 LAMP T , , , ,168-24,103 59, ,400 38,257 80,657 WRAP , , ,500 2HSS 2LX , ,640 6,394 33,034 2SX , ,400 1,296 6,696 4LTX , , ,619 F7S , ,000 2,880 14,880 1X4 2 LAMP T , , , ,465-6,254 15, ,660 11,150 22,810 WRAP , , ,174 2LX 4STWSS , ,099 2,184 11,283 1X4 2 LAMP T , , , ,384-4,250 26, ,632 12,918 29,550 WRAP , ,384 5,132 26,516 2LX 1X4 2 LAMP T WRAP LX 1X4 2 LAMP WALL BRACKET LX 1X3 2 LAMP T WALL BRACKET LX 2X2 2 LAMP U ,528 TROFFER LX 2X2 2 LAMP U , ,681 TROFFER ,048 6LX 2X2 2 LAMP U , , , , ,336 3,341 6,677 TROFFER , , ,143 6LX 1X2 2 LAMP WRAPAROUND LX 1X8 2 LAMP T , , , , ,700 3,980 7,680 Siemens Industry, Inc. - Building Technologies Division Energy and Environmental Solutions Page 7 Submitted May 31, 2011
Low Cost Building Automation System for Small- and Medium- Sized Commercial Buildings
Low Cost Building Automation System for Small- and Medium- Sized Commercial Buildings Srinivas Katipamula, Ph.D. Staff Scientist, Pacific Northwest National Laboratory Other TAG Members: Irfan Rehmanji
More informationENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company.
Report To: Mr. John Smith Smith Printing Company ENERGY AUDIT 123 Main Street Mississauga, Ontario January 1, 2009 120 Carlton Street, Suite 212 Toronto, Ontario M5A 4K2 Tel 416-964-3246 Toll Free 1-866-964-3246
More informationVOORHEES TOWNSHIP BOARD OF EDUCATION OSAGE ELEMENTARY SCHOOL 128 E CHEWS LANDING RD, VOORHEES, NJ, FACILITY ENERGY REPORT
VOORHEES TOWNSHIP BOARD OF EDUCATION OSAGE ELEMENTARY SCHOOL 128 E CHEWS LANDING RD, VOORHEES, NJ, 08043 FACILITY ENERGY REPORT Voorhees Township Public Schools Osage Elementary School TABLE OF CONTENTS
More informationEnergy Savings. Performance contracting installs energy. costs, paid for out of guaranteed energy savings from your existing operating budget.
Energy Savings Performance Contracting Performance contracting installs energy efficient i facility improvements, with no up front costs, paid for out of guaranteed energy savings from your existing operating
More informationLow-Hanging Fruit Simple Steps Toward Energy Effective Building Operations
Low-Hanging Fruit Simple Steps Toward Energy Effective Building Operations Roger Ebbage Northwest Water / Energy Education Institute Lane Community College May 7-9 Enzian Inn - Leavenworth, Washington
More informationCondenser Water Heat Recovery"
PLEASE MUTE CELL PHONES Condenser Water Heat Recovery" Julian de Bullet ASHRAE Distinguished Lecturer Director of Industry Relations McQuay International 703-395-5054 1 What Is Sustainability? sustainable
More informationBaffled Openings at Chain Link Fencing: Design shall consist of two end-posts set 4 feet apart, and a 10 foot wide chain-link fence panel equal in height as the adjacent fence. Chain link fence panel shall
More informationHamilton Board of Education Robinson Elementary School Hamilton, NJ 08610
Steven Winter Associates, Inc. 50 Washington Street Telephone (203) 857-0200 Architects and Engineers Norwalk, CT 06854 Facsimile (203) 852-0741 www.swinter.com E-mail: swinter@swinter.com July 17, 2009
More informationEstablishing a Baseline, Energy Audits and Energy Star s Portfolio Manager
Establishing a Baseline, Energy Audits and Energy Star s Portfolio Manager Glenn Barnes Environmental Finance Center University of North Carolina at Chapel Hill 919-962-2789 glennbarnes@sog.unc.edu Energy
More informationFACILITIES MANAGEMENT Energy Conservation Projects Summary Updated 05/22/2016
FACILITIES MANAGEMENT Energy Conservation Projects Summary Updated 05/22/2016 Utility Operations Completed in FY16 Buchtel Parking Garage LED Lighting Upgrades - Project scope includes the upgrade of (139)
More informationAdvantages of Financing Continuous Commissioning As An Energy Conservation Retrofit Measure
Advantages of Financing Continuous Commissioning As An Energy Conservation Retrofit Measure Guanghua Wei, P.E. Malcolm Verdict, C.E.M Joseph T. Martinez Energy Systems Laboratory, 3581 TAMU Texas A&M University
More informationEnergy Reduction Strategy Through 2020
Through 2020 Revised: August 2017 Executive Summary Auburn University is a land, sea and space grant university established in 1856. The university consists of 11,629,000 square feet on 1,840 acres and
More informationENGLEWOOD CLIFFS PUBLIC SCHOOLS NORTH CLIFF ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO.
ENGLEWOOD CLIFFS PUBLIC SCHOOLS NORTH CLIFF ELEMENTARY SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24385 November 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054
More informationExisting Building Upgrades
Existing Building Upgrades Greg Swiss - Building Energy Specialist Smart Energy Design Assistance Center (SEDAC), University of Illinois at Urbana Champaign Providing effective strategies for public and
More informationELIAS BOUDINOT ELEMENTARY SCHOOL Pearl and Ellis Street, Burlington NJ 08016
BURLINGTON CITY PUBLIC SCHOOLS ELIAS BOUDINOT ELEMENTARY SCHOOL Pearl and Ellis Street, Burlington NJ 08016 LOCAL GOVERNMENT ENERGY AUDIT PROGRAM FOR NEW JERSEY BOARD OF PUBLIC UTILITIES September 2014
More informationEnergy Audit Checklist
UNIVERSITY OF COLORADO Energy Audit Checklist Building Date Proctor name Phone # Responsible for what part of the Building Email: 1. Please complete this audit checklist yourself to the best of your abilities.
More informationYWCA 1503 S. Denver Tulsa, Oklahoma 5/18/2010 Performed By
Energy Audit for YWCA 1503 S. Denver Tulsa, Oklahoma 5/18/2010 Performed By 220 E. 8th Street Tulsa, Oklahoma 74119 918-582.0229 Fax: 918.599.0665 www.craftontullsparks.com Table of Contents Cover Page...
More informationOptimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning
Optimizing Energy Use in a HealthCare Setting Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning AIA Quality Assurance The Building Commissioning Association is a Registered
More informationMarysville School District Resource Conservation Program. John Bingham Marysville S.D. Ray Burton Snohomish Co. P.U.D.
Marysville School District Resource Conservation Program John Bingham Marysville S.D. Ray Burton Snohomish Co. P.U.D. Tools Resource Conservation Program Utility budget Utility tracking Benchmarking Load
More informationCity of La Palma Agenda Item No. 10
City of La Palma Agenda Item No. 10 MEETING DATE: June 3, 2014 TO: FROM: SUBMITTED BY: CITY COUNCIL CITY MANAGER Mike Belknap, Community Services Director AGENDA TITLE: Energy Service Contract with Climatec
More informationRecommissioning Energy Savings Persistence
Recommissioning Energy Savings Persistence Martin Selch and James Bradford, PE, PhD Nexant, Inc. Synopsis Utilities, administrators, or turnkey providers in many areas around the country offer recommissioning
More informationElectricity Survey and Analysis
Electricity Survey and Analysis Prepared for: Centre in the Square Inc. 101 Queen St. North Kitchener, ON N2H 6P7 Prepared by: Stantec Consulting Ltd. 49 Frederick St. Kitchener, ON N2H 6M7 September 14,
More informationRhode Island Commercial Codes FAQs
Rhode Island Commercial Codes FAQs When does the new code go into effect? The new suite of building codes (including the new state energy conservation code, SBC-8) was adopted on July 1, 2013. A brief
More informationENERGY AND WATER CONSERVATION AND DEMAND MANAGEMENT PLAN
ENERGY AND WATER CONSERVATION AND DEMAND MANAGEMENT PLAN 2014 2019 CONTENTS EXECUTIVE SUMMARY... 3 1. CENTENNIAL COLLEGE - DISTRIBUTION OF ENERGY CONSUMPTION IN 2012... 4 1.1. Overview of Centennial College
More informationIntegrated Energy Audit:
Integrated Energy Audit: College of the Redwoods Prepared for: Pacific Gas and Electric Company Prepared by: KEMA Quality Assurance Check by: Charles Middleton (signature line) Copyright 2010 Pacific Gas
More informationNo Cost/Low Cost Energy
No Cost/Low Cost Energy Saving Strategies Randall D. Manteufel University of Texas at San Antonio Energy Efficiency in Local Government andschool Districts in the Border Region No Cost/Low Cost Relatively
More informationResource Conservation Management Program
Resource Conservation Management Program Procedure 6811 Introduction The focus of the Resource Conservation Management Program is long-term, sustainable measures, practices and procedures that reduce consumption
More informationIndiana University Glick Eye Institute. LEED Measurement & Verification Plan
Indiana University Glick Eye Institute LEED Measurement & Verification Plan April 10, 2012 1 Table of Contents General Introduction... 3 Facility Description... 4 M&V Objectives... 4 M&V Approach/Option...
More informationTexas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES
This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission
More informationPowering Michigan Agriculture with Renewable Energy
Powering Michigan Agriculture with Renewable Energy ENERGY AUDIT & RENEWABLE ENERGY ASSESSMENT ENERGY PYRAMID MICHIGAN STATE UNIVERSITY MI Agricultural Energy Use Significant MI Dairy Farms Energy Use
More informationK-12 Proposition 39 Update. Jillian Rich March 23, 2015
K-12 Proposition 39 Update Jillian Rich March 23, 2015 Agenda Time Category 1 PM Welcome and Introductions (All) 1:05 PM State of Prop 39 Implementation (Jillian) 1:10 PM New Prop 39 Guidelines: What s
More informationExample LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal
Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal
More informationEnergy Efficiency in Multi-Tenant Office Buildings
Energy Efficiency in Multi-Tenant Office Buildings Presented by David Herman, PE, LEED AP Principal, EnerG Associates, LLC 3/10/2015 1 Learning Objectives 1. List the principal sources and uses of energy
More informationGreen Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING
Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING WWW.STOPWASTE.ORG New Addition Consider the following green remodeling options in a new addition.
More informationCounty of Mercer McDade Administration Building 640 South Broad Street Trenton, NJ 08611
Steven Winter Associates, Inc. 293 Route 18, Suite 330 Telephone (866) 676-1972 Building Systems Consultants East Brunswick, NJ 08816 Facsimile (203) 852-0741 www.swinter.com October 1, 2010 Local Government
More informationSouth Carolina Society for Hospital Engineers
South Carolina Society for Hospital Engineers Selecting Energy Partners: Criteria & Pitfalls and the Top 10 Ways to Reduce Energy in a Hospital Presented by Jon Dierking, PE, CEM, LEED AP Director of Energy
More informationDuke Energy Corporation
Commercial Audit for Account: 12345-56789 Thank you for completing the Duke Energy Corporation Business Energy Check. We hope the information and recommendations provided will assist you in managing your
More informationHotels: Water and Energy
Hotels: Water and Energy Agenda 01 Introduction 05 Hotel System Options 02 Company Overview 06 Hotel Energy Conservation 03 Hotel Energy & Water Use 07 Hotel Project Examples 04 Design Philosophy Introduction
More informationEnergy Efficiency Solutions for Multifamily Housing. Clark Energy Group LLC
Energy Efficiency Solutions for Multifamily Housing Clark Energy Group LLC 1 Agenda About Clark Energy Group Energy Service Company (ESCO) Overview ESCO Services Utility Rate Forecasts Making the Decision
More informationKlatt Elementary School
Klatt Elementary School 1190 Juniper Drive Anchorage, Alaska 99517 AkWarm-C ID No. CIRI-ANC-CAEC-28 Submitted by: Central Alaska Engineering Company Contact: Jerry P. Herring, P.E., C.E.A. 32215 Lakefront
More informationCity of Fort Collins Building Automation Systems Enhances Savings and Commissioning Efficiency Works Training
City of Fort Collins Building Automation Systems Enhances Savings and Commissioning Efficiency Works Training November 18, 2015 Agenda Commissioning Monitoring Based Commissioning Building Tune up Case
More informationWARWICK TOWNSHIP Dept. of Planning & Zoning
For Warwick Township Use Only WARWICK TOWNSHIP Dept. of Planning & Zoning 1733 Township Greene, Jamison, PA 18929 : (215) 343-6100 www.warwick-bucks.org Check #: Check Amount: Received by: BUILDING PERMIT
More informationComprehensive Energy Audit For. Quinhagak Utility Building
Comprehensive Energy Audit For Quinhagak Utility Building Prepared For City of Quinhagak May 11, 2016 Prepared By: ANTHC-DEHE 4500 Diplomacy Dr., Anchorage, AK 99508 1 Table of Contents PREFACE... 3 ACKNOWLEDGMENTS...
More informationFebruary 9, 2016 VIA ELECTRONIC FILING AND HAND DELIVERY
1407 W. North Temple, Suite 330 Salt Lake City, Utah 84116 February 9, 2016 VIA ELECTRONIC FILING AND HAND DELIVERY Public Service Commission of Utah Heber M. Wells Building, 4 th Floor 160 East 300 South
More informationENERGY AUDIT REPORT. (Photo From Google Maps) City of Kenai Airport 305 North Willow Kenai, Alaska CAEC Project No. CIRI-ENA-CAEC-04 May 2012
ENERGY AUDIT REPORT (Photo From Google Maps) City of Kenai Airport 305 North Willow Kenai, Alaska 99611 CAEC Project No. CIRI-ENA-CAEC-04 May 2012 SUBMITTED BY: PRIMARY CONTACT: 220 SE 51 st Street 32266
More informationCase Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency
Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency Summary Major Fortune 500 Telecom Company Estimated 40% the corporate building portfolio still use pneumatic thermostats
More informationENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134
, NJ ENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134 SOUTH BRUNSWICK BOARD OF EDUCATION PO BOX 181 MONMOUTH JUNCTION, NJ 08852 ATTN: MR. ANTHONY TONZINI BUSINESS ADMINSTRATOR CONCORD ENGINEERING GROUP
More informationGETTING TO EFFICIENT BUILDINGS
GETTING TO EFFICIENT BUILDINGS Andy Robinson, SEDAC SEDAC + EPA Moraine Valley Community College Dec 2016 SEDAC GOALS FOR OUR CLIENTS: Save energy dollars Identify efficient equipment upgrades Identify
More informationDTE Energy Commercial & Industrial Energy Optimization Program. Trade Ally Meeting. Guardian Plumbing & Heating January 20, 2011
DTE Energy Commercial & Industrial Energy Optimization Program Trade Ally Meeting Guardian Plumbing & Heating January 20, 2011 Agenda Introduction DTE Energy Your Energy Savings Program Overview 2011 Program
More informationLivingston Harrison Elementary School Livingston, NJ 07039
Steven Winter Associates, Inc. 293 Route 18 South, Suite 330 Telephone: (866) 676-1972 Architects and Engineers East Brunswick, NJ 08816 E-mail: swinter@swinter.com www.swinter.com February 7, 2010 Local
More informationPUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor TO: All Parties in R.13-11-005 FROM: Robert Hansen, Utilities Engineer DATE:
More informationINVESTMENT GRADE AUDIT ARRA Funded Project
INVESTMENT GRADE AUDIT Presented By: 60 E. Rio Salado Parkway Suite 1001 Tempe, AZ 85281 602.744.5000 Table of Contents 1.0 Executive Summary...1 1.1. Key Milestones... 1 2.0 Investment Grade Audit Overview...2
More informationReducing Costs with Energy Efficiency
Reducing Costs with Energy Efficiency Presented to Pennsylvania Demand Side Response Working Group February 9, 2007 2/9/2007 1 Austin Energy Municipally-owned 700,000 population Area > 400 sq. miles Generation
More informationItalcementi Center for Research and Innovation
Italcementi Center for Research and Innovation Bergamo, Italy LEED-NC v2.1 EAc1 A. Project Narrative (Viridian) analyzed the energy use of the proposed Italcementi Center for Research and Innovation located
More informationComprehensive Energy Audit For Kongiganak Health Clinic
Comprehensive Energy Audit For Kongiganak Health Clinic Prepared For Native Village of Kongiganak September 15, 2011 Prepared By: ANTHC DEHE Energy Projects Group Anchorage, Alaska 99508 1 Table of Contents
More informationUnion College Combined Cooling, Heat and Power Project
Union College Combined Cooling, Heat and Power Project Presented by: Mark Donovan, PE Union College, Assistant Director of Utilities Aaron Bolhous, PEng CHA, Project Engineer Agenda Introduction to Union
More informationCheldelin Middle School
Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:
More informationRetrocommissioning (RCx)
Retrocommissioning (RCx) Facilities & Services - Engineering Services Saving the planet, two buildings at a time. Mr. Karl Helmink Mr. Damon McFall Creating a Sustainable Campus What is Retrocommissioning
More informationSchool Without Walls
INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationRecreation Centers of Sun City West R.H. Johnson Campus
R.H. Johnson Campus SUN CITY WEST, AZ Renewable Energy System Feasibility Study Final Report February 21, 2014 4742 N. 24 th Street Suite 100 Phoenix, AZ 85016 (602) 429.5800 AEI Project No. 13180-00 Table
More informationFor. Prepared For ANTHC DEHE
Comprehensive Energy Audit For Tuluksakk Health Clinic Prepared For Tuluksak Native Community February 7, 20122 Prepared By: ANTHC DEHE 1901 Bragaw, Suite 200 Anchorage, AK 99508 1 Table of Contents 1.
More informationWillard Bowman Elementary School
Willard Bowman Elementary School 11700 Gregory Rd Anchorage, Alaska 99517 AkWarm ID No. CIRI-ANC-CAEC-26 Submitted by: Central Alaska Engineering Company Contact: Jerry P. Herring, P.E., C.E.A. 32215 Lakefront
More informationCONCORD ENGINEERING GROUP 520 SOUTH BURNT MILL ROAD VOORHEES, NJ TELEPHONE: (856) FACSIMILE: (856)
ENERGY AUDIT FINAL REPORT JANUARY 6, 2010 UNION COUNTY COLLEGE ELIZABETH CAMPUS LESSNER BUILDING 12 W. JERSEY STREET ELIZABETH, NJ 07201 ATTN: MR. HENRY KEY, DIRECTOR OF FACILITIES CEG PROJECT NO. CONCORD
More informationBryant University s Energy Guidelines for Sustainability
Bryant University s Energy Guidelines for Sustainability Rising carbon emissions have a disruptive impact on global climate patterns and pose a risk to the security of communities around the world. The
More informationENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134
, NJ ENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134 SOUTH BRUNSWICK BOARD OF EDUCATION PO BOX 181 MONMOUTH JUNCTION, NJ 08852 ATTN: MR. ANTHONY TONZINI BUSINESS ADMINISTRATOR CONCORD ENGINEERING GROUP
More informationLOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT
LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT PREPARED FOR: MT. OLIVE TWP. SCHOOL DISTRICT CHESTER M. STEPHENS ELEMENTARY SCHOOL 99 SUNSET DRIVE BUDD LAKE, NJ, 07828 ATTN: MR. THOMAS SCERBO
More informationComprehensive Energy Audit For Kiana Water Treatment Plant
Comprehensive Energy Audit For Kiana Water Treatment Plant Prepared For City of Kiana July 12, 2016 Prepared By: Bailey Gamble ANTHC-DEHE 4500 Diplomacy Dr., Suite 545 Anchorage, AK 99508 1 Table of Contents
More informationSPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)
SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in
More informationEnergy modeling in IDA ICE according to ASHRAE , app. G
Energy modeling in IDA ICE according to ASHRAE 90.1-2007, app. G About this document This document is a user s guide for a relatively experienced IDA ICE operator for using the 90.1 add-in and for performing
More informationComprehensive Energy Audit For Sleetmute Community Center
Comprehensive Energy Audit For Sleetmute Community Center Prepared For The Traditional Council of Sleetmute, and the Alaska Rural Utility Collaborative Apr 26, 2011 Prepared By: ANTHC 1901 Bragaw St. Suite
More informationComprehensive Energy Audit For. Kiana Lift Station
Comprehensive Energy Audit For Kiana Lift Station Prepared For City of Kiana July 27, 2016 Prepared By: Bailey Gamble ANTHC 4500 Diplomacy Dr., Suite 545 Anchorage, AK 99508 1 Table of Contents PREFACE...
More informationPremium Sample Reports
Premium Sample Reports Under the WegoWise Premium subscription, we deliver the following reports in pdf format to present actionable information and answers to common questions property managers and owners
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationA CASE STUDY IN ACTUAL BUILDING PERFORMANCE AND ENERGY MODELING WITH REAL WEATHER DATA
A CASE STUDY IN ACTUAL BUILDING PERFORMANCE AND ENERGY MODELING WITH REAL WEATHER DATA Cherag Mehta 1, and Alan S. Fung 2 1 Engineer-in-Training APEGA, MBSc and LEED GA 2 Mechanical and Industrial Engineering,
More informationApplication of a cooling tower model for optimizing energy use
Advances in Fluid Mechanics X 305 Application of a cooling tower model for optimizing energy use G. C. O Mary & D. F. Dyer Department of Mechanical Engineering, Auburn University, USA Abstract The overall
More informationThe Mirenda Center for Sports, Spirituality, and Character Development
prepared by: Zachary Heilman MECHANICAL OPTION prepared for: James Freihaut, PhD Technical Report 3: (Mechanical Systems Existing Conditions Evaluation) Due Date: November 29, 2010 The Mirenda Center for
More informationDate Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection
Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over
More informationNorth Carolina Public Schools Facility Survey and Recommendations Report for Duplin County Schools
North Carolina Public Schools Facility Survey and Recommendations Report for Duplin County Schools Duplin, North Carolina October 2011 School Planning Mail address: 6319 Mail Service Center School Planning,
More informationEVESHAM TOWNSHIP SCHOOL DISTRICT MARLTON ELEMENTARY FACILITY ENERGY REPORT 190 TOMLINSON MILL ROAD MARLTON, NJ 08053
EVESHAM TOWNSHIP SCHOOL DISTRICT MARLTON ELEMENTARY 190 TOMLINSON MILL ROAD MARLTON, NJ 08053 FACILITY ENERGY REPORT TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY DESCRIPTION...
More informationNEWMOA June 30, Fran Boucher LEED AP, Certified Energy Manager Senior Energy Engineer
NEWMOA June 30, 2009 Fran Boucher LEED AP, Certified Energy Manager Senior Energy Engineer Utility Incentives MA, RI, NH, VT, ME, CT, Long Island NY, Gas in NYC New construction and gas in Upstate NY.
More informationBERGEN COUNTY VOTING MACHINE WAREHOUSE 660 GOTHAM PKWY CARLSTADT, NJ FACILITY ENERGY REPORT
BERGEN COUNTY VOTING MACHINE WAREHOUSE 660 GOTHAM PKWY CARLSTADT, NJ 07072 FACILITY ENERGY REPORT TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY DESCRIPTION... 7 III. MAJOR EQUIPMENT
More informationExisting Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne
Existing Building Cx: Processes & Results A Cultural Journey Barry Abramson Senior Vice President Servidyne AIA Quality Assurance Learning Objectives 1. Define the key steps in the process of retrocommissioning
More informationValue of Air Source Heat Pumps in Light of Variable Energy Prices. Jeff Haase. Energy Design Conference February 27, 2013
Value of Air Source Heat Pumps in Light of Variable Energy Prices Jeff Haase Energy Design Conference February 27, 2013 Agenda Overview of Air Source Heat Pump Technologies History, General Comparison
More informationDesignTools Software Energy Analyzer User Manual
DesignTools Software Energy Analyzer User Manual Table of Contents Introduction...1 Installing Energy Analyzer...3 Getting Started...4 General...4 Project Details (Energy Analyzer Wizard Application)...5
More informationBERGEN COUNTY PROBATION OFFICE 133 RIVER ST. HACKENSACK, NJ FACILITY ENERGY REPORT
BERGEN COUNTY PROBATION OFFICE 133 RIVER ST. HACKENSACK, NJ 07601 FACILITY ENERGY REPORT TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY DESCRIPTION... 7 III. MAJOR EQUIPMENT LIST...
More informationCOOLIDGE SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationAir Source Heat Pumps in the Commercial Market. Thursday, February 5, :00-10:30 a.m.
Air Source Heat Pumps in the Commercial Market Thursday, February 5, 2015 9:00-10:30 a.m. 1. Commercial Equipment Applications, Benefits, Limitations 2. Case Studies 3. Efficiency Vermont Technical & Financial
More informationMorehouse School of Medicine
/0/00 Print /0/00 00 Campus General Building ID Built 7098 98 Renovated Gross Square Feet Building Type Current Replace Value 00 - ACADEMIC FALITIES $ FC/QI (%) > 00.00 Electrical Lighting upgrades/retrofits
More informationPort Heiden Final Report
Village End Energy Efficiency Measures Program 05 06 AEA Grant # 2195225 Administered by Alaska Building Science Network Port Heiden Final Report Community Summary 6 Community buildings and 3 teacher housing
More informationWhole Building Assessment Initiative
Gaudet Middle School Middletown, Rhode Island Prepared for NATIONAL GRID Prepared by B2Q Associates, Inc. Beverly, MA Whole Building Assessment Initiative Revision Date 8/24/2010 5 Arrowhead Lane Beverly,
More informationIdentifying Strong ROI Opportunities for Green Upgrades and Engaging your Entire Portfolio on Incremental Change
Identifying Strong ROI Opportunities for Green Upgrades and Engaging your Entire Portfolio on Incremental Change Presented by: Ryan Delliacono, AGPM, LLD DeeAnne McClenahan, Greystar Kelly Thompson, HD
More informationA Plan for a Sustainable Toronto Discovery District
A Plan for a Sustainable Toronto Discovery District Judy Simon, IndEco Strategic Consulting ABSTRACT The members of the Toronto Discovery District (TDD), located in downtown, Toronto Canada, have developed
More informationProperty Condition Assessment
Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072
More informationBELLMAWR BOROUGH SCHOOL DISTRICT ETHEL M. BURKE ELEMENTARY SCHOOL 112 SOUTH BLACK HORSE PIKE BELLMAWR, NJ FACILITY ENERGY REPORT
BELLMAWR BOROUGH SCHOOL DISTRICT ETHEL M. BURKE ELEMENTARY SCHOOL 112 SOUTH BLACK HORSE PIKE BELLMAWR, NJ 08031 FACILITY ENERGY REPORT TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY
More informationGround-Coupled Heat Pump And Energy Storage
Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system
More informationLOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT
LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT PREPARED FOR: GEORGE J. MITCHELL ELEMENTARY SCHOOL 950 ROUTE 539 LITTLE EGG HARBOR TWP, NJ 08087 ATTN: MS. LYNN COATES SCHOOL BUSINESS ADMINISTRATOR
More informationENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134
Crossroads North Upper Elementary School, NJ ENERGY AUDIT FINAL REPORT CEG PROJECT NO. 9C08134 SOUTH BRUNSWICK BOARD OF EDUCATION PO BOX 181 MONMOUTH JUNCTION, NJ 08852 ATTN: MR. ANTHONY TONZINI BUSINESS
More informationSolar Energy Technologies
1 Solar Energy Technologies ME 430 Queen s University The Solar Energy Resource Varies over day and year, (i.e., intermittent) Generally non-dispatchable Ottawa average for year ~4 kwh/m 2 per day e.g.,
More informationBuilding Energy Analysis for a Multi-Family Residential Building (Multi V III VRF Heat-Pump System)
Building Energy Analysis for a Multi-Family Residential Building (Multi V III VRF Heat-Pump System) Residential-Building Energy-Modeling Engineering Study VRF-ES-BH-001-US 012E03 Executive Summary Contents
More informationTraining Certification Categories
Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and
More information