1 North Carolina Department of Transportation Design-Build Projects

2 Introductions Chad Kimes, PE is the Division Construction Engineer for the North Carolina Department of Transportation in Division 3. Jimmy Zepeda, PLS is a senior technician for SEPI Engineering and Construction. Katie Hite, PE, PTOE is the Division Traffic Engineer for the North Carolina Department of Transportation in Division 3. Morgan Foster is a Summer Engineering Assistant with the North Carolina Department of Transportation in Division 3.

3 Design-Build Background : Department was authorized to use the Design-Build process on 3 transportation projects annually : allowed up to 10 Design-Build projects annually : allowed up to 25 Design-Build projects annually 2011: removed the annual limit on Design-Build projects

4 Why do we use design-build? To provide an alternate method of delivery To expedite construction To speed up completion dates To enhance innovation and constructability To reduce costs

5 Applicable Design-Build Projects Projects that need to be expedited Emergency Projects Projects with complex constructability Projects with traffic phasing issues Projects affording opportunities for innovation Projects that do not lend themselves to normal design-bidbuild procedures New location projects Large interstate widening or rehabilitation projects Projects with heavy traffic volume Large or unique bridge projects

6 Design-Build Team Evaluation and Selection 1. Selection of Technical Review Committee 2. Submission of Statements of Qualifications 3. Shortlisting of Design-Build Teams 4. Submission of Technical Proposals and Price Proposals 5. Evaluation of Technical Proposals 6. Opening of Price Proposals 7. Determination of the Best-Value Design-Build Team 8. Recommendation for Action by the Secretary of Transportation

7 Utilities within Design-Build Projects Design-Build is not well suited for compact projects with extraordinary utility conflicts (too many unknowns)

8 Engineering and Inspection Services Required Department staff conducts construction engineering and inspection services for design-build projects Department may use a third party private engineering firm or include these services in the design-build contract Services may include off-site fabrication, sampling and testing, surveying, etc. Requirements may include: type and frequency of reports level of detail and type of documentation for materials used the in the construction of the project

9 Variations Of Design-Build Design-Build may also be used in the following forms: Express Design-Build Contract Modified Design-Build Contract Nested Design-Build Contract Express Design-Build projects must meet both of the following requirements: Projects with limited opportunity for innovation Projects with a narrow scope of work (e.g. small bridge replacements or Spot Safety improvements)

10 Past Projects

11 Washington Bypass The U.S. 17 Washington Bypass is Beaufort County s first design-build project Constructed to relieve congestion on existing U.S. 17 Project Cost: $200 million Contractor cost: $192 million Completed 8 months early (March 2010) Contractor: Flatiron/United, Joint Venture Design Firm: AECOM

12 Washington Bypass

13 Washington Bypass

14 Washington Bypass

15 Washington Bypass

16 Washington Bypass

17 Washington Bypass

18 Wilmington Bypass Resident Engineer: Wayne Currie, P.E. Contractor: Barnhill Contracting Company Design Firm: HDR Project cost: $87.1 million Contractor cost: $81.6 million

19 Wilmington Bypass

20 Wilmington Bypass

21 Wilmington Bypass

22 Wilmington Bypass

23 I-85/I-485 Turbine Interchange Charlotte, NC The turbine design is notable for its left-turning ramps that sweep around the center of the interchange in a spiral pattern The original proposal called for a four-level stack design that would require an off-site detour for interstate traffic The turbine eliminated the use of flyovers and multiple 1,000- foot-long bridges The design saved the NCDOT nearly $30 million Project Cost: $92.2 million Resident Engineer: Dennis Cloud, P.E. Contractor: Lane Construction Corporation/STV

24 I-85/I-485 Turbine Interchange Charlotte, NC

25 I-85/I-485 Turbine Interchange Charlotte, NC

26 Current Projects

27 Nine Bridge Projects (C ) Why was design-build chosen for this project? Much faster delivery How much was it accelerated? The replacement of the bridges took place faster than if they were done through the TIP, LIBR, or if they had been let separately. How much did it cost? $8.3 million This project is about 70% complete. Today, 7 of the 9 bridges are completed. We are working on bridges 16 and 20 on NC 211. They are to be completed before the end of the year.

28 Brunswick Bridge 3

29 Brunswick Bridge 25

30 Brunswick Bridge 54

31 Brunswick Bridge 101

32 Brunswick Bridge 102

33 Brunswick Bridge 16 & 20

34 Pender Bridge 144

35 Pender Bridge 215

36 Leland Causeway Project Engineer: Jimmy Zepeda, PLS (Sepi) Contractor: S.T. Wooten Project Cost: $56 million Contractor cost:$55.5 million ADT: 100,000 vehicles/day (challenge in itself)

37 Leland Causeway

38 Leland Causeway

39 Leland Causeway

40 Leland Causeway

41 Leland Causeway

42 Leland Causeway: Divergent Diamond Interchange

43 Pros of Design-Build Faster track to construction Delays caused by right of way and utilities are eliminated or minimized Contractor is in control of all phases of the work Design issues are contractor s responsibility to correct Bridges are constructed timely Single accountability - engineering and construction under a single contract Early knowledge of a firm price Design and construction personnel evaluate alternative systems, materials and methods efficiently and accurately Design team involved from start to finish Contractor provides as-builts All survey work is contractor s responsibility

44 Cons of Design-Build More change orders Maintaining updated set of plans is difficult Incomplete plans when work starts Resident office must review submittals Tracking and paying for work is harder Contractor has more unknowns in bids Unorthodox line items Unknown cost of items All survey work is contractor s responsibility

45 Questions?

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016 House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions March 28, 2016 US Highway 70 Main highway route from I-40 & I-95 to the Global TransPark and the Port of Morehead

More information

The Essential Elements of a SMARTZONE Contract

The Essential Elements of a SMARTZONE Contract AASHTO (TIG) Workshop St. Louis, MO September 12-13 13 The Essential Elements of a SMARTZONE Contract Steve Kite, PE NCDOT Work Zone Traffic Control Project Engineer How do I start? http://tig.transportation.org

More information

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting. On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting. Located in the heart of South Carolina, the I-20/26/126 Corridor is the crossroads of the state

More information

DEVELOPMENT AND IMPLEMENTATION OF A 10-YEAR PLAN TO MANAGE INTERSTATE PAVEMENTS IN NC

DEVELOPMENT AND IMPLEMENTATION OF A 10-YEAR PLAN TO MANAGE INTERSTATE PAVEMENTS IN NC 0 0 0 0 DEVELOPMENT AND IMPLEMENTATION OF A 0-YEAR PLAN TO MANAGE INTERSTATE PAVEMENTS IN NC Judith Corley-Lay, Ph.D., PE (Corresponding Author) Pavement Management Unit, NCDOT Mail Service Center Raleigh,

More information

NCDOT Overview. Nick Tennyson, Chief Deputy Secretary March 4, 2015

NCDOT Overview. Nick Tennyson, Chief Deputy Secretary March 4, 2015 NCDOT Overview Nick Tennyson, Chief Deputy Secretary March 4, 2015 Overview Major Functions of DOT Board of Transportation Highway System Overview Construction- Road Building Process Operations and Maintenance

More information

Ellis Powell, PE NCDOT State Construction Engineer

Ellis Powell, PE NCDOT State Construction Engineer 7 Bridges in 74 Days (Or Less) Ellis Powell, PE NCDOT State Construction Engineer NC 12 Detour Ocracoke Island Former hangout of Blackbeard late 1600 s to early 1700 s National Seashore owned and controlled

More information

US 36 Truss Bridge Rehabilitation Schedule-Critical Deadline Met with Teamwork and Innovation

US 36 Truss Bridge Rehabilitation Schedule-Critical Deadline Met with Teamwork and Innovation US 36 Truss Bridge Rehabilitation Schedule-Critical Deadline Met with Teamwork and Innovation March 7, 2018 Who We Are Dave Day, PE Senior Project Manager 34 years with American Structurepoint, Inc. Purdue

More information

TH 169/TH 494 DESIGN BUILD PROJECT

TH 169/TH 494 DESIGN BUILD PROJECT TH 169/TH 494 DESIGN BUILD PROJECT PROJECT OVERVIEW Eliminates traffic signals at Highwood/Townline, South Ramp termini, and North Ramp termini. Adds WB 494 to SB 169 flyover ramp. Adds direct NB 169 to

More information

TSM&O STUDIES & IMPROVEMENT STRATEGIES IN MID-ATLANTIC

TSM&O STUDIES & IMPROVEMENT STRATEGIES IN MID-ATLANTIC TSM&O STUDIES & IMPROVEMENT STRATEGIES IN MID-ATLANTIC 2017 TRAFFIC & SAFETY CONFERENCE Barry Brandt, PE, PTOE Agenda Background Maryland Statewide TSM&O Methodology Analysis Hot Spot Identification Evaluate

More information

January25, **Revised** P3 enables Anthony Henday Drive S.E. to open in 2007

January25, **Revised** P3 enables Anthony Henday Drive S.E. to open in 2007 January25, 2005 **Revised** P3 enables Anthony Henday Drive S.E. to open in 2007 Edmonton...Traffic congestion in south Edmonton will be significantly reduced by fall 2007, thanks to the construction of

More information

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager Interstate 66 Widening from Gainesville to Haymarket RFQ Information Meeting January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager John C. Daoulas, P.E. APD Project Manager and POC Introduction

More information

Transportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement. August 22, 2014

Transportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement. August 22, 2014 Transportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement August 22, 2014 Agenda Program Overview Update TIA Risk Management Solicitation Information Project Overviews TIA Overview

More information

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares

More information

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services Kevin Western, MnDOT State Bridge Engineer House Transportation Policy and Finance Committee April 11, 2016 Introduction to Design

More information

RE Request for FY 2018 UPWP Budget Adjustments

RE Request for FY 2018 UPWP Budget Adjustments November 30, 2017 William Eastin Southeast Georgia Branch Chief GDOT Office of Planning 600 W. Peachtree St. NW, 5th Floor Atlanta, GA 30308 RE Request for FY 2018 UPWP Budget Adjustments Dear Mr. Easton:

More information

BILLINGS BYPASS UPDATE

BILLINGS BYPASS UPDATE July 18, 2018 BILLINGS BYPASS UPDATE TEDD Steering Committee Monthly Meeting Project Update EIS and ROD Documents through Current Design Preliminary Design Completed preliminary design for full-build

More information

Automated Machine Guidance

Automated Machine Guidance House Select Committee on Strategic Planning and Long Term Funding Solutions October 24, 2016 Automated Machine Guidance Lamar Sylvester, PE State Construction Engineer Automated Machine Guidance (AMG)

More information

Public Private Partnerships: Lessons from Florida

Public Private Partnerships: Lessons from Florida Florida Department of TRANSPORTATION Public Private Partnerships: Lessons from Florida Leon Corbett FDOT Project Finance Manager Southern Legislative Conference July 19, 2015 If we had the money 2 Discussion

More information

I-64 Capacity Improvements Segment III RFQ Information Meeting

I-64 Capacity Improvements Segment III RFQ Information Meeting I-64 Capacity Improvements Segment III RFQ Information Meeting April 5, 2017 Janet Hedrick, P.E. Design Project Manager Joseph Clarke, P.E. APD Project Manager and POC I-64 Capacity Improvements Segment

More information

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI)

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI) I-17 and Happy Valley Road Diverging Diamond Interchange (DDI) Bharat Kandel (ADOT) and Jeremy Neuman (HDR) February 28, 2018 Project Purpose and Overview New interchange will accommodate current and future

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

US 84 Mississippi River Bridge

US 84 Mississippi River Bridge US 84 Mississippi River Bridge U29 And U49 Pin Rehabilitation Justin Walker, PE MDOT Director Of Structures, State Bridge Engineer James Gregg, PE HNTB Bridge Department Manager Project Location Vicksburg,

More information

Review of Erosion and Sedimentation Program Delegation to the North Carolina Department Of Transportation, Division of Highways

Review of Erosion and Sedimentation Program Delegation to the North Carolina Department Of Transportation, Division of Highways Review of Erosion and Sedimentation Program Delegation to the North Carolina Department Of Transportation, Division of Highways November 7, 2013 Performed by: T. Gray Hauser, Jr., P.E. State Sedimentation

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Derry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing

Derry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing Derry-Londonderry 13065 - I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing July 25, 2018 Purpose of Meeting Purpose and Need Current Project Status Alternatives Overview

More information

VDOT Major Projects Update

VDOT Major Projects Update VDOT Major Projects Update April 20, 2017 Agenda Introduction Peninsula Projects Southside Projects Harbor Crossing Questions/Comments 2 Summary Construction Execution Timeline I-64 Peninsula Seg. I PE

More information

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM 2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM A. District: 1 2 3 4 5 6 7 TPK C.O. B. Nomination Category: (Select only one category) Outstanding Major Project Outstanding

More information

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions General Overview What is the I-65/I-70 North Split Reconstruction Project? The I-65/I-70 North Split Reconstruction Project

More information

The Great Impact of Geotechnical Features on System Performance

The Great Impact of Geotechnical Features on System Performance The Great Impact of Geotechnical Features on System Performance Scott A. Anderson, Ph.D., P.E. Benjamin S. Rivers, P.E. FHWA Resource Center Geotechnical Technical Services Team Keywords Transportation

More information

TABLE OF CONTENTS. Section Section 2 Alternative A...7 Section 2 Alternative B...7

TABLE OF CONTENTS. Section Section 2 Alternative A...7 Section 2 Alternative B...7 TABLE OF CONTENTS I. General Description...................................................... 3 II. Need for Project.......................................................... 3 III. Adjacent Projects........................................................

More information

Development Overview

Development Overview Development Overview Utilities Infrastructure GIS Webpage Identify Land Review Applicable Regulations Contact Planning Staff Develop Concept Plan Development Overview Submit an Application for Utility

More information

SEISMIC DESIGN AND RETROFIT OF BRIDGES ON MISSOURI S EARTHQUAKE PRIORITY ROUTES

SEISMIC DESIGN AND RETROFIT OF BRIDGES ON MISSOURI S EARTHQUAKE PRIORITY ROUTES SEISMIC DESIGN AND RETROFIT OF BRIDGES ON MISSOURI S EARTHQUAKE PRIORITY ROUTES Shyam Gupta, 1 P.E., Bryan A. Hartnagel, 2 Ph.D., P.E. Abstract The heart of the New Madrid Seismic Zone lies in the southeast

More information

Review of Construction Costs and Time Schedules for Virginia Highway Projects

Review of Construction Costs and Time Schedules for Virginia Highway Projects Joint Legislative Audit and Review Commission of the Virginia General Assembly Review of Construction Costs and Time Schedules for Virginia Highway Projects JLARC Staff Briefing December 19, 2000 Introduction

More information

Replacing the Aging US 52 Mississippi River Bridge

Replacing the Aging US 52 Mississippi River Bridge 2019 TRANSPORTATION & HIGHWAY ENGINEERING CONFERENCE F. Duncan, PE, G. Hasbrouck, PE and A. Dour, PE Replacing the Aging US 52 Mississippi River Bridge February 26, 2019 Project Overview US 52 / IL 64

More information

Joint House and Senate Transportation Committee Update to the Ten Year Plan

Joint House and Senate Transportation Committee Update to the Ten Year Plan Joint House and Senate Transportation Committee 2019 Update to the Ten Year Plan Federal and State Funding Sources 2 AFY19 Budget Revenue Estimates 3 FY19 Federal & State Funds Federal Funds 38% State

More information

I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016

I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016 I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia RFQ Information Meeting - November 9, 2016 Krishna Potturi, PE Project Manager Suril Shah APD Project

More information

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project 06/2014 PROJECT STUDY REPORT (Cal Poly Pomona Senior Project) For Conceptual Approval of an Interchange Improvement And Cooperative Agreement with The City of Lake Elsinore for completion of Project Approval

More information

I-64/ Route 15 (Zion Crossroads) RFQ Information Meeting

I-64/ Route 15 (Zion Crossroads) RFQ Information Meeting I-64/ Route 15 (Zion Crossroads) Diverging Diamond Interchange RFQ Information Meeting December 13, 2011 Brian Arnold District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction

More information

PENNSYLVANIA TURNPIKE COMMISSION

PENNSYLVANIA TURNPIKE COMMISSION PENNSYLVANIA TURNPIKE COMMISSION RETENTION OF AN ENGINEERING OR CONSTRUCTION MANAGEMENT FIRM Construction Inspection / Project Management Services Six Lane Widening, Mileposts 326-333 Montgomery County

More information

I-10 KENDALL EXTENSION. Open House

I-10 KENDALL EXTENSION. Open House I-10 KENDALL EXTENSION Open House The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT

More information

Express Permitting. Jon Nance, PE. Joint Legislative Transportation Oversight Committee April 23, 2008

Express Permitting. Jon Nance, PE. Joint Legislative Transportation Oversight Committee April 23, 2008 Express Permitting Jon Nance, PE Joint Legislative Transportation Oversight Committee April 23, 2008 Purpose of Permitting Safety Mobility Of all the responsibilities that NCDOT has, few day-to-day functions

More information

Overview of Maintenance and Construction Programs. Mike Holder, PE, Chief Engineer Jennifer Brandenburg, PE, State Asset Management Engineer

Overview of Maintenance and Construction Programs. Mike Holder, PE, Chief Engineer Jennifer Brandenburg, PE, State Asset Management Engineer Overview of Maintenance and Construction Programs Mike Holder, PE, Chief Engineer Jennifer Brandenburg, PE, State Asset Management Engineer March 3, 2015 Overview Maintenance and Construction State v.

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 6/2/2014 Project 140353 Addendum No. 1 PID No. 86675 MOT IR 75 11.75/11.80

More information

Lincoln County Board of Commissioner s Agenda Item Cover Sheet

Lincoln County Board of Commissioner s Agenda Item Cover Sheet Lincoln County Board of Commissioner s Agenda Item Cover Sheet Board Meeting Date: Agenda Item Type: Consent Agenda: Public Hearing: Regular Agenda: Presentation Time (est): Submitting Person: Phone Number/Ext:

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

Route 7 Truck Climbing Lane. RFQ Information Meeting

Route 7 Truck Climbing Lane. RFQ Information Meeting Route 7 Truck Climbing Lane From West Market Street to Route 9 RFQ Information Meeting November 9, 2012 Mark Gibney, PE District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction

More information

Monthly Monthly Management Dashboard February Accomplishments

Monthly Monthly Management Dashboard February Accomplishments Monthly Monthly Management Dashboard Accomplishments As part of succession planning, SCDOT has developed a leadership education and development (LEAD) program which is designed to provide cross training

More information

Lehigh Valley Transportation Study

Lehigh Valley Transportation Study ITEM: IV-A Lehigh Valley Transportation Study SUBJECT: PA 33 Preservation SR 22-Belfast COUNTY... Northampton FED.-AID SYSTEM... On-NHS S.R./SEC.... 33/07M DECADE OF INVESTMENT... No A.D.T.... 25,463 CAPITAL

More information

Breaking the Diamond: DDIs, CFIs, and SPUIs

Breaking the Diamond: DDIs, CFIs, and SPUIs Breaking the Diamond: DDIs, CFIs, and SPUIs Smith Siromaskul, P.E. Abstract With a recent push towards innovative solutions in interchange design, the diverging diamond interchange has been the next big

More information

Using Integrated Asset Management System to perform Corridor-Level Analysis

Using Integrated Asset Management System to perform Corridor-Level Analysis Using Integrated Asset Management System to perform Corridor-Level Analysis Jim Edgerton AgileAssets Inc. September 30, 2014 Acknowledgements Neil Mastin, P.E. Pavement Program Analyst, Pavement Management

More information

3/27/2016. Introduction. Introduction. Blanchard et al. (2009) Project delivery: Right attitudes Right personalities

3/27/2016. Introduction. Introduction. Blanchard et al. (2009) Project delivery: Right attitudes Right personalities Rapid Construction: Considerations and Case Studies Rocky Mountain Asphalt Conference February 26, 2016 Introduction Accelerated construction means...minimizing time impacts to the public... (Blanchard,

More information

GDOT s Design-Build Program Past, Present and Future

GDOT s Design-Build Program Past, Present and Future GDOT s Design-Build Program Past, Present and Future John D. Hancock, P.E. Assistant State Innovative Program Delivery Engineer September 16, 2013 Agenda Program Overview GA Code 32-2-81 (SB 70) Look Ahead

More information

448 INNOVATIVE BIDDING TOOLKIT

448 INNOVATIVE BIDDING TOOLKIT Publication 448 INNOVATIVE BIDDING TOOLKIT 2013 Edition, Change 2 Bureau of Project Delivery, Highway Delivery Division Project Schedules, Specifications and Constructability Section PUB 448 (05-16) This

More information

WINDSOR CORPORATE CENTER

WINDSOR CORPORATE CENTER WINDSOR CORPORATE CENTER Andrew Jackson Hwy (Hwy 74/76) & Mercantile Dr NE, Leland, NC 28451 For More Information Contact: Cody Cress 910-409-8421 cody.cress@thecressgroup.com www.thecressgroup.com Tyler

More information

Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC

Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC 2 Presentation Outline Construction Manager/General Contractor (CM/GC) and ABC CM/GC Project Highlights Hartford Bridge Replacement

More information

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)

More information

EIGHT PLANNING FACTORS

EIGHT PLANNING FACTORS EIGHT PLANNING FACTORS Under the provisions of SAFETEA-LU, all Metropolitan Planning Organizations (MPOs) are required to consider eight (8) broad planning factors in the development of multi-modal transportation

More information

Perpetual Pavement Demonstration

Perpetual Pavement Demonstration Perpetual Pavement Demonstration September 12, 2007 Cedar Road from Brainard Rd. to Lander Rd. Cuyahoga County Engineer s Presenters: Brian Brian Driscoll, P.E. Chief Highway Design Engineer Thomas Thomas

More information

TASK 1 Interchange Justification for US 52 in Lawrence County, Ohio

TASK 1 Interchange Justification for US 52 in Lawrence County, Ohio REQUEST FOR PROPOSALS SPECIFICATIONS KYOVA Interstate Planning Commission Group 1: Lawrence County, Ohio US 52 Interchange Project PID: 104526 June 5, 2017 The KYOVA Interstate Planning Commission is seeking

More information

Ohio Department of Transportation. American Council Engineering Companies of Ohio. ODOT/ACEC Partnering Award. Excellence in Highway Design

Ohio Department of Transportation. American Council Engineering Companies of Ohio. ODOT/ACEC Partnering Award. Excellence in Highway Design Ohio Department of Transportation American Council Engineering Companies of Ohio ODOT/ACEC Partnering Award Excellence in Highway Design State Route 44 over the LaDue Reservoir Nomination Deadline: March

More information

Diverging Diamond Interchanges and their Relation to Sustainable Design

Diverging Diamond Interchanges and their Relation to Sustainable Design Diverging Diamond Interchanges and their Relation to Sustainable Design FINAL SUBMITTAL MARCH 0 th, 0 Word Count:, (, Paper + Abstract + Title Page; Exhibits,,00 words) 0 Jason Starr, PE Associate HDR

More information

Supersizing of Wake County s Solid Waste Convenience Centers

Supersizing of Wake County s Solid Waste Convenience Centers Supersizing of Wake County s Solid Waste Convenience Centers Roy Baldwin Wake County Solid Waste Management Jeffrey Murray, PE, BCEE HDR NC SWANA Spring 2016 Technical Conference Greensboro, North Carolina

More information

INNOVATIVE CONTRACTING GUIDELINES

INNOVATIVE CONTRACTING GUIDELINES Office of Construction and Innovative Contracting INNOVATIVE CONTRACTING GUIDELINES A+B Bidding Lane Rentals Incentives/ Disincentives Liquidated Savings Design-Build Warranties Pay for Performance No

More information

Pottstown Pike Congestion Mitigation Feasibility Study

Pottstown Pike Congestion Mitigation Feasibility Study Pottstown Pike Congestion Mitigation Feasibility Study Study Advisory Committee Meeting #3 November 15, 2017 Transportation Solutions Building Better Communities Agenda 1. Background Information 2. Review

More information

Project Delivery, Utilizing Consultants, and Backlog

Project Delivery, Utilizing Consultants, and Backlog Project Delivery, Utilizing Consultants, and Backlog Nevada Department of Transportation Board of Directors March 11, 2016 John M. Terry, P.E. Asst. Director Engineering NDOT Use of Consultants Resources

More information

Accelerated Construction: A Path Forward by Texas Department of Transportation 512/ All Rights Reserved

Accelerated Construction: A Path Forward by Texas Department of Transportation 512/ All Rights Reserved Accelerated Construction: A Path Forward 2018 by Texas Department of Transportation 512/416-2500 All Rights Reserved Introduction The construction zone is the visible and perhaps only connection between

More information

Transportation Management Plan

Transportation Management Plan Transportation Management Plan I 80 PE County, MP 51.38 to MP 62.49 One Inch Mill and Two Inch Fill With Open Grade July 2016 Prepared by Lisa Ouellette Nevada Department of Transportation Executive Summary

More information

Design/Build. How Utilities Are Handled. Gus Kretschmer Michael Baker Engineering

Design/Build. How Utilities Are Handled. Gus Kretschmer Michael Baker Engineering Design/Build How Utilities Are Handled Gus Kretschmer Michael Baker Engineering US 601 Union County, NC NCDOT Union County, NC US 601 $53.8 Million Construction Costs Widening of 11 Miles of two lane roadway

More information

Carolina Connector Intermodal Terminal (CCX)

Carolina Connector Intermodal Terminal (CCX) Joint Legislative Oversight Committee January 6, 2017 Carolina Connector Intermodal Terminal (CCX) Paul C. Worley, CPM, Rail Division Director CCX is a three legged stool: State, Community and Railroad

More information

VDOT UPDATE Hampton Roads Local Damage Prevention Committee - VA811 Membership Meeting

VDOT UPDATE Hampton Roads Local Damage Prevention Committee - VA811 Membership Meeting VDOT UPDATE Hampton Roads Local Damage Prevention Committee - VA811 Membership Meeting April 22, 2015 Michael T. Wilder Southeast Regional Utilities Manager VDOT Mission Statement Our mission is to plan,

More information

Evaluation of Rural Interstate Work Zone Traffic Management Plans in Iowa Using Simulation

Evaluation of Rural Interstate Work Zone Traffic Management Plans in Iowa Using Simulation 184 MID-CONTINENT TRANSPORTATION SYMPOSIUM 2000 PROCEEDINGS Evaluation of Rural Interstate Work Zone Traffic Management Plans in Iowa Using Simulation STEVEN D. SCHROCK AND T. H. MAZE Traffic levels on

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 4/14/2015 Project 150249 Addendum No. 2 PID No. 81747 FRA IR 270

More information

Transportation Investment Generating Economic Recovery Discretionary Grant Program Fiscal Year 2012

Transportation Investment Generating Economic Recovery Discretionary Grant Program Fiscal Year 2012 Transportation Investment Generating Economic Recovery Discretionary Grant Program Fiscal Year 2012 Project Name: Highway 71 New Location (Future Interstate 49) Project Type: Project Location: Area Type:

More information

Life Cycle Cost Analysis

Life Cycle Cost Analysis Life Cycle Cost Analysis Executive Summary Senate Bill 402, Section 34.25 requires NCDOT to report to the legislature on our life cycle cost analysis procedure by February 1, 2014. The four topics that

More information

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH Timothy Nickel, P.E. Project Management Administrator (225) 379-1110 Timothy.Nickel@la.gov Post Office Box 94245 Baton Rouge, LA 70804-9245 A Project within

More information

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk

More information

SD Executive Briefing SDDOT 2011 Statewide Customer Satisfaction Assessment

SD Executive Briefing SDDOT 2011 Statewide Customer Satisfaction Assessment Connecting South Dakota and the Nation South Dakota Department of Transportation Office of Research SD2010-03 Executive Briefing SDDOT 2011 Statewide Customer Satisfaction Assessment Chris Tatham, ETC

More information

Design/ Build. Engineering Services. Construction MECHANICAL SYSTEMS SOLUTIONS

Design/ Build. Engineering Services. Construction MECHANICAL SYSTEMS SOLUTIONS Design/ Build & Construction Engineering Services MECHANICAL SYSTEMS SOLUTIONS Your single source for building MEP systems Effective building construction and the supporting mechanical, electrical and

More information

Standard Performance Attributes for Transportation Projects

Standard Performance Attributes for Transportation Projects Standard s for Transportation Projects Mainline Operations Local Operations Maintainability Construction Impacts Environmental Impacts Project Schedule An assessment of traffic operations and safety on

More information

2010 Indiana Logistics Summit

2010 Indiana Logistics Summit 2010 Indiana Logistics Summit Michael B. Cline Commissioner, INDOT October 26, 2010 INDOT 3,912 INDOT employees 1,702 Highway Technicians 594 Managers/Supervisors 325 Engineers 805 District CO 3,106 State

More information

7 Bridges in 74 Days. NC 12 Detour

7 Bridges in 74 Days. NC 12 Detour 7 Bridges in 74 Days (Or Less) NC 12 Detour Ocracoke NC 12 Bridges Ocracoke NC 12 Bridges Existing 7 bridges built in 1950's Timber structures w/ ACP Clear width 22.5 ft. 36 to 152 ft. long Limited redirective

More information

I-95/US 322 Interchange Improvement Project. Website Update

I-95/US 322 Interchange Improvement Project. Website Update I-95/US 322 Interchange Improvement Project Website Update The following is an outline of the I-95/US 322 website showing the primary pages and then sub-pages within the primary pages. The outline indicates

More information

SCOPE OF SERVICES. Consultant Engineering and Inspection Services. Interstate 85/385 Interchange Improvements Greenville County.

SCOPE OF SERVICES. Consultant Engineering and Inspection Services. Interstate 85/385 Interchange Improvements Greenville County. SCOPE OF SERVICES Consultant Engineering and Inspection Services Interstate 85/385 Interchange Improvements Greenville County Description The Interstate 85/385 Interchange Project consists of improvements

More information

Mega Projects at WSDOT

Mega Projects at WSDOT Mega Projects at WSDOT Managing multiple projects in major urban corridors LINEA LAIRD, WSDOT ASSISTANT SECRETARY ENGINEERING & OPERATIONS Presentation to Oregon State Legislature Congestion Work Group

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

North Carolina Ferry Division

North Carolina Ferry Division Study on Reducing Off- Season Crossings, Adjusting Fares, and Using Partnerships Can Improve Ferry Division Efficiency Sterling Baker, P.E., Director of Facilities Management & Acting Special Deputy Ferry

More information

NASCIO Award Application. Section A: Cover Page. NCDOT Vendor Prequalification System. Digital Government: Government to Business (G to B)

NASCIO Award Application. Section A: Cover Page. NCDOT Vendor Prequalification System. Digital Government: Government to Business (G to B) NASCIO Award Application Section A: Cover Page NCDOT Vendor Prequalification System Digital Government: Government to Business (G to B) North Carolina Contact Information: Name Role Phone Email Tim Frost

More information

SOUTH MEDFORD INTERCHANGE BRIDGES

SOUTH MEDFORD INTERCHANGE BRIDGES Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is

More information

Adaptation of HERS-ST Models for the South Carolina Interactive Interstate Management System

Adaptation of HERS-ST Models for the South Carolina Interactive Interstate Management System Adaptation of HERS-ST Models for the South Carolina Interactive Interstate Management System presented to the Transportation Research Board HERS Modeling and Data Integration Conference presented by William

More information

Background. I-64 Sherman Minton Bridge Inspection, Closure, & Structure Retrofit. Background. Background. Background. Why was there concern?

Background. I-64 Sherman Minton Bridge Inspection, Closure, & Structure Retrofit. Background. Background. Background. Why was there concern? Background I-64 Sherman Minton Bridge Inspection, Closure, & Structure Retrofit Background Background The bridge carries approximately 70,000 vehicles per day on I-64 over the Ohio River. Consists of two

More information

HIGHWAY 71 CORRIDOR IMPROVEMENT STUDY BELLA VISTA BYPASS MISSOURI STATE LINE BENTON COUNTY

HIGHWAY 71 CORRIDOR IMPROVEMENT STUDY BELLA VISTA BYPASS MISSOURI STATE LINE BENTON COUNTY HIGHWAY 71 CORRIDOR IMPROVEMENT STUDY BELLA VISTA BYPASS MISSOURI STATE LINE BENTON COUNTY DRAFT December 2017 Highway 71 Corridor Improvement Study Bella Vista Bypass to Missouri State Line BENTON COUNTY

More information

Executive Summary ORGANIZATION CHANGES MANAGEMENT, DECISION- MAKING, AND DAY-TO-DAY OPERATION STRUCTURE

Executive Summary ORGANIZATION CHANGES MANAGEMENT, DECISION- MAKING, AND DAY-TO-DAY OPERATION STRUCTURE Executive Summary The Lane Construction Corporation and HDR have once again assembled a strong team (Lane-HDR) that provides the best value to TxDOT and the CTRMA. Our success in delivering design-build

More information

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No. Palm Beach County, Florida Palm Beach Metropolitan Planning Organization April 217 Project Study Area LIMITS: SR 9/I-95: from S of 45th Street to N of 45th Street 45th Street: From Village Boulevard to

More information

US 70 Corridor James City Project Update. Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015

US 70 Corridor James City Project Update. Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015 US 70 Corridor James City Project Update Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015 Presentation Overview Improving the US 70 Corridor The Project Team Where Are We Today?

More information

Promoting Innovation Through SHRP2 s Pavement Solutions. Lyndi Davis Blackburn, PE, Asst. State Materials & Tests Engineer, Alabama DOT

Promoting Innovation Through SHRP2 s Pavement Solutions. Lyndi Davis Blackburn, PE, Asst. State Materials & Tests Engineer, Alabama DOT Promoting Innovation Through SHRP2 s Pavement Solutions Lyndi Davis Blackburn, PE, Asst. State Materials & Tests Engineer, Alabama DOT SHRP2 Alabama DOT Implementation Efforts Performance Specifications

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

Falling Behind: The Condition and Funding of Maine s Roads, Highways & Bridges

Falling Behind: The Condition and Funding of Maine s Roads, Highways & Bridges Falling Behind: The Condition and Funding of Maine s Roads, Highways & Bridges October 2009 Prepared by: TRIP 1726 M Street, NW, Suite 401 Washington, D.C. 20036 202-466-6706 (voice) 202-785-4722 (fax)

More information

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: June 17, 2014 Comment Deadline: July 17, 2014 Corps Action ID#: SAW-2009-00655 NC DOT TIP: R-4903 The Wilmington District, Corps

More information

Construction Management Transportation

Construction Management Transportation Construction Management Transportation Transforming the Way We Travel gaiconsultants.com/transportation Construction Management Streamlining Solutions GAI is dedicated to safeguarding our clients interests

More information

South Carolina Department of Transportation. Engineering Directive

South Carolina Department of Transportation. Engineering Directive South Carolina Department of Transportation Engineering Directive Directive Number: ED-17 Effective: May 5, 2015 Subject: Encroachment Permits References: S.C. Code of Laws, Sections 57-3-110, 57-5-1080,

More information