Modularization : Challenges and Opportunities. World First AP1000 Unit
|
|
- Derick Norris
- 6 years ago
- Views:
Transcription
1 Modularization : Challenges and Opportunities Modularization Construction Experiences of World First AP1000 Unit cnfdxl@163.com
2 Contents 1 Retrospect on Sanmen AP1000 Modularization Construction 2 Modularization Construction Experiences of World First AP1000 Unit 3 Challenges and Proposals
3 Overview 1) Sanmen1# is the world first AP1000 unit. 2) Features:. Passive safety system;. Modularization ation construction; ction 3)parties. Owner: SMNPC, SDNPC. Designer: WEC consortium. project Management : JPMO(WEC,SHAW,SNPEC). Constructor: CNF, CNI22, CNI24
4 Overall Schedule Sanmen Unit1 ATP+0 ATP+71 Unit2 Haiyang Unit1 Unit2 4month 6month 5month
5 Milestones Schedule of Sanmen 1#Unit
6 2 Retrospect on SanmenAP1000 NPP et ospect o Sa e 000 Construction
7 1#NI excavation started on #NI Basemat Construction
8 The dental concrete started on Aug,24,2008 1#NI Basemat Construction
9 On Sep. 18, 2008, lower mudmat concrete of 1#NI finished. 1#NI Basemat Construction
10 On Oct. 15, 2008, upper mudmat concrete of 1#NI finished. 1#NI Basemat Construction
11 O J b t f 1# NI On Jan. 12, 2009, basement of 1# NI rebar finished. 1#NI Basemat Construction
12 On Jan. 22, 2009, first equipment module KB10 was set. 1#NI Basemat Construction
13 On Feb. 19,2009, stay in place form installation finished. 1#NI Basemat Construction
14 1#NI Basemat Construction On Feb. 28, 2009, the embedded piping installation was finished and ready for FCD.
15 1#NI FCD on Mar. 29, #NI FCD
16 Night Shift 1#NI FCD
17 1#NI FCD On Mar. 31, 2009, monolithic concrete placement of more than 5000 m 3 was achieved. It took 47 hours for 1#Unit.
18 AP1000 ModularizationConstruction Process Modularization Construction Flowchart Module Assembly shop Fabrication Module Transportation Module Lifting engineering Set
19 shop Fabrication of Structural Module
20 In August of 2008, CA assembly area was available. Construction Progress Show CA20 Assembly
21 Construction Progress Show CA20 Assembly By the end of 2008, the first batch of sub modules of CA20 delivered on site.
22 Sub modules Fitting up Construction Progress Show CA20 Assembly CA20 Floor
23 Construction Progress Show CA20 Assembly Sub modules Welding
24 Construction Progress Show CA20 Assembly 1 2 The assembled subassemblies overturn and erected, ready for integrated assembly 3 4
25 Construction Progress Show CA20 Assembly Integrated assembly of structural module
26 Construction Progress Show CA20 Transportation and Lifting The structural module transported from assembly area to NI through heavy haul road Two 25 axes hydraulic trailers
27 CA20 module, about 1000T, lifted and set in NI on Jun. 29, 2009 Construction Progress Show CA20 Transportation and Lifting
28 on Oct. 23, 2008, CV assembly area was available CVBH Assembly and Lifting
29 CVBH Assembly CVBH Assembly and Lifting
30 CVBH Welding CVBH Assembly and Lifting
31 CVBH welding finished and ready for transportation CVBH Assembly and Lifting
32 CVBH Assembly and Lifting CVBH Lifting 1#CVBH was set at NI on Dec. 21, 2009
33 CV Shell Assembly & Transport
34 1#NI CV1# ring was CV Shell Lifting Set on Mar,18,2010 1#NI CV2# ring was set on
35 CV Shell Lifting 1#NI CV3# ring was set on #NI CV4# ring was set on
36 shop Fabrication of Equipment Module
37 Equipment Module KB11 Lifting Construction Progress Show Equipment Module Lifting KB12 Lifting
38 R151 Lifting Construction Progress Show Equipment Module Lifting R161 Lifting
39 2 Modularization Construction Experiences of World First AP1000 Unit 1) A detailed, intergrated schedule shall be prepared prior to project construction and implemented to ensure continuous, smooth construction on site.. Detailed design must be preliminarily completed to meet the requirements of material procurement and module fabrication.
40 2 Modularization Construction ti Experiences of World First AP1000 Unit 2)Much longer duration is required to use heavy load equipments for lifting and transportation t ti Equipment AP1000 Other PWR Heavy load Crane 2600T/3200T, for the 800T, interval utilization whole construction period Medium Crane Two 400T N/A Hydraulic Transporter 1000T, 400T 400T
41 2 Construction Experiences of World First AP1000 Unit 3) Module fabrication shall be started prior to FCD to meet site construction, The installation i of bulk material ilshall hllbe started right after FCD is finished. then:. The procurement ofbulk material and equipment shall be started at an earlier time.. award oftheconstruction contract shall satisfythe the construction requirements.
42 2 Construction Experiences of World First AP1000 Unit 4) The parallel/intercrossed construction for civil and erection needs more close coordinate, and the civil and erection work shall be performed at the sametimeand and together withoutside module fabrication.. Logic relation.. Lifting and transportation passage.
43 Typical Construction Logic Figure CA01 set CA04 set CA05 set Concrete placement for layer 4 Concrete placement for layer 2 Concrete placement for layer3 Concrete placement for layer1
44 On Apr. 28, 2009, CR10 module was set. CV Internal Structure Construction
45 CV Internal Structure Construction On Aug 1, 2009, exterior foundation layer A was poured.
46 On Aug. 1,2009,CVBH was set. CV Internal Structure Construction
47 On Jan 12, 2010,interior structure layer1 was poured. CV Internal Structure Construction
48 On Jan 26, 2010, the lifting of CA04 module was successfully performed. CV Internal Structure Construction
49 CV Internal Structure Construction On Feb. 10,2010, interior structure layer2 was poured.
50 CV Internal Structure Construction On Feb. 28,2010, CA05 module was set. On Mar. 11, 2011,interior structure layer3 was poured.
51 CV Internal Structure Construction
52 CV Internal Structure Construction CA01 Lifting
53 CV Internal Structure Construction On Mar. 27, 2010, CA01 module was successfully set.
54 2 Construction Experiences of World First AP1000 Unit 5) The stick installation is changed into the modularization construction, which makes the work at shop(module fabrication) easier, while the site work (module transportation, assembly, lifting, erection)more difficult. Structure module assembly:. overhead position welding required;. Irregular shaped assembly structure, hard to locatethethe CG;. Integral outline dimension is hard to control due to fabrication and assembly deviation accumulation.
55 2 Construction Experiences of AP1000 First Unit 6) Flexible site module adjustment The actually delivered KB15 module is not completed, and the unfinished parts inside module, such as piping, will be installed on site. Integrated KB15 module in 3D Model
56 2 Construction Experiences of World First AP1000 Unit 7) Weather Protective Measures. Temporary cover;. Hard and soft cover for individual;. Paint after permanent coverd. The assemblyfor temporary top cover is ongoing. Main truss Annular truss
57 3 Challenges and Proposals 1) Increase of Construction Cost:. The fees for lifting&transportation equipment are increased..more manpower resources: due to the parallel construction of civil and erection, the construction period for these two disciplines has been extended, which caused that the manmonth input has been increased.
58 3 Challenges and Proposals 1)Increase of Construction Costs:.Lower labor efficiency : The construction logic is strictly required, if any deviation of schedule hdl on any link, such as design, equipment and material supply, the progress for major structure will be slowly, and even local suspension willbe caused, so that the laborefficiency becomelower and lower.. Heavy haul road, module assembly field and facilities shall be added.
59 3 Challenges and Proposals 1) Increase of Construction Costs large quantity for temporary steel structure CVBH Temporary Steel Structure Support Structural Module Temporary Steel Structure Support
60 3 Challenges and Proposals 1) Increase of Construction Costs large quantity for temporary steel structure CVTH Temporary Steel Structure CVTH Temporary Steel Structure Supports
61 3 Challenges and Proposals 2) Increaseof difficulty of Finished Products Protection Outdoor Installation of Equipment Module
62 3 challenges and Proposals 3) Large Difficulty for Management of Intercrossed Construction Intercrossed d construction for structural module and embedded bdddpiping, civil RV cavity structural module CA04 Embedded piping Embedded cable conduit CB65 structural module
63 3 challenges and Proposals 3) Large Difficulty for Management of Intercrossed Construction
64 3)Big Difficulty for Management of Intercrossed Construction. The layout tfor each building of AP1000 is compact, the Open Top method shall be adopted, so that the layout of site cranes, location of tower cranes and operation managementare are critical.
65 3 Challenges and Proposals 4) Increase of Construction Difficulty : The deformation control during structural module fabrication, assembly and installation is greatly difficult. The connection after setting of equipment module, such as site piping, is very difficult to be performed. The location precision is high, and as the precision requirements for multi location and multi points need to be met, alignment is very difficult to be performed.
66 Pipe terminal of R155 module Pipe terminal of R151 module Site connection issues after these two modules are set: as the accumulated deviations for module fabrication and installation, the pipe position is difficult to be aligned.
67 3 Challenges and Proposals 5) Prior to design finalization, the detailed constructability &maintenance evaluation and optimization must be performed:. Module lifting and transportation passage.. The decoration after module set is very difficult to be performed, so that the final decoration must be finished before modulesetting.
68 Install equipment module by Open Top Method Lifting of equipment module Equipment module set
69 3 Challenges and Proposals. Installation space, equipment module internal space is small, so that cable layout and maintenance is very difficult to be performed. The distance between floor module and cable tray is very short, so that the cable layout and maintenance is very difficult to be performed.
70 3 Challenges and Proposals 5) Prior to design finalization, the detailed constructability&mainenance evaluation and optimization must be performed:.operation space while installation (scaffolding, welding and NDE)..Evaluation for module transportation and lifting passage.
71 3 Challenges and Proposals 5) Prior to design finalization, the detailed constructability& maintenance evaluation and optimization i i must be performed: The evaluation of maintainability is also vey important:. The evaluation of maintainability is also vey important: equipment moved in through Open Top Method and the operation space and passage moveout of equipment components during maintenance must be considered.
72 3 Challenges and Proposals 6) Prior to design finalization, the detailed economy evaluation and optimization i must be performed:. Whether moduleshall be adoptedornot or not, bigorsmallsize size shall be used.. Considering the costs for integrated link (design, fabrication and site construction).
73 Conclusion The most valuable contribution for modularization is that the construction period (FCD~CO) reduced, so as to reduce the investment, however, partial works need to be performed in advance (change from after FCD to before FCD) and with good planning and organization & implementation, otherwise, the stick installation method is better.
74 Thanks! net sanmen.com ap1000.com
Westinghouse AP1000. Reactor
Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East
More informationThe Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services
The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT AND MANAGER that offers comprehensive management throughout the project, from concept to completion, yielding the greatest possible benefit to the owner. IPS will offer uncolored
More informationStatus of ITER Buildings construction and next procurement steps
Status of ITER Buildings construction and next procurement steps Laurent Schmieder Site, Buildings and Power Supplies Project Manager IBF/15 DIRECTORY IBF/15 March 25-27 March 25-27, 2015 Palais du Pharo
More informationTHE GLOBAL GROWTH OF PREVENTION THROUGH DESIGN. Bradley Giles, P.E., CSP, STS Vice President ESH&S, URS Corporation
THE GLOBAL GROWTH OF PREVENTION THROUGH DESIGN Bradley Giles, P.E., CSP, STS Vice President ESH&S, URS Corporation Safety Considerations in Design How it Started Content started in Constructability reviews
More informationConcrete Masonry. Weights and Process. Grades & Types
Concrete Masonry Weights and Process Two basic weights Normal weight 40 lbs. / unit 1,200-1,800psi comp strength Lightweight 22-28 lbs. / unit 700-1,000 psi comp strength Molded with a very dry mix - 3
More informationDIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK
DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,
More informationAdministration Division Public Works Department Anchorage: Performance. Value. Results.
Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,
More informationCF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE
CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document
More informationWAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet
March 5, 2015 WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet Overview The purpose of this Project is to repair damages to the Waikoloa Reservoir No. 1 which were sustained during
More informationPROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404
LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:
More informationREPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017
REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 G. MANENTI, V. PESCUMA AND S. SARTI, ALFA LAVAL OLMI SPA, ITALY, PROVIDE AN OVERVIEW OF THE DELIVERY SCHEDULE FOR A KEY PIECE OF HEAT TRANSFER EQUIPMENT, PROCESS
More informationPlanned Procurement Opportunities Report. February 2018
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationSECTION BASIC ELECTRICAL MATERIALS AND METHODS
SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:
More informationThe Australian Institute of Building. Queensland Construction Outlook Paul Hodgson (Chief Operating Officer) Construction Skills Queensland
The Australian Institute of Building Queensland Construction Outlook Paul Hodgson (Chief Operating Officer) Construction Skills Queensland Queensland Construction Outlook AIB Qld Chapter Tattersalls Club,
More informationJhajjar Project Management An Insight. March 4, 2013
Jhajjar Project Management An Insight March 4, 2013 2 x 660 MW Mahatma Gandhi Thermal Power Plant Jhajjar, Haryana, INDIA 2 A Brief Introduction 2x 660 MW greenfield project, named as Mahatma Gandhi Thermal
More informationLARGE STORAGE TANK PROJECT
INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf
More informationState Project No.: , N501 Contract ID Number: C DB66
Request for Proposal Letter of Submittal Design-Build I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) Norfolk, Virginia State
More informationModule Set Process. Presentation to the Quality Modular Building Task Force. October 19, 2000
Results from Studies of the Module Set Process Presentation to the Quality Modular Building Task Force October 19, 2000 Dr. Michael A. Mullens, PE - UCF Agenda Background & Approach Findings Conclusions
More informationSection 5 - Project Logistics
Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,
More informationThe modern solution to in-situ concrete stairs
The modern solution to in-situ concrete stairs The LEXISTIR System LEXISTIR is a permanent, lightweight galvanized steel shuttering system for forming an in-situ stair. or use on reinforced concrete and
More informationFDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider
Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor
More information1. FROM (Bidder): (Name)
Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationTROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)
TROJAN DECOMMISSIONING STATUS OPUC Meeting March 8, 2005 (draft) 1 Meeting Agenda Trojan Decommissioning Overview History Major Projects Overall Performance Remaining Major Activities Current Issues USDOE
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationPlanned Procurement Opportunities Report. January 2018
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationVerizon Wireless Collocation Guidelines Washington/Baltimore/Virginia
Verizon Wireless Washington/Baltimore/Virginia Network Engineering 1831 Rady Court Richmond, VA 23222 804-347-2572 Verizon Wireless Collocation Guidelines Washington/Baltimore/Virginia The Verizon Wireless
More informationThe GRI Sustainability Reporting Guidelines -Main Features of G4- Ásthildur Hjaltadóttir Interim Director Network Relations
The GRI Sustainability Reporting Guidelines -Main Features of G4- Ásthildur Hjaltadóttir Interim Director Network Relations Hong Kong, 13 November 2013 Sponsor of this event: Hosted by: Topics Introduction
More informationGUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410
GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific
More information13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking
9-10 May 2016 KL Rectangular shield jacking/tbm and comparison with pipe roof Singapore Society for Trenchless Technology () Focuses Introduction of rectangular shield jacking Comparison of Pipe roof /
More informationLATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.
LATRINE CONSTRUCTION Pour flush latrine 2 Pour flush micro septic tank 3 Initial investment, location, human resources 4 Concrete rings 5 Box 6 Cover 7 Slab and ceramic pan 8 Ring mold 9 Structure and
More informationTHE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK
THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK or our breadth of capability. Of all the storage tank manufacturers doing business today, no other offers Caldwell s range of capability. We are the only manufacturer
More informationPRESENTATION CENTER SURREY, BC CANADA
PRESENTATION CENTER SURREY, BC CANADA 1 VIEW OF THE PROPOSED OPTIMA 3 TOWERS (AFTER OBTAINING THE HIGH DENSITY THAT IS UNDER STUDY) ALONG WEST WHALLEY RING ROAD 2 3 IHI WILL BUILD THE OPTIMA PRESENTATION
More informationPlanned Procurement Opportunities Report. December 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationTCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum
TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum FGP-WPMP Major Construction Scope Overview Jorge Calvo 30 January 2017 Atyrau, Kazakhstan Tengizchevroil
More informationA. Drawings and general provisions of the Contract, including General Conditions Specification Sections, apply to this section.
Page 1 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions Specification Sections, apply to this section. 1.2 SUMMARY A. The shade structure
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More information11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...
Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3
More informationOWN The Owner s Estimate Requirements Document
OWN.1393 The Owner s Estimate Requirements Document Larry R. Dysert, CCC CEP Abstract The Estimate Requirements Document is a planning document that should be used by owner companies to clarify goals,
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,
More informationHolds a B. Sc. in Mechanical Power Engineering and has over 10 years hands-on experience working in construction and piping.
103785-MEC-CW-E-2003 Site Team Leader Holds a B. Sc. in Mechanical Power Engineering and has over 10 years hands-on experience working in construction and piping. PERSONAL DATA Nationality : Egyptian Birth
More informationWhat is NUFORM HOUSE KIT?
Introduction Nuform Building Technologies Inc. (NUFORM ) is creating a better way to deliver affordable housing the NUFORM HOUSE KIT is a solution for creating neighborhoods where people live with pride
More informationV.C. Summer Nuclear Station Units 2 & 3
V.C. Summer Nuclear Station Units 2 & 3 Quarterly Report to the South Carolina Office of Regulatory Staff Submitted by South Carolina Electric & Gas Company Pursuant to Public Service Commission Order
More informationINOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:
INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win
More informationPage 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS
Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 FOUNDATION SYSTEM SECTION 10 CONTENTS INTRODUCTION... 10-3 PRODUCT BENEFITS... 10-3 RECOMMENDED FACTORS of SAFETY for DESIGN...
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationRAMO INDUSTRIES PTE LTD PROJECT GALLERY
RAMO INDUSTRIES PTE LTD PROJECT GALLERY Type of Works - Civil, Structural,Mechanical, Electrical & Architectural Works Project Pre-fabricated and Pre-Engineered Building Structure for Accommodation Camp(Ongoing)
More informationCOMOS Training Calendar 2017/2018
COMOS Training Calendar 2017/2018 www.siemens.com/comos Scan this code for further informations. Calendar 2017/2018 Offer Whether you re looking for basic knowledge for first-time users or specialist know-how
More informationINDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2
INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...
More informationPLANNING INTERACTIVE. 4-A s of SAFETY. Bridging the GAPS between FEP & Execution 2. ASSESS 3. ADDRESS 4. ABORT 2/18/2015
INTERACTIVE PLANNING Bridging the GAPS between FEP & Execution Presented by John Fish Feb 18, 2015 Director Project Support Services Ford, Bacon & Davis, LLC /S & B Engineers and Constructors, Ltd. HBR
More informationWelcome to Taishan NP site
Welcome to Taishan NP site 1 Content Project Introduction Project Progress Main Tasks in 2011 2 Site Conditions TSNP is situated at Yaogu village of Chixi town in Taishan city, Guangdong province, 70km,
More informationCE 6506 CONSTRUCTION TECHNIQUES, EQUIPMENTS AND PRACTICES UNIT 1 CONCRETE TECHNOLOGY 1. List the various methods of mix design. 2. Name some methods of non-destructive testing of concrete. 3. What is the
More informationILC ASIAN DRAFT SCHEDULE
ILC ASIAN DRAFT SCHEDULE K Foraz, M Gastal & J Osborne Many thanks to all contributors Objectives and scope To provide a target baseline construction schedule for the 2 Asian sample sites Address remarks
More informationPLASTERFORM GLASSFIBER REINFORCED GYPSUM (GRG) REV: 4/11
Plasterform Inc. 1180 Lakeshore Road East, Mississauga, Ontario Canada L5E 1E9 t 905.891.9500 1.800.268.4534 f 905.891.2232 plasterform.com SECTION 09285 PLASTERFORM GLASSFIBER REINFORCED GYPSUM (GRG)
More informationNew Reclaim Tunnel at Coal Fired Plant
Omaha SAME Post Monthly Meeting 10 July 2014 New Reclaim Tunnel at Coal Fired Plant By: Steve Morrissette Zapata Incorporated Omaha, NE Coal Fired Power Plant Generating capacity: 2,090 megawatts base
More informationVoisey s Bay Project Update
Voisey s Bay Project Update Presentation to the Newfoundland and Labrador Branch of the CIM November 5, 2004 This presentation will include projections and other forward-looking statements. While these
More informationAnalysis of Productivity by Comparing Mivan and Conventional Formwork
Analysis of Productivity by Comparing Mivan and Conventional Formwork 1 Prathul U, 2 Leeladhar Pammar 1 PG student, 2 Assistant Professor 1, 2 Department of Civil Engineering, NMAMIT, Nitte Abstract Productivity
More informationPlanned Procurement Opportunities Report. November 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationConcrete vs. Steel Structures: Comparison of Documentation Requirements. GBS gravity base structure. Concrete Steel Commments
http://kepp.no Concrete vs. Steel Structures: Comparison of Documentation Requirements Concrete Steel Commments Engineering calculation notes engineering drwgs technical specs Concrete drawings are assumed
More informationScope of Work Bid Package C-3 - West Precast Concrete
Scope of Work Bid Package C-3 - West Precast Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationInstalling DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site
Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan
More informationJobsite Layout Considerations
1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration
More informationStructural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options
Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements
More informationOverview for a feasibility study
Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to
More informationShigeru Sakamoto Construction Technology Development Department Taisei Corporation
At present the Japanese construction industry and related areas in Japan are suffering from a number of problems. The problem of stagnant productivity and ever-increasing accidents are reflected in the
More informationDIVISION 02 SELECTIVE DEMOLITION
DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.
More informationContents of my presentation
1 Design and Techniques for Safety in High Rise Buildings- Focus on Temp. Structures-Formwork Dr. Kumar Neeraj Jha Department of Civil Engineering Indian Institute of Technology Delhi Email: knjha@civil.iitd.ac.in
More informationSECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM
ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary
More informationEN DK NA:2007
EN 1995-1-1 DK NA:2007 National Annex to Eurocode 5: Design of timber structures - Part 1-1: General - Common rules and rules for buildings Foreword In connection with the incorporation of Eurocodes into
More informationBUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS. March 2014
BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS March 2014 Energy Safe Victoria (ESV) continues to receive complaints concerning defective builder s construction supplies.
More informationThe Aizhai Suspension Bridge is
INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
SECTION 14651 FREE STANDING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial
More informationTECHNICAL ASSIGNMENT 2
PENN STATE AE SENIOR THESIS 2011-2012 TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis BRIANNE KYLE Construction Management Thesis Advisor: Dr. Chimay
More informationCOMPLETE REVISION November Process Industry Practices Structural. PIP STF05530 Grating Fabrication Details
COMPLETE REVISION November 2006 Process Industry Practices Structural PIP STF05530 Grating Fabrication Details PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process
More informationMarina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle
Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte
More informationVogtle. Ninth/Tenth Semi-annual Vogtle Construction Monitoring Report. units 3 & 4. February 2014 Docket No
Vogtle units 3 & 4 Ninth/Tenth Semi-annual Vogtle Construction Monitoring Report February 2014 Docket No. 29849 U.S. Secretary of Energy Dr. Ernest Moniz and Georgia Power representatives finalize the
More informationBIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample
BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:
More informationCreating Customized Solutions
Creating Customized Solutions We Work Collaboratively to Deliver High-Impact Results Kelley Blue Book partners with advertisers to create tailor-made products and campaigns that meet unique goals and objectives
More informationCrane Certification FAQs
Crane Certification FAQs The following are common FAQs explaining what you need to know in order to be in compliance with the new OSHA crane certification requirement. General Questions What is the new
More informationWestinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant
Westinghouse s plant for the Nuclear Renaissance : AP000 Fernando Naredo Milan, January 30, 006 AP000 Advanced Passive Plant Designed to compete with other sources in deregulated power markets - Two loop,
More informationElevated Slab Sequence
Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)
More informationMACHINE-LAY Installation Manual
MACHINE-LAY Installation Manual PaveDrain Installation Manual Table of Contents Section 1: Base Preparation (pages 3 6) Section 2: Machine-Lay PaveDrain Blocks (pages 8 11) Section 3: Edge Restraints (pages
More informationSIMULATION OF BORED PILE CONSTRUCTION
Proceedings of the 2001 Winter Simulation Conference B. A. Peters, J. S. Smith, D. J. Medeiros, and M. W. Rohrer, eds. SIMULATION OF BORED PILE CONSTRUCTION Tarek M. Zayed Assistant Professor Construction
More informationThe Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage
The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco
More informationPROCUREMENT PLAN. Consulting Services
PROCUREMENT PLAN Basic Data Project Name: North Eastern Region Capital Cities Development Investment Program - Tranche 2 Project : 35290-033 Approval : 2834 Country: India Executing Agency: Ministry of
More informationJosh Raphael CM Dr. Riley. Technical Report 3. Holiday Inn Express Absecon, NJ
Josh Raphael CM Dr. Riley Technical Report 3 Holiday Inn Express Absecon, NJ Table of Contents Executive Summary....... 2 Constructability Challenges....... 3-4 New Entry.... 3 Existing Facility..... 3-4
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationSECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS
SECTION 270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Communications equipment coordination and installation. 2. Sleeves for pathways and cables. 3. Raceway
More informationDeveloping and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,
Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Risk Integration Management Pty Ltd Presentation Outline
More informationConstruction Technologies and Management of NPP
Construction Technologies and Management of NPP Nuclear Power Division Ki Sig Kang International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready
More informationFlamanville 3 EPR, safety assessment and on-site inspections
Flamanville 3 EPR, safety assessment and on-site inspections Corinne. PIEDAGNEL, François TARALLO, Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire, DSR/SAMS 92262 Fontenay-aux-Roses Cedex,
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
GORBEL PRODUCT SPECIFICATIONS 2010 Gorbel, Inc., P.O., Box 593, Fisher, New York 14453-0593 PHONE: 800-821-0086, FAX: 585-924-6273; WEBSITE: www.gorbel.com November SECTION 41 22 31PRIVATE FREE STANDING
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More information