1 RE-USE AND REPURPOSING OF UNDERUTILIZED BUILDINGS: STRATEGIC PLANS FOR COMPETITIVE RESEARCH ENVIRONMENTS
2 INTRODUCTIONS SETTING THE STAGE CASE STUDY: PRINCETON UNIVERSITY
3 01 INTRODUCTIONS
4 Liz Cook AIA, LEED AP Marc Carola PE, LEED AP BD+C Mark Wilson AIA, LEED AP BD+C
5 02 SETTING THE STAGE
6 Impacting Decisions of New Building Vs. Renovation TRENDS AND DRIVERS
7 THE COST» Do More with Less» Change in Funding Streams» Accountability» Speed to Market Phasing Swing Space Premium Time Other Site Isolation Code upgrades Abatement Demo Fit-Up Core& Shell Site New Renovation Occupied Renovation Construction Cost Allocations
8 STANDARDS AND DATA» Evidence Based Design» POE s» Benchmarking» Strategic Planning» Proof of Investment
9 THE CAMPUS» Community & Context» Re-centralizing» Refit vs. Reinvent» Repurposing
10 SUSTAINABILITY» Students are driving perception» Energy costs are driving efficiency» Lifecycle cost analysis mandates» Net Zero is the new LEED
11 THE GREENEST BUILDING IS ALREADY BUILT 10 TO 80 YEARS Time required for a new building to overcome the negative impacts created during its construction 20 TO 30 YEARS Time required to compensate for the initial carbon impact from construction for a majority of building types *Statistics by the USGBC & National Trust for Historic Preservation 2012
12 ATTRACT AND RETAIN ENVIRONMENT» Enrollment decline Population Decrease Over 25 Mergers» 50% drop out rate
13 CAMPUS STATS» 20-30% of buildings were completed between » 10-20% of buildings were completed between » 30-50% of the campus has greater value than ever to be invested in Steve Cadman
14 What we think is historic and what is historic
15 GREAT BONES, BAD SYSTEMS 1973 OIL CRISIS BONES SYSTEMS Floor to Floor Heights Super Structure MEP Systems Distribution Exterior Systems POST WORLD WAR II MODERN Reinforced Concrete Hard Balanced, Constant Volume, Pneumatic Control Systems Masonry Construction with Strip Windows or Curtain Wall Reinforced Concrete Hard Balanced, Constant Volume, Pneumatic Control Systems Masonry Construction with Strip Windows or Curtain Wall Flexible System of Structural Steel or Concrete VAV, Chilled Beams, Intelligent Building Systems Energy Efficient Thermal Systems Code Focus on Safety Focus on Safety Energy Codes, ADA
16 REVOLUTION OF THE RESEARCH ENVIRONMENT MODERN» PI-Centric» Closed and Enclosed» Ideas come from within the Lab» Zoned Functions» Open and Shared» Ideas come from the spaces in-between
17
18 A GOOD STRATEGIC PLAN:» Considers Current and Future Environment» Prioritizes Investment $ Rank» Categorizes Must Haves & Want to Haves» Balance Built Infrastructure & Sustainability Research Environment» Accounts for Surprise» Provides a roadmap for decisions.
19 UTILIZES TOOLS FOR DECISION MAKING:» Laser Surveying» Code Analysis» Energy Modeling» Sustainability Charette» Cost Modeling» User Interviews» Project Vision
20 ADJUSTABLE FOR THE SPECIFIC SCENARIO: Program» Departmental» Good of the whole» Change behavior and learning» Expectations Modular, flexible Space type variety Researcher» Grant Funded» High Profile» High Result» Expectations Exacting Environment Tune to specific research CORE CORE
21 CASE STUDY: 03 PRINCETON UNIVERSITY
22
23 E STILL DIDN T KNOW WHO WAS MOVING IN. THE STORY OF THE CHEMISTRY DEPARTMENT E-QUAD» Recently modernized asset HOYT LAB» Adequate vacated chemistry building» Embedded energy» Valued asset» Near e-quad» Integral to the fabric of the campus Demolition is not an option. Find a value-added solution.
24 E STILL DIDN T KNOW WHO WAS MOVING IN. IDEA FIRST PROGRAM AFTER For a modest amount, we can turn it into something very usable» Scrub it up, make it look presentable» Building systems were at the end of their useful life but» Always need for space» Much faster to reuse than tear down» New buildings have new rules, more roadblocks» Cost is incurred even if it isn t occupied Who, what, where, and when?
25 EAS IDENTIFYING WHO» Which group?» Can they perform their research?» Who would benefit from collocation?» Who can meet the budget? People were identified, but was more complicated than just placing people.
26 THE REALITY
27 HOYT S HISTORY
28 1ST, 2ND & 3RD FLOOR PLAN PUBLIC/OFFICE/ADMIN LABORATORY MECHANICAL
29 BASEMENT AND 4 TH FLOOR PLANS 600 sf 600 sf PUBLIC/OFFICE/ADMIN LABORATORY MECHANICAL
30 STRATEGIC GOALS Is it in the right place? Is it the right size to accommodate the program? Does it also accommodate growth? Will the new space avoid grossly unequal conditions? Will the building be able to sustain through time? Are budgets realistic? Will it meet The University s energy goals (30% or better)? Will User productivity be compromised for cost / schedule? Yes Yes Yes Yes Yes???
31 We need a strategic plan
32 CHALLENGES OF REUSE & REPURPOSE» 12 floor-to-floor height» MEP equipment approaching life expectancy» Vertical distribution limitations» Limit amount of structural reinforcement» Improve daylighting/quality» Spaces that facilitate collaboration and transparency» Provide a prototype laboratory» Meet or beat contingency goals
33 CHALLENGES OF REUSE & REPURPOSE» 12 floor-to-floor height» MEP equipment approaching life expectancy» Vertical distribution limitations» Limit amount of structural reinforcement» Improve daylighting/quality» Spaces that facilitate collaboration and transparency» Provide a prototype laboratory» Meet or beat contingency goals
34 CHALLENGES OF REUSE & REPURPOSE» 12 floor-to-floor height» MEP equipment approaching life expectancy» Vertical distribution limitations» Limit amount of structural reinforcement» Improve daylighting/quality» Spaces that facilitate collaboration and transparency» Provide a prototype laboratory» Meet or beat contingency goals
35 CHALLENGES OF REUSE & REPURPOSE» 12 floor-to-floor height» MEP equipment approaching life expectancy» Vertical distribution limitations» Limit amount of structural reinforcement» Improve daylighting/quality» Spaces that facilitate collaboration and transparency» Provide a prototype laboratory» Meet or beat contingency goals
36 CHALLENGES OF REUSE & REPURPOSE» 12 floor-to-floor height» MEP equipment approaching life expectancy» Vertical distribution limitations» Limit amount of structural reinforcement» Improve daylighting/quality» Spaces that facilitate collaboration and transparency» Provide a prototype laboratory» Meet or beat contingency goals
37 Feasibility Study to Establish Project Parameters
38 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Feasibility Study Design Phase Bidding Phase Construction Phase TIMELINE
39 HE STRATEGY FEASIBILITY STUDY TASKS» Meet w/ AHJ Perform Code/ADA Analysis» Hazmat Recommended Sampling Plan» Building Roof, Envelope and Architectural Finishes Evaluation» MEP Equipment/Distribution Options» Energy Modeling for Base Line and Options» Casework Evaluation» Sustainability Charette» Laboratory Floor Plate Schemes» Life Cycle Cost Studies» 3rd Party Elevator/Environment Rm. Evals.» De-Bundling Cost Estimate
40 HE RESULTS BASE CASE» Code/ADA Upgrades» Hazmat Remediation» Replace Outdated MEP Infrastructure Equipment» New roof, exterior repair, re-glaze failing/unsightly windows/skylights» Build on upper floors to reduce future renovation disruption» Add toilet fixtures to accommodate anticipated population» Extend Fire protection» Replace floor, ceilings and lighting fixtures» Modify corridor installation of interior Tech Center Refurbish elevator ADA controls» Electrostatically paint casework
41 REPLACE OUTDATED MEP INFRASTRUCTURE EQUIPMENT
42 NEW ROOF, EXTERIOR REPAIR, RE-GLAZE FAILING/UNSIGHTLY WINDOWS/SKYLIGHTS
43 MODIFY CORRIDOR FOR INSTALLATION OF INTERIOR GLASS TECH CENTER SPACE
44 ELECTROSTATICALLY PAINT CASEWORK
45 HE RESULTS OPTIONS» Add amenity spaces (i.e. pantries)» Upgrade Elevator Finishes» Additional plumbing fixtures» Renovate restrooms» Replace casework» Replace casework tops and hardware» New MEP mains/distribution» New utility mains» Chilled Beams for offices» Interior windows to labs / offices» Refurbish environmental rooms» New Penthouse
46 INTERIOR WINDOWS TO LABS / OFFICES
47 REFURBISH ENVIRONMENTAL ROOMS
48 NEW PENTHOUSE
49 REUSE / REPURPOSE SHOULDN T COMPROMISE SUSTAINABILITY» Replace constant volume air system» Retrofit fumehoods» Energy Recovery Systems» VGDD for exhaust» AHU Economizers» Chilled beams» 100% Automatic lighting control» Integrated lighting and thermal controls» Daylight harvesting» Increased daylight views
50 BEFORE AND AFTER OFFICE
51 BEFORE AND AFTER CORRIDOR
52 BEFORE AND AFTER CORRIDOR
53 BEFORE AND AFTER OPEN LABORATORY FUMEHOOD AREA
54 BEFORE AND AFTER ENVIRONMENTAL ROOM
55 BEFORE AND AFTER CORE SPACES
56 BEFORE AND AFTER OPEN LABORATORY LOOKING TO CENTER OF BUILDING
57 BEFORE AND AFTER OPEN LABORATORY LOOKING TO EXTERIOR
58 BEFORE AND AFTER OPEN LABORATORY MAIN AISLE
59 WAS IT A SUCCESSFUL RE-PURPOSE?» Was it completed in a timely manner?» Was it within budget?» Is the building sustainable for the next 20 years?» Is the building flexible for the foreseeable future?» Was it worth it?
60 UNIVERSITY RESULTS» Highly efficient valuable asset» Annual energy reduction 67% improvement (University Goal - 30%)» Annual fumehood energy savings $3.8K to $7.6K (80/60 FPM)» Increased daylight views for 100% of regularly occupied spaces
61 USER RESULTS» Enticing» State of the art purpose built design» Collaborative space = idea exchange» Recruitment showcase» Created a knowledge center It was worth the move.wouldn t go back
62 TRADELINE THREE» Repurpose with a Purpose» Lessons Learned Matter; if you don t have them find them» Everything is on the table; the best strategy comes from considering all options
TEXAS A&M ENGINEERING
TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas
More informationMANHATTAN COLLEGE STUDENT COMMONS
MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017
FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationLEWIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using
More informationTechnical Facility Management FACILITY CONSULTING SERVICES. The Facility Audit Program
Technical Facility Management FACILITY CONSULTING SERVICES The Facility Audit Program TFM Audit Program - Schedule Customer: Dates of Visit: AREA TFM CUSTOMER SUBJECT Goals/Objectives Schedule Key Interviews
More informationCENTENNIAL SCHOOL DISTRICT
CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites
More informationDLR Group is ranked #1 by ARCHITECT, the official publication of the American Institute of Architects, in its 2012 ARCHITECT 50 ranking of U.S.
DLR Group is ranked #1 by ARCHITECT, the official publication of the American Institute of Architects, in its 2012 ARCHITECT 50 ranking of U.S. firms. This ranking is based on design excellence (reflected
More informationRATIONALE AND REASONING
RATIONALE AND REASONING Background The main tenant residing in BMH is the Anthropology Department. Most of the building systems constructed in the building are over forty years old and are at the end of
More informationFacility Assessment Report, Montgomery Independent School District
NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2
More informationElement Z General Design Requirements Existing Facilities Information
Anderson Central 100B, PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G
More informationDESIGN AND CONSTRUCTION STANDARDS. Section 2: Standards for Specific Categories of Work. Laboratory Standards
Laboratory Standards These criteria include general planning guidelines. They are intended for use of Designers during the design phases of the project. Planning Assumptions Overview In order to maximize
More informationBSL: Building Codes, Sustainability, and Structural Systems (RV-10632)
BSL: Building Codes, Sustainability, and Structural Systems (RV-10632) Building Codes Codes and Regulations The building design of a nursing home can be required to comply with the basic mandates of all
More informationCornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits
Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits 1 Cornell Rolling Counter Fire Doors Earning LEED v4 Credits Cornell Rolling Counter Fire Doors can provide a significant
More informationChilled Beams. The new system of choice?
Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams
More informationBuilding Code 8 th Edition
Massachusetts State Building Code 8 th Edition Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com RW R.W. Sullivan Engineering
More informationCase Study: Element PROJECT DESCRIPTION
Case Study: Element PROJECT DESCRIPTION Project type: Project gross SF: Number of keys: Location: Hotel (Hospitality), extended-stay prototype Varies, prototypical SF: 79,035 SF gross Varies, prototypical:
More informationSchool Without Walls
INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationRetrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E.
Retrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E. Degenkolb Engineers MCEER 2006 Annual Meeting Diagnostic & Treatment Building Designed
More informationCode Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617)
Code Requirements for Existing Buildings R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS) was established in 1945 and currently
More informationLECKIE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationCompleted projects. Projects in progress. Program developments
1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site
More information2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES)
2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of Project: Address:
More informationAnalysis 1. LEED Analysis of Laboratory Buildings. Penn State School of Forest Resources University Park, PA
Analysis 1 LEED Analysis of Laboratory Buildings Background The LEED program (Leadership in Energy and Environmental Design) established by the U.S. Green Building Council is becoming the standard by which
More informationApplying the Building Code During Design
Applying the Building Code During Design A Step-By-Step Process AIA Learning Units The Salt Lake City CSI Chapter is a Registered Provider with The American Institute of Architects Continuing Education
More informationThermiser Insulated Rolling Doors Comprehensive Guide to Earning LEED v4 Credits
Thermiser Insulated Rolling Doors Comprehensive Guide to Earning LEED v4 Credits 1 Thermiser Insulated Rolling Doors Earning LEED v4 Credits Cookson s Thermiser Insulated Rolling Doors can provide a significant
More informationSECTION ALTERNATES
SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationUSGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit
USGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit Jeffrey Salay, PE, CEM, LEED AP Senior Principal 13 December 2017 GHT Limited is a
More informationJMU Capital Projects SWaM Outreach Event Presentations
JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom
More informationVelma F Thomas Early Childhood Center
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationLASALLE - BACKUS EDUCATION CAMPUS
INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationChapel House- Design Process- Envelope and Energy savings
Colgate - Chapel House Renovation Heating Energy - Summary rev. 9/23/16 With Actual Blower Door Assembly R-Values Other Loads DORMITORY Stone Wall Window Spandrel Sill/Band Slab Edge (below grade) Roof
More informationINSPIRE each student to develop a strong
DEL PASO MANOR ELEMENTARY SCHOOL Valuing a culturally and academically DIVERSE COMMUNITY, Del Paso Manor Elementary School s Mission is to EDUCATE and INSPIRE each student to develop a strong A C A D E
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationBRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING
PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING
More informationEJ Industrial Spine BOA Nomination Study
A. Selecting Priority Sites Section V. Redevelopment of Priority Sites Section IV of this Nomination Study presents a summary of the analyses of the Study Area and market conditions affecting the E-J BOA
More informationKAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner
KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner McLean, Virginia Brooke Helgesen Advisor: Dr. Chimay Anumba Construction Management PRESENTATION OUTLINE Cost/ Schedule Impact KAISER PERMANENTE
More informationSalt lake city Public Safety Building. Case Study CS 2. Grounded in strength.
Salt lake city Public Safety Building CS 2 Case Study Grounded in strength. Forterra Structural & Specialty Products High-Efficiency Design, Precast Envelope System Put Dramatic Public Safety Building
More informationEnergy Trigger (A Existing Building Upgrade Mechanism Model)
Trigger (A-11.2.1.2 Existing Building Upgrade Mechanism Model) Applicability All Building Permit applications for projects related to existing buildings are required to follow the energy upgrade trigger
More informationOn Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)
TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED
More informationCITY OF NOVI. Police Department
CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master
More informationThe parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.
EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building
More informationCheldelin Middle School
Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:
More informationSTRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225
GENERAL NOTES DESIGN NOTES (CONTINUED) FOUNDATION NOTES STRUCTURAL ABBREVIATIONS CONCRETE MASONRY NOTES DESIGN NOTES S-001 CONCRETE NOTES COLD-FORMED STEEL FRAMING NOTES PRE-ENGINEERED METAL BUILDING NOTES
More informationRe: College of Lake County: AB Wing HVAC Remodeling Programming Mtg #3 Architect s Project Number: Meeting Minutes
March 6, 204 VIA Email College of Lake County 935 West Washington Street Grayslake, Illinois 60030 Re: College of Lake County: AB Wing HVAC Remodeling Programming Mtg #3 Architect s Project Number: 2406.00
More informationUNIVERSITY OF NORTH CAROLINA PEMBROKE
PROGRAM FOR RENOVATIONS AND ADDITIONS 30 June 2011 B A Livermore Library Renovations C B GPAC Additions & Renovations F A D C Business Education Renovations D D.F. Lowry Renovations E Old Main Renovations
More informationWhat is NUFORM HOUSE KIT?
Introduction Nuform Building Technologies Inc. (NUFORM ) is creating a better way to deliver affordable housing the NUFORM HOUSE KIT is a solution for creating neighborhoods where people live with pride
More informationMadison School District. Strategic Five-Year Facility Maintenance Plan
Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since
More informationDivision 09 FINISHES TABLE OF CONTENTS
Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING
More informationTotal Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet
FLANDERS ELEMENTARY SCHOOL Located at 167 Boston Post Road, East Lyme, Connecticut the school s original structure was built in 1964 and replaced the Central Office Building as the elementary school. Two
More information- DATA REQUIREMENTS BIM
UHS BIM Protocol S E C T I O N 1 - DATA REQUIREMENTS BIM authoring software: The design team is required to use parametric BIM authoring software for creation of models that include all geometry, physical
More informationEnergy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort
Please add relevant logo here Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Presented by: Peter J. Arsenault, FAIA, NCARB, LEED-AP Disclaimer: This presentation was developed by
More informationSIDEWALK & RAILING REPLACEMENT BOARD OF ED BUILDING
PROJECT: 25 E 5 S SALT LAKE CITY, UTAH 84111 CODE ANALYSIS APPLICABLE CODES 675 E. 5 S. Suite 4 DFCM PROJECT NUMBER: 182782 DFCM CONTRACT NUMBER: 18793 STRUCTURAL ENGINEER: REAVELEY ENGINEERS + ASSOCIATES
More informationManufacturing Facilities Proposal
Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business
More informationOffice of Planning, Design and Construction. Capital Program Update May 10, 2017
Office of Planning, Design and Construction Capital Program Update May 10, 2017 Projects Under Construction Translational Research Center Translational Research Center Phase I Site work Status: Completed
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationUAA Science Renovation Phase 2 Narrative EXISTING BUILDING SITE
UAA Science Renovation Phase 2 Narrative A EXISTING BUILDING SITE The existing building is situated along the campus spine and connected by elevated walkways to the engineering building toward the west
More informationCWA C W A S S O C I A T E S, P L L C. O c cwa copyright
Construction After BOGGS BUILDING RESTORATION Steamboat Springs, CO Exterior Storefront and Interior Renovation of a Historic Old Town Steamboat Commercial Building, Divided into Commercial Condos with
More informationIconography. KAPSARC Mosque
Iconography As node and center of the KAPSARC residential community, the mosque creates an iconic and contemplative space of worship, reflection and repose. A unique and contemporary space, the design
More informationItalcementi Center for Research and Innovation
Italcementi Center for Research and Innovation Bergamo, Italy LEED-NC v2.1 EAc1 A. Project Narrative (Viridian) analyzed the energy use of the proposed Italcementi Center for Research and Innovation located
More informationSTRUCTURAL CONDITION ASSESSMENT
STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,
More informationUniversity of Wisconsin La Crosse Science Lab Building DFD# 13B3H / RA# 1290.A December 3, 2014
SCHEMATIC DESIGN REVIEW MEETING NO. 3 / DECEMBER 3, 2014 MEETING START TIME: MEETING END TIME: 2:00 p.m. 5:00 p.m. PRESENT: Beth Alderman Division of Facilities Development Val Schute River Architects
More informationHQ Building Renovation. Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO
HQ Building Renovation Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO Agenda Roll Call Introduction Presentation of Design Concepts and Cost Estimate Financing Options and Recommendation
More informationLEED Analysis of the Knight Management Center. Energy & Atmosphere. Materials & Resources
LEED of the Knight Management Center Energy & Atmosphere Materials & Resources Energy & Atmosphere: 17 possible points LEED-NC Scorecard LEED for New Construction v2.2 Registered Project Checklist Project
More informationA Summary of the Four Options Under Consideration for Colorado State University s Football Stadium
A Summary of the Four Options Under Consideration for Colorado State University s Football Stadium October 2014 Preamble This summary booklet is provided by Colorado State University to enable decision
More informationHow to estimate the cost of new air conditioning system to an existing storage warehouse.
How to estimate the cost of new air conditioning system to an existing storage warehouse. 1 How to estimate the cost of new air conditioning system to an existing storage warehouse. Table of Contents Section
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationCivil Engineering & Architecture PLTW Scope and Sequence Year at a Glance First Semester Three Weeks
Civil Engineering & Architecture PLTW Scope and Sequence Year at a Glance First Semester Three Weeks 1 st 3 weeks 2 nd 3 weeks 3 rd 3 weeks 4 th 3 weeks 5 th 3 weeks 6 th 3 weeks Topics/ Concepts I. Overview
More informationLEED v4 Building Design and Construction Quiz #8 EQ
LEED v4 Building Design and Construction Quiz #8 EQ 1. Which of these is considered an unoccupied space? [Choose three] A. School classroom B. Mechanical room C. Meeting room D. Locker room E. Restroom
More informationModular Wood Framing Goes Vertical
Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported
More informationMargaret Batts Tobin Laboratory
Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of
More informationLEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies
MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules
More informationMinnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017
Minnesota Healthcare Engineers Association, Fall Conference Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Categories of Rehabilitation Work in Healthcare Facilities Bob Dehler, P.E. robert.dehler@state.mn.us
More informationRow House Henz-Noirfalise in Eupen, Belgium
Row House Henz-Noirfalise in Eupen, Belgium PROJECT SUMMARY Transforming a 19th century row house into a Passive House SPECIAL FEATURES Inside insulation of the facade ARCHITECT Fhw architectes scprl www.fhw.be
More information45% 39% 17% 92% 100% All paints and adhesives are low VOC
HGSE LONGFELLOW HALL RENOVATION LEED CI-2009 13 APPIAN WAY CAMBRIDGE, MA 02138 LEED PLATINUM PROJECT PROFILE The Harvard Graduate School of Education (HGSE) made significant upgrades to Longfellow Hall
More informationTECHNICAL ASSIGNMENT 2
PENN STATE AE SENIOR THESIS 2011-2012 TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis BRIANNE KYLE Construction Management Thesis Advisor: Dr. Chimay
More informationTable of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8
WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2
More informationCode Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617)
Code Requirements for Existing Buildings R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS) was established in 1945 and currently
More informationHIGHLANDVIEW CEMETERY CHAPEL
HIGHLANDVIEW CEMETERY CHAPEL CONTACT: Ferris State University Small Town Studio Christopher Cosper, AIA, LEED, AP, Assistant Professor cosperc@ferris.edu 23.59.33 Sheet List Sheet Name Sheet # COVER A00
More informationINOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:
INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win
More informationFDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider
Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor
More informationMueller Laboratory Renovation
Mueller Laboratory Renovation Technical Report #1 By Mark Jackson Construction Management Option 9/19/14 Executive Summary The Mueller Laboratory building on the Penn State University Park campus was built
More informationBuilding Inspection Report
Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941
More informationHERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW
HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com
More informationThermal Bridging and Whole Building Energy Performance
Thermal Bridging and Whole Building Energy Performance Steve Murray, P.Eng. PMP Morrison Hershfield May 8 & 9, 2013 1 Acknowledgments The real work for ASHRAE 1365 RP was done by others in MH s Vancouver
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationLEED LEED. Leadership in Energy and Environmental Design. A voluntary, consensus-based. high-performance, sustainable buildings and neighborhoods
LEED An Introduction to LEED V3 2009 LEED Leadership in Energy and Environmental Design A voluntary, consensus-based national standard for developing high-performance, sustainable buildings and neighborhoods
More informationSubject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3
MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape
More informationTate Laboratory of Physics Building Analysis
Tate Laboratory of Physics Building Analysis Adam Lapacz, Andrew Olson, Daniel Greuel, Indira Manandhar, Kyle Snyder, Mark Kelly, Molly McClung, Stefanie Perez, Tony Palmer Built: 1927 Located: East Bank
More informationInvolving Stakeholders in the Professional s Design and Construction Process
Involving Stakeholders in the Professional s Design and Construction Process Presented By: Peter Trozze, AIA Managing Director of Middle Eastern Operations Continuing Education The Middle East Chapter
More informationVFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT)
VFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT) I. Purpose As part of a strategic planning directive, the has decided to undertake a comprehensive condition audit and plant capital renewal
More informationBronx Mental Health Redevelopment Project
Bronx Mental Health Redevelopment Project Residential Village Bronx Campus Transitional Living Residences, Haven House Horizon House, and Studio Apartments BIM Orientation December 20, 2012 1 Bronx Mental
More informationPearl River Tower. Guangzhou, China. AEI Professional Project Awards January 2014 PHOTO CREDIT: TIM GRIFFITH
Pearl River Tower Guangzhou, China AEI Professional Project Awards January 2014 PHOTO CREDIT: TIM GRIFFITH Pearl River Tower The 71-story (309m) Pearl River Tower (PRT) redefines what is possible in sustainable
More informationPRESENTATION CENTER SURREY, BC CANADA
PRESENTATION CENTER SURREY, BC CANADA 1 VIEW OF THE PROPOSED OPTIMA 3 TOWERS (AFTER OBTAINING THE HIGH DENSITY THAT IS UNDER STUDY) ALONG WEST WHALLEY RING ROAD 2 3 IHI WILL BUILD THE OPTIMA PRESENTATION
More informationEdouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com
Edouard Modern Living Made Easy uichomes.com - new construction - 3 stories + full basement - 4 bedrooms - 2.5 baths - 2,380 s.f. call 314.881.2333 or e-mail sales@uicstl.com PLAN NTS DECK 13' 0" X 12'-0"
More informationArchitectural Services
Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District
More informationFA R-0014 FTEV , Alter Area for 19 SOS Sim Parts Storage Bldg Questions & Answers
FA4417-17-R-0014 FTEV 16-1177, Alter Area for 19 SOS Sim Parts Storage Bldg. 90710 Questions & Answers Question 1 Please clarify the extents of removal of pipe with asbestos containing insulation shown
More information