The World Bank Vietnam Renewable Energy Development Project (P103238)

Size: px
Start display at page:

Download "The World Bank Vietnam Renewable Energy Development Project (P103238)"

Transcription

1 Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 15 ARCHIVED on 14-Feb-2018 ISR29615 Implementing Agencies: Ministry of Industry and Trade, The Renewable Energy Dv Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:05-May-2009 Planned Mid Term Review Date:03-Dec-2012 Original Closing Date:30-Jun-2014 Project Development Objectives Effectiveness Date:14-Sep-2009 Actual Mid-Term Review Date:26-Nov-2012 Revised Closing Date:30-Jun-2018 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The objective of the proposed project is to increase the supply of electricity to the national grid from renewable energy sources on a commercially, environmentally and socially sustainable basis. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Renewable Energy Investments - IDA funds:(cost $ M) Public Disclosure Authorized Regulatory Development:(Cost $1.03 M) Pipeline Development:(Cost $3.35 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions 2/14/2018 Page 1 of 9

2 As of January 15, 2018, the project has fully achieved and exceeded two main development objective indicators: (i) 960 GWh/year of renewable electricity supplied to the grid; and (ii) 5.1 GWh/year of electricity supplied to the grid by grid-connected renewables projects using avoided cost tariff (ACT). Nineteen subprojects have been approved under REDP providing an estimated amount of 1,250 GWh renewable electricity annually to the grid under REDP and exceeding the PDO target of 960 GWh/year. Among them, 14 subprojects have been completed with total capacity of MW, 960 GWh/year. The five remaining subprojects are in progress to be completed in 2018 and early 2019; most of the proposed activities under SECO grant have been completed by the Grant closing date (June 30, 2017). MOIT will use the IDA credit to complete three ongoing and new activities, and seek other grant sources to implement remaining tasks; (iii) Carbon Partnership Facilities (CPF) progressed satisfactorily. The fifth verification is expected to be conduction in March The IDA credit amount has been fully committed. The cumulative IDA disbursement was US$146.5 million (74%). The figure for the SECO Grant was US$1.524 million (67%) and an unused amount of US$ 822,243 has been returned to SECO. CPF disbursement was US$ 0.53 million or 6% of CPF fund. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Moderate Moderate Fiduciary -- Moderate Moderate Environment and Social -- Moderate Substantial Stakeholders -- Moderate Moderate Other Overall -- Moderate Moderate Results Project Development Objective Indicators PHINDPDOTBL Electricity supplied to the national grid by renewable energy project financed under REDP (Gigawatt-hour (GWh), Custom) Date 31-Dec Jun Dec Dec /14/2018 Page 2 of 9

3 PHINDPDOTBL Electricity supplied to the national grid by grid connected renewable energy projects using Avoided Cost Tariff (Gigawatt-hour (GWh), Custom) , , , Date 31-Dec Jun Dec Jun-2018 PHINDPDOTBL Percentage renewable energy projects (small hydro) meeting new environment and social best practices (Percentage, Custom) Overall Comments Intermediate Results Indicators Renewable energy capacity installed under REDP (Megawatt, Custom) Date 31-Dec Jun Dec Jun /14/2018 Page 3 of 9

4 Generation Capacity of Hydropower constructed or rehabilitated under the project (Megawatt, Custom) Generation Capacity of Hydropower constructed under the project (Megawatt, Custom Breakdown) Date 05-May Jun Jan Jun-2018 Renewable energy capacity financed using ACT by non IDA sources (Megawatt, Custom) , Date 31-Dec Jun Dec Jun-2018 Proportion of commissioned subprojects under REDP meeting appraised budget, timetable and performance (Percentage, Custom) /14/2018 Page 4 of 9

5 Law on Energy Conservation (Text, Custom) Under preparation Passed Passed Passed Renewable Energy Deverlopment Stratery (Text, Custom) Not in place Approved Approved Approved Adoption of technical standards for small hydro (Text, Custom) Not in place Technical standard for small hydro adopted Technical standard for small hydro adopted Technical standard for small hydro adopted Environmental guideline for small hydro (Text, Custom) Not in place Approved and launched Approved and launched Issued at the MTR and implemented at ICR 2/14/2018 Page 5 of 9

6 Social guideline for small hydro (Text, Custom) Not in place Approved and launched Approved and launched Issued at the MTR and implemented at ICR Annual updating of the ACT (Text, Custom) Approved Updated for 2009, 2010, 201, 2012, 2013, 2014, 2015, 2016 and New circular on ACT has been issued Updated for 2009, 2010, 201, 2012, 2013, 2014, 2015, 2016 and New circular on ACT has been issued Implemented Number of SPPAs signed for grid-connected renewables (Number, Custom) Date 05-May Jun Jan Jun-2018 National Renewable Energy Database (Text, Custom) No national renewable energy database is available Under preparation Under preparation A national renewable energy database is developed Date 30-Jun Jun Dec Jun /14/2018 Page 6 of 9

7 Capacity of pipeline of RE subprojects supported by the facility (Megawatt, Custom) Number of improved/new training courses offered on a cost-sharing basis (Number, Custom) Number of trainees from banks and sponsors (Number, Custom) Study on financing needs for pipeline of renewable energy projects (Text, Custom) None Completed Completed Completed Overall Comments 2/14/2018 Page 7 of 9

8 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P IDA Effective USD % P TF Closed USD % Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P IDA Effective 05-May Jun Sep Jun Jun-2018 P TF Closed 20-Dec Apr Apr Jun Jun-2017 Cumulative Disbursements Restructuring History Level Approved on 02-Jul-2014,Level 2 Approved on 30-Jun /14/2018 Page 8 of 9

9 Related Project(s) P Vietnam Renewable Energy Development Project 2/14/2018 Page 9 of 9

The World Bank AO-Market Oriented Smallholder Agriculture Project (P093699)

The World Bank AO-Market Oriented Smallholder Agriculture Project (P093699) Public Disclosure Authorized AFRICA Angola Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 06-Nov-2015 ISR21246 Implementing Agencies: Ministry of Agriculture

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy EUROPE AND CENTRAL ASIA Croatia Water Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 15 ARCHIVED on 24-Dec-2015 ISR22041 Implementing

More information

Public Disclosure Copy. Implementation Status & Results Report Indonesia: Scholarships Prog. for Strengthening Reforming Institutions (P118150)

Public Disclosure Copy. Implementation Status & Results Report Indonesia: Scholarships Prog. for Strengthening Reforming Institutions (P118150) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Governance Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 9 ARCHIVED on 05-Jan-2016 ISR22346 Implementing Agencies: BAPPENAS,

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 13 ARCHIVED on 17-Jun-2015 ISR19767 Implementing Agencies: Hanoi Urban

More information

Public Disclosure Copy. Implementation Status & Results Report Indonesia: Scholarships Prog. for Strengthening Reforming Institutions (P118150)

Public Disclosure Copy. Implementation Status & Results Report Indonesia: Scholarships Prog. for Strengthening Reforming Institutions (P118150) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Public Sector Governance Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 8 ARCHIVED on 22-May-2015 ISR18498 Implementing Agencies:

More information

The World Bank Stormwater Mgt. and Climate Change Adaptation Project (P122841)

The World Bank Stormwater Mgt. and Climate Change Adaptation Project (P122841) Public Disclosure Authorized AFRICA Senegal Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 9 ARCHIVED on 30-Jun-2017 ISR26846 Implementing

More information

The World Bank Stormwater Mgt. and Climate Change Adaptation Project (P122841)

The World Bank Stormwater Mgt. and Climate Change Adaptation Project (P122841) Public Disclosure Authorized AFRICA Senegal Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 10 ARCHIVED on 26-Dec-2017 ISR30717

More information

INDONESIA: IMPROVING TEACHER PERFORMANCE AND ACCOUNTABILITY (KIAT GURU)

INDONESIA: IMPROVING TEACHER PERFORMANCE AND ACCOUNTABILITY (KIAT GURU) Public Disclosure Authorized INDONESIA: IMPROVING TEACHER PERFORMANCE AND ACCOUNTABILITY (KIAT GURU) (P159191) EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Malawi Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 14 ARCHIVED on 30-Jun-2016 ISR23059 Implementing Agencies:

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Malawi Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 13 ARCHIVED on 04-Nov-2015 ISR21002 Implementing Agencies:

More information

The World Bank KI: Telecommunications and ICT Development Project (P126324)

The World Bank KI: Telecommunications and ICT Development Project (P126324) Public Disclosure Authorized EAST ASIA AND PACIFIC Kiribati Transport & ICT Global Practice IBRD/IDA Technical Assistance Loan FY 2013 Seq No: 7 ARCHIVED on 15-Jun-2016 ISR23726 Implementing Agencies:

More information

Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916)

Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916) Operation Name: WAPP APL 2 - OMVS

More information

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions The World Bank LATIN AMERICA AND CARIBBEAN Chile Governance Global Practice Institutional Development Fund FY 2013 Seq No: 3 ARCHIVED on 13-Nov-2015 ISR21160 Implementing Agencies: Dirección Nacional de

More information

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199)

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Operation

More information

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199)

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Operation

More information

Name Previous Rating Current Rating

Name Previous Rating Current Rating Public Disclosure Authorized Public Disclosure Copy MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Environment & Natural Resources Global Practice Global Environment Project Investment Project Financing

More information

Implementation Status & Results Indonesia ID-Urban Water Supply and Sanitation (P090991)

Implementation Status & Results Indonesia ID-Urban Water Supply and Sanitation (P090991) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia ID-Urban Water Supply and Sanitation (P090991) Operation Name: ID-Urban Water Supply and

More information

The World Bank Sustainable Land Management Project (P133133)

The World Bank Sustainable Land Management Project (P133133) Public Disclosure Authorized AFRICA Ethiopia Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 9 ARCHIVED on 04-Dec-2017 ISR28418 Implementing Agencies:

More information

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199)

Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Pelotas - Rio Grande do Sul Integrated Municipal Development Program (APL) (P094199) Operation

More information

Implementation Status & Results Indonesia Geothermal Power Generation Development (P099757)

Implementation Status & Results Indonesia Geothermal Power Generation Development (P099757) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Geothermal Power Generation Development

More information

Implementation Status & Results Iraq IQ-TF EMERG. WATER, SANITATION & URBAN (P087910)

Implementation Status & Results Iraq IQ-TF EMERG. WATER, SANITATION & URBAN (P087910) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Iraq IQ-TF EMERG. WATER, SANITATION & URBAN (P087910) Operation Name: IQ-TF EMERG. WATER, SANITATION

More information

Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460)

Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460) Operation Name: Bahia Integrated

More information

Implementation Status & Results Africa Central African Backbone - APL2 (P117652)

Implementation Status & Results Africa Central African Backbone - APL2 (P117652) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa Central African Backbone - APL2 (P117652) Operation Name: Central African Backbone - APL2

More information

Implementation Status & Results Indonesia Barefoot Engineers III (P131387)

Implementation Status & Results Indonesia Barefoot Engineers III (P131387) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Barefoot Engineers III (P131387) Operation

More information

Implementation Status & Results Cameroon Agricultural Competitiveness Project (P112635)

Implementation Status & Results Cameroon Agricultural Competitiveness Project (P112635) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Cameroon Agricultural Competitiveness Project (P112635) o C Operation

More information

Implementation Status & Results Africa NELSAP Regional Agricultural Trade and Productivity TA (Phase II) (P115414)

Implementation Status & Results Africa NELSAP Regional Agricultural Trade and Productivity TA (Phase II) (P115414) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa NELSAP Regional Agricultural Trade and Productivity TA (Phase II) (P115414) Operation Name:

More information

Implementation Status & Results Indonesia Western Indonesia National Roads Improvement Project (P090990)

Implementation Status & Results Indonesia Western Indonesia National Roads Improvement Project (P090990) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Western Indonesia National Roads Improvement Project (P090990) Operation Name: Western

More information

Implementation Status & Results Indonesia ID-Domestic Gas Market Development Project (P077175)

Implementation Status & Results Indonesia ID-Domestic Gas Market Development Project (P077175) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia ID-Domestic Gas Market Development Project

More information

Public Disclosure Copy. Public Disclosure Copy. The World Bank

Public Disclosure Copy. Public Disclosure Copy. The World Bank Public Disclosure Authorized Public Disclosure Authorized losure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Rio de Janeiro Sustainable Integrated Ecosystem

More information

Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

More information

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871)

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Vietnam Second Transmission and Distribution Project

More information

Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046)

Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046) Operation Name: Second Agricultural Technology

More information

Implementation Status & Results Chile Ministry of Public Works Institutional Strengthening TAL (P102931)

Implementation Status & Results Chile Ministry of Public Works Institutional Strengthening TAL (P102931) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Chile Ministry of Public Works Institutional Strengthening TAL (P102931) Operation Name: Ministry

More information

Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021)

Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021) Operation Name: Andhra Pradesh Road Sector Project

More information

Implementation Status & Results India Rajasthan Rural Livelihoods Project (RRLP) (P102329)

Implementation Status & Results India Rajasthan Rural Livelihoods Project (RRLP) (P102329) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results India Rajasthan Rural Livelihoods Project (RRLP) (P102329) Operation Name: Rajasthan Rural Livelihoods

More information

Implementation Status & Results Brazil Rio de Janeiro Mass Transit Project II (P111996)

Implementation Status & Results Brazil Rio de Janeiro Mass Transit Project II (P111996) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Rio de Janeiro Mass Transit Project II (P111996) Operation Name: Rio de Janeiro Mass Transit

More information

Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021)

Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results India Andhra Pradesh Road Sector Project (P096021) Operation Name: Andhra Pradesh Road Sector Project

More information

Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460)

Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Bahia Integrated State Highway Management Project (P095460) Operation Name: Bahia Integrated

More information

Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046)

Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Nicaragua Second Agricultural Technology Project (P087046) Operation Name: Second Agricultural Technology

More information

Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112)

Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112) Operation Name: QUALITY PROTECT (GEF) (P085112)

More information

Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Montenegro Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

More information

Implementation Status & Results Brazil Energy Sector Technical Assistance Project (P076977)

Implementation Status & Results Brazil Energy Sector Technical Assistance Project (P076977) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Energy Sector Technical Assistance Project (P076977) Operation Name: Energy Sector Technical

More information

Implementation Status & Results Brazil Sustainable Cerrado Initiative (P091827)

Implementation Status & Results Brazil Sustainable Cerrado Initiative (P091827) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Sustainable Cerrado Initiative (P091827) Operation Name: Sustainable Cerrado Initiative (P091827)

More information

Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources Management (P089929)

Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources Management (P089929) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources

More information

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715)

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Operation

More information

Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112)

Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Bosnia and Herzegovina QUALITY PROTECT (GEF) (P085112) Operation Name: QUALITY PROTECT (GEF) (P085112)

More information

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715)

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Operation

More information

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715)

Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil National Biodiversity Mainstreaming and Institutional Consolidation Project (P094715) Operation

More information

Implementation Status & Results Benin Benin Emergency Urban Env. Project (P113145)

Implementation Status & Results Benin Benin Emergency Urban Env. Project (P113145) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Benin Benin Emergency Urban Env. Project (P113145) Operation Name: Benin Emergency Urban Env. Project

More information

The World Bank Pernambuco Rural Economic Inclusion (P120139)

The World Bank Pernambuco Rural Economic Inclusion (P120139) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PERNAMBUCO RURAL ECONOMIC INCLUSION APPROVED ON MARCH 6, 2012 TO STATE

More information

Implementation Status & Results Brazil BR GEF Rio Grande do Sul Biodiversity (P086341)

Implementation Status & Results Brazil BR GEF Rio Grande do Sul Biodiversity (P086341) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil BR GEF Rio Grande do Sul Biodiversity (P86341) o C Operation

More information

The World Bank. Key Dates. Project Development Objectives. Component(s) Public Disclosure Copy Overall Ratings

The World Bank. Key Dates. Project Development Objectives. Component(s) Public Disclosure Copy Overall Ratings Implementation Status & Results Benin Benin Emergency Urban Env. Project (P113145) Operation Name: Benin Emergency Urban Env. Project (P113145) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED

More information

Implementation Status & Results Report Coastal Watersheds Conservation in the Context of Climate Change Project (P131709)

Implementation Status & Results Report Coastal Watersheds Conservation in the Context of Climate Change Project (P131709) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Mexico Environment & Natural Resources Global Practice Global Environment Project Investment Project Financing FY 2014 Seq No: 9 ARCHIVED on 30-Oct-2017

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING SUSTAINABLE PROD. IN AREAS PREVIOUSLY CONVERTED TO AGRICULTURAL USE APPROVED ON JULY 18, 2014

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING SUSTAINABLE PROD. IN AREAS PREVIOUSLY CONVERTED TO AGRICULTURAL USE APPROVED ON JULY 18, 2014 Public Disclosure Authorized The World Bank REPORT NO.: RES27088 Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF Public Disclosure Authorized SUSTAINABLE PROD. IN

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-42150,IDA-42160,IDA-42170,IDA-46450,IDA- 30-Jun ,000,000.

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-42150,IDA-42160,IDA-42170,IDA-46450,IDA- 30-Jun ,000,000. Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020037 Public Disclosure Authorized Public Disclosure Authorized Project ID P094916 Project Name 3A-WAPP

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA TF-51229) ON A

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA TF-51229) ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2603 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

Thailand Power Development Plan ( ) TANONGSAK WONGLA

Thailand Power Development Plan ( ) TANONGSAK WONGLA Thailand Power Development Plan (2010-2030) TANONGSAK WONGLA August 2013 GOV. POLICY Structure of Thailand Power Sector Regulators EGAT (44%) IPPs (38%) Imports (7%) SPPs (10%) VSPPs (

More information

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS Edwin Castro CNEE Guatemala Viena, september 2009 What is the reason to develop this model? In our own electricity market

More information

The World Bank Ethiopia: Supporting Open Data Initiative (P156400)

The World Bank Ethiopia: Supporting Open Data Initiative (P156400) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF ETHIOPIA: SUPPORTING OPEN DATA INITIATIVE APPROVED ON OCTOBER 15, 2015

More information

Financial Results of PGNiG SA Q August 13th 2008

Financial Results of PGNiG SA Q August 13th 2008 Financial Results of PGNiG SA 28 August 13th 28 Financial Highlights PGNiG Group (PLN m) 27 28 change Sales revenue 3,392 3,929 16% EBIT 412 294 (29%) EBITDA 785 665 (15%) Net profit 326 28 (14%) Net margin

More information

SREP Operational and Results Report TITLE SLIDE. DATE December 14, 2017 PLACE Washington, DC VENUE SREP Sub-Committee Meeting

SREP Operational and Results Report TITLE SLIDE. DATE December 14, 2017 PLACE Washington, DC VENUE SREP Sub-Committee Meeting SREP Operational and Results Report TITLE SLIDE DATE December 14, 2017 PLACE Washington, DC VENUE SREP Sub-Committee Meeting SREP Countries Africa Benin Ethiopia Ghana Kenya Lesotho Liberia Madagascar

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

Completion Report. People s Republic of China: Hebei Zhanghewan Pumped Storage Project. Project Number: Loan Number: 1922 August 2014

Completion Report. People s Republic of China: Hebei Zhanghewan Pumped Storage Project. Project Number: Loan Number: 1922 August 2014 Completion Report Project Number: 28212 Loan Number: 1922 August 2014 People s Republic of China: Hebei Zhanghewan Pumped Storage Project This document is being disclosed to the public in accordance with

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Sep ,000, Original Commitment 550,000,

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Sep ,000, Original Commitment 550,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020046 Public Disclosure Authorized Operation ID P132768 Country Brazil Operation Name BR-Pernambuco

More information

Evolution of SWIFT pricing. September 2015

Evolution of SWIFT pricing. September 2015 Evolution of SWIFT pricing September 2015 Learn more about the evolution of SWIFT's pricing over the past years, and plans to continue to evolve pricing in the context of SWIFT2020 2 SWIFT s pricing initiatives

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22361 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA South Asia Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2011 Seq No: 14 ARCHIVED on 14-Dec-2016 ISR25669 Implementing Agencies:

More information

Japan s Assistance for the Reconstruction of Iraq

Japan s Assistance for the Reconstruction of Iraq Japan s Assistance for the Reconstruction of Iraq - Contents - I. Overview II. Reconstruction Assistance by Japan s Self-Defense Force III. Japan s Official Development Assistance (ODA) (1) General view,

More information

Emissions Trading in China Progress on the Path towards a Unified National System

Emissions Trading in China Progress on the Path towards a Unified National System Emissions Trading in China PRESENTED BY Chen Zhibin SinoCarbon Feb. 2016 Bottom - Up ETS in China 1 Led by NDRC (National Reform and Development commission) One registry system ETS Development in China

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

Learnings from Bihar, India An evolutionary process and the impact of a market development program to create a functioning sanitation market

Learnings from Bihar, India An evolutionary process and the impact of a market development program to create a functioning sanitation market Learnings from Bihar, India An evolutionary process and the impact of a market development program to create a functioning sanitation market Shankar Narayanan PSI India UNC Water & Health Conference 2015

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 50,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 50,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020344 Public Disclosure Authorized Project ID P106702 Country Brazil Project Name BR Integr. Solid

More information

Thailand s Solar Energy Policy and New Alternative Energy Development Plan ( )

Thailand s Solar Energy Policy and New Alternative Energy Development Plan ( ) Thailand s Solar Energy Policy and New Alternative Energy Development Plan (2015-2036) Ms. Thidarat Sawai Bureau of solar energy development Department of Alternative Energy Development and Efficiency

More information

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Wind Workshop Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Objective of this session: Understand BC Hydro s definitions and calculation methodology of dependable capacity

More information

Terms of Reference Governance Committee

Terms of Reference Governance Committee 1. Purpose Terms of Reference Governance Committee The Governance Committee is responsible for ensuring that BC Assessment and its Board develop and implement an effective approach to corporate governance.

More information

COURSE LISTING. Courses Listed. Training for Applications with Integration in SAP Business One. 27 November 2017 (07:09 GMT) Advanced

COURSE LISTING. Courses Listed. Training for Applications with Integration in SAP Business One. 27 November 2017 (07:09 GMT) Advanced Training for Applications with Integration in SAP Business One Courses Listed Advanced TB1000 - SAP Business One - Logistics TB1100 - SAP Business One - Accounting TB1200 - SAP Business One - Implementation

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Nov ,493,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Nov ,493,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021025 Public Disclosure Authorized Public Disclosure Authorized Project ID P106703 Country Brazil Project

More information

For Bandon Utilities Commission

For Bandon Utilities Commission For Bandon Utilities Commission July 12, 2017 Profile BPA, a component of the U.S. Department of Energy, is a non-profit and self-funded power marketing administration in the Pacific Northwest. Congress

More information

Wairakei site tour. 22 October 2015 Dennis Barnes, Chief Executive Officer

Wairakei site tour. 22 October 2015 Dennis Barnes, Chief Executive Officer Wairakei site tour 22 October 2015 Dennis Barnes, Chief Executive Officer 1 Cautionary statement This presentation may contain projections or forward-looking statements regarding a variety of items. Such

More information

Dominican Republic Mid-Term Report. Pedro García Brito Climate Change Director Focal Point for REDD+

Dominican Republic Mid-Term Report. Pedro García Brito Climate Change Director Focal Point for REDD+ Dominican Republic Mid-Term Report Pedro García Brito Climate Change Director Focal Point for REDD+ Dominican Republic and Climate Change The Dominican Republic s Constitution: declares as a national priority

More information

PROJECTS & ACHIEVEMENTS in Energy Efficiency and Renewable Energies in Lebanon

PROJECTS & ACHIEVEMENTS in Energy Efficiency and Renewable Energies in Lebanon PROJECTS & ACHIEVEMENTS in Energy Efficiency and Renewable Energies in Lebanon By Rani Al Achkar, Senior Programmes Engineer Secretary of the Board OMAINTEC 2017 October 24, 2017 Beirut, Lebanon Presentation

More information

Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE

Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE Regional Expert Meeting on Climate Change and Enhanced Renewable Energy Deployment in East and Southern Africa Addis Ababa, Ethiopia

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,000,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020618 Public Disclosure Authorized Public Disclosure Authorized Project ID P113402 Country Sri Lanka

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Rajasthan Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include

More information

People s Republic of China: Fujian Pacific Electric Company Limited

People s Republic of China: Fujian Pacific Electric Company Limited Performance Evaluation Report Project Number: PPE: PRC 29712 Equity Investment Number: 7144 Loan Number: 1610-PRC June 2006 People s Republic of China: Fujian Pacific Electric Company Limited Operations

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

Contents. Introduction. Introduction. First Power Plant based on AC Tesla s s principles 1900! Recent Energy Sector Development

Contents. Introduction. Introduction. First Power Plant based on AC Tesla s s principles 1900! Recent Energy Sector Development ENERGY AGENCY OF THE REPUBLIC OF SERBIA Contents Recent Energy Sector Development and AERS Responsibilities Ljiljana Hadžibabić Head of the Energy Department NARUC Energy Regulatory Partnership Program

More information

PJM EIS Generation Attribute Tracking System (GATS)

PJM EIS Generation Attribute Tracking System (GATS) PJM EIS Generation Attribute Tracking System (GATS) Presented to NASEO 2015 Mid-Atlantic Regional Meeting June 22, 2015 Who is PJM EIS? PJM Environmental Information Services, Inc. Formed in February 2005

More information

Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE

Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE Renewable Energy and Climate Change: The CIF Experience TITLE SLIDE Regional Expert Meeting on Climate Change and Enhanced Renewable Energy Deployment in Central Africa Libreville, Gabon June 1, 2016 CIF

More information

The World Bank Market Instruments for climate change mitigation in Chile (P130378)

The World Bank Market Instruments for climate change mitigation in Chile (P130378) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF MARKET INSTRUMENTS FOR CLIMATE CHANGE MITIGATION IN CHILE APPROVED ON

More information

The World Bank Burkina Faso - Bagre Growth Pole Project (P119662)

The World Bank Burkina Faso - Bagre Growth Pole Project (P119662) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF BURKINA FASO - BAGRE GROWTH POLE PROJECT APPROVED ON JUNE 21, 2011 TO

More information

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities Country Partnership Strategy: Papua New Guinea, 2011 2015 SECTOR ASSESSMENT (SUMMARY): POWER 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. In Papua New Guinea (PNG), less than

More information

Electric Price Outlook April 13, 2017

Electric Price Outlook April 13, 2017 Electric Price Outlook April 13, 2017 Scott Drzycimski, Director Customer, Community and Economic Development Jason Nielsen, Manager Regulatory Affairs Keeping you informed Ongoing pricing outlook webinars

More information

Financial Results Meeting: The 1st 3 Months of FY Ending March (April 1, 2016 June 30, 2016) August 9, 2016

Financial Results Meeting: The 1st 3 Months of FY Ending March (April 1, 2016 June 30, 2016) August 9, 2016 Financial Results Meeting: The 1st 3 Months of FY Ending March 2017 (April 1, 2016 June 30, 2016) August 9, 2016 Unification of Accounting Period Unify accounting period (financial reporting period) of

More information

Project Name PROJECT INFORMATION DOCUMENT (PID) Nepal Village Micro Hydro Carbon Offset Project. South Asia SASSD P095978

Project Name PROJECT INFORMATION DOCUMENT (PID) Nepal Village Micro Hydro Carbon Offset Project. South Asia SASSD P095978 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower(s) Implementing Agency PROJECT INFORMATION

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE FOREST PROTECTION AND REFORESTATION PROJECT

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE FOREST PROTECTION AND REFORESTATION PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT

More information

BUSINESS PLAN COVER PAGE

BUSINESS PLAN COVER PAGE BUSINESS PLAN COVER PAGE OWNERS Your Business Name Street Address City, State ZIP Code E-Mail Telephone Table of Contents EXECUTIVE SUMMARY... 1 BUSINESS DESCRIPTION... 2 Overview... 2 Targeted Market

More information

Alumina in focus Supply, Demand and Pricing

Alumina in focus Supply, Demand and Pricing Alumina in focus Supply, Demand and Pricing 2015 Metal Bulletin B&A Conference Simon Storesund, SVP Commercial, B&A 26 February 2015 (1) Cautionary note Certain statements included within this announcement

More information

Eugene Water & Electric Board. The Future of Utilities in the Pacific Northwest

Eugene Water & Electric Board. The Future of Utilities in the Pacific Northwest Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest 1 Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest Erin Erben Manager, Power & Strategic Planning

More information

ENERGY AND WATER STATISTICS 2016

ENERGY AND WATER STATISTICS 2016 ENERGY AND WATER STATISTICS 216 Introduction This issue of Economic and Social Indicators presents Statistics on Energy and Water for the years 215 and 216. The statistics have been compiled in close collaboration

More information