The minutes to the Prebid Meeting held on June 13, 2018 are attached.
|
|
- Job Abner Benson
- 5 years ago
- Views:
Transcription
1 ADDENDUM NUMBER ONE TO BIDDING AND CONTRACT DOCUMENTS FOR RUNWAY 5R-23L REHABILITATION PROECT - CONSTRUCTION PHASE 3 PIEDMONT TRIAD INTERNATIONAL AIRPORT GREENSBORO, NORTH CAROLINA TO: All Prospective Bidders Date: Monday, une 25, 208 This addendum forms a part of the Contract Documents and modifies the original Bidding Documents as noted below. Acknowledge receipt of this addendum in the space provided on the Bid Form (B-4) AND by acknowledging receipt of this Addendum by returning the attached Acknowledgement Form (Attachment A) via fax, or mail. FAILURE TO DO SO MAY SUBECT A BIDDER TO DISQUALIFICATION. PREBID MEETING The minutes to the Prebid Meeting held on une 3, 208 are attached. SPECIFICATIONS AND CONTRACT DOCUMENTS COVER SHEET o Delete the cover sheet in its entirety and replace with the attached cover sheet. BID FORMS o Delete Pages B-3a thru B-3l of the BID SCHEDULE, and replace with the attached Pages B-3a thru B-3l. TECHNICAL SPECIFICATIONS o Delete paragraph and replace with the following: The ALCMS support services shall be measured on a per unit basis and shall be based on a daily rate of eight (8) hours for one personnel including incidental labor and tools to support the owner furnished vendor of the ALCMS for field commissioning and certification of the ALCMS to provide a complete in place, accepted and ready for operation system. o Add the following pay item to Item L : Item L Reinstall Existing Taxiway Edge Light and Isolation Transformer on New Base per each Addendum No. Page of 4
2 Reinstallation of existing L-86T, taxiway edge light, connected to existing L-830 transformers on a new L-867B base, refurbished base plate, L-823 connectors, and all incidentals. Align and level as required - per Each. o Delete paragraph and replace with the following: ALCMS SUPPORT SERVICES. Payment for this item shall be made at the contract unit price for each day of coordination required to support the efforts of the ALCMS vendor. The price shall be full compensation for furnishing all materials and labor in support of the modifications to the ALCMS, including site coordination and escorting of ALCMS manufacturer, corrections or modifications of contractor installed material in support of the ALCMS equipment, testing and commissioning support of the ALCMS by the ALCMS manufacturer and for all other preparation, management, coordination, assembly and installation of the materials, and for all labor equipment, tools, and incidentals necessary to complete the item. Payment will be made under: Item L : ALCMS Support Services per day DRAWINGS o Delete Sheets G-00 thru G-003 and replace with the attached Sheets G- 00 thru G-003. o Delete Sheet G-0 and replace with the attached Sheet G-0. o Delete Sheets C-602 thru C-605 and replace with the attached Sheet C-602 thru C-605. o Delete Sheets C-60, C-606 thru C-609, and C-65 in their entirety. o Delete Sheets E-20 thru E-204 and replace with the attached Sheets C- 20 thru E-204. o Add the following as Note 4 on Drawing E-252: The existing isolation transformers connected to the existing runway edge lights shall be removed and reinstalled with the reinstalled runway centerline lights. The series isolation transformers connected to the existing runway centerline lights shall be removed and delivered to a location designated by the Airport Authority. o Delete Sheet E-254 and replace with the attached sheet E-254. o Delete Sheet E-263 and replace with the attached sheet E-263. o Delete Sheet E-402 and replace with the attached sheet E-402. The grade tables are provided in Microsoft Excel format. Addendum No. Page 2 of 4
3 PLANHOLDER QUESTIONS. What items will be considered for stored materials, or will any items NOT be considered? Items to be considered for stored materials are at the discretion of the Engineer in accordance with Paragraph of the General Provisions. 2. Will items be considered for partial payments? If so, which items, and at what %? Items to be considered for partial payments are at the discretion of the Engineer in accordance with Paragraph of the General Provisions. 3. Regarding the project bid item #58 (ALCMS Support): I am requesting that this item be listed in the bid tab with a predetermined cost to the contractor(s) in order to not allow this sole sourced proprietary item to affect the overall pricing for the balance of the airfield lighting product package. Per FAA procurement guidelines as defined in the current FAA D, this type of material or service must be either procured separately by the airport on a separate RFQ or listed with the cost clearly presented. This Bid Item is for labor costs associated with the Contractor support of the ALCMS vendor for site coordination and commissioning. 4. Because the staging area is a significant distance from the work site, can a secondary staging area be provided in order to store active equipment/materials? A secondary staging area will be provided closer to the work area. The site will be coordinated with the successful bidder. 5. Can an anticipated NTP be provided in order to assist in potential scheduling of the work? General consensus is that une timeframe is preferable over April/May due to weather and resource availability. It is anticipated that a construction Notice to Proceed (NTP) will be issued in une 209. It is also anticipated that an administrative NTP will be issued prior to the construction NTP to allow for submittal review, schedule development, procurement of materials, and other activities to prepare for construction activities to begin. 6. Is night work permitted? Yes, night work is permitted. END OF ADDENDUM NUMBER ONE Addendum No. Page 3 of 4
4 ATTACHMENT A ACKNOWLEDGEMENT FORM Contract Supervisor, I, (we) am/are returning this acknowledgement to your office as a receipt to the following Addendum: PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 ADDENDUM NO. Company Name BY: Recipient s Signature Date: This acknowledgement must be returned to: Heather Leopardi Michael Baker Engineering, Inc. 200 Centreport Drive, Suite 350 Greensboro, NC Phone: (42) Fax: (42) hleopardi@mbakerintl.com Addendum No. Page 4 of 4
5
6 Pre-Bid Meeting PROECT: DATE: PLACE: Piedmont Triad International Airport Runway 5R-23L Rehabilitation Project, Construction Phase 3 Wednesday, une 3, 208 at 0:00 am Stanley Frank Board Room INTRODUCTIONS: Deputy Executive Director Alex Rosser / rossera@gsoair.org PTAA Project Manager Lisa Elmore / elmorel@gsoair.org PTAA Project Manager Lorin Akins / akinsl@gsoair.org PTAA Operations Chris Bishop / bishopc@gsoair.org PTAA Operations Ben Rodkey / rodkeyb@gsoair.org Michael Baker PM Heather Leopardi / hleopardi@mbakerintl.com PROECT SUMMARY a. Work in base bid will include: Rehabilitation (milling, grooving, paving, and painting) of 3,000 feet of Runway 5R-23L pavement, including shoulders and transitions onto connector taxiways. Complete removal of Taxiway M3 Installation of underdrain, existing structure abandonment, adjustment, removal and/or replacement Replacement of runway centerline and edge lighting systems. Existing runway centerline light fixtures and transformers will be reinstalled. Adjustment of RW 5R PAPI to accommodate changes in runway grades Necessary Erosion and Sedimentation (E&S) control measures for the project limits b. A combination of alternates will be developed which include a total of,450 of additional runway length. Work in the alternates will include additional work as described above. PROECT BIDDING a. Base Bid (3000 feet of runway): Work as described above between Runway Stations and b. Add Alternate (,450 feet of runway): Work as described above between Runway Stations and If Add Alternate is awarded, Add Alternates 2, 3, and 4 will not be awarded. c. Add Alternate 2/3 (93 feet of runway): Work as described above between Runway Stations and Add Alternate 2 starts at the end of the Base Bid and extends for 600 feet. Add Alternate 3 starts at the end of the Base Bid and extends for 33 feet if Add Alternate 2 is not awarded. Add Alternate 3 starts at the end of Add Alternate 2 and extends for 33 feet if Add Alternate 2 is awarded. d. Add Alternate 4 (40 feet of runway): Work as described above between Runway Stations 3+87 and L:\PROECTS\GSO\65742 RW 5R-23L REHAB, PH3\2.0 CORRESPONDENCES\MEETINGS\MINUTES\208_06_3 GSO RW5R-23L REHAB PHASE 3 PREBID MINUTES.DOC
7 Pre-Bid Meeting Add Alternate 4 starts at the end of Add Alternate 3 and extends for 40 feet. Add Alternate 4 will not be awarded if both Add Alternate 2 and Add Alternate 3 are not awarded. SCHEDULE a. Last Day for Questions une 20, 208-2:00 p.m. to hleopardi@mbakerintl.com b. Addendum une 25, 208 c. Bids Due uly, 208-2:00 p.m. d. Bid Opening uly, 208-2:00 p.m. e. Notice to Proceed Administrative NTP Fall 208 Construction NTP Spring 209 f. Completion of Work 95 calendar days PROECT DOCUMENTS a. Bid Requirements Instructions to Bidders b. DBE Requirements 2.3% c. Liquidated Damages $3,000 per calendar day d. Bid Security 5% of total Bid e. Prime contractor to complete at least 25% of the total work as defined in Paragraph 3.2 of the Instructions to Bidders and General Provision FUNDING a. FAA Grant Funding b. Davis Bacon Wage Rates Attachment to the General Provisions will be updated by Addendum if necessary CONSTRUCTION a. Contractors Staging Area b. Haul Routes c. Airfield Access d. Air and Vehicle Traffic Control e. Scheduling/Coordination f. Detailed Paving Plan Paving Workshop (Owner/Engineer/CM/Contractor) QA/QC Procedures Production Rates/Lift Thicknesses Rolling and Compaction Procedures Hot and Cold oints Lighting Considerations g. P-40 Bituminous Paving ASTM D3666 Certified Lab SuperPave Gyratory Compactor instead of Marshall Mix h. P-60 Concrete ASR Testing (ASTM C260 and C567) PHASING a. Phase (95 Calendar Days) L:\PROECTS\GSO\65742 RW 5R-23L REHAB, PH3\2.0 CORRESPONDENCES\MEETINGS\MINUTES\208_06_3 GSO RW5R-23L REHAB PHASE 3 PREBID MINUTES.DOC
8 Pre-Bid Meeting b. Phase A (2 Calendar Days) c. Phase B (5 Calendar Days) d. Phase C (5 Calendar Days) SAFETY AND SECURITY a. OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION ACTIVITIES, General Requirement 0030, Airport Project Procedures Construction Safety Phasing Plan (CSPP) included in Appendix E of project manual Contractor is responsible for preparing a Safety Plan Compliance Document as stated in the General Provisions, paragraph b. Security & Badging Requirements included in Appendices A, B, and C of project manual DISCUSSION/QUESTIONS The following questions were asked/discussed during the prebid meeting. Responses will be provided in the addendum if appropriate: a. Because the staging area is a significant distance from the work site, can a secondary staging area be provided in order to store active equipment/materials? b. Can an anticipated NTP be provided in order to assist in potential scheduling of the work? General consensus is that une timeframe is preferable over April/May due to weather and resource availability. c. Is night work permitted? d. Can the grade tables be provided in Microsoft Excel format? e. Can clarification be made on which line items partial payments will be allowed? L:\PROECTS\GSO\65742 RW 5R-23L REHAB, PH3\2.0 CORRESPONDENCES\MEETINGS\MINUTES\208_06_3 GSO RW5R-23L REHAB PHASE 3 PREBID MINUTES.DOC
9 Heath er M. Leopa rdi Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, bakerintl.com, c=us Date: :4:37-04'00' Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, engineers.com, c=us Date: :23:39-04'00'
10 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - BASE BID - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 0000 MOBILIZATION LS $ $ 2 P-0 BITUMINOUS PAVEMENT REMOVAL 2,600 SY $ $ 3 P-0 COLD MILLING 70,000 SY $ $ 4 P-0 ASPHALTIC CONCRETE OINT AND CRACK REPAIR 5,000 LF $ $ 5 P-0 ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 3,000 LF $ $ 6 P-52 EMBANKMENT IN PLACE 2,000 CY $ $ 7 P-56 CONSTRUCTION ENTRANCE 2 EA $ $ 8 P-56 SOD INLET PROTECTION 3 EA $ $ 9 P-56 BLOCK AND GRAVEL INLET PROTECTION 5 EA $ $ 0 P-56 INSTALLATION AND REMOVAL OF SILT FENCE,950 LF $ $ P-56 TEMPORARY SKIMMER DEVICE INSTALLATION EA $ $ 2 P-56 TEMPORARY SEEDING AND MULCHING 5.9 ACRE $ $ 3 P-40 BITUMINOUS SURFACE COURSE 28,000 TON $ $ 4 P-40 BITUMINOUS LEVELING COURSE 5,000 TON $ $ 5 P-603 BITUMINOUS TACK COAT 7,000 GAL $ $ 6 P-620 WATERBORNE, TYPE III MARKING, WHITE 30,000 SF $ $ 7 P-620 WATERBORNE, TYPE III MARKING, YELLOW 3,700 SF $ $ 8 P-620 WATERBORNE, TYPE III MARKING, BLACK 0,700 SF $ $ 9 P-620 WATERBORNE, TYPE II MARKING, TEMPORARY 33,700 SF $ $ 20 P-620 REFLECTIVE MEDIA, TYPE III 3,750 LB $ $ 2 P-620 MARKING REMOVAL,000 SF $ $ 22 P-62 GROOVING 43,400 SY $ $ 23 D INCH REINFORCED CONCRETE PIPE, CLASS V 8 LF $ $ 24 D-70 STORM PIPE REMOVAL 400 LF $ $ 25 D-70 GROUT EXISTING PIPE 0 CY $ $ 26 D D-705 UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6- INCH DIAMETER 4,900 LF $ $,500 LF $ $ 28 D-75 UNDERDRAIN CLEANOUT 2 EA $ $ 29 D-75 ABANDON EXISTING STRUCTURE 9 EA $ $ B-3a
11 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - BASE BID - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 30 D-75 REMOVE EXISTING DRAINAGE STRUCTURE EA $ $ 3 D-75 ADUST INLET TO GRADE EA $ $ 32 T-90 SEEDING 5.9 ACRE $ $ 33 T-905 TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 2,400 CY $ $ 34 T-905 TOPSOILING (FURNISHED FROM OFF THE SITE) 800 CY $ $ 35 T-908 MULCHING 28,500 SY $ $ 36 L L L-05 TEMPORARY AIRFIELD LIGHTING UMPERS AS INDICATED ON THE DRAWINGS, COMPLETE REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING SEMIFLUSH RUNWAY EDGE LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) LS $ $ 40 EA $ $ 2 EA $ $ 39 L-05 REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 60 EA $ $ 40 L-05 REMOVE EXISTING UNCTION BOX 50 EA $ $ 4 L L L-05 REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN- PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT 6,500 LF $ $ 7,800 LF $ $ 27,000 LF $ $ 44 L-05 REMOVE AIRFIELD GUIDANCE SIGN AND BASE 4 EA $ $ 45 L L L-0 48 L-0 49 L-0 50 L-0 5 L-0 52 L-5 #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2- WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40 -WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA CONCRETE ENCASED ELECTRICAL DUCTBANK, 4- WAY, 4" PVC CONDUIT, SCHEDULE 40 ADUST ELECTRICAL STRUCTURE TO FINISHED GRADE 57,000 LF $ $ 3,000 LF $ $ 4,00 LF $ $ 5,400 LF $ $ 200 LF $ $ 900 LF $ $,00 LF $ $ 4 EA $ $ 53 L-5 NEW AIRCRAFT RATED ELECTRICAL MANHOLE 2 EA $ $ B-3b
12 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - BASE BID - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 54 L L L-25 NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 6 EA $ $ 24 EA $ $ 60 EA $ $ 57 L L-25 REINSTALL EXISTING TAXIWAY EDGE LIGHT AND ISOLATION TRANSFORMER ON ADUSTED BASE REINSTALL EXISTING TAXIWAY EDGE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 4 EA $ $ EA $ $ 59 L-25 ALCMS SUPPORT SERVICES DAY $ $ 60 MC-00 ISOLATED FULL DEPTH PATCHING 700 SY $ $ Total Bid Schedule Base Bid $ B-3c
13 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 0000 MOBILIZATION LS $ $ 2 P-0 COLD MILLING 33,200 SY $ $ 3 P-0 ASPHALTIC CONCRETE OINT AND CRACK REPAIR 8,500 LF $ $ 4 P-0 ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 2,000 LF $ $ 5 P-56 SOD INLET PROTECTION 3 EA $ $ 6 P-56 BLOCK AND GRAVEL INLET PROTECTION 2 EA $ $ 7 P-56 TEMPORARY SEEDING AND MULCHING 0.90 ACRE $ $ 8 P-40 BITUMINOUS SURFACE COURSE,000 TON $ $ 9 P-603 BITUMINOUS TACK COAT 6,640 GAL $ $ 0 P-620 WATERBORNE, TYPE III MARKING, WHITE 28,000 SF $ $ P-620 WATERBORNE, TYPE III MARKING, YELLOW,900 SF $ $ 2 P-620 WATERBORNE, TYPE III MARKING, BLACK 6,00 SF $ $ 3 P-620 WATERBORNE, TYPE II MARKING, TEMPORARY 29,900 SF $ $ 4 P-620 REFLECTIVE MEDIA, TYPE III 3,330 LB $ $ 5 P-620 MARKING REMOVAL 200 SF $ $ 6 P-62 GROOVING 2,300 SY $ $ 7 D-70 GROUT EXISTING PIPE 30 CY $ $ 8 D D-705 UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6- INCH DIAMETER 2,400 LF $ $,200 LF $ $ 20 D-75 UNDERDRAIN CLEANOUT 2 EA $ $ 2 D-75 ABANDON EXISTING STRUCTURE 5 EA $ $ 22 T-90 SEEDING 0.90 ACRE $ $ 23 T-905 TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 340 CY $ $ 24 T-905 TOPSOILING (FURNISHED FROM OFF THE SITE) 20 CY $ $ 25 T-908 MULCHING 4,50 SY $ $ 26 L L-05 REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA $ $ 29 EA $ $ 28 L-05 REMOVE EXISTING UNCTION BOX 2 EA $ $ B-3d
14 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 29 L L-05 3 L L L L-0 35 L-0 36 L-0 37 L-0 38 L L L-25 REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN- PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2- WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40 -WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE,800 LF $ $ 3,800 LF $ $ 7,500 LF $ $ 2,000 LF $ $ 5,300 LF $ $ 2,00 LF $ $ 2,300 LF $ $ 20 LF $ $ 250 LF $ $ 2 EA $ $ 2 EA $ $ 29 EA $ $ 4 L-25 ADUSTMENT OF EXISTING L-880 PAPI UNITS ON EXISTING FOUNDATIONS (RUNWAY 5R) EA $ $ 42 MC-00 ISOLATED FULL DEPTH PATCHING 500 SY $ $ Total Bid Schedule Add Alternate $ B-3e
15 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 2 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 0000 MOBILIZATION LS $ $ 2 P-0 COLD MILLING 3,350 SY $ $ 3 P-0 ASPHALTIC CONCRETE OINT AND CRACK REPAIR 3,600 LF $ $ 4 P-0 ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 850 LF $ $ 5 P-56 SOD INLET PROTECTION EA $ $ 6 P-56 BLOCK AND GRAVEL INLET PROTECTION EA $ $ 7 P-56 TEMPORARY SEEDING AND MULCHING 0.50 ACRE $ $ 8 P-40 BITUMINOUS SURFACE COURSE 4,500 TON $ $ 9 P-603 BITUMINOUS TACK COAT 2,700 GAL $ $ 0 P-620 WATERBORNE, TYPE III MARKING, WHITE 7,600 SF $ $ P-620 WATERBORNE, TYPE III MARKING, BLACK,800 SF $ $ 2 P-620 WATERBORNE, TYPE II MARKING, TEMPORARY 7,600 SF $ $ 3 P-620 REFLECTIVE MEDIA, TYPE III 850 LB $ $ 4 P-62 GROOVING 8,670 SY $ $ 5 D D-705 UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6- INCH DIAMETER,200 LF $ $ 600 LF $ $ 7 D-75 UNDERDRAIN CLEANOUT 8 EA $ $ 8 T-90 SEEDING 0.50 ACRE $ $ 9 T-905 TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 200 CY $ $ 20 T-905 TOPSOILING (FURNISHED FROM OFF THE SITE) 70 CY $ $ 2 T-908 MULCHING 2,400 SY $ $ 22 L L-05 REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 6 EA $ $ 2 EA $ $ 24 L-05 REMOVE EXISTING UNCTION BOX 6 EA $ $ 25 L L L L-08 REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN- PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT B-3f 700 LF $ $,500 LF $ $ 2,800 LF $ $ 8,00 LF $ $
16 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 2 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 29 L L-0 3 L-0 32 L-0 33 L-0 34 L L-25 #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2- WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40 -WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 2,00 LF $ $,200 LF $ $ 600 LF $ $ 20 LF $ $ 75 LF $ $ 6 EA $ $ 2 EA $ $ 36 MC-00 ISOLATED FULL DEPTH PATCHING 20 SY $ $ Total Bid Schedule Add Alternate 2 $ B-3g
17 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 3 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 0000 MOBILIZATION LS $ $ 2 P-0 COLD MILLING 7,000 SY $ $ 3 P-0 ASPHALTIC CONCRETE OINT AND CRACK REPAIR,900 LF $ $ 4 P-0 ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 440 LF $ $ 5 P-56 SOD INLET PROTECTION EA $ $ 6 P-56 BLOCK AND GRAVEL INLET PROTECTION EA $ $ 7 P-56 TEMPORARY SEEDING AND MULCHING 0.30 ACRE $ $ 8 P-40 BITUMINOUS SURFACE COURSE 2,400 TON $ $ 9 P-603 BITUMINOUS TACK COAT,400 GAL $ $ 0 P-620 WATERBORNE, TYPE III MARKING, WHITE 4,900 SF $ $ P-620 WATERBORNE, TYPE III MARKING, BLACK,00 SF $ $ 2 P-620 WATERBORNE, TYPE II MARKING, TEMPORARY 4,900 SF $ $ 3 P-620 REFLECTIVE MEDIA, TYPE III 550 LB $ $ 4 P-62 GROOVING 4,530 SY $ $ 5 D D-705 UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6- INCH DIAMETER 630 LF $ $ 600 LF $ $ 7 D-75 UNDERDRAIN CLEANOUT 6 EA $ $ 8 T-90 SEEDING 0.30 ACRE $ $ 9 T-905 TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 00 CY $ $ 20 T-905 TOPSOILING (FURNISHED FROM OFF THE SITE) 30 CY $ $ 2 T-908 MULCHING,400 SY $ $ 22 L L-05 REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA $ $ 6 EA $ $ 24 L-05 REMOVE EXISTING UNCTION BOX 3 EA $ $ 25 L L L L-08 REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN- PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT B-3h 35 LF $ $ 800 LF $ $,500 LF $ $ 4,200 LF $ $
18 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 3 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 29 L L-0 3 L-0 32 L L-25 #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2- WAY, 2" PVC CONDUIT, SCHEDULE 40 NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE,050 LF $ $ 630 LF $ $ 35 LF $ $ 2 EA $ $ 6 EA $ $ 34 MC-00 ISOLATED FULL DEPTH PATCHING 0 SY $ $ Total Bid Schedule Add Alternate 3 $ B-3i
19 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 4 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 0000 MOBILIZATION LS $ $ 2 P-0 COLD MILLING 9,700 SY $ $ 3 P-0 ASPHALTIC CONCRETE OINT AND CRACK REPAIR 2,400 LF $ $ 4 P-0 ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 600 LF $ $ 5 P-56 SOD INLET PROTECTION 2 EA $ $ 6 P-56 BLOCK AND GRAVEL INLET PROTECTION EA $ $ 7 P-56 TEMPORARY SEEDING AND MULCHING 0.20 ACRE $ $ 8 P-40 BITUMINOUS SURFACE COURSE 3,200 TON $ $ 9 P-603 BITUMINOUS TACK COAT,940 GAL $ $ 0 P-620 WATERBORNE, TYPE III MARKING, WHITE 3,400 SF $ $ P-620 WATERBORNE, TYPE III MARKING, YELLOW,900 SF $ $ 2 P-620 WATERBORNE, TYPE III MARKING, BLACK 3,00 SF $ $ 3 P-620 WATERBORNE, TYPE II MARKING, TEMPORARY 5,300 SF $ $ 4 P-620 REFLECTIVE MEDIA, TYPE III,700 LB $ $ 5 P-620 MARKING REMOVAL 200 SF $ $ 6 P-62 GROOVING 5,930 SY $ $ 7 D-70 GROUT EXISTING PIPE 30 CY $ $ 8 D-705 UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT 300 LF $ $ 9 D-705 UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6- INCH DIAMETER 600 LF $ $ 20 D-75 UNDERDRAIN CLEANOUT 6 EA $ $ 2 D-75 ABANDON EXISTING STRUCTURE 5 EA $ $ 22 T-90 SEEDING 0.20 ACRE $ $ 23 T-905 TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 80 CY $ $ 24 T-905 TOPSOILING (FURNISHED FROM OFF THE SITE) 30 CY $ $ 25 T-908 MULCHING 800 SY $ $ 26 L L-05 REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA $ $ 8 EA $ $ 28 L-05 REMOVE EXISTING UNCTION BOX 3 EA $ $ 29 L-05 REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE B-3j 700 LF $ $
20 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 BID SCHEDULE - ADD ALTERNATE 4 - ADDENDUM ITEM SPEC UNIT EXTENDED QUANTITY NO. NO. DESCRIPTION UNIT PRICE TOTAL 30 L-05 3 L L L L-0 35 L-0 36 L-0 37 L-0 38 L L-25 REMOVE EXISTING -WAY, 2-INCH DUCT, IN- PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2- WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40 -WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE,200 LF $ $ 2,300 LF $ $ 6,900 LF $ $,700 LF $ $ 50 LF $ $,200 LF $ $ 00 LF $ $ 200 LF $ $ 2 EA $ $ 4 EA $ $ 40 L-25 REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 8 EA $ $ 4 L-25 ADUSTMENT OF EXISTING L-880 PAPI UNITS ON EXISTING FOUNDATIONS (RUNWAY 5R) EA $ $ 42 MC-00 ISOLATED FULL DEPTH PATCHING 50 SY $ $ Total Bid Schedule Add Alternate 4 $ B-3k
21 PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R-23L REHABILITATION PROECT, CONSTRUCTION PHASE 3 SUMMARY SHEET OF AWARD SCENARIOS: ADDENDUM Total Bid Schedule in Figures Total Bid Schedule in Words Total Bid Schedule Base Bid Only $ Total Bid Schedule Base Bid + Total Bid Schedule Add Alternate $ Total Bid Schedule Base Bid + Total Bid Schedule Add Alternate 2 $ Total Bid Schedule Base Bid + Total Bid Schedule Add Alternate 3 $ Total Bid Schedule Base Bid + Total Bid Schedule Add Alternate 2 + Total Bid Schedule Add Alternate 3 $ Total Bid Schedule Base Bid + Total Bid Schedule Add Alternate 2 + Total Bid Schedule Add Alternate 3 + Total Bid Schedule Add Alternate 4 $ It is the intent of the Owner to award a Contract to the bidder with the lowest responsive and responsible total base bid plus bid or bids for any owner selected alternates meeting the requirements set forth in the Contract Documents, the total of which does not exceed the funds available. Owner will select one of the following award scenarios, at the Owner's option: Base Bid Only Base Bid + Add Alternate Base Bid + Add Alternate 2 Base Bid + Add Alternate 3 Base Bid + Add Alternate 2 + Add Alternate 3 Base Bid + Add Alternate 2 + Add Alternate 3 + Add Alternate 4 B-3l
22 PIEDMONT TRIAD PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) AIP # XI IW H TA W AY E AY W N RU X R 23 TA 5L AY TA R TA U N X W AY IWA Y 4 D -3 TA 2 XI W AY A TA W XI AY W N RU TA XI W AY AY XI W AY M FORSYTH COUNTY GUILFORD COUNTY WINSTONSALEM K GREENSBORO 3L -2 R 5 PROECT LOCATION DAVIDSON COUNTY C INDEX OF DRAWINGS C-42 DRAINAGE TABLES G-00 TITLE SHEET AND INDEX OF DRAWINGS C-45 DRAINAGE DETAILS G-002 -G-003 SUMMARY OF QUANTITIES C-50 - C-530 PAVING GRADE TABLES G-004 GENERAL NOTES, LEGEND, AND ABBREVIATIONS C C-605 PAVEMENT MARKING PLANS G-005 PROECT DESCRIPTION PLAN C-65 PAVEMENT MARKING DETAILS G-006 PROECT LAYOUT PLAN X-0 - X-05 TAXIWAY M3 CROSS SECTIONS G-007 HORIZONTAL AND VERTICAL CONTROL PLAN E-00 AIRFIELD ELECTRICAL GENERAL NOTES G-0 SAFETY AND PHASING PLANS AND DETAILS E-002 G-20 BORING LOCATION PLAN AIRFIELD ELECTRICAL LEGEND AND ABBREVIATIONS E-0 - E-05 AIRFIELD ELECTRICAL DEMOLITION PLANS G-300 EROSION AND SEDIMENTATION CONTROL NOTES G-30 - G-307 EROSION AND SEDIMENTATION CONTROL PLANS G-35 EROSION AND SEDIMENTATION CONTROL DETAILS C-0 TYPICAL PAVEMENT SECTIONS C-20 - C-204 MILLING AND PAVING PLANS C-25 PAVING DETAILS C-30 - C-302 RUNWAY PROFILES C-40 - C-405 GRADING AND DRAINAGE PLANS E-5 AIRFIELD ELECTRICAL DEMOLITION DETAILS E-20 - E-205 AIRFIELD ELECTRICAL INSTALLATION PLANS E-23 - E-232 LIGHTING SCHEDULES E-25 - E-264 AIRFIELD ELECTRICAL INSTALLATION DETAILS E-30 AIRFIELD LIGHTING VAULT PLAN E-40 - E402 CIRCUIT PLANS HIGH POINT RANDLEMAN Heather M. Leopardi Manik K. Arora TITLE SHEET AND INDEX OF DRAWINGS ROCKINGHAM COUNTY PIEDMONT TRIAD INTERNATIONAL AIRPORT INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerintl.com, c=us Date: :27:2-04'00' Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, =marora@aroraengine ers.com, c=us Date: :5:44-04'00' KWO DESIGNED KWO DRAWN HML CHECKED HML APPROVED MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: UNE, 208 SCALE: AS SHOWN REVISIONS NO. DATE BY 6/8/8 HML REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING SHEET DESCRIPTION ADDENDUM G-00
23 BASE BID BASE BID (CONT) ADD ALTERNATE ITEM ITEM DESCRIPTION QUANTITY UNIT AS-BUILT 0000 MOBILIZATION LS P-0-6. BITUMINOUS PAVEMENT REMOVAL 2,600 SY P COLD MILLING 70,000 SY P ASPHALTIC CONCRETE OINT AND CRACK REPAIR 5,000 LF P ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 3,000 LF P EMBANKMENT IN PLACE 2,000 CY P CONSTRUCTION ENTRANCE 2 EA P SOD INLET PROTECTION 3 EA P BLOCK AND GRAVEL INLET PROTECTION 5 EA P INSTALLATION AND REMOVAL OF SILT FENCE,950 LF P TEMPORARY SKIMMER DEVICE INSTALLATION EA P TEMPORARY SEEDING AND MULCHING 5.9 ACRE P BITUMINOUS SURFACE COURSE 28,000 TON P BITUMINOUS LEVELING COURSE 5,000 TON P BITUMINOUS TACK COAT 7,000 GAL P WATERBORNE, TYPE III MARKING, WHITE 30,000 SF P WATERBORNE, TYPE III MARKING, YELLOW 3,700 SF P WATERBORNE, TYPE III MARKING, BLACK 0,700 SF P WATERBORNE, TYPE II MARKING, TEMPORARY 33,700 SF P REFLECTIVE MEDIA, TYPE III 3,750 LB P MARKING REMOVAL,000 SF P GROOVING 43,400 SY D INCH REINFORCED CONCRETE PIPE, CLASS V 8 LF D STORM PIPE REMOVAL 400 LF D GROUT EXISTING PIPE 0 CY D UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT 4,900 LF D UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6-INCH DIAMETER,500 LF D UNDERDRAIN CLEANOUT 2 EA D ABANDON EXISTING STRUCTURE 9 EA D REMOVE EXISTING DRAINAGE STRUCTURE EA D ADUST INLET TO GRADE EA T SEEDING 5.9 ACRE T TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 2,400 CY T TOPSOILING (FURNISHED FROM OFF THE SITE) 800 CY T MULCHING 28,500 SY L L L L TEMPORARY AIRFIELD LIGHTING UMPERS AS INDICATED ON THE DRAWINGS, COMPLETE REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING SEMIFLUSH RUNWAY EDGE LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) LS 40 EA 2 EA 60 EA L REMOVE EXISTING UNCTION BOX 50 EA ITEM ITEM DESCRIPTION QUANTITY UNIT AS-BUILT L L REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN-PAVEMENT, COMPLETE 6,500 LF 7,800 LF L REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT 27,000 LF L REMOVE AIRFIELD GUIDANCE SIGN AND BASE 4 EA L L L-0-5. L L #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40 57,000 LF 3,000 LF 4,00 LF 5,400 LF 200 LF L WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA 900 LF L CONCRETE ENCASED ELECTRICAL DUCTBANK, 4-WAY, 4" PVC CONDUIT, SCHEDULE 40,00 LF L-5-5. ADUST ELECTRICAL STRUCTURE TO FINISHED GRADE 4 EA L NEW AIRCRAFT RATED ELECTRICAL MANHOLE 2 EA L L L L NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE REINSTALL EXISTING TAXIWAY EDGE LIGHT AND ISOLATION TRANSFORMER ON ADUSTED BASE 6 EA 24 EA 60 EA 4 EA L REINSTALL EXISTING TAXIWAY EDGE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE EA L ALCMS SUPPORT SERVICES DAY MC ISOLATED FULL DEPTH PATCHING 700 SY ITEM ITEM DESCRIPTION QUANTITY UNIT AS-BUILT 0000 MOBILIZATION LS P COLD MILLING 33,200 SY P ASPHALTIC CONCRETE OINT AND CRACK REPAIR 8,500 LF P ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 2,000 LF P SOD INLET PROTECTION 3 EA P BLOCK AND GRAVEL INLET PROTECTION 2 EA P TEMPORARY SEEDING AND MULCHING 0.90 ACRE P BITUMINOUS SURFACE COURSE,000 TON P BITUMINOUS TACK COAT 6,640 GAL P WATERBORNE, TYPE III MARKING, WHITE 28,000 SF P WATERBORNE, TYPE III MARKING, YELLOW,900 SF P WATERBORNE, TYPE III MARKING, BLACK 6,00 SF P WATERBORNE, TYPE II MARKING, TEMPORARY 29,900 SF P REFLECTIVE MEDIA, TYPE III 3,330 LB P MARKING REMOVAL 200 SF P GROOVING 2,300 SY D GROUT EXISTING PIPE 30 CY D UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT 2,400 LF D UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6-INCH DIAMETER,200 LF D UNDERDRAIN CLEANOUT 2 EA D ABANDON EXISTING STRUCTURE 5 EA T SEEDING 0.90 ACRE T TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 340 CY T TOPSOILING (FURNISHED FROM OFF THE SITE) 20 CY T MULCHING 4,50 SY L L REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA 29 EA L REMOVE EXISTING UNCTION BOX 2 EA L L L L L L-0-5. L L REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN-PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE 40,800 LF 3,800 LF 7,500 LF 2,000 LF 5,300 LF 2,00 LF 2,300 LF 20 LF L WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA 250 LF L L L L NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE ADUSTMENT OF EXISTING L-880 PAPI UNITS ON EXISTING FOUNDATIONS (RUNWAY 5R) 2 EA 2 EA 29 EA EA MC ISOLATED FULL DEPTH PATCHING 500 SY PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 KWO DESIGNED LS CHECKED SUMMARY OF QUANTITIES KWO DRAWN HML APPROVED MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: UNE, 208 Heather M. Leopardi Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerintl.com, c=us Date: :27:35-04'00' NO. DATE BY 6/8/8 HML REVISIONS DESCRIPTION ADDENDUM SCALE: NONE SHEET G-002 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
24 ADD ALTERNATE 2 ADD ALTERNATE 3 ADD ALTERNATE 4 ITEM ITEM DESCRIPTION QUANTITY UNIT AS-BUILT 0000 MOBILIZATION LS P COLD MILLING 3,350 SY P ASPHALTIC CONCRETE OINT AND CRACK REPAIR 3,600 LF P ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 850 LF ITEM ITEM DESCRIPTION QUANTITY UNIT AS-BUILT 0000 MOBILIZATION LS P COLD MILLING 7,000 SY P ASPHALTIC CONCRETE OINT AND CRACK REPAIR,900 LF P ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 440 LF ITEM ITEM DESCRIPTION QUANTITY UNIT 0000 MOBILIZATION LS P COLD MILLING 9,700 SY P ASPHALTIC CONCRETE OINT AND CRACK REPAIR 2,400 LF P ASPHALTIC CONCRETE OINT AND CRACK FILLING WITH SAND MIXTURE 600 LF PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) P SOD INLET PROTECTION EA P BLOCK AND GRAVEL INLET PROTECTION EA P TEMPORARY SEEDING AND MULCHING 0.50 ACRE P BITUMINOUS SURFACE COURSE 4,500 TON P BITUMINOUS TACK COAT 2,700 GAL P WATERBORNE, TYPE III MARKING, WHITE 7,600 SF P WATERBORNE, TYPE III MARKING, BLACK,800 SF P WATERBORNE, TYPE II MARKING, TEMPORARY 7,600 SF P REFLECTIVE MEDIA, TYPE III 850 LB P GROOVING 8,670 SY D UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT,200 LF D UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6-INCH DIAMETER 600 LF D UNDERDRAIN CLEANOUT 8 EA T SEEDING 0.50 ACRE T TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 200 CY T TOPSOILING (FURNISHED FROM OFF THE SITE) 70 CY T MULCHING 2,400 SY L L REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 6 EA 2 EA L REMOVE EXISTING UNCTION BOX 6 EA L L L L L L-0-5. L L REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN-PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE LF,500 LF 2,800 LF 8,00 LF 2,00 LF,200 LF 600 LF 20 LF L WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA 75 LF L NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE 6 EA L REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 2 EA MC ISOLATED FULL DEPTH PATCHING 20 SY P SOD INLET PROTECTION EA P BLOCK AND GRAVEL INLET PROTECTION EA P TEMPORARY SEEDING AND MULCHING 0.30 ACRE P BITUMINOUS SURFACE COURSE 2,400 TON P BITUMINOUS TACK COAT,400 GAL P WATERBORNE, TYPE III MARKING, WHITE 4,900 SF P WATERBORNE, TYPE III MARKING, BLACK,00 SF P WATERBORNE, TYPE II MARKING, TEMPORARY 4,900 SF P REFLECTIVE MEDIA, TYPE III 550 LB P GROOVING 4,530 SY D UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT 630 LF D UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6-INCH DIAMETER 600 LF D UNDERDRAIN CLEANOUT 6 EA T SEEDING 0.30 ACRE T TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 00 CY T TOPSOILING (FURNISHED FROM OFF THE SITE) 30 CY T MULCHING,400 SY L L REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA 6 EA L REMOVE EXISTING UNCTION BOX 3 EA L L L L L L-0-5. L L REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN-PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE 35 LF 800 LF,500 LF 4,200 LF,050 LF 630 LF 35 LF 2 EA L REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE 6 EA MC ISOLATED FULL DEPTH PATCHING 0 SY P SOD INLET PROTECTION 2 EA P BLOCK AND GRAVEL INLET PROTECTION EA P TEMPORARY SEEDING AND MULCHING 0.20 ACRE P BITUMINOUS SURFACE COURSE 3,200 TON P BITUMINOUS TACK COAT,940 GAL P WATERBORNE, TYPE III MARKING, WHITE 3,400 SF P WATERBORNE, TYPE III MARKING, YELLOW,900 SF P WATERBORNE, TYPE III MARKING, BLACK 3,00 SF P WATERBORNE, TYPE II MARKING, TEMPORARY 5,300 SF P REFLECTIVE MEDIA, TYPE III,700 LB P MARKING REMOVAL 200 SF P GROOVING 5,930 SY D GROUT EXISTING PIPE 30 CY D UNDERDRAIN PIPE, PERFORATED, 6-INCH DIAMETER INSTALLED IN PAVEMENT 300 LF D UNDERDRAIN OUTLET PIPE, NON-PERFORATED, 6-INCH DIAMETER 600 LF D UNDERDRAIN CLEANOUT 6 EA D ABANDON EXISTING STRUCTURE 5 EA T SEEDING 0.20 ACRE T TOPSOILING (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) 80 CY T TOPSOILING (FURNISHED FROM OFF THE SITE) 30 CY T MULCHING 800 SY L L REMOVE EXISTING ELEVATED LIGHT FIXTURE AND BASE (DELIVER FIXTURE TO AIRPORT) REMOVE EXISTING IN-PAVEMENT LIGHT FIXTURE AND BASE (FIXTURE FOR REINSTALLATION) 2 EA 8 EA L REMOVE EXISTING UNCTION BOX 3 EA L L L L L L-0-5. L L REMOVE EXISTING -WAY, 2-INCH DUCT, DIRECT BURIED, COMPLETE REMOVE EXISTING -WAY, 2-INCH DUCT, IN-PAVEMENT, COMPLETE REMOVE EXISTING AIRFIELD LIGHTING CABLE IN CONDUIT OR DUCT #8, 5KV, L-824, TYPE C AIRFIELD LIGHTING CABLE INSTALLED IN DUCT BANK OR CONDUIT #6 AWG, SOLID, BARE COUNTERPOISE WIRE, INSTALLED ABOVE DUCT BANK OR CONDUIT CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONCRETE ENCASED ELECTRICAL DUCTBANK, 2-WAY, 2" PVC CONDUIT, SCHEDULE 40 CONTROLLED LOW STRENGTH MATERIAL ENCASED ELECTRICAL DUCTBANK, -WAY, 2" PVC CONDUIT, SCHEDULE LF,200 LF 2,300 LF 6,900 LF,700 LF 50 LF,200 LF 00 LF L WAY, 2" PVC CONDUIT, SCHEDULE 40, UNPAVED AREA 200 LF PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 KWO DESIGNED LS CHECKED SUMMARY OF QUANTITIES KWO DRAWN HML APPROVED L L L L NEW L-850C RUNWAY SEMIFLUSH EDGE LIGHT ON NEW BASE NEW L-862 RUNWAY ELEVATED EDGE LIGHT ON NEW BASE REINSTALL EXISTING L-850A RUNWAY CENTERLINE LIGHT AND ISOLATION TRANSFORMER ON NEW BASE ADUSTMENT OF EXISTING L-880 PAPI UNITS ON EXISTING FOUNDATIONS (RUNWAY 5R) 2 EA 4 EA 8 EA EA MC ISOLATED FULL DEPTH PATCHING 50 SY MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) Heather M. Leopardi Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerintl.c om, c=us Date: :27:46-04'00' NO. DATE BY 6/8/8 HML REVISIONS DESCRIPTION ADDENDUM DATE: UNE, 208 SCALE: NONE SHEET G-003 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
25 60' 250' TOTAL PROECT DURATION 95 CALENDAR DAYS PHASE I - STATIONS (95 CALENDAR DAYS) RUNWAY 5R-23L WILL BE CLOSED DURING THIS PHASE AREA AVAILABLE TO CONTRACTOR 24 HOURS PER DAY TAXIWAYS D, K, K2, K3, M, M3, M4, M5, AND A PORTION OF TAXIWAY M WILL BE CLOSED DURING THIS PHASE MILL AND PAVE EXISTING RUNWAY 5R-23L WITHIN PHASE LIMITS MILL AND PAVE EXISTING RUNWAY 5R-23L SHOULDERS WITHIN PHASE LIMITS INSTALLATION OF UNDERDRAIN WITHIN PHASE LIMITS GRADING, SEEDING AND MULCHING ALONG EDGES OF RUNWAY 5R-23L WITHIN PHASE LIMITS REMOVE LIGHT BASES AND LIGHT FIXTURES FROM WITHIN PHASE LIMITS REMOVE CABLE AND CONDUIT WITHIN PHASE LIMITS TRENCH PAVEMENT FOR NEW ELECTRICAL WORK WITHIN PHASE LIMITS EXISTING STRUCTURE ABANDONMENT, ADUSTMENT, REMOVAL, AND/OR REPLACEMENT REPLACE RUNWAY 5R-23L CENTERLINE LIGHTS, CABLE AND CONDUIT WITHIN PHASE LIMITS AND REINSTALL EXISTING FIXTURES REPLACE RUNWAY 5R-23L EDGE LIGHTS, FIXTURES, CABLE AND CONDUIT WITHIN PHASE LIMITS PAVEMENT MARKING PHASE IA (2 CALENDAR DAYS) 60' 60' PHASE IA REMOVE TAXIWAY M3 PAVEMENT REMOVE TAXIWAY M3 TAXIWAY EDGE LIGHTS REMOVE TAXIWAY M3 SIGNS REMOVE TAXIWAY M3 CENTERLINE MARKINGS LOCATED ON TAXIWAY M GRADING, SEEDING, AND MULCHING TAXIWAY M WILL BE CLOSED BETWEEN TAXIWAY D AND TAXIWAY M4 ONCE WORK IS WITHIN 60 FEET FROM THE TAXIWAY M CENTERLINE. ONCE WORK COMMENCES FOR THIS PHASE, CONTRACTOR HAS 2 CALENDAR DAYS TO COMPLETE THIS PHASE 60' 60' PHASE IC (GROOVING & MARKING) 60' PHASE IC (MARKING) 60' PHASE IA 60' 60' 60' NOTES: 60'. RED BARRICADE LIGHTS SHALL BE SOLAR 360 OMNIDIRECTIONAL. 2. BARRICADES SHALL BE INTERLOCKED AND CONTINUOUS, UNLESS OTHERWISE INDICATED; OR DIRECTED BY THE ENGINEER. 3. CONTRACTOR SHALL MAINTAIN BARRICADE LIGHTS AT ALL TIMES DURING CONSTRUCTION. EACH BARRICADE MUST HAVE BOTH LIGHTS OPERATING AT ALL TIMES. 4. BARRICADES SHALL BE HELD IN PLACE BY ENOUGH SANDBAGS TO PREVENT MOVEMENT FROM ET BLAST. SANDBAGS SHALL BE EITHER ORANGE OR WHITE. G-0 8'-0" 60' HIGH INTENSITY RED FLASHING LIGHT SECURED TO BARRICADE (TWO PER BARRICADE) INTERNATIONAL ORANGE AND WHITE STRIPES (BOTH SIDES) LOW PROFILE BARRICADE LOW PROFILE BARRICADE DETAIL NTS PHASE IB SURFACE OF PAVEMENT/GROUND LEGEND A LOW PROFILE BARRICADE Heather M. INDICATES THE PHASE Leopardi 60' Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerin tl.com, c=us Date: :28:00-04'00' PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 KWO DESIGNED SAFETY AND PHASING PLAN AND DETAILS KWO DRAWN PHASE B (5 CALENDAR DAYS) HML CHECKED HML APPROVED TAXIWAYS K3 AND M5 WILL BE CLOSED DURING THIS PHASE TAXIWAYS K3 AND M5 CANNOT BE CLOSED AT THE SAME TIME AS TAXIWAYS K2 AND M4 REMOVE EXISTING ELECTRICAL CONDUIT REMOVE EXISTING UNCTION BOXES REMOVE EXISTING ELECTRICAL CABLES INSTALL NEW ELECTRICAL CABLES PHASE IC (5 CALENDAR DAYS) GROOVING OF RUNWAY 5R-23L NEW PAVING REMARK ENTIRE RUNWAY 5R-23L AND TAXIWAY CONNECTORS AS INDICATED ON PAVEMENT MARKING PLANS NOTES:. THE CONTRACTOR SHALL FURNISH TWO (2) LIGHTED RUNWAY CLOSURE MARKINGS FOR USE ON THE PROECT. THE CONTRACTOR SHALL MAINTAIN, POSITION, OPERATE, FUEL AND STORE THE MARKERS THROUGHOUT THE DURATION OF THE PROECT. 2. CONTRACTOR TO USE ONE () MARKER FOR EACH END OF THE RUNWAY. 3. ONE () MARKER SHALL BE PLACED ON THE RUNWAY 5R BLAST PAD 60 FEET FROM TAXIWAY A CENTERLINE. ONE () MARKER SHALL BE PLACED ON THE 23L RUNWAY DESIGNATION. 2 G-0 CLOSED RUNWAY MARKER NTS NO. DATE BY 6/9/8 HML SCALE IN FEET REVISIONS DESCRIPTION ADDENDUM MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: SCALE: UNE, 208 AS SHOWN SHEET G-0 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
26 20' 6' WIDE WHITE STRIPE NOTES:. BASE BID SHALL INCLUDE ALL PAVEMENT MARKINGS. 2. ALL PERMANENT MARKINGS HAVE 6" BLACK OUTLINE ON ALL SIDES. 3. ALL RUNWAY MARKINGS ARE TO BE CENTERED ON THE RUNWAY 5R-23L BASELINE. PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) MATCHLINE - SEE SHEET C ' (TYP) RUNWAY 5R-23L BASELINE LIMIT OF PAVING SEE NOTE 7 REMOVE EXISTING TAXIWAY CENTERLINE MARKING 30' WIDE WHITE STRIPE(TYP) ' (TYP) END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR REMOVE EXISTING TAXIWAY CENTERLINE MARKING " YELLOW STRIPE ' SPACE (TYP) 20' WHITE STRIPE (TYP) 500' 500' END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR 75' (TYP) 5' WHITE STRIPE 3' WIDE WHITE STRIPE 3' WIDE MATCHLINE - SEE SHEET C ALL COORDINATE POINTS ARE TO THE CENTER OF THE MARKING. 5. IN ALL INSTANCES WHERE RUNWAY AND TAXIWAY MARKINGS INTERSECT, THE TAXIWAY MARKINGS SHALL ABUT THE RUNWAY MARKINGS AND SHALL RESUME AFTER THE RUNWAY MARKING. 6. ANY MARKINGS BEYOND THE PLANNED MARKING LIMITS THAT BECOME OBSCURED DUE TO CONSTRUCTION ACTIVITIES AS DETERMINED BY THE ENGINEER SHALL BE REPAINTED AT NO ADDITIONAL EXPENSE TO THE CONTRACT. 7. ALL EXISTING MARKINGS BEYOND LIMIT OF PAVING SHALL BE REMARKED IN EXISTING LOCATIONS EXCEPT WHERE OTHERWISE NOTED IN ACCORDANCE WITH ITEM P AN APPLICATION OF TEMPORARY PAVEMENT MARKING WILL BE REQUIRED ON ALL NEW PAVEMENT PRIOR TO THE APPLICATION OF PERMANENT MARKINGS, IN ACCORDANCE WITH ITEM P-620. POINT MARKING POINT TABLE NORTHING EASTING DESCRIPTION PT R=95' PC PC R=95' PT PT R=95' PC PC PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 PAVEMENT MARKING PLANS R=95' PT Heather M. Leopardi SCALE IN FEET KEY MAP Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerintl.co m, c=us Date: :28:9-04'00' KWO DESIGNED DLF CHECKED KWO DRAWN HML APPROVED MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: SCALE: UNE, 208 AS SHOWN NO. DATE BY 6/9/8 HML REVISIONS DESCRIPTION ADDENDUM SHEET C-602 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
27 NOTES:. BASE BID SHALL INCLUDE ALL PAVEMENT MARKINGS. 2. ALL PERMANENT MARKINGS HAVE 6" BLACK OUTLINE ON ALL SIDES. 3. ALL RUNWAY MARKINGS ARE TO BE CENTERED ON THE RUNWAY 5R-23L BASELINE. PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) MATCHLINE - SEE SHEET C-602 RUNWAY 5R-23L 200' (TYP) BASELINE ' 3' WIDE (TYP) 3' WIDE WHITE STRIPE 80' SPACE (TYP) 20' WHITE STRIPE (TYP) 500' 500' 500' 75' (TYP) (TYP) 6' WIDE WHITE STRIPE (TYP) REMOVE EXISTING TAXIWAY CENTERLINE MARKING " YELLOW STRIPE 3-03 END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR ' MATCHLINE - SEE SHEET C ALL COORDINATE POINTS ARE TO THE CENTER OF THE MARKING. 5. IN ALL INSTANCES WHERE RUNWAY AND TAXIWAY MARKINGS INTERSECT, THE TAXIWAY MARKINGS SHALL ABUT THE RUNWAY MARKINGS AND SHALL RESUME AFTER THE RUNWAY MARKING. 6. ANY MARKINGS BEYOND THE PLANNED MARKING LIMITS THAT BECOME OBSCURED DUE TO CONSTRUCTION ACTIVITIES AS DETERMINED BY THE ENGINEER SHALL BE REPAINTED AT NO ADDITIONAL EXPENSE TO THE CONTRACT. 7. ALL EXISTING MARKINGS BEYOND LIMIT OF PAVING SHALL BE REMARKED IN EXISTING LOCATIONS EXCEPT WHERE OTHERWISE NOTED IN ACCORDANCE WITH ITEM P AN APPLICATION OF TEMPORARY PAVEMENT MARKING WILL BE REQUIRED ON ALL NEW PAVEMENT PRIOR TO THE APPLICATION OF PERMANENT MARKINGS, IN ACCORDANCE WITH ITEM P-620. POINT MARKING POINT TABLE NORTHING EASTING DESCRIPTION PT R=95' PC R=95' PT PT R=95' PC PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 PAVEMENT MARKING PLANS END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR Heather M. Leopardi SCALE IN FEET KEY MAP Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakeri ntl.com, c=us Date: :28:32-04'00' KWO DESIGNED DLF CHECKED KWO DRAWN HML APPROVED MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: SCALE: UNE, 208 AS SHOWN NO. DATE BY 6/9/8 HML REVISIONS DESCRIPTION ADDENDUM SHEET C-603 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
28 NOTES:. BASE BID SHALL INCLUDE ALL PAVEMENT MARKINGS. 2. ALL PERMANENT MARKINGS HAVE 6" BLACK OUTLINE ON ALL SIDES. 3. ALL RUNWAY MARKINGS ARE TO BE CENTERED ON THE RUNWAY 5R-23L BASELINE. PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) MATCHLINE - SEE SHEET C ' (TYP) RUNWAY 5R-23L BASELINE 3' WIDE WHITE STRIPE 80' SPACE (TYP) 20' WHITE STRIPE (TYP) 3' WIDE (TYP) 6" YELLOW STRIPE 200' (TYP) MATCHLINE - SEE SHEET C ALL COORDINATE POINTS ARE TO THE CENTER OF THE MARKING. 5. IN ALL INSTANCES WHERE RUNWAY AND TAXIWAY MARKINGS INTERSECT, THE TAXIWAY MARKINGS SHALL ABUT THE RUNWAY MARKINGS AND SHALL RESUME AFTER THE RUNWAY MARKING. 6. ANY MARKINGS BEYOND THE PLANNED MARKING LIMITS THAT BECOME OBSCURED DUE TO CONSTRUCTION ACTIVITIES AS DETERMINED BY THE ENGINEER SHALL BE REPAINTED AT NO ADDITIONAL EXPENSE TO THE CONTRACT. 7. ALL EXISTING MARKINGS BEYOND LIMIT OF PAVING SHALL BE REMARKED IN EXISTING LOCATIONS EXCEPT WHERE OTHERWISE NOTED IN ACCORDANCE WITH ITEM P AN APPLICATION OF TEMPORARY PAVEMENT MARKING WILL BE REQUIRED ON ALL NEW PAVEMENT PRIOR TO THE APPLICATION OF PERMANENT MARKINGS, IN ACCORDANCE WITH ITEM P-620. PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 PAVEMENT MARKING PLANS REMOVE EXISTING TAXIWAY ENHANCED CENTERLINE Heather M. Leopardi Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakeri ntl.com, c=us Date: :28:45-04'00' SCALE IN FEET KEY MAP KWO DESIGNED DLF CHECKED KWO DRAWN HML APPROVED END REMOVAL OF EXISTING TAXIWAY ENHANCED CENTERLINE MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: SCALE: UNE, 208 AS SHOWN NO. DATE BY 6/9/8 HML REVISIONS DESCRIPTION ADDENDUM SHEET C-604 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
29 NOTES:. BASE BID SHALL INCLUDE ALL PAVEMENT MARKINGS. 2. ALL PERMANENT MARKINGS HAVE 6" BLACK OUTLINE ON ALL SIDES. 3. ALL RUNWAY MARKINGS ARE TO BE CENTERED ON THE RUNWAY 5R-23L BASELINE. PIEDMONT TRIAD AIRPORT AUTHORITY 000A Ted ohnson Parkway Greensboro, NC OFC: (336) FAX: (336) MATCHLINE - SEE SHEET C-604 3' WIDE ' SPACE 20' WHITE STRIPE 80' SPACE 00' WHITE STRIPE 60' SPACE 00' WHITE STRIPE 60' SPACE 00' WHITE STRIPE 80' SPACE 20' WHITE STRIPE ' WIDE WHITE STRIPE END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR REMOVE EXISTING TAXIWAY CENTERLINE MARKING 6" YELLOW STRIPE ' (TYP) REMOVE EXISTING TAXIWAY CENTERLINE MARKING (TYP) RUNWAY 5R-23L BASELINE LIMIT OF PAVING SEE NOTE 7 MATCHLINE - SEE SHEET C ALL COORDINATE POINTS ARE TO THE CENTER OF THE MARKING. 5. IN ALL INSTANCES WHERE RUNWAY AND TAXIWAY MARKINGS INTERSECT, THE TAXIWAY MARKINGS SHALL ABUT THE RUNWAY MARKINGS AND SHALL RESUME AFTER THE RUNWAY MARKING. 6. ANY MARKINGS BEYOND THE PLANNED MARKING LIMITS THAT BECOME OBSCURED DUE TO CONSTRUCTION ACTIVITIES AS DETERMINED BY THE ENGINEER SHALL BE REPAINTED AT NO ADDITIONAL EXPENSE TO THE CONTRACT. 7. ALL EXISTING MARKINGS BEYOND LIMIT OF PAVING SHALL BE REMARKED IN EXISTING LOCATIONS EXCEPT WHERE OTHERWISE NOTED IN ACCORDANCE WITH ITEM P AN APPLICATION OF TEMPORARY PAVEMENT MARKING WILL BE REQUIRED ON ALL NEW PAVEMENT PRIOR TO THE APPLICATION OF PERMANENT MARKINGS, IN ACCORDANCE WITH ITEM P-620. POINT MARKING POINT TABLE NORTHING EASTING DESCRIPTION PT R=95' PC R=95' PT PC R=95' PIEDMONT TRIAD INTERNATIONAL AIRPORT RUNWAY 5R - 23L REHABILITATION - CONSTRUCTION PHASE 3 PAVEMENT MARKING PLANS PT END REPAINTING OF EXISTING TAXIWAY CENTERLINE AT THE HOLD BAR R=95' PC Heather M. Leopardi Digitally signed by Heather M. Leopardi DN: cn=heather M. Leopardi, o=michael Baker International, ou=aviation, =hleopardi@mbakerintl.co m, c=us Date: :29:0-04'00' KWO DESIGNED KWO DRAWN SCALE IN FEET KEY MAP DLF CHECKED HML APPROVED MICHAEL BAKER ENGINEERING, INC. 200 Centreport Dr. Suite 350 Greensboro,NC OFC: (336) FAX: (336) DATE: SCALE: UNE, 208 AS SHOWN NO. DATE BY 6/9/8 HML REVISIONS DESCRIPTION ADDENDUM SHEET C-605 REV. 04/25/206 IF THIS DRAWING IS LESS THAN 22" x 34", IT IS A REDUCED SIZE DRAWING
30 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, om, c=us Date: :59:8-04'00'
31 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, om, c=us Date: :58:28-04'00'
32 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, om, c=us Date: :57:33-04'00'
33 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, om, c=us Date: :56:26-04'00'
34 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, c=us Date: :54:03-04'00'
35 Manik K. Arora Digitally signed by Manik K. Arora DN: cn=manik K. Arora, o, ou, om, c=us Date: :53:4-04'00'
ADDENDUM NUMBER THREE
ADDENDUM NUMBER THREE TO BIDDING AND CONTRACT DOCUMENTS FOR RUNWAY 5R-23L REHABILITATION PROECT - CONSTRUCTION PHASE 3 PIEDMONT TRIAD INTERNATIONAL AIRPORT GREENSBORO, NORTH CAROLINA TO: All Prospective
More informationCompany Page 1 of 13
ITEM NO. REVISION WBS (ITEM) DESCRIPTION UNIT QUANTITY (WRITTEN) MC-001-5.1 Mobilization/Demobilization and Construction Layout Surveying LS 1 MC-003-6.1 Temporary Construction Items LS 1 MC-003-6.2 Taxiway
More informationTABULATION OF BIDS DODGE CITY REGIONAL AIRPORT DODGE CITY, KANSAS RECONSTRUCT RUNWAY 14-32: SUMMARY PROJECT NO.: AIP
RECONSTRUCT RUNWAY 14-32: SUMMARY., BID SUMMARY TOTAL COST TOTAL COST TOTAL COST TOTAL COST TOTAL COST Schedule 1 Cost of Construction $4,717,480.00 $5,106,762.00 $5,697,026.50 $4,430,910.42 $4,640,166.10
More informationADDENDUM NO. ONE REHABILITATION OF TAXIWAY G AND RECONSTRUCTION OF TAXIWAY D FOR THE TRENTON-MERCER AIRPORT AB
ADDENDUM NO. ONE Notice is hereby given that on June 22, 2017 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Agent in the Mercer County McDade Administration
More informationAll Prospective Bidders. Date: Wednesday, November 29, 2017
ADDENDUM NUMBER TWO TO BIDDING AND CONTRACT DOCUMENTS FOR RUNWAY 5R-23L REHABILITATION PROJECT - CONSTRUCTION PHASE 1 PIEDMONT TRIAD INTERNATIONAL AIRPORT GREENSBORO, NORTH CAROLINA TO: All Prospective
More informationURS CORPORATION NY Contract No. C REPUBLIC AIRPORT RUNWAY 1-19 RUNWAY SAFETY AREA (RSA) IMPROVEMENTS ADDENDUM NO. 4 TO:
URS CORPORATION NY Contract No. C015548 ADDENDUM NO. 4 TO: DATE: May 12, 2016 CONTRACT NO. C015548-S13-FRGRSA COUNTY: SUFFOLK IN THE LETTING OF May 16, 2016 NOTICE TO PROSPECTIVE BIDDERS The following
More informationBID FORM. Alt. Bid: Additional extension of proposed taxiway from STA: to TW F/G intersection, approximately 1,095 feet.
BID FORM TxDOT CSJ 1812CONRO Project Description: TW Extension, Lighting and Signage Improvements Base Bid: The project consists of the extension of existing 50 TW approximately 2,640 feet. The proposed
More informationBID TABULATION ( BIDS OPENED MONDAY, APRIL 24, 1:00 P.M. ) CONSTRUCT PARALLEL TAXIWAY - PHASE 3 HABERSHAM COUNTY AIRPORT, CORNELIA, GEORGIA
BASE BID 1 01000 MOBILIZATION 1.00 L. SUM $799,945.96 $799,945.96 $1,150,000.00 $1,150,000.00 2 01510 FIELD ENGINEER'S OFFICE 1.00 L. SUM $40,000.00 $40,000.00 $5,000.00 $5,000.00 3 ALL-1 4 ALL-2 5 MISC-1
More informationADDENDUM #2 JUNE 30, It is required that all bidders acknowledge receipt of Addenda on Page BF-2 of the Bid Form.
ADDENDUM #2 JUNE 30, 2017 APRON REHABILITATION PHASE 3 HENRY E. ROHLSEN AIRPORT ST. CROIX, U.S. VIRGIN ISLANDS FAA AIP No.: 3-78-0002-037-2017 This addendum modifies or interprets the proposal documents
More informationA D D E N D U M N O. 1
A D D E N D U M N O. 1 TO: PROJECT: All Prospective Bidders (LVJ) Signage, Gate and Pavement Marking Improvements TxDOT CSJ No. Project No. 007250 (0500.051.000) ISSUE DATE: October 25, 2017 The following
More informationMETROPOLITAN WASHINGTON AIRPORTS AUTHORITY
DATE SCALE METROPOLITAN WASHINGTON PROJECT IDENTIFIER DA03 DESIGNED CHECKED DRAWN AIRPORTS AUTHORITY RONALD REAGAN WASHINGTON NATIONAL AIRPORT WASHINGTON, D.C. SHEET NAME GN02.000 VOLUME NUMBER ACCEPTED
More informationTABULATION OF BIDS DENVER INTERNATIONAL AIRPORT. Denver, Colorado CONTRACT NO. CE CONCOURSE C EAST APRON EXPANSION BID SUMMARY
Contract No. CE 80017 Bid Date: 1/29/2008 TABULATION OF BIDS Denver, Colorado BID SUMMARY Bid Bond DBE Goals Addendum One Schedule I Schedule II Total Bid 34,030,330.50 4,560,072.50 38,590,403.00 Page
More informationADDENDUM NUMBER FOUR
Department of Aviation Airport Office Building 8500 Peňa Boulevard Denver, Colorado (303) 342-2200 www.flydenver.com March 28, 2017 2017 Annual Airfield Pavement Rehabilitation CONTRACT NO. 201733182 ADDENDUM
More informationADDENDUM #1. The following sheets have been revised and are being reissued as part of this addendum:
ADDENDUM #1 AIRFIELD IMPROVEMENTS EXTEND, MARK, AND LIGHT RUNWAY 6-24 AND TAXIWAY ALPHA REHABILITATE RUNWAY 6-24 at the LAKE WALES MUNICIPAL AIRPORT FAA AIP NO: TBD FDOT FM NO: TBD BID NO: 16-412 5/11/16
More information2013 ANNUAL AIRFIELD PAVEMENT REHABILITATION CONTRACT NO ADDENDUM NUMBER TWO. Scope of this Addendum
D E N V E R I N T E R N A T I O N A L A I R P O R T CONTRACT NO. 201208796 ADDENDUM NUMBER TWO Scope of this Addendum Addendum Number Two includes modifications to the following Contract Documents issued
More informationCOMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO.1 UPPER SKAGIT INDIAN TRIBE PAGE 1
UPPER SKAGIT INDIAN TRIBE COMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO. 1 (7 pages total) Issue Date: May 11, 2016 General: Recitations of each and every section of the bid documents impacted
More informationAddendum No. 3 Page 1 of 6
ADDENDUM NUMBER THREE TO BIDDING AND CONTRACT DOCUMENTS FOR RUNWAY 5R-23L REHABILITATION PROECT - CONSTRUCTION PHASE 3 PIEDMONT TRIAD INTERNATIONAL AIRPORT GREENSBORO, NORTH CAROLINA TO: All Prospective
More informationA D D E N D U M N O. 4
A D D E N D U M N O. 4 TO: PROJECT: All Prospective Bidders (T78) Drainage Improvements TxDOT CSJ No. Klotz Project No. 0500.041.002 ISSUE DATE: January 30, 2017 The following information is provided to
More informationRFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered
RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater
More informationEXHIBIT A-2 SCOPE OF SERVICES HAS PROJECT NUMBER 646A PROFESSIONAL ENGINEERING DESIGN SERVICES FOR TAXIWAYS RA, RB, SA, AND SB AT IAH
1. INTRODUCTION EXHIBIT A-2 SCOPE OF SERVICES HAS PROJECT NUMBER 646A PROFESSIONAL ENGINEERING DESIGN SERVICES FOR TAXIWAYS RA, RB, SA, AND SB AT IAH 1.1. The objective of this Project includes: 1.1.1.
More informationBid Form. Schedule 2 Alternate Bid No. 4: Install gutters and downspouts. (100% Local Funded)
Bid Form TxDOT CSJ No. 17HGRCKPT Project: Aransas County Airport - 2017 Hangar Project Project Description: Schedule 1A Base Bid: Construct TxDOT 360 concrete apron pavement for box hangar. Schedule 1A
More informationBID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of. a Partnership consisting of
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of a Partnership consisting of an Individual doing business as. TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction
More informationSAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6
SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO. 18-4501 SOLICITATION NO. CO-00198 ADDENDUM 6 (September 10, 2018) To Respondent of Record: This addendum, applicable to work referenced
More informationBASE BID Description Written & Numeric Price
PROPOSAL Proposal TxDOT CSJ No. Project : Airfield drainage improvements to alleviate storm water conveyance issues at in Liberty, TX. The improvements include: re-grading of existing concrete lined infields,
More informationBid Form. To the Texas Department of Transportation hereinafter called the Agent.
Bid Form TxDOT CSJ No. 1809HILLS Project: 2017 Airport Improvements Project Description: Schedule 1 Base Bid: Rehabilitate and mark RW 16-34, partial parallel TW, stub TWs including run-up areas, terminal
More informationSUBJECT: ADDENDUM #1 IFB # Taxiway A Rehabilitation - Bid Package 1 at Myrtle Beach International Airport (MYR) NOTICE of REVISIONS:
Office of Procurement Conway, SC 29526 3230 Hwy 319 E Conway, SC 29526 843.915.5380 (Ph) 843.365.9861 (Fx) TO: FROM: ALL INTERESTED PARTIES Kimberly Massie, CPPB, Director of Procurement DATE: May 31,
More informationADDENDUM NO. 1. CITY OF FORT MORGAN CONSTRUCT RUNWAY BID AIP Project No March 7, 2014
ADDENDUM NO. 1 CONSTRUCT RUNWAY 14-32 BID AIP Project No. 3-08-0024-11 March 7, 2014 To all prospective bidders: This Addendum is hereby made a part of the Contract Documents and Specifications of the
More informationFor Reference Only - Not For The Purpose Of Bidding BP-1 PROPOSAL. PROPOSAL OF, a corporation a. partnership consisting of
PROPOSAL PROPOSAL OF, a corporation a partnership consisting of and an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction and Invitations to Bidders, the undersigned
More informationADDENDUM #1 MARCH 10, CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF
ADDENDUM #1 MARCH 10, 2016 CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF TO: ALL PLAN HOLDERS This Addendum No. 1 to the Contract Documents for City of Winter Springs project "Central Winds
More informationAPPENDIX H. Capital Improvement Program Detail Project Costs NORTH PERRY AIRPORT MASTER PLAN UPDATE APPENDICES
MASTER PLAN UPDATE APPENDICES APPENDIX H Capital Improvement Program Detail Project Costs Montgomery Consulting Group August 11, 2009 Appendix H CAPITAL IMPROVEMENT PROGRAM Short Term (0-5 years) SUB-
More informationAPPENDIX A MEASUREMENT AND PAYMENT
P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged
More informationADDENDUM NO. 1 NOVEMBER 8, 2016
SAN ANTONIO WATER SYSTEM C_13 BROADWAY CORRIDOR PROJECT SEWER REHABILIATION PACKAGE 2.C AND 4.C SAWS JOB NO. 15-45111 (2.C) & 15-4514 (4.C) SOLICITATION NO. CO-00097 ADDENDUM NO. 1 NOVEMBER 8, 2016 TO
More informationADDENDUM NUMBER THREE
January 22, 2019 Runway 17R-35L Complex Pavement Rehabilitation CONTRACT NO. 201846271 ADDENDUM NUMBER THREE This Addendum Number Three supersedes and/or supplements all portions of the Contract Documents
More informationITEM DESCRIPTION EST. QUANT. UNIT UNIT PRICE P
BID FORM (continued) DAYTON INTERNATIONAL AIRPORT TERMINAL APRON RECONSTRUCTION PHASE 2 21% DBE PARTICIPATION) FEDERAL CONSTRUCTION FUNDS) ITEM DESCRIPTION EST. QUANT. UNIT UNIT PRICE P-101-5.1.1 FULL
More informationBID FORM. TxDOT CSJ No. 1507JNCTN. Project Description: T-Hangar Development Project. Bid by: Name of Bidder. Address: Address:
BID FORM TxDOT CSJ No. 1507JNCTN Project Description: T-Hangar Development Project Bid by: Name of Bidder Address: Telephone: FAX: Email Address: To the Texas Department of Transportation hereinafter called
More informationADDENDUM #1 AUGUST 25, INTERSECTION IMPROVEMENTS AT SR 434 AND TUSCORA DRIVE Bid # ITB-06/16/BF
ADDENDUM #1 AUGUST 25, 2016 INTERSECTION IMPROVEMENTS AT SR 434 AND TUSCORA DRIVE Bid # ITB-06/16/BF TO: ALL PLAN HOLDERS This Addendum No. 1 to the Contract Documents for City of Winter Springs project
More informationBID PROPOSAL FORM
GENERAL BID INFORMATION EXHIBIT A PROJECT BID PROPOSAL FORM (ATTACHMENT FOR FORM NO. 96) A. Bidder:. B. Project Name: Parking Lot Remediation #15-01-192 C. Project Location: 1501 W. Washington Street,
More information2018 Roadway Erosion Control CONTRACT NO ADDENDUM NUMBER TWO
July 27, 2018 2018 Roadway Erosion Control ADDENDUM NUMBER TWO This Addendum Number Two supersedes and/or supplements all portions of the Contract Documents with which it conflicts. Bidders must acknowledge
More information[ADD / DELETE / MODIFY FOLLOWING ITEMS AS APPROPRIATE TO THE PROJECT:]
SECTION 14 - REMOVALS 14-1 GENERAL This item shall consist of removing, [salvaging], [abandoning,] [stockpiling] and/or disposing of existing [pavements,] [asphalt-treated bases (ATB),] [cement-treated
More informationADDENDUM NO. 2 TO PROPOSAL AND CONTRACT DOCUMENTS RUSSELL REGIONAL AIRPORT ROME, GEORGIA RUNWAY 1/19 OVERLAY FLOYD COUNTY BID NO.
ADDENDUM NO. 2 TO PROPOSAL AND CONTRACT DOCUMENTS ROME, GEORGIA TO: ALL PROSPECTIVE BIDDERS DATE: MAY 31, 2018 This Addendum forms a part of the Proposal and Contract Documents and modifies the original
More information2. Insert Pre-Bid Meeting Minutes, and Sign-in Sheet before Technical Specifications.
June 7, 207 Addendum No. To Plans, Contract Documents and Specifications CNW TSTC Waco Airport Airfield Improvements - Stage III TxDOT CSJ No. 609TSTCW This addendum shall be a part of the Plans, Contract
More informationADDENDUM NO. 1. FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA
ADDENDUM NO. 1 FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA Bids to be received until 2:00 p.m., local time, July 9, 2012 SPECIFICATIONS Delete Section 00 41 53 Bid Unit Price in
More informationMaine Turnpike Authority
PAVEMENT REHABILITATION & CLEAR ZONE IMPROVEMENTS MM 80.7 TO MM 88.6 202.121 Removing Existing Concrete (6CY) 1.00 LS 202.127 Removing of Existing Bituminous Pavement (470 SY) 1.00 LS 202.202 Removing
More informationPRE-BID MEETING August 10, :00 P.M.
PRE-BID MEETING August 10, 2018 3:00 P.M.. AGENDA INTRODUCTIONS PROJECT COMPONENTS CONTRACT TIME PROJECT SCHEDULE ENGINEER S ESTIMATE OF PROBABLE CONSTRUCTION COSTS SAFETY ON AIRPORTS DURING CONSTRUCTION
More informationAnnual 2012 Asphalt Overlay Work Order Construction Contract Job No Solicitation No. B MR BID PROPOSAL. PROPOSAL OF, a corporation a
Job No. 12-0101 Solicitation No. B-12-013-MR BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of and an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction
More informationCITY OF ALBANY Public Works Department ADDENDUM #1 ST CROCKER LANE RECONSTRUCTION
CITY OF ALBANY Public Works Department ADDENDUM # ST-6-02 CROCKER LANE RECONSTRUCTION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and shall
More information2019 Annual Airfield Pavement Rehabilitation CONTRACT NO ADDENDUM NUMBER ONE
February 13, 2019 2019 Annual Airfield Pavement Rehabilitation CONTRACT NO. 201947110 ADDENDUM NUMBER ONE This Addendum Number One supersedes and/or supplements all portions of the Contract Documents with
More informationCITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION
CITY OF ALBANY Public Works Department ADDENDUM #1 ST-13-04-2014, MAIN STREET REHABILITATION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and
More informationSan Antonio Water System ADDENDUM NO. 1
San Antonio Water System ADDENDUM NO. 1 Historic Mission Reach, Phase IV ADDENDUM NO. 1 To Bidder of Record: February 26, 2010 This addendum, applicable to work referenced above, is an amendment to the
More informationSnow Removal Equipment Storage Building
June 6, 2011 ADDENDUM 2 (Rev.1) For Snow Removal Equipment Storage Building URS Project No. 25338534 Prepared For 2933 Airport Blvd. Abilene, TX 79602 Prepared By URS Corporion 1950, North Stemmons Freeway
More informationBidder Name: ITEMIZED BID: The bidder should complete the following section in accordance with Sec 102.7. The bidder proposes to furnish all labor, materials, equipment, services, etc. required for the
More information2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationTaxiways P and P7 Drainage Improvements Re-bid CONTRACT NO ADDENDUM NUMBER ONE
Department of Aviation Airport Office Building 8500 Peňa Boulevard Denver, Colorado (303) 342-2200 www.flydenver.com March 3, 2015 Taxiways P and P7 Drainage Improvements Re-bid ADDENDUM NUMBER ONE This
More informationPublic Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel
Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED
More informationNovember 29, CITY OF PLANT CITY Purchasing Division (813)
November 29, 2018 CITY OF PLANT CITY Purchasing Division (813) 659-4270 IFB 18-014UM-LG 12-inch Water Transmission Main-Franklin St., Hancock St. and Terrace Drive West ADDENDUM No. 3 *Bidders are required
More informationCITY OF TACOMA Department of Public Utilities Tacoma Power
CITY OF TACOMA Department of Public Utilities Tacoma Power ADDENDUM NO. 1 DATE: August 4, 2017 REVISIONS TO: Request for Bids Specification No. PG17-0130F TPU Eductor Waste Decant Facility NOTICE TO ALL
More informationSTEUBEN COUNTY DEPARTMENT OF PUBLIC WORKS. 3 East Pulteney Square Bath, New York 14810
STEUBEN COUNTY DEPARTMENT OF PUBLIC WORKS 3 East Pulteney Square Bath, New York 14810 County Route 22 over Canisteo River Bridge Replacement Project BIN 3333290 D035511 PIN 6755.06 ADDENDUM #1 October
More informationA. Modifications to DIVISION 40 STANDARD CONSTRUCTION SPECIFICATIONS FOR ASPHALT SURFACING. Routed depth shall be 1-1/2 inch.
Date: April 2, 2014 To: All Planholders of Record Re: Addendum No. 3 Pavement Crack Sealing Palmer Municipal Airport This addendum consists of two (2) pages plus one (1) attachment. Attachment is as follows:
More informationACKNOWLEDGEMENT OF RECEIPT OF ADDENDUM
WELLS COUNTY HIGHWAY DEPARTMENT 1600 W. WASHINGTON STREET BLUFFTON, INDIANA 46714 PHONE 260/824-6430 FAX 260/824-6431 WELLS COUNTY HIGHWAY DEPARTMENT & BOARD OF COMMISSIONERS Date: January 8, 2019 To:
More informationURS CORPORATION NY Contract No. C REPUBLIC AIRPORT RUNWAY 1-19 RUNWAY SAFETY AREA (RSA) IMPROVEMENTS ADDENDUM NO. 3 TO:
URS CORPORATION NY Contract No. C015548 ADDENDUM NO. 3 TO: DATE: May 4, 2016 CONTRACT NO. C015548-S13-FRGRSA COUNTY: SUFFOLK IN THE LETTING OF May 16, 2016 NOTICE TO PROSPECTIVE BIDDERS The following Addendum
More informationDECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids
General Info Number: PROJECT NO. 43-17-04 : BRIDGE DECK REPAIR AND BRIDGE REMOVAL OHIO TURNPIKE OVER QUARRY ROAD, M.P. 138.0 OHIO TURNPIKE OVER INACTIVE RAILROAD, M.P. 138.2 LORAIN COUNTY, OHIO Deadline:
More informationSOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004
SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004 General: Sections of the Minnesota Department of Transportation (Mn/DOT), Standard Specification for Construction, 2000 or Current
More informationMADRAS MUNICIPAL AIRPORT TAXIWAY RECONSTRUCTION AIP NO PRE-BID CONFERENCE (VOLUNTARY) June 25, 2018 AGENDA
MADRAS MUNICIPAL AIRPORT TAXIWAY RECONSTRUCTION AIP NO. 3-41-0035-010 PRE-BID CONFERENCE (VOLUNTARY) June 25, 2018 AGENDA (Pass around sign in sheet, fill in Name, Company, Phone #, Fax #) 1. INTRODUCTIONS
More informationACKNOWLEDGEMENT OF RECEIPT OF ADDENDUM
WELLS COUNTY HIGHWAY DEPARTMENT 1600 W. WASHINGTON STREET BLUFFTON, INDIANA 46714 PHONE 260/824-6430 FAX 260/824-6431 WELLS COUNTY HIGHWAY DEPARTMENT & BOARD OF COMMISSIONERS Date: January 4, 2019 To:
More informationAddendum No. 1 Page 1 of 2
Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT
More informationADDENDUM #3. STATE ROUTE 60 AT POTRERO BOULEVARD INTERCHANGE PHASE I AND IA City Project No ; Federal Project No.
ADDENDUM #3 STATE ROUTE 60 AT POTRERO BOULEVARD INTERCHANGE PHASE I AND IA City Project No. 2016-003; Federal Project No. DEM10L-5209(008) November 9, 2017 Addendum for: AND IA STATE ROUTE 60 AT POTRERO
More informationMPA Project No. W278-C1 Project Title: Rehabilitate Runway and Other Airfield Improvements Location: Worcester Regional Airport
MPA Project No. W278-C1 Project Title: Rehabilitate Runway 11-29 and Other Airfield Improvements Location: Worcester Regional Airport RESPONSES TO QUESTIONS and/or RFI s Date: August 22, 2018 The attention
More informationApril 1, CITY OF PORTSMOUTH Public Works Department. Bid # Annual Paving Project ADDENDUM NO. 1 NOTICE TO ALL BIDDERS
April 1, 2009 CITY OF PORTSMOUTH Public Works Department Bid #54-09 2009 Annual Paving Project ADDENDUM NO. 1 NOTICE TO ALL BIDDERS This Addendum forms part of the original document marked Bid #54-09 2009
More informationForsyth County Procurement
August 1, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 Bid 17-72-3340 For: Providing all materials, equipment and labor for the Jot em Down Road Water Tank
More informationSECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.
SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section
More informationPAY QUANTITY NOTES INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS EARTHWORK WHERE NO QUANTITY IS SHOWN ON P & P SHEETS.
PAY QUANTITY NOTES (F-1) (F-2) (F-3) (F-4) (F-5) (F-6) (F-7) (F-8) (F-9) (F-10) (F-11) (F-12) (F-13) (F-14) (F-15) (F-16) (F-17) (F-18) (F-19) INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS
More informationDALLAS FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 2. Northeast End Around Taxiway Package I East Air Freight Taxiway and Utilities
DALLAS FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 2 Northeast End Around Taxiway Package I East Air Freight Taxiway and Utilities CONTRACT NO. 9500623 February 23, 2018 The Request for Bids for the
More informationDOCUMENT ADDENDA AND MODIFICATIONS
DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications
More informationADDENDUM NO. 1. for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA. Posting Date: June 20, 2013
ADDENDUM NO. 1 for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA Posting Date: June 20, 2013 BIDDERS SHALL CONFORM TO THE FOLLOWING CHANGES AS A PART OF THE BID DOCUMENTS, WHICH SHALL BECOME
More informationSUMMARY TO MINUTES OF PRE-BID CONFERENCE FOR T-HANGAR REPLACEMENT
SUMMARY TO MINUTES OF PRE-BID CONFERENCE FOR T-HANGAR REPLACEMENT SARASOTA BRADENTON INTERNATIONAL AIRPORT August 14, 2017 10:00 AM 1. INTRODUCTION Sign-in Sheet. 2. SUBMITTAL The Bid opening date is Wednesday
More informationNew Jersey Department of Transportation DATE : 05/17/12 PAGE : TABULATION OF BIDS
PAGE : 409-1 CONTRACT TIME : 02/28/13 COMPLETION DATE CONTRACT DESCRIPTION : URBAN PROJECT(S) : STATE ROUTE 45 ROADWAY DRAINAGE IMPROVEMENT CONTRACT DP 12409 BOROUGH OF WESTVILLE, GLOUCESTER COUNTY VENDOR
More informationADDENDUM NO. 1 FOR ROADWAY RECONSTRUCTION RFP # June 7, 2016
ADDENDUM NO. 1 FOR ROADWAY RECONSTRUCTION RFP #2017-01 NOTICE TO PROSPECTIVE BIDDERS June 7, 2016 Prospective bidders are hereby informed of the following corrections, additions, deletions, and/or modifications
More informationIFB # R Blythe Creek Grinder Pump Eliminations
IFB # 2019-015R Blythe Creek Grinder Pump Eliminations ADDENDUM No. 1 ISSUE DATE: October 10, 2018 *******************************************************************************************************************
More informationRUNWAY 34R EXTENSION AND RELATED WORK PACKAGE 2 BRIDGE STRUCTURE EXTENSIONS. Manassas Regional Airport ADDENDUM NO. 2
RUNWAY 34R EXTENSION AND RELATED WORK PACKAGE 2 BRIDGE STRUCTURE EXTENSIONS Manassas Regional Airport ADDENDUM NO. 2 April 19, 2013 This Addendum is hereby made a part of the Contract Documents and Specifications
More informationANSWERS TO QUESTIONS RECEIVED THROUGH 1:00 PM ON MAY 24, 2018:
ADDENDUM NO. 3 PROJECT NO. 43805 (PART A & B) PAGE 2 ANSWERS TO QUESTIONS RECEIVED THROUGH :00 PM ON MAY 24, 208: Q#32 Addendum # answered Question #7 indicating that an average depth of 3 feet for the
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2017.02 Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5 The following changes are made to the Proposal, Specifications and Plans: SPECIFICATIONS:
More informationMAY 11, 2017 T-MC-107A & T-MC-107B1
Schedule of Bid Items - Part A ROADWAY 107A 201(A) - CLEARING AND GRUBBING - LSUM 1.00 30,000.00 30,000.00 $100,000.00 $100,000.00 $65,000.00 $65,000.00 $120,000.00 $120,000.00 $50,000.00 $50,000.00 $18,262.05
More informationNovember 2, 2018 CITY OF BERKELEY FY 2018 MEASURE M STREET REHABILITATION SPECIFICATION NO C (Re-Issued) ADDENDUM NO. 1
Department of Public Works Engineering Division November 2, 2018 CITY OF BERKELEY FY 2018 MEASURE M STREET REHABILITATION ADDENDUM NO. 1 Dear Bidder: The following amendments are hereby made to the subject
More informationJob Order Sewer Repair Services
Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified
More informationBID FORM (LUMP SUM CONTRACT)
BID FORM (LUMP SUM CONTRACT) Place County of El Paso Purchasing Department Date Project No. 11-016 Proposal of (hereinafter called Bidder), a corporation organized under the laws of the State of /a partnership/an
More informationADDENDUM NO. 1 CITY OF SOUTH PORTLAND, MAINE WATERMAN DRIVE PARKING IMPROVEMENTS BID # August 21, 2014 PREPARED BY:
ADDENDUM NO. TO CITY OF SOUTH PORTLAND, MAINE WATERMAN DRIVE PARKING IMPROVEMENTS BID #04-5 August 2, 204 PREPARED BY: SEBAGO TECHNICS, INC. 75 John Roberts Road Suite A South Portland, ME 0406 3036 Addendum
More informationGeneral Water Bid Items Item No.
BID PROPOSAL PROPOSAL OF, a corporation organized and existing under the laws of the State of, a partnership consisting of, an individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018 The City of Atlanta is providing an opportunity for public comment until July 23, 2018 related to the
More informationNOTICE TO OFFERORS ADDENDUM NO. 1 WASTE COLLECTION SITE DEVELOPMENT PLAN FOR THE COUNTY OF SHENANDOAH
November 29, 2018 NOTICE TO OFFERORS ADDENDUM NO. 1 WASTE COLLECTION SITE DEVELOPMENT PLAN FOR THE COUNTY OF SHENANDOAH To Holders of Bid Proposals: Please make the following clarifications, additions,
More informationTAXIWAY 'B' CULVERT REPLACEMENT
CONTRACT DRAWINGS FOR THE CONSTRUCTION OF TAXIWAY 'B' CULVERT REPLACEMENT HALF MOON BAY AIRPORT SAN MATEO COUNTY STATE OF CALIFORNIA FAA AIP PROJECT # 3-06-0097-015-2015 (DESIGN) C&S PROJECT # I16.002.002
More informationFAA AIP No.: WKD Job No.: CA
ADDENDUM NO. 1 July 16, 2014 at 12:00 pm to the Plans, Specifications and ontract Documents for the Fairfield ounty Airport Perimeter Security Fence Project Fairfax, South arolina FAA AIP No.: 3-45-0058-013-2014
More informationC. W. Matthews Contracting Co., Inc. (L)
BID TABULATION Page 1 of 5 E.R. Snell Contractor, 001 Photograph Documentation 8 MO $110.00 $880.00 $250.00 $2,000.00 $97.17 $777.36 $1,250.00 $10,000.00 002 Traffic Control Project No. F-1056 1 LS $192,000.00
More informationNew Jersey Department of Transportation DATE : 10/21/10 PAGE : TABULATION OF BIDS
PAGE : 133-1 CONTRACT TIME : 12/20/11 COMPLETION DATE CONTRACT DESCRIPTION : URBAN PROJECT(S) : BR-080-5(094) ROUTE 80 BRIDGE OVER ROUTE 287 NORTHBOUND AND SMITH ROAD GRADING, PAVING & STRUCTURRS CONTRACT
More informationYES, we received Addendum No. 1
TRANSMITTAL SHEET Date sent: Friday, April 6, 2018 Sent to: All Planholders Deliver to: Project Estimator Transmission sent from: Reichhardt & Ebe Engineering Number of pages including this page: 36 CONFIRMATION
More informationEach Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal.
ACKNOWLEDGEMENT BY RESPONDENT Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal. This undersigned acknowledges receipt of this Addendum No. 1
More informationIII. CHANGES TO DIVISION 0 BIDDING REQUIREMENTS AND CONDITIONS OF THE CONTRACT: V. CHANGES TO DIVISIONS 2 THROUGH 16 (TECHNICAL SPECIFICATIONS):
ADDENDUM NO: 001 TO: All Planholders FROM: Parkhill, Smith and Cooper, Inc. PROJECT NAME: Littlefield Taylor Brown Municipal Airport Airfield Pavement Rehabilitation, Apron Reconstruction, Marking, Drainage
More informationFor Addendum No. 6 Revised Bid Form Page 1 of 7. Revised Bid Form
For Addendum No. 6 Revised Bid Form Page 1 of 7 Revised Bid Form Deliver bid to: CITY OF FREDERICK PURCHASING DEPARTMENT 111 AIRPORT DRIVE EAST FREDERICK MARYLAND 21701 CITY OF FREDERICK WWTP ENR UPGRADE
More informationSUBJECT: ITB , Oxford Road Complete Street Improvements Project ADDENDUM #1
DATE: May 18, 2016 TO: FROM: All Bidders/Proposers Willie Velez, CPPB Procurement Administrator City of Casselberry Purchasing Division SUBJECT: ITB-2016-0023, Oxford Road Complete Street Improvements
More informationE. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17
S&L Gravel, Section B: Proposal Page 10701.0 - TRAFFIC CONTROL - LUMP SUM 1.00 $6,425.00 $6,425.00 $6,425.00 $10,000.00 10720.0 - TRAFFIC CONTROL SIGN - PORTABLE ARROW BOARD - DAYS 25.00 $25.00 $625.00
More information