ELECTRICAL SAFETY INSPECTION REPORT

Size: px
Start display at page:

Download "ELECTRICAL SAFETY INSPECTION REPORT"

Transcription

1 ELECTRICAL SAFETY INSPECTION REPORT ALIF GARMENTS Ltd, Dhaka, Bangladesh Prepared for: JANUARY 14, 2014

2 Alif Garments Ltd. PAGE 1 SUMMARY The seven-story factory housing Alif Textiles Ltd. & Hexa Garments Ltd. located in Dhaka, Bangladesh was surveyed for Electrical Safety on 06 December 2013 by Woosun Energy and Construction Co Ltd. This summary identifies the critical and major deficiencies that were identified during the inspection as documented in the Electrical Safety Inspection Report, dated 14 January 2014, submitted to the Accord. The factory building was surveyed to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial inspection was limited to the review and identification of critical and major electrical safety issues. The inspection did not include identification of minor deficiencies, which will be further addressed as part of follow-up inspections. Table 1 summarizes the critical and major electrical safety issues identified during the inspection. Recommendations have been provided to address each issue. Reference photos are provided in Attachment 1. An implementation schedule shall be developed by the factory to remediate each of the findings in Table 1. The specific timing of improvements, including any requested extensions due to design / installation constraints, shall be submitted to the Accord for approval.

3 Alif Garments Ltd. PAGE 2 Table 1. Findings and Recommendations No. Category Finding Recommendation Timeline E-1 Transformer and service line The service lines (cables) from pole mounted outdoor transformer to 6 th floor are strung without support and protection against harsh weather. E-2 Service line from another pole mounted transformer is drawn on the 2 nd floor unsupported. E-3 The remaining opening after passing the service cables through wall on 6 th floor is not sealed. E-4 440KVA Diesel Generator set Generator is located at the ground floor left of entrance with door opening towards the entrance. E-5 Cables entering/leaving the terminal box are connected without cable gland and base pate. E-6 Cables are laid directly on concrete floor. E-7 Panels Cables entering or leaving panels are connected directly to MCCBs without supports. The cables must be weather resistant and supported with steel wire. It is recommended that the cables be drawn underground from pole to the factory building. The cables must be weather resistant and supported with steel wire. It is recommended that the cables be drawn underground from pole to the factory building. The openings must be sealed corresponding to the fire rating required in the compartment/room after the cables re-drawn. Refer to fire safety recommendations; change the door opening to avoid the main entrance. Cables terminating must be fixed using cable glands and the terminal box base must be closed with gland plates. Cables run on floors must be protected and supported on cable trays or in trenches. Cables entering or leaving panels must be firmly fixed/supported at the base plate using cable glands Photo Ref E.1 E.2 E.3 E.4 E.5 E.6 E.7

4 Alif Garments Ltd. PAGE 3 No. Category Finding Recommendation Timeline E-8 Spacing between different phases The copper bus bars may be and bus bars are too close and redesigned and insulated to sign of arcing is seen (main panel) prevent arcing between different E-9 Cables in panels are dressed with sharp bends. E-10 Flexible PVC conduit used to cover wiring inside and outside panels E-11 Bus bar chamber (panel) is too congested and does not have adequate space inside for maintenance. E-12 Phase barrier between different phases are not installed in MCCBs E-13 Wiring inside panels are extended through mid -span joints or repaired with PVC insulation tapes. E-14 Receptacles Two socket outlets are connected through a circuit. phases and earthed parts. Cables and wires in panels must be dressed and fixed to panel safely without stress. Cables must be supported on cable trays/ladders or raisers and fixed firmly on the wall. The bus bar panel must be designed in accordance to the number of cables connecting and the rating of the bus bar. Phase barriers between different phases for voltage exceeding 230 volts must be installed. Joints must be avoided and wires damaged must be repaired by soldering and insulated such that it has sufficient electrical and mechanical strength. It is recommended that joints and repairing 1 (when the conductor is damaged) must be avoided. Socket outlets must be connected with separate circuit and connected with earth. Within 6 Within 6 Within 6 Photo Ref E.8 E.9 E.10 E.11 E.12 E.13 E.14 1 Repairing wiring for damaged conductor is not permitted. Repair of damaged insulation may be permitted if the engineer verifies that the wire has adequate electrical insulation and mechanical strength after repairing.

5 Alif Garments Ltd. PAGE 4 No. Category Finding Recommendation Timeline E-15 Fluorescent light fittings are not Light fittings must be safely covered (connections and fitting installed and all live parts must be wiring) and connections are covered. All metal parts/frames exposed. must be earthed. E-16 Fans and lights are extended from the same wiring and fan locations. E-17 Wiring & Cables Cables laid on floors/ceilings or walls are not protected. E-18 Cables and wirings are run through stairways. E-19 Wiring is drawn out from the conduit junction boxes for modification / extension of wirings. Every lighting circuit must not be connected/loaded more than the designed rating 2. The joints must be looped at the terminals 3. Cables run on floors must be supported on cable trays or laid in trenches. Cables on walls must be supported on ladder or raisers. Main cables passing through different floors must be separated through service shaft or enclosed in corresponding fire rated enclosures as per the compartment/room it passes through. It is recommended that stairways not be used as electrical shafts. Practice of extending existing wiring must stopped 4 and all modifications must be re-wired, by safe practices, to avoid joints in wires. Within 6 Photo Ref E.15 E.16 E.17 E.18 2 Each lighting circuit must not be connected with more than 800W. 3 Mid-span joints must be avoided in circuits (between switch & light fittings or between fittings connected in parallel. 4 Any additional points must be connected through new wiring from the distribution panel either the existing supports or installing additional supports.

6 Alif Garments Ltd. PAGE 5 No. Category Finding Recommendation Timeline E-20 Wooden ducts, without cover, are used as wiring supports in the production floors. Some insulation damages (probably by rats) can be seen in wiring. E-21 Wires are joined (mid-span and Tee joints) are made in wooden ducts and repaired/insulated using PVC insulation tape. E-22 Wiring in boiler room is not protected from external heat. E-23 Connection in terminal box is not protected and not maintained (box cover open) regularly. E-24 Wiring inside boiler control panels is not dressed and protected. Wooden ducts must be replaced with safe factory fabricated ducts. The ducts may be designed such that the wirings supported in it are safe and protected from dust and external damages. Joints in cable ducts must be avoided and where PVC insulation are to be repaired (minor damages), it must be insulated and tested (IR measurement). Wirings in boiler room must be protected from external heat 5. Wires must not be joined other than at the designated terminals. Terminals boxes must be covered to protect from dust and physical damages besides risk of electric shock to the operators. Cables and wiring must be firmly fixed to the devices and protected/supported to prevent damages (aging of insulator) due to heat from boiler. Wiring inside boiler control panel must be checked and maintained on regular basis. The wiring after maintenance must be redressed safely. Within 6 Photo Ref E.19 E.20 E.21 E.22 E.23 5 Wiring must be protected from external heat by enclosing in heat resistant covers, placing at safe distance on supports or using heat rated cables/wires.

7 Alif Garments Ltd. PAGE 6 No. Category Finding Recommendation Timeline E-25 Extension of wiring and additional PVC flexible conduits must not be Within 6 wires are drawn in flexible conduit used for permanent wirings 6 and and not supported. when used in short points, must be supported/fixed on wall/ceiling PVC conduits are not firmly at regular intervals to avoid stress. supported/fixed with saddles. E-26 Transitions between different wiring systems are not covered or adapted for proper joints. E-27 The openings left after passing the main cables through walls are not sealed. E-28 Conduit wiring systems crossing building expansion joints without expansion joints. E-29 Earth systems Mid-span and tee joints are made in earth conductors. Wiring system must be consistent and try to use single system from distribution board to load points. All additional points must be wired in separate conduit/duct, without crossing existing wirings. The opening (excess) remaining after passing the cables must be sealed such that it meets the fire resistant specifications. Conduit wiring must avoid crossing expansion joints and where it is unavoidable, conduit expansion joints must be used. Joint in earth conductors (midspan and tee) must be avoided. All earth connections must be distributed from earth strips installed in panels. Within 6 Photo Ref E.24 E.25 E.26 E E PVC flexible must not be used in industrial wiring of permanent nature. Where unavoidable, the flexible conduit selected must be industrial grade.

8 Alif Garments Ltd. PAGE 7 No. Category Finding Recommendation Timeline E-30 Panels and metal parts of All panels must be connected to Within 6 electrical appliances/devices used earth at least at two points for are not earthed. guaranteed earth connection. All metal parts of electrical appliances and devices must be connected to earth. Panel doors and other metal parts used must be connected with earth bond. Photo Ref

9 Alif Garments Ltd. PAGE 8 ATTACHMENT 1 PHOTOGRAPHS OF FINDINGS/ISSUES

10 Alif Garments Ltd. PAGE 9 Pole mounted transformer Photo E.1 Service Line cables, entering factory building at 6 th Floor, without supports 2 nd Service cable entering 1 st floor Photo E.2 Second service cables, entering building at 1 st floor, without supports Photo E.3 Opening after service cable passed through wall not sealed

11 Alif Garments Ltd. PAGE 10 Photo E.4 Generator room door opening to main stair ways at ground floor Photo E.5 Cables in the generator terminal box directly supported at the terminations Photo E.6 Cables in Generator room laid directly on concrete floor

12 Alif Garments Ltd. PAGE 11 Photo E.7 Cables not supported with glands and base plates in panels Photo E.8 Bus bars in panels without maintaining safety clearances (typical) Photo E.9 Cables and wirings in Panels stressed and not arranged safely (typical)

13 Alif Garments Ltd. PAGE 12 Photo E.10 Flexible PVC conduits are used to protect wires and cables Photo E.11 Bus Bar panel without maintaining safety clearances (typical) Photo E.12 Phase barrier plates not installed in MCCB (typical)

14 Alif Garments Ltd. PAGE 13 Photo 13 Single fire alarm bell provided on each floor Photo E.14 Two socket outlets connected to a circuit Photo E.15 Fitting connections (fluorescent light) not covered

15 Alif Garments Ltd. PAGE 14 Photo E.16 Cables on floors and wall not supported and not protected (typical) Photo E.17 Cables in stair ways (not service shaft) Photo E.18 Wiring extended from conduit junction box (with joints) (typical)

16 Alif Garments Ltd. PAGE 15 Photo E.19 Wooden ducts supporting wirings are not covered. Conductor insulation damaged by rats (inset) Photo E.20 Wire joints in duct (typical) Photo E.21 Wiring and cables in boiler room not protected from external heat (typical)

17 Alif Garments Ltd. PAGE 16 Photo E.22 Connection of devices in Boiler room not protected and fixed (typical) Photo E.23 Wiring inside boiler control panel not arranged/dressed (typical) Photo E.24 Conduit wirings (flexible/rigid) on ceilings and walls not fixed adequately (typical)

18 Alif Garments Ltd. PAGE 17 Photo E.25 Transition between different wiring systems not safe (typical) Photo E.26 Gaps not sealed/protected after wirings passed through walls and ceilings (typical) Expansion joints Photo E.27 Conduit wiring crossing expansion joints

19 Alif Garments Ltd. PAGE 18 Photo E.28 Earth conductor joints (typical)

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH January 14, 2013 Redpoint Jackets Ltd. PAGE 1 SUMMARY The four-story factory housing Redpoint Jackets Ltd. located in Dhaka Export

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. SREERAMPUR, DHAKA, BANGLADESH Factory List: Graphics Textiles Limited Inspected on May 20, 2014 SUMMARY Graphics Textiles Limited is located in Sreerampur, Dhaka. Reportedly,

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT TARATEX (BD) LTD. Plot 23/1, Sataish Road, Tongi, Gazipur, Bangladesh Factory List: 1) Taratex (BD) Ltd. 2) S. P. M Design Ltd. Inspected by : Luv Kumar Chhetri Report

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Sumilpara, Adamjee Nagar, Shiddirgonji, Narayangonj, Bangladesh Factory List: 1. Moonlux Kinit Garments Limited. 2. West knit Wear Limited. 3. West Fashion. 4. Moonlus

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ABIR FASHIONS Kutubail, Fatullah (Post Office Road), Narayangonj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi & Mamun Report Generated by: Pema Wangdi Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ACTIVE COMPOSITE MILLS LTD. Dewan Idris Road, Zirabo, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Active Composite Mills Ltd. Inspected by: Hemlal Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. House 8 & 10, Road 3, Section 7, Mirpur Industrial Area, Dhaka, Bangladesh Factory List: 1. Alliance Garments Ltd. Inspected on May 5, 2014 ELECTRICAL SAFETY INSPECTION

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT BOVS APPARELS LTD. JAMUR MUCHIPARA, HEMAYETPUR, SAVAR, DHAKA, BANGLADESH Factory List: 1. BOVS APPARELS LTD. Inspected on April 13, 2014 SUMMARY The Bovs Apparels Ltd

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Plot # B-32,BSCIC I/E,Tongi,Gazipur Factory List: 1. Kento Asia Limited. Inspected on May 15, 2014 SUMMARY Kento Asia Ltd. factory is established in a rented premises

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT M/S. PROUD TEXTILE Plot 31/A, BSCIC Industrial Estate, Fatullah, Narayanganj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi Report Generated by: Pema Wangdi

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FRESH FASHION WEAR LTD. 638, Sharifpur, P.O-National University, Gazipur Sadar, Bangladesh Factory List: 1. Passion Apparels and Wears Ltd. 2. Inspected by: Jobair Ibna

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA ROAD, DHAKA, BANGLADESH. Factory List: 1. Inspected on May 14, 2014 ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT K.L FASHION LTD. 75/1, Mudafa West, Master Bari, Tongi, Gazipur, Bangladesh Factory List: 1. Inspected by: Jobair Ibna Abdul Alim Report Generated by: Jobair Ibna Abdul

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT LIBAS TEXTILES LTD., Mouchak, Kaliakoir, Gazipur, Bangladesh Factory List: 1. Libas Textiles Ltd. Inspected on April 6, 2014 SUMMARY The Libas Textiles Ltd., factory

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADHUNIK POSHAK SHILPA LIMITED Civil Engineer Tower, Mirpur, Dhaka, Bangladesh Factory List: 1. Adhunik Poshak Shilpa Ltd. 2. Crazy Fashions Ltd. 3. Kazipur Fashion Ltd.

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT Zirabo Bazar, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Inspected by: Khan & Tapu Report Generated by: Khan Inspected on Feb 6 th 2015 SUMMARY factory building

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FASHION FORUM LTD. 53-54, Diakhali, Zamgara, savar, Dhaka, Bangladesh. Factory List: 1. Fashion Forum Ltd. 2. IDS Washing Ltd. Inspected by: Karma Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SINCERE KNIT GARMENTS LIMITED UNIT-1 East Isdair, Chandmari, Fatullah, Narayangonj, Bangladesh Factory List: 1. Unit-1 2. Fakir Knit Ltd. Inspected by: Sherab Dorji

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT METRO KNITTING & DYEING MILLS LTD.(FACTORY-02), CHARBAG, ASHULIA, SAVAR, DHAKA, BANGLADESH Factory List: 1. Inspected by: Younten Report Generated by: Das Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AKH APPARELS LIMITED 128 Hemayetpur, AKH Tower, Savar, Dhaka-1340, Bangladesh. Factory List: 1. AKH Apparels Limited Inspected by: Deonarayan Khatiwara Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MAHID APPAREL LTD. Nowpara, Madhabdi, Narsingdi, Bangladesh Factory List: 1. MAHID APPAREL LTD. Inspected by: Nazmul Huda Report Generated by: Nazmul Huda Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AG s APPARELS LIMITED. Plot No. A/1&2 Block-B, BSCIC I/A Fouzderhat, Sagarika Road, Dhaka-1207, Bangladesh Factory List: 1. AG s Apparels Limited. Inspected by: Sherub

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT, SOUTH VANGNAHATI, SREEPUR, GAZIPUR, BANGLADESH. Factory List: 1. Hams Garments Ltd. Inspected on April 03, 2014 ELECTRICAL SAFETY INSPECTION REPORT, GAZIPUR, BANGLADESH

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FIRST WEAR LMITED 68/Y, Sagarika Road, Pahartoli, Chittagong, Bangladesh Factory List: 1. Inspected by: Moin Hasan Report Generated by: Moin Hasan Inspected on August

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AHMED FASHIONS 34/1, Darus Salam Road (Technical), Mirpur-1, Dhaka, Bangladesh. Factory List: 1. Inspected by: Yang Generated by: Yang Inspected on 06 March 2015 SUMMARY

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT (1ST FLOOR BOTH WINGS) CHITTAGONG EXPORT PROCESSING ZONE SOUTH HALISHAHAR, CHITTAGONG Factory List: 1. 2. Regency Garments Ltd. 3. ABC Camp Inspected on May 10, 2014

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. ANTIM KNIT COMPOSITE LTD., Barpa, Rupshi, Rupgonj, Narayangonj, Bangladesh. Factory List: 1. Antim Knit Composite Ltd. 2. Antim Knitting & Finishing Ltd. Inspected

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th) Factory Name Address Shashongaon, Plot - S, A-646, Enayet nagar, Fatullah,Narayanganj Factory ID 9468 Electrical Safety dates Initial Date 07/07/2014 20/09/2016 Date of 5 th Follow Up Report Received Date

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th) Factory Name Address Joyna Bazer Road, Jamirdia, Valuka Factory ID 9504 Electrical Safety dates Initial Date 06/07/2014 Date of 5 th Follow Up Report Received Date 07/27/2015 Date of 6 th Follow Up Date

More information

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING 2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING E3305.3: now reads The space equal to the width and depth of the panelboard and extending

More information

DEPARTMENT OF PLANNING SERVICES BUILDING INSPECTION DIVISION 1555 N 17 TH AVENUE, GREELEY, CO (970)

DEPARTMENT OF PLANNING SERVICES BUILDING INSPECTION DIVISION 1555 N 17 TH AVENUE, GREELEY, CO (970) DEPARTMENT OF PLANNING SERVICES BUILDING INSPECTION DIVISION 1555 N 17 TH AVENUE, GREELEY, CO 80631 (970) 400-6100 BASIC REQUIREMENTS FOR WIRING A SINGLE FAMILY DWELLING Colorado State law permits individuals

More information

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL). 16450 GROUNDING ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 05 26 An optional keynote to the

More information

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

(Condensed from National Electric Code)

(Condensed from National Electric Code) WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,

More information

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION E11 : General Electrical Earthing and LIGHTNING Protection PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION 1 2009-05-12 Review of Mechanical / Electrical and Control

More information

SECTION EARTHING AND EARTH FAULT PROTECTION

SECTION EARTHING AND EARTH FAULT PROTECTION SECTION 16660 PART 1 - GENERAL 1.01 DESCRIPTION A. The work to be performed includes, but is not necessarily limited to, all work involved with the construction and assembly of a complete electrical earthing

More information

OVERHEAD SERVICES - SECONDARY

OVERHEAD SERVICES - SECONDARY OVERHEAD SERVICES - SECONDARY Contents - Overhead Services... O-1 General Requirements for Overhead Service... O-2 Names of Parts for Overhead Service... O-3 Service Attachment on an Unguyed Service Mast...

More information

Basic Requirements for Residential Electrical Installations

Basic Requirements for Residential Electrical Installations Basic Requirements for Residential Electrical Installations Wayne County Building Department 428 West Liberty Street Wooster, Ohio 44691 Phone: 330-287-5525 Fax: 330-287-5649 This brochure is intended

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge

More information

Homeowner electrical wiring guide. Including the 2015 Canadian Electrical Code amendments

Homeowner electrical wiring guide. Including the 2015 Canadian Electrical Code amendments Homeowner electrical wiring guide Including the 2015 Canadian Electrical Code amendments Table of Contents Homeowner electrical wiring guide... 1 Required inspections... 2 Rough inspections (prior to any

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS PART 1 - GENERAL 01.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this Section.

More information

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS ISSUE DATE: 5/1/90 EFFECTIVE DATE: 2/4/92 REVIEW DATE:

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

METERING INSTALLATION

METERING INSTALLATION 4.01 METERING SPECIFICATIONS METERING INSTALLATION Metering specifications will be issued to the customer by OPPD. Metering specifications are required before any work is started on all new wiring or additions

More information

Temporary Wiring. Low-Voltage Electrical Safety Orders

Temporary Wiring. Low-Voltage Electrical Safety Orders Temporary Wiring Low-Voltage Electrical Safety Orders 2405.1. Scope. Except as specifically modified in this Article, all other requirements of this Order for permanent wiring shall also apply to temporary

More information

RESIDENTIAL BUILDING REQUIREMENTS

RESIDENTIAL BUILDING REQUIREMENTS RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell

More information

IET Wiring Regulations (BS 7671:2008+A3:2015) - SECTION 705 AGRICULTURAL AND HORTICULTURAL PREMISES

IET Wiring Regulations (BS 7671:2008+A3:2015) - SECTION 705 AGRICULTURAL AND HORTICULTURAL PREMISES IET Wiring Regulations (BS 7671:2008+A3:2015) - SECTION 705 AGRICULTURAL AND HORTICULTURAL PREMISES 705.1 Scope The particular requirements of this section apply to fixed electrical installations indoors

More information

Click here to get back to 2011 NEC Code Updates Part 1

Click here to get back to 2011 NEC Code Updates Part 1 www.garyklinka.com Page 1 of 13 2011 NEC Code Updates Code Language Part 1 Click here to get back to 2011 NEC Code Updates Part 1 100 Definitions Ampacity. The maximum current, in amperes, that a conductor

More information

SECTION GROUNDING

SECTION GROUNDING SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment

More information

RESIDENTIAL QUICK REFERENCE

RESIDENTIAL QUICK REFERENCE RESIDENTIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

Huntsville Utilities Underground Residential Service Requirements

Huntsville Utilities Underground Residential Service Requirements Huntsville Utilities Underground Residential Service Requirements Sections: Scope General Conduit Installation Conduit Termination at Riser Pole Conduit Termination at Padmount Transformer or Secondary

More information

Same as Client Address. 40, Havelock Close. India Way. London. Postcode: W12 7NQ

Same as Client Address. 40, Havelock Close. India Way. London. Postcode: W12 7NQ DOMESTIC ELECTRICAL INSTALLATION CONDITION REPORT Issued in accordance with British Standard BS 7671 - Requirements for Electrical Installations Certificate Reference: 1 DETAILS OF THE CLIENT 2 ADDRESS

More information

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with):

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with): DOMESTIC ELECTRICAL INSTALLATION CONDITION REPORT Issued in accordance with British Standard BS 7671 - Requirements for Electrical Installations Certificate Reference: DEICR000021652 1 DETAILS OF THE CLIENT

More information

City of Santa Monica Building and Safety Division

City of Santa Monica Building and Safety Division This is to be used as a general checklist; it is not inclusive of all code requirements and inspection criteria. General requirements Verify that address on permit matched Address, Description and Approvals:

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

a) Line and load compartments must be separated by a stable barrier.

a) Line and load compartments must be separated by a stable barrier. 1.00 GENERAL 1.01 The electric utility shall furnish and connect all meters, instrument transformers, test switches, and meter control wiring necessary to complete the meter installation. 1.02 The customer

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

AS/NZS 3000: 2018 Changes to Wiring Rules Standard

AS/NZS 3000: 2018 Changes to Wiring Rules Standard BUILDING SERVICES Ref: BCA 19-01 Current at January 2019 AS/NZS 3000: 2018 Changes to Wiring Rules Standard The new edition of AS/NZS 3000 Wiring Rules Standard (Electrical Installations) was published

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 604 NOVEMBER 2004 CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:

More information

HOMEOWNER PERMITS AND ELECTRICAL WIRING GUIDE

HOMEOWNER PERMITS AND ELECTRICAL WIRING GUIDE HOMEOWNER PERMITS AND ELECTRICAL WIRING GUIDE Revised 20 1 APPLICATION FOR HOMEOWNER PERMITS This pamphlet is only a guide. It describes methods of installation that have been tried and tested and which

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 614 NOVEMBER 2012 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT TABLE OF CONTENTS 614.01 SCOPE 614.02 REFERENCES 614.03 DEFINITIONS

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

CITY OF GRANDE PRAIRIE

CITY OF GRANDE PRAIRIE Inspection Services CITY OF GRANDE PRAIRIE HOMEOWNER S PERMIITS AND WIRING GUIDE FOR ELECTRICAL INSTALLATIONS 2016 INDEX Page Applying for an Electrical Permit 3 Permit Application Requirements 3 Permit

More information

Standard of Practice - Campus Electrical Distribution System

Standard of Practice - Campus Electrical Distribution System A26.3 Standard of Practice - Campus Electrical Distribution System NOTE: Significant revisions or additions to the previous standards are highlighted in italics. GENERAL Designers shall verify that all

More information

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.)

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.) SBI-AO2 Project Residency Rd Br-elect/RBO-4 SCHEDULE OF QUANTITIES FOR ELECTRICAL WORKS. DATE : 24/4/2018 Sl. No. DESCRIPTION OF WORK UNIT QTY 1 READYMADE FINAL DISTRIBUTION BOARDS Supply, Instillation,

More information

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual [Type text] Heber Light & Power Developers & Excavators Electrical Service Requirements Manual May 2017 E.1.1 - GENERAL REQUIREMENTS PURPOSE This section was prepared to aid developers, contractors, engineers

More information

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance. SERVICE ENTRANCES 3.01 POINT OF ENTRANCE General Service The customer, or the customer s electrician, should provide OPPD with a site plan, load schedule, and voltage requirements when requesting service.

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Grounding & Bounding. 1. Bonded Connected to establish electrical continuity and conductivity.

Grounding & Bounding. 1. Bonded Connected to establish electrical continuity and conductivity. & Bounding Article 100 Definitions 1. Bonded Connected to establish electrical continuity and conductivity. 2. Raceway fittings bonds sections of raceway Bonding jumper bonds receptacles to boxes Threaded

More information

T. SUNDUPALLI BRANCH (04427)

T. SUNDUPALLI BRANCH (04427) STATE BANK OF INDIA T. SUNDUPALLI BRANCH (04427) REGION 2, KADAPA RURAL TIRUPATI (A.O) ELECTRICAL WORK BILL OF QUANTITIES SL. NO. DESCRIPTION QTY. UNIT RATE AMOUNT Rs. Rs. 1 Supply, installation, testing

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin February 2019 Page 1 of 5 2018 CANADIAN ELECTRICAL CODE SUBJECT: Section 6 Services and service equipment Rule 6-102 Number of supply services permitted Row housing

More information

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID SBI INFRA MANAGEMENT SOLUTIONS PVT.LTD. 3 rd Floor, Local Head Office,Bank Street, Koti, Hyderabad- 500095 On behalf of On behalf of On behalf of Cash Management Product GOC (CMP GOC) & Internal Audit

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL 8.01 GENERAL This material is not intended to cover service from OPPD s network in the downtown Omaha area. See Chapter 12 for details

More information

WALCHAND COLLEGE OF ENGINEERING, SANGLI An Autonomous Institute Government Aided Institute TENDER DOCUMENT. TENDER FORM COST : Rs.

WALCHAND COLLEGE OF ENGINEERING, SANGLI An Autonomous Institute Government Aided Institute TENDER DOCUMENT. TENDER FORM COST : Rs. WALCHAND COLLEGE OF ENGINEERING, SANGLI An Autonomous Institute Government Aided Institute TENDER DOCUMENT TENDER FORM COST : Rs.500/- LAST DATE OF RECEIVING 2 nd September, 2016 up to 12:00 noon DATE

More information

CS-21 STREET STRUCTURES TABLE OF CONTENTS

CS-21 STREET STRUCTURES TABLE OF CONTENTS TABLE OF CONTENTS CS-21.0 Street Structures... 1 CS-21.1 Road Signs... 1 CS-21.2 Safety Barriers... 1 CS-21.3 Bollards and Removable Bollards... 1 CS-21.4 Pedestrian Barrier Rails and Handrails... 1 CS-21.5

More information

Article 300: Wiring Methods And Materials

Article 300: Wiring Methods And Materials Part E: Code Book Questions Article 300: Wiring Methods And Materials 1.! Conductors of A.C. or D.C. circuits rated 600 volt or less, shall be permitted to occupy the same! conduit if.! (a)!conductors

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

Sections through of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE

Sections through of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE Sections 5-100 through 5-105 of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE Sec. 5-100. Adoption of published code. There is hereby adopted

More information

Section 7: Specifications

Section 7: Specifications Section 7: Specifications 29 31 Building Boundary of Clear Area See Note # 1 8' Shrubs 8' Concrete Pad Equipment 8' TRAVELED WAY M Meter Pedestal 8' Curb Protective Vehicle Posts (Bollards) If Required

More information

DEVICES AND LUMINAIRES

DEVICES AND LUMINAIRES CHAPTER 40 DEVICES AND LUMINAIRES SECTION E4001 SWITCHES E4001.1 Rating and application of snap switches. General-use snap switches shall be used within their ratings and shall control only the following

More information

WIRING METHODS CHAPTER 38

WIRING METHODS CHAPTER 38 CHAPTER 38 WIRING METHODS SECTION E3801 GENERAL REQUIREMENTS E3801.1 Scope. This chapter covers the wiring methods for services, feeders and branch circuits for electrical power and distribution. E3801.2

More information

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 5/12/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 5/12/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 5/12/10 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. Is it illegal to install a wet-niche luminaire face-up

More information

Section 70 Airport Transformer Vault and Vault Equipment (FAA L-109)

Section 70 Airport Transformer Vault and Vault Equipment (FAA L-109) Black text from standard FAA spec Strikeout text deletions from FAA standard spec Blue text additions to FAA standard spec Red text notes to the Engineer/won t appear in spec I. DESCRIPTION 1. This item

More information

Specifications for Residential Overhead Electric Service Installation

Specifications for Residential Overhead Electric Service Installation Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be

More information

SECTION FIELD PANELS

SECTION FIELD PANELS Stanford University Facilities Design Guidelines SECTION 25 14 23 FIELD PANELS PART 1 - GENERAL 1.1 SUMMARY A. This section includes control panel and enclosure requirements for building control systems.

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES 7.01 GENERAL UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES Also refer to Chapter 3 (Service Entrances), and Chapter 4 (Metering Installation). OPPD will install,

More information