ELECTRICAL SAFETY INSPECTION REPORT

Size: px
Start display at page:

Download "ELECTRICAL SAFETY INSPECTION REPORT"

Transcription

1 ELECTRICAL SAFETY INSPECTION REPORT M/S. PROUD TEXTILE Plot 31/A, BSCIC Industrial Estate, Fatullah, Narayanganj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi Report Generated by: Pema Wangdi Inspected on February 20 th 2015

2 SUMMARY The M/S Proud Textile factory is established its nine storied (G+8) building and a rented six storied (G+5) building. The two buildings are adjoined and are interconnected. The whole ground floor of the building is occupied by an embroidery factory. The nine storied building and six storied building were constructed in the 1998 and 1997 respectively. Production in these buildings began in the The building has been formally approved for industrial purposes. During the time of the inspection, the factory accommodated a total of about 489 workers working on regular basis. The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The purpose of the survey was to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial electrical safety inspection was limited to the review and identification of major electrical safety issues. The inspection did not include identification of minor deficiencies, which would be further dealt with as part of follow-up inspections. The table below summarizes the major electrical safety issues identified during the inspection. Recommendations have been provided to each finding. The implementation schedule shall be developed by the factory to remediate each of the findings. The specific timing of improvements, including any requested extensions due to design/installation constraints, shall be submitted to the Accord for an approval. Page 2 of 16

3 FINDINGS AND RECOMMENDATIONS FINDING NO: E-1 CATEGORY: DESIGN, DRAWINGS & RECORDS Electrical Single Line Diagram (SLD) is unavailable. Draw as-built electrical SLD mentioning all required information by qualified engineer and get it reviewed by Accord. REMEDIATION TIMEFRAME: 12 WEEKS FINDING NO: E-2 CATEGORY: DESIGN, DRAWINGS & RECORDS Thermographic scanning of the entire electrical system has not been performed. Thermographic scanning of the entire electrical system must be performed twice in a year. PRIORITY: P1 REMEDIATION TIMEFRAME: 8 WEEKS FINDING NO: E-3 CATEGORY: DESIGN, DRAWINGS & RECORDS Insulation resistance test of electrical equipment is not performed. Insulation resistance test of all power cables (up to floor distribution board or SDB) must be performed in a periodic manner and recorded. REMEDIATION TIMEFRAME: 8 WEEKS Page 3 of 16

4 FINDING NO: E-4 CATEGORY: DESIGN, DRAWINGS & RECORDS Earth pits are not identifiable Identify each earth pit and mark it for periodic maintenance purpose REMEDIATION TIMEFRAME: 8 WEEKS FINDING NO: E-5 CATEGORY: DESIGN, DRAWINGS & RECORDS Earth Pit resistance record is unavailable Record earth pit resistance for all the earth pit and do once in a year REMEDIATION TIMEFRAME: 8 WEEKS FINDING NO: E-6 CATEGORY: DESIGN, DRAWINGS & RECORDS Electric safety program is not initiated. Electrical safety training and awareness program for the electrical personnel and workers must be initiated and recorded. REMEDIATION TIMEFRAME: 8 WEEKS FINDING NO: E-7 CATEGORY: LIGHTNING PROTECTION & EARTH Lightning Protection System (LPS) needed but has not been installed. Design and install Lightning Protection System (LPS) in the factory; the LPS designs must be submitted to Accord before starting installation. PRIORITY: P1 REMEDIATION TIMEFRAME: 8 WEEKS Page 4 of 16

5 FINDING NO: E- 8 CATEGORY: SERVICE LINE Service line between the pole mounted distribution transformer and building are not supported. Service cables must be supported on trays or raisers throughout its length to prevent any damage to its cable insulation. REMEDIATION TIMEFRAME: 5 WEEKS LT service line from the DPDC transformer FINDING NO: E-9 MCCB and re-wireable fuses mounted on wooden plank/board (typical) Provide metallic enclosure instead of wood for the MCCB and replace the semi-enclosed rewire able fuses with MCCB and put inside the metallic enclosure. PRIORITY: P1 REMEDIATION TIMEFRAME: 10 WEEKS The distribution board FINDING NO: E-10 CATEGORY: GENERATOR ROOM Generator output cables laid on concrete floor without protection. Cable terminating at Generator output terminal box must be supported on riser and protected. Existing cables laid on floor may be installed in covered cable trench or on trays. PRIORITY: P1 REMEDIATION TIMEFRAME: 5 WEEK The diesel generator output cables Page 5 of 16

6 FINDING NO: E- 11 CATEGORY: TRANSFORMER ROOM Oil cup below transformer breather is empty. Breather oil cup must be filled with transformer oil to required level as instructed by the manufacturer. PRIORITY: P1 REMEDIATION TIMEFRAME: 1 WEEK The transformer breather FINDING NO: E- 12 CATEGORY: GENERATOR ROOM Generator battery placed without cover. Generator Battery must be placed on the battery stand made of noncombustible, acid proof material (steel fabricated frame). REMEDIATION TIMEFRAME: 5 WEEKS The generator batteries FINDING NO: E- 13 MCCBs mounted on wall without enclosure. Protective devices should be encased in metal casing made of 20 SWG thickness metal sheets to reduce the risk of fire spreading due to short circuit. PRIORITY: P1 REMEDIATION TIMEFRAME: 5 WEEKS The MCCBs mounted on the wall Page 6 of 16

7 FINDING NO: E- 14 CATEGORY: CABLE & CABLE SUPPORT Cables are not arranged on the cable tray. Cable must be arranged and latched properly on the cable tray. Provide cover made of noncombustible material preferably metallic sheet to protect the cables insulation from physical damage as well as prevent the ingress of debris, dust and lint. REMEDIATION TIMEFRAME: 10 WEEKS Cables entering/exiting the changeover switch FINDING NO: E- 15 Panel doors not connected with earth bond. All metal panel doors must have an earth connection of at least 4 rm earth cable. The changeover switch FINDING NO: E- 16 Inadequate working space around changeover switch. Ensure at least 1.07 meter (or equal to the width of board, whichever is higher) working clearance in front of each panel. The changeover switches Page 7 of 16

8 FINDING NO: E- 17 Cable glands are not used and the changeover switch base/top is not sealed Provide cable gland according to the respective cable size so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. REMEDIATION TIMEFRAME:10 WEEKS The changeover switch FINDING NO: E- 18 Multiple cables are terminated into single point of changeover switch. Multiple cable termination from the changeover switch terminal must be removed. A distribution panel must be installed to avoid multiple cable termination. The changeover switches Page 8 of 16

9 FINDING NO: E- 19 CATEGORY:GENERATOR ROOM Generator frame not connected to earth properly. Two separate earthing (35 sq. mm) for generator frame/body and one separate earthing (35 sq. mm) for neutral must be installed for generator. The earth resistance should one exceed 1 ohm. The generator frame earth FINDING NO: E- 20 CATEGORY:BOILER & COMPRESSOR ROOM Compressor input cables laid on floor without protection. Use steel pipe/cable tray to ensure the mechanical protection of the cable laid on floor otherwise cable insulation may damage due to falling object or stepping of occupants onto it. REMEDIATION TIMEFRAME:10 WEEKS The air compressor FINDING NO: E- 21 CATEGORY: GENERATOR ROOM Combustible materials in generator room. Generator room must be kept clean and dry. PRIORITY: P1 REMEDIATION TIMEFRAME:1 WEEK Combustible materials in generator room Page 9 of 16

10 FINDING NO: E- 22 CATEGORY: GENERATOR ROOM Inadequate working space around the generators. Expand the existing generator room to provide safe working space as per BNBC table or keep sufficient space (1.07 meter preferably) around the generator. The generator room FINDING NO: E- 23 CATEGORY: CABLE & CABLE SUPPORT Cables are not protected and randomly arranged in cable tray. Cable must be arranged and latched properly on the cable tray. Provide cover made of noncombustible material preferably metallic sheet to protect the cables insulation from physical damage as well as prevent the ingress of debris, dust and lint. Keep 20%-30% free inside cable tray/channels/ducts for proper heat dissipation. The cables on the tray FINDING NO: E- 24 CATEGORY:BOILER & COMPRESSOR ROOM Power cables encased in PVC flexible duct laid on concrete floor. Install cable tray to protect the compressor power cables. Provide covers made of noncombustible material preferably metal to protect the cable s insulation from any physical damage as well as prevent the ingress of debris, dust and lint. PRIORITY: P1 REMEDIATION TIMEFRAME:1 WEEK The compressor room Page 10 of 16

11 FINDING NO: E- 25 CATEGORY: CABLE & CABLE SUPPORT Cables drawn in a haphazard manner. The cables are not supported/protected. The cables must be dressed and shall be drawn in covered cable tray or rigid conduit. PRIORITY: P3 The cables in the compressor room FINDING NO: E- 26 Unused gland holes in top and base plates left open. The unused gland holes must be sealed using suitable size panel hole plugs. REMEDIATION TIMEFRAME:1 WEEK The distribution board Page 11 of 16

12 FINDING NO: E- 27 CATEGORY:BOILER & COMPRESSOR ROOM Boiler is not separated from the work place. Separate the boiler from working area by constructing fire rated construction. REMEDIATION TIMEFRAME:10 WEEKS The boiler in the production floor FINDING NO: E- 28 CATEGORY:BOILER & COMPRESSOR ROOM Power contactor in the boiler panel not fixed to the frame. Power contactor inside the boiler control panel must be firmly fixed to the frame. The boiler control panel Page 12 of 16

13 FINDING NO: E- 29 CATEGORY:BOILER & COMPRESSOR ROOM Power and control circuit of boiler are carried through flexible PVC pipe. Use industrial graded (heat resistant) pipe conduit for power and control circuit of boiler. REMEDIATION TIMEFRAME:10 WEEKS The boiler in the production floor FINDING NO: E- 30 Combustible materials stored near distribution board. Combustible materials must not be piled in the distribution board vicinity. REMEDIATION TIMEFRAME:1 WEEK The distribution board Page 13 of 16

14 FINDING NO: E- 31 Multiple cables inserted into single lugs. Use proper sized cable lug for each single cable and punch them by a proper hand puncher or hydraulic puncher to avoid loose connection. Enlarge the earth bus bar size according to the capacity of the panel and make more holes. Use single point (hole) of bus bar to terminate each single cable (lugs). The distribution board REMEDIATION TIMEFRAME:1 WEEK FINDING NO: E- 32 Openings in the panel top cover plate. Provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. The distribution board REMEDIATION TIMEFRAME:3 WEEKS Page 14 of 16

15 FINDING NO: E- 33 Phase barrier/separators between different phases are not installed. Phase barriers between different phases supplied by the breaker manufacturer must be installed to avoid arc flashing. REMEDIATION TIMEFRAME:1 WEEK The distribution board FINDING NO: E- 34 Multiple cable termination from MCCB. Remove all the multiple cable termination from the MCCB and busbars may be installed if necessary. The distribution board Page 15 of 16

16 FINDING NO: E- 35 Cables entering panel not arranged and supported properly. Cables below and top of panel must be carried through rigid pipes/tray and supported properly (clamped with saddle, at regular interval of 600 mm).the conduit/tray shall run vertically or horizontally, shall never at angle. The cables entering/exiting the distribution board FINDING NO: E- 36 Cables for the sewing machines laid on the floor. Install cable tray with metallic cover to provide mechanical support to cables laid haphazardly on the floor. The power cables for the sewing machines Page 16 of 16

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ABIR FASHIONS Kutubail, Fatullah (Post Office Road), Narayangonj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi & Mamun Report Generated by: Pema Wangdi Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT BOVS APPARELS LTD. JAMUR MUCHIPARA, HEMAYETPUR, SAVAR, DHAKA, BANGLADESH Factory List: 1. BOVS APPARELS LTD. Inspected on April 13, 2014 SUMMARY The Bovs Apparels Ltd

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AG s APPARELS LIMITED. Plot No. A/1&2 Block-B, BSCIC I/A Fouzderhat, Sagarika Road, Dhaka-1207, Bangladesh Factory List: 1. AG s Apparels Limited. Inspected by: Sherub

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MAHID APPAREL LTD. Nowpara, Madhabdi, Narsingdi, Bangladesh Factory List: 1. MAHID APPAREL LTD. Inspected by: Nazmul Huda Report Generated by: Nazmul Huda Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SINCERE KNIT GARMENTS LIMITED UNIT-1 East Isdair, Chandmari, Fatullah, Narayangonj, Bangladesh Factory List: 1. Unit-1 2. Fakir Knit Ltd. Inspected by: Sherab Dorji

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT Zirabo Bazar, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Inspected by: Khan & Tapu Report Generated by: Khan Inspected on Feb 6 th 2015 SUMMARY factory building

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ACTIVE COMPOSITE MILLS LTD. Dewan Idris Road, Zirabo, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Active Composite Mills Ltd. Inspected by: Hemlal Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT K.L FASHION LTD. 75/1, Mudafa West, Master Bari, Tongi, Gazipur, Bangladesh Factory List: 1. Inspected by: Jobair Ibna Abdul Alim Report Generated by: Jobair Ibna Abdul

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT LIBAS TEXTILES LTD., Mouchak, Kaliakoir, Gazipur, Bangladesh Factory List: 1. Libas Textiles Ltd. Inspected on April 6, 2014 SUMMARY The Libas Textiles Ltd., factory

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FRESH FASHION WEAR LTD. 638, Sharifpur, P.O-National University, Gazipur Sadar, Bangladesh Factory List: 1. Passion Apparels and Wears Ltd. 2. Inspected by: Jobair Ibna

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT METRO KNITTING & DYEING MILLS LTD.(FACTORY-02), CHARBAG, ASHULIA, SAVAR, DHAKA, BANGLADESH Factory List: 1. Inspected by: Younten Report Generated by: Das Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA ROAD, DHAKA, BANGLADESH. Factory List: 1. Inspected on May 14, 2014 ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Plot # B-32,BSCIC I/E,Tongi,Gazipur Factory List: 1. Kento Asia Limited. Inspected on May 15, 2014 SUMMARY Kento Asia Ltd. factory is established in a rented premises

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FIRST WEAR LMITED 68/Y, Sagarika Road, Pahartoli, Chittagong, Bangladesh Factory List: 1. Inspected by: Moin Hasan Report Generated by: Moin Hasan Inspected on August

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AHMED FASHIONS 34/1, Darus Salam Road (Technical), Mirpur-1, Dhaka, Bangladesh. Factory List: 1. Inspected by: Yang Generated by: Yang Inspected on 06 March 2015 SUMMARY

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADHUNIK POSHAK SHILPA LIMITED Civil Engineer Tower, Mirpur, Dhaka, Bangladesh Factory List: 1. Adhunik Poshak Shilpa Ltd. 2. Crazy Fashions Ltd. 3. Kazipur Fashion Ltd.

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. SREERAMPUR, DHAKA, BANGLADESH Factory List: Graphics Textiles Limited Inspected on May 20, 2014 SUMMARY Graphics Textiles Limited is located in Sreerampur, Dhaka. Reportedly,

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. House 8 & 10, Road 3, Section 7, Mirpur Industrial Area, Dhaka, Bangladesh Factory List: 1. Alliance Garments Ltd. Inspected on May 5, 2014 ELECTRICAL SAFETY INSPECTION

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th) Factory Name Address Shashongaon, Plot - S, A-646, Enayet nagar, Fatullah,Narayanganj Factory ID 9468 Electrical Safety dates Initial Date 07/07/2014 20/09/2016 Date of 5 th Follow Up Report Received Date

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Sumilpara, Adamjee Nagar, Shiddirgonji, Narayangonj, Bangladesh Factory List: 1. Moonlux Kinit Garments Limited. 2. West knit Wear Limited. 3. West Fashion. 4. Moonlus

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AKH APPARELS LIMITED 128 Hemayetpur, AKH Tower, Savar, Dhaka-1340, Bangladesh. Factory List: 1. AKH Apparels Limited Inspected by: Deonarayan Khatiwara Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT TARATEX (BD) LTD. Plot 23/1, Sataish Road, Tongi, Gazipur, Bangladesh Factory List: 1) Taratex (BD) Ltd. 2) S. P. M Design Ltd. Inspected by : Luv Kumar Chhetri Report

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ALIF GARMENTS Ltd, Dhaka, Bangladesh Prepared for: JANUARY 14, 2014 Alif Garments Ltd. PAGE 1 SUMMARY The seven-story factory housing Alif Textiles Ltd. & Hexa Garments

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FASHION FORUM LTD. 53-54, Diakhali, Zamgara, savar, Dhaka, Bangladesh. Factory List: 1. Fashion Forum Ltd. 2. IDS Washing Ltd. Inspected by: Karma Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH January 14, 2013 Redpoint Jackets Ltd. PAGE 1 SUMMARY The four-story factory housing Redpoint Jackets Ltd. located in Dhaka Export

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT, SOUTH VANGNAHATI, SREEPUR, GAZIPUR, BANGLADESH. Factory List: 1. Hams Garments Ltd. Inspected on April 03, 2014 ELECTRICAL SAFETY INSPECTION REPORT, GAZIPUR, BANGLADESH

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th) Factory Name Address Joyna Bazer Road, Jamirdia, Valuka Factory ID 9504 Electrical Safety dates Initial Date 06/07/2014 Date of 5 th Follow Up Report Received Date 07/27/2015 Date of 6 th Follow Up Date

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT (1ST FLOOR BOTH WINGS) CHITTAGONG EXPORT PROCESSING ZONE SOUTH HALISHAHAR, CHITTAGONG Factory List: 1. 2. Regency Garments Ltd. 3. ABC Camp Inspected on May 10, 2014

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. ANTIM KNIT COMPOSITE LTD., Barpa, Rupshi, Rupgonj, Narayangonj, Bangladesh. Factory List: 1. Antim Knit Composite Ltd. 2. Antim Knitting & Finishing Ltd. Inspected

More information

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS ISSUE DATE: 5/1/90 EFFECTIVE DATE: 2/4/92 REVIEW DATE:

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION E11 : General Electrical Earthing and LIGHTNING Protection PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION 1 2009-05-12 Review of Mechanical / Electrical and Control

More information

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID SBI INFRA MANAGEMENT SOLUTIONS PVT.LTD. 3 rd Floor, Local Head Office,Bank Street, Koti, Hyderabad- 500095 On behalf of On behalf of On behalf of Cash Management Product GOC (CMP GOC) & Internal Audit

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Project Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /19/2011 PAGE 1 OF 4 FACILITY LIGHTING SYSTEMS INSTALLATION

Project Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /19/2011 PAGE 1 OF 4 FACILITY LIGHTING SYSTEMS INSTALLATION Project Procedure 07/19/2011 PAGE 1 OF 4 1.0 PURPOSE The purpose of this procedure is to ensure that facility lighting system installations are accomplished in compliance with Project specifications, applicable

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

SECTION GROUNDING

SECTION GROUNDING SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 614 NOVEMBER 2012 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT TABLE OF CONTENTS 614.01 SCOPE 614.02 REFERENCES 614.03 DEFINITIONS

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

SECTION EARTHING AND EARTH FAULT PROTECTION

SECTION EARTHING AND EARTH FAULT PROTECTION SECTION 16660 PART 1 - GENERAL 1.01 DESCRIPTION A. The work to be performed includes, but is not necessarily limited to, all work involved with the construction and assembly of a complete electrical earthing

More information

T. SUNDUPALLI BRANCH (04427)

T. SUNDUPALLI BRANCH (04427) STATE BANK OF INDIA T. SUNDUPALLI BRANCH (04427) REGION 2, KADAPA RURAL TIRUPATI (A.O) ELECTRICAL WORK BILL OF QUANTITIES SL. NO. DESCRIPTION QTY. UNIT RATE AMOUNT Rs. Rs. 1 Supply, installation, testing

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin February 2019 Page 1 of 5 2018 CANADIAN ELECTRICAL CODE SUBJECT: Section 6 Services and service equipment Rule 6-102 Number of supply services permitted Row housing

More information

SECTION BUSWAYS

SECTION BUSWAYS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and

More information

Essex County College - West Essex Campus Addition And Renovations dlb # / 11-14

Essex County College - West Essex Campus Addition And Renovations dlb # / 11-14 SECTION 270526 - GROUNDING AND BONDING FOR COMMUNICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads, and

More information

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

NEUTRAL GROUNDING TRANSFORMERS INSTALLATION AND MAINTENANCE INSTRUCTIONS

NEUTRAL GROUNDING TRANSFORMERS INSTALLATION AND MAINTENANCE INSTRUCTIONS 1 Table of Contents SECTION 1 Unpacking... 3 1.1 Shipping... 3 1.2 Receiving... 3 SECTION 2 Installation... 3 SECTION 3 Inspection... 4 SECTION 4 Connection... 4 4.1 Neutral Lead... 5 4.2 Ground Lead...

More information

CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram

CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram 695 027 No. C-DIT/CG-Elec/18-19/T044 Date: 19.07.2018 TENDER NOTICE Sealed tenders are invited

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables MUNICIPAL AND COMMON DIVISION 2000 ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 - ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads,

More information

56-SDMS-01 REV. 01 SPECIFICATIONS FOR

56-SDMS-01 REV. 01 SPECIFICATIONS FOR 56-SDMS-01 REV. 01 SPECIFICATIONS FOR 13.8KV UNIT SUBSTATIONS This specification is property of SEC and subject to change or modification without any notice CONTENTS PAGE No. 1.0 SCOPE 3 2.0 CROSS REFERENCES

More information

OVERHEAD SERVICES - SECONDARY

OVERHEAD SERVICES - SECONDARY OVERHEAD SERVICES - SECONDARY Contents - Overhead Services... O-1 General Requirements for Overhead Service... O-2 Names of Parts for Overhead Service... O-3 Service Attachment on an Unguyed Service Mast...

More information

31-SDMS-03 REV. 01 SPECIFICATIONS FOR

31-SDMS-03 REV. 01 SPECIFICATIONS FOR 31-SDMS-03 REV. 01 SPECIFICATIONS FOR LOW VOLTAGE CABINET FOR POLE MOUNTED TRANSFORMER This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Description

More information

CHAPTER 5 METERING REQUIREMENTS

CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS 5.1 General 1. All installations connected to, or intended to be connected to HK Electric s supply of electricity must comply with HK Electric

More information

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC). SECTION 16111 CONDUITS PART 1 - GENERAL 1.01 DESCRIPTION A. General: Provide conduits, complete, as shown, specified or required per Contract Documents. Principal items include: 1. Rigid aluminum conduit.

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

INTER PLANT STANDARD STEEL INDUSTRY

INTER PLANT STANDARD STEEL INDUSTRY INTER PLANT STANDARD STEEL INDUSTRY IPSS SPECIFICATION FOR PROTECTIVE PANELS FOR dc CRANES (Second Revision) Corresponding IS does not exist IPSS:1-10-013-11 Formerly : IPSS: 1-10-013-03 0. FOREWORD 0.1

More information

OVERHEAD SERVICE. Table of Contents - Section 400

OVERHEAD SERVICE. Table of Contents - Section 400 OVERHEAD SERVICE Table of Contents - Section 400 PARAGRAPH 400.0 OVERHEAD SERVICES (0-600 VOLTS)... 1 400.1 GENERAL 1 400.2 IDENTIFICATION OF CONDUCTORS. 1 400.3 MAXIMUM SERVICE ENTRANCE CONDUCTOR SIZE

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard PART 1 GENERAL 1.1 Scope A. The intent of this specification is to provide power control for the parallel operation of generator

More information

Tender No.:- RITES/CO/B&A/EE/CUK- Gulbarga/External/E-2/2012.

Tender No.:- RITES/CO/B&A/EE/CUK- Gulbarga/External/E-2/2012. Amendment No. 1. Sub. : Tender: Supply, Erection, Testing & Commissioning of 11kV/440 V substation, Transformers, DG Sets, HT/ LT panels, HT/LT Cables, Street Lighting etc at University Campus at Khadaganchki

More information

SECTION MOTOR CONTROL CENTER

SECTION MOTOR CONTROL CENTER SECTION 16445 MOTOR CONTROL CENTER PART 1 GENERAL 1.01 DESCRIPTION A. This section covers the contract item Motor Control Center (MCC). The contract item includes demolition and removal of existing MCC;

More information

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge

More information

BILL OF MATERIALS Name of the work: F.T.S Modernisation Work

BILL OF MATERIALS Name of the work: F.T.S Modernisation Work 1 BILL OF MATERIALS Name of the work: F.T.S Modernisation Work Erection,Testing and commissioning of Converter transformer 3 PH,11 KV/2 X 1800 V,4000 KVA outdoor Transformer size of 3150 L X 2800 D X 3200

More information

BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI

BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI Page 1 BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI-110075 I. INSTALLATION OF SUB-STATION EQUIPMENT The rates shall include the following : 1. Assembling loose

More information

Addendum - 2 for 11KV VCB Panel Specifications GETCO / E / TS HTPB 5401 / R1 Dt and GETCO / E / TS HTPB 5402 / R1 Dt

Addendum - 2 for 11KV VCB Panel Specifications GETCO / E / TS HTPB 5401 / R1 Dt and GETCO / E / TS HTPB 5402 / R1 Dt Addendum - 2 for 11KV VCB Panel Specifications GETCO / E / TS HTPB 5401 / R1 Dt. 25.01.12 and GETCO / E / TS HTPB 5402 / R1 Dt. 27.01.2012 Part - A 11KV Common Standard Busbar Configuration with Integrated

More information

legend. #1 is a gas relief valve? If so does Enbridge supply with station?

legend. #1 is a gas relief valve? If so does Enbridge supply with station? Michael Pacholok, Director Purchasing and Materials Management Division City Hall, 8 th Floor, West Tower 00 Queen Street West Toronto, Ontario M5H N Joanne Kehoe Manager Construction Services May 4, 06

More information

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein. 16470 PANELBOARDS ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 24 16 An optional keynote to

More information

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 48 (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.01 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section

More information

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING 2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING E3305.3: now reads The space equal to the width and depth of the panelboard and extending

More information

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. AFC Cable Systems, Inc. Product Specification This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. SECTION 260519.13 METAL CLAD CABLE-MC

More information

CS-21 STREET STRUCTURES TABLE OF CONTENTS

CS-21 STREET STRUCTURES TABLE OF CONTENTS TABLE OF CONTENTS CS-21.0 Street Structures... 1 CS-21.1 Road Signs... 1 CS-21.2 Safety Barriers... 1 CS-21.3 Bollards and Removable Bollards... 1 CS-21.4 Pedestrian Barrier Rails and Handrails... 1 CS-21.5

More information

NYULMC AMBULATORY CARE CENTER FIT-OUT PHASE 1 Perkins & Will Architects PC 222 E 41st ST, NYC Project: Issued for GMP March 15, 2017

NYULMC AMBULATORY CARE CENTER FIT-OUT PHASE 1 Perkins & Will Architects PC 222 E 41st ST, NYC Project: Issued for GMP March 15, 2017 SECTION 27 05 26 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

Specification Lightning Protection Systems

Specification Lightning Protection Systems Specification Lightning Protection Systems General: Summary A) This Section specifies the lightning protection system for the building(s) or structure(s). This system provides safety for the building and

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

16300 HIGH VOLTAGE DISTRIBUTION

16300 HIGH VOLTAGE DISTRIBUTION 16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (URD) Index General Discussion... 1-2 Description... 3-7 Drawings (Available

More information

SPECIFICATION FOR SIMPLEX SWITCHBOARDS

SPECIFICATION FOR SIMPLEX SWITCHBOARDS SPECIFICATION FOR SIMPLEX SWITCHBOARDS 1.0 SCOPE This specification presents general guidelines, design criteria, and construction requirements for AZZ ENCLOSURE SYSTEMS SIMPLEX PANELS for providing control

More information

2600SEG135 SAFETY STANDARD FOR INDUSTRIAL LADDERS AND STAIRCASES IN BUILDINGS

2600SEG135 SAFETY STANDARD FOR INDUSTRIAL LADDERS AND STAIRCASES IN BUILDINGS 1.0 OBJECTIVE The purpose of this standard is to establish the minimum requirements applicable to standard ladders and staircases of general use in buildings and industrial installations of the Panama

More information

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.)

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.) SBI-AO2 Project Residency Rd Br-elect/RBO-4 SCHEDULE OF QUANTITIES FOR ELECTRICAL WORKS. DATE : 24/4/2018 Sl. No. DESCRIPTION OF WORK UNIT QTY 1 READYMADE FINAL DISTRIBUTION BOARDS Supply, Instillation,

More information

SYSTEM 600 BILL CHANGER INSTALLATION INSTRUCTIONS Congratulations...

SYSTEM 600 BILL CHANGER INSTALLATION INSTRUCTIONS Congratulations... www.standardchange.com 1-800-968-6955 Technical Phone Support is from 8:00AM to 7:30PM E.S.T., Monday-Friday Walk-in Service is from 8:00AM to 4:30PM E.S.T., Monday-Friday Parts Department is from 8:00AM

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL 8.01 GENERAL This material is not intended to cover service from OPPD s network in the downtown Omaha area. See Chapter 12 for details

More information

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 INDEX Page SECTION 1.0: SCOPE 1 1.1 Toronto Hydro Requirements 1 1.2 Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 SECTION 3.0: DEFINITIONS AND THE INTERNATIONAL SYSTEM OF UNITS 1 3.1 Definitions

More information

It is standard practice and all manufacturers to abide by this. It is standard practice and all manufacturers to abide by this.

It is standard practice and all manufacturers to abide by this. It is standard practice and all manufacturers to abide by this. 1 162 General 2 162 General We recommend to specify door handle to singe shot latch type, bolted construction of Door shall not be acceptable. Closing and Tripping Coils shall be rated for continuous supply,

More information

FIRESTOPPING & SMOKE SEALS

FIRESTOPPING & SMOKE SEALS FIRESTOPPING & SMOKE SEALS SPECIFICATION SECTION 07860 1 General 1.1 SECTION INCLUDES.1 Comply with Division 1, General Requirements and Documents referred to therein..2 It is the intent of this section

More information

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL WARNING Before digging or trenching... Call 811 Indiana Underground Protection Service 1-800-382-5544 AVOID BURIED POWER CABLES 4901 East Park 30 Drive P.O.

More information

8. REVENUE METERING. Operational Excellence Model. 8.1 Introduction

8. REVENUE METERING. Operational Excellence Model. 8.1 Introduction 8. 8.1 Introduction The purpose of this section is to outline requirements of the customer, as set forth herein by PSEG Long Island, as they pertain to Electric Revenue Metering at Primary and Secondary

More information

2015 Code Rollout Meeting Q & A

2015 Code Rollout Meeting Q & A 1 SECTION QUESTION SaskPower Inspections Dept. ANSWER 2 3 4 5 6 7 8 9 10 11 12 15-02-024 15-02-200 15-02-200 15-02-200 15-02-314 Are existing single or double 'weather proof when not in use' covers allowed

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 11 00 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Stack Parking Surface Mounted Stackers

Stack Parking Surface Mounted Stackers 1 / 6 Stack Parking Surface Mounted Stackers swiss-park V-2 Comfort The V-2 is designed to park cars of any size thanks to its vertical adjustability. It will accommodate cars as tall as the garage ceiling

More information