1 Executable EMP for Residential & Commercial Project Ishanya by Mahanagar Realty CTS no. 373(pt), 375, (pt),378 (pt), S. No. 19A/3A, Dhanakawadi, Pune Project Details: Old data New data 1 Plot Area 23,794 sqm 23,794 sqm 2 BUA 71,476,.68 1,20, Tenements Shops 1 P a g e

2 1. Air Environment: 1.1 Construction Phase a) Mobile source emissions I. Transportation of raw materials required for construction will be carried out during non-peak hours. Proper traffic management for construction vehicles. II. Parking of delivery trucks or other equipment will not be permitted on public road during unloading or when not in active use. III. To minimize dust emissions due to trucks carrying cement, gravel, sand to site, ready mix concrete carried in enclosed container will be used, which is a better option as compared to on site batch mixing. IV. Use of Dust Control measures during material transport like Water Sprinkling, Covering the trucks. b) For stationary source emissions: I. Most of the machinery related to construction will be located close to construction area for ease of handling. Machinery such as crushers, conveyers and mixers will be screened with sheets of suitable material to reduce generation of suspended particulate matter and noise. II. Areas prone to fugitive dust emissions due to activities such as excavation, grading sites and routes of delivery vehicles across patches of exposed Earth, will be frequently water sprinkled to prevent re-entrainment of dust. III. Apart from these, equipment/machines and vehicles will always be kept in good state of repair to minimize emissions. Low emission vehicles/equipment should be used wherever feasible. Construction areas will be enclosed, wherever possible. 1.2 Operation Phase: Use of 365 DG as per CPCB norms; HSD used as fuel Optimum Air to Fuel ratio for Reduced NOx Levels Adequate Parking provision with driveways Effective traffic management Half yearly monitoring for AAQ will be done as per CPCB guidelines 2. Water Environment: 2 P a g e

3 2.1 Construction Phase Construction water requirement met through tankers Monitoring of surface and ground water for change in quality due to construction. Drinking water analysis (Monthly) Provision of 10 temporary toilets for 100 workers with proper disposal of sewage through public sewer line Use of tanker water for construction 2.2 Operation Phase We will install scientifically designed Rain Water Harvesting System, Sewage Treatment Plant. Rainwater harvesting system will have two-fold objective: 1. To utilize rain water available on the plot in direct way or indirect way to reduce the load on water supply system. 2. To minimize the storm water drainage load to avoid water logging locally as well as on larger scale. The total water collected by rainwater harvesting on the plot will be used for Ground water recharge which would increase ground water table of the area and reduce storm water quantity. We will implement properly designed storm water drains. Rain water harvesting will be done through Pits Operation and Maintenance for Rain Water Harvesting System: Sr. Activity Operation and Maintenance Frequency No. 1 Harvesting clean water The roof top shall be made free of dumps and unwanted material. The Yearly dust and other material will be removed prior to monsoon. 2 Cleaning of grill Cleaning of a grill with mesh will be fixed at the entrance of the drain pipes on the terrace to filter large particles like leaves, litter etc. Weekly during monsoon. 3 Care to avoid contamination Flush first runoff water (or 1000 lit) of storm shall be diverted to the sewer drain to avoid any contamination further. 4 System cleaning Entire system to checked and cleaned after every dry period of more than one month Every month 5 Leakage Leakage to be repaired After observations first monsoon 6 Tank Physical inspection and repairing Six monthly maintenance cracks with cement at 3 P a g e

4 7 Water quality testing Water quality testing for drinking water as IS Quarterly in terms of water tank Yearly during mid monsoon Other Measures includes; Awareness campaign for residents about effective treatment and recycling of treated waste water, and rain water harvesting. Provision of STP (380 KLD capacity) with tertiary treatment (FAB) Quarterly monitoring for STP inlet & outlet. Use of recycled water for flushing, gardening Strom water drainage will be properly maintained. MBBR: S. Activity O and M Frequency Remarks N. 1 Manual Bar Screen cleaning 2 twice daily in first and second shift 2 Raw Sewage Automatic level switches Low level pumping arrange pump off & High level pump on 3 All Submersible pump Oil level and impeller 6 months If pump maintenance condition. Automaton check- clogged on site 4 All Submersible Jet Aerator maintenance up Oil level and impeller condition. Automaton checkup 5 MMF and ACF Backwashing for 15 minutes should be done daily 6 Green Belt Shredding/Cutting of Phragamites (Plants) as per requirement 7 Yearly shut down, if any Once a year for one only for automation and MCC Panel check maintained 6 months If aerator clogged on site maintained Once daily Media to be changed after 2 years. 6 months Pumps shall be non operational from 11 am to 7 pm 3. Solid Waste Management: 4 P a g e

5 3.1 During construction: 1. Disposal of debris to authorized contractor. Demolition waste to authorized vendor. 2. Debris generated during construction is used as filling material on site for Plinth filling. 3.2 During operation phase: 1. Segregation of dry waste and wet waste at source. 2. Separate collection system for plastic, Paper, Metal, Glass, Inert/ash and E-waste at society level, transferred to authorized distributors. 3. Awareness campaign for residents for effective solid waste management & segregation. 4. Treatment of wet waste through mechanical composting of 714 kg/ day capacity. 5. Use of manure for garden. 6. Hazardous waste is not applicable 7. Disposal of Dry waste through authorized vendors S. N. SOPs: Activity O and M Frequency 1 Moisture maintenance 2 Culture maintenance 3 Machine maintenance Remove excess moisture Avoid addition of uncut fruits Avoid loading of inorganic material Addition of saw dust (initially 40 %,gradually decrease to 5% in 12 weeks) Add 0.1 % (by weight) composting culture Gear box needs refilling with grease after 5 years Preventive maintenance for Gear Box with as per manual ACF filter to be replaced Daily Daily Monthly 4 ACF filter 5 years maintenance 5 Blower inlet pipe To be cleaned if clogged with saw dust Weekly 4. Noise Environment 4.1 Construction Phase Barricades along the periphery of the Site Ear Plugs for Laborers DG set: Acoustic enclosure for noise control Work to be carried out only during day time to avoid noise pollution at night times 4.2 Operation Phase DG set: Acoustic enclosure for noise control Adequate plantation which will act as external noise barrier for the residents Half yearly monitoring will be done 5. Land Environment 5 P a g e

6 5.1 Resource Management: The resources such as sand, metal etc will be taken from Govt. owned / approved agencies. One of the impacts on the land environment during construction phase is the requirement of construction materials as identified. It is proposed to use fly ash to partially offset use of cement in the construction. This will reduce sand requirement by about 20% & will also solve the problem of fly ash disposal. The proposed project involves removal of sub-stratum during excavation for foundation. The impact of excavation for foundation will be reduced due to use of excavated material / debris generated for filling purposes and for road construction. The solid waste generated due to packaging material will preferably be recycled and/or reused. 5.2 Traffic Management: Another impact identified during studies is the minor increase in traffic volume in the area in construction phase (because of the movement of trucks carrying raw materials) & in operation phase (due to vehicles movement for ferrying building occupants) Special care will be taken during transportation of construction material like cement, sand, aggregate etc as such material would be transported from various material suppliers. Since road transport is unavoidable, such movement will be carried out during non- peak hours as far as possible. The entry/exit to the site will be with adequate curvature at turning so that vehicles coming out/entering the building do not impinge on road traffic directly. As far as possible, material carrying trucks should be parked inside the complex & should not be parked on public road. 6 P a g e

7 6. Guidelines for Bio-Aesthetic Management 6.1 Green belt/landscape Management :Greenbelt is important feature as far as landscape of the premises as well as biological environment is considered. Purpose: 1. Enhancement of aesthetic value of the area 2. Proposed project is Residential Complex so proper landscape management is necessary to beautify the area. 3. Help to reduce Air and Noise pollution. 4. Prior to plantation of trees Ecological value as well as aesthetic value of tree species should be considered. 6.2 Plantation Specifications: Trees should be planted in 1 cu. m pits. The tree pits should preferably be in a row that is not concretized, with exposed ground, to facilitate infiltration of more water into the ground and healthy growth of root system. Good anchorage would help minimize uprooting of trees during unfavorable weather conditions. The pit should be filled with an even mixture of red earth, sand and farmyard manure. Saplings should be healthy 3-year old in age to ensure better survival. Trees should be watered on alternate days during dry season, for 4-5 years. Weekly watering is often required at later stage of growth. During this growing period, care should be taken to ensure that the tree is growing vertically and is without horizontal branches. Any branch appearing within 8 feet from ground should be removed by sawing at the trunk level. 6.3 Some Recommended species for plantation: Butea monosperma Ficus blackiana Azadiracta indica Cassia fistula Cordial sebestena Lagerstromea sperciosa Spathodia campulata Milingtonia Hortentis Plumeria alba Murraya panniculata Mangifera india Butea monosperma Ficus blackiana Azadiracta indica Cassia fistula Cordial sebestena Shrubs should be planted between trees, in the same way as the trees but in smaller pits (0.3 x 0.3 x 0.3 m). 7 P a g e

8 7. Energy conservation aspects: Solar water heaters: S.N. Activity O and M Frequency 1 Avoid objection of light Check for maximum interception Monthly ofsunlight. Avoide any shadow from trees, other objects Cleaning of collector glass Once in week 2 Broken glass To be replaced As and When required 3 Maintain pressure of Maintain necessary pressure for inlet. Weekly inlet 4 Occasional leakage Leakage in entire system should be repaired As and when required 5 Care for out of use equipment Entire system should be drained totally and collector should be covered. Before the equipment is to 6 Instructions leading to use of hot water by users Instructions reg. use of hot water: for use at one time to save optimum electricity savings be closed Once in a day Solar electricity: S. N. Activity O and M Frequency 1 Avoid objection of light Check for maximum interception Monthly ofsunlight. Avoide any shadow from trees, other objects Cleaning of PV cell glass Once in week 2 Broken glass To be replaced As and when required 3 Battery maintenance Check for wiring, other regular Monthly maintenance Water level in acid batteries Monthly Replacement of expired batteries Every three years 8 P a g e

9 8. Socio Economic Aspects The proposed construction project is specifically demarcated for residential development. Thus, there would not be any adverse impact on local population due to the project. This is seen as a positive impact on socio-economic environment as it will create additional jobs & give thrust to development of services sector in the city. 8.1 Construction phase: The health and safety of the workers for the construction project should be ensured by: Adequate drinking water, toilet and bathing facilities for workers Personal protective and safety equipments will be provided. Doctor & First aid facility for workers Crèche for children of workers Regular health check up for workers Educational and awareness program for safety measures 8.2 Operation Phase: For safety purpose during operational phase Awareness programs regarding socio-economic impacts of residential projects on surrounding area. Environmental and safety awareness programs for surrounding area. Disaster management/emergency preparedness plan will be explained with the help of experts. In addition, we will construct a compound wall of 1.5 M height and plant the trees within premises along compound wall, to attenuate the noise level. Periodic inspection and maintenance of all water storage tanks should be carried out at regular intervals to prevent outbreak of waterborne diseases 9 P a g e

10 9. Regulatory Compliance: 1. Obtain Consent to Establish from MPCB before start of work 2. Obtain Consent to Operate from MPCB before occupation of project. 3. Payment of Water Cess to MPCB in case consent prescribes it. 4. Filing of Environmental Statement before 30 th Sep every year if prescribed in consent. 5. Six monthly monitoring of air, water, noise, soil and submission of six monthly compliance reports to MoEFCC and MPCB. 10. Responsibilities: 1. During construction phase, contractors as well as site-in-charge will be responsible for implementing all the mitigation measures recommended. 2. Planting of trees on open spaces and road-side should be initiated during construction phase itself. 3. In operational phase, the work will be continued along with post-monitoring of planted area. An officer will be appointed by us to ensure monitoring and inspection during construction period as explained above. 4. Prime properties have constituted Environmental Management Cell (EMC) including inhouse and outside experts (5 in Number) to deal with environmental issues at project stage for every project site. EMC meets every fortnight and assess the environmental issues at various on-going sites. After the society formation, a special training program to be organized for society office bearers to look into environment management in project operation stage. The Responsibility matrix is as follows: a. Construction phase: Sr. no Activity Impacts Precautions Responsibilit ies 1. Air Excavation Increased dust Use of dust controlling measures Site levels during material transport incharge Site clearance Air pollution by traffic Increased air pollutants Water sprinklers Covering the trucks Contractor 10 P a g e

11 Use of RMC Use of DG sets as per CPCB norms Proper maintenance, LSD fuel use, proper and safe storage of fuel 2. Noise Traffic movement Use of DG sets Construction activities 3. Water Use of fresh water for construction activity Generation of waste water Disposal of site runoff in storm water drain 4. Soil Excavation Disturbance of natural contour by cutting, backfilling Cutting of trees for land clearance for construction Increased noise level Pollution of water in nearby water sources Sedimentation Stress on freshwater supply on municipal body Loss of fertile soil Soil contamination due to mixing of construction materials Soil erosion Tree plantation to reduce dust spreading Barricades along the periphery of site Ear plugs for labourers DG set: acoustic enclosure for noise Work to be carried out during day time to avoid noise at night Monitoring of surface and ground water for change in quality due to construction activity Drinking water analysis Provision of temporary toilets with proper disposal of sewage through public sewer line Use of tanker/recycled water for construction to lesser the burden on municipal drinking water supply Minimum disturbance to natural contour, minimizing cutting and filling activities Preservation of topsoil for landscaping Maximum area to be covered by trees Site incharge Contractor Site incharge Contractor STP managing personnel Soil expert Site incharge 5. Biological Environment Soil pollution due to waste generation by labourers Cutting of trees Site clearance Disturbance of natural fauna and flora Plantation of native species of trees before operational phase, to minimize environmental impact during construction Site incharge 6. Socio economic environment Construction activity by labourers Safety and hygiene Trees with canopy will be planted along the roads to control vehicular pollution. Adequate drinking water and toilet facilities Personal protective and safety equipments will be provided. First aid facility for workers Contractor Site incharge Regular health check up for workers Educational and awareness program for safety measures 11 P a g e

12 b. Operation phase: 1 Air Increase in vehicles Use of DG sets Traffic problems Air pollution by vehicular exhaust Use of DG sets (220 KVA x 1 Nos. and 330 KVA x 1 Nos.) as per CPCB norms with fuel as LSD Tree plantation along the internal roads to control vehicular pollution. Speed limit for vehicles to 20 kmph Adequate Parking provision with driveways Effective traffic management Six monthly monitoring will be done Environme nt Monitoring Cell of Project Proponent till handing over to society Society managem ent after handing over by PP 2 Noise Use of DG set Increase in vehicular traffic Increase in nose level DG set: Acoustic enclosure for noise control Adequate plantation which will act as external noise barrier for the residents Six monthly monitoring will be done Environme nt Monitoring Cell of Project Proponent till handing over to society Society managem ent after handing over by PP 3 Water Generation of waste water Increased demand for fresh water Pollution of water bodies Stress on existing water supply Increased site runoff Awareness campaign for residents about effective treatment and recycling of treated waste water, and rain water harvesting. Use of water saving devices/fixtures Duel pipe plumbing in every building. Provision of STP (200 KLD) with tertiary treatment and disinfecting facility Environme nt Monitoring Cell of Project Proponent till handing over to society Society managem ent after handing over by PP 4 Soil Solid waste generation Improper disposal of waste Increased paved area Use of paver blocks instead of impermeable concrete blocks to allow water percolation. Top soil conservation for Landscape development STP operator Environme nt Monitoring Cell of Project 12 P a g e

13 Proper maintenance of STP and solid waste management system to avoid land pollution through leakages. Proponent till handing over to society Society managem ent after handing over by PP 5 Landscape Introduction of new tree species Disturbance of natural flora and fauna due to increased anthropogenic activities Landscape development area m 2 No. of trees to be planted is 182 Fruit bearing trees, Drought tolerant species, Bird attracting species, plants having medicinal value, are given OWC operator Environme nt Monitoring Cell of Project Proponent till handing over to society Society managem ent after handing over by PP 6 Socio economic environment Influx of people Stress on all utilities, risk due to manmade activities Awareness programs regarding socioeconomic impacts of residential projects on surrounding area. Environmental and safety awareness programs for residents. Disaster management/emergency preparedness plan will be explained with the help of experts. Mock up drills at regular intervals regarding fire fighting. Landscape contractor Environme nt Monitoring Cell of Project Proponent till handing over to society Society managem ent after handing over by PP *** 13 P a g e

Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra Executable EMP for Green Valley Project Project Location: S. no 257, Wakad, Pune Project Details: 1 Plot Area 9899 sqm 2 BUA 29464.01 sqm 3 Tenements Residential: 179, 1 twin bungalow, Commercial: 5 convinient

More information

ENVIRONMENT MANAGEMENT PLAN CONSTRUCTION PHASE. suppression instead of water wherever possible. Cell)

ENVIRONMENT MANAGEMENT PLAN CONSTRUCTION PHASE. suppression instead of water wherever possible. Cell) ENVIRONMENT MANAGEMENT PLAN No. 1. Increase in water demand due to water usage for, dust suppression and for domestic purpose of workers 2. Sewage generation (9 KLD) and disposal 3. Solid waste generation

More information

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors 1. Increased water demand (12 KLD) due water usage for, dust suppression and for workers 2. Sewage generation (11 KLD) and disposal 3. Municipal solid waste generation (15 kg/day) by workers 4. Construction

More information

Municipal solid / hazardous waste

Municipal solid / hazardous waste (10) ENVIRONMENTAL MANAGEMENT PLAN The mitigation measures for reducing the adverse environmental impacts together constitute a part of EMP. The environmental issues, which need management, plan for the

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION ENVIRONMENTAL MANAGEMENT PLAN An environmental management plan (EMP) has been prepared for the proposed construction of commercial project to minimize negative impacts and is formed on the

More information

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006.

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Thus, EIA is not applicable for proposed project. We have derived project

More information

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan ENVIRONMENTAL MANAGEMENT PLAN Of Hotel Project for Mohamed Ilyas & Ms. Alamzahan at Khasra No. 269Ga, 269Kh, 266Kh & 270 Village Majra, Tehsil Central Doon, District Dehradun (Uttarakhand) GENERAL ENVIRONMENTAL

More information

5. ENVIRONMENT MANAGEMENT PLAN

5. ENVIRONMENT MANAGEMENT PLAN 5. ENVIRONMENT MANAGEMENT PLAN The environmental management plan consist of the set of mitigation measures, management and, monitoring measures to be taken during construction and operation phase to eliminate

More information

Health and safety norms of CPWD should be followed during construction.

Health and safety norms of CPWD should be followed during construction. Status of Compliance of Conditions of the Environmental Clearance Issued to Riveria Commercial Developers Ltd. DLF Center, Sansad Marg, New Delhi 110001- Construction of "YASHWANT PLACE COMMUNITY CENTRE"

More information

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the, operation and the

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the construction and

More information

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005.

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005. GENERAL CONDITIONS 1. The Project Proponent shall comply with all the conditions stipulated in the building approval letter. 2. The applicant (Project proponent) will take necessary measures for preventions,

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Six Monthly Compliance Report June-2015 M/s Mahagun Real Estate Pvt. Ltd SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex Mahagunpuram AT VILLAGE Mehrauli, Dasna, Ghaziabad, U.P. Being developed

More information

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES Environmental / Social issue/ aspect/ activity Anticipated negative impact Management and mitigation

More information

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018)

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018) TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Oct 2017 to Mar 2018) Environment Department Tata

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan 1. OBJECTIVE The objective of Environmental Management Plan (EMP) is to formulate which will: Mitigate adverse impacts on various environmental components, which have been

More information

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan Report on 1. PROJECT LOCATION & LAND USE The Ganesh Park 3 is a residential building project constructed on plot 608 to 613/5 Vil: GIDC Ankleshwar in Bharuch district of Gujarat state. The project land

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

TABLE OF CONTENTS. Para No. Contents Page No

TABLE OF CONTENTS. Para No. Contents Page No TABLE OF CONTENTS Para No. Contents Page No Chapter-1 Introduction 1.0 Preamble 1 1.1 Location of the project 1 1.2 Objectives of the EIA study 3 1.3 Methodology of study 3 1.4 Structure of EIA report

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION An Environmental Management Plan (EMP) is a site-specific plan developed to ensure that all necessary measures are identified and implemented in order to protect

More information

ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION 1.2 EMP DURING CONSTRUCTION PHASE

ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION 1.2 EMP DURING CONSTRUCTION PHASE ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

Environmental Management Plan during Construction Phase

Environmental Management Plan during Construction Phase Management Plan during Phase Sr 1 Ambient Air Quity Negative inside site premises outside site 2 ise Negative near noise generation sources inside premises on ambient noise levels in the Surrounding area

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

Details of the proposed project as presented before the committee are tabulated below:

Details of the proposed project as presented before the committee are tabulated below: Shrungal Homes Block No. 141, F.P.No.42, O.P.No.42, T.P.S.No.58 (Bamroli), Choryasi, Surat. Screening & scoping / appraisal. Details of the proposed project as presented before the committee are tabulated

More information

Environment Compliance Report (Apr 2017 to Sep 2017)

Environment Compliance Report (Apr 2017 to Sep 2017) TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Apr 2017 to Sep 2017) Environment Department Tata

More information

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017 COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER - 2016 TO MARCH-2017 F.No. SEIAA 281/2014/EC/110 SUBMITTED BY- M/S. TERON CONSTRUCTION PVT. LTD MAA PADMA COMMERCIAL COMPLEX, H/N-

More information

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity) [Vide Paragraph - 6 of Notification dated 14 th September 2006, only for construction projects listed under item 8 of the Schedule] (1) LAND ENVIRONMENT (Attach panoramic view of the project site and the

More information

Check list for construction Project of EC [Category 8(a)]:

Check list for construction Project of EC [Category 8(a)]: Check list for construction Project of EC [Category 8(a)]: Provide authenticated (with stamp & Signature) hard copy of this check-list during submission of hard copy of ToR application. Sr. no. Checklist

More information

No construction activity started

No construction activity started Sr. Particulars Details No. 1. Proposal is for New Project 2. Type of Project Residential Flats and Shops 3. Project / Activity No. 8(a) [8(a) or 8(b)] 4. Name of the project Kaveri Soham Vistara 5. Name

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE For PROPOSED RESIDENTIAL AND COMMERCIAL DEVELOPMENT AT Plot bearing survey no. 86/1, 86/2, 86/3 (pt), 86/4 (pt), 86/5 (pt), 115/1 (pt), 115/2 (pt), 115/3 (pt), 115/4 (pt), 115/5

More information

Environmental Clearance for Proposed development at Kandivali (E), Mumbai ANNEXURES

Environmental Clearance for Proposed development at Kandivali (E), Mumbai ANNEXURES ANNEXURES 35 LIST OF ANNEXURES Annexure I : Solid Waste Management Annexure II : Water Supply & Wastewater Management Annexure III : Proposed Area Statement Annexure IV : Environmental Management Plan

More information

Promoter: Navkar Prime Developers Private Limited ENVIRONMENTAL MANAGEMENT PLAN & CER

Promoter: Navkar Prime Developers Private Limited ENVIRONMENTAL MANAGEMENT PLAN & CER ENVIRONMENTAL MANAGEMENT PLAN & CER 52 ENVIRONMENTAL & SOCIAL MANAGEMENT PLAN 1.1 INTRODUCTION: The Environmental impact can be defined as any alteration of environmental conditions, adverse or beneficial,

More information

1. ENVIRONMENT MANAGEMENT PLAN

1. ENVIRONMENT MANAGEMENT PLAN 1. ENVIRONMENT MANAGEMENT PLAN The Environment Management Action Plan (EMP) is required to ensure sustainable development of the proposed Sewerage System in District A of Allahabad, Uttar Pradesh. The

More information

This project does not attract EIA Notification and provisions in CRZ Notification [Clause no. 4.2 (i) (b)] also exempt preparation of EIA report.

This project does not attract EIA Notification and provisions in CRZ Notification [Clause no. 4.2 (i) (b)] also exempt preparation of EIA report. The proposal under consideration, Regularization of Existing Resort at Sidheshwarwadi, Village Ubhadanda, Taluka Vengurla, Dist. Sindhudurg is located in CRZ III area having total plot area of 4000 m 2,

More information

Indicative Checklist for construction projects of EC [Category 8(a)]:

Indicative Checklist for construction projects of EC [Category 8(a)]: Indicative Checklist for construction projects of EC [Category 8(a)]: Sr. Checklist point Remark Yes/No Pg. no./ annexure 1. Covering letter signed by the applicant Yes Form-1 Page 1 page 13 2. Completed

More information

Application of Low and Non Waste Technology in the production process;

Application of Low and Non Waste Technology in the production process; 9.0 ENVIRONMENT MANAGEMENT PLAN (EMP) 9.1 INTRODUCTION Environment Management Plan is required for ensuring sustainable development. It should not affect the surrounding environment adversely. The management

More information

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment 1993 Specifications CSJ'S 0912-71-554 & 0912-71-555 SPECIAL SPECIFICATION ITEM 1016 Tree Preservation and Treatment 1. Description. This section specifies the requirements for protecting trees and related

More information

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area.

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area. ENVIRONMENT CLEARANCE COMPLIANCE STATUS ENVIRONMENT CLEARANCE No. J-11015/406/2006-IA.II(M) dt. 13/04/2007 DHANGARWADI MINES Sr. CONDITIONS COMPLIANCE No. A) Specific Conditions :- i) Top soil to be stacked

More information

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT GUJARAT HOUSING BOARD

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT GUJARAT HOUSING BOARD PRE FEASIBILITY REPORT FOR PROPOSED CONSCTRUCTION BUILDING PROJECT (66460.23 SQ. M) BY GUJARAT HOUSING BOARD AFFORDABLE RESIDENTIAL BUILDING & COMMERCIAL PROJECT PACKAGE 23, PLOT NO. 61/1, 63/1 & 64, TARSAMIYA,

More information

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT QUERY 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? Attach Maps

More information

Escondido Best Management Practices (BMP s)

Escondido Best Management Practices (BMP s) Escondido Best Management Practices (BMP s) GROUNDS MAINTENANCE & GOOD HOUSEKEEPING Regularly dry sweep paved areas including parking lots, outdoor areas and dumpster areas. Do NOT use a hose. Collect

More information

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra.

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Pre- feasibility Report For Shiv Kailasha At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Proposed By M/S Om Shivam Buildcon Private

More information

1. ENVIRONMENT MANAGEMENT PLAN

1. ENVIRONMENT MANAGEMENT PLAN Project : Environmental Management Plan for District E Allahabad 1. ENVIRONMENT MANAGEMENT PLAN The Environment Management Action Plan (EMP) is required to ensure sustainable development of the proposed

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative) Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in

More information

[FORM-V] PART-A PART-B

[FORM-V] PART-A PART-B [FORM-V] (See Rule 14) Environment Statement for the financial year ending the 31 st March 2015 PART-A (1) Name and address of the owner - M/s. Serajuddin and Co. / Occupier of the industry, Balda Block

More information

Concrete Waste Management

Concrete Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

Environmental Guidelines for Construction Sites

Environmental Guidelines for Construction Sites Inspection Items Guidelines Remarks 1) Air Pollution Control 1a) Notification to EPD before Work Commencement If the work is classified as notifiable work such as site formation, reclamation, building

More information

RAJASTHAN REFINERY TOWNSHIP PROJECT, RAJASTHAN

RAJASTHAN REFINERY TOWNSHIP PROJECT, RAJASTHAN Page 1 of 10 PRE-FEASIBILITY REPORT FOR Page 2 of 10 Contents 1.0 Introduction... 3 2.0 Approach... 3 3.0 Environmental Sustainability Measures... 4 3.1 Environmental Measures... 4 3.2 Social measures...

More information

J-11011/45/2009- IA II (I)

J-11011/45/2009- IA II (I) SL SPECIFIC CONDITIONS STATUS 1 Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks shall be provided. The particulate emissions shall be controlled within 50 mg/nm

More information

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In earlier project planning the total plot area

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

Approval of Terms of Reference (TOR) For Development of Smart City Project, Ranchi, Jharkhand. M/s Ranchi Smart City Corporation Limited.

Approval of Terms of Reference (TOR) For Development of Smart City Project, Ranchi, Jharkhand. M/s Ranchi Smart City Corporation Limited. 1. INTRODUCTION The proposed Development of Smart City Project is at Ranchi, Jharkhand. The developer of the project is M/s Ranchi Smart City The Land use of the project site is as per master plan of the

More information

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc.

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc. Project name:- Project Code :- Registration Category :- General Comments :- Drawings Feedback:- 1st feedback No Dwg Name Dwg Description Recommendation 1 Site survey plan Site plan showing following in

More information

Environment protection measures / technology

Environment protection measures / technology Sr. No. Conditions A. Specific Conditions: i. The gaseous and particulate matter emissions from various units should conform to the standards prescribed by the State Pollution Control Board. At no time,

More information

SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016

SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016 SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016 GROUP HOUSING COMPLEX MAHAGUN MANTRA - II AT GH-01, Sector-10, Greater Noida, U.P. Being developed by. The Corenthum Tower-B, Office no. B-44, Plot no.-a-41,

More information

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT Annexure B Land Possession letters & N.A. permission letters Annexure C Photograph of the Site Annexure D Details of Buildings Area Calculation Annexure 1 Topo Sheet Annexure 2 Soil Analysis Report Annexure

More information

Larsen & Turbo Limited ENVIRONMENTAL MANAGEMENT PLAN

Larsen & Turbo Limited ENVIRONMENTAL MANAGEMENT PLAN ` Larsen & Turbo Limited The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plans for which the

More information

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS APPENDIX II (See paragraph 6) FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT (Attach panoramic view of the project

More information

Amrut Manthan + Shree Mahalaxmi & Primus Residences by M/s Gurukrupa Developers ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers pr

Amrut Manthan + Shree Mahalaxmi & Primus Residences by M/s Gurukrupa Developers ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers pr ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers proposes a Slum Rehabilitation project Amrut Manthan + Shree Mahalaxmi & Primus Residences located at C.T.S. No. 4091, 4091/1 to 37,

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

Environment Management Plan For B 2 Category Project

Environment Management Plan For B 2 Category Project Environment Management Plan For B 2 Category Project Project Proponent - Kirtikumar Nathubhai Shah Address - N/V Damlai, Taluka- Jhagadia District - Bharuch Near Village Taluka District Area Survey No.

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan (EMP) would consist of all mitigation measures for each component of the environment due to the activities increased during the construction,

More information

sqm. 123 kld (Landscaping - 31 kld, Dual Flushing 73 kld Car Washing - 19 kld) Quantity Of Wastewater Discharge

sqm. 123 kld (Landscaping - 31 kld, Dual Flushing 73 kld Car Washing - 19 kld) Quantity Of Wastewater Discharge DETAILS OF PROJECT The project proponent wants to develop a Residential Building with all modern amenities Premises No. 116, Roy Bahadur Road (previously known as 352, Roy Bahadur Road), Kolkata - 700053

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment

More information

ECO MESH PIPE. ECO-Mesh Inc.

ECO MESH PIPE. ECO-Mesh Inc. ECO MESH PIPE ECO-Mesh Inc. http://www.eco-mesh.com ECO MESH PIPE - Manufacturing ECO Mesh Pipe is Made of Extruded Plastic Shape of ECO Mesh Pipe Square Mesh Pipe Arched Mesh Pipe Mesh Drainage Pipe v

More information

Total Built Up Area. Quantum Of Water Required Quantity Of Wastewater Generation 332kld

Total Built Up Area. Quantum Of Water Required Quantity Of Wastewater Generation 332kld DETAILS OF PROJECT The project proponent, P N Memorial Neurocentre & Research Institute Limited, is developing a Hospital Building at Premises No.-720, Anandapur, Ward. Kolkata- 700 107, KMC, Ward No.

More information

Permeable Pavement. Pavements constructed with these units create joints that are filled with permeable

Permeable Pavement. Pavements constructed with these units create joints that are filled with permeable Permeable Permeable pavement is a paving system which allows rainfall to percolate through the surface into the underlying soil or an aggregate bed, where stormwater is stored and infiltrated to underlying

More information

Details of Project. Underground source

Details of Project. Underground source Details of Project The project proponent wants to develop a Residential complex with all modern amenities at R.S./L.R. Dag No - (442,447,453,454, 443,444), J.LNo-29 Of Khamar Mouja & R.S./L.R. Dag No-(99(P),101,102(P),103,105,106,107,108,109,110,111,112,113(P),114(P),115,125,126,

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

Environment Management Plan For B 2 Category Project

Environment Management Plan For B 2 Category Project Environment Management Plan For B 2 Category Project Project Proponent Shri Alihusen Haji Mohammadali Alirajpurwala Address - N/V Kanawant, Taluka & District - Chhotaudepur Near Taluka District Area Survey

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN For SOWPARNIKA SAMETHANA M/s SOWPARNIKA PROJECTS AND INFRASTRUCTURE PVT LTD Sy No.57/1,57/2 & 277 of Anugondanahalli hobli, Samethanahalli village,hoskote Taluk, Bangalore

More information

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 1.1 INTRODUCTION The primary function of an environmental impact assessment study is to predict and quantify potential impacts, and assess & evaluate

More information

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER M/s. Subham Planners Ltd.

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER M/s. Subham Planners Ltd. COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER 2013 Name of The Company : M/s. Subham Planners Ltd. Project : Construction of group housing project at Village Betkuchi,

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

WELCOM TO THE STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT APPRAISAL COMMITTEE,A.P. For the Presentation proposed Granite Mine 7.50 Acres M/S N.R.

WELCOM TO THE STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT APPRAISAL COMMITTEE,A.P. For the Presentation proposed Granite Mine 7.50 Acres M/S N.R. WELCOM TO THE STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT APPRAISAL COMMITTEE,A.P. For the Presentation proposed Granite Mine 7.50 Acres M/S N.R.Global Granites Production Granite Black Granits At Survey

More information

PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT

PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT AT Survey No 3, Sampigehalli Main Road Yelahanka Hobli Bangalore North PREPARED BY: M/S Seamak Hi-tech Products #797, 1 st cross, 12 th Main, HAL

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan Of Dr. Mittal Laboratories Pvt. Ltd. Plot No. C-10/2, SARA Industrial Estate Ltd., Village Rampur, Dehradun - Chakrata Road, Selaqui, Dehradun, Uttrakhand For Manufacturing

More information

PRESENTATION FOR ADDITIONAL DETAILS FOR ENVIRONMENTAL CLEARANCE TO STATE LEVEL EXPERT APPRASIAL COMMITTEE FOR

PRESENTATION FOR ADDITIONAL DETAILS FOR ENVIRONMENTAL CLEARANCE TO STATE LEVEL EXPERT APPRASIAL COMMITTEE FOR PRESENTATION FOR ADDITIONAL DETAILS FOR ENVIRONMENTAL CLEARANCE TO STATE LEVEL EXPERT APPRASIAL COMMITTEE FOR PROPOSED CONSTRUCTION BUILDING PROJECT OF NILA INFRASTRUCTURES LTD (25988.59 m 2 Built up Area)

More information

BMP #: Infiltration Basin

BMP #: Infiltration Basin Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with

More information

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E3072 v2 GEF Large City Congestion and Carbon Reduction Project Environment Management

More information

Concrete Waste Management WM-8

Concrete Waste Management WM-8 Standard Symbol BMP Objectives Soil Stabilization Sediment Control Tracking Control Wind Erosion Control Non-Storm Water Management Materials and Waste Management Definition and Purpose Appropriate Applications

More information

Environment Management Plan. SEZ Phase III Residential Project,

Environment Management Plan. SEZ Phase III Residential Project, For SEZ Phase III Residential Project, at Village Hinjewadi, Taluka - Mulshi, District Pune. Proposed by Paranjape Schemes (Construction) Ltd. CONSULTANT Mahabal Enviro Engineers Pvt. Ltd. Plot F-7, Road

More information

Paving and Grinding Operations

Paving and Grinding Operations Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2 THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2.6 MILLION TPA CEMENT & THERMAL POWER PLANT 36 MW EC Lr. No. : J-11011/403/2006-IA-II

More information

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER FOR SPECIAL CONDITIONS AND PERMIT NUMBERING GENERAL NOTES: HOUSE GREEN HOUSE 1900 S. NORFOLK ST. SUITE 350 GARAGE GRADING

More information

Plaza and Sidewalk Cleaning

Plaza and Sidewalk Cleaning Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Pollutants on sidewalks and other pedestrian traffic areas and plazas are typically due to littering and vehicle use. This

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

Air Traffic Control Tower and Technical Block, Netaji Subhash Chandra Bose International Airport, Kolkata

Air Traffic Control Tower and Technical Block, Netaji Subhash Chandra Bose International Airport, Kolkata 1. ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan (EMP) would consist of all mitigation measures for each component of the environment due to the activities increased during the construction,

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information