PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT

Size: px
Start display at page:

Download "PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT"

Transcription

1 PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT AT Survey No 3, Sampigehalli Main Road Yelahanka Hobli Bangalore North PREPARED BY: M/S Seamak Hi-tech Products #797, 1 st cross, 12 th Main, HAL 2 nd Stage, Indiranagar Bangalore-08

2 INDEX SL NO CONTENT 1 Form 1 2 Form 1A 3 Prefeasibility Report ANNEXURES I Site plan 2 Landscape plan 3 Land documents 4 CDP plan 5 Sewage treatment plant Report 6 Savings in Electrical power consumption 7 Topo Map 8 Contour Map 9 Google Image 10 Village Map

3 1. INTRODUCTION 1.1 Background of the project Provident Housing Limited, #130/1, Ulsoor Road, Bangalore 42, propose to develop Residential apartment at Sy No. 3 of Sampigehalli Village, Yelahanka Hobli, Bangalore North which consists of 249 apartments. Total site area of the proposed project is Sq m with the built up area of Sq m. The Company has now evolved to have safe operation in the above-proposed area that has led for the Environmental Management Plan (EMP). Since the proposed activity constitutes construction of buildings, it requires Environmental Clearance from State Environment Impact Assessment Authority (SEIAA), under sector 8(b) of EIA Notification The Conceptual Plan describes all the details of the project and its specific activities that will be considered for investigation of the significant adverse impacts. The report also provides specific measures that will be put to practice to minimize the impacts on the Environment. 2. DESCRIPTION OF THE PROJECT SITE 2.1 Location The proposed construction of Residential group house project is located at Sy No. 3 of Sampigehalli Village, Yelahanka Hobli, Bangalore North which is in Latitude 13 5'0.14"N and Longitude 77 37'13.52"E. The Satellite Image of the project site is shown in Figure 2.1 the location of the project site is shown in Figure 2.2 and the Site Layout & Landscape map of the project site is shown in Annexure I & Annexure II. The land documents is enclosed as Annexure III 35

4 Figure 2.1 Satellite Image of the Project Site 36

5 Figure 2.2 Maps Showing the Location of the Project Site 37

6 2.2 Environmental Sensitivity of the project site The project site selected to develop the residential apartment is categorized as Residential Use Zone as per CDP map is enclosed in Annexure IV. The existing land use does not get altered as the proposed project is Residential project. The Location plan of the project site is given in Figure 2.3 indicated that the facilities adjacent to the proposed project site are mostly residential and less commercial. The project site is connected to Sampigehalli main road & close to Tanisandra main road. Hence proposed development/land use is consistent with the surroundings. The Site plan is enclosed as Annexure I. The environmental setting of the project site is given in Table 2.1. Figure 2.3 Location Plan of Project 38

7 Table 2.1 Environmental setting of the Project site Sl. No Particulars Details 1 Site Latitude 13 5'0.14"N 2 Site Longitude 77 37'13.52"E 3 Topography Plain 4 Nearest Bus Stand Chokkanahalli Bus Stop( NE)- 650 Mtr 5 Nearest Railway Station Yelahanka Railway station (NW)-5.9 Km 6 Nearest airport Kempegowda International Airport (N) 26.5 KM 7 Nearest Highway Ballary main Road (W) 4.3 Km 8 National parks/ Wildlife Sanctuaries Banneraghatta National Park(S) 53 Km 9 Reservoir/Lake Jakkur Lake(W) -700 Mtr 10 Seismic Zone Seismic zone II 39

8 2.3. Topography & Drainage The contour map of the project site is given in Figure

9 2.4 PROJECT DESCRIPTION Overview of the project M/s Puravankara Projects Ltd Proposes to construct 249 residential apartments at Sy No. 3 of Sampigehalli Village, Yelahanka Hobli, Bangalore North. The breakup details of the land area is detailed below in Table 2.2 Table 2.2 Summary of the project site details Sl No. Description Area in Sqm Area in % 1 Total Site Area a Civic Amenities - - b Building Coverage Area c Drive way d 1. Park and open Space On podium Green Area total (A+B) FAR Area (2.248) - 3 Built Up Area No. of apartment Proposed Total No of Floors B+G+9 Floors 6 Maximum height of the Building Mtr - The land ownership documents are given in Annexure II. The total built-up area of the proposed project is Sq m. The project proponents will apply for BBMP plan sanction after all statutory clearances. The area statement for each block is given in Site plan (Annexure I) 2.5 Population Details The total man power requirement during the construction phase and the expected population during the operational phase of the proposed project are given below in Table 2.3 and Table 2.4 respectively. 41

10 Table 2.3 Manpower Requirement during Construction Period Sl.No Description 1 Approximately 150persons Inclusive of workmen, Labourers, Supervisors, Engineers, Architects and Managers Table 2.4 Expected Population Details during Operational Phase Description No. of Persons/Unit Total No. of Persons Dwelling Units (249) Floating Population ( 10% of total Population) Total population Project cost The expected project cost for the proposed Residential group house project is estimated to be around Rs. 75 Crores 2.7 Construction Materials Quantity of construction materials required for the proposed construction is given in Table 2.5 Table 2.5 Quantity of Construction Materials Required Material Description Units of measurement Approximate Quantity for 249Units Concrete Cu m 4000 Steel MT 1400 Cement Cu m 5000 Sand Cu m 6000 Aggregate Cu m

11 2.8 WATER CONSUMPTION DETAILS Fresh Water requirement during construction phase shall be 5 KLD which will be supplied by private water tankers. Total water requirement during operation phase shall be 173KLD and the sewage generated shall be around 156 KLD which shall be treated through a sewage treatment plant of 160 KLD. The quantity of treated water from the STP is 156 KLD. From the treated water 60 KLD shall be reused for flushing, 16.3 KLD shall be reused for gardening within the facility and 2.5 KLD for car washing. The excess 77KLD of treated water will be used for construction purposes to our upcoming construction projects in the nearby area & to UGD. The quantification of the water demand in the proposed project has been enlisted in Table 2.6 Sl No Table 2.6 Details of Water requirement Calculation for 249units Description 1 Dwelling Units(249No) Occupancy Water Break up of Fresh Water Recycle Details Demand/ demand / Demand in ltr water person/day person / day in (Drinking, cooking, demand in ltr washing utensils, ltr Bathing) Club House Total The total water requirement for 249 units is lit/day (173 KLD) & the waste water generated after 10% evaporation loss is lit/day i.e. 156 KLD. The most important aspect under the water supply scheme is the selection of source of Water, which should be reliable and potable. The proponents of the proposed project intend to utilize the supply of water through BWSSB. It is distributed through a network of distribution system. 43

12 Recycling Total Water Required 173 KLD Sourced from BWSSB Recycled Water 60 KLD Fresh Water KLD Domestic 112 KLD Club House 1.2KLD 10% evaporation loss 156KLD Sewage Treatment Plant of 160 KLD Recycled water Available 156 KLD Water for Flushing 60 KLD Landscaping & car washing 19 KLD Excess treated water will be used for construction of our upcoming projects in nearby area & UGD 77KLD Figure 2.8 Water Balance Chart WATER TYPE & TREATMENT Water treatment plant shall be provided in accordance with the various usage requirements. The various types / quality of water and their water treatment plant are as follows: Domestic Water: Domestic water is treated in Water treatment plant to produce drinking water that is pure enough for the most critical of its intended uses, usually for human consumption. Individual tenant can treat the water further (if required) by using localized UV unit (OR) R.O plant. 44

13 Flushing Water: Flushing water for the complex shall be sourced from the in-house sewage treatment plant (STP). The treated effluent for flushing shall be obtained after tertiary treatment at STP. The treated effluent shall be colour-less, odourless and shall be in acceptable chemical/ bacteriological parameters as per KSPCB standards. Irrigation Water: Irrigation water for landscape use shall be sourced from the in-house STP and shall have acceptable parameters as per KSPCB standards SEWAGE TREATMENT PLANT It is proposed to provide sewage treatment plants of 160 KLD capacities for treatment of sewage water. The treated effluent shall be of a quality suitable for domestic use, flushing and for horticulture for external areas. Following parameters shall be adopted for the design of sewage treatment plant. Parameters for design of sewage treatment plant Parameters V a l u e Before Treatment After Treatment ph BOD Mg/L Less than 10 Mg/L Suspended Solids Mg/L Less than 20 Mg/L COD Mg/L Less than50 Mg/L Fecal coliform MPN/100 NIL PROCESS DESCRIPTION In order to conserve water, sewage treatment plant shall be designed to ensure that treated effluent (water) characteristics are well below the permissible limits, even under varying flow conditions which are typical for such systems. This implies that the selected process shall be able to withstand shock load situations. The sewage water is treated in Membrane filtration in MBR technology and reused for domestic purposes, Flushing and for external horticulture. The detailed STP report is enclosed as Annexure-V 2.9. Preventive measures to avoid leaching of treated sewage into nearby water courses Treated water from Sewage Treatment Plants will be conveyed to Treated water Tank through pipelines. All the joints from piping system will be checked periodically and carrying 45

14 treated wastewater pipes will be laid in conduits wherever road crossings are expected. Garland drains will be constructed all around the Development for intercepting water from outside and inside. Thus no leaching of treated sewage into nearby water courses shall take place. 2.1 Solid Waste Generation, Collection, Transport and Disposal The quantity of solid waste generated from the proposed project is estimated to be 498Kg/day. Waste generated by users- Domestic wastes food left over s, vegetable peels, plastic, house sweepings, clothes, ash, etc. commercial waste generally comprises of paper, cardboard, plastic, wastes like batteries, bulbs, tube lights etc. Colored bin system for different categories of waste is a good option for segregation at household level. Storage facilities will be created and established by taking into account quantities of waste generation in a given area and the population densities. The estimation of solid waste generation for Residential houses is taken as 0.4 kg/person/day. Solid waste generated in total is about 498 kg/day. Table 2.7 details the calculation of total solid waste generated. The organic waste is 299/day; inorganic waste is 199 Kg/day. STP sludge of about 16kg/day would be filter pressed and used as manure for greenbelt development. Solid waste are collected from individual houses are segregated in to organic & inorganic waste, organic waste is converted into manure using organic converter & used for the development of greenery & inorganic waste will be sent for recycling. Table 2.8 Solid Waste Generation Sl No Description Quantity(Kg/Day) Method of Treatment /Disposal 1 Organic Waste 299 Converted into manure by using Organic waste converter & used for gardening 2 Inorganic Waste 199 Authorized recyclers 3 STP Sludge 16 Filter pressed & used as manure for gardening 4 E-Waste - Collected separately & handed over to Authorized E-waste recyclers 5 Biomedical Waste - Collected separately & handed over to Authorized BMW recyclers 46

15 2.11 RAIN WATER HARVESTING The proposed project has a green belt of Sq.m. Coefficient for Rain fall for landscape area = 0.35 = x 0.35 = Cu.m/hr Coefficient for Evaporation, Spillage and first flush wastage can be considered as 0.8 (for all situations) = x 0.8 = Cu.m /hr There are about 12Recharge pits of 1.2m dia (3 mts Depth varies) Recharging pits are filled with graded media to facilitate percolation of harvested rain water to recharge ground water table. The excess rain water, if any, shall be drained off to the Storm water drain. ROOF TOP HARVESTING Intensity of rainfall in Bangalore is 100 mm The proposed project has a building coverage area of Sq m = Sqm x 1 = Sq m Roof is having tiled finish so coefficient of roof surface can be taken a 0.9 Coefficient for evaporation, spillage & first flush wastage can be considered as 0.80 (for all situations) = Sq mx 0.9 x 0.8 = Cu.m Hence Cu.m of rainwater can be effectively harvested during rainy season from the proposed project. Roof top rain water is collected in rain water collection sumps of 55 cu.m capacity, pre treated & used for daily purpose. Rain water tank capacity 55 Cum Size 5.05m x 3.45m x 3.2m HARDSCAPE & DRIVEWAY The proposed project has a paved area of Sq m For Paved area coefficient of runoff can be taken as 0.7 = X 0.7cum/hr = cum/hr Coefficient for evaporation, spillage & first flush wastage can be considered as 0.80 (for all situations) = x 0.8 = cu.m The project proponents shall also provide 12 Recharging pits along the inner periphery of the boundary wall with recharging pit of size 1.2 m dia x 3m deep spaced at 20 m center to 47

16 center. These recharging pits are filled with graded media comprising of Boulder at bottom and with coarse aggregates to facilitate percolation of harvested rain water to Recharge Ground Water table. The Recharge Pits are interconnected in such a way that the rain led to the first recharge pit is also led to the next pit. The excess rain water shall be drained off to the storm water drain. 600 mm wide storm water drain with pre cast & perforated cover is provided inside the periphery of the boundary POWER SOURCE & REQUIREMENT Power will be availed from BESCOM. Total Electric load for the proposed project is 1420KW. three D G sets with total capacity of 700 KVA ( 2 X X 200) will be used as backup power. DG sets shall be of standby duty and with acoustic enclosure as per CPCB norms. DG set will have AMF panel inside the acoustic enclosure along with fuel tank, batteries and engine mounted control panel. The details of the DG to be used are given in the Table 2.8 Table 2.8 DG Set Details DG set capacity Type of Fuel Material of the Stack Diameter of the Stack Height of the Stack 250 KVA x 2no, 200 KVA x 1no, Diesel MS 150 mm 2meter above roof level (ARL) 2.13 FIRE FIGHTING & FIRE PROTECTION SYSTEM Reference Standards The design and planning of Fire Protection System shall be done keeping in view the following criteria: National Building Code Sept 2005: Part IV for Fire Protection Local Bye-Laws. Relevant BIS codes: Specifically IS: 3011, IS: 5290 and IS: 5312, IS: 908 and IS: 2190, IS: 3811, IS: NFPA & TAC Manual (for reference and guideline). Consultation with local Chief Fire Officer. 48

17 Basis/ Concept of Design The fire fighting arrangement shall be designed as per the requirement of local guidelines, National building code of India -2005, NFPA & engineering design standard. The entire fire safety installation shall be compliant with the most stringent codes / standard and local by laws for the entire site to ensure the highest safety standard and uniformity of system. Further, before property is opened to public, the fire protection shall be fully operated and tested under simulated conditions to demonstrate compliance with the most stringent standards, codes and guidelines. Following functional system shall be provided; strictly in compliance with the listed reference standards: a. Piping System Piping system confirming to IS: 1239 MS Heavy Class. b. Fire water static Fire water static storage has been provided in accordance to Storage Fire NOC from Dept. of Fire and Emergency Services. 50 KLD fire water storage sump is provided c. Fire Pumping Pumping system comprising of hydrant jockey & diesel system engine. d. Hydrant system External & internal hydrant complete with hose reel. e. Hand held fire extinguishers Strategically placed at designated areas. 49

18 2.14 CAR PARKING Parking is a major facility in this residential project. About 280 four wheelers are envisaged to be added to the existing traffic once the construction activity is completed and the building is operational. CARPET AREA PER DWELLING UNIT 50 TO 150 SQ.MT 1 OFF STREET PARKING SPACES AT THE RATE OF FOR EVERY DWELLING CAR PARKING STATEMENT NO OF UNITS NO OF CARS REQUIRED NO OF CARS PROVIDED UNITS BASEMENT COVERED/ PARTIALLY COVERED SURFACE 83 10% OF VISITOR'S CLUBHOUSE 1 FOR EVERY 50 SQ.M FLOOR AREA TOTAL NO OF CARS REQUIRED 280 TOTAL NO OF CARS PROVIDED ENERGY CONSERVATION MEASURES Building Envelope Design is designed in an energy efficient way. Use of virgin wood and other building materials with high embodied energy will be minimized. Recycling and reuse of construction debris to minimize virgin materials. Building materials with high recycle content will be used. The building materials will be made available regionally within 250 miles radius from the project site. Various measures such as protection of soil for reuse for landscaping, barricading to prevent dust, soil and debris movement beyond site to neighboring areas during site planning shall be done. Rain water harvesting to minimize storm water runoff from site 50

19 Selection of low flow toilet fixtures to reduce water consumption Selection of native and adaptive landscaping species Electrical appliances with energy star rating will be installed Use of low VOC materials such as paints, adhesives etc LED Luminaries will be used in all common areas, basement parking area, street lighting, wherever feasible. Lighting and switching to be designed by keeping concept of day lighting integration for all common areas. Combination of Photo cells and Digital programmable timers will be used for switching of External lighting. Copper Conductors -PVC insulated flexible wires will be used for Internal Wiring throughout the project. Pumping Machineries based on Variable Speed Drives will be provided due to variation in demands and head on account of phasing, contours etc to reduce and economize in power consumption to comply to ECBC / LEED guidelines All pumping machineries shall be proposed with Energy Efficiency coating which shall also provide approximately 10 % energy saving. Automatic Power Factor Improvement panels will be provided at each load center for common areas to reduce the overall system losses. Pre Heating hot water requirement through solar based Heating System will be implemented for each tenant spaces. 100% street lighting will be provided with stand alone solar panels + Batteries set mounted on the pole itself. All electrical equipments-domestic/commercial will be with 4/5 Star rating as recommended by BEE, India. Savings in Electrical power consumption are provided in Annexure VI. 51

20 3. ENVIRONMENTAL MANAGEMENT PLAN The mitigation measures suggested for the impacts identified on the various environmental components due to the project activities are given in this section. A detailed environmental management plan is presented in the table 3.1 to mitigate all the identified environmental impacts that are found to be significant. Table 3.1 Environmental Management Plan Construction & Operation Phase Activity Emission from construction vehicles and machinery. Dust generation due to material handling, operation of construction equipments, movement of construction vehicles and construction activities Environmental Impact Construction Phase Impact on Air Quality Decrease of ambient air quality and adverse health impacts. Deterioration of ambient air quality and adverse health effects on construction workers. Mitigation Measures 1. Vehicles transporting construction materials prone to dust emissions should be covered. 2. Trucks carrying sand should be provided with tarpaulin sheets to cover the top and sides of the trucks. 3. All construction vehicles should comply with air emission standards and be maintained properly. 4. Quality of the fuel should be good while using it for construction vehicles and machinery. 1. Sprinkling of water should be carried out on a regular basis during the entire construction period 2. Air quality monitoring should be conducted as per Environmental Monitoring Plan. 3. Adequate stack height will be provided for releasing emissions from the DG sets which will be used occasionally for construction power. 4. Roads should be well maintained for easy and smooth flow of vehicles. 5. Roads to be regularly sprayed with water to suppress dust generation. 6. Workers will be provided with face masks to reduce health hazard. 7. Air quality monitoring should be conducted periodically 52

21 Noise generated from construction vehicles and equipments Surface runoff from the construction site and labor sheds. Disposal of construction wastes, sewage on land. Working Environment of the workers Impact on Noise level Workers will get affected however the impact will be localized and intermittent. Impact on Water Quality Deterioration of water quality of community water sources. Impact on Soil Quality contamination Soil results in infertility of the soil 1. Vehicles used for transportation of construction material should be well maintained. 2. Generator sets should be provided with acoustic enclosures. 3. The workers operating high noise machinery or operating near it should be provided with ear plugs. 4. The high noise generating machinery should not be used during night time. 5. The construction equipment will undergo maintenance test at routine intervals. 6. Noise quality monitoring should be conducted periodically 1. No labour camps and other heavy machinery should be located near to water bodies. 2. No discharge from such establishments should follow their path into nearby water bodies. 3. Dumping of debris in or near to water bodies to be strictly avoided. Waste products must be collected, stored and scientifically disposed. 4. Adequate sanitary facilities, drainage, washing and toilet facilities with mobile STP and refuse collection and disposal should be provided to the workers. 5. Water quality monitoring should be conducted periodically 1. The construction waste will be used for road leveling & drive way 2. The excavated topsoil will be used for landscaping. 3. No disposal of sewage / other waste on land. 4. Soil quality monitoring should be conducted periodically Impact on health and safety of the workers Health and Safety of 1. Adequate water and sanitation facilities the construction will be made available to the workers. workers 2. Safety of workers undertaking various operations during construction should be 53

22 Operation of D.G. sets. Operation Phase change in ambient air quality and noise quality ensured by providing them helmets, masks, safety goggles etc 3. The electrical equipment should be checked regularly to avoid risks to workers. 4. Traffic lighting devices and safety signal devices shall be installed. 5. At work place, a readily available first aid unit and mode of transport (ambulance) will be provided. 6. Quarterly health check-ups of construction workers should be organized at workers colony. 1. Low sulphur diesel will be used for the generators. 2. Acoustic enclosures shall be provided for D.G. sets. 3. Adequate stack height will be provided for the generators for dispersion of pollutants. 4. Ear muffs / plugs will be provided to the personnel in the close vicinity of noise sources. 5. Green belt will be developed which acts as both noise and pollutants absorber. Periodic stack & noise monitoring will be conducted in the operation phase & reports will be submitted to MoEF regional as well as KSPCB Vehicular movement inside the campus. Sewage generation change in ambient air quality and noise quality Affect land and water bodies if not properly 1. Restricting the speed of the vehicles inside the campus. 2. Internal roads will be maintained properly for free movement of vehicles. 3. Roadside tree plantation to be restored and maintained. 4. Separate Exit & Entrance. 5. Separate foot path for pedestrians. 6. Sufficient Parking Facility including extra 10 % for visitors parking. 7. Deploying guards for monitoring the traffic flow within the houses as well as at the junction of the houses & main road. Sewage from the various buildings will be conveyed to the 160 KLD sewage treatment 54

23 Solid generation waste Abstraction of water from bore wells and open wells to meet daily water requirement. disposed. Affect land and water bodies if not properly disposed Depletion of water resources plant with MBR technology. The treated water from sewage treatment plant will be reused for green belt development, toilet flushing and domestic purposes. 1. Proper segregation and collection of wastes will be practiced. 2. Organic waste is about 299 Kg/day and Inorganic waste is about 199 Kg/day. Solid waste will be collected and segregated. The organic waste collected is converted in to manure using organic waste converter and inorganic waste will be sent for recycling. 3. The non-biodegradable solid wastes are sold to vendors and while transporting the waste the vehicles are covered properly to avoid spillages. 1. Rain water harvesting structures will be constructed to recharge the ground water. 2. Percolation pits will be made at suitable points to collect the runoff generated from the paved areas and rainwater from the roof top will be taken to Recharge Trench constructed near all the buildings. Water Conservation Measures 1. Selection & use of native species of vegetation to reduce landscape water requirement. 2. Minimizing the paved surfaces to minimize the storm water runoff volume thereby increases the aquifer recharge. 3. An effective storm water management plan will be implemented. Storm water drains will be constructed to collect the runoff from the paved areas. 4. Since the water consumption is more for flushing applications, treated sewage will be used. Dual plumbing system will be adopted for using treated sewage for flushing purposes. 5. Water efficient fixtures and devices can be used. 55

24 3.1 Environmental management cell Environment Management Cell (EMC) will look after the environment related matters during the construction and operation phase of the project. EMC will perform the following assignments. Regular monitoring of emissions and report any abnormalities for immediate corrective measures. Regular monitoring of ambient air quality, ground and surface water quality. Regular noise monitoring of the work zone and surrounding area. Green belt plantation, maintenance, development of other forms of greenery. Regular monitoring of solid wastes quantity and ascertaining avenues for utilization of solid wastes. Development & maintenance of schemes for water conservation. The Environmental Management Cell (EMC) will take the overall responsibility for coordination of the actions required for environmental management and mitigation, and for monitoring the progress of the proposed management plans and actions to be taken. The organizational set up of the Environmental Management Cell is shown in Figure 3.1 Head of the Environmental Management Engineer- Environment Manager Health & Safety Workers / laborers Safety stewards & nurse STP Operation, Solid waste management, Green Belt Development and Maintenance and Water and Energy Conservation Fire Fighting Safety/ First Aid/ Ambulance Works Involved Figure 3.1 Environmental Management Cell 56

25 3.2 EMP Budgetary Provisions Environmental monitoring and other mitigation measures as proposed in the above sections shall be implemented by the Project Proponent during the construction and operation period. The capital cost works out to around Rs.180Lakhs and the operational cost comes to around Rs.25 Lakhs. The detailed budget provisions are presented in below table S. No EMP Component Capital Cost (Lakhs) Operational Cost (Lakhs) / yr. 1 Monitoring of Environmental - 03 components 2 Water Conservation Measures & Sewage Water Treatment Plant 3 Energy Conservation Measures (Solar equipments) 4 Green Belt Development Environmental Management Cell Total

26 3.4 Environmental Monitoring Schedule It is proposed to monitor essential parameters for ambient air quality, ambient noise quality, ground water quality, and waste water quality both during the construction and operation phases of the project. The frequency of monitoring and method of monitoring will be conducted as per norms of CPCB. However the monitoring schedule is given in Table 3.2. Table 3.2 Environmental Monitoring Schedule S. No Particulars Monitoring Frequency Duration Sampling of Important Parameters Monitoring 1 Ambient Air Quality Monitoring Project site Once in 6 Months 24 hr continuously except CO PM 10, PM 2.5,SO2, NO x & CO 2 Stack Monitoring DG Set Stack Once in 6 Months 30 min SO 2, NO x, PM, CO, Temperature, Flow rate & Velocity of the gas 3 Ambient Noise Level Near DG set Once in 6 Months 8 hr continuous with 1 hr interval Noise level in db(a) 4 Ground/Drinking Water Quality Monitoring Ground Water at project site Once in 6Months Grab Sampling Parameters specified under IS:10500, Soil Quality At the green belt area Once in a year Samples were collected from three different depths viz., 30cm, 60cm, and 100cm below the surface Parameter for soil quality: ph, texture, electrical conductivity, organic matter, nitrogen, phosphate, sodium, calcium, potassium and Magnesium. 58

PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT

PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT PRE-FEASIBILITY REPORT OF A RESENTIAL APARTMENT PROJECT AT Sy No. 86/1, 86/4, 95/1, 95/2 and 95/3 of Thanisandra Village, K R Puram Hobli, Bangalore East PREPARED BY: M/S Seamak Hi-tech Products #797,

More information

5. ENVIRONMENT MANAGEMENT PLAN

5. ENVIRONMENT MANAGEMENT PLAN 5. ENVIRONMENT MANAGEMENT PLAN The environmental management plan consist of the set of mitigation measures, management and, monitoring measures to be taken during construction and operation phase to eliminate

More information

ENVIRONMENT MANAGEMENT PLAN CONSTRUCTION PHASE. suppression instead of water wherever possible. Cell)

ENVIRONMENT MANAGEMENT PLAN CONSTRUCTION PHASE. suppression instead of water wherever possible. Cell) ENVIRONMENT MANAGEMENT PLAN No. 1. Increase in water demand due to water usage for, dust suppression and for domestic purpose of workers 2. Sewage generation (9 KLD) and disposal 3. Solid waste generation

More information

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS Annexure No - 13 SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS File No : Name of the Project: Proposed Commercial project called Bagmane Tech Park RIO Campus of M/s. Bagmane Developers

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION ENVIRONMENTAL MANAGEMENT PLAN An environmental management plan (EMP) has been prepared for the proposed construction of commercial project to minimize negative impacts and is formed on the

More information

TABLE OF CONTENTS. Para No. Contents Page No

TABLE OF CONTENTS. Para No. Contents Page No TABLE OF CONTENTS Para No. Contents Page No Chapter-1 Introduction 1.0 Preamble 1 1.1 Location of the project 1 1.2 Objectives of the EIA study 3 1.3 Methodology of study 3 1.4 Structure of EIA report

More information

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors 1. Increased water demand (12 KLD) due water usage for, dust suppression and for workers 2. Sewage generation (11 KLD) and disposal 3. Municipal solid waste generation (15 kg/day) by workers 4. Construction

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan Report on 1. PROJECT LOCATION & LAND USE The Ganesh Park 3 is a residential building project constructed on plot 608 to 613/5 Vil: GIDC Ankleshwar in Bharuch district of Gujarat state. The project land

More information

Municipal solid / hazardous waste

Municipal solid / hazardous waste (10) ENVIRONMENTAL MANAGEMENT PLAN The mitigation measures for reducing the adverse environmental impacts together constitute a part of EMP. The environmental issues, which need management, plan for the

More information

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006.

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Thus, EIA is not applicable for proposed project. We have derived project

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION 1.2 EMP DURING CONSTRUCTION PHASE

ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION 1.2 EMP DURING CONSTRUCTION PHASE ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

Details of the proposed project as presented before the committee are tabulated below:

Details of the proposed project as presented before the committee are tabulated below: Shrungal Homes Block No. 141, F.P.No.42, O.P.No.42, T.P.S.No.58 (Bamroli), Choryasi, Surat. Screening & scoping / appraisal. Details of the proposed project as presented before the committee are tabulated

More information

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the, operation and the

More information

The emphasis on the EMP development is on the following;

The emphasis on the EMP development is on the following; ENVIRONMENTAL MANAGEMENT PLAN 1.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality. The

More information

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In earlier project planning the total plot area

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Six Monthly Compliance Report June-2015 M/s Mahagun Real Estate Pvt. Ltd SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex Mahagunpuram AT VILLAGE Mehrauli, Dasna, Ghaziabad, U.P. Being developed

More information

Check list for construction Project of EC [Category 8(a)]:

Check list for construction Project of EC [Category 8(a)]: Check list for construction Project of EC [Category 8(a)]: Provide authenticated (with stamp & Signature) hard copy of this check-list during submission of hard copy of ToR application. Sr. no. Checklist

More information

Approval of Terms of Reference (TOR) For Development of Smart City Project, Ranchi, Jharkhand. M/s Ranchi Smart City Corporation Limited.

Approval of Terms of Reference (TOR) For Development of Smart City Project, Ranchi, Jharkhand. M/s Ranchi Smart City Corporation Limited. 1. INTRODUCTION The proposed Development of Smart City Project is at Ranchi, Jharkhand. The developer of the project is M/s Ranchi Smart City The Land use of the project site is as per master plan of the

More information

CONECPTUAL PLAN. w.r.t. Amendment (Expansion) Project of Kalpataru Solitaire. M/s Kalpataru Limited December, 2016

CONECPTUAL PLAN. w.r.t. Amendment (Expansion) Project of Kalpataru Solitaire. M/s Kalpataru Limited December, 2016 CONECPTUAL PLAN w.r.t. Amendment (Expansion) Project of Kalpataru Solitaire at of J.V.P.D scheme of Vile Parle (W), by December, 2016 GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD. (An ISO 9001:2008 Certified

More information

Health and safety norms of CPWD should be followed during construction.

Health and safety norms of CPWD should be followed during construction. Status of Compliance of Conditions of the Environmental Clearance Issued to Riveria Commercial Developers Ltd. DLF Center, Sansad Marg, New Delhi 110001- Construction of "YASHWANT PLACE COMMUNITY CENTRE"

More information

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017 COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER - 2016 TO MARCH-2017 F.No. SEIAA 281/2014/EC/110 SUBMITTED BY- M/S. TERON CONSTRUCTION PVT. LTD MAA PADMA COMMERCIAL COMPLEX, H/N-

More information

No construction activity started

No construction activity started Sr. Particulars Details No. 1. Proposal is for New Project 2. Type of Project Residential Flats and Shops 3. Project / Activity No. 8(a) [8(a) or 8(b)] 4. Name of the project Kaveri Soham Vistara 5. Name

More information

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc.

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc. Project name:- Project Code :- Registration Category :- General Comments :- Drawings Feedback:- 1st feedback No Dwg Name Dwg Description Recommendation 1 Site survey plan Site plan showing following in

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment

More information

Details of Project. Underground source

Details of Project. Underground source Details of Project The project proponent wants to develop a Residential complex with all modern amenities at R.S./L.R. Dag No - (442,447,453,454, 443,444), J.LNo-29 Of Khamar Mouja & R.S./L.R. Dag No-(99(P),101,102(P),103,105,106,107,108,109,110,111,112,113(P),114(P),115,125,126,

More information

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: -

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Conceptual plan Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Area of plot= 5293SQM, Sanctioned FAR = 10586SQM as per earlier sanctioned.(2) Sanctioned Built up Area=19480.63

More information

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005.

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005. GENERAL CONDITIONS 1. The Project Proponent shall comply with all the conditions stipulated in the building approval letter. 2. The applicant (Project proponent) will take necessary measures for preventions,

More information

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS. File No : Name of the Project: Residential and Commercial Building

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS. File No : Name of the Project: Residential and Commercial Building SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS File No : Name of the Project: Residential and Commercial Building Sl. No DOCUMENTS / X 1 Form -1 2 Form -1A 3 Environmental management plan

More information

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT QUERY 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? Attach Maps

More information

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan ENVIRONMENTAL MANAGEMENT PLAN Of Hotel Project for Mohamed Ilyas & Ms. Alamzahan at Khasra No. 269Ga, 269Kh, 266Kh & 270 Village Majra, Tehsil Central Doon, District Dehradun (Uttarakhand) GENERAL ENVIRONMENTAL

More information

Indicative Checklist for construction projects of EC [Category 8(a)]:

Indicative Checklist for construction projects of EC [Category 8(a)]: Indicative Checklist for construction projects of EC [Category 8(a)]: Sr. Checklist point Remark Yes/No Pg. no./ annexure 1. Covering letter signed by the applicant Yes Form-1 Page 1 page 13 2. Completed

More information

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018)

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018) TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Oct 2017 to Mar 2018) Environment Department Tata

More information

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity) [Vide Paragraph - 6 of Notification dated 14 th September 2006, only for construction projects listed under item 8 of the Schedule] (1) LAND ENVIRONMENT (Attach panoramic view of the project site and the

More information

GUIDELINES ON ENERGY CONSERVATION IN SEZs

GUIDELINES ON ENERGY CONSERVATION IN SEZs 1 GUIDELINES ON ENERGY CONSERVATION IN SEZs SEZs are special enclaves aimed at creating world class infrastructure. The guidelines and certification for SEZs is to be implemented as follows: Entire SEZ

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan Of Dr. Mittal Laboratories Pvt. Ltd. Plot No. C-10/2, SARA Industrial Estate Ltd., Village Rampur, Dehradun - Chakrata Road, Selaqui, Dehradun, Uttrakhand For Manufacturing

More information

CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT M/s. DAR Housing Ltd. Proposed Group Housing Project ATS Rhapsody, At Plot No. GH-12/1, Sector-01, Greater Noida (U.P.), having Plot

More information

sqm. 123 kld (Landscaping - 31 kld, Dual Flushing 73 kld Car Washing - 19 kld) Quantity Of Wastewater Discharge

sqm. 123 kld (Landscaping - 31 kld, Dual Flushing 73 kld Car Washing - 19 kld) Quantity Of Wastewater Discharge DETAILS OF PROJECT The project proponent wants to develop a Residential Building with all modern amenities Premises No. 116, Roy Bahadur Road (previously known as 352, Roy Bahadur Road), Kolkata - 700053

More information

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT Annexure B Land Possession letters & N.A. permission letters Annexure C Photograph of the Site Annexure D Details of Buildings Area Calculation Annexure 1 Topo Sheet Annexure 2 Soil Analysis Report Annexure

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan 10.1 INTRODUCTION The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project and ensuring the existing environmental quality.

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Total Built Up Area. Quantum Of Water Required Quantity Of Wastewater Generation 332kld

Total Built Up Area. Quantum Of Water Required Quantity Of Wastewater Generation 332kld DETAILS OF PROJECT The project proponent, P N Memorial Neurocentre & Research Institute Limited, is developing a Hospital Building at Premises No.-720, Anandapur, Ward. Kolkata- 700 107, KMC, Ward No.

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED

FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED Ford Motor Private Limited- Conceptual Plan 1 Contents 1 INTRODUCTION 3 1.1 BACKGROUND 3 1.2 PROJECT LOCATION 3 1.3 PROJECT FEATURES

More information

TABLE-1 PROJECT AT A GLANCE. Location S. F. Nos. 442/1, 442/3, 442/5, 443/1, 443/2, 443/3, 443/4, 443/5, 434/7, 434/8, 434/9 of Kolappalur Village

TABLE-1 PROJECT AT A GLANCE. Location S. F. Nos. 442/1, 442/3, 442/5, 443/1, 443/2, 443/3, 443/4, 443/5, 434/7, 434/8, 434/9 of Kolappalur Village TABLE-1 PROJECT AT A GLANCE Registered Address M/s. Pallavada Technical Textiles Park Private Limited, No. 78, Greams Road, Thousand Lights, Chennai-600006. Communication Address of M/s. Pallavada Technical

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE For PROPOSED RESIDENTIAL AND COMMERCIAL DEVELOPMENT AT Plot bearing survey no. 86/1, 86/2, 86/3 (pt), 86/4 (pt), 86/5 (pt), 115/1 (pt), 115/2 (pt), 115/3 (pt), 115/4 (pt), 115/5

More information

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative) Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in

More information

Department of Ecology and Environment Room No.709, 7 th Floor, IV-Gate, M.S. Building, Bangalore ,

Department of Ecology and Environment Room No.709, 7 th Floor, IV-Gate, M.S. Building, Bangalore , No. SEIAA: 7 : KAR: 2007 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA (Constituted by Ministry of Environment & Forests, Government of India) Department of Ecology and Environment Room

More information

Environment Compliance Report (Apr 2017 to Sep 2017)

Environment Compliance Report (Apr 2017 to Sep 2017) TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Apr 2017 to Sep 2017) Environment Department Tata

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the construction and

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN For SOWPARNIKA SAMETHANA M/s SOWPARNIKA PROJECTS AND INFRASTRUCTURE PVT LTD Sy No.57/1,57/2 & 277 of Anugondanahalli hobli, Samethanahalli village,hoskote Taluk, Bangalore

More information

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath Pre-Feasibility Report for Educational Institute Allen Career Institute-Supath at Plot No. 1, Educational Scheme, Naya Nohra & Hanuwantkhera, Kota, Rajasthan-324001 By M/s. Allen Career Institute Registered

More information

CONCEPTUAL PLAN. for. Submitted to: State Level Environmental Impact Assessment Authority (SEIAA), MoEF&CC, Telangana State.

CONCEPTUAL PLAN. for. Submitted to: State Level Environmental Impact Assessment Authority (SEIAA), MoEF&CC, Telangana State. CONCEPTUAL PLAN for Proposed IT Office Building - 1 Million sft Building in Survey No 124/P, Gopanapally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad, Telangana Submitted to: State

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

Environment Management Plan for Prior Environmental Clearance

Environment Management Plan for Prior Environmental Clearance BRIGADE RESIDENTIAL DEVELOPMENT Environment Management Plan for Prior Environmental Clearance Project Address: Survey No.248/2 (Old No.43/29), Kambipura Village, Kengeri Hobli, Bengaluru South Taluk, Bengaluru

More information

SIA/PB/NCP/53462/2016)

SIA/PB/NCP/53462/2016) Item No.148.08: Application for environmental clearance under EIA notification dated 14.09.2006 for the development of group housing project namely SSL Highway Towers at Chandigarh-AmbalaHighway, Dera

More information

BRIGADE MIXED USE DEVELOPMENT

BRIGADE MIXED USE DEVELOPMENT BRIGADE MIXED USE DEVELOPMENT Terms of Reference (TOR) At Sy. No. 171/1, 171/2, 171/3, 171/4, 172, 173/1, 173/2, 173/3, 183/2, 183/3, 183/6A, 183/6B, 183/7, 183/8, 183/9, 183/11 and 184/1(P) Varthur Village,

More information

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT GUJARAT HOUSING BOARD

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT GUJARAT HOUSING BOARD PRE FEASIBILITY REPORT FOR PROPOSED CONSCTRUCTION BUILDING PROJECT (66460.23 SQ. M) BY GUJARAT HOUSING BOARD AFFORDABLE RESIDENTIAL BUILDING & COMMERCIAL PROJECT PACKAGE 23, PLOT NO. 61/1, 63/1 & 64, TARSAMIYA,

More information

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra.

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Pre- feasibility Report For Shiv Kailasha At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Proposed By M/S Om Shivam Buildcon Private

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Promoter: Navkar Prime Developers Private Limited ENVIRONMENTAL MANAGEMENT PLAN & CER

Promoter: Navkar Prime Developers Private Limited ENVIRONMENTAL MANAGEMENT PLAN & CER ENVIRONMENTAL MANAGEMENT PLAN & CER 52 ENVIRONMENTAL & SOCIAL MANAGEMENT PLAN 1.1 INTRODUCTION: The Environmental impact can be defined as any alteration of environmental conditions, adverse or beneficial,

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Environment Management Plan ENVIRONMENTAL MANAGEMENT PLAN M/s Brigade Enterprises Limited is an ISO 9001 2009, ISO 14001 2004 and OHSAS 18001 2008 certified company with more than twenty-nine years of

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

This project does not attract EIA Notification and provisions in CRZ Notification [Clause no. 4.2 (i) (b)] also exempt preparation of EIA report.

This project does not attract EIA Notification and provisions in CRZ Notification [Clause no. 4.2 (i) (b)] also exempt preparation of EIA report. The proposal under consideration, Regularization of Existing Resort at Sidheshwarwadi, Village Ubhadanda, Taluka Vengurla, Dist. Sindhudurg is located in CRZ III area having total plot area of 4000 m 2,

More information

CONCEPTUAL PLAN. Purva Haveli RESIDENTIAL APARTMENT. AT Municipal No 5, Lalbagh Road, Ward No 48, Sudhamanagar Ward, Pid No.

CONCEPTUAL PLAN. Purva Haveli RESIDENTIAL APARTMENT. AT Municipal No 5, Lalbagh Road, Ward No 48, Sudhamanagar Ward, Pid No. CONCEPTUAL PLAN Purva Haveli RESIDENTIAL APARTMENT AT Municipal 5, Lalbagh Road, Ward 48, Sudhamanagar Ward, Pid. 48-31-5 Bangalore PREPARED BY M/S Seamak Hi-tech Products #797, 1 st cross, 12 th Main,

More information

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated 10.08.2009 Period : January 2018 to June 2018 Sl.No. CONDITIONS STIPULATED BY MoEF COMPLIENCE Specific Conditions

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

SEIAA: 42 (B): CON: 2007 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA

SEIAA: 42 (B): CON: 2007 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA To, Sir, No. SEIAA: 42 (B): CON: 2007 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA (Constituted by Ministry of Environment & Forests, Government of India) M/s. Prestige Estates Projects

More information

PROPOSED TERMS OF REFERENCE FOR PROPOSED RESIDENTIAL DEVELOPMENT

PROPOSED TERMS OF REFERENCE FOR PROPOSED RESIDENTIAL DEVELOPMENT FOR AT SURVEY NOS. 123, 127(P) & 128, K R PURAM HOBLI, BENGALURU EAST TALUK, PROMOTER: M/s. PRESTIGE ESTATES PROJECTS LIMITED, PREPARED BY M. D. SANJAY KUMAR C/o. M/s. A&N TECHNOLOGIES # 855, 3 RD FLOOR,

More information

Amrut Manthan + Shree Mahalaxmi & Primus Residences by M/s Gurukrupa Developers ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers pr

Amrut Manthan + Shree Mahalaxmi & Primus Residences by M/s Gurukrupa Developers ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers pr ENVIRONMENTAL MANAGEMENT PLAN Introduction M/s Gurukrupa Developers proposes a Slum Rehabilitation project Amrut Manthan + Shree Mahalaxmi & Primus Residences located at C.T.S. No. 4091, 4091/1 to 37,

More information

BRIGADE RESIDENTIAL DEVELOPMENT

BRIGADE RESIDENTIAL DEVELOPMENT BRIGADE RESIDENTIAL DEVELOPMENT Terms of Reference (TOR) At Plot No. R5 and Plot No. R8, Hi Tech, Defense and Aerospace park (Hardware Sector), KIADB Industrial Area, Jala Hobli, Yelahanka Bengaluru North

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 PREAMBLE Environmental Protection and Sustainable development have been the cornerstones of the policies and procedures governing the residential, commercial, industrial and

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN of SECRETARIAT STAFF HOUSING PROJECT AMARAVATI, ANDHRA PRADESH PICTORIAL VIEW OF THE SECRETARIAT STAFF HOUSING PROJECT SEPTEMBER 2017 PROJECT PROPONENT Andhra Pradesh Capital

More information

PROJECT CONCEPT REPORT

PROJECT CONCEPT REPORT PROJECT CONCEPT REPORT for Proposed RESIDENTIAL BLOCK UNDER Expansion (Phase-2) of MANI CASADONA PROJECT at Plot No. IIF/04, Action Area-II, New Town, P.S. Rajarhat, New Town Kolkata Development Authority,

More information

FORM 1, FORM 1A, CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN OCEANUS CARMEL HEIGHTS

FORM 1, FORM 1A, CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN OCEANUS CARMEL HEIGHTS FORM 1, FORM 1A, CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN FOR OCEANUS CARMEL HEIGHTS DEVELOPMENT OF RESIDENTIAL APARTMENT AT SY. NO. 16(P), WHITEFIELD VILLAGE, K. R. PURAM HOBLI, BENGALURU EAST

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

2. The expected cost of the project is Rs.50 crores.

2. The expected cost of the project is Rs.50 crores. Subject Application for obtaining Environmental Clearance for development of an "Integrated Municipal Solid Waste Management System for Pathankot Cluster" by Municipal Council, Pathankot at Village Kalanaur,

More information

COMPREHENSIVE PROJECT REPORT FOR PROPOSED Training Center - TVS Institute for Quality and Leadership

COMPREHENSIVE PROJECT REPORT FOR PROPOSED Training Center - TVS Institute for Quality and Leadership COMPREHENSIVE PROJECT REPORT FOR PROPOSED Training Center - TVS Institute for Quality and Leadership At Survey Nos. 63, 64/1, 64/2, 64/3, 65/1, 65/2, 66, 67, 68, 69/1, 69/2, 69/3, 69/4, 70/1,70/2, 71/3,75,

More information

Environmental Management Plan during Construction Phase

Environmental Management Plan during Construction Phase Management Plan during Phase Sr 1 Ambient Air Quity Negative inside site premises outside site 2 ise Negative near noise generation sources inside premises on ambient noise levels in the Surrounding area

More information

CHAPTER-1 INTRODUCTION

CHAPTER-1 INTRODUCTION CHAPTER-1 INTRODUCTION PREAMBLE: The Ministry of Environment & Forest has recently amended its Environmental Impact Assessment Notification vide S.O. 60(E) dated 27.01.1994, covering the following Projects:

More information

ADDITIONAL ATTACHMENTS TO FORM-1 M/S. SDB DIAMOND BOURSE

ADDITIONAL ATTACHMENTS TO FORM-1 M/S. SDB DIAMOND BOURSE ADDITIONAL ATTACHMENTS TO FORM-1 FOR OBTAINING ENVIRONMENT CLEARANCE For Proposed Commercial Complex Surat Diamond Bourse M/S. SDB DIAMOND BOURSE Block No. 177/P, Moje- Khajod, Taluka- Surat City, District

More information

M/s. Salarpuria Properties Private Limited Page 1 of 105

M/s. Salarpuria Properties Private Limited Page 1 of 105 Environmental Impact Assessment Report Proposed Residential & Commercial Development M/s. Salarpuria Properties Private Limited Page 1 of 105 Environmental Impact Assessment Report Proposed Residential

More information

Environment protection measures / technology

Environment protection measures / technology Sr. No. Conditions A. Specific Conditions: i. The gaseous and particulate matter emissions from various units should conform to the standards prescribed by the State Pollution Control Board. At no time,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report Environmental Clearance Compliance Half Yearly Report HALF YEARLY COMPLIANCE REPORT- April 2015 to September 2015 Ref: 1. MOEF, New Delhi Environment Clearance F. No. J-11011/119/2007- IA II (I) dated

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Collection of Base line data in any season other than Monsoon season in study area of 10 kms radius from Lease Area. Based on the Meteorological data from

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

Water Management. How do we reduce and recycle our wastewater?

Water Management. How do we reduce and recycle our wastewater? How do we reduce and recycle our wastewater? SRM IST has a long-term commitment for conservation for water. The Institute of Science and Technology will regularly monitor the use of water with frequent

More information

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh EXECUTIVE SUMMARY SUBMITTED BY M/s. Lakshmanan Cements Pvt Ltd No. 58-A, 25

More information

SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016

SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016 SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016 GROUP HOUSING COMPLEX MAHAGUN MANTRA - II AT GH-01, Sector-10, Greater Noida, U.P. Being developed by. The Corenthum Tower-B, Office no. B-44, Plot no.-a-41,

More information

Pre-Feasibility Report

Pre-Feasibility Report PROJECT PREFEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENTAL CLEARENCE IN TERMS OF PROVISIONS OF EIA NOTIFICATION-2006 1.0 EXECUTIVE SUMMARY OF THE PROJECT Sr. No Description Details 1 Proposed project

More information

Point wise reply. There is no change in water requirement and wastewater generation. However, water balance enclosed as Annexure-I.

Point wise reply. There is no change in water requirement and wastewater generation. However, water balance enclosed as Annexure-I. Mohammadpur Korji, P.S.- Phulwarisharif, District- Patna, Bihar by M/s Balprada Built Pvt. Ltd. Point wise reply Point 1: Submit revised water balance for the Project There is no change in water and wastewater

More information

J-11011/45/2009- IA II (I)

J-11011/45/2009- IA II (I) SL SPECIFIC CONDITIONS STATUS 1 Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks shall be provided. The particulate emissions shall be controlled within 50 mg/nm

More information