Dulles Corridor Metrorail Project
|
|
- Moris Ferguson
- 6 years ago
- Views:
Transcription
1 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2016 NOVEMBER 2016
2 Phase 2 Cost Summary September Expenditures $ 29.0 Million Total Expenditures $ Million Total Budget $ Billion Total Forecast $ Billion
3 Phase 2 Contingency Utilization Total Contingency Contingency Utilized through August 2016 $ Million $ 99.4 Million Contingency Utilized in September 2016 $ 1.9 Million Total Contingency Utilized through September 2016 Remaining Contingency $ 101.3Million $ Million
4 September Contingency Utilization Total Contingency Utilized in September 2016 $ 1.9 Million Package A (CRC) $ 1.8 Million $ 952,000 Revisions related to bus shelters at Innovation & Herndon Stations (Settled at credit of $908,000) Technical clarification of the Herndon Station South facilities - Design (Settled at $511,500) Redesign of the proposed contact rail heater controller (Settled at $159,000) Dispose of solid asphalt rubble mixed with soil Differing Site Conditions at Airport Traction Power Substation (TPSS) 15 and Storm Water Maintenance Pond 2-7C (Settled at $1,313,000) Lighting specifications, schedule, and calculation refinements for fixture additions Design $ 731,500 $ 59,000 $ 25,900 $ 13,000
5 Current Guideway & Stations Design-Build Activities Advancement of Design Packages: Critical Path Design packages complete. Outstanding packages: o o o o o Reston Parkway Improvements IFP* & IFC** Herndon South Site IFP & IFC Herndon South Utilities Relocation IFP & IFC Projectwide Signage IFC Loudoun Gateway Water & Sewer - IFC 150 Identified Design and Field Changes: 89 in process; 61 yet to be submitted by CRC 26 reviewed/processed by MA-39 last month 13 Permit Amendments issued for Design Revisions 80 Supplier Submittals reviewed/processed *IFP Issued for Permit **IFC Issued for Construction
6 Upcoming Guideway & Stations Design-Build Activities Reston Station Pour foundations, station walls and continue precast installation. Herndon Station Continue station precast installation and installation of underground systems and utilities. Innovation Station Complete steel erection and precast work, continue electrical and plumbing rough-in and construct pedestrian bridge columns. Dulles Station Continue casting columns and aerial guideway substructures, complete demolition of walkback tunnel. Aerial Guideway Continue to install decks and girders at the Airport, strip forms from straddle bent #YL2-3 and move to Greenway median. Track Continue installation of aerial and at grade rail.
7 Guideway & Stations Design-Build Activities Construct Abutments in Greenway Median
8 Guideway & Stations Design-Build Activities Install Piles in DIAAH Median for Future Town Center Parkway Underpass
9 Guideway & Stations Design-Build Activities Cast Guideway Decks Over Rudder Road
10 Guideway & Stations Design-Build Activities Form and Pour Last of Guideway Columns at Airport
11 Guideway & Stations Design-Build Activities Set Girders Along Airport Cargo Facilities
12 Guideway & Stations Design-Build Activities Erect Structural Steel at Innovation Station
13 Guideway & Stations Design-Build Activities Pulling Cables to Platform in Conduits at Innovation Station
14 Guideway & Stations Design-Build Activities Precast Installation at Herndon Station
15 Guideway & Stations Design-Build Activities Begin Setting Precast at Reston Station
16 Guideway & Stations Design-Build Activities Dulles Station Precast Erection
17 Guideway & Stations Design-Build Activities Completing Walkback Tunnel Demolition
18 September Contingency Utilization Package B (HP) $ 0.1 Million Finger platform length change (Settled at $115,000) $ 75,000 Revise equipment provisions for Transportation Police Building crime scene work area (Settled at $45,500) Transportation Police Building generator connector - Design and Installation Re-perform TPSS ground grid calculations to conform with existing WMATA criteria (Settled at $5,568) $ 40,500 $ 10,000 $ 568
19 WMATA Rail Yard & Maintenance Facility Design-Build Activities Current Construction of all at grade and underground facilities has been permitted. Blasted rock is being crushed, screened and stockpiled. Final grading, storm and sanitary utility installation and yard layout continues. Current efforts are concentrated in the Service and Inspection Building (SIB) basement walls, hoist pit slabs and walls, and traction power distribution ductbanks.
20 WMATA Rail Yard & Maintenance Facility Design-Build Activities Upcoming Construction of all facilities. Advance Projectwide design documents to Issued For Permit. Working with WMATA to resolve pending design change requests. Review shop documents and revised design documents.
21 WMATA Rail Yard & Maintenance Facility Design-Build Activities Retaining Wall Construction at Horsepen Lake
22 WMATA Rail Yard & Maintenance Facility Design-Build Activities Service and Inspection Building Car Hoist Pits
23 WMATA Rail Yard & Maintenance Facility Design-Build Activities Service and Inspection Building Basement
24 WMATA Rail Yard & Maintenance Facility Design-Build Activities Rock Crushing Operation
25 DULLESMETRO.COM
26 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 MONTHLY COST SUMMARY As of September 30, 2016 Description Budget Total Expenditures to Date Contract Contract Amount Forecast Amount Total NTP Substantial Percent b c c/b DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A 1,193,777,000 1,292,690, ,609,747 43% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280, ,363,964 67,554,765 25% 18-Nov Jun-18 ROW 58,600,000 58,397,000 6,296,744 11% 8-Jul Sep-17 WMATA 305,324, ,324,718 42,929,307 14% N/A 3-Feb-20 PRELIMINARY ENGINEERING 75,000,000 75,000,000 73,266,056 98% 15-Jul Dec-13 PROJECT MANAGEMENT 320,802, ,345, ,730,517 48% N/A 2-Jan-19 CONTINGENCY 551,451, ,113,635 TOTAL FOR DCMP 2,778,235,564 2,778,235, ,387,137
27 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 CONTINGENCY UTILIZATION As of September 30, 2016 ATTA Description Amount in million ($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Total Contingency $ Contingency Utilized through August 2016 $ 99.4 Expended Contingency in September 2016* $ 1.9 Total Contingency Utilized through September 2016 $ Remaining Contingency $ *See table below for details Package A (CRC) $1.8 Million Revisions Related to Bus Shelters at Innovation & Herndon Station (Settled at $ 952,000 credit of $908,000) Technical Clarification of the Herndon Station South Facilities - Design (Settled at $ 731,500 $511,500) Redesign of the Proposed Contact Rail Heater Controller (Settled at $159,000) $ 59,000 Dispose of Solid Asphalt Rubble Mixed with Soil Differing Site Conditions at TPSS 15 and SWM Pond 2-7C (Settled at $1,313,000) Lighting Specifications, Schedule, and Calculation Refinements for Fixture Additions - Design $ $ 25,900 13,000 Package B (HP) $0.1 Million Finger Platform Length Change (Settled at $115,000) $ 75,000 Revise Equipment Provisions for Transportation Police Building Crime Scene Work $ 40,500 Area (Settled at $45,500) Transportation Police Building Generator Connector - Design and Installation $ 10,000 Re-perform TPSS Ground Grid Calculations to Conform to Existing WMATA Criteria (Settled at $5,568) $ 568
28 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A DCMP 5401 Package A - Mainline (CRC) 1,177,777,000 DCMP 5406 Commodity Escalation 16,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package A 1,193,777,000 DESIGN-BUILD Package B+S DCMP 5402 Package B - Yard 269,280,530 DCMP 5402 Package S - Yard Site Preparation incl above DCMP 5406 Commodity Escalation 4,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package B+S 273,280,530 ROW DCMP 5404 Land & Relocation 47,225,000 DCMP 5404 Support Services 11,375,000 DCMP 5408 Contingency SUBTOTAL - ROW 58,600,000 WMATA DCMP 5405 WMATA Vehicles 205,868,200 DCMP 5405 WMATA other costs 90,205,767 DCMP 5405 WMATA Non Revenue Vehicles 9,250,751 DCMP 5408 Contingency SUBTOTAL - WMATA 305,324,718 PRELIMINARY ENGINEERING DCMP 5406 PRELIMINARY ENGINEERING 75,000,000 SUBTOTAL - PRELIMINARY ENGINEERING 75,000,000 PROJECT MANAGEMENT DCMP 5406 MWAA Staff 34,000,000 DCMP 5406 MWAA Allocated Cost 13,560,000 DCMP 5406 Rent 9,200,000 DCMP 5406 Relocation, IT, Furniture 2,700,000
29 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DCMP 5406 MWAA ODCs 17,060,000 DCMP 5406 Insurance (OCIP) 49,082,137 DCMP 5406 PMSS 140,000,000 DCMP 5406 VDOT 10,000,000 DCMP 5406 DRC Prof Svcs 2,500,000 DCMP 5406 CTI (Special Inspections) 14,000,000 DCMP 5406 DGS 2,000,000 DCMP 5406 TRIP II 2,000,000 DCMP 5406 Dept of Conservation & Recreation (DCR) 2,000,000 DCMP 5406 MWAA Permits/Inspection 4,000,000 DCMP 5406 Power for System Testing 16,000,000 DCMP 5406 Historical/Archaeologic 2,700,000 DCMP 5408 Contingency SUBTOTAL - PROJECT MANAGEMENT 320,802,137 CONTINGENCY DCMP 5408 Contingency - Package A 289,067,231 DCMP 5408 Secondary mitgation amount - Package A 0 DCMP 5408 Contingency - Package B 109,006,387 DCMP 5408 Secondary mitgation amount - Package B 0 DCMP 5408 Contingency - ROW 5,860,000 DCMP 5408 Contingency - WMATA 30,532,472 DCMP 5408 Contingency Project Management 116,985,089 SUBTOTAL - CONTINGENCY 551,451,179 TOTAL FOR DCMP - PHASE 2 2,778,235,564
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationCapital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager
Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.
More informationAPPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED
APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H: ALTERNATIVES PREVIOUSLY CONSIDERED This appendix provides an overview of the process that led to the selection of the Locally Preferred Alternative
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationDULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue
DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue Submitted to the Federal Transit Administration For Final Design Submitted by Metropolitan Washington Airports Authority In cooperation with
More information7/30/2014 Correspondence
7/30/2014 Correspondence July 29, 2014 Mr. Mark Canale Fairfax County 4050 Legato Rd Suite 400 Fairfax, VA 221822228 Project [813C001] Dulles Corridor Metrorail Project, Phase 2 Pkg A Location Code (multi)
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationReport to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016
Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package P Stormwater Management Facilities February 13, 2017 Rev. 0 Statement of Work February 13, 2017 THIS PAGE INTENTIONALLY
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationConstruction Update. May 2016
Construction Update May 2016 Project Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor Statistics
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationINNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT
INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT ROCKS ENGINEERING COMPANY 1960 Gallows Road, Suite 300 Vienna, VA 22182 Voice (703) 556-4000 INNOVATION STATION MIXED USE DEVELOPMENT PROJECT
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More information2016 ACEC/PA ANNUAL MEETING
2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA
More informationConstruction Update. November 2015
Construction Update November 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 1 2
More informationPlanned Procurement Opportunities Report. February 2018
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationFY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT
FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationSunrise Project South I-205 Corridor Improvement Project
Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205
More informationProgress Report Sounder Program
Progress Report Sounder Program Continued construction work for the Tacoma Trestle at East 26th and East G Streets. March 2017 Prepared by Project Control l Design, Engineering & Construction Management
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationLA 1 Bridge Project Status Update Feb. 12, 2007 WSA/DOTD A Partnership
New Bridge Old Bridge LA 1 Bridge Project Status Update Feb. 12, 2007 Satellite Image of Southern Louisiana Project Location Project Overview 2 1C 1B 1A Major Project work modules 1. Mapping, Location,
More informationReason for Acceptance or Rejection
Value Engineering Approval Form Project: 25th Avenue & Union Pacific Grade Separation #6 VE Study Date: January 28 through February 1, 2013 Form updated: 5/7/2013 (Final) FHWA Functional ENV 1 ROW 1 The
More informationMay Monthly Development Report 34,440. Current Population Est.
Monthly Development Report 34,440 Current Population Est. Town of Little Elm Development Services Department 100 W. Eldorado Parkway Little Elm, TX 75068 214-975-0472 The Development Services Department
More informationProgress Report Sounder Program
Progress Report Sounder Program Completing downspouts and other final touches on the Mukilteo Sounder Program new platform. September 2015 Prepared by Project Control September 2015 l Design, Engineering
More informationPROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404
LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:
More informationMetro Gold Line Foothill Extension Project
Metro Gold Line Foothill Extension Project Monthly Project Status Report September/October 2012 TABLE OF CONTENTS PHASE II FOOTHILL EXTENSION PROJECT STATUS Project Description... 3 Pasadena to Azusa Segment...
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationProgress Report Sounder Program
Progress Report Sounder Program Sound Transit added a mid-day Sounder train to its popular south line service beginning Monday, September 12th September 2016 Prepared by Project Control l Design, Engineering
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationCrenshaw/LAX Transit Project Construction Update Meeting July 28, 2015
Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More informationPlanned Procurement Opportunities Report. August 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationElectric Forward Market Report
Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08
More informationPlanned Procurement Opportunities Report. January 2018
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationTRANSVERSE SECTION TABLE OF CONTENTS CHAPTER 9
TABLE OF ONTENTS HAPTER FILE TITLE DATE TABLE OF ONTENTS AND INTRODUTION 0.TO- Table of ontents - hapter... 2Sep20 0.00- Introduction - hapter... 0Jul202 PLAN 0.0- General Information... 2Sep20 SAMPLE
More informationDistrict Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016
District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About
More informationTECHNICAL MEMORANDUM
California High-Speed Train Project TECHNICAL MEMORANDUM 15% Design Scope Guidelines TM 0.1 Signed document on file Prepared by: 12 May 08_ Ken Jong, PE Checked by: Signed document on file 12 May 08_ John
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationHamilton Rapid Transit Preliminary Design and Feasibility Study
Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT
More informationPlanned Procurement Opportunities Report. May 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationMiami River Freight Improvement Plan Financial Management Number:
Miami River Commission January 8, 2018 Miami, FL Carlos A. Castro, District Freight Coordinator Miami River Freight Improvement Plan Financial Management Number: 437946-1-22-01 Agenda Study Background
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationGreen Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session
Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services
More informationSAND POINT CITY DOCK REPLACEMENT ALTERNATIVES ANALYSIS REPORT
SAND POINT CITY DOCK REPLACEMENT ALTERNATIVES ANALYSIS REPORT Prepared for: City of Sand Point 3380 C Street, Suite 205 Anchorage, Alaska 99503 Prepared by: PND Engineers, Inc. 1506 W. 36 th Avenue Anchorage,
More informationRegion of Waterloo Stage 1 Light Rail Transit Project. Definitions, Acronyms, Cited References Article 1 Definitions.
Region of Waterloo Stage 1 Light Rail Transit Project Definitions, Acronyms, Cited References Article 1 Definitions Table of Contents 1.0 Definitions... 1-1 ARTICLE 1 DEFINITIONS 1.0. Definitions. In the
More information% Change. Total. Total Retail Sales Index* Estimate ($M)
Index % Change RETAIL SALES INDEX RETAIL SALES ROSE 2.6 PER CENT The total retail sales index was 2.6 per cent higher than the level reached in January. Building material stores recorded the largest growth
More informationOngoing and Future Project Work. Construction Management
Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era
More informationI-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010
VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY Dan Staron, P.E. HNTB Corporation MARCH 4, 2010 PRESENTATION OVERVIEW Project Background/Highlights Design Challenges Technical Details Concrete Applications/Details
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationThe Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok
The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District
More informationRoute 606 Loudoun County Parkway/ Old Ox Road Reconstruction and Widening
R e s p o n s e t o Request for Proposals Route 606 Loudoun County Parkway/ Old Ox Road Reconstruction and Widening ORIGINAL A Design-Build Projec t From: 0.265 Miles South of Route 621 Evergreen Mills
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction
More informationMASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK
MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,
More informationADDENDUM NO. 1. for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA. Posting Date: June 20, 2013
ADDENDUM NO. 1 for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA Posting Date: June 20, 2013 BIDDERS SHALL CONFORM TO THE FOLLOWING CHANGES AS A PART OF THE BID DOCUMENTS, WHICH SHALL BECOME
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction Phase 1 Overview The Re-routed Q train will
More informationDulles Corridor Metrorail Extension Project Tunneling Options for Tysons Corner
Dulles Corridor Metrorail Extension Project Tunneling Options for Tysons Corner John Rudolf Bechtel Infrastructure Corporation, Vienna, Virginia Vojtech Gall Gall Zeidler Consultants, LLC, Ashburn, Virginia
More informationSOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY
SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY Ryers Station Improvement Project Robert L. Lund, Jr., PE Assistant General Manager Engineering, Maintenance and Construction Division David J. Sands,
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationHighway Cost Index Estimator Tool Final report PRC 17-73
Highway Cost Index Estimator Tool Final report PRC 17-73 Highway Cost Index Estimator Tool Texas A&M Transportation Institute PRC 17-73 March 2018 Authors Brett Huntsman Brianne Glover, J.D. Samir Huseynov
More informationTransportation Cost Estimation
Transportation Decision-making Principles of Project Evaluation and Programming Transportation Cost Estimation Kumares C. Sinha and Samuel Labi 1 Transportation Costs Classification of Costs Agency Costs
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationNORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA
NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection
More informationAccelerated Bridge Construction (ABC) National Status
Accelerated Bridge Construction (ABC) National Status by Mary Lou Ralls, P.E., Ralls Newman, LLC 88 th Annual Transportation Short Course Texas A&M University College Station, Texas Session: Construction
More informationAviation Capital Construction Program Update
Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More informationBids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000)
General Info Number: PROJECT NO. 43-7-05 Description: BRIDGE DECK REPAIR AND REHABILITATION, BOSTON MILLS ROAD OVER OHIO TURNPIKE M.P. 78.0, OLDE EIGHT ROAD OVER OHIO TURNPIKE M.P. 79.5, NICHOLS ROAD OVER
More informationLoudoun County Chamber of Commerce
Loudoun County Chamber of Commerce INFRASTRUCTURE INVESTMENT The Loudoun County Chamber supports managed, thoughtful growth in the county. This includes support for well-planned commercial growth and development
More informationREPORT Condition D19 Permanent Noise Barriers
REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION
Sheet 1 of 5 Add a new SECTION to DIVISION 700: KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION SECTION 737 CONTROLLED DEMOLITION 737.1 DESCRIPTION Controlled
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationRoute 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building
PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 UNION PEARSON EXPRESS SPUR AND T1 STATION Srdjan Brasic, P.Eng, AECOM Canada Andrew Barr AECOM Canada ABSTRACT The Union Pearson Express Spur and station in Terminal
More informationI-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA
15th International Conference on Managed Lanes I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA Case Study for Funding of Transit Service and Transportation Demand Management
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationPLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationPeter Dahl Technical Assignment #2 Executive Summary
Primary Faculty Consultant: Riley Due Date: Wednesday, October 22 nd, 2003 Technical Assignment #2 Project Delivery Evaluation Executive Summary Every owner, and in turn every project, will require a different
More informationNew Hope Crushed Stone. Monthly Update Solebury Communications Group October 2017
New Hope Crushed Stone Monthly Update Solebury Communications Group October 2017 Tom Wolf, Governor Patrick McDonnell, Secretary October 2017 Project Status STATUS AS OF: October 31, 2017 PROJECT START
More informationConstruction of the Superstructure of Major Sea Crossings
Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge 2 Second Penang Bridge Donghai Bridge
More informationCapital Sales and Purchases. Cash flow Income Statement Financing. Assets. Costs. Liabilities Schedule F 1
Capital Sales and Purchases Costs Assets ROI Revenues Cash flow Income Statement Financing Liabilities Schedule F 1 Financial data collection Financial analyses F 2 Finances : Forecasting costs Penelope
More informationThe bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge.
The Design and Construction of Alfords Point Bridge Mark Bennett, Senior Bridge Engineer (New Design) RTA Harry Cheung, Project Engineer, RTA Trung Doan Project Engineer, RTA Synopsis The bridge over the
More informationITR CONCESSION COMPANY LLC
ITR CONCESSION COMPANY LLC 52551 ASH ROAD GRANGER, INDIANA 46530 APPLICATION FOR UTILITY CROSSING PERMIT (File in Triplicate) New Construction (Kind of Utility) Alteration of Facility Relocated During
More informationThe Service Desk Balanced Scorecard
The Service Desk Balanced Scorecard Your Overall Measure of Service Desk Performance MetricNet Best Practices Series Your Speaker: Jeff Rumburg Co Founder and Managing Partner, MetricNet, LLC Winner of
More informationCOMMUNITY BOARD EIGHT
SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and
More informationWatts Bar Nuclear Plant Unit 2 Completion Project
Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly
More informationDulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs)
Executive Summary In 2009, the Federal Government, through Executive Order 13502, reversed an earlier order and now recommends that all federally funded projects with a total installed cost greater than
More informationPlanned Procurement Opportunities Report. November 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationConstruction Project Briefing. April 20, 2015
Construction Project Briefing April 20, 2015 Today s Presentation Traction Power Farwell/Armitage/Hill Substations Kimball/Princeton/State Substations 95 th Street Terminal Improvement Program Wilson Transfer
More information